The briefing · records dated through November 2026

Where the money building AI is going

Who is paying whom for the chips, data centers and power behind AI — 196 deals, each said in one line.

New here? Take a tour: Nvidia's circular deals · Where AI gets its power

The flow Who pays whom, left to right. Ribbon width is a rough size in $B, per year for multi-year deals.

← swipe to see the whole flow →

sourced deal · 105 of 168 estimated size · 63 of 168 full amount, no yearly rate · 24 of 168
Tap a ribbon or a company to see its flows here.
The flow as a table 175 links, 7 the chart can't draw

168 are drawn above; each of the other 7 says why it isn't.

FromTo$BBasisDeal in the record
OpenAIMicrosoft$250B
paid over years at a rate no record gives · drawn at its full amount
sourcedMicrosoft has committed $13B to OpenAI and owns about 24% of it. OpenAI committed $250B more to Microsoft's cloud.
OpenAIAmazon / AWS$138B
paid over years at a rate no record gives · drawn at its full amount
sourcedAmazon invested $50B in OpenAI, all paid by Q3 2026. OpenAI agreed to spend $38B on Amazon's cloud, then added $100B more over eight years.
AnthropicSpaceX$120.5B
paid over years at a rate no record gives · drawn at its full amount
estimated, deal sourced
Anthropic's filed ceiling, drawn at face: it agreed to spend 'up to $120.5 billion' over terms into 2029. Once initial non-cancelable periods end in Jan and Mar 2027, either side may cancel on 90 days' notice, so past them it is potential money, not a commitment.
Anthropic agreed to pay SpaceX up to $120.5B for computing — about $3.1B a month once all the capacity is delivered, per its IPO filing — but after initial periods ending in early 2027 either side can cancel on 90 days' notice.
OpenAIAMD$90B
paid over years at a rate no record gives · drawn at its full amount
estimated, deal sourced
No value is disclosed (AMD says 'tens of billions'): 6 GW of chips at ~$15B per GW ≈ $90B, the low end of the $90–100B+ range.
OpenAI plans to buy up to 6 GW of AMD chips. As it buys chips and AMD's stock rises, OpenAI earns the right to buy nearly 10% of AMD at a cent a share.
MetaAMD$90B
paid over years at a rate no record gives · drawn at its full amount
estimated, deal sourced
No value is disclosed anywhere: 6 GW at ~$15B per GW ≈ $90B, the same basis as OpenAI's AMD deal, between the $60B (Reuters) and >$100B (WSJ) estimates.
Meta plans to buy up to 6 GW of AMD chips. As it buys chips and AMD's stock rises, Meta earns the right to buy nearly 10% of AMD at a cent a share.
Other investorsAnthropic$83B
range 83–98
estimated, no deal recordno deal record
Venture firms, sovereign funds and strategic investors with no entry of their own put $83–98B into Anthropic's funding rounds through May 2026 (Epoch AI's funding data); drawn at the low end, since Microsoft's and Nvidia's part of the Series G is undisclosed.
SK TelecomNvidia$70B
paid over years at a rate no record gives · drawn at its full amount
estimated, deal sourced
Letters of intent only, no purchase filed: SK Telecom's Nvidia AI factory of up to 2 GW × ~$35B of chips per GW (Fortune) ≈ $70B at that ceiling — over twice the ~$15B per GW drawn for AMD's deals, an estimate for AMD's chips. Nvidia puts its Vera Rubin revenue at ~$40B per GW.
Nvidia and SK Group announced a '$500B-plus' plan for Nvidia to buy SK hynix memory and SK to buy Nvidia supercomputers. Only letters of intent are signed.
Northstar Compute (SPV)Anthropic$63B sourcedBank of America, Citi, Morgan Stanley and Blackstone announced $63B to fund a lease of Broadcom AI chips and networking gear to Anthropic. Broadcom could owe up to about $43B if Anthropic defaults.
SoftBankOpenAI$60.5B sourcedSoftBank has paid $64.6B for about 13% of OpenAI since 2024. It made the last three payments in 2026 with $30B in borrowed money.
OpenAIOracle$300B
over 5 years · ≈ $60B a year
sourcedOracle agreed to develop up to 4.5 GW more data-center capacity for OpenAI. The companies say their partnership exceeds $300B over five years.
Amazon / AWSOpenAI$50B sourcedAmazon invested $50B in OpenAI, all paid by Q3 2026. OpenAI agreed to spend $38B on Amazon's cloud, then added $100B more over eight years.
OpenAIBroadcom$150B
over 3 years · ≈ $50B a year
estimated, deal sourced
No value is disclosed (a term sheet): 10 GW of custom chips at ~$15B per GW ≈ $150B, the same per-GW basis as the AMD deals.
Broadcom builds and deploys AI chips that OpenAI designs, with 10 GW announced through 2029. Only 1.3 GW for 2027 is under contract so far.
AnthropicFluidstack$50B
paid over years at a rate no record gives · drawn at its full amount
estimated, deal sourced
Anthropic's announced $50B to build US data centers with Fluidstack: a program, not a payment to Fluidstack. No one says who spends it, where or when.
Anthropic announced a $50B data-center plan with Fluidstack without naming sites or who pays for what; separately, Apollo-led funds agreed to buy $35B of Broadcom-built computing for Anthropic.
AnthropicNscale$44.6B
paid over years at a rate no record gives · drawn at its full amount
sourcedAnthropic signed four agreements to rent dedicated Nvidia Vera Rubin systems from Nscale at its West Virginia campus, worth up to about $44.6B to Nscale; Anthropic pays nothing until each batch is built and accepted, and when Nscale filed to go public it had not secured the financing to build them.
AnthropicLambda$41.3B
paid over years at a rate no record gives · drawn at its full amount
sourcedAnthropic agreed in May, June and August 2026 to spend about $41.3B on computing on Nvidia GPUs from Lambda over terms running into 2034, owing fees only as capacity is delivered and accepted; about $34.9B of it is the August agreement, which either side may now end because Lambda did not secure the facility lease in time; neither has given notice, and Anthropic does not currently intend to.
GoogleAnthropic$40B sourcedGoogle committed up to $40B to Anthropic: $10B of stock up front and $30B more through 2030, drawn as TPU capacity is delivered to Anthropic and as its revenue meets targets, or put in early at Google's option — $10B of which went into Anthropic's May 2026 round, leaving $20B — and $10B of that Google has agreed to take as stock at Anthropic's IPO price if the IPO completes, leaving $10B.
OracleNvidia$40Bestimated, press report
No party gives a price: the FT reported in May 2025 that Oracle would spend about $40B on ~400,000 GB200s for Abilene; one research group's per-GPU arithmetic puts them nearer $20B. Neither company has confirmed a figure.
Oracle fills the Abilene campus with Nvidia GB200 systems it runs for OpenAI: 'more than 450,000' GPUs by Ellison's count, about 400,000 by a press report; neither discloses what Oracle pays.
ApolloSpaceX$40B sourcedSpaceX committed to rent AI chips and equipment from an entity Apollo manages. It expects to repay about $40B plus interest at an undisclosed fixed rate.
OpenAISamsung$35B
paid over years at a rate no record gives · drawn at its full amount
estimated, deal sourced
No party gives a value: an unnamed analyst's '>₩100 trillion' (~$70B) split evenly between Samsung and SK hynix ≈ $35B each.
OpenAI signed letters of intent with Samsung and SK hynix for up to 900,000 memory-chip wafers a month; the companies have disclosed no contract, price or start date.
OpenAISK Hynix$35B
paid over years at a rate no record gives · drawn at its full amount
estimated, deal sourced
No party gives a value: an unnamed analyst's '>₩100 trillion' (~$70B) split evenly between Samsung and SK hynix ≈ $35B each.
OpenAI signed letters of intent with Samsung and SK hynix for up to 900,000 memory-chip wafers a month; the companies have disclosed no contract, price or start date.
