Microsoft–Constellation

Microsoft signed a 20-year deal for the output of the retired Three Mile Island reactor, about 835 , which Constellation plans to restart in 2027; the price is undisclosed.

A deal between Microsoft, Constellation

Why it matters

Microsoft's data-center demand is bringing a retired reactor back into service. The price remains undisclosed, and Constellation's presentations leave open whether Microsoft buys physical power or a financial hedge. The '$16B deal' label misrepresents a lobbying study's GDP figure as the deal value.

Tap a figure for the line in its source.

Constellation gives Microsoft

  • of the reactor's output for 20 years — power or a financial hedge; its decks differ

Microsoft gives Constellation

  • payments at an undisclosed price; the $98–120 per MWh quoted are analyst estimates

Sep 20, 2024 announced by Constellation; 8-K the same dayupdated Nov 21, 2026restart underway → 2H 2027 target disclosed by the parties

What happened

Microsoft's data-center demand is bringing the retired Three Mile Island Unit 1 reactor back into service. The 20-year agreement is tied to the plant's roughly 835 of output. The restart is targeted for 2027, with a government-guaranteed loan of up to $1 billion behind it. Microsoft's price is undisclosed. Every quoted price is an analyst's estimate. Constellation's own presentations leave open whether Microsoft buys the physical power or a financial hedge on that power.

Sources 7 documents — 7 SEC filings

Research trail Found 163 documents and read 157 of them while checking this deal and related ones.

  1. Constellation · SEC filingsec.gov
    States PPA term
  2. Constellation · SEC filingsec.gov
    States 835 MW announced capacity
  3. Constellation · SEC filingsec.gov
    States up to $1B doe loan guarantee
  4. Constellation · SEC filingsec.gov
    States 0.375% doe loan rate maturity
  5. Constellation · SEC filingsec.gov
    States restart target
  6. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  7. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: CEG 8-Ks + FY25 10-K + Q3'26 10-Q + DOE/FFB loan agreement (ex-10.1) + investor decks; PJM/DOE/SRBC regulatory record · as of Nov 2026

The evidence 5 sourced figures · 6 disputes

The record's headline Microsoft–Constellation: 20-yr PPA restarts Three Mile Island

Size
835 MW / 20 yr
When
Sep 2024 → restart 2027 (target)
Status
restart underway → 2H 2027 target
Structure
power purchase agreement (Mar-2026 deck: 'virtual PPA' — see contested)
Programme
Time-to-power
Parties
Microsoft offtaker · Constellation nuclear-operator + DOE/FFB borrower
Record
disclosed / primary source · as of Nov 2026

Resolved figures 5 each with the verbatim line from its document

  • ppa-term20 years
    20-year PPA announced 2024-09-20 (executed Sept 2024 per the FY24/FY25 10-Ks); the plant is TMI Unit 1, retired 2019 for economic reasons, renamed Crane Clean Energy Center
    “On September 20, 2024, Constellation Energy Corporation (Constellation) announced the signing of a 20-year power purchase agreement with Microsoft that will pave the way for the restart of Three Mile Island Unit 1, to be renamed the Crane Clean Energy Center, which was retired in 2019 due to economic conditions.”
    CEG 8-K 9/20/2024 · sec.gov
  • announced-capacity835 MW
    ~835 MW is the ANNOUNCED/contracted figure both counterparties use — the independent regulatory record measures differently (see contested capacity-conventions)
    “Constellation signs its largest-ever power purchase agreement with Microsoft, a deal that will restore TMI Unit 1 to service and keep it online for decades; add approximately 835 megawatts of carbon-free energy to the grid”
    CEG launch PR (8-K ex-99.1) · sec.gov
  • doe-loan-guaranteeup to $1B
    up to $1.0B unsecured FFB loan, DOE-guaranteed (Energy Dominance Financing), closed Nov 2025 — NOT the '$1.6B DOE loan' in circulation (that conflates the Oct-2024 WaPo-reported request and/or the restart capex); still undrawn — the Q3-2026 10-Q (filed Nov 9 2026): 'There have been no borrowings on this loan as of the date of this filing' (it matures Nov 2055, as the loan agreement says); initial borrowing required by May 17, 2027 and advances ≤80% of eligible project costs, per the earlier FY25 10-K / Q1-2026 10-Q, which the Q3 10-Q does not restate
    “In November 2025, the DOE Office of Energy Dominance Financing issued a guarantee for up to $1.0 billion for an unsecured loan from the Federal Financing Bank to support the restart of the Crane Clean Energy Center.”
    CEG Q3'26 10-Q · sec.gov
  • doe-loan-rate-maturity0.375%
    +0.375%/yr over comparable-maturity Treasuries, fixed per advance; final maturity Nov 17, 2055 — the executed loan agreement settles the 10-K's own internal 'October 2055' (MD&A) vs 'November 2055' (notes) conflict
    “Principal will be payable in full on the final maturity date of November 17, 2055. The interest rate for each advance will be established by FFB at the time that the respective advance is made and, shall be 0.375% per annum over the current average yield on outstanding marketable obligations of the United States of comparable maturity, as determined by the Secretary of the Treasury.”
    CEG 8-K 11/17/2025 (loan agreement filed as ex-10.1) · sec.gov
  • restart-target2027
    2H 2027 company target (accelerated from the original 2028; a superseding revision with a documented date, not a conflict) — full grid deliverability is a separate question, see contested grid-timeline
    “Crane Clean Energy Center will return to service in 2027”
    CEG Q2'25 8-K ex-99.1 · sec.gov

