OpenAI–Oracle

Oracle agreed to develop up to 4.5 more data-center capacity for OpenAI. The companies say their partnership exceeds $300B over five years.

A deal between OpenAI, Oracle

Why it matters

The largest compute contract in the group is visible mostly from the outside. The companies say the partnership exceeds $300 billion over five years, a figure absent from Oracle's filings. Oracle reports $288B in signed data-center leases yet to start, naming neither the sites nor OpenAI, and its lease bills start as each campus is handed over.

Tap a figure for the line in its source.

OpenAI gives Oracle

  • over five years, the parties' own value for the partnership; no Oracle filing states it, and the press disagrees on what it pays for

Oracle gives OpenAI

  • of new capacity, at sites in Texas, New Mexico, Wisconsin and Michigan, with customer delivery starting 1H27
  • delivered at the Abilene, Texas flagship by Sep 2026: six of eight buildings, 75% of the campus

Jul 2, 2025 reported by Bloomberg; OpenAI announced it Jul 22updated Nov 21, 2026Abilene 75% delivered disclosed by the parties

What happened

In July 2025, OpenAI agreed to rent up to 4.5 more gigawatts of computing capacity from Oracle. That is in addition to the flagship campus Oracle already runs for OpenAI in Abilene, Texas. The companies describe the partnership as worth more than $300 billion over five years. Oracle does not own the buildings. It leases them from developers who build each campus with borrowed money. The leases run for 15 years or more, and Oracle installs the chips. It uses Nvidia's GB200s at Abilene. By September 2026, six of Abilene's eight buildings had been handed over. Oracle says the four newer sites will start delivering capacity in 1H27 or 2H27. Those sites are in Texas, New Mexico, Wisconsin and Michigan. Oracle sent the New Mexico developer a force-majeure notice over possible power delays. Oracle says the notice by itself does not establish a delay. Oracle's annual and quarterly reports never name OpenAI. They report a $664 billion backlog of business and $288 billion of data-center leases that have yet to start, without identifying whose they are. Oracle named OpenAI only as one of its largest cloud customers in its February 2026 plan to raise money for new capacity. It gave no figure for any of those customers.

Sources 53 documents — 12 SEC filings · 12 press reports · 11 company releases · 6 other documents · 3 transcripts · 3 social posts · 3 government statements · 3 research notes

Research trail Found 384 documents and read 356 of them while checking this deal and related ones.

