Fermi–Siemens Energy, Project Matador

Fermi agreed to buy three Siemens Energy F-class gas turbines for about $324.4M, plus up to about $240M over ten years paid by how reliably they run, and ordered six smaller ones expected in 2028, borrowing through a loan facility of up to $500.0M that also refinanced an earlier loan and supports Fermi's other turbines, and one of up to $165.0M for the six.

A deal between Fermi America, Siemens Energy

Why it matters

Fermi borrowed against its turbines before it had signed a lease with a tenant. The MUFG loan closed about six months before Fermi's first customer lease at Matador, which ended without taking effect, and an amendment that dropped the loan's 400 lease condition came with $25.0M in fees. Part of Siemens Energy's pay is contingent: up to about $240M over ten years, set by how reliably the three F-class turbines run.

Tap a figure for the line in its source.

Siemens Energy gives Fermi America

  • large F-class gas turbines and related equipment for Project Matador, purchase agreed Jan 28 2026 — at the Port of Houston in July 2026, two of the turbines on site by Nov 12; their rating is given five ways (simple-cycle-capacity)
  • smaller gas turbines ordered in October 2025, scheduled in pairs during 2028 — no filing on file gives their price

Fermi America gives Siemens Energy

  • the fixed price for the three, ~$276.6M of it paid by Mar 31 2026, part of it from the MUFG loan's first borrowing; shipping and import duties on top
  • more over ten years from the turbines' provisional acceptance, under a Rated Capacity Agreement: $80 thousand to $2M per turbine a quarter, by how reliably each runs — none recognized by Sep 30 2026
  • progress payments for the six SGT-800s: $38.43M paid by Fermi before the Beal Bank USA loan closed, later ones paid from that loan

Sep 25, 2025 announced by Fermi as a letter of intent for the three F-class turbines disclosed by the parties

What happened

Fermi is building Project Matador, a power and data-center campus in the Texas Panhandle. In September 2025 it signed a letter of intent with Siemens Energy for three large F-class gas turbines. It agreed the purchase in January 2026, at a fixed price of about $324.4 million plus shipping and import duties. By the end of March it had paid about $276.6 million. A related Rated Capacity Agreement adds payments to Siemens for ten years once the turbines are provisionally accepted. Each quarter Fermi would pay Siemens between $80 thousand and $2 million per turbine, depending on how reliably it runs. Those payments are capped at about $240 million. Nothing had been recognized under that agreement by September 30, 2026. Each purchase sits in a Fermi subsidiary that borrows against the turbines. MUFG's loan facility of up to $500.0 million closed in February 2026, at SOFR plus 4.0%. It also repaid an earlier Macquarie loan and supports Fermi's other turbines. $444.9 million was outstanding at September 30. Without a 400 lease or by November 10, 2026, its minimum repayments would have been 10% a quarter instead of 5%. The lenders' agent could also have begun marketing the turbines. An October amendment removed that condition, among other changes, and Fermi paid $25.0 million in amendment fees. MUFG passed its loans to a syndicate of new lenders and stayed on as agent. Fermi must still close fully committed financing for Matador's first phase, enough with any equity for at least 400 MW, by February 10, 2027, or the loan is in default. In March 2026 a second subsidiary took a loan facility of up to $165.0 million at 12.00%. It pays for six smaller Siemens SGT-800 turbines, ordered in October 2025 and expected in 2028. The latest filing names the lender as Beal Bank USA; earlier filings named its affiliate CSG Investments. An exit fee of $37.0 million, less the interest and commitment fees already paid, comes due at the end. Both loans closed before Fermi signed its first customer lease at Matador, with TensorWave in August 2026. That lease was terminated in November without taking effect.