NvidiaTSMC$30Bestimated, no deal recordno deal record
TSMC makes and packages Nvidia's chips: Nvidia books about 59% of TSMC's CoWoS packaging (Epoch AI, May 2026). No contract value is disclosed, so the width is our magnitude.
Blue OwlMeta$27B sourcedBlue Owl's funds own 80% of the firm holding part of Meta's Hyperion data center, funded by a $27.3B bond. Meta rents the space and guarantees its resale value.
NvidiaSK Hynix$25Bestimated, no deal recordno deal record
SK hynix, the largest HBM maker (62% of 2Q25 shipments), supplies the memory on Nvidia's chips; their 2026 letters of intent add future HBM4 purchases with no figure. The width is our magnitude.
OpenAICoreWeave$22B
paid over years at a rate no record gives · drawn at its full amount
sourcedOpenAI agreed to buy up to about $22.4B in computing power from CoreWeave. CoreWeave gave OpenAI $350M of its own stock.
AnthropicBroadcom$21Bestimated, deal sourced
Broadcom's two 2025 orders from Anthropic, $10B + $11B. Ghosted: since recast as a chip sale, what Broadcom books is undisclosed. Anthropic's S-1/A files ~$161.2B of rent on its Broadcom leases but splits it by no lessor, lease or gigawatt, so none of it is drawn.
Broadcom supplies Anthropic with Google-designed AI chips. Anthropic's filing to go public lists about $161.2B in rent on Broadcom leases over five-year terms.
MetaOracle$20B
paid over years at a rate no record gives · drawn at its full amount
estimated, press report
No party publishes a value: the width is Bloomberg's reported ~$20B, which no one else confirms; Oracle files no Meta-specific figure.
Meta agreed in October 2025 to rent about $40B of cloud computing over several years. Filings name no vendors, but press reports tie parts to Google and Oracle.
OpenAICerebras$20B
paid over years at a rate no record gives · drawn at its full amount
sourcedOpenAI guarantees more than $20B in purchases from Cerebras and lends it $1B to build data centers. OpenAI gets up to 15% of Cerebras nearly free in return.
OpenAISB Energy$390B
over 20 years · ≈ $20B a year
estimated, deal sourced
Rent is redacted in every filed lease: SB Energy's filing puts ~$430B on 8.8 GW of signed leases, and PORTS-Pike is 8.0 GW of them → ~$390B over 20 years, if rent per MW is uniform.
Nvidia will cover up to $105B if OpenAI defaults on 4.25 GW of SB Energy leases in Ohio. In return, the site must use only Nvidia chips for at least 20 years.
Amazon / AWSAnthropic$18B sourcedAmazon is investing up to $25B in Anthropic, which committed to spend at least $110B on Amazon's cloud over ten years, much of it on Amazon's Trainium chips.
MetaEntergy Louisiana$18B
paid over years at a rate no record gives · drawn at its full amount
estimated, deal sourced
What Meta pays under the power contracts is not filed; the width is roughly the filed cost of what they pay for: about $18B of new gas plants and power lines in Entergy's filings.
Meta signed 15- and 20-year power contracts with Entergy Louisiana, which plans about 7.5 GW of new gas plants for Meta's Hyperion campus; Meta's total payments are not public.
Other investorsOpenAI$17.5Bestimated, no deal recordno deal record
Venture firms, sovereign funds and strategic investors with no entry of their own put up to ~$17.5B into OpenAI's rounds from 2019 to 2025 (Epoch AI's funding data). The 2026 round is not drawn: only Amazon's and SoftBank's legs are on record as paid, each on its own ribbon.
AnthropicAMD$17B
paid over years at a rate no record gives · drawn at its full amount
estimated, deal sourced
AMD's price is not disclosed: Anthropic's S-1/A expects over $20.0B of spending on the first batch, through manufacturers and service providers, not AMD's revenue. Drawn at the low end of analysts' $17–27.2B for AMD's revenue on the 2 GW.
Anthropic plans to deploy up to 2 GW of AMD's newest chips — expecting to spend over $20B if it takes the whole first batch, per its IPO filing — and AMD committed to buy up to $5B of Anthropic's stock, at Anthropic's choice, as deliveries hit milestones — $2.5B of it, Anthropic's amended filing says, at the IPO price right after the offering if the IPO completes.
NvidiaGroq$17B sourced · not drawn above: Nvidia and Groq sit in the same part of the chainNvidia says it paid $13.0B at closing for Groq hires and a non-exclusive license to Groq's chip technology for running AI models, with $4B more due within a year; the press reported $20B.
AnthropicGoogle$121.3B
over 7.3 years · ≈ $17B a year
sourcedAnthropic plans to use up to 1 million Google TPUs; its IPO filing shows at least ~$121.3B committed to Google through July 2033, and an estimated $125–150B more from Google or another TPU provider.
MetaBroadcom$15B
paid over years at a rate no record gives · drawn at its full amount
estimated, deal sourced
No value is disclosed: more than 1 GW of Meta's own MTIA chips, drawn at 1 GW × ~$15B per GW, the same basis as the AMD deals.
Meta committed to more than 1 GW of its own AI chips, co-designed with Broadcom — the first phase of a multi-gigawatt rollout; no dollar figure disclosed.
Blue OwlCrusoe$15Bestimated, deal sourced
The $15B is the joint venture's announced size for the whole Abilene campus, construction loans included; no party says how much of it is Blue Owl's own money. The only filed equity total is the first two buildings' $926.8M.
A $15B joint venture formed by Crusoe, Blue Owl-managed funds and Primary Digital is building Abilene's 1.2 GW campus. Oracle rents all eight buildings.
Lenders & bondholdersRelated Digital$14B sourcedOracle has leased all of a $16B data-center campus going up in Saline Township, Michigan, for OpenAI work. Related Digital and Blackstone property funds own it.
GoogleTSMC$13.1B
range 9–17.6
a year
estimated, no deal recordno deal record
TSMC makes Google's TPU chips, like nearly every advanced AI chip; no contract is disclosed. The width is the full value of TPUs delivered in 2025 (Epoch AI), an upper bound: TSMC's cut is a fraction.
BlackRockMeta$12.5B sourcedBlackRock's funds own 80% of the venture building a ~$14B, 1 GW El Paso campus, the companies say. Meta rents it all and guarantees its value up to ~$13B.
MicrosoftOpenAI$12B sourcedMicrosoft has committed $13B to OpenAI and owns about 24% of it. OpenAI committed $250B more to Microsoft's cloud.
TSMCASML$12Bestimated, no deal recordno deal record
ASML is the only maker of EUV machines, which print the finest chip features, and TSMC makes nearly every advanced AI chip. No purchase value is disclosed, so the width is our magnitude.
AnthropicAmazon / AWS$110B
over 10 years · ≈ $11B a year
sourcedAmazon is investing up to $25B in Anthropic, which committed to spend at least $110B on Amazon's cloud over ten years, much of it on Amazon's Trainium chips.
GoogleSpaceX$30B
over 2.8 years · ≈ $11B a year
estimated, deal sourced
The filing discloses a rate, not a total: $920M a month from Oct 2026 to Jun 2029 × 33 months ≈ $30B, cancellable on 90 days' notice after Dec 31 2026.
Google agreed to pay SpaceX $920M a month from October 2026 to June 2029 for about 110,000 Nvidia chips; from 2027 either side can end it on 90 days' notice.
MGXSpaceX$10Bestimated, no deal recordno deal record
MGX is named among the investors in xAI's Series C (Dec 2024) and Series E (Jan 2026) rounds (Epoch AI's funding data), and xAI has been part of SpaceX since February 2026; neither round says how much MGX put in, so the width is our magnitude.
BlackstoneCoreWeave$8.5B sourcedCoreWeave finalized an $8.5B loan with Blackstone as a main lender. The fixed-rate portion carries about 5.9% interest.
