Why it matters
DTE Electric's model for serving Google's data center needs some 677 of new capacity in 2033, when Google's capacity credits and demand response lapse. DTE Electric prices that capacity as a gas plant with carbon capture that would outlast the contract. Its cost is included in DTE Electric's claimed $1.7B benefit, which the Michigan Public Service Commission declined to endorse.
Tap a figure for the line in its source.
DTE Electric gives Google
- of electric service at DTE's large-load rate, from Dec 2027 to full load in Dec 2028 (Google may push that back up to 18 months), for 20 years from first service, with up to two 5-year renewals
- of new solar or wind farms that DTE develops and owns for the load, their renewable energy credits going to Google, which pays each project's full actual cost within the contract's term, faster where a project will outlast it; the filed contract redacts a cost target that limits only which projects DTE may add on its own, and a cap on overruns from events such as a change in law
- of energy storage (the contract allows batteries or another technology) that DTE builds, buys or contracts for the load, at Google's cost within redacted cost caps; 'up to' in the contract, but the Commission made treating this and the 1,600 as minimums a condition of approval
Google gives DTE Electric
- minimum bill: demand charges on 80% of the contracted capacity whether used or not (or on what DTE could actually deliver, if less) — about $13.8M a month at full load at today's rates, by DTE's calculation
- exit payment if the contract ends at full load: the minimum bills up to the 15th anniversary of full load, at today's rates
- of capacity credits (MISO zonal resource credits) handed to DTE 'at no cost to DTE Electric' (the 8-K) each season from Jun 2028 to May 2033, Google being credited for them up to what they earn in MISO's capacity auction
- the level Google must cut its load to when called, Jun 2027–May 2033, under a separate demand-response agreement
- disputedtoward the distribution upgrades DTE builds for the campus, which DTE expects to cost less, plus the cost of any unexpected site conditions; the Commission conditioned approval on removing any cap on that contribution
- credit support for both contracts: a parent guaranty from Alphabet that becomes a letter of credit if Alphabet's credit rating falls below a threshold
What happened
DTE Electric, the utility for Detroit and southeast Michigan, signed contracts with Google to power a planned 1-gigawatt data center in Van Buren Township, in Wayne County. The contracts cover 20 years of electricity. Google pays demand charges, or fees for capacity, on at least 80% of the contracted capacity whether it uses it or not. Google owes about $2.5 billion if it walks away at full load. Google will pay for up to 1,600 megawatts of new solar or wind farms and 480 megawatts of energy storage that DTE develops for it. Google pays the actual cost of those projects. The contract caps only part of the cost and keeps those caps confidential. The Google contracts went through a full contested case, a formal process for hearing objections. DTE's Oracle contracts did not go through that process. On October 1, 2026, the Michigan Public Service Commission approved the Google contracts with conditions. One condition makes DTE absorb any costs of serving Google that Google does not pay, with none passed on to DTE's other customers. Another makes the 1,600 and 480 megawatts targets that can be exceeded. DTE says the contracts will save its other customers $1.7 billion over 20 years. The Commission endorsed no figure. Other parties recalculated the savings at about $0.5 billion to $1 billion. DTE had 30 days, to October 31, to accept the conditions. Its November 5 filings say DTE secured approval and is moving forward to serve two hyperscale data center customers. The filings do not say whether DTE filed its acceptance letter.
Sources 37 documents — 17 regulatory filings · 12 SEC filings · 3 government statements · 2 transcripts · 2 press reports · 1 company release
Research trail Found 166 documents and read 159 of them while checking this deal and related ones.