Sources 20 documents — 12 SEC filings · 5 company releases · 1 transcript · 1 other document · 1 law-firm note
  1. SEC · SEC filingsec.gov
    States 19 figures: up to $240M rca max · up to $2M rca quarterly · at least $80,000 rca floor · rca term · rca recognized · up to $500M mufg facility · mufg use · $444.9M mufg outstanding · 65% mufg LTV · $25M mufg amendment · 5% min principal · at least 400 MW financing test · up to $165M beal facility · beal lender · $37M beal exit fee · beal maturity · $32.3M beal outstanding · beal guaranty · $126.2M siemens commitments
  2. SEC · SEC filingsec.gov
    States 4 figures: f class epa · $324.4M f class price · rca integrated · 4% mufg rate
  3. SEC · SEC filingsec.gov
    States 2 figures: 12% beal rate · $38.43M sgt800 progress
  4. PR Newswire · company releaseprnewswire.com
    States LOI
  5. SEC · SEC filingsec.gov
    States delivery
  6. SEC · SEC filingsec.gov
    States sgt800 order
  7. SEC · SEC filingsec.gov
    States first lease
  8. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  9. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  10. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  11. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  12. company releaseprnewswire.com
    Cited by the record; no single figure is quoted from it.
  13. company releaseprnewswire.com
    Cited by the record; no single figure is quoted from it.
  14. company release (archived copy)accessnewswire.com
    Cited by the record; no single figure is quoted from it.
  15. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  16. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  17. transcriptstockanalysis.com
    Cited by the record; no single figure is quoted from it.
  18. other documentukozvhzgrcnkcatjqfoo.supabase.co
    Cited by the record; no single figure is quoted from it.
  19. company releasesiemens-energy.com
    Cited by the record; no single figure is quoted from it.
  20. law-firm notedavispolk.com
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: Fermi FY2025 10-K (filed Mar 30 2026) + Q1, Q2 and Q3 2026 10-Qs (May 14, Aug 14, Nov 12); 8-Ks of Feb 10, Mar 27 and Oct 16 2026 with the MUFG and Beal credit agreements (Ex. 10.1); Fermi releases of Sep 25 2025, Feb 10, Mar 27 and Jul 21 2026; Fermi's May, Aug and Nov 2026 investor decks · as of Nov 2026

The evidence 29 sourced figures · 3 disputes

The record's headline Fermi–Siemens Energy, Project Matador: three SGT6-5000F gas turbines at a ~$324.4M fixed price, plus up to ~$240M over ten years by how reliably they run, and six SGT-800s expected in 2028 — paid for partly through turbine-warehouse loans of up to $165.0M (Beal Bank USA) and up to $500.0M (MUFG, which also refinanced an earlier loan and supports Fermi's other turbines), both closed before Fermi had signed its first customer lease

Size
3 SGT6-5000F at a ~$324.4M fixed price + up to ~$240M over 10 years by reliability · 6 SGT-800s, price in no filing on file · MUFG facility up to $500.0M ($444.9M outstanding) · Beal Bank USA facility up to $165.0M ($32.3M outstanding), at Sep 30 2026
When
Sep 25 2025 letter of intent for three F-class units → Oct 2025 six SGT-800s ordered → Jan 28 2026 F-Class EPA and Rated Capacity Agreement → Feb 10 2026 MUFG facility closes, $201.6M (or $168.3M) to Siemens → Mar 26 2026 Beal Bank USA facility → Jul 2026 F-class units at the Port of Houston → Oct 9 2026 MUFG Amendment No. 1, loans assigned to a syndicate → Nov 12 2026 two F-class turbines on site
Status
the three F-class units reached the Port of Houston in July 2026; by Nov 12 two of the turbines and all three generators were on site and the third turbine awaited transport (delivery). Nothing recognized under the Rated Capacity Agreement at Sep 30 2026; its ten years start only at the turbines' provisional acceptance. The six SGT-800s scheduled in pairs during 2028. Both loans partly drawn at Sep 30 2026: $444.9M on the MUFG facility, $32.3M on the Beal facility. The MUFG facility's Feb 10 2027 project-financing test not yet met when the Q3 10-Q was filed (financing-test). Fermi's first customer lease at Matador, TensorWave's, ended without taking effect (first-lease)
Structure
turbine warehouses: each order sits in its own Fermi subsidiary, which borrows against the turbines. Fermi Turbine Warehouse LLC holds the F-class purchase and the Rated Capacity Agreement, which Fermi calls 'a single integrated commercial arrangement with Siemens' (rca-integrated), and borrows under the MUFG facility, secured on the equipment, with Firebird Equipment Holdco as subsidiary guarantor ('non-recourse' in Fermi's Feb 10 release). Fermi Turbine Warehouse II LLC took the October 2025 SGT-800 supply agreement by assignment and borrows under the Beal Bank USA facility, which Fermi guarantees (beal-guaranty)
Programme
Time-to-power
Parties
Fermi America buyer, borrower and payer under the Rated Capacity Agreement, through Fermi Turbine Warehouse LLC (the F-class units; MUFG facility) and Fermi Turbine Warehouse II LLC (the six SGT-800s; Beal Bank USA facility); guarantor of the Beal facility · Siemens Energy seller of both orders, through Siemens Energy, Inc., and payee under the Rated Capacity Agreement; paid partly from the loans' proceeds, and named as a lender in neither facility
Record
disclosed / primary source · as of Nov 2026