NvidiaMicron$8Bestimated, no deal recordno deal record
Micron says it is in high-volume HBM4 production for Nvidia's Vera Rubin (June 2026), but estimates run from none of Rubin's HBM to low-20s% of the HBM4 market. No value is disclosed; the width is about a third of SK hynix's, by 2Q25 HBM shipment shares (21% vs 62%).
BlackstoneCoreWeave$7.5B sourcedBlackstone and Magnetar led a $7.5–7.6B loan to CoreWeave in 2024, backed by its chips and customer contracts. Lenders added $3.0B in 2025.
AnthropicMicrosoft$47.2B
over 6.6 years · ≈ $7.2B a year
sourcedNvidia (up to $10B) and Microsoft (up to $5B) agreed in November 2025 to invest in Anthropic, which committed to buy $30B of computing on Microsoft's Azure cloud — at least $47.2B, and up to $49.2B, once amended; Anthropic says a portion of those investments went into its February 2026 funding round.
NvidiaPoolside$6Bestimated, press report
Press reports only: the $6B license fee in Poolside's investor letter, as Newcomer and the WSJ read it, with Bloomberg's sources giving the same $6B (Bloomberg credits Newcomer with first reporting it). Neither company has published it, and no Nvidia filing names Poolside.
· not drawn above: the money runs from Nvidia back up the chain to Poolside; the chart draws money running back only into a cloud, a neocloud or a data center (as their customer or tenant)
Nvidia reportedly agreed to pay Poolside $6B for a non-exclusive license to its system for building AI models and invest $1B, per Poolside's unpublished investor letter.
IRENDell$5.8B sourcedMicrosoft committed about $9.7B through 2031 to rent Nvidia chips in four IREN data center halls in Texas. It may cancel halls delivered too late.
US governmentIntel$5.7B sourcedThe US government agreed to take up to 433.3M new Intel shares for up to $8.87B in already-awarded CHIPS Act funds. It paid $5.695B at closing, with the rest tied to Intel's defense chip work.
MicrosoftNscale$43.8B
over 8 years · ≈ $5.5B a year
sourcedMicrosoft has deals to rent Nvidia AI chips from Nscale for up to about $43.8B through 2033 if Nscale delivers on time and keeps the chips available.
MetaNebius$27B
over 5 years · ≈ $5.4B a year
sourcedMeta agreed to rent about $2.9B of computing power from Nebius in 2025, then up to about $27B more in 2026, including up to $15B Meta must buy if Nebius doesn't sell it to others.
NvidiaIntel$5B sourcedNvidia paid $5B for 214.8M new Intel shares. Intel plans to make custom processors for Nvidia's AI systems and PC chips with Nvidia graphics.
AIP (fund)Aligned DC$5B sourcedAIP, MGX and BlackRock's GIP bought all of Aligned Data Centers, valuing it at about $40B. They committed another $5B to expand it.
MicrosoftNiSource$4.5B
paid over years at a rate no record gives · drawn at its full amount
estimated, deal sourced
No contract value is public. The width adds two figures NiSource gives for what it plans to add to serve the deal (our sum): ~$2.3B for two gas turbines with their transmission and infrastructure, and ~$2.2B it expects to pay over ~20.5 years to rent a battery ≈ $4.5B.
Microsoft will buy power for a planned Indiana data center from NiSource's NIPSCO for 20 years, rising to 788 MW from 2031, fully funding the new supply, NiSource says; it awaits Indiana's approval.
Blackstone Digital Infrastructure TrustAmazon / AWS$4.33B sourcedAmazon agreed to sell 75.1% of 13 data centers worth $5.0B to Blackstone Digital Infrastructure Trust if paid at least $4.33B in cash at closing. Amazon will rent all 13 back.
Amazon / AWSTSMC$4.3B
range 3.7–5
a year
estimated, no deal recordno deal record
TSMC makes Amazon's Trainium chips; no contract is disclosed. The width is the full value of Trainium chips delivered in 2025 (Epoch AI), an upper bound: TSMC's cut is a fraction.
Amazon / AWSSK Telecom$4B sourcedSK Telecom is building a 103 MW AI data center in Korea with AWS as its 15-year partner. Korea's science ministry, not SK or AWS, puts AWS's investment at $4B.
Lenders & bondholdersApplied Digital$3.94B sourcedCoreWeave rents all 400 MW of Applied Digital's Polaris Forge 1 campus in Ellendale, North Dakota, under three leases of about 15 years that Applied Digital counts at about $11B. With the leases, Applied Digital gave CoreWeave warrants on about 21.5 million of its shares.
Lenders & bondholdersGalaxy$3.507B sourcedCoreWeave is renting 526 MW of data-center capacity at Galaxy's Helios campus in West Texas, a former bitcoin mine, under three 15-year leases — the first 133 MW handed over in 2026, the other 393 MW due from 2027 — for rent Galaxy puts at more than $15B.
Lenders & bondholdersNebius$3.5B sourcedNebius signed a $3.5B bridge loan from Citi to fund computing power from graphics chips and general business needs. It's due in 364 days.
NvidiaMediaTek$3.5B sourcedNvidia bought $3.5B in MediaTek bonds that can convert to shares. MediaTek agreed to offer Nvidia technology that connects custom AI chips to Nvidia systems.
MetaCoreWeave$21B
over 6.7 years · ≈ $3.1B a year
sourcedMeta committed to pay CoreWeave up to about $21B for computing through 2032. Filings leave open whether that includes Meta's earlier $14.2B order.
Lenders & bondholdersCoreWeave$3.1B sourcedCoreWeave borrowed up to $3.1B from investors in May 2026 to buy servers with graphics chips for its OpenAI and Cohere contracts.
SoftBankOpenAI$3B
a year · term unstated
estimated, deal sourced
Drawn at SoftBank Group's announced $3B a year, since it stated no term. Not a paid figure: SoftBank says the full $3B was not incurred in its year to March 2026, and no document settles whether it pays OpenAI or their Japanese venture.
SoftBank Group said it would spend $3B a year on OpenAI's products for its companies, and SoftBank and OpenAI formed SB OAI Japan, a 50:50 venture, to sell a package of them in Japan.
MicrosoftNebius$17.4B
over 6 years · ≈ $2.9B a year
sourcedMicrosoft committed to pay Nebius up to $17.4B to rent AI chip capacity through 2031, even if unused after delivery. It paid about $7B up front.
NvidiaAmkor$2.8B
range 2.8–3
sourcedNvidia agreed to pay Amkor about $1.5B up front to expand chip packaging in Arizona and about $1.3B more for South Korea. Both payments are expected in 2027.
Lenders & bondholdersCoreWeave$2.75B sourcedCoreWeave sold $2.75B of unsecured bonds in April 2026. The bonds pay 9.75% a year until October 2031.
AEPBloom Energy$2.65B sourcedAEP plans to spend about $4 billion on a 702 MW plant of Bloom Energy fuel cells near Cheyenne, Wyoming, and sell its power to Google for 20 years; the price is not disclosed.
AramcoHUMAIN$2.6B sourcedAramco took 49% of Saudi Arabia's AI company HUMAIN for about $2.6B (SAR 9.9B) in cash paid into HUMAIN in 2026 plus AI assets it hasn't named or valued. Sovereign fund PIF keeps 51%.
Lenders & bondholdersCoreWeave$2.6B sourcedCoreWeave borrowed up to $2.6B from investors in August 2026 to buy servers with graphics chips for customer contracts that average about three years.
Lenders & bondholdersBlackstone Digital Infrastructure Trust$2.5B sourcedAmazon agreed to sell 75.1% of 13 data centers worth $5.0B to Blackstone Digital Infrastructure Trust if paid at least $4.33B in cash at closing. Amazon will rent all 13 back.
AnthropicCoreWeave$12B
over 5 years · ≈ $2.4B a year
estimated, press report
Neither party discloses the value; the width is a trade-press report of ~$12B over five years, from a page that can no longer be opened.
Anthropic agreed to rent computing power from CoreWeave in phases over several years, using graphics chips. Neither company has disclosed the deal's value.