- States 4 figures: 50% d11 comparison · $2.48B termination payment · collateral · approval
- States 3 figures: 1,000 MW contract capacity · 80% minimum bill · $13.8M minimum monthly charge
- States 3 figures: 650 MW firm service level · 677 MW capacity gap 2033 · $308M transmission upgrade
- States 2 figures: 1 GW announced · up to 480 MW storage
- States 2 figures: parties · term years
- States 2 figures: up to 1,600 MW renewables · 300 MW capacity credits
- States cost condition
- States 90% load factor
- States 11,017 MW system peak
- States $5B dte capex
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: DTE–Google amended PSA and CCAA (DTE 10-Q for Q1 2026, ex. 10.1/10.2) + First Amendment (Exhibit A-22); DTE 8-K (Mar 17 2026); MPSC order U-22058 et al. (Oct 1 2026) + release; DTE application and testimony (Foley, Burgdorf, Bilyeu, Brooks, Benyard; Willis's Exhibit A-19) and discovery answers in the intervenors' exhibits; DTE's 10-Q for Q2 2026, investor decks and 2026 IRP testimony; Google's blog and Nevada testimony; MISO's expedited project review; DTE's Q4 2025 call for the preview; the Attorney General, ABATE, MEICEO, MNS and Staff filings, DTE's initial brief and Latitude Media for the contested cells (read 2026-10); DTE's 10-Q for Q3 2026, results release (ex. 99.1) and earnings deck (ex. 99.2) of Nov 5 2026 for the capex line and the approval's status · as of Nov 2026
The evidence 20 sourced figures · 10 disputes
The record's headline DTE–Google: power for a 1 data center in Van Buren Township for 20 years from first service — an 80% minimum bill, a ~$2.48B exit payment at full load, and Google paying for up to 1,600 of renewables and 480 MW of energy storage that DTE develops; approved Oct 1 2026 after a contested case, on conditions DTE had 30 days to accept
- Size
- 1,000 MW contract capacity · 80% minimum billing demand · minimum monthly charge ~$13.8M at full load (U-21860 D11 rates) · termination payment ~$2.48B at full load, declining · CCAA: up to 1,600 MW of renewables and up to 480 MW of storage at Google's cost, plus 300 MW of zonal resource credits · 20-year term from first service + two 5-year renewals
- When
- Dec 17 2025 (original PSA dated, undisclosed) → Feb 17 2026 (DTE expects to reach final terms with an unnamed additional customer 'in the coming weeks') → Mar 12 2026 (contract date of the amended PSA and the CCAA) → Mar 16 2026 (DTE Energy's board approves execution) → Mar 17 2026 (8-K, application, Google's announcement) → Jun 30 2026 (evidentiary hearing) → Aug 3 2026 (reply briefs; the date by which the schedule closed the record) → Sep 10 2026 (the contracts' approval deadline passes) → Oct 1 2026 (conditionally approved) → by Oct 31 2026 (DTE's acceptance due) → Nov 5 2026 (DTE's Q3 10-Q: approval 'secured', the ~$5B now inside its five-year plan) → Jun 2027 (demand response begins) → Dec 2027 (first service) → Jun 2028 (capacity credits begin) → Dec 2028 (full load scheduled) → May 31 2033 (credits and demand response end) → ~2047 (20th anniversary of first service)
- Status
- conditionally approved Oct 1 2026 after a contested case; DTE had to file a letter accepting all the conditions within 30 days, by Oct 31 (none is among the documents read, nor any rehearing petition or appeal; DTE's Q3 10-Q, Nov 5, says it 'secured MPSC approval in the fourth quarter of 2026' and its results release that it 'is moving forward to serve two hyperscale data center customers', and neither says whether the letter was filed). The contracts' own deadline for approval, Sep 10 2026 (per DTE's Foley), had passed; the order notes that the PSA settles how the parties handle a conditional approval (its §§4.4–4.5, redacted in the copy filed with the SEC; the order quotes §4.4.2, under which, after a conditional approval, the parties may meet and confer to 'negotiate in good-faith any amendments necessary to such agreement to implement the conditions') and that 'DTE Electric is free to reject the Commission’s conditional approval'. Supplements to its integrated resource plan and renewable energy plan due within 21 days; reporting from Apr 15 2027; service from Dec 2027, full load scheduled Dec 2028
- Structure
- two special contracts conditionally approved together — an Amended and Restated Schedule Designation D11 Primary Supply Agreement (PSA: service under DTE's Rate D11 for 20 years from first service, with an 80% minimum billing demand, a termination payment, an affordability backstop and credit support) and a Clean Capacity Accelerator Agreement (CCAA: DTE develops and owns up to 1,600 MW of solar or wind, and builds, buys or contracts up to 480 MW of storage, and recovers each project's actual cