Georgia Power–OpenAI

Georgia Power will supply OpenAI's planned Project Camellia campus near Savannah with up to 3,210 for 25 years and can have it cut up to 1,000 MW when the grid is strained; the price is secret.

A deal between OpenAI, Georgia Power

Why it matters

Georgia Power filed OpenAI's contract as a trade secret 'in its entirety', keeping the dollar amounts private. The regulator's staff used its 30-day objection window to secure broader commitments. On data-center contracts approved under Georgia's 2025 rules, Georgia Power promised not to ask the commission to make customers under 100 cover early-exit shortfalls.

Tap a figure for the line in its source.

Georgia Power gives OpenAI

  • of electric service for the campus, delivered in phases between 2028 and 2032, for 25 years

OpenAI gives Georgia Power

  • a monthly minimum bill, owed whether or not it uses the power and set to recover the cost of serving it over the term; the amount is a trade secret
  • upfront payments for the local infrastructure built for the campus, such as lines, substations and grid equipment, before service starts
  • of its demand cut when Georgia Power calls for it to protect the grid, within limits that are not public, while still paying the full minimum bill
  • an exit payment if it ends the contract early, and security from creditworthy backers such as a parent guaranty, letter of credit or surety bond; neither amount is public

Jul 22, 2026 announced by OpenAI and Georgia Powerupdated Nov 21, 2026deemed approved Aug 26 2026 disclosed by the parties

What happened

Georgia Power, the state's biggest utility, will supply OpenAI's planned 'Project Camellia' data-center campus in Effingham County, near Savannah. The contract covers up to 3,210 megawatts for 25 years, phased in from 2028. OpenAI pays a monthly minimum bill even if it uses no power. It pays upfront for local grid equipment built for the campus, such as lines and substations. It owes an exit payment if it leaves early. It must cut up to 1,000 megawatts when Georgia Power calls on it. The contract was filed as a trade secret, so none of the dollar amounts is public. Georgia's regulators never voted on it. Under their 2025 rules, a contract is approved unless commission staff objects within 30 days. An objection only sends it to the commissioners, who then have 30 days to act. The staff dropped its threatened objection in August 2026 once Georgia Power made several promises. One applies to every data-center contract approved under those rules. Georgia Power promised not to ask the commission to make customers under 100 megawatts pay any shortfall if a data center leaves early. Homes and nearly every business fall below that threshold. It is up to the commission whether other big customers or Georgia Power itself would cover the shortfall.

Sources 45 documents — 14 regulatory filings · 11 press reports · 8 other documents · 6 company releases · 2 SEC filings · 2 research notes · 1 transcript · 1 government statement

Research trail Found 228 documents and read 179 of them while checking this deal and related ones.