GoogleEntergy Arkansas$2.4B
paid over years at a rate no record gives · drawn at its full amount
estimated, deal sourced
What Google pays is redacted. The width adds two filed costs Entergy says Google's rates are built to cover (our sum): the Cypress solar plant with batteries, $1.8B with construction financing, and the two new batteries' $550.6M ≈ $2.4B — before the transmission and the PPA.
Google buys power for its Arkansas data center from Entergy for 20 years, at rates Entergy says pay for a $1.6B solar plant; a pending amendment adds 250 MW and ~$600M of batteries and lines.
MagnetarCoreWeave$2.3B sourcedMagnetar and Blackstone led a $2.3B loan to CoreWeave in July 2023. It was backed by the servers with graphics chips that the loan financed.
AnthropicRUM Group$13.7B
over 6 years · ≈ $2.3B a year
sourcedAnthropic agreed in August 2026 to buy about $13.7B of GPU computing over six years from RUM Group, Rumble's parent, at a Georgia data center RUM had yet to build or finance — the last third binding only once Anthropic approves its delivery date — and RUM gave Anthropic the right to buy up to 50.8M RUM shares at a cent each, half of them unlocking as the three parts are delivered, accepted and paid for.
Lenders & bondholdersCleanSpark$2.276B sourcedMeta's subsidiary Anviran rents a 175 MW data center CleanSpark is building in Sandersville, Georgia for 20 years, about $6.6B of rent by CleanSpark's estimate, with a 'limited' Meta guarantee.
TeslaSamsung$16.5B
over 8 years · ≈ $2.1B a year
sourced · not drawn above: Tesla is not in the chart's columnsSamsung will make AI chips for Tesla under a contract it values at about $16.5 billion, running to the end of 2033 — a value and term it says may change; Tesla says the deal is for its next AI6 chip.
SoftBankIntel$2B sourcedSoftBank paid $2B for 86,956,522 new Intel shares at $23.00 each. The deal was signed on August 18, 2025 and closed that September.
BlackstoneRelated Digital$2Bestimated, press report
No party states the equity. Blackstone's own earnings presentation names 'a BREP investment', from its real-estate fund family, in the venture without an amount; Bloomberg's sources put Blackstone's share at about $2B, a figure others read as both sponsors' equity together.
Oracle has leased all of a $16B data-center campus going up in Saline Township, Michigan, for OpenAI work. Related Digital and Blackstone property funds own it.
NvidiaLumentum$2B sourcedNvidia invested $2B each in laser makers Lumentum and Coherent, with multi-billion-dollar purchase commitments and non-exclusive rights to future capacity.
NvidiaCoherent$2B sourcedNvidia invested $2B each in laser makers Lumentum and Coherent, with multi-billion-dollar purchase commitments and non-exclusive rights to future capacity.
Lenders & bondholdersCipher Digital$2B sourcedAmazon's subsidiary is renting, for 15 years, the 300 MW data center Cipher is making of a former bitcoin mine near Wink, Texas — about $5.5B of rent by Cipher's estimate — under a 'limited' Amazon.com guarantee, and a Cipher subsidiary has borrowed $2.0B of bonds to build it.
MicrosoftIREN$9.7B
over 5 years · ≈ $1.9B a year
sourcedMicrosoft committed about $9.7B through 2031 to rent Nvidia chips in four IREN data center halls in Texas. It may cancel halls delivered too late.
Reflection AISpaceX$6.3B
over 3.5 years · ≈ $1.8B a year
estimated, deal sourced
Reflection told TechCrunch it pays $150M a month from Jul 2026 through 2029; 42 months of that is the reported 'up to $6.3 billion', a ceiling either side can end on 90 days' notice after three months, which no party document states.
Reflection AI told reporters it would pay SpaceX $150M a month from July 2026 through 2029 for Nvidia's newest chips, cancellable on 90 days' notice after three months.
MetaGoogle$10B
over 6 years · ≈ $1.7B a year
estimated, press report
No party publishes a value: the width is CNBC's reported 'more than $10B' over six years, from one source chain.
Meta agreed in October 2025 to rent about $40B of cloud computing over several years. Filings name no vendors, but press reports tie parts to Google and Oracle.
AnthropicAkamai$11.6B
over 7 years · ≈ $1.7B a year
sourcedAnthropic committed about $11.6B to Akamai over two seven-year plans of dedicated CPU computing, subject to delivery; Akamai expects to spend ~$5.5B and gave it the right to buy up to ~5% of Akamai.
IRENDell$1.6B sourcedNvidia agreed to pay IREN about $3.4B over five years for AI chip capacity in Texas for its own use. It pays only after accepting delivery.
BrookfieldBloom Energy$1.56B sourcedBrookfield ventures buy and own Bloom fuel-cell plants under a framework raised from up to $5B to up to $25B, ~$2B committed by mid-2026; in 2025 they bought $862.1M of Bloom systems and installation.
MicrosoftG42$1.5B sourcedMicrosoft paid $1.5B for a minority stake and a board seat at Abu Dhabi's G42, which is building 200 MW of data-center capacity for Microsoft.
NvidiaSB Energy$1.5B sourcedNvidia will cover up to $105B if OpenAI defaults on 4.25 GW of SB Energy leases in Ohio. In return, the site must use only Nvidia chips for at least 20 years.
Lenders & bondholdersGalaxy$1.4B sourcedCoreWeave is renting 526 MW of data-center capacity at Galaxy's Helios campus in West Texas, a former bitcoin mine, under three 15-year leases — the first 133 MW handed over in 2026, the other 393 MW due from 2027 — for rent Galaxy puts at more than $15B.
NvidiaHut 8$19.6B
over 15 years · ≈ $1.3B a year
estimated, deal sourced
Hut 8's 10-Q files $19.6B as the base value of two leases but names no tenant; Nvidia is on this ribbon only by FT and WSJ reporting, which Nvidia has not confirmed.
Hut 8 has leased 704 MW of data-center capacity it is building in Texas, $19.6B of rent over two 15-year leases, to a tenant it never names — reportedly Nvidia.
OpenAIGeorgia Power$32B
over 25 years · ≈ $1.3B a year
estimated, deal sourced
No price, minimum bill or total is public. The width is the county development authority's tax model of the campus's power bill: 1.9 billion kWh a month at its estimated 6¢ per kWh, about $1.37B a year once built, for 25 years, the first three at ¼, ½ and ¾ of that ≈ $32B.
Georgia Power will supply OpenAI's planned Project Camellia campus near Savannah with up to 3,210 MW for 25 years and can have it cut up to 1,000 MW when the grid is strained; the price is secret.
Amazon / AWSGenerac$2.4B
over 2 years · ≈ $1.2B a year
estimated, deal sourced
Generac's own expectation, not a stated commitment: its 8-K says first deliveries are 'expected to total $2.4 billion in 2027 and 2028', and the floor of firm orders beside it is redacted. Drawn as an average over those two years; Generac gives no split by year.
Generac, a maker of backup generators, signed a long-term deal to supply Amazon's data centers, expecting first deliveries of $2.4B in 2027 and 2028, and gave Amazon the right to buy up to 1.69M Generac shares at $200.9266 — 307,954 at once, the rest as Amazon pays, counting up to $8B of payments: a ceiling, not an order.
NvidiaNscale$1.18B sourcedNvidia agreed to put $1.0B into Nscale before its stock market debut, with the investment convertible to shares. It already paid about $1.18B for Nscale shares.
NvidiaKYEC$1.1B sourcedNvidia says it's paying King Yuan Electronics $1.1B up front for new US chip-testing capacity. King Yuan says it will credit the advance against testing fees.
Amazon / AWSTalen Energy$18B
over 17 years · ≈ $1.1B a year
estimated, deal sourced
The power price is not disclosed; the width is Talen's own ~$18B projection of the contract's revenue (its decks state it on two different bases), not a committed sum.
