Why it matters
EverWind says Anthropic's lease for 95 anchors financing for a planned 420 MW campus, with no tenant named for the 325 MW expansion. The private landlord says the lease runs 20 years and has disclosed no rent. Its C$8B+ figure is the campus budget.
Tap a figure for the line in its source.
Anthropic gives EverWind
- rent under the lease — the amount is not disclosed; the C$8B+ in the announcement is what EverWind plans to spend building the whole campus, not the rent
EverWind gives Anthropic
- of data-centre capacity in the campus's first phase, which EverWind targets for late 2027; a further 325 is EverWind's own plan, with no tenant named
What happened
On October 16, 2026, EverWind announced plans for a data-centre campus at the marine terminal it owns at Point Tupper on Cape Breton Island. EverWind is a privately held Nova Scotia energy company. It said it had reached a long-term lease for the first phase with 'a leading frontier AI developer'. Anthropic identified itself as the tenant that day and called it its first data-centre lease in Canada. EverWind's finance chief later told a Nova Scotia legislative committee that the lease covers the first 95 megawatts. EverWind's later documents describe it as a 20-year lease with Anthropic. Neither company has published what Anthropic will pay. EverWind plans to spend more than C$8 billion to develop, build and finance the full 420-megawatt campus. It plans about C$2 billion for four wind farms. EverWind plans to use private financing. Its documents name no lender or investor for the campus. EverWind aims to deliver the first 95 megawatts in late 2027. Approvals were still outstanding in late October. EverWind plans a further 325-megawatt expansion with no tenant named. The company says the project will pay its own grid costs. No document shows whether Anthropic will pay any of those costs through its lease.
Sources 28 documents — 12 press reports · 6 company releases · 2 social posts · 2 SEC filings · 2 regulatory filings · 2 other documents · 1 transcript · 1 law-firm note
Research trail Found 85 documents and read 83 of them while checking this deal and related ones.
- States 5 figures: 325 MW expansion plan (for context) · 420 MW campus total · landlord campus budget (for context) · landlord total plan · water use
- States 2 figures: tenant · community benefit
- States 2 figures: 95 MW lease scope · phase 1 power service
- States 2 figures: financing anchor · phase 1 battery
- States s1 coverage
- States 95 MW phase 1 load
- States ownership
- States approvals status
- States lease value
- States construction status
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: EverWind press release (Oct 16 2026), campus website, and Nov 3–4 2026 open-house deck, boards and info sheet; Nova Scotia Hansard, Standing Committee on Natural Resources and Economic Development (Oct 27 2026); IESO Nova Scotia System Impact Studies SIS-005-R1 (Jul 16 2026) and SIS-011 rev. 3 (Oct 27 2026); Jacob Glick's LinkedIn post (Oct 16 2026); Anthropic S-1 and S-1/A (Oct 26 and Nov 2 2026), which do not name the lease; Reuters via The Star, CBC, The Globe and Mail, Canadian Press via 980 CJME and Global News, The Logic, Halifax Examiner, White & Case, Membertou's Oct 20 statement (read 2026-11) · as of Nov 2026
The evidence 15 sourced figures · 9 disputes · 2 for context
The record's headline EverWind–Anthropic, Point Tupper NS: a long-term lease on the 95 first phase of a planned 420 MW campus, 20 years on EverWind's own account, rent undisclosed — Anthropic's first data-centre lease in Canada, where the headline dollars (C$8B+ campus, C$2B wind) are the landlord's build budget, not the lease's value
- Size
- 95 MW first phase · long-term lease, 20 years on EverWind's account · rent undisclosed · landlord's plan: C$8B+ for a campus planned at 420 MW
- When
- Oct 16 2026 announced (EverWind's release names no tenant; Anthropic names itself that day) → late 2027 target for the first 95 MW → 2028 target for a further 325 MW (EverWind's plan, no tenant named); 20 years on EverWind's account
- Status
- signed, not built — Anthropic: 'has signed a lease' (Oct 16 2026); EverWind's CFO: 'signed a long-term lease agreement with Anthropic for the first 95 megawatts' (Oct 27). The lease is unpublished and no filing states its value. Land clearing was under way at the announcement (CBC); on EverWind's own status table (as of Oct 29) the Phase 1 power contract is signed, rate approval awaited, an industrial approval filed and building permits still to come; no lender or financial close is named for the campus
- Structure
- direct lease between the lab and a private developer, with no cloud or neocloud in between, for the first phase of a campus the landlord will develop, build and own on its own industrial land at Point Tupper; the rent, the term's mechanics, any renewals and any credit support are unpublished. The landlord plans to finance the campus privately, phase by phase, on project debt through investment banks, 'Anchored by' this lease. Power comes from the Nova Scotia grid under an interruptible tariff, with a 200 MWh Phase 1 battery and diesel backup generators on site; EverWind says its planned wind farms, expected in commercial operation in 2028 and 2029, will then supply most of the campus's electricity through the grid. EverWind says it will fund the grid-connection and upgrade costs attributable to the project; how those costs fall between landlord and tenant under the lease is not disclosed
- Programme
- Anthropic direct leases
- Parties
- Anthropic tenant — 'has signed a lease with EverWind for data centre capacity at Point Tupper', on its own account (Jacob Glick, LinkedIn, Oct 16 2026); its first data-centre lease in Canada. Its S-1/A names neither EverWind nor the site · EverWind landlord and developer, privately held — will 'develop, build and own' the campus on its own land at Point Tupper, financing it privately, anchored by this lease; no operator named
- Record
- disclosed / primary source · as of Nov 2026
Flows 2 as the record states them
- Anthropic → EverWindlease-paymentsrent under a long-term lease of the first 95 MW — not disclosed by either party (EverWind officials 'declined to disclose the value of the lease': Canadian Press, Oct 16 2026); 20 years on EverWind's account (contested lease-term). The C$8B+ campus budget is EverWind's build cost, not this rent
- EverWind → Anthropiccapacity95 MW of data-centre capacity in the first phase of the campus at Point Tupper, a grid-load figure (IESO SIS-005-R1; no document states critical IT); EverWind targets it online in late 2027 (contested phase-1-in-service), with 200 MWh of battery storage for Phase 1. A further 325 MW is EverWind's plan, with no tenant named
Resolved figures 15 each with the verbatim line from its document
- tenantAnthropic, in its own words. Jacob Glick (its head of public policy for Canada, per Reuters) posted that Anthropic 'has signed a lease with EverWind for data centre capacity at Point Tupper, Nova Scotia' and that it is 'our first data centre lease in Canada'; EverWind's CEO Trent Vichie named Anthropic in a statement quoted by The Globe and Mail. EverWind's Oct 16 release named no tenant: 'a leading frontier AI developer'. CBC reports Anthropic issued its own news release later that day, saying the site 'will power Claude models and serve growing demand from Canadian and global customers'; that release is not on file. Glick's post gives no megawatts, term or price. Anthropic's S-1/A, filed weeks later, names neither EverWind nor Point Tupper (s1-coverage)
“Anthropic has signed a lease with EverWind for data centre capacity at Point Tupper, Nova Scotia. It's our first data centre lease in Canada.”
Jacob Glick (Anthropic), LinkedIn post, Oct 16 2026 · linkedin.com - lease-scope95 MWthe first 95 megawatts only, on the landlord's own account to the legislature: Matthew Tinari, EverWind's CFO and chief strategy officer, told Nova Scotia's Standing Committee on Natural Resources and Economic Development on Oct 27 2026, 'We’ve signed a long-term lease agreement with Anthropic for the first 95 megawatts of the campus. Further expansion will proceed as commercial, technical, and regulatory requirements are met.' The Oct 16 release ties the lease to 'the initial phase'. Nothing in the documents commits Anthropic to the 325 MW expansion (expansion-plan); press copy saying a lease 'for the centre' (Canadian Press, Oct 30) and an aggregator's '95 MW by late 2027 and 325 MW more in 2028' are loose on scope. The lease itself is unpublished
“We’ve signed a long-term lease agreement with Anthropic for the first 95 megawatts of the campus.”
