Why it matters
The largest compute contract in the group is visible mostly from the outside. The companies say the partnership exceeds $300 billion over five years, a figure absent from Oracle's filings. Oracle reports $288B in signed data-center leases yet to start, naming neither the sites nor OpenAI, and its lease bills start as each campus is handed over.
Tap a figure for the line in its source.
OpenAI gives Oracle
- over five years, the parties' own value for the partnership; no Oracle filing states it, and the press disagrees on what it pays for
Oracle gives OpenAI
- of new capacity, at sites in Texas, New Mexico, Wisconsin and Michigan, with customer delivery starting 1H27
- delivered at the Abilene, Texas flagship by Sep 2026: six of eight buildings, 75% of the campus
What happened
In July 2025, OpenAI agreed to rent up to 4.5 more gigawatts of computing capacity from Oracle. That is in addition to the flagship campus Oracle already runs for OpenAI in Abilene, Texas. The companies describe the partnership as worth more than $300 billion over five years. Oracle does not own the buildings. It leases them from developers who build each campus with borrowed money. The leases run for 15 years or more, and Oracle installs the chips. It uses Nvidia's GB200s at Abilene. By September 2026, six of Abilene's eight buildings had been handed over. Oracle says the four newer sites will start delivering capacity in 1H27 or 2H27. Those sites are in Texas, New Mexico, Wisconsin and Michigan. Oracle sent the New Mexico developer a force-majeure notice over possible power delays. Oracle says the notice by itself does not establish a delay. Oracle's annual and quarterly reports never name OpenAI. They report a $664 billion backlog of business and $288 billion of data-center leases that have yet to start, without identifying whose they are. Oracle named OpenAI only as one of its largest cloud customers in its February 2026 plan to raise money for new capacity. It gave no figure for any of those customers.
Sources 53 documents — 12 SEC filings · 12 press reports · 11 company releases · 6 other documents · 3 transcripts · 3 social posts · 3 government statements · 3 research notes
Research trail Found 384 documents and read 356 of them while checking this deal and related ones.
- States 3 figures: 10% customer concentration · $55.7B capex fy26 (for context) · $43B notes fy26
- States 2 figures: up to 4.5 GW capacity agreement · more than $300B contract value
- States 2 figures: 42% abilene delivered jun 2026 · 115 MW site schedule
- States 2 figures: $664B RPO · $288B lease commitments
- States 2 figures: 618 MW abilene delivered sep 2026 · $90–95B capex fy27 guidance
- States oracle filings
- States 1.2 GW abilene campus
- States 200 MW abilene operational apr 2026
- States 1.4 GW shackelford capacity
- States port washington
- States $16B saline value
- States 438% RPO Q2 fy26
- States funding 2026
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: OpenAI/Oracle/SoftBank joint release (Sep 23 2025); Oracle FY2026 10-K, Q1 FY2027 10-Q, Feb 2026 funding plan (FWP) and earnings materials, and EDGAR full-text searches of its filings; Oracle X post, CEO blog and data-centers page; Crusoe, Vantage, DigitalBridge and Related/Blackstone releases; Bloomberg, WSJ, AP, Reuters, Tom's Hardware, Epoch AI, Yes Energy and SemiAnalysis for the contested cells (read 2026-10) · as of Sep 2026
The evidence 18 sourced figures · 12 disputes · 1 for context
The record's headline OpenAI–Oracle: up to 4.5 of 'additional' capacity and a partnership the parties say exceeds $300B over five years — Abilene 618 delivered (Sep 2026), four more sites from 1H27; the $300B is in no Oracle filing, and Oracle's annual and quarterly reports never name OpenAI
- Size
- >$300B / 5 yr (the parties' figure) · up to 4.5 GW + Abilene's 1.2 GW · >$300B (the parties' figure)
- When
- Jul 2025 (4.5 GW agreed) → Sep 2025 (>$300B stated) → Abilene 75% delivered Sep 2026 → other sites 1H27–2H27
- Status
- Abilene 75% delivered (Sep 2026); Shackelford, Doña Ana, Port Washington and Saline contracted Aug–Oct 2025, customer delivery 1H27–2H27; Doña Ana under a force-majeure notice (Sep 2026)
- Structure
- cloud capacity agreement: developers build each campus with their own construction debt, Oracle leases it for 15–19 years, fits it with GPUs (Nvidia GB200s at Abilene, sg-orcl-nvda) and sells the compute to OpenAI on OCI; contract terms, payment schedule and the per-site split are undisclosed
- Term
- 5 yr
- Programme
- Stargate
- Parties
- OpenAI compute customer; 'subtenant' of the Oracle-leased campuses (WSJ) · Oracle cloud operator; tenant of each campus on 15–19-year leases; runs the GPUs (their buyer at Abilene by the FT's report, sg-orcl-nvda; neither company says who owns them)
- Site
- Stargate Abilene
- Record
- disclosed / primary source · as of Sep 2026
Flows 2 as the record states them
- OpenAI → Oraclecompute-spend>$300B over five years by the parties' own description of the partnership; what it pays for (compute or construction), its start and its schedule are contested; no Oracle filing states it
- Oracle → OpenAIcapacityAbilene's 1.2 GW campus (618 MW delivered by Sep 2026) + up to 4.5 GW of additional capacity at Shackelford, Doña Ana, Port Washington and Saline, customer delivery from 1H27
Resolved figures 18 each with the verbatim line from its document
- capacity-agreementup to 4.5 GWup to 4.5 GW of 'additional' capacity, agreed in July 2025 — first reported by Bloomberg on Jul 2 2025 ('about 4.5 gigawatts of data center power', people familiar), announced by OpenAI on Jul 22 2025 ('Stargate Advances with 4.5GW Partnership with Oracle', as Oracle's data-centers page lists it) and restated in the parties' Sep 23 2025 joint release. 'Additional' to Abilene in the July wording; whether later totals include Abilene is contested (abilene-in-total). The sites: Shackelford County TX, Doña Ana County NM, Port Washington WI (the release's unnamed 'Midwest site') and, contracted a month later, Saline Township MI
“In July, OpenAI and Oracle entered an agreement to develop up to 4.5 gigawatts of additional Stargate capacity.”
OpenAI/Oracle/SoftBank joint release, Sep 23 2025 (SoftBank Group copy) · group.softbank - contract-valuemore than $300Bmore than $300B over five years — the parties' only figure, a floor ('exceeds') on a 'partnership', with no breakdown, start date or payment schedule. The Wall Street Journal had reported it on Sep 10 2025 as a $300B purchase of computing power starting in 2027 (see contested contract-measure). No Oracle filing states it
“This represents a partnership that exceeds $300 billion between the two companies over the next five years.”
OpenAI/Oracle/SoftBank joint release, Sep 23 2025 (SoftBank Group copy) · group.softbank - oracle-filingswhat Oracle's own filings say about the deal: almost nothing. EDGAR full-text searches across all of Oracle's filings (run Oct 7 2026) find 'Stargate' once — this Mar 10 2025 earnings release, where Safra Catz lists OpenAI among companies Oracle had 'signed cloud agreements' with and says Oracle looks 'forward to signing our first Stargate contract' — and 'OpenAI' in three documents, none of them a 10-K or 10-Q: this release; the Sep 9 2025 release, which names ChatGPT as a model customers can use; and the Feb 1 2026 funding plan, which names OpenAI among Oracle's largest cloud customers (funding-2026). The FY2026 10-K and the Q1 FY2027 10-Q never name OpenAI or Stargate (in the text on file); the Jun 30 2025 8-K's 'more than $30 billion in annual revenue starting in FY28' contract names no customer. No Oracle filing contains '300 billion': the $300B appears only in the joint release and the press
“And we expect RPO to continue to grow rapidly—as we look forward to signing our first Stargate contract—yet another big opportunity for Oracle to expand both its AI training and AI inferencing businesses in the near future.”
Oracle Q3 FY2025 earnings release (8-K ex-99.1, Mar 10 2025) + EDGAR full-text search · sec.gov - abilene-campus1.2 GWAbilene, the flagship: eight buildings and 1.2 GW of total campus capacity (the developer's measure — power, not IT load), owned by the Crusoe–Blue Owl joint venture (sg-crusoe-jv) and leased whole by Oracle, which runs it on OCI for OpenAI — 'our flagship Stargate site', where OpenAI says GPT-5.5 was trained (Apr 2026). Completion slipped from mid-2026 to 'by the end of 2026' (see contested abilene-completion). The 1.2 GW is the finished campus, not what is running: the previous version of this record carried it as '~1.2GW live on OCI' at tier 1
“The second phase, which added six additional buildings to bring total campus capacity to 1.2 GW, is expected to reach completion by the end of 2026.”