  1. SEC · SEC filingsec.gov
    States 3 figures: 10% customer concentration · $55.7B capex fy26 (for context) · $43B notes fy26
  2. SoftBank · company releaseSep 24, 2025group.softbank
    States 2 figures: up to 4.5 GW capacity agreement · more than $300B contract value
  3. company releaseblogs.oracle.com
    States 2 figures: 42% abilene delivered jun 2026 · 115 MW site schedule
  4. SEC · SEC filingsec.gov
    States 2 figures: $664B RPO · $288B lease commitments
  5. Stock Analysis · transcriptstockanalysis.com
    States 2 figures: 618 MW abilene delivered sep 2026 · $90–95B capex fy27 guidance
  6. SEC · SEC filingsec.gov
    States oracle filings
  7. company releasecrusoe.ai
    States 1.2 GW abilene campus
  8. X · social postapi.fxtwitter.com
    States 200 MW abilene operational apr 2026
  9. company releasevantage-dc.com
    States 1.4 GW shackelford capacity
  10. DigitalBridge · company releaseir.digitalbridge.com
    States port washington
  11. Blackstone · company release (archived copy)blackstone.com
    States $16B saline value
  12. SEC · SEC filingsec.gov
    States 438% RPO Q2 fy26
  13. SEC · SEC filingsec.gov
    States funding 2026
  14. press reportnews.bloomberglaw.com
    Cited by the record; no single figure is quoted from it.
  15. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  16. SEC filingefts.sec.gov
    Cited by the record; no single figure is quoted from it.
  17. SEC filingefts.sec.gov
    Cited by the record; no single figure is quoted from it.
  18. SEC filingefts.sec.gov
    Cited by the record; no single figure is quoted from it.
  19. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  20. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  21. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  22. company releasecrusoe.ai
    Cited by the record; no single figure is quoted from it.
  23. company releaseoracle.com
    Cited by the record; no single figure is quoted from it.
  24. transcriptstockanalysis.com
    Cited by the record; no single figure is quoted from it.
  25. transcriptSep 11, 2026fool.com
    Cited by the record; no single figure is quoted from it.
  26. company releaseopenai.com
    Cited by the record; no single figure is quoted from it.
  27. government statementarrington.house.gov
    Cited by the record; no single figure is quoted from it.
  28. company releaseoracle.com
    Cited by the record; no single figure is quoted from it.
  29. company releaseoracle.com
    Cited by the record; no single figure is quoted from it.
  30. government statementJul 2026env.nm.gov
    Cited by the record; no single figure is quoted from it.
  31. government statementJul 2026env.nm.gov
    Cited by the record; no single figure is quoted from it.
  32. press reportdatacenterdynamics.com
    Cited by the record; no single figure is quoted from it.
  33. social postpublish.x.com
    Cited by the record; no single figure is quoted from it.
  34. press reporttelecom.economictimes.indiatimes.com
    Cited by the record; no single figure is quoted from it.
  35. press report (archived copy)datacenterdynamics.com
    Cited by the record; no single figure is quoted from it.
  36. press reportMar 8, 2026gulf-times.com
    Cited by the record; no single figure is quoted from it.
  37. press reporttomshardware.com
    Cited by the record; no single figure is quoted from it.
  38. other documentMar 27, 2026news4jax.com
    Cited by the record; no single figure is quoted from it.
  39. other documenthindustantimes.com
    Cited by the record; no single figure is quoted from it.
  40. research noteepoch.ai
    Cited by the record; no single figure is quoted from it.
  41. research noteepoch.ai
    Cited by the record; no single figure is quoted from it.
  42. social postlinkedin.com
    Cited by the record; no single figure is quoted from it.
  43. other documentyesenergy.com
    Cited by the record; no single figure is quoted from it.
  44. other documentdpr.com
    Cited by the record; no single figure is quoted from it.
  45. press reportnews.bloomberglaw.com
    Cited by the record; no single figure is quoted from it.
  46. press reportchannelnewsasia.com
    Cited by the record; no single figure is quoted from it.
  47. press reportnews.bloomberglaw.com
    Cited by the record; no single figure is quoted from it.
  48. press reportksl.com
    Cited by the record; no single figure is quoted from it.
  49. press reportSep 19, 2026thestar.com.my
    Cited by the record; no single figure is quoted from it.
  50. research notenewsletter.semianalysis.com
    Cited by the record; no single figure is quoted from it.
  51. other documentppc.land
    Cited by the record; no single figure is quoted from it.
  52. other documentbloorresearch.com
    Cited by the record; no single figure is quoted from it.
  53. press reportwheresyoured.at
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: OpenAI/Oracle/SoftBank joint release (Sep 23 2025); Oracle FY2026 10-K, Q1 FY2027 10-Q, Feb 2026 funding plan (FWP) and earnings materials, and EDGAR full-text searches of its filings; Oracle X post, CEO blog and data-centers page; Crusoe, Vantage, DigitalBridge and Related/Blackstone releases; Bloomberg, WSJ, AP, Reuters, Tom's Hardware, Epoch AI, Yes Energy and SemiAnalysis for the contested cells (read 2026-10) · as of Sep 2026

The evidence 18 sourced figures · 12 disputes · 1 for context

The record's headline OpenAI–Oracle: up to 4.5 of 'additional' capacity and a partnership the parties say exceeds $300B over five years — Abilene 618 delivered (Sep 2026), four more sites from 1H27; the $300B is in no Oracle filing, and Oracle's annual and quarterly reports never name OpenAI

Size
>$300B / 5 yr (the parties' figure) · up to 4.5 GW + Abilene's 1.2 GW · >$300B (the parties' figure)
When
Jul 2025 (4.5 GW agreed) → Sep 2025 (>$300B stated) → Abilene 75% delivered Sep 2026 → other sites 1H27–2H27
Status
Abilene 75% delivered (Sep 2026); Shackelford, Doña Ana, Port Washington and Saline contracted Aug–Oct 2025, customer delivery 1H27–2H27; Doña Ana under a force-majeure notice (Sep 2026)
Structure
cloud capacity agreement: developers build each campus with their own construction debt, Oracle leases it for 15–19 years, fits it with GPUs (Nvidia GB200s at Abilene, sg-orcl-nvda) and sells the compute to OpenAI on OCI; contract terms, payment schedule and the per-site split are undisclosed
Term
5 yr
Programme
Stargate
Parties
OpenAI compute customer; 'subtenant' of the Oracle-leased campuses (WSJ) · Oracle cloud operator; tenant of each campus on 15–19-year leases; runs the GPUs (their buyer at Abilene by the FT's report, sg-orcl-nvda; neither company says who owns them)
Site
Stargate Abilene
Record
disclosed / primary source · as of Sep 2026

Flows 2 as the record states them

  • OpenAI → Oraclecompute-spend>$300B over five years by the parties' own description of the partnership; what it pays for (compute or construction), its start and its schedule are contested; no Oracle filing states it
  • Oracle → OpenAIcapacityAbilene's 1.2 GW campus (618 MW delivered by Sep 2026) + up to 4.5 GW of additional capacity at Shackelford, Doña Ana, Port Washington and Saline, customer delivery from 1H27