Resolved figures 29 each with the verbatim line from its document

  • loi3
    where it began: a letter of intent of Sep 25 2025 under which 'Siemens Energy will negotiate to deliver' three SGT6-5000F units — a negotiation, not yet a purchase (f-class-epa). Its 'up to 1.1 GW' is one of four combined-cycle ratings Fermi has given them (combined-cycle-capacity). A second letter of intent the same day, on nuclear steam turbines and generators, is not this record (note)
    “Under the first letter of intent, Siemens Energy will negotiate to deliver three F-class SGT6-5000F gas turbine units, producing up to 1.1 GW at ISO conditions once in combined cycle mode.”
    Fermi release, Sep 25 2025 (PR Newswire) · prnewswire.com
  • f-class-epa3
    the purchase: on Jan 28 2026 Fermi formed Fermi Turbine Warehouse LLC and, through it, agreed with Siemens Energy, Inc. to buy three SGT6-5000F units and related equipment and services — the 'Siemens F-Class EPA'. It carries 'performance warranties and liquidated damages for delay or performance shortfalls, subject to negotiated caps' (same filing). The EPA itself is not filed
    “On January 28, 2026, the Company formed its first long-lead equipment warehouse entity, Fermi Turbine Warehouse LLC (“FTW”), a Texas limited liability company and an indirect wholly owned subsidiary of the Company, and entered into an arrangement with Siemens Energy, Inc. (“Siemens”) for the purchase of three SGT6-5000F gas turbine units and related equipment and services for Project Matador (the “Siemens F-Class EPA”).”
    Fermi Q1 2026 10-Q, MD&A — Recent Developments (filed May 14 2026) · sec.gov
  • f-class-price$324.4M
    ~$324.4M, the fixed price for the three units; ~$276.6M of it paid by Mar 31 2026; shipping and import duties paid on top, as incurred. The FY2025 10-K gives the same two figures. The Rated Capacity Agreement's payments come on top of this (rca-max). Drawn as the record's one ribbon
    “The fixed price portion of the Siemens F-Class EPA is approximately $324.4 million, and as of March 31, 2026, the Company has paid approximately $276.6 million. In addition to the fixed price amount, the Company is obligated to pay shipping costs and applicable import duties, as incurred, pursuant to the contract.”
    Fermi Q1 2026 10-Q, MD&A — Recent Developments (filed May 14 2026) · sec.gov
  • rca-maxup to $240M
    the Rated Capacity Agreement's ceiling: approximately $240.0M, undiscounted, over ten years — 'additional, contingent consideration for the turbines', owed to Siemens by how reliably each turbine runs. It is what $2M a quarter for each of three turbines comes to over 40 quarters. Note 8 of the same 10-Q states the terms in thousands ('$2,000', '$80', '$240,000'). The agreement itself is not filed
    “Under the RCA, the Company is liable to pay Siemens up to $2 million per turbine per calendar quarter based on the operating reliability of each turbine, and not less than $80 thousand per turbine per quarter, for ten years commencing upon provisional acceptance of the turbines, subject to a maximum of approximately $240.0 million on an undiscounted basis.”
    Fermi Q3 2026 10-Q, MD&A — Commitments (filed Nov 12 2026) · sec.gov
  • rca-quarterlyup to $2M
    up to $2M per turbine per calendar quarter, 'based on the operating reliability of each turbine' — the most a quarter can cost. How reliability is measured is not disclosed; the Q1 10-Q's first account says the payments are 'based primarily on specified reliability metrics' (rca-integrated)