  1. Georgia PSC · regulatory filingservices.psc.ga.gov
    States 5 figures: 3,210 MW contract capacity · term · up to 1,000 MW demand response · upfront infrastructure · termination
  2. Georgia PSC · regulatory filingservices.psc.ga.gov
    States 4 figures: approval · joint statement · at least $15 downward pressure · exit letter to psc
  3. Motley Fool · transcriptJul 30, 2026fool.com
    States 3 figures: 100% minimum bill · security · 1 GW generation gap
  4. SEC · SEC filingsec.gov
    States 2 figures: at least $949M downward pressure per year · framework
  5. Georgia PSC · regulatory filingservices.psc.ga.gov
    States 2 figures: 3,200 MW april commitment · 2,800 MW load ramp Q1
  6. company release (archived copy)openai.com
    States 3.2 GW announced
  7. Georgia PSC · regulatory filingservices.psc.ga.gov
    States load ramp
  8. DocumentCloud (hosted document) · other documents3.documentcloud.org
    States county power model
  9. regulatory filingservices.psc.ga.gov
    Cited by the record; no single figure is quoted from it.
  10. regulatory filingservices.psc.ga.gov
    Cited by the record; no single figure is quoted from it.
  11. regulatory filingservices.psc.ga.gov
    Cited by the record; no single figure is quoted from it.
  12. regulatory filingservices.psc.ga.gov
    Cited by the record; no single figure is quoted from it.
  13. regulatory filingpsc.ga.gov
    Cited by the record; no single figure is quoted from it.
  14. regulatory filingservices.psc.ga.gov
    Cited by the record; no single figure is quoted from it.
  15. regulatory filingservices.psc.ga.gov
    Cited by the record; no single figure is quoted from it.
  16. regulatory filingservices.psc.ga.gov
    Cited by the record; no single figure is quoted from it.
  17. regulatory filingservices.psc.ga.gov
    Cited by the record; no single figure is quoted from it.
  18. regulatory filingpsc.ga.gov
    Cited by the record; no single figure is quoted from it.
  19. company releasegeorgiapower.com
    Cited by the record; no single figure is quoted from it.
  20. company releasegeorgiapower.com
    Cited by the record; no single figure is quoted from it.
  21. company releasegeorgiapower.com
    Cited by the record; no single figure is quoted from it.
  22. company releasegeorgiapower.com
    Cited by the record; no single figure is quoted from it.
  23. other documentprojectcamellia.com
    Cited by the record; no single figure is quoted from it.
  24. other documentprojectcamellia.com
    Cited by the record; no single figure is quoted from it.
  25. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  26. company releases27.q4cdn.com
    Cited by the record; no single figure is quoted from it.
  27. other documents3.documentcloud.org
    Cited by the record; no single figure is quoted from it.
  28. government statementeffinghamcounty.org
    Cited by the record; no single figure is quoted from it.
  29. other documentAug 2026projectcamelliaeffingham.com
    Cited by the record; no single figure is quoted from it.
  30. other documents3.documentcloud.org
    Cited by the record; no single figure is quoted from it.
  31. press reportAug 14, 2026gpb.org
    Cited by the record; no single figure is quoted from it.
  32. press reportAug 4, 2026thecurrentga.org
    Cited by the record; no single figure is quoted from it.
  33. press reportAug 8, 2026thecurrentga.org
    Cited by the record; no single figure is quoted from it.
  34. press reportAug 27, 2026thecurrentga.org
    Cited by the record; no single figure is quoted from it.
  35. press reportAug 30, 2026wtoc.com
    Cited by the record; no single figure is quoted from it.
  36. press reporteffinghamherald.net
    Cited by the record; no single figure is quoted from it.
  37. press reportdatacenterknowledge.com
    Cited by the record; no single figure is quoted from it.
  38. press reportJul 28, 2026insurancejournal.com
    Cited by the record; no single figure is quoted from it.
  39. other documentcleanenergy.org
    Cited by the record; no single figure is quoted from it.
  40. other documentwsbradio.com
    Cited by the record; no single figure is quoted from it.
  41. press reportaol.com
    Cited by the record; no single figure is quoted from it.
  42. press reportaol.com
    Cited by the record; no single figure is quoted from it.
  43. press reportaol.com
    Cited by the record; no single figure is quoted from it.
  44. research noteaidatacenterinsights.substack.com
    Cited by the record; no single figure is quoted from it.
  45. research notemeasuredai.substack.com
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: Georgia PSC Docket 44280: Georgia Power's transmittals (Jul 15, Aug 27, Sep 8 2026), review-extension letter (Aug 13), Joint Statement with PSC Staff (Aug 26), public contract summary (Sep 8) and minimum-revenue filing (Aug 27), PSC order voted Apr 15 and issued Apr 17 2025; Georgia Power's Q1 and Q2 2026 large-load reports; PSC data-center fact sheet (Sep 2026); Georgia Power releases (Jul 22, Aug 26 2026), its customer pledge and its Effingham County transmission-project page; OpenAI post, FAQ and fact sheet; Southern Company's Q2-2026 10-Q (signed Jul 29) and its call and call slides (Jul 30 2026); the county development authority's tax model and its values tab, its MOU with Octans GA and the MOU's amendment, and the County's PILOT projections; GPB, The Current, WTOC and SACE for the process and the contested cell; the Effingham Herald, Data Center Knowledge and Bloomberg (via Insurance Journal) for the rest; and, for the readings not adopted in the note, Kala Hunter's Ledger-Enquirer reports and the Savannah Morning News (both via AOL), WSB Radio, The Ledger and Measured AI (read 2026-10); Southern Company's 10-Q for Q3 2026 (filed Nov 5 2026) for its large-load book and the Aug 26 commitment's dollars · as of Nov 2026

The evidence 19 sourced figures · 1 dispute

The record's headline Georgia Power–OpenAI: 3,210 for 25 years for the Project Camellia campus near Savannah, up to 1,000 MW of it curtailable on call — the contract filed as a trade secret in its entirety, deemed approved on Aug 26 2026 when PSC Staff did not object, without a Commission vote

Size
3,210 MW (the executed contract) · 25-year term · up to 1,000 MW of on-call demand reduction · minimum bill, upfront infrastructure charges, termination payment and security: amounts trade secret
When
Oct 30 2025 (Georgia Power brokers OpenAI's first meeting with the county's development authority — The Current) → Apr 2026 (Georgia Power books 3,200 MW of new commitments, which count requests for service as well as contracts; inferred to be this project's request for service) → Jul 15 2026 (contract filed unexecuted) → Jul 22 (announced) → Aug 13 (Staff signals an objection; Georgia Power extends the review to Aug 26) → Aug 26 (Joint Statement; deemed approved) → Aug 27 (executed contract filed) → Sep 8 (public summary) → 2028–2032 (service, in phases)
Status
deemed approved Aug 26 2026 (Staff did not object; no Commission vote); executed contract filed Aug 27, public summary Sep 8; service from 2028 (Q2 2028 in Georgia Power's latest forecast)
Structure
a Contract for Electric Service (CES) between Georgia Power Company and OpenAI — the contracting entity is not named in any public filing — written on Georgia Power's large-load framework: under its Rules and Regulations as revised in Jan 2025, a customer of 100 MW or more can be required to sign a longer contract with a minimum bill, a termination payment and performance security, and under the PSC's April 2025 order each such contract is filed at least 30 days before it is executed and is deemed approved unless Staff objects within 30 days (an objection sends it to the five commissioners, and it is still approved if they take no action within 30 days). The campus's county side — the land and a bond-lease property-tax abatement — runs through OpenAI's affiliate Octans GA, LLC and the county's development authority under a separate memorandum (not this record)
Programme
Time-to-power
Parties
OpenAI customer — 'OpenAI' in the public summary and in the title of the executed contract's public version; the contracting entity is not named (the campus's county incentives run through its affiliate Octans GA, LLC); pays the minimum bill, the upfront infrastructure charges and any termination payment, posts performance security, and must cut up to 1,000 MW on call · Georgia Power utility — serves the load under its Rules and Regulations, may curtail up to 1,000 MW and suspend service to protect the grid, files the contract and its reports with the PSC; a subsidiary of Southern Company
Record
disclosed / primary source · as of Nov 2026