Amazon bought a data-center campus beside Talen's Pennsylvania nuclear plant for $650M and agreed to buy up to 1,920 MW of its power through 2042, delivered over the grid.
Lenders & bondholdersLambda$1.008B sourcedLambda borrowed up to $1.008B at a fixed 6.78% from insurers and other investors. It draws funds as servers for two unnamed investment-grade customers start up.
NvidiaCorning$1B sourcedNvidia paid Corning $500M for warrants covering up to 18M Corning shares. Corning's filings also show a $1.0B Nvidia deposit under a supply deal through 2029.
NvidiaKinsus$1B sourcedKinsus says Nvidia is putting more than $1B in cash into new equipment at its Youth campus in Taoyuan, Taiwan. Nvidia says Kinsus plans to raise the substrate capacity dedicated to Nvidia there to more than 3.5 times today's.
NvidiaNokia$1B sourcedNvidia paid $1B for 166.4M new Nokia shares. Nokia agreed to build mobile network base stations that run on Nvidia's computing platform.
CoreWeaveGalaxy$15B
over 15 years · ≈ $1B a year
estimated, deal sourced
Galaxy's own 'more than $15 billion' of contracted rent across the three Helios leases, stated only on its website; its filings give a figure for the first lease alone, $4.68B still to come at Sep 30 2026.
CoreWeave is renting 526 MW of data-center capacity at Galaxy's Helios campus in West Texas, a former bitcoin mine, under three 15-year leases — the first 133 MW handed over in 2026, the other 393 MW due from 2027 — for rent Galaxy puts at more than $15B.
SandiskNanya Technology$0.97B sourcedSandisk agreed to buy about 139 million new Nanya shares for about $1.0 billion. Nanya also has a multi-year deal to supply Sandisk with memory chips.
US governmentGlobalFoundries$0.955B
paid over years at a rate no record gives · drawn at its full amount
estimated, deal sourced
Up to $955M of GlobalFoundries' existing CHIPS award, moved to silicon photonics, SiGe and packaging without raising the award's total; it is to be paid toward GF's spending from 2027, so it is drawn as money not yet paid.
Japan is to pay about $10 billion for a chip plant at GlobalFoundries' Malta, New York, site, or up to $21 billion total if a second plant is approved.
AnthropicTeraWulf$19B
over 20 years · ≈ $0.95B a year
sourcedAnthropic rents a 401 MW data center TeraWulf is building in Kentucky, about $19B over 20 years; Google backs the rent from each finished building until Anthropic is rated investment grade.
AMDCore Scientific$14B
over 15 years · ≈ $0.93B a year
estimated, deal sourced
Core Scientific's '>$14B' of potential revenue over 15 years, stated only in a press release, covers both tenants (AMD and an unnamed neocloud); AMD's own share is not disclosed.
AMD signed 15-year leases for 377 MW of data center capacity from Core Scientific and got the right to buy up to 30M Core Scientific shares in return.
Lenders & bondholdersLambda$0.926B sourcedLambda borrowed $926M from institutional investors to buy servers with graphics chips for one unnamed customer. Lambda says the customer is investment-grade.
MicrosoftChronoScale$2.7B
over 3 years · ≈ $0.9B a year
estimated, deal sourced
ChronoScale’s 10-Q gives $2.7B of contracted revenue, over three-year terms, for GPU services agreements with two customers signed in the quarter Microsoft’s was. It names neither and splits nothing, so Microsoft’s share is an undisclosed part of it.
ChronoScale agreed to provide Microsoft dedicated Nvidia GB300 computing at about 50 MW in Texas for about three years. It says the rollout partly depends on financing.
GoogleConstellation$17B
over 20 years · ≈ $0.85B a year
estimated, deal sourced
No price is disclosed; Bloomberg's pre-deal '$1 billion or more' is a floor from unnamed sources. The width is 890 MW for 20 years at ~$110/MWh — the rate drawn for Microsoft's Three Mile Island restart, borrowed — ≈ $17B; the 15-year, 2,700 MW agreement is left out.
Google will buy for 20 years the 890 MW that upgrades are to add at 11 Constellation nuclear units, the first by 2028, plus 2,700 MW from existing plants for 15 years; neither price is disclosed.
CoreWeaveCore Scientific$10B
over 12 years · ≈ $0.83B a year
sourcedCoreWeave rents about 590 MW of data-center capacity at five Core Scientific sites — 262 MW of it at Denton, Texas — on 12-year licenses Core Scientific counts at more than $10B, and pays for most of the construction itself, getting part of it back as credits against its fees.
MicrosoftConstellation$16B
over 20 years · ≈ $0.8B a year
estimated, deal sourced
The power price is not disclosed: 835 MW for 20 years at an estimated ~$110 per MWh (analysts' range $98–120) ≈ $16B over the contract's life.
Microsoft signed a 20-year deal for the output of the retired Three Mile Island reactor, about 835 MW, which Constellation plans to restart in 2027; the price is undisclosed.
Amazon / AWSVistra$16B
over 20 years · ≈ $0.8B a year
estimated, deal sourced
No price is disclosed. The width is 1,200 MW for 20 years at ~$75/MWh, the low end of analysts' estimates for this deal ($75–$120; half worked back from Vistra's own cash-flow forecasts, the rest showing no working) ≈ $16B; at $120 it would be ≈ $25B.
Vistra is to supply Amazon 1,200 MW ('up to', its results release says) of Comanche Peak nuclear power for 20 years from late 2027; the price is undisclosed, and Texas has yet to approve the hookup.
Lenders & bondholdersNebius$0.775B sourcedNebius raised about $775M from banks led by MUFG. It pledged graphics chips already serving one unnamed investment-grade customer and the customer's payments.
GoogleAES Indiana$0.77B
paid over years at a rate no record gives · drawn at its full amount
estimated, deal sourced
No contract value is public; Google's rates are confidential. The width adds two filed costs its payments are set to cover (our sum): the $737.3M Monrovia Project — batteries, solar and grid upgrades — and the $32.3M it prepays to connect its site ≈ $0.77B.
AES Indiana will power 390 MW of new load at Google's planned data center in Monrovia, Indiana, under a 15-year contract approved on Oct 7, 2026, adding $737.3 million of batteries, solar and power lines whose yearly cost Google's rates are set to cover even at its minimum demand — though the order also has all customers share in the $73.8 million of network upgrades.
CoreWeaveApplied Digital$11B
over 15 years · ≈ $0.73B a year
sourcedCoreWeave rents all 400 MW of Applied Digital's Polaris Forge 1 campus in Ellendale, North Dakota, under three leases of about 15 years that Applied Digital counts at about $11B. With the leases, Applied Digital gave CoreWeave warrants on about 21.5 million of its shares.
MetaConstellation$14B
over 20 years · ≈ $0.7B a year
estimated, deal sourced
No price is disclosed: our arithmetic, 1,121 MW every hour for 20 years at ~$70/MWh, the low end of outside estimates for this deal ($70–90) ≈ $14B gross. Constellation calls it a virtual PPA; if it settles financially, this width would overstate what Meta pays.
Meta signed a 20-year deal for the output of Constellation's Clinton nuclear plant in Illinois from June 2027: 1,121 MW, 30 MW of it from upgrades expected to be complete in 2029; the price is undisclosed.
NeubergerCrusoe$0.7B sourcedNeuberger Specialty Finance gave Crusoe a $700M credit facility to buy gas generators for on-site power at AI data centers Crusoe builds and owns.
BlackstoneDigital Realty$0.7B sourcedBlackstone's funds agreed to put about $700M into a venture for an 80% stake in four Digital Realty data center campuses, then planned at about 500 MW.
NvidiaIREN$3.4B
over 5 years · ≈ $0.68B a year
sourcedNvidia agreed to pay IREN about $3.4B over five years for AI chip capacity in Texas for its own use. It pays only after accepting delivery.