    “Under the RCA, the Company is liable to pay Siemens up to $2 million per turbine per calendar quarter based on the operating reliability of each turbine, and not less than $80 thousand per turbine per quarter, for ten years commencing upon provisional acceptance of the turbines, subject to a maximum of approximately $240.0 million on an undiscounted basis.”
    Fermi Q3 2026 10-Q, MD&A — Commitments (filed Nov 12 2026) · sec.gov
  • rca-floorat least $80,000
    at least $80 thousand per turbine per quarter, whatever the reliability
    “Under the RCA, the Company is liable to pay Siemens up to $2 million per turbine per calendar quarter based on the operating reliability of each turbine, and not less than $80 thousand per turbine per quarter, for ten years commencing upon provisional acceptance of the turbines, subject to a maximum of approximately $240.0 million on an undiscounted basis.”
    Fermi Q3 2026 10-Q, MD&A — Commitments (filed Nov 12 2026) · sec.gov
  • rca-term10 years
    ten years, starting only at the turbines' provisional acceptance — a date no filing on file gives
    “Under the RCA, the Company is liable to pay Siemens up to $2 million per turbine per calendar quarter based on the operating reliability of each turbine, and not less than $80 thousand per turbine per quarter, for ten years commencing upon provisional acceptance of the turbines, subject to a maximum of approximately $240.0 million on an undiscounted basis.”
    Fermi Q3 2026 10-Q, MD&A — Commitments (filed Nov 12 2026) · sec.gov
  • rca-recognized
    nothing recognized under the Rated Capacity Agreement at Sep 30 2026, as at Jun 30 (Q2 10-Q); Fermi accounts for it as contingent consideration under its 10-K's policy
    “No amounts were recognized under the RCA as of September 30, 2026.”
    Fermi Q3 2026 10-Q, Note 8 Commitments and Contingencies (filed Nov 12 2026) · sec.gov
  • rca-integrated
    one bargain: the Q1 10-Q's first account of the agreement calls it 'a related long-term commercial agreement with Siemens providing for ongoing payments over a ten-year period following acceptance of the equipment, based primarily on specified reliability metrics', entered by Fermi Turbine Warehouse LLC, negotiated with the purchase and meant to work with it as one
    “The equipment supply contract and the related agreement were negotiated together and are intended to operate as a single integrated commercial arrangement with Siemens.”
    Fermi Q1 2026 10-Q, MD&A — Recent Developments (filed May 14 2026) · sec.gov
  • delivery
    the three F-class units reached the Port of Houston in July 2026 (Fermi's Jul 21 release: 'the arrival of three Siemens Energy SGT6-5000F natural gas turbines at the Port of Houston'). On Fermi's Nov 12 deck: 'Two turbines on site', 'All three generators on site', and the third turbine still to move
    “One turbine awaiting transport to site in late November/early December”
    Fermi Q3 2026 investor presentation (Ex. 99.2 to the Nov 12 2026 8-K) · sec.gov
  • mufg-facilityup to $500M
    MUFG Bank's senior secured equipment loan warehouse facility of up to $500.0M, entered Feb 10 2026 by Fermi Turbine Warehouse LLC, with Firebird Equipment Holdco as subsidiary guarantor and MUFG 'as initial sole lender'. Borrowings allowed for nine months from closing; matures 18 months from closing, Aug 10 2027. Fermi's release calls it 'non-recourse'; the MUFG executives it quotes call it 'an initial step toward what will become the largest power and AI datacenter campus'
    “The Credit Agreement provides for a senior secured equipment loan warehouse facility in an aggregate principal amount of up to $500.0 million.”
    Fermi Q3 2026 10-Q, MD&A — Liquidity (filed Nov 12 2026) · sec.gov
  • mufg-use