Flows 3 as the record states them

  • Georgia Power → OpenAIpowerelectric service up to 3,210 MW, phased in between 2028 and 2032 — 1,200 MW in 2028 rising to 3,210 MW in 2032 in Georgia Power's Q2 2026 forecast for the one project of that size in its report (anonymized; load-ramp) — for 25 years
  • OpenAI → Georgia Powerpower-paymentsmonthly bills of at least the minimum bill, which is set to recover the cost of serving the campus over the term and is owed even when it uses less or is curtailed, plus upfront charges for local infrastructure before service; every amount is a trade secret. The only public basis for a dollar estimate of the power bill is the county development authority's tax model: about $1.37B a year once built, at its own placeholder of 6¢ per kWh (county-power-model)
  • OpenAI → Georgia Powerdemand-responseup to 1,000 MW of demand reduction on Georgia Power's call, 'subject to defined limits on frequency, duration, and magnitude' that are not public

Resolved figures 19 each with the verbatim line from its document

  • announced3.2 GW
    first public on Jul 22 2026, the same day in OpenAI's post and Georgia Power's release; OpenAI: 'we are contracting with Georgia Power Company for 3.2 gigawatts of power which will be delivered in phases between 2028 and 2032', and its FAQ: 'phased development between 2028 and 2032, with initial capacity potentially coming online beginning in 2028'. Georgia Power's release the same day: OpenAI 'is expected to need approximately 3,200 megawatts (MW) of power'. The contract was already a week into PSC review — filed unexecuted on Jul 15 (approval) — but that filing named no customer: its public version is titled 'GPC & REDACTED - CES Packet'. On Southern's Jul 30 call its chief executive said 'Georgia Power signed a 3.2 GW 25-year contract for electric service with OpenAI', nearly four weeks before the contract was approved and executed
    “To support the data center, we are contracting with Georgia Power Company for 3.2 gigawatts of power which will be delivered in phases between 2028 and 2032.”
    OpenAI, 'Building AI infrastructure with the Effingham County community' (Jul 22 2026; Wayback snapshot) · web.archive.org
  • contract-capacity3,210 MW
    3,210 MW — the contract's quantity in the public summary Georgia Power filed under PSC Docket 44280 on Sep 8 2026, the one filing that ties the number to OpenAI ('the recently approved CES for the 3,210 MW OpenAI project located in Effingham County, Georgia'), and that caps the load: the customer 'may not increase its load above the applicable target – ultimately 3,210 MW – without Georgia Power's consent'. Georgia Power's transmittal of the executed contract (Aug 27 2026) gives the same 'large load contract for 3,210MW of electric service' without naming the customer. Georgia Power's releases ('approximately 3,200 megawatts (MW) of power' on Jul 22, '3,200 megawatts (MW) of new demand' on Aug 26), the PSC's fact sheet ('a 3,200MW contract between Georgia Power and a data center company') and OpenAI ('3.2 gigawatts') round it. A ceiling on the campus's load, not its average use; no filing says how much of it is IT load. WTOC's '3.1 gigawatts' and the Savannah Morning News's '3.2-megawatt demand' are slips (note)
    “Core protections introduced by the Rules and Regulations and subsequently included within the recently approved CES for the 3,210 MW OpenAI project located in Effingham County, Georgia, include:”
    Georgia Power public summary of the OpenAI contract (PSC Docket 44280, doc 228337, Sep 8 2026) · services.psc.ga.gov
  • term25 years
    25 years — the public summary Georgia Power filed with the PSC (Sep 8 2026): 'Extended Term: A contract term of 25 years.'; Georgia Power's release (Jul 22 2026): 'Under the 25-year agreement'; Southern's CFO on the Jul 30 call: 'the OpenAI contract is 25 years'. Georgia Power's customer pledge has new users of 100 MW or more sign 'long-term contracts of 15 to 25 years' — this one is at the top of that range. When the 25 years start is not public: the summary is headed 'Effective August 26, 2026' and dates the minimum bill from 'the service date', and neither says when the term starts
    “Extended Term: A contract term of 25 years.”
    Georgia Power public summary of the OpenAI contract (PSC Docket 44280, doc 228337, Sep 8 2026) · services.psc.ga.gov
  • demand-responseup to 1,000 MW
    up to 1,000 MW — about 31% of the 3,210 MW (our division) — that Georgia Power can call on OpenAI to shed. The public summary filed with the PSC (Sep 8 2026): 'The customer must reduce its electric demand by up to 1,000 MW when called upon by Georgia Power to protect system reliability. This allows the Company to defer or avoid generation capacity that would otherwise be required to serve the customer's load. The flexible demand reductions are subject to defined limits on frequency, duration, and magnitude' — limits not public; if OpenAI does not reduce, 'Georgia Power may curtail demand at the customer's premises', and 'The customer must continue paying its full minimum bill even during demand reductions'. Beyond the demand reductions, the summary gives Georgia Power 'the right to suspend service and install or operate protective equipment at the customer's expense' to protect the system (§1). Georgia Power calls it 'among the largest single-facility demand response commitments in the country'; asked on the Jul 30 call whether it was the first time Southern had done this for a data center, its chief executive answered 'Yes'. The '60 minutes' to respond comes from OpenAI's Hank Evans, as the Effingham Herald reports him; no filing states this contract's response time. Georgia Power's release of Jul 22 2026 gave the same ceiling first: OpenAI 'has agreed to provide up to 1,000 MW of flexible demand response where it will reduce its power use in times of high demand'
    “The customer must reduce its electric demand by up to 1,000 MW when called upon by Georgia Power to protect system reliability.”
    Georgia Power public summary of the OpenAI contract (PSC Docket 44280, doc 228337, Sep 8 2026) · services.psc.ga.gov
  • approval
    deemed approved on Aug 26 2026 without a Commission vote. Under the PSC's April 2025 order Georgia Power files each large-load contract at least 30 days before executing it, and 'If Staff does not file an objection within thirty (30) days of the filing of the contract, the contract shall be deemed approved'; 'While the PSC is required to review these large-load data center contracts, it does not have to vote to approve them' (The Current). Georgia Power filed this one on Jul 15 as 'a seventh large load contract for Commission Staff review prior to execution', unexecuted and 'trade secret in their entirety' (§3). On Aug 13 the PSC's utilities director, Tom Bond, told the commissioners 'Right now, unless the company agrees to certain changes, staff would file an objection' (GPB) — an objection would have sent the contract to the five commissioners — and the same day Georgia Power agreed that 'the filing date of the contract for purposes of the 30-day review cycle will be July 27, 2026', moving the deadline from Aug 14 to Aug 26: 12 days (§4). On Aug 26 Staff and Georgia Power filed the Joint Statement (joint-statement, downward-pressure) and Staff did not object. The executed contract followed on Aug 27, 'filed as trade secret in its entirety', its one-page public version titled 'Executed CES - OpenAI & GPC' and 'Redacted in its entirety' (§5)