FluidstackTeraWulf$6.7B
over 10 years · ≈ $0.67B a year
sourced
TeraWulf's own $6.7B of contracted revenue over the leases' first 10 years, stated only in press releases, never in its annual or quarterly reports.
Fluidstack rents 378 MW of data-center capacity from TeraWulf for about $6.7B over ten years; Google covers up to about $3.2B if Fluidstack defaults, for near-free TeraWulf shares.
InfraHUMAIN$0.667B sourcedSaudi Arabia's state infrastructure fund, Infra, signed two financing facilities of up to SAR 2.5B (~$667M) with HUMAIN: up to SAR 1.1B to buy GPUs for about 25 MW, and up to SAR 1.4B for grid works designed for up to 1 GW.
Amazon / AWSTalen Energy$0.65B sourcedAmazon bought a data-center campus beside Talen's Pennsylvania nuclear plant for $650M and agreed to buy up to 1,920 MW of its power through 2042, delivered over the grid.
Amazon / AWSConstellation$13B
over 20 years · ≈ $0.65B a year
estimated, deal sourced
No price is disclosed and the record has no estimate for this plant: 690 MW for 20 years at ~$110/MWh — the rate drawn for Microsoft's Three Mile Island restart, borrowed — ≈ $13B. About 500 MW of it is output the plant already makes; 190 MW is new.
Amazon will buy 690 MW of Constellation's Calvert Cliffs nuclear power for 20 years, about 190 MW of it from upgrades due in 2030–2032; the price is undisclosed, and the power stays on the grid.
GoogleNextEra Energy$14B
over 25 years · ≈ $0.56B a year
estimated, deal sourced
No price is disclosed and the record has no estimate for this plant: the low end of Google's contested share, ~565 MW, for 25 years at ~$110/MWh — the rate drawn for Microsoft's Three Mile Island restart, borrowed — ≈ $14B, if the plant runs that long; its licence ends in 2034.
Google signed a 25-year deal for most of the power of Iowa's shut Duane Arnold nuclear plant (615 MW), which NextEra plans to restart by early 2029 if regulators approve; the price is undisclosed.
GoogleQuaise Energy$0.5B
paid over years at a rate no record gives · drawn at its full amount
estimated, deal sourced
Neither company's announcement gives a value, price or term. The width is the floor Quaise gave the press, 'more than $500 million', drawn whole because no party states the years it is paid over.
Google will buy 50 MW of superhot geothermal power from Quaise Energy's Project Obsidian in Central Oregon, a plant whose first well was being drilled in October, beginning as early as 2030, for its data centers at The Dalles; neither company gives a price or a term, and Quaise told the press the deal is valued at more than $500 million.
NvidiaCorning$0.5B sourcedNvidia paid Corning $500M for warrants covering up to 18M Corning shares. Corning's filings also show a $1.0B Nvidia deposit under a supply deal through 2029.
MicronGlobalWafers$0.5B sourcedMicron plans to put $500M into expanding GlobalWafers' Texas wafer plant and buy its silicon wafers for 10 years. GlobalWafers says they signed a letter of intent.
OpenAISB Energy$0.5B sourcedOpenAI is renting two data-center buildings on 15-year leases, with about 753 MW for computing. SoftBank's SB Energy is building them in Texas.
FluidstackHut 8$7B
over 15 years · ≈ $0.47B a year
sourcedFluidstack is renting a 245 MW data center Hut 8 is building in Louisiana for Anthropic — $7.0B over 15 years — and Google guarantees the rent, amount undisclosed.
AnthropicRiot Platforms$9.1B
over 20 years · ≈ $0.45B a year
sourcedAnthropic is renting a 191 MW data center that Riot is building in Texas — about $9.1B of rent over 20 years, up to $16.1B with extensions.
OracleDTE Electric$7.8B
over 17.3 years · ≈ $0.45B a year
estimated, deal sourced
No total is filed. The width adds the contracts' own numbers: the minimum monthly charge at full ramp ($19.03M) for the 207 months to Feb 2045 ≈ $3.9B, plus DTE's ~$3.9B estimate of the battery charges ≈ $7.8B — before energy bills and the batteries' market credits.
An Oracle subsidiary will buy the Saline Township campus's power from DTE until February 2045, paying for at least 80% of 1,383 MW used or not, and for up to 1,383 MW of new batteries.
Amazon / AWSBlackstone Digital Infrastructure Trust$4.9B
over 12 years · ≈ $0.41B a year
estimated, deal sourced
No document gives the rent in dollars. BXDC's 7.0% cap rate is the first year's base rent over the $5.0B value, so about $350M to start; rising 2.75% a year, the 12-year weighted-average initial term comes to about $4.9B. Our arithmetic, on rounded inputs.
Amazon agreed to sell 75.1% of 13 data centers worth $5.0B to Blackstone Digital Infrastructure Trust if paid at least $4.33B in cash at closing. Amazon will rent all 13 back.
US governmentMP Materials$0.4B sourcedThe Pentagon paid $400M for MP Materials preferred stock and lent it $150M. It backs a new Texas magnet plant for ten years and tops up a magnet material's price to $110 a kilogram through 2035.
TSMCGlobalFoundries$2B
over 5 years · ≈ $0.4B a year
sourced · not drawn above: TSMC and GlobalFoundries sit in the same part of the chainGlobalFoundries says it will make silicon parts for TSMC's chip packaging in Malta, New York, in a $2 billion deal with an initial term of five years.
FluidstackCipher Digital$3.8B
over 10 years · ≈ $0.38B a year
sourced
Cipher's own ~$3.8B over the lease's first 10 years, stated only in a press release, never in its annual or quarterly reports.
Fluidstack is renting Cipher's new Texas data center for about $3.8B over 10 years; Google guarantees up to $1.73B of the rent and gets about 5.4% of Cipher, nearly free.
Amazon / AWSCipher Digital$5.5B
over 15 years · ≈ $0.37B a year
sourced
Cipher's own ~$5.5B over the lease's first 15 years, stated only in its releases and slides; its annual and quarterly reports give no dollar figure for the lease, and no Amazon document in the record states one.
Amazon's subsidiary is renting, for 15 years, the 300 MW data center Cipher is making of a former bitcoin mine near Wink, Texas — about $5.5B of rent by Cipher's estimate — under a 'limited' Amazon.com guarantee, and a Cipher subsidiary has borrowed $2.0B of bonds to build it.
CoreWeaveBackblaze$0.335B
paid over years at a rate no record gives · drawn at its full amount
sourcedCoreWeave is to pay Backblaze an estimated $335M under order forms of five and seven years for storage — space on Backblaze's hard drives in Backblaze's data centers, and Backblaze's storage software run in CoreWeave's — and Backblaze gave CoreWeave warrants for up to 4,194,876 of its shares at $7.60 that unlock as the contract runs.
MetaCleanSpark$6.6B
over 20 years · ≈ $0.33B a year
sourced
CleanSpark's own ~$6.6B over the lease's first 20 years, stated only in its releases, slides and calls; the filed parts of its 8-Ks, its 10-Q and the bond indenture give no dollar figure for the lease.
Meta's subsidiary Anviran rents a 175 MW data center CleanSpark is building in Sandersville, Georgia for 20 years, about $6.6B of rent by CleanSpark's estimate, with a 'limited' Meta guarantee.
Fermi AmericaSiemens Energy$0.32B sourcedFermi agreed to buy three Siemens Energy F-class gas turbines for about $324.4M, plus up to about $240M over ten years paid by how reliably they run, and ordered six smaller ones expected in 2028, borrowing through a loan facility of up to $500.0M that also refinanced an earlier loan and supports Fermi's other turbines, and one of up to $165.0M for the six.
GoogleFervo Energy$4.7B
over 15 years · ≈ $0.31B a year
estimated, deal sourced
No price or contract value is public. The width is our difference of Fervo's own backlog: ~$11.9B at Sep 30 less ~$7.2B at Jun 30 ≈ $4.7B — the quarter this 396 MW PPA was its only addition (1,054 − 658 MW) — over the 15-year term.