Resolved figures 18 each with the verbatim line from its document

  • capacity-agreementup to 4.5 GW
    up to 4.5 GW of 'additional' capacity, agreed in July 2025 — first reported by Bloomberg on Jul 2 2025 ('about 4.5 gigawatts of data center power', people familiar), announced by OpenAI on Jul 22 2025 ('Stargate Advances with 4.5GW Partnership with Oracle', as Oracle's data-centers page lists it) and restated in the parties' Sep 23 2025 joint release. 'Additional' to Abilene in the July wording; whether later totals include Abilene is contested (abilene-in-total). The sites: Shackelford County TX, Doña Ana County NM, Port Washington WI (the release's unnamed 'Midwest site') and, contracted a month later, Saline Township MI
    “In July, OpenAI and Oracle entered an agreement to develop up to 4.5 gigawatts of additional Stargate capacity.”
    OpenAI/Oracle/SoftBank joint release, Sep 23 2025 (SoftBank Group copy) · group.softbank
  • contract-valuemore than $300B
    more than $300B over five years — the parties' only figure, a floor ('exceeds') on a 'partnership', with no breakdown, start date or payment schedule. The Wall Street Journal had reported it on Sep 10 2025 as a $300B purchase of computing power starting in 2027 (see contested contract-measure). No Oracle filing states it
    “This represents a partnership that exceeds $300 billion between the two companies over the next five years.”
    OpenAI/Oracle/SoftBank joint release, Sep 23 2025 (SoftBank Group copy) · group.softbank
  • oracle-filings
    what Oracle's own filings say about the deal: almost nothing. EDGAR full-text searches across all of Oracle's filings (run Oct 7 2026) find 'Stargate' once — this Mar 10 2025 earnings release, where Safra Catz lists OpenAI among companies Oracle had 'signed cloud agreements' with and says Oracle looks 'forward to signing our first Stargate contract' — and 'OpenAI' in three documents, none of them a 10-K or 10-Q: this release; the Sep 9 2025 release, which names ChatGPT as a model customers can use; and the Feb 1 2026 funding plan, which names OpenAI among Oracle's largest cloud customers (funding-2026). The FY2026 10-K and the Q1 FY2027 10-Q never name OpenAI or Stargate (in the text on file); the Jun 30 2025 8-K's 'more than $30 billion in annual revenue starting in FY28' contract names no customer. No Oracle filing contains '300 billion': the $300B appears only in the joint release and the press
    “And we expect RPO to continue to grow rapidly—as we look forward to signing our first Stargate contract—yet another big opportunity for Oracle to expand both its AI training and AI inferencing businesses in the near future.”
    Oracle Q3 FY2025 earnings release (8-K ex-99.1, Mar 10 2025) + EDGAR full-text search · sec.gov
  • abilene-campus1.2 GW
    Abilene, the flagship: eight buildings and 1.2 GW of total campus capacity (the developer's measure — power, not IT load), owned by the Crusoe–Blue Owl joint venture (sg-crusoe-jv) and leased whole by Oracle, which runs it on OCI for OpenAI — 'our flagship Stargate site', where OpenAI says GPT-5.5 was trained (Apr 2026). Completion slipped from mid-2026 to 'by the end of 2026' (see contested abilene-completion). The 1.2 GW is the finished campus, not what is running: the previous version of this record carried it as '~1.2GW live on OCI' at tier 1
    “The second phase, which added six additional buildings to bring total campus capacity to 1.2 GW, is expected to reach completion by the end of 2026.”
    Crusoe release, Mar 27 2026 · crusoe.ai
  • abilene-operational-apr-2026200 MW
    200 MW 'already operational' at Abilene on Apr 22 2026, by Oracle's own post, which adds that delivery of the eight-building campus 'remains on schedule' — the post Epoch used to revise its estimate of live capacity down (see contested abilene-live-capacity)
    “In Abilene, 200MW is already operational, and delivery of the 8-building campus remains on schedule.”
    Oracle on X, Apr 22 2026 (fxtwitter mirror of x.com/Oracle) · api.fxtwitter.com
  • abilene-delivered-jun-202642%
    42% of Abilene's total capacity delivered by Jun 10 2026, the remainder 'in the subsequent quarters' — Oracle's co-CEO Clay Magouyrk, summarising the Q4 FY26 call on his blog. Delivered to the customer, not necessarily running; the denominator is not stated
    “Abilene, TX – Delivered 42% of total capacity today with the remainder delivering in the subsequent quarters.”
    Oracle CEO blog, 'From the Q4 Earnings Call' (Jun 12 2026) · blogs.oracle.com
  • abilene-delivered-sep-2026618 MW