Contested figures 6 not reconciled — every position side by side, with its source and tier

ppa-priceone entry, in its own words
$98–$120/MWh — NO primary source of any kind (Bloomberg: 'The companies haven't disclosed terms of the 20-year deal'); the spread collapses to 3 independent sell-side back-solves of one CEG EPS-accretion slide: Morgan Stanley $98 / Bloomberg Intelligence ≥$100 / Jefferies ~$112 (its '$110–115' is the same bank via a second wire) sell-side estimates via Bloomberg/Reuters/Utility Dive
deal-structureone entry, in its own words
physical vs financial: launch deck says 'fixed-price off-take agreement for plant's full output'; the Mar-2026 deck lists Crane as '835 MWs from nuclear restart under virtual PPA'. No filing reconciles — the Q3-2026 10-Q says only that the PPA is 'to purchase the output generated from the renewed plant', without saying whether it settles physically — and the executed PPA is in no public record — Constellation's Sep 20 2024 8-K ties the purchase to Microsoft's 'goal to help power its data centers in PJM with clean energy', but no filing says the power is delivered to those data centers physically CEG investor decks (both tier 1, 18 months apart)
total-valueone entry, in its own words
undisclosed. The circulating '$16B deal' is The Brattle Group's 20-yr PENNSYLVANIA GDP impact (advocacy-commissioned) mislabeled as contract value — the monitor's est ribbon arithmetic (835 MW × 20 yr × ~$110/MWh) lands near the same number by coincidence and stays tier-3/est no primary; bluff traced via 8-K ex-99.1 footnote
capacity-conventionsone entry, in its own words
835 MW (announced) / 837 MW (pre-retirement generating) / 871 MW gross (DOE Final EIS + SRBC filings — the figure the independent regulatory record uses) / 885 MW pre-shutdown gross (NPDES) / 859.0 MW capability of which 803.0 MW PJM-recognized Capacity (Phase I study) — different measurement conventions, never reconciled in one document DOE EIS / SRBC / PJM AH1-695 / CEG filings
grid-timelineone entry, in its own words
company 2H-2027 return-to-service vs PJM: transmission upgrades for FULL deliverability as late as Dec 2030 (press: '2031') — bridged by the Jun-2026 FERC waiver moving 760 MW of Eddystone CIRs to Crane (docket ER26-2028, IMM opposed; CEG's Q3-2026 10-Q confirms it — 'In June 2026, FERC granted the waiver request and we subsequently transferred the CIRs to Crane' — and still gives 'December 2030' as the latest projected in-service date of the study's contingent upgrades, but states no MW; the FERC order itself is NOT among the documents read — 760 MW and the IMM's opposition rest on trade press) CEG Q3'26 10-Q + PJM Phase I study vs trade press on FERC waiver
restart-capexone entry, in its own words
~$1.6B public company estimate (FY24/FY25 filings; The Hill flags it may predate full scope) ← $1.5B board authorization July 2024 ← ~$1.4B contemporaneous private estimate (both earlier figures via the SEC insider-trading complaint, which also discloses the internal codename 'Project Tetris') — chronological estimate lineage, not a dispute; no updated figure exists CEG filings + SEC v. Muggleston complaint

Scope note what this record leaves to other records

NRC license runs to 4/19/2034 (subsequent renewal application planned 2029, targeting ≥2054); water: 73.2 mgd peak-day withdrawal requested (SRBC); staffing is a time series 80 → 550+ FTEs (Jun 2026) against a 600-650 target; final-year capacity factor 96.3%. SEC v. Muggleston (6/2026): alleged insider bought 550 calls pre-announcement, ~$1.4M alleged profit; CEG closed +22.3% at $254.98 on announcement day

More between Microsoft and Constellation

The record holds no other deal between them.