Google will buy 396 MW of Fervo's Utah geothermal output for 15 years, used or not, first power expected in 2028; Fervo must offer about 600 MW more by June 2030, and the price is undisclosed.
SK TelecomHYAICO$0.26B sourcedSK Telecom committed up to $480M to buy new shares in HYAICO, SK hynix's US AI investment company, to be paid in as HYAICO calls for it, until June 2030. It had paid $257.2M by September 30, 2026.
CohereBell Canada$0.22B
paid over years at a rate no record gives · drawn at its full amount
estimated, deal sourced
Cohere's own figure: 'a landmark C$309 million GPU cloud partnership with Bell AI Fabric', about US$0.22B at 1.3993 Canadian dollars to the US dollar. Cohere gives no term and names no BUZZ; whether it is the money behind HIVE's contract, no document says.
HIVE's GPU-cloud arm, BUZZ HPC, will run about 2,300 Nvidia GB200 GPUs at Bell's Merritt, B.C., data center for Cohere to run its models on, under a three-year contract HIVE values at about $225M and says Bell pays; to buy the GPUs it borrowed about $129M at a fixed 9.0%, secured only on the chips.
ChronoScaleOD1 JV Holdings$0.22B sourced · not drawn above: OD1 JV Holdings is not in the chart's columnsSTN put its contract to supply an unnamed frontier AI lab with GPU computing in Odessa, Texas — expected to bring up to $7.5B over about six years — into a venture it is to share 50/50 with ChronoScale, which lent the venture $220M, $200M of it for GPUs from Super Micro.
OD1 JV HoldingsSupermicro$0.2B sourced · not drawn above: OD1 JV Holdings is not in the chart's columnsSTN put its contract to supply an unnamed frontier AI lab with GPU computing in Odessa, Texas — expected to bring up to $7.5B over about six years — into a venture it is to share 50/50 with ChronoScale, which lent the venture $220M, $200M of it for GPUs from Super Micro.
GoogleAEP$4B
over 20 years · ≈ $0.2B a year
estimated, deal sourced
No price is public. The width stands in with the ~$4B AEP plans to invest in the plant whose power Google buys for 20 years — not Google's payments, which would also have to cover the plant's gas, its running costs and AEP's return.
AEP plans to spend about $4 billion on a 702 MW plant of Bloom Energy fuel cells near Cheyenne, Wyoming, and sell its power to Google for 20 years; the price is not disclosed.
SK TelecomPenguin Solutions$0.2B sourcedSK Telecom sold its Penguin Solutions stake to an SK hynix unit for $377.2M cash in October 2026. It had invested $200M, then bought AI hardware from Penguin.
AnthropicEverWind$4B
over 20 years · ≈ $0.2B a year
estimated, deal sourced
Neither side publishes the rent. The width is our arithmetic: Anthropic's 20-year leases at TeraWulf and Riot run about $40–48M per MW, so 95 MW is roughly $4B over 20 years. A comparison, not a figure from this lease.
Anthropic leases the first 95 MW of EverWind's planned Point Tupper campus in Nova Scotia, its first data-centre lease in Canada; EverWind calls it a 20-year lease, and the rent is undisclosed.
KTMicrosoft$1B
over 5 years · ≈ $0.2B a year
sourced
KT files the commitment in won only: ₩1,365 billion. At the Fed's daily rates since its term began (₩1,322–1,556 to the dollar) that is $0.88–1.03B; drawn at about $1B.
KT's cloud arm committed to buy at least ₩1,365B of Microsoft cloud services. It and KT supply Microsoft with US$450M in network and data center infrastructure, a figure KT says may change.
GoogleBlack Hills Corp.$4.2B
over 22 years · ≈ $0.19B a year
estimated, deal sourced
No contract value is public. The width adds two Black Hills figures through 2048 (our sum): the $1.8B it invests in generation, which the contracts repay in full, and ~$2.4B of unlevered free cash flow after it ≈ $4.2B — before the fuel and operating costs Google also bears.
Black Hills will power Google's planned data center in Cheyenne, Wyoming through 2048 — up to 590 MW from the grid, most of it from new gas generation it is spending about $1.8 billion to build, plus about 2.1 GW of other companies' plants it manages for the campus on a private microgrid — with Google bearing the costs, by Black Hills' account; Google has also advanced $398.8 million for the equipment, which Black Hills is to repay by June 2027.
GoogleDTE Electric$3.1B
over 19 years · ≈ $0.16B a year
estimated, deal sourced
No total is filed. The width is the minimum bill alone, at today's rates: about $165.1M a year for the ~19 years from full load to the term's expected end ≈ $3.1B — before energy bills and the cost of the renewables and storage Google pays for, which is not public.
Google will buy power for its 1 GW Michigan data center from DTE for 20 years, paying for at least 80% of it used or not, plus up to 1,600 MW of renewables and 480 MW of storage at their actual cost.
GoogleXcel Energy$2.4B
over 15 years · ≈ $0.16B a year
estimated, deal sourced
No total is filed. The width is the minimum bill alone at the petition's sample rate: 75% of demand charges on 780 MW at $22.84 per kW-month ≈ $160M a year × 15 years ≈ $2.4B — before energy, riders and the charge for the 1,900 MW of clean energy, whose cost is redacted.
Google will buy the power for a planned 780 MW data center at Pine Island, Minnesota, from Xcel Energy for 15 years, paying a minimum bill whatever it uses and, through a Clean Energy Accelerator Charge, the yearly cost of 1,900 MW of wind, solar and long-duration batteries that Xcel would own and run for all its customers; the contract awaits Minnesota regulators, with a decision expected in early 2027.
Thinking Machines LabBoost Run$0.47B
over 3 years · ≈ $0.16B a year
sourcedThinking Machines Lab agreed in May 2026 to pay Boost Run about $471.7M to rent 5,000 Nvidia B300 GPUs, with storage and CPU servers, for an initial 36 months — orders it cannot cancel, with fees owed whether or not it uses the servers.
US governmentMP Materials$0.15B sourcedThe Pentagon paid $400M for MP Materials preferred stock and lent it $150M. It backs a new Texas magnet plant for ten years and tops up a magnet material's price to $110 a kilogram through 2035.
Lenders & bondholdersHIVE Digital$0.129B sourcedHIVE's GPU-cloud arm, BUZZ HPC, will run about 2,300 Nvidia GB200 GPUs at Bell's Merritt, B.C., data center for Cohere to run its models on, under a three-year contract HIVE values at about $225M and says Bell pays; to buy the GPUs it borrowed about $129M at a fixed 9.0%, secured only on the chips.
CerebrasDigi Power X$1.1B
over 10 years · ≈ $0.11B a year
sourcedCerebras licenses a whole 40 MW data center Digi Power X is building in Alabama for ten years at $195/kW a month, ~$1.1B by Digi Power X's count; 25 MW hinges on financing Cerebras approves.
CohereBoost Run$0.53B
over 5 years · ≈ $0.11B a year
sourcedCohere agreed in September 2026 to pay Boost Run about $525.6M for dedicated racks of Nvidia GB300 GPUs, each rented for about five years from the day Cohere accepts it; nothing is owed on a rack before then, and if too little is accepted by July 15, 2027 Cohere can walk away with its prepayment refunded.
NebiusAIB Data Centers$1.25B
over 12 years · ≈ $0.1B a year
estimated, deal sourced
Neither company files the rent or a total. The width is the lowest estimate on file, an analyst's ~$1.25B over the 12-year term, read out on AIB's call; AIB's own deck implies ~$1.32B, a figure it first worked out before the lease was signed.
Nebius has signed for 50 MW of computing capacity in two halls that AIB Data Centers is building on a former bitcoin-hosting site in South Carolina, for 12 years from each hall's start, with Nebius's parent guaranteeing; Nebius's prepayment, paid into an escrow that AIB draws on for the build, comes back if AIB misses its dates, and no contract value is filed.