    three uses, so not all of the $500.0M is the F-class units': their purchase, repaying the Macquarie Term Loan (repaid in full on Feb 10 2026, with a $24.8M loss on extinguishment), and turbines 'across Fermi's existing fleet'
    “The Turbine Warehouse Equipment Financing was entered into to fund purchases under the Company’s equipment purchase agreement with Siemens Energy, Inc. (“Siemens”) for three SGT6-5000F turbines (the “Siemens F-Class EPA”) and related equipment for Project Matador, refinance the Company’s then-existing Macquarie Term Loan (as defined below), and support the delivery, construction, and deployment of turbines across Fermi’s existing fleet.”
    Fermi Q3 2026 10-Q, MD&A — Liquidity (filed Nov 12 2026) · sec.gov
  • mufg-rate4%
    Term SOFR or Daily Simple SOFR plus 4.0% a year. The Q3 10-Q's debt table gives an effective interest rate of 12.3% at Sep 30 2026
    “Borrowings bear interest at Term SOFR or Daily Simple SOFR, in each case plus 4.0% per annum.”
    Fermi Q1 2026 10-Q, MD&A — Recent Developments (filed May 14 2026) · sec.gov
  • mufg-outstanding$444.9M
    $444.9M outstanding at Sep 30 2026, the same as at Jun 30; $396.6M at Mar 31 (Q1 10-Q)
    “As of September 30, 2026, $444.9 million was outstanding under the facility.”
    Fermi Q3 2026 10-Q, MD&A — Liquidity (filed Nov 12 2026) · sec.gov
  • mufg-ltv65%
    the loan is sized to the turbines' appraised value: a target of 65% for delivered equipment and 55% for undelivered. An event of default follows if the ratio stays above target for 30 days after an appraisal more than 2% below the first, unless the shortfall is paid
    “The target loan-to-value ratio for delivered equipment is 65%, and the target loan-to-value ratio for undelivered equipment is 55%.”
    Fermi Q3 2026 10-Q, MD&A — Liquidity (filed Nov 12 2026) · sec.gov
  • mufg-amendment$25M
    Limited Waiver and Amendment No. 1, Oct 9 2026: the minimum quarterly principal is set at 5% of loans outstanding (min-principal), and it 'eliminated the condition under which the minimum principal payments would have increased, and the administrative agent could have begun marketing the financed equipment, if we had not entered into a lease or offtake arrangement for at least 400 MW at Project Matador by November 10, 2026' (same section) — 'the covenant requiring the Company to enter into a lease or offtake arrangement for 400 MW', in the Oct 16 8-K. MUFG's loans went to a syndicate of new lenders, MUFG staying as administrative agent; $25.0M of amendment fees. The 8-K's estimate of what it saves: 'approximately $22 million in the fourth quarter of 2026, approximately $19 million in the first quarter of 2027 and approximately $15 million in the second quarter of 2027' of principal payments. It also allowed the turbines to be stored on site and elsewhere and waived, once, possible defaults over moving equipment from a Houston port facility and over insurance. Whether it is a modification or an extinguishment, Fermi is still evaluating
    “In connection with Amendment No. 1, MUFG assigned all of its loans and commitments under the Credit Agreement to a syndicate of new lenders and continues to serve as administrative agent, and the Borrower paid amendment fees totaling $25.0 million.”
    Fermi Q3 2026 10-Q, MD&A — Liquidity (filed Nov 12 2026) · sec.gov
  • min-principal5%
    5% of loans outstanding each quarter, from the nine-month anniversary of closing (Nov 10 2026), nothing being due before then; before the amendment it would have been 10% without a 400 MW lease or offtake for Matador's first phase