    “Based on the above agreements, Staff acknowledges that the existing Large Load contract portfolio protects Non-Large Load customers from bearing any of the costs of serving new Large Load customers, and therefore Staff does not object to the contract filed on July 27, 2026.”
    Joint Statement of PSC Staff and Georgia Power (PSC Docket 44280, doc 228126, Aug 26 2026) · services.psc.ga.gov
  • joint-statement
    what Staff's non-objection rests on, filed jointly on Aug 26: if any large-load data-center contract 'approved pursuant to the Orders' (the 2025 review process this one went through) ends early, Georgia Power 'shall not seek to recover from Non-Large Load customers' — those 'with loads below 100 MW' — any 'Incremental Cost Revenue Deficiency' for the rest of the contract's term. The deficiency is measured across ALL such data-center customers (their forecast incremental cost against their actual and forecast revenue over the contracts' initial terms), reduced by termination payments, by mitigation ('including but not limited to remarketing of capacity, avoided generation capacity, avoided transmission, retirements, and replacement customer loads') and by their net benefits; what is left is the Commission's to place: 'It shall be at the Commission's discretion to determine if, and how, any Incremental Cost Revenue Deficiency not mitigated will be recovered, including the allocation of such costs to other Large Load customers.' The PSC's utilities director on what that means: 'we'll have to decide whether we'll get Georgia Power to eat it or we're going to make other large-load customers pay for it' (WTOC). The same letter also commits Georgia Power to a semi-annual public report on the large-load data-center portfolio, a public summary of each contract at filing, the conditional $15 floor (downward-pressure) and a letter to the Commission within 15 days of any early-termination notice (exit-letter-to-psc). It covers every such contract, not OpenAI's alone, and says nothing of what OpenAI's own exit would cost (termination)
    “In the event of an early termination of a Large Load Data Center Customer contract approved pursuant to the Orders (“Large Load Data Center Customer”), the Company agrees that, in future ratemaking proceedings, it shall not seek to recover from Non-Large Load customers any Incremental Cost Revenue Deficiency associated with serving Large Load Data Center Customers during the remaining term for which the contract would have been in place but for early termination.”
    Joint Statement of PSC Staff and Georgia Power (PSC Docket 44280, doc 228126, Aug 26 2026) · services.psc.ga.gov
  • downward-pressureat least $15
    at least $15.00 a month of 'downward pressure' on rates for the typical residential customer (1,000 kWh a month) in 2029, 2030 and 2031, raised from the $8.50 Georgia Power agreed to in the Dec 2025 stipulation — a replacement, not an addition: $15 × 12 = $180 a year, Georgia Power's own 'from the company's December 2025 commitment of $102 per year to $180 per year' (the additive '$15 per month plus the $8.50 per month … totals $180' in Kala Hunter's Ledger-Enquirer report, syndicated on AOL, which credits the sum to Georgia Power's chief executive ('Greene added'), does not add up — the company's own release quotes the chief executive: 'Today, that number is expected to be $180'). Conditional and portfolio-wide: 'to the extent this and future Large Load contracts sufficient to cover the generating capacity certified in Docket Nos. 56298 and 56310 are approved' — the stipulation that set the $8.50, and with it the Dec 2025 certification (9,885 MW in Southern's filings, 9,985 MW in the PSC's fact sheet — georgiapower) — delivered 'by agreeing to a minimum incremental revenue forecast', dated Aug 26 and filed Aug 27 with every year REDACTED. On that capacity the PSC's fact sheet says: 'With the execution of the August 2026 contract, Georgia Power has secured customers for all 9,985 MW of energy generation'. Georgia Power puts the savings from the large-load portfolio's projected revenue at about $950M a year, $2.847B over 2029–31; Southern's Q3 10-Q files the yearly dollars as 'at least $949 million per year, on a levelized basis' (downward-pressure-per-year). Not a cut to today's bills — 'increases from other factors, such as storm damage and fuel costs, can outstrip the promised cuts' (The Current) — and not OpenAI's money alone, though OpenAI's fact sheet lists '$180/year' of residential savings among the project's benefits (in the copy on file under its July 26 file name, a later version titled '9.13 Camellia Fact Sheet V2') and Georgia Power credits the increase to this contract: 'It was $102 back in December of 2025, and now it is $180 thanks to this contract with OpenAI' (its spokesperson Matthew Kent, in WSB Radio's 'Georgia Power says OpenAI deal could save customers about $15 a month starting in 2029')
    “To further ensure that residential customers and small commercial customers benefit from the large load growth, and to the extent this and future Large Load contracts sufficient to cover the generating capacity certified in Docket Nos. 56298 and 56310 are approved, the Company agrees to increase the downward pressure on rates from $8.50 per month to now provide at least $15.00 per month to the typical residential customer using an average of 1,000 kWh per month for the years 2029, 2030, and 2031 by agreeing to a minimum incremental revenue forecast for those years.”
    Joint Statement of PSC Staff and Georgia Power (PSC Docket 44280, doc 228126, Aug 26 2026) · services.psc.ga.gov
  • downward-pressure-per-yearat least $949M
    at least $949 million a year, levelized, for 2029, 2030 and 2031 — Southern's own aggregate figure for the Aug 26 commitment, which the Joint Statement states per typical home (at least $15.00 a month; its text carries that and no total — downward-pressure) and Georgia Power's release gives as 'approximately $950 million per year, increasing customer benefits to $2.847 billion over the three-year period of 2029-2031' (3 × $949M is $2,847M — our arithmetic). The Q3 10-Q says it was 'as a result of additional large load contracts' that Georgia Power agreed 'to increase the amount of downward pressure on rates for non-large load customers to be included in its next base rate case' to that amount — the Dec 19 2025 8-K's 'at least $556 million per year' ($8.50 a month), raised. It names no customer, so it does not say whose contract it was, and it does not repeat the condition the Joint Statement attaches (contracts 'sufficient to cover the generating capacity certified' in Dockets 56298 and 56310). It also restates the Joint Statement's other term in Southern's words: Georgia Power 'will not seek recovery from non-large load customers for any revenue deficiency associated with serving large load data center customers in the event of an early contract termination', and 'The Georgia PSC will continue to have discretion to allow recovery of any such revenue deficiency, including the allocation to other large load data center customers' (joint-statement)
    “agreed to increase the amount of downward pressure on rates for non-large load customers to be included in its next base rate case to at least $949 million per year, on a levelized basis, for the years 2029, 2030, and 2031.”
    Southern Company / Georgia Power combined 10-Q, Q3 2026 (Note (B), Regulatory Matters — Georgia Power; repeated in Georgia Power's MD&A) · sec.gov
  • exit-letter-to-psc15 days
    15 days: how long Georgia Power has to tell the Commission, by letter, after a large-load customer gives notice that it is ending its contract early — the utility's reporting duty, not the customer's notice period. The customer's own notice is 'significant advance written notice' (public summary), its length not public. This clause is not a 15-day cancellation notice for the customer.
    “provide a letter to the Commission within 15 days of the Company’s receipt of termination notification from the Large Load customer.”
    Joint Statement of PSC Staff and Georgia Power (PSC Docket 44280, doc 228126, Aug 26 2026) · services.psc.ga.gov
  • minimum-bill100%
    a monthly minimum bill whose amount is a trade secret. The public summary: 'A minimum bill requirement that recovers the costs to serve the customer over the term of the CES. The customer must pay at least the monthly minimum bill amount after the service date regardless of whether it consumes electric service'. Southern's CFO, asked on the Jul 30 call how the large-load tariffs work 'from a credit standpoint' for 'OpenAI and other customers who maybe are not investment-grade credits': 'Our minimum bills cover 100% of the incremental cost to serve.' How that cost is computed is not public either — the PSC's April 2025 order: 'the minimum bill amounts would be set to recover the transmission and generation costs being incurred to serve the new large-load customers', and 'The Company has provided Staff with a framework for determining minimum bills, but not a definitive calculation that Staff can replicate' (§7)
    “Our minimum bills cover 100% of the incremental cost to serve.”
    Southern Company Q2 2026 earnings call (Motley Fool transcript, Jul 30 2026) — CFO David Poroch · fool.com
  • upfront-infrastructure
    upfront charges for the local grid built for the campus, paid before service starts — amount not public: 'Upfront charges requiring the customer to pay for local infrastructure – like transmission lines, substations, and grid reliability equipment – before the customer receives service' (public summary); Georgia Power, Aug 26: 'OpenAI will pay the full cost of the infrastructure needed to serve it'. Georgia Power's page for a new 500/230 kV Effingham County substation and 500 kV transmission infrastructure says that project 'is being developed to serve the electric needs of a large-load customer' and also strengthens the local grid, on a timeline it calls tentative (substation land acquisition from fall 2026, substation construction from fall 2027); it names no customer and no cost, and how the cost splits between that customer and everyone else is not public. Generation is not among the upfront charges the summary lists; under the 2025 framework the minimum bill recovers it over the term (minimum-bill, generation-gap), and if the contract ends early the termination payment recovers the investments made to serve the customer (termination)
    “Upfront charges requiring the customer to pay for local infrastructure – like transmission lines, substations, and grid reliability equipment – before the customer receives service.”
    Georgia Power public summary of the contract (PSC Docket 44280, doc 228337, Sep 8 2026) · services.psc.ga.gov
  • termination
    an exit payment whose amount, exact formula and notice period are trade secret: 'A termination payment framework that recovers costs of investments made to serve the customer if the CES is terminated prior to the end of its term. Customer early termination requires significant advance written notice (thus allowing Georgia Power time to make alternative grid planning arrangements) and payment of a substantial termination payment amount' (public summary). Southern's CFO: 'there are default provisions in there, and those default payments are tied to collateral' (security). How many years of bills an exit covers under Georgia's framework is disputed (contested exit-cost); any shortfall is measured across all the data-center contracts approved under the PSC's review process, and Georgia Power has promised not to seek it from customers under 100 MW (joint-statement)
    “Customer early termination requires significant advance written notice (thus allowing Georgia Power time to make alternative grid planning arrangements) and payment of a substantial termination payment amount.”
    Georgia Power public summary of the contract (PSC Docket 44280, doc 228337, Sep 8 2026) · services.psc.ga.gov
  • security
    performance security whose amount is not public: 'from creditworthy sources, such as a parent guaranty, letter of credit, or surety bond', with replacement security due, on pain of default, if a provider's creditworthiness falls below thresholds in the contract (public summary). The one figure said about it was withdrawn on the same call: Southern's CFO first told an analyst 'you asked specifically about OpenAI, and that is about $20.8 billion of collateral that will be in the aggregate on full ramp', then corrected himself — 'I was talking about the entire portfolio, so I apologize for that. You know, the whole portfolio of the 17 GW, we got about $21 billion of collateral.' So $20.8B and $21B are Southern's large-load portfolio's, never OpenAI's alone (the correction is the CFO's own) — but which part of the portfolio is not settled: the whole 17 GW in the CFO's words, while Southern's own slide for the call lists '$21B+ collateral' (required by 2028) under its '13GW contracted after Q2 2025' alone, not under the '17GW total signed across 31 projects' (the two readings differ: one takes the Q2 10-Q's ~13 GW of contracts with collateral terms (framework; the Q3 10-Q's is ~16 GW) as settling it on the newer contracts; the other leaves the scope unsettled). Southern's Q2 and Q3 10-Qs describe the form, not the amount (framework)
    “the whole portfolio of the 17 GW, we got about $21 billion of collateral.”
    Southern Company Q2 2026 earnings call (Motley Fool transcript, Jul 30 2026) — CFO David Poroch · fool.com
  • framework
    Southern's own filed description of its large-load contracts, as its Q3 10-Q words it (quarter to Sep 30, filed Nov 5 2026; whether it counts this one among them, it does not say — below): 'All of the Large Load Contracts contain minimum bill provisions', and those 'totaling approximately 16 GWs of electric load (including substantially all signed after 2024) also contain minimum duration, termination payment requirements, and financial security requiring customers to post collateral or provide an acceptable guarantee based on the customer's credit ratings'; 'Certain Large Load Contracts requiring construction of specifically dedicated assets contain provisions for contribution by the customer to construction costs.' The Q2 10-Q (quarter to Jun 30, signed Jul 29 2026) had the same sentence at 'approximately 13 gigawatts', over a smaller book: it counted 'approximately 11 gigawatts' of contracts 'reviewed by the applicable state PSC' and 'approximately five gigawatts' more that 'have been agreed with customers and are subject to review by the applicable state PSC' ('approximately 16 gigawatts of new contracts'), where the Q3 10-Q counts 'approximately 16 GWs' reviewed and 'approximately four GWs' more awaiting review ('approximately 20 GWs of new contracts'), and moves the start of service under the remaining contracts from 'through 2028' to 'through 2029'. Neither 10-Q names a customer or says whether it counts this contract, filed with the PSC on Jul 15 and deemed approved Aug 26: a contract then under Staff review would fit the Q2 10-Q's 'approximately five gigawatts' awaiting review, and the Q3 10-Q's reviewed count is about 5 GW above the Q2 10-Q's (our reading from the rounded figures — neither filing ties either change to a customer); the 'over 17 GW' Southern's chief executive gave on Jul 30 counts it ('these four projects representing 6 GW of newly contracted customer load', Alabama's three and OpenAI's)
    “Large Load Contracts totaling approximately 16 GWs of electric load (including substantially all signed after 2024) also contain minimum duration, termination payment requirements, and financial security requiring customers to post collateral or provide an acceptable guarantee based on the customer's credit ratings.”
    Southern Company / Georgia Power combined 10-Q, Q3 2026 (MD&A) · sec.gov
  • generation-gap1 GW
    the contract outruns the generation Georgia Power has had approved: 'The OpenAI contract in Georgia pushes us beyond our recently approved capacity by right around 1 GW' (Southern's chief executive, Christopher Womack, Jul 30 2026), added to the CFO's answer on the generation RFPs ('Thing I would add … So just making sure that was real clear terms of where we are'); earlier in the Q&A, answering another analyst, the CFO, David Poroch, had said 'we are probably about 1 GW or 2 away from if you will, selling out the capacity. That we had approved in Georgia last year'; later on the call the CFO put it the chief executive's way: 'We are about 1 GW or so oversubscribed, if you will. In Georgia based on what we have signed.' Neither names the capacity; Georgia Power's latest approval is the Dec 2025 All-Source certification — 9,885 MW in Southern's filings, 9,985 MW in the PSC's Sep 2026 fact sheet, which says the August contract filled it: 'With the execution of the August 2026 contract, Georgia Power has secured customers for all 9,985 MW of energy generation, four months ahead of schedule' (georgiapower). Spoken on a call, not filed. The CFO's rule of thumb from the same call — 'about $2 billion or so, a little bit above maybe related to 1 GW of new generating capacity' — is Southern's own capital, not a payment by OpenAI; Kala Hunter's report for the Columbus Ledger-Enquirer, syndicated on AOL, turns it into 'about $7 billion for 3.2 GW project' and credits the chief executive with it (note)
    “The OpenAI contract in Georgia pushes us beyond our recently approved capacity by right around 1 GW.”
    Southern Company Q2 2026 earnings call (Motley Fool transcript, Jul 30 2026) — CEO Christopher Womack · fool.com
  • april-commitment3,200 MW
    3,200 MW of new commitments in April 2026, three months before the announcement — the footnote to Georgia Power's Q1 large-load report (as of Mar 31, filed May 15 2026), whose cover letter redacts the number. The Q2 report (Aug 17) carries it: the portfolio 'has grown by 3,200 MW, reaching a total of 15,600 MW across 32 customers', from the Q1 report's 12,400 MW across 31 — 'commitments' meaning 'Contracts for Electric Service plus Requests for Electric Service', and at Jun 30 the report's one 3,210 MW row still stood at 'Request for Service', with a contract under Commission review only 'Since Q2' (load-ramp). No report names the customer: that the April commitment is OpenAI's is inference — the size, the date and the Q2 report's one 3,210 MW project (load-ramp) line up, and Data Center Knowledge, writing on Jul 28 before the Q2 report existed, drew the same inference from the Q1 report's footnote and attachment while noting that 'anonymized planning records cannot definitively identify the customer' — not a statement. Read with The Current's account that Georgia Power brokered OpenAI's first meeting with the county's development authority on Oct 30 2025
    “There were commitments added totaling 3,200 MW in April of 2026 that are not included in these values, which will be included in the second quarter report.”
    Georgia Power Q1 2026 Large Load Economic Development Report (PSC Dockets 55378/56002, doc 226607, May 15 2026), footnote 1 · services.psc.ga.gov
  • load-ramp
    Georgia Power's latest forecast for the one 3,210 MW project in its Q2 2026 large-load report (as of Jun 30, filed Aug 17): service from Jun 1 2028 (the date the workbook gives every project due to start in Q2 2028), then 1,200 MW in 2028, 1,300 in 2029, 2,300 in 2030, 2,700 in 2031 and 3,210 from 2032 — the row's stage moved from 'Technical Review' to 'Request for Service', footnoted as quoted. OpenAI's own 'delivered in phases between 2028 and 2032' fits it. Anonymized: the tie to OpenAI is inferred from the 3,210 MW and the footnote — the contract Staff was reviewing then is the 3,210 MW one (contract-capacity) — not stated. The executed contract's own target ramp is not public: the summary says only that the load may not exceed 'the applicable target – ultimately 3,210 MW' without Georgia Power's consent. The previous quarter's version of this ramp ran a year faster (load-ramp-q1)
    “*Since Q2 this project has a Contract for Electric Service currently under Commission review.”
    Georgia Power Q2 2026 Large Load Economic Development Report, public workbook (PSC Dockets 55378/56002, doc 227753, Aug 17 2026) · services.psc.ga.gov
  • load-ramp-q12,800 MW
    the same row one quarter earlier, in the Q1 2026 report (as of Mar 31, filed May 15): 'Technical Review', initial service Q2 2028, then 1,200 MW in 2028, 1,500 in 2029, 2,800 in 2030 and 3,210 from 2031 (the quoted line is the row's 2028–2036 cells). The Q2 report's 'Ramp Change' sheet shows the revision for 2029–31: −200, −500 and −510 MW, full load a year later. A dated series of one issuer's forecast, not a dispute — the 'load ramp' remained disputed because the Q2 version was known only through relays such as The Ledger's and no document gives the executed contract's own ramp; the Q2 workbook settles which forecast is current, not the contract's ramp (load-ramp). Data Center Knowledge's 'The projected load ramps to approximately 3.2 GW by 2031' read this earlier version
    “1,200 1,500 2,800 3,210 3,210 3,210 3,210 3,210 3,210”
    Georgia Power Q1 2026 Large Load Economic Development Report (PSC Dockets 55378/56002, doc 226607, May 15 2026), attachment · services.psc.ga.gov
  • county-power-model1,900,000,000
    the only public basis for an estimate of what the campus will spend on power, and not from the contract: a forecast spreadsheet of the county's development authority ('Industrial Building Model'; '7-1-26' and 'scenario-a' in its file name — 'The development authority released its revenue estimate spreadsheets' to The Current, which links them as a DocumentCloud set; this copy is on DocumentCloud, and the model's 2029 and 2032 PILOT rows match, within a million dollars, the County's published 'approximately $10 million'/'$14 million' and '$27 million'/'$39 million') assumes the built-out campus uses 1,900,000,000 kWh a month, about 22.8 TWh a year or about 2.6 GW on average — some 81% of the 3,210 MW (our arithmetic) — at 'Electricity cost per kWh 0.0600 Estimate', to forecast sales tax on the power bill: about $1.37B a year once all four of its buildings are in ('Building 1' to 'Building 4' in its companion values tab), phased over 2029–32 (our multiplication; Measured AI publishes the same, note). A tax planner's placeholder price, not a tariff — the contract's rates are trade secret and the public summary gives none. The link's est width is drawn on it
    “Electricity used per month 1,900,000,000 kWh”
    Effingham County Industrial Development Authority forecast model, Scenario A (DocumentCloud; '7-1-26' in its file name) · s3.documentcloud.org

Contested figures 4 not reconciled — every position side by side, with its source and tier

exit-cost4 positions, side by side
the remaining term's minimum bills — the draft terms Staff reviewed in 2025: 'If the customer ended the contract early, the customer would be liable for the minimum bill amounts (not tariffed rate amounts) for each period for the remaining term of the contract'; Southern's own July call slides tie its framework's termination payments, likewise, 'to the remaining incremental costs to serve over the life of the contract' PSC order on Georgia Power's Revision to Rules and Regulations Tariff Compliance Filing (Docket 44280; voted Apr 15, issued Apr 17 2025); Southern Company Q2 2026 call slides (Jul 30 2026)
two years of minimum bills — 'it was later revealed that if a contract is terminated early, only 2 years of minimum bills are required, not the full length of the remaining contract' (Maggie Shober, SACE, Aug 17 2026, on the 2025 rules) SACE (cleanenergy.org), Aug 17 2026
four years of fifteen — Peter Hubbard, now a commissioner, as The Current reports what he said at a data center forum in Savannah in June: 'loopholes in the rules the PSC passed in 2025 allow a company to make only four years of payments, instead of a full 15' The Current, Aug 4 2026
for this contract, 'a substantial termination payment amount' that 'recovers costs of investments made to serve the customer' — no number, no formula (termination); any shortfall is then measured across all the data-center contracts approved under the PSC's review process, net of termination payments, mitigation and their net benefits, and what remains is the Commission's to place: it decides 'if, and how' that is recovered — from other large-load customers, or, in the PSC utilities director's words, by having Georgia Power 'eat it' — while Georgia Power has promised not to seek it from customers under 100 MW (joint-statement) Georgia Power public summary (Sep 8 2026); Joint Statement (Aug 26 2026); the PSC utilities director as WTOC quotes him (Aug 30 2026)

Scope note what this record leaves to other records

Not this record: the campus and its county deal — the Effingham County Industrial Development Authority's memorandum of understanding with OpenAI's affiliate Octans GA, LLC ('dated for purposes of reference as of July 21, 2026' and 'effective, as of July 21, 2026' on its face; its Aug 31 amendment, on DocumentCloud, recites 'as of July 25, 2026' — a date that remains disputed): a bond-lease property-tax abatement, an 'estimated cumulative capital investment of at least $20,000,000,000' over an estimated five phases and an 'estimated cumulative creation of at least 400 new jobs', the land sale, and the residents' and SELC's lawsuits — not carried here for a site record; the '$20 billion' the press carries is that goal, not a figure in the PSC docket, and Bloomberg's 'probably be more than $30 billion' at full size is one interview with OpenAI's Sachin Katti. Southern Company's large-load contracts (the Q2 10-Q's ~16 GW of 'new contracts' since 2023, 'over 17 GW' on the call, the Q3 10-Q's ~20 GW), their collateral (~$21B: the whole 17 GW's in the CFO's spoken correction, the 13 GW contracted after Q2 2025 on Southern's own call slide — a scope that remains disputed between the two readings; security) and the Dec 2025 certification sit on georgiapower; Meta's Entergy contracts are ent-meta-esas. Not adopted: WTOC's '3.1 gigawatts, about 14% of Georgia Power's total capacity' (sourced to a Georgia Power web page 'last updated in December', before the deal); the Savannah Morning News's '3.2-megawatt demand' (a unit slip); Kala Hunter's 'about $7 billion for 3.2 GW project' (the CFO's ~$2B-per-GW rule of thumb for Southern's own generation, applied to the whole load and credited to Southern's chief executive) and '$15 per month plus the $8.50 per month … totals $180' (credited there to Georgia Power's chief executive; the $15 replaces the $8.50), both in her Columbus Ledger-Enquirer reports, syndicated on AOL; the $20.8B of collateral the CFO withdrew as the whole portfolio's (security); Georgia Power's own 'now it is $180 thanks to this contract with OpenAI' (its spokesperson, as WSB Radio relays him — the issue is WSB's headline, which credits Georgia Power; the pledge is conditional and portfolio-wide — downward-pressure); The Ledger's 'fifteen-day summary' (a page on the AI Data Center Insights Substack, not a newspaper; the Joint Statement gives 10 days); and Measured AI's 'The Bill: $1.37 Billion a Year, $32 Billion over 25 Years', which reads like contract economics (Measured AI names its basis, the development authority's fiscal model at 'the model's estimated price of $0.06' — county-power-model).

More between OpenAI and Georgia Power

The record holds no other deal between them.