Crusoe release, Mar 27 2026 · crusoe.ai - abilene-operational-apr-2026200 MW200 MW 'already operational' at Abilene on Apr 22 2026, by Oracle's own post, which adds that delivery of the eight-building campus 'remains on schedule' — the post Epoch used to revise its estimate of live capacity down (see contested abilene-live-capacity)
“In Abilene, 200MW is already operational, and delivery of the 8-building campus remains on schedule.”
Oracle on X, Apr 22 2026 (fxtwitter mirror of x.com/Oracle) · api.fxtwitter.com - abilene-delivered-jun-202642%42% of Abilene's total capacity delivered by Jun 10 2026, the remainder 'in the subsequent quarters' — Oracle's co-CEO Clay Magouyrk, summarising the Q4 FY26 call on his blog. Delivered to the customer, not necessarily running; the denominator is not stated
“Abilene, TX – Delivered 42% of total capacity today with the remainder delivering in the subsequent quarters.”
Oracle CEO blog, 'From the Q4 Earnings Call' (Jun 12 2026) · blogs.oracle.com - abilene-delivered-sep-2026618 MWsix of the eight buildings, 618 MW, '75% of total capacity', delivered to the customer by September 2026 (Oracle's co-CEO Clay Magouyrk, Q1 FY27 call, Sep 10 2026); Oracle's data-centers page: 'Delivered 75% of total capacity as of September 2026 with the remainder delivering in the subsequent quarters'. 618 / 0.75 ≈ 824 MW is the whole this implies — the monitor's arithmetic; Oracle never states the denominator or says whether the megawatts are IT load (see contested abilene-it-capacity). In June Oracle had guided 'an additional 35% of capacity' within 90 days on top of 42%, i.e. 77% (Q4 FY26 call): 75% delivered is close to, and just short of, that guidance
“Six of the eight campus buildings, representing 618 megawatts and 75% of total capacity, have now been delivered to the customer.”
Oracle Q1 FY2027 earnings call (StockAnalysis transcript, Sep 10 2026) · stockanalysis.com - site-schedule115 MWOracle's other four sites for OpenAI, in its CEO's summary of Jun 12 2026 (repeated on oracle.com/data-centers through Sep 2026): Shackelford County TX — contracted Aug 2025, customer delivery begins 1H27, 115 MW of power already available; Doña Ana County NM — contracted Sep 2025, delivery begins 1H27, power from Bloom fuel cells; Saline Township MI — contracted Oct 2025, delivery 2H27; Port Washington WI — contracted Sep 2025, delivery 2H27. Developers: Vantage (Shackelford, Port Washington), STACK/BorderPlex (Doña Ana), Related Digital (Saline)
“Shackelford, TX – Contracted in August 2025. Customer delivery begins in 1H27. 115MW of power capacity is already available, over 1 month ahead of schedule.”
Oracle CEO blog, 'From the Q4 Earnings Call' (Jun 12 2026) · blogs.oracle.com - shackelford-capacity1.4 GWShackelford County (Vantage's 'Frontier'): 1.4 GW of GPU compute capacity — the developer's own figure, an IT-side measure, for a $25B+ campus of ten buildings (same Aug 19 2025 release). Epoch's ~2.0 GW is modelled facility power, and the 2.58 GW of reciprocating engines Vantage ordered for the site (Cleanview's newsletter, read for this record, not cited here) is generation, not load. Acreage stays unreconciled: 1,200 acres (Vantage) vs 700 (Oracle's fact sheet)
“In particular, the launch of our Frontier campus with 1.4GW of GPU compute capacity marks a watershed moment for Vantage as we deliver on our promise to meet the unprecedented requirements of our customers”
Vantage Data Centers release, Aug 19 2025 · vantage-dc.com - port-washington4Port Washington, Wisconsin (Vantage's 'Lighthouse'), announced Oct 2025 as the joint release's 'Midwest site' and 'part of OpenAI and Oracle's previously announced partnership to invest up to 4.5 gigawatts': four buildings, 'close to a gigawatt of AI capacity', $15B+, completion scheduled for 2028. The same release is the only party text that puts the program in IT terms: 'This campus, combined with other Stargate campuses in collaboration with Oracle, can deliver over 4.5 gigawatts of IT capacity' (see contested abilene-in-total)
“The campus will feature four cutting-edge data centers providing close to a gigawatt of AI capacity.”