    “Thereafter, following the amendment described below under “—Amendment No. 1,” the minimum quarterly principal payment is 5% of the aggregate principal amount of loans outstanding. Prior to that amendment, the minimum principal payment would have been 10% of the aggregate principal amount of loans outstanding if no lease or offtake agreement with respect to the first phase of Project Matador for at least 400 MW of power had been signed prior to the nine-month anniversary of the Closing Date.”
    Fermi Q3 2026 10-Q, MD&A — Liquidity (filed Nov 12 2026) · sec.gov
  • financing-testat least 400 MW
    untouched by the amendment: an event of default unless Fermi closes, by Feb 10 2027, fully committed financing for Matador's first phase that, with any equity, funds at least 400 MW of generation. Not done when the Q3 10-Q was filed: 'we have not consummated such a financing as of the date of this Quarterly Report'
    “An event of default will also occur if we or one of our affiliates has not consummated, by February 10, 2027, a fully committed financing facility for the first phase of Project Matador sufficient, together with any equity, to fund at least 400 MW of power generation capacity.”
    Fermi Q3 2026 10-Q, MD&A — Liquidity (filed Nov 12 2026) · sec.gov
  • beal-facilityup to $165M
    a senior secured term loan of up to $165.0M, entered Mar 26 2026 by Fermi Turbine Warehouse II LLC 'to fund the acquisition of six Siemens SGT-800 industrial gas turbines and related equipment'; up to $22.9M of it reserved for interest and commitment fees; at most 45 borrowings. Fermi's release calls it a 'first lien delayed draw term loan'
    “The Beal Credit Agreement provides for a senior secured term loan facility in an aggregate principal amount of up to $165.0 million (the “Total Loan Commitment”).”
    Fermi Q3 2026 10-Q, MD&A — Liquidity (filed Nov 12 2026) · sec.gov
  • beal-lender
    who lends: the Q3 10-Q names 'Beal Bank USA, as lender', and the signed agreement's signature page has 'BEAL BANK USA, as Lender'. The Q1 and Q2 10-Qs named 'CSG Investments, an affiliate of Beal Bank USA', and Fermi's Mar 27 release a loan 'from CSG Investments, Inc., an affiliate of Beal Bank USA'; the agreement has fees paid to CSG Investments, Inc. under a fee letter. The lender's counsel, Davis Polk, says it 'advised Beal Bank USA as lender'. The Mar 27 8-K names only CLMG Corp. and 'the lenders party thereto'. CLMG Corp. is agent in every filing
    “entered into an Equipment Supply Loan Financing Agreement (the “Beal Credit Agreement”) with Beal Bank USA, as lender, and CLMG Corp., as administrative agent and collateral agent for the lenders”
    Fermi Q3 2026 10-Q, MD&A — Liquidity (filed Nov 12 2026) · sec.gov
  • beal-rate12%
    12.00% a year, fixed (14.00% on default), paid quarterly, plus 1% a year on the unused commitment. The Q3 10-Q's debt table gives an effective interest rate of 16.9% at Sep 30 2026, and Fermi's Nov 12 deck '12.0% per annum' for the facility. Not adopted: '12.9% per annum' beside 'Beal Bank $165 MM' on Fermi's August deck (Ex. 99.2), which gives Keystone's facility '12.0% per annum' — the reverse of the signed agreement and of Keystone's notes, which bear 12.90% (Q3 10-Q)
    ““Interest Rate” means twelve percent (12.00%) per annum.”
    Beal Credit Agreement, Ex. 10.1 to Fermi's Mar 27 2026 8-K · sec.gov
  • beal-exit-fee$37M
    an exit fee at maturity or earlier repayment of $37.0M less the interest and commitment fees paid by then, never below zero (the agreement) — in effect, the lenders receive at least $37.0M beyond principal, by our reading of the formula
    “On the maturity date (or upon earlier payment in full), FTW II is required to pay an exit fee equal to $37.0 million less the cumulative amount of interest and commitment fees paid to the lenders through such date.”