    six of the eight buildings, 618 MW, '75% of total capacity', delivered to the customer by September 2026 (Oracle's co-CEO Clay Magouyrk, Q1 FY27 call, Sep 10 2026); Oracle's data-centers page: 'Delivered 75% of total capacity as of September 2026 with the remainder delivering in the subsequent quarters'. 618 / 0.75 ≈ 824 MW is the whole this implies — the monitor's arithmetic; Oracle never states the denominator or says whether the megawatts are IT load (see contested abilene-it-capacity). In June Oracle had guided 'an additional 35% of capacity' within 90 days on top of 42%, i.e. 77% (Q4 FY26 call): 75% delivered is close to, and just short of, that guidance
    “Six of the eight campus buildings, representing 618 megawatts and 75% of total capacity, have now been delivered to the customer.”
    Oracle Q1 FY2027 earnings call (StockAnalysis transcript, Sep 10 2026) · stockanalysis.com
  • site-schedule115 MW
    Oracle's other four sites for OpenAI, in its CEO's summary of Jun 12 2026 (repeated on oracle.com/data-centers through Sep 2026): Shackelford County TX — contracted Aug 2025, customer delivery begins 1H27, 115 MW of power already available; Doña Ana County NM — contracted Sep 2025, delivery begins 1H27, power from Bloom fuel cells; Saline Township MI — contracted Oct 2025, delivery 2H27; Port Washington WI — contracted Sep 2025, delivery 2H27. Developers: Vantage (Shackelford, Port Washington), STACK/BorderPlex (Doña Ana), Related Digital (Saline)
    “Shackelford, TX – Contracted in August 2025. Customer delivery begins in 1H27. 115MW of power capacity is already available, over 1 month ahead of schedule.”
    Oracle CEO blog, 'From the Q4 Earnings Call' (Jun 12 2026) · blogs.oracle.com
  • shackelford-capacity1.4 GW
    Shackelford County (Vantage's 'Frontier'): 1.4 GW of GPU compute capacity — the developer's own figure, an IT-side measure, for a $25B+ campus of ten buildings (same Aug 19 2025 release). Epoch's ~2.0 GW is modelled facility power, and the 2.58 GW of reciprocating engines Vantage ordered for the site (Cleanview's newsletter, read for this record, not cited here) is generation, not load. Acreage stays unreconciled: 1,200 acres (Vantage) vs 700 (Oracle's fact sheet)
    “In particular, the launch of our Frontier campus with 1.4GW of GPU compute capacity marks a watershed moment for Vantage as we deliver on our promise to meet the unprecedented requirements of our customers”
    Vantage Data Centers release, Aug 19 2025 · vantage-dc.com
  • port-washington4
    Port Washington, Wisconsin (Vantage's 'Lighthouse'), announced Oct 2025 as the joint release's 'Midwest site' and 'part of OpenAI and Oracle's previously announced partnership to invest up to 4.5 gigawatts': four buildings, 'close to a gigawatt of AI capacity', $15B+, completion scheduled for 2028. The same release is the only party text that puts the program in IT terms: 'This campus, combined with other Stargate campuses in collaboration with Oracle, can deliver over 4.5 gigawatts of IT capacity' (see contested abilene-in-total)
    “The campus will feature four cutting-edge data centers providing close to a gigawatt of AI capacity.”
    OpenAI/Oracle/Vantage release, Oct 22 2025 (DigitalBridge IR copy) · ir.digitalbridge.com
  • saline-value$16B
    Saline Township, Michigan: a $16B campus 'purpose-built for Oracle', financing secured Apr 2026 — equity from Related Digital and Blackstone funds, fixed-rate long-term debt anchored by PIMCO; Related's chairman thanks 'our partners at Oracle and OpenAI'. The developer's figure, which this record follows over DCD's unattributed $10B (Dec 2025). The developers' joint venture borrows through its own special-purpose issuer; Oracle leases. The financing in full → related-blackstone-oracle-saline
    “DALLAS – Related Digital, a vertically integrated data center development and investment platform, and Blackstone (NYSE: BX) announced today that financing has been secured for Related Digital's $16 billion data center campus in Saline Township, Michigan, purpose-built for Oracle.”
    Related Digital/Blackstone release, Apr 24 2026 (Wayback) · web.archive.org
  • rpo$664B
    Oracle's remaining performance obligations: $664B at Aug 31 2026 (Q1 FY27 10-Q), from $638B at May 31 2026 and $138B a year before that (FY2026 10-K: the increase 'primarily attributable to certain significant cloud contracts'). About 13% is expected to become revenue in the next twelve months. All customers together: no filing gives OpenAI's share (see contested rpo-share)
    “Remaining performance obligations were $664 billion as of August 31, 2026, of which we expect to recognize approximately 13% as revenues over the next twelve months, 37% over the subsequent month 13 to month 36, 34% over the subsequent month 37 to month 60 and the remainder thereafter.”