Nova Scotia Hansard, Standing Committee on Natural Resources and Economic Development, Oct 27 2026 — Matthew Tinari (EverWind) · nslegislature.ca - lease-valuenot disclosed by either party. 'EverWind officials declined to disclose the value of the lease with the company' (Canadian Press, Oct 16 2026), and the wire's Oct 23 story has it leased 'under undisclosed financial terms'. Neither EverWind's own materials nor Anthropic's S-1/A (s1-coverage) state a value. The C$8B+ and C$10B+ in the announcement are EverWind's build budget (landlord-campus-budget, landlord-total-plan), not the lease's value — XCyberNow ran the C$10 billion as the lease's value and corrected it on Oct 24 2026
“EverWind officials declined to disclose the value of the lease with the company, which says the site will power its Claude AI assistant and growing Canadian demand.”
Canadian Press via 980 CJME, Oct 16 2026 · cjme.com - s1-coveragenot stated: neither Anthropic's S-1/A (Nov 2 2026) nor its S-1 (Oct 26 2026) names EverWind, Nova Scotia or Point Tupper. Both say 'We have also entered into leases for data center capacity in Australia and Canada', and both list, in a subsequent-events note, a March 2026 lease 'for a data center to be constructed', 'expected to commence in 2027 and is for a term of 20 years from the date the data center is delivered to the Company' — the same term and start year as EverWind's first phase, but no document ties the two, and none gives the EverWind lease's signing date. So the filings can't be read as corroborating this lease or its term, or as placing it inside the S-1/A's $451.2B of leases not yet commenced at Sep 30 2026 or its $100.2B of commitments entered into after that date
“We have also entered into leases for data center capacity in Australia and Canada, and we are pursuing data center capacity in additional jurisdictions outside the United States.”
Anthropic S-1/A (Nov 2 2026), Facilities section and subsequent-events note · sec.gov - phase-1-load95 MW95 MW, as an electrical load at the grid connection — the only capacity figure any document gives for the leased phase; none says how much of it is critical IT (the figure TeraWulf's and Riot's filings give for Anthropic's other direct leases). IESO Nova Scotia studied it as request IRL03 ('IRL03 – Everwind Terminal'), a 95 MW load at the existing 138 kV Point Tupper Marine Terminal substation, and concluded the connection 'has no adverse impacts on the reliability of the Nova Scotia grid, provided the items below are addressed'. The figure originates in EverWind's own interconnection request, so it shows what EverWind asked to connect, not what has been built
“The requested Point of Interconnection (POI) for the 95 MW load facility is an existing 138 kV substation, 46C Point Tupper Marine Terminal.”
IESO Nova Scotia, System Impact Study SIS-005-R1 (IRL03 – Everwind Terminal), Jul 16 2026 · ieso-ns.ca - campus-total420 MW420 MW at full planned development (95 + 325), a plan ('would'), not a leased or approved total: only the first 95 MW has a tenant, and EverWind's own website answers 'Is the full 420 MW campus approved today?' with 'No.' IESO's study also speaks of 'the combined Everwind 420 MW load'. This record follows EverWind's and IESO's figure over The Coast's 425 MW, which it credits to 'Initial capacity estimates from EverWind' though its own parts, 95 and 320, sum to 415, and the Ecology Action Centre's 'around 450', which names no source
“At full development, the 420 MW campus would expand Canada’s domestic computing capacity to meet growing demand for artificial intelligence and digital services.”
EverWind press release, Oct 16 2026 · everwindfuels.com - landlord-total-planmore than C$10Bmore than C$10 billion across the campus (C$8B+) and EverWind's Nova Scotia wind portfolio (C$2 billion for four projects), which EverWind calls the largest privately funded investment in the province's history — the headline figure, a plan covering the whole campus and the wind portfolio, not what Anthropic pays. Bloomberg's conversion was US$7.1 billion
“EverWind today announced plans for more than $10 billion in private investment in a data centre campus at its existing Point Tupper industrial site and new wind power generation in Nova Scotia.”