OpenAI/Oracle/Vantage release, Oct 22 2025 (DigitalBridge IR copy) · ir.digitalbridge.com - saline-value$16BSaline Township, Michigan: a $16B campus 'purpose-built for Oracle', financing secured Apr 2026 — equity from Related Digital and Blackstone funds, fixed-rate long-term debt anchored by PIMCO; Related's chairman thanks 'our partners at Oracle and OpenAI'. The developer's figure, which this record follows over DCD's unattributed $10B (Dec 2025). The developers' joint venture borrows through its own special-purpose issuer; Oracle leases. The financing in full → related-blackstone-oracle-saline
“DALLAS – Related Digital, a vertically integrated data center development and investment platform, and Blackstone (NYSE: BX) announced today that financing has been secured for Related Digital's $16 billion data center campus in Saline Township, Michigan, purpose-built for Oracle.”
Related Digital/Blackstone release, Apr 24 2026 (Wayback) · web.archive.org - rpo$664BOracle's remaining performance obligations: $664B at Aug 31 2026 (Q1 FY27 10-Q), from $638B at May 31 2026 and $138B a year before that (FY2026 10-K: the increase 'primarily attributable to certain significant cloud contracts'). About 13% is expected to become revenue in the next twelve months. All customers together: no filing gives OpenAI's share (see contested rpo-share)
“Remaining performance obligations were $664 billion as of August 31, 2026, of which we expect to recognize approximately 13% as revenues over the next twelve months, 37% over the subsequent month 13 to month 36, 34% over the subsequent month 37 to month 60 and the remainder thereafter.”
Oracle Q1 FY2027 10-Q (quarter ended Aug 31 2026) · sec.gov - rpo-q2-fy26438%the jump after the deal: RPO up 438% year on year in dollars, to $523B at Nov 30 2025 — the Q2 FY2026 10-Q's $523.3B against $97.3B a year earlier gives the same +438%. This record follows the reported figure over the 433% in a third-party transcript of the call, which this record reads as the constant-currency rate the finance chief used, not a conflicting figure
“Total Remaining Performance Obligations were up 438% year-over-year in USD to $523 billion.”
Oracle Q2 FY2026 earnings release (8-K ex-99.1, furnished) · sec.gov - customer-concentration10%Oracle's only quantified concentration test is on revenue, not backlog: no customer was 10% of revenue in fiscal 2024–2026. It does not bound OpenAI's share of the RPO (see contested rpo-share); the same note says only that the returns on its large cloud build-outs depend on 'the ability of our key customers to meet their contractual obligations'
“No single customer accounted for 10% or more of our total revenues in fiscal 2026, 2025 or 2024.”
Oracle FY2026 10-K · sec.gov - lease-commitments$288Bhow Oracle carries the buildings: $288B of leases signed but not yet started at Aug 31 2026 ($260B at May 31 2026), substantially all data centers, 15–19-year terms, off the balance sheet until each begins. The May 31 figure includes 'a lease for which we have guaranteed up to $3.3 billion of the lessor's borrowing, which matures in September 2026' (10-K) — the only exposure to a developer's debt Oracle has filed; the Aug 31 10-Q mentions no guarantee. Neither report names a site or OpenAI; the developers, not Oracle, borrow the construction money (note)
“As of August 31, 2026, we had $288 billion of additional lease commitments, substantially all related to data center arrangements, that are generally expected to commence between the second quarter of fiscal 2027 and fiscal 2029 and for terms of fifteen to nineteen years that were not reflected on our condensed consolidated balance sheets as of August 31, 2026 or in the maturities table above.”
Oracle Q1 FY2027 10-Q (quarter ended Aug 31 2026) · sec.gov - capex-fy27-guidance$90–95Bfiscal 2027 guidance: $90–95B of capex with 'not more than $70 billion in net cash CapEx' (Q1 FY27 call, Sep 2026) — the difference is customer prepayments and timing, 'expected at around $20 billion-$25 billion, so our reported CapEx will be higher by this amount' (Q4 FY26 call, Jun 2026). Customers pre-paying for, or bringing, their own GPUs is how Oracle funds part of the build
“We continue to anticipate $90 billion-$95 billion in CapEx for the full year, with not more than $70 billion in net cash CapEx.”
Oracle Q1 FY2027 earnings call (StockAnalysis transcript, Sep 10 2026) · stockanalysis.com - notes-fy26$43B$43.0B of senior notes issued in fiscal 2026, 'for general corporate purposes' — with a $5.0B mandatory convertible preferred (FY2026) and a $20B at-the-market share programme, completed in Q1 FY27. None of it is tied to Stargate in any filing. The convertible, the share programme and an early-2026 bond sale were announced together in Oracle's Feb 1 2026 funding plan, which says the money is to build capacity for the 'contracted demand' of its largest cloud customers, OpenAI among them (funding-2026; see contested stargate-debt)
“During fiscal 2026, we issued a total of $43.0 billion par value of senior notes comprising the following:”
Oracle FY2026 10-K (liquidity) · sec.gov - funding-2026Oracle's plan for calendar 2026, announced Feb 1 2026 and filed with the SEC as a free writing prospectus: $45–50B of gross cash proceeds, about half from equity (a mandatory convertible preferred and an at-the-market programme of up to $20B) and half from a single early-2026 bond sale, raised 'to build additional capacity to meet the contracted demand from our largest Oracle Cloud Infrastructure customers' — six named, OpenAI among them, 'and others'. It gives no amount or share for any customer and does not mention Stargate. Of the three Oracle filings that name OpenAI (oracle-filings), it is the only one that ties Oracle's financing to it
“Oracle is raising money in order to build additional capacity to meet the contracted demand from our largest Oracle Cloud Infrastructure customers, including AMD, Meta, NVIDIA, OpenAI, TikTok, xAI and others.”
Oracle free writing prospectus (Rule 163), Feb 1 2026 · sec.gov
Contested figures 28 not reconciled — every position side by side, with its source and tier
For context, not this deal's figures 1 kept beside the deal so they are not mistaken for its numbers
- capex-fy26$55.7BOracle's own capital spending in fiscal 2026 (to May 31 2026): $55.7B — $48B net of about $8B of customer prepayments and timing, by the Q4 call. Company-wide: no filing assigns any of it to OpenAI or a site
“partially offset by $55.7 billion of cash used for capital expenditures”
Oracle FY2026 10-K (liquidity) · sec.gov
Scope note what this record leaves to other records
The developers' debt, which no Oracle filing shows (WSJ via Hindustan Times, Apr 24 2026, unless noted): about $10B of construction loans for Crusoe's Abilene campus (sg-crusoe-jv: $9.4B per Blue Owl's counsel, $9.6B per JPMorgan); $38B borrowed by Vantage for Shackelford and Port Washington; about $18B raised for STACK's Doña Ana campus (with ~$3B of Blue Owl equity, Reuters); Saline's $16B campus financed with Related and Blackstone equity and PIMCO-anchored debt. Oracle's filed exposure is the lease bill ($288B not yet commenced) and, at May 31 2026, a guarantee of up to $3.3B of one lessor's borrowing due in September 2026 (10-K; the Aug 31 10-Q mentions no guarantee). Not this record — carried elsewhere or not carried: the Doña Ana campus's $360M of payments in lieu of taxes (a county–developer term, not the OpenAI–Oracle deal); the 900 MW Crusoe campus for Microsoft next to Abilene (a separate deal, crusoe-msft-abilene); Abilene's GPUs on sg-orcl-nvda and its ownership and loans on sg-crusoe-jv; Oracle's ~$40B FY2027 debt-and-equity plan and its BBB rating path (entity-level). Corrected from the previous version: '~1.2GW live on OCI' (tier 1) was the finished campus's power, not what was running — see abilene-campus and abilene-live-capacity; the two Dec-2025 'completion' cells are kept as site-delays, now cited to the Bloomberg and Reuters pages. Not adopted: Bloomberg Law's 'OpenAI signed a $400 billion deal with Oracle and SoftBank' (the $400B is the umbrella's planned investment); 'Oracle recently inked an $18 billion debt deal' and 'a $38 billion deal' (the Public Enterprise report 'Bubble or Nothing', Nov 2025 — the borrowers are the developers); a Motley Fool transcript of the Q1 FY27 call giving 'more than 3 thousand GPUs' where Oracle's release and the StockAnalysis transcript say 300,000 — why the call is cited from StockAnalysis.