    Oracle Q1 FY2027 10-Q (quarter ended Aug 31 2026) · sec.gov
  • rpo-q2-fy26438%
    the jump after the deal: RPO up 438% year on year in dollars, to $523B at Nov 30 2025 — the Q2 FY2026 10-Q's $523.3B against $97.3B a year earlier gives the same +438%. This record follows the reported figure over the 433% in a third-party transcript of the call, which this record reads as the constant-currency rate the finance chief used, not a conflicting figure
    “Total Remaining Performance Obligations were up 438% year-over-year in USD to $523 billion.”
    Oracle Q2 FY2026 earnings release (8-K ex-99.1, furnished) · sec.gov
  • customer-concentration10%
    Oracle's only quantified concentration test is on revenue, not backlog: no customer was 10% of revenue in fiscal 2024–2026. It does not bound OpenAI's share of the RPO (see contested rpo-share); the same note says only that the returns on its large cloud build-outs depend on 'the ability of our key customers to meet their contractual obligations'
    “No single customer accounted for 10% or more of our total revenues in fiscal 2026, 2025 or 2024.”
    Oracle FY2026 10-K · sec.gov
  • lease-commitments$288B
    how Oracle carries the buildings: $288B of leases signed but not yet started at Aug 31 2026 ($260B at May 31 2026), substantially all data centers, 15–19-year terms, off the balance sheet until each begins. The May 31 figure includes 'a lease for which we have guaranteed up to $3.3 billion of the lessor's borrowing, which matures in September 2026' (10-K) — the only exposure to a developer's debt Oracle has filed; the Aug 31 10-Q mentions no guarantee. Neither report names a site or OpenAI; the developers, not Oracle, borrow the construction money (note)
    “As of August 31, 2026, we had $288 billion of additional lease commitments, substantially all related to data center arrangements, that are generally expected to commence between the second quarter of fiscal 2027 and fiscal 2029 and for terms of fifteen to nineteen years that were not reflected on our condensed consolidated balance sheets as of August 31, 2026 or in the maturities table above.”
    Oracle Q1 FY2027 10-Q (quarter ended Aug 31 2026) · sec.gov
  • capex-fy27-guidance$90–95B
    fiscal 2027 guidance: $90–95B of capex with 'not more than $70 billion in net cash CapEx' (Q1 FY27 call, Sep 2026) — the difference is customer prepayments and timing, 'expected at around $20 billion-$25 billion, so our reported CapEx will be higher by this amount' (Q4 FY26 call, Jun 2026). Customers pre-paying for, or bringing, their own GPUs is how Oracle funds part of the build
    “We continue to anticipate $90 billion-$95 billion in CapEx for the full year, with not more than $70 billion in net cash CapEx.”
    Oracle Q1 FY2027 earnings call (StockAnalysis transcript, Sep 10 2026) · stockanalysis.com
  • notes-fy26$43B
    $43.0B of senior notes issued in fiscal 2026, 'for general corporate purposes' — with a $5.0B mandatory convertible preferred (FY2026) and a $20B at-the-market share programme, completed in Q1 FY27. None of it is tied to Stargate in any filing. The convertible, the share programme and an early-2026 bond sale were announced together in Oracle's Feb 1 2026 funding plan, which says the money is to build capacity for the 'contracted demand' of its largest cloud customers, OpenAI among them (funding-2026; see contested stargate-debt)
    “During fiscal 2026, we issued a total of $43.0 billion par value of senior notes comprising the following:”
    Oracle FY2026 10-K (liquidity) · sec.gov
  • funding-2026
    Oracle's plan for calendar 2026, announced Feb 1 2026 and filed with the SEC as a free writing prospectus: $45–50B of gross cash proceeds, about half from equity (a mandatory convertible preferred and an at-the-market programme of up to $20B) and half from a single early-2026 bond sale, raised 'to build additional capacity to meet the contracted demand from our largest Oracle Cloud Infrastructure customers' — six named, OpenAI among them, 'and others'. It gives no amount or share for any customer and does not mention Stargate. Of the three Oracle filings that name OpenAI (oracle-filings), it is the only one that ties Oracle's financing to it
    “Oracle is raising money in order to build additional capacity to meet the contracted demand from our largest Oracle Cloud Infrastructure customers, including AMD, Meta, NVIDIA, OpenAI, TikTok, xAI and others.”
    Oracle free writing prospectus (Rule 163), Feb 1 2026 · sec.gov