EverWind press release, Oct 16 2026 · everwindfuels.com - ownershipEverWind — it 'will develop, build and own the physical data centre campus' on land it already owns in the Point Tupper Heavy Industrial Park, 'with specialist third-party operators supporting operations' (its CFO to the legislature: 'it will be operated by a specialist data centre operator'; no operator is named). Anthropic is the tenant. A Membertou-led consortium's talks over a minority stake in the campus are first-nations-stake; the consortium's 51% is in EverWind's wind portfolio, not the campus
“EverWind will develop, build and own the physical data centre campus, with specialist third-party operators supporting operations.”
EverWind campus website FAQ · everwinddc.com - financing-anchorhow EverWind says the campus will be paid for: 'Privately financed by EverWind, investors, banks and Indigenous partners' and 'Anchored by a 20-year lease with Anthropic, a leading AI company' (Nov 4 open-house deck), and, in CFO Matthew Tinari's e-mail to The Globe and Mail, 'We have engaged leading investment banks to issue the project debt and each phase will be financed separately.' Speaking of the wind power contracts after the Oct 27 hearing, Tinari said 'with our 20-year binding commitment at least some of those electrons have a clear home in Point Tupper and this is a meaningful de-risking event' (Halifax Examiner). The lease's role here is the landlord's description; the lease is unpublished, and no lender, investor or amount is named (financing-status)
“Anchored by a 20-year lease with Anthropic, a leading AI company”
EverWind open-house presentation, Nov 4 2026 · everwinddc.com - phase-1-battery200200 MWh of stored energy for Phase 1 (EverWind's boards: about 2 hours of Phase 1's power) — an energy figure; neither EverWind's documents nor IESO's give the battery's power rating in MW, and the '200 MW' in some press and commentary conflates the two. More batteries are planned for Phase 2
“200 MWh of battery storage for Phase 1”
EverWind open-house presentation, Nov 4 2026 · everwinddc.com - phase-1-power-serviceEverWind says electricity service agreements for the first 95 MW are signed, and its own status table lists the Nova Scotia Power contract as 'Signed Sept 28'; service is interruptible — the system operator or Nova Scotia Power can direct the campus to reduce its grid use on 10 minutes' notice. No terms are public, and the rate still needs the Nova Scotia Energy Board (approvals-status). At first the campus runs on the provincial grid: EverWind expects its wind farms online in 2028 and 2029, and as of Oct 27 2026 there were 'no executed power purchase agreements as part of the prescribed projects regulations for EverWind' (David Miller, Department of Energy, Hansard)
“We already signed electricity service agreements for the initial 95 megawatts, and independent system impact studies have now been completed for both phases of the planned 420-megawatt campus.”
Nova Scotia Hansard, Standing Committee on Natural Resources and Economic Development, Oct 27 2026 — Matthew Tinari (EverWind) · nslegislature.ca - approvals-statusEverWind's own table, as of Oct 29 2026: for Phase 1 the grid impact study is complete, the Facilities Study and power contract with Nova Scotia Power are 'Signed Sept 28', rates and cost recovery before the Nova Scotia Energy Board are 'Awaiting approval', the industrial approval was 'Filed Oct 9' and building and development permits are 'Next'; for Phase 2 the grid impact study is complete and the rest is 'In progress', 'Next' or 'In preparation'. The table warns: 'Filed is not approved: each approval can add conditions the project must meet.'
“Status as of October 29, 2026. Filed is not approved: each approval can add conditions the project must meet.”