SupermicroLambda$0.0925B sourcedSuper Micro took a 10-year lease on 21 MW of data center space in Vernon, California, and sublicensed it all to Lambda, staying liable to the landlord.
NscaleWhiteFiber$0.865B
over 10 years · ≈ $0.09B a year
sourcedNscale rents 40 MW of IT capacity at WhiteFiber's NC-1 data center in Madison, North Carolina, for ten years: about $865M by WhiteFiber's count, yearly price rises and one-time installation charges included and power billed on top. All 40 MW were running by November 2026.
SpaceXStateline Power$0.086B sourcedStateline Power — owned 50.1% by Solaris Energy Infrastructure, which runs it, and 49.9% by a SpaceX subsidiary — is to rent SpaceX about 900 MW of power-generation equipment for an initial seven years to run a data center off the grid; SpaceX paid $86M in cash for its stake, Solaris put in $86.4M of non-cash assets, and the rent has not been disclosed.
GoogleOG&E$0.8B
over 10 years · ≈ $0.08B a year
estimated, deal sourced
No total is filed: Google's demand and term are redacted. The width is the Commission staff's hypothetical ~$79M a year of demand charges, for 10 years ≈ $0.8B before energy and fuel — the 10 being HB 2992's minimum term, which the proposed findings say the ESAs meet.
OG&E will power three Google data centers planned in Muskogee County and Stillwater, Oklahoma, with minimum charges and Google paying 100% of the lines built only to connect them — and Google sells OG&E, for 15 years, about 360 MW of summer and 120 MW of winter capacity from two solar farms, paid for by all OG&E's customers; Oklahoma approved it in November 2026, and Arkansas has yet to rule on the capacity contracts.
CerebrasZone Frontier$0.8B
over 10 years · ≈ $0.08B a year
sourcedCerebras has signed for all 40 MW of IT load at a data center being built in Minnesota, for ten years at about $800M as Zone Frontier puts it; Zone took 79% of the landlord after the contract was signed and says it needs project debt, not yet committed, to fund the build.
Bell CanadaHIVE Digital$0.225B
over 3 years · ≈ $0.08B a year
sourced
HIVE's ~$225M over three years ($220M for GPU compute, the rest connectivity and storage), stated only in releases it furnishes to the SEC and its deck, never filed. HIVE's November deck names Bell as the paying party; Bell's own documents give no value.
HIVE's GPU-cloud arm, BUZZ HPC, will run about 2,300 Nvidia GB200 GPUs at Bell's Merritt, B.C., data center for Cohere to run its models on, under a three-year contract HIVE values at about $225M and says Bell pays; to buy the GPUs it borrowed about $129M at a fixed 9.0%, secured only on the chips.
Lenders & bondholdersOD1 JV Holdings$0.074688B sourced · not drawn above: OD1 JV Holdings is not in the chart's columnsSTN put its contract to supply an unnamed frontier AI lab with GPU computing in Odessa, Texas — expected to bring up to $7.5B over about six years — into a venture it is to share 50/50 with ChronoScale, which lent the venture $220M, $200M of it for GPUs from Super Micro.
CoreWeaveBlockfusion$1.1B
over 15 years · ≈ $0.07B a year
estimated, deal sourced
No filing values the 35 MW lease, and its rent line is redacted. Width is our arithmetic: the $145 per kW a month its definitions name, on 35 MW, rising 3% a year for 15 years, ≈ $1.1B. The landlord's 'up to $2.8 billion' counts 85 MW, 50 of them on conditions.
CoreWeave has leased 35 MW of take-or-pay capacity at the AI data center Blockfusion is developing in Niagara Falls, New York, for 15 years once both phases are delivered (targeted for 2028), and agreed to pay $50 million toward the site's power hookup. Separately, it paid Blockfusion $30 million, not counted as rent, for a warrant on about 2.8 million shares.
Thinking Machines LabCrusoe$0.065B
a year · term unstated
sourcedThinking Machines Lab will pay Crusoe $65 million a year to serve its open models on a dedicated Nvidia B200 cluster Crusoe runs under a service-level agreement; no term, GPU count or site is given.
CoreWeaveBlockfusion$0.05B sourcedCoreWeave has leased 35 MW of take-or-pay capacity at the AI data center Blockfusion is developing in Niagara Falls, New York, for 15 years once both phases are delivered (targeted for 2028), and agreed to pay $50 million toward the site's power hookup. Separately, it paid Blockfusion $30 million, not counted as rent, for a warrant on about 2.8 million shares.
NV EnergyOrmat Technologies$0.7B
over 15 years · ≈ $0.05B a year
estimated, deal sourced
No contract value is stated. The width is the PPA's own numbers: $107/MWh on the first year's supply amount, 437,623 MWh, for the 15 contract years after the build-out ≈ $0.7B — about 50 MW, the contract's floor. At its 150 MW ceiling it would be about three times that.
Ormat will build 50 to 150 MW of new geothermal plants across Nevada and sell their power to NV Energy at a fixed $107 per megawatt-hour until 15 years after the build-out ends, in 2030 at the latest, and NV Energy passes all of it to Google's data centers through its Clean Transition Tariff, under which Google says it covers the cost; Nevada's regulators have yet to approve it.
GoogleNV Energy$0.7B
over 15 years · ≈ $0.05B a year
estimated, deal sourced
What Google pays NV Energy is in filings the record could not read. Ormat and Google say the tariff has Google cover the cost, so the width is the cost it takes on: the PPA's $107/MWh on its first year's 437,623 MWh, for 15 years ≈ $0.7B.
Ormat will build 50 to 150 MW of new geothermal plants across Nevada and sell their power to NV Energy at a fixed $107 per megawatt-hour until 15 years after the build-out ends, in 2030 at the latest, and NV Energy passes all of it to Google's data centers through its Clean Transition Tariff, under which Google says it covers the cost; Nevada's regulators have yet to approve it.
LambdaSupermicro$0.4365B
over 10 years · ≈ $0.04B a year
sourcedSuper Micro took a 10-year lease on 21 MW of data center space in Vernon, California, and sublicensed it all to Lambda, staying liable to the landlord.
MicrosoftKT$0.45B
over 15 years · ≈ $0.03B a year
sourced
KT's Mar 2026 bond prospectus gives the whole US$450M a 15-year supply period; its Sep 2024 filing gives the 15 years to the data centers and the network part none. Drawn over 15 years, ≈ $30M a year — an average no filing schedules, and KT says the amount may change.
KT's cloud arm committed to buy at least ₩1,365B of Microsoft cloud services. It and KT supply Microsoft with US$450M in network and data center infrastructure, a figure KT says may change.
CoreWeaveBlockfusion$0.03B sourcedCoreWeave has leased 35 MW of take-or-pay capacity at the AI data center Blockfusion is developing in Niagara Falls, New York, for 15 years once both phases are delivered (targeted for 2028), and agreed to pay $50 million toward the site's power hookup. Separately, it paid Blockfusion $30 million, not counted as rent, for a warrant on about 2.8 million shares.
Amazon / AWSX-energy$0.02B sourced
Drawn at the $20M convertible note, the one Amazon investment X-energy's filings put a figure on: a floor, not Amazon's total. Amazon's own pages say '$500 million'; X-energy's release and Amazon's 2024 report give about $500 million as the round's size; it closed at $700M.
Amazon anchored X-energy's 2024 round, got a warrant for no extra payment, held 22.9% of its Class A shares after the 2026 listing, and has first call on 2031–2039 reactor slots it need not buy.
Not on the map yet 45 in the record no ribbon reaches so far

LatestWhat's new

November 2026

  1. Nov 18
  2. Nov 17 updated Nov 21
  3. Nov 17 updated Nov 21
  4. Nov 17
  5. Nov 17
  6. Nov 16
  7. Nov 16 updated Nov 21
  8. Nov 11 updated Nov 21
Filters · showing everything
Show
Basis
Tier
Min