Contested figures 28 not reconciled — every position side by side, with its source and tier

abilene-in-total3 positions, side by side
Abilene outside: 'The three new sites – located in Shackelford County, Texas; Doña Ana County, New Mexico; and a site in the Midwest … combined with an additional potential expansion of 600 megawatts near the flagship Stargate site in Abilene, Texas – can deliver over 5.5 gigawatts of capacity' OpenAI/Oracle/SoftBank joint release (Sep 23 2025)
Abilene inside: 'The three new sites, combined with Abilene and the nearby expansion, can deliver over 5.5 gigawatts of capacity' — Oracle's own fact sheet the same day (marked 'Confidential – Oracle Internal', posted by Rep. Arrington's office). The two documents differ by Abilene's whole 1.2 GW Oracle Fact Sheet: Stargate Data Centers (Sep 23 2025)
a third framing, in IT load: 'This campus, combined with other Stargate campuses in collaboration with Oracle, can deliver over 4.5 gigawatts of IT capacity' (Port Washington release, Oct 2025) — Abilene is itself a Stargate campus in collaboration with Oracle, and the release does not say whether it is counted. DCD's reading of the contract is the July wording: '4.5GW of capacity beyond the original site' OpenAI/Oracle/Vantage release (Oct 22 2025); DCD analysis (Nov 2025)
contract-measure4 positions, side by side
a partnership 'that exceeds $300 billion between the two companies over the next five years' — the parties' only words; no breakdown, start date or schedule joint release (Sep 23 2025)
a purchase of computing power: 'OpenAI has reportedly agreed to buy compute power worth $300 billion from Oracle in a five-year-deal', starting in 2027 (WSJ, Sep 10 2025, via DCD); the WSJ reporter: 'Contract starts in 2027 and OpenAI will have to pay an average of $60bn a year over five years to make it work' — an average, not a schedule WSJ via DCD (Sep 11 2025); Berber Jin on X
construction spending: 'The two companies have agreed to spend $300 billion on the construction of data centers over roughly five years' (NYT News Service, two people familiar) — a different quantity from the WSJ's compute purchase NYT via ETTelecom (Sep 11 2025)
an annual figure with no name on it: Oracle's 8-K of Jun 30 2025 — 'we signed multiple large cloud services agreements including one that is expected to contribute more than $30 billion in annual revenue starting in FY28' (FY28 begins Jun 2027). DCD read it as OpenAI's 4.5 GW; Oracle never says so, and the 8-K is furnished under Item 7.01 Oracle 8-K Item 7.01 (Jun 30 2025, furnished)
rpo-share2 positions, side by side
about half or more, by outside estimates: S&P's downgrade (Jul 9 2026) cites 'OpenAI's roughly half-share of a $638 billion remaining performance obligation backlog'; 'Bank of America estimates that more than half of the $638bn backlog is a single counterparty'. Neither report is on file; both reach it through secondary pages S&P via PPC Land; Bank of America via Bloor Research
undisclosed by Oracle: no filing, release or call gives RPO by customer; the 10-K's only concentration test is on revenue (customer-concentration) Oracle FY2026 10-K + Q1 FY2027 10-Q
abilene-live-capacity3 positions, side by side
what Oracle says, dated: 200 MW 'already operational' (Apr 22 2026) → 42% of total capacity delivered (Jun 10 2026) → six of eight buildings, 618 MW, 75% delivered (Sep 2026). 'Operational' and 'delivered' are never defined, and no figure is labelled IT or facility power Oracle X post, CEO blog, Q1 FY27 call
about 0.3 GW of facility power running in April 2026, not the 0.6 GW Epoch had estimated: 'a subsequent post by Oracle implied that only 200 megawatts (or about 0.3 GW of total facility power by our estimate) was operational as of April 22nd' — Epoch's own conversion of Oracle's 200 MW, not a second observation. Its data (as fetched Nov 2 2026) takes Oracle's 618 MW of Sep 10 as IT power and estimates 824 MW of IT power from Nov 1, when it counts all eight buildings in serviceEpoch AI, data_center_timelines.csv, "OpenAI Stargate Abilene" — 2026-09-10: Buildings operational 6.0; IT power (MW) 618.0 — 2026-11-01: Buildings operational 8.0; IT power (MW) 824.0 Epoch AI, 'OpenAI Stargate: where the US sites stand' (Apr 2026) + Data Centers hub timeline (data_center_timelines.csv, snapshot 2026-11-19) · epoch.ai
metered grid load: the campus 'ramped up at an unprecedented level in June (to about 407 MW)', after adding 'just 225 MW over the previous five quarters' — consumption, a different measure from delivered or nameplate capacity Yes Energy blog (2026)
abilene-it-capacity2 positions, side by side
~824 MW implied by Oracle's own 618 MW = 75% — the monitor's arithmetic on a statement that names no total and no basis; about 800 MW if each building carries the contractor DPR's 100 MW of IT load Oracle Q1 FY27 call (arithmetic)
824 MW of IT power for all eight buildings — Epoch's model of the finished campus as fetched Nov 2 2026 (843 MW projected for Q4 2026 on its explorer page as read Oct 7 2026), against the developer's 1.2 GW of total power. It is 8 × 103 MW: Epoch divides Oracle's 618 MW among the six buildings delivered — '618 MW = 6 x 103 MW, matching the per-building IT power figure Crusoe reported earlier' — so it now equals the monitor's 618 MW ÷ 75%. The two agree because both are built on the companies' own figures, not because Epoch measured the finished campusEpoch AI, data_center_timelines.csv, "OpenAI Stargate Abilene" — 2026-11-01: Buildings operational 8.0; IT power (MW) 824.0; Power (MW) 1154.0 Epoch AI Data Centers hub timeline (data_center_timelines.csv, snapshot 2026-11-19) + satellite explorer (read Oct 2026) · epoch.ai
abilene-completion2 positions, side by side
mid-2026 — the developer's plan when phase 2 began (Crusoe, Mar 18 2025) and Oracle's fact sheet in Sep 2025 ('expected to be complete in mid-2026') Crusoe release (Mar 2025); Oracle fact sheet (Sep 2025)
'by the end of 2026' (Crusoe, Mar 27 2026); Oracle in Sep 2026 gives no date — 'the remainder delivering in the subsequent quarters'. Epoch moved its 1.2 GW milestone 'from Q3 to Q4 2026'. No document records completion Crusoe release (Mar 2026); oracle.com/data-centers (Sep 2026)
abilene-expansion3 positions, side by side
cancelled: 'Oracle and OpenAI elected not to go forward with tentative plans to lease a large expansion', after talks 'complicated by financing and OpenAI's often-changing demand forecasting' (Bloomberg, Mar 6 2026, people familiar); OpenAI's head of compute infrastructure, Sachin Katti, in a post on X that AP quoted: 'We considered expanding it further, but ultimately chose to put that additional capacity in other locations.' Bloomberg adds that Nvidia 'paid a $150mn deposit to Crusoe and began helping court Meta as a tenant' — no Meta, Nvidia or Crusoe statement confirms it Bloomberg via Gulf Times (Mar 8 2026); Katti's X post as quoted by AP (via News4Jax, Mar 27 2026)
denied, or narrower than reported: Oracle posted on X that the coverage was 'false and incorrect' (Mar 9 2026, via Tom's Hardware); Tom's reading is that 'the existing Abilene campus is unaffected' and that what collapsed was 'a separate, never-finalized expansion lease' Tom's Hardware (Mar 10 2026)
re-tenanted to Microsoft: 'lenders balked at financing the expansion of a data-center complex in Abilene, Texas, if Oracle were the tenant … That led the developer, Crusoe, to lease it to Microsoft instead' (WSJ, Apr 24 2026, people familiar); AP, Mar 27 2026: 'Microsoft is taking over a data center construction project in Texas after OpenAI declined to pursue it'. Crusoe's own release that day calls it 'a new, dedicated AI factory campus' 'adjacent to Crusoe's existing Abilene AI factory infrastructure' and a 'newly announced expansion of the campus' — 900 MW, two buildings of 336 MW critical IT each, the whole site 2.1 GW — and never mentions OpenAI or the capacity OpenAI and Oracle had planned there. No party says the Microsoft campus is the capacity OpenAI and Oracle gave up WSJ via Hindustan Times; AP via News4Jax; Crusoe release (Mar 27 2026)
expansion-sizeone entry, in its own words
600 MW: 'an additional potential expansion of 600 megawatts near the flagship Stargate site' (joint release, Sep 2025) — vs ~0.8 GW, 'expanding the facility from 1.2 gigawatts to about 2.0 gigawatts' (Bloomberg, Mar 2026) — vs the 900 MW campus Crusoe is now building for Microsoft next door. Three sizes, no document reconciling them joint release; Bloomberg via Gulf Times; Crusoe release
site-delays2 positions, side by side
some of the sites Oracle is developing for OpenAI pushed back from 2027 to 2028, 'largely due to labor and material shortages' (Bloomberg, Dec 12 2025, people familiar) Bloomberg Law (Dec 12 2025)
denied the same day: 'There have been no delays to any sites required to meet our contractual commitments, and all milestones remain on track' (Oracle spokesperson Michael Egbert, to Reuters). Oracle's own guidance six months later put Saline and Port Washington at 2H27 delivery, and Doña Ana is now under a force-majeure notice (dona-ana-schedule) Reuters via CNA (Dec 13 2025)
dona-ana-schedule3 positions, side by side
customer delivery begins in 1H27 — Oracle's guidance (Jun 2026), still on its data-centers page in Sep 2026 Oracle CEO blog (Jun 12 2026); oracle.com/data-centers
Oracle sent the developer, a Blue Owl unit, 'a notice citing force majeure' over potential power delays (Bloomberg, Sep 24 2026) — by Bloomberg's sources, a way to put off payments should the campus 'fail to come online in 2028 as planned', which could win Oracle 'a three-year delay on rent'; Oracle's spokesperson, to Bloomberg: such notices 'do not, by themselves, establish a project delay or change delivery expectations'; a Reuters source: Oracle 'cannot terminate the lease under any circumstances' and Blue Owl has 'about $3 billion in equity in the project'. About $18B of construction loans from some 20 banks (Bloomberg) were quoted at 89 to 91 cents on the dollar (FT, via Reuters, Sep 18 2026) Bloomberg Law; Reuters via KSL; FT via Reuters/The Star
first power in 2029: 'our base case moved first power off 2027 entirely and out to 2029', for want of a gas pipeline and permits SemiAnalysis newsletter (2026)
dona-ana-powerone entry, in its own words
up to 2.45 GW of installed Bloom fuel-cell capacity (Oracle/BorderPlex/Bloom, Apr 27 2026), replacing the gas turbines of the Sep-2025 design — generation, not IT load — vs 'initially set to be powered by 2.2 gigawatts of gas turbines' (FT via Reuters) vs 'That facility alone could grow to 4.5GW at full buildout' (DCD, no source given; the 4.5 GW in party documents is Oracle's multi-site commitment). Oct 2026: Yucca Growth Infrastructure (YGI), the microgrid's air-permit applicant, proposed an enforceable output cap of 1,600 MW on its 2,462 MW nameplate — 'YGI will not operate the facility at more than 1,600 MW' — as a supplement to its pending application, so a proposed limit, not a granted one; Oracle says the change cuts permitted emissions 'by approximately 35%' and leaves the data center's planned IT capacity unchanged Oracle release (Apr 27 2026); FT via Reuters/The Star; DCD analysis (Nov 2025); Oracle release (Oct 15 2026); YGI's filings in NMED air-permit docket AQB-26-57 (Oct 23 and Oct 27 2026)
stargate-debt2 positions, side by side
'reportedly carrying more than $100 billion in debt to fund its Stargate commitments' (Tom's Hardware); 'taken on around $115 billion in debt just to build Stargate's data centers' (Ed Zitron) — Oracle's corporate borrowings relabelled, and Zitron's sum adds the developers' loans Tom's Hardware; Where's Your Ed At
no filing allocates Oracle debt to Stargate: total senior notes and other borrowings were $130.1B at May 31 2026, the year's $43.0B of notes issued 'for general corporate purposes'; Oracle's Feb 2026 funding plan says its 2026 raise is to build capacity for the 'contracted demand' of its largest cloud customers, naming OpenAI among six, with no amount for any (funding-2026); the site construction loans sit with the developers — 'Oracle is the tenant and OpenAI is the subtenant on the deals, but the debt doesn't sit on Oracle's balance sheet' (WSJ) Oracle FY2026 10-K + Feb 2026 funding plan (FWP); WSJ via Hindustan Times (Apr 2026)