EverWind open-house boards, Nov 3–4 2026 · everwinddc.com - community-benefit'tens of millions of dollars' for the first phase, no figure stated — Anthropic's Glick ('committing tens of millions of dollars to community priorities, which local leaders and residents will help decide') and EverWind's release ('a substantial community development program, valued in the tens of millions of dollars for the initial phase of the project'), neither saying who pays what share of it. EverWind says the funding is separate from ordinary taxes and statutory payments
“That includes committing tens of millions of dollars to community priorities, which local leaders and residents will help decide.”
Jacob Glick (Anthropic), LinkedIn post, Oct 16 2026; EverWind press release, Oct 16 2026 · linkedin.com - water-use500,000about 100,000 litres a day for the first phase and about 500,000 litres a day on average at the full 420 MW — EverWind's design estimates for a closed-loop, mostly air-cooled campus; averages, with no peak-day figure published and nothing metered (the campus is unbuilt). This record follows EverWind's design estimates over one source's 'per year'. How these compare with Landrie Lake's safe yield is contested (water-share)
“At the planned 420 MW full build-out, average water use is expected to be approximately 500,000 litres per day.”
EverWind press release, Oct 16 2026 · everwindfuels.com - construction-statuspre-construction at the announcement: CBC on Oct 16 2026 had land clearing under way and officials hoping 'to have foundations poured before winter', and EverWind's CEO said more than 20 Nova Scotian contractors were already working on the site (Canadian Press, Oct 23 2026). The approvals still outstanding are approvals-status
“Land clearing is underway and officials said they hope to have foundations poured before winter.”
CBC News, Oct 16 2026 · cbc.ca
Contested figures 11 not reconciled — every position side by side, with its source and tier
For context, not this deal's figures 2 kept beside the deal so they are not mistaken for its numbers
- expansion-plan325 MWa further 325 MW that EverWind plans, 'targeted for 2028, subject to applicable commercial, technical, and regulatory conditions' — EverWind's plan, with no tenant named; the lease is tied to the initial phase (lease-scope). IESO Nova Scotia studied it as request IRL01 (SIS-011, rev. 3 dated Oct 27 2026), a 325 MW load at a new 230 kV switching station, with the 95 MW modelled alongside it; EverWind's website says it 'will not be energized until those requirements are complete'. The same study's '325MW of backup generation' is a different figure for the same phase, not this load (backup-generation-phase-1)
“The campus is planned to begin with an initial 95-megawatt (MW) phase in late 2027, followed by a 325 MW expansion targeted for 2028, subject to applicable commercial, technical, and regulatory conditions.”
EverWind press release, Oct 16 2026 · everwindfuels.com - landlord-campus-budgetmore than C$8Bmore than C$8 billion 'to develop, construct, own, and finance the campus' at full 420 MW — EverWind's plan for the whole campus, not the lease's value and not money raised (financing-status); no split between the first 95 MW and the expansion is published. The release writes '$' with no currency; EverWind's counsel White & Case writes 'more than CAD 8 billion', and Reuters's total is 'C$10 billion'
“The planned investment includes more than $8 billion to develop, construct, own, and finance the campus, alongside $2 billion to advance EverWind’s Nova Scotia onshore wind portfolio.”
EverWind press release, Oct 16 2026 · everwindfuels.com
Scope note what this record leaves to other records
NOT this record (not carried here): EverWind's wind portfolio — Bear Lake, Windy Ridge, Kmtnuk and Upper Afton, their capacities on EverWind's, IESO's and the regulations' different bases, turbine counts, in-service dates, power purchase agreements and the Membertou-led consortium's 51% of them; Nuveen's US$175M (C$240M) March 2026 financing; the Point Tupper terminal's 2022 purchase from NuStar; Newfoundland and Labrador's Crown-land fee dispute with EverWind; EverWind's Davis Pier economic projections and its municipal-tax and jobs figures; the campus's diesel-use and emissions scenarios beyond Phase 1's 42–102 MW; Landrie Lake's withdrawal limits and utility demand; Anthropic's company-wide S-1 commitments, valuation and losses. Not public anywhere on file: the lease itself — rent, escalators, renewal or extension terms, any credit support, the signing date.