    Fermi Q3 2026 10-Q, MD&A — Liquidity (filed Nov 12 2026) · sec.gov
  • beal-maturity33 months
    33 months from the Mar 26 2026 closing
    “The loans mature on the date that is 33 months after the closing date of the Turbine Warehouse II Equipment Financing.”
    Fermi Q3 2026 10-Q, MD&A — Liquidity (filed Nov 12 2026) · sec.gov
  • beal-outstanding$32.3M
    $32.3M outstanding at Sep 30 2026; $14.7M at Jun 30 (Q2 10-Q) and $3.0M at Mar 31 (Q1 10-Q)
    “As of September 30, 2026, $32.3 million was outstanding under the facility.”
    Fermi Q3 2026 10-Q, MD&A — Liquidity (filed Nov 12 2026) · sec.gov
  • beal-guaranty
    secured on the turbines, and Fermi itself guarantees its subsidiary's obligations. The agreement restricts selling the equipment, 'subject to a permitted disposition of three turbines under certain conditions' (same section)
    “The obligations under the Turbine Warehouse II Equipment Financing are secured by a first-priority security interest in the financed equipment and related collateral, and the Company has provided a guaranty of FTW II’s obligations pursuant to a Sponsor Equity Contribution and Guaranty Agreement.”
    Fermi Q3 2026 10-Q, MD&A — Liquidity (filed Nov 12 2026) · sec.gov
  • sgt800-order6
    six more SGT-800s, ordered from Siemens Energy in October 2025 and assigned to Fermi Turbine Warehouse II. Fermi's Mar 27 release: 'six Siemens Energy SGT-800-57 (57MW) gas turbines with deliveries scheduled in pairs throughout 2028'; the Beal agreement defines each as 'an SGT-800 (57MW) power generation turbine'. No filing on file gives their price. Not the first six SGT-800s, which came with Firebird in July 2025 (note)
    “In October 2025, we entered into an equipment supply agreement with Siemens Energy for an additional six SGT-800 industrial gas turbines, with delivery expected in 2028.”
    Fermi FY2025 10-K (filed Mar 30 2026) · sec.gov
  • sgt800-progress$38.43M
    $38.43M of progress payments Fermi had already made by the Beal closing; from there the loan pays 'progress payments to Siemens' under the supply agreement (Q3 10-Q)
    “WHEREAS, as of the Closing Date, Sponsor has made Progress Payments (as defined herein) in the amount of $38,430,000.”
    Beal Credit Agreement, Ex. 10.1 to Fermi's Mar 27 2026 8-K — Recitals · sec.gov
  • siemens-commitments$126.2M
    what Fermi still owed Siemens on both orders at Sep 30 2026: about $126.2M, plus shipping. Note 8 schedules Fermi's long-lead equipment purchase obligations — $22.0M in the rest of 2026, $71.3M in 2027, $32.9M in 2028 — of which about $111.6M is expected to be drawn on its equipment facilities
    “As of September 30, 2026, we had purchase commitments of approximately $126.2 million under executed contracts with Siemens (the “Siemens Contracts”) for the supply of three SGT6-5000F gas turbine generator units and six SGT-800 gas turbine generator units for Project Matador.”
    Fermi Q3 2026 10-Q, MD&A — Commitments (filed Nov 12 2026) · sec.gov
  • first-lease
    the setting: both loans closed (Feb 10 and Mar 26 2026) before Fermi signed its first customer lease at Matador, TensorWave's of Aug 9 2026. It never took effect: 'on November 10, 2026, the TensorWave Lease was terminated in accordance with its terms' (Q3 10-Q; fermi-tensorwave). The Q3 10-Q says its ground lease's condition of a Phase 1 tenant lease of at least 200 MW 'has not been satisfied'
    “The TensorWave Lease represents the Company’s first customer lease at its Project Matador campus”
    Fermi Q2 2026 10-Q, Note 9 Subsequent Events (filed Aug 14 2026) · sec.gov

Contested figures 3 not reconciled — every position side by side, with its source and tier

closing-paymentone entry, in its own words
what the MUFG facility's first borrowing paid Siemens: 'Proceeds of borrowings on the Closing Date in respect of Siemens Energy F-Class Equipment will be used, in part, to make a payment to Siemens Energy in an amount equal to $168,300,000 pursuant to the applicable equipment purchase agreement' (Fermi's Feb 10 2026 8-K) vs 'Proceeds of borrowings on the Closing Date were used, in part, to make payments to Siemens in an amount equal to $201.6 million pursuant to the Siemens F-Class EPA' (Q3 10-Q; the FY2025 10-K and the Q1 and Q2 10-Qs say $201.6 million was paid, without 'on the Closing Date'). No filing explains the $33.3 million between them Feb 10 2026 8-K vs FY2025 10-K and Q1–Q3 2026 10-Qs
simple-cycle-capacityone entry, in its own words
what the three F-class units make in simple cycle, five ways in Fermi's own documents: 'rated at nominal capability of 220 MW each in simple cycle' (its East Campus air-permit application to Texas's environmental regulator, Mar 27 2026 — 660 MW for three) vs 'approximately 240 MW of simple cycle capacity at our site elevation, representing an additional 720 MW of contracted nameplate capacity' (FY2025 10-K) vs '726 MW' (its May and August investor decks) vs 'rated up to 728 MW in simple cycle mode, each more than 242 MW' (its Aug 2026 call; '728 MW' again in the Nov 12 deck) vs 'rated at up to 780 megawatts in simple-cycle mode', 'up to 260 megawatts' each (its Jul 21 2026 release) — 260 MW is the top of Siemens Energy's own rating for the model ('up to 260 MW', its product page). Only the permit papers and the 10-K state a basis (nominal; site elevation). No rating sheet or test for these units is on file East Campus permit application vs FY2025 10-K vs May/Aug/Nov decks vs Aug call vs Jul 21 release
combined-cycle-capacityone entry, in its own words
once steam equipment is added: 'up to 1.1 GW at ISO conditions once in combined cycle mode' (the Sep 25 2025 letter-of-intent release) vs '1,047 MW' (Fermi's May and August decks) vs '1,042 MW' (its Nov 12 deck, with no reason given for the change) vs '352 MW each in combined cycle', nominal (its East Campus air-permit application, Mar 27 2026 — 1,056 MW for three). Fermi intends to start the units in simple cycle and convert them to combined cycle later (Q3 10-Q); no test of these units is on file Sep 25 2025 release vs May/Aug/Nov decks vs East Campus permit application

Scope note what this record leaves to other records

Not this deal — carried elsewhere or not carried: the first six SGT-800s, their 6x1 combined-cycle package and the Siemens contract of 2022 behind them, which Fermi took over by buying Firebird in July 2025 (with the MAD Energy notes and net profits interest) — though the MUFG facility also funds turbines 'across Fermi's existing fleet' (mufg-use); the Keystone/Cape high-voltage facility, the Yorkville note and the 2031 convertible notes, and the '$785 million' of equipment financing Fermi totals from MUFG, Keystone and Beal; the Macquarie Term Loan beyond its repayment; Siemens Energy's turbine backlog and slot reservations (pw-siemens-energy-sra); the Siemens nuclear-collaboration letter of intent of Sep 25 2025; TSK's early-works engineering for the F-class units; the TensorWave lease (fermi-tensorwave) and the Nov 10 2026 hyperscaler letter of intent (fermi entity); Fermi's air permits, nuclear plan, Hillcore framework, IPO, land and power ramps. Not adopted: '12.9% per annum' for the Beal facility on Fermi's August deck (beal-rate).

More between Fermi America and Siemens Energy

The record holds no other deal between them.

Everything between Fermi America and Siemens Energy →