For context, not this deal's figures 1 kept beside the deal so they are not mistaken for its numbers

  • capex-fy26$55.7B
    Oracle's own capital spending in fiscal 2026 (to May 31 2026): $55.7B — $48B net of about $8B of customer prepayments and timing, by the Q4 call. Company-wide: no filing assigns any of it to OpenAI or a site
    “partially offset by $55.7 billion of cash used for capital expenditures”
    Oracle FY2026 10-K (liquidity) · sec.gov

Scope note what this record leaves to other records

The developers' debt, which no Oracle filing shows (WSJ via Hindustan Times, Apr 24 2026, unless noted): about $10B of construction loans for Crusoe's Abilene campus (sg-crusoe-jv: $9.4B per Blue Owl's counsel, $9.6B per JPMorgan); $38B borrowed by Vantage for Shackelford and Port Washington; about $18B raised for STACK's Doña Ana campus (with ~$3B of Blue Owl equity, Reuters); Saline's $16B campus financed with Related and Blackstone equity and PIMCO-anchored debt. Oracle's filed exposure is the lease bill ($288B not yet commenced) and, at May 31 2026, a guarantee of up to $3.3B of one lessor's borrowing due in September 2026 (10-K; the Aug 31 10-Q mentions no guarantee). Not this record — carried elsewhere or not carried: the Doña Ana campus's $360M of payments in lieu of taxes (a county–developer term, not the OpenAI–Oracle deal); the 900 MW Crusoe campus for Microsoft next to Abilene (a separate deal, crusoe-msft-abilene); Abilene's GPUs on sg-orcl-nvda and its ownership and loans on sg-crusoe-jv; Oracle's ~$40B FY2027 debt-and-equity plan and its BBB rating path (entity-level). Corrected from the previous version: '~1.2GW live on OCI' (tier 1) was the finished campus's power, not what was running — see abilene-campus and abilene-live-capacity; the two Dec-2025 'completion' cells are kept as site-delays, now cited to the Bloomberg and Reuters pages. Not adopted: Bloomberg Law's 'OpenAI signed a $400 billion deal with Oracle and SoftBank' (the $400B is the umbrella's planned investment); 'Oracle recently inked an $18 billion debt deal' and 'a $38 billion deal' (the Public Enterprise report 'Bubble or Nothing', Nov 2025 — the borrowers are the developers); a Motley Fool transcript of the Q1 FY27 call giving 'more than 3 thousand GPUs' where Oracle's release and the StockAnalysis transcript say 300,000 — why the call is cited from StockAnalysis.

More between OpenAI and Oracle

  1. May 22, 2025 updated Nov 21
  2. Mar 7, 2025 updated Nov 20
  3. Jan 21, 2025 updated Nov 21

Everything between OpenAI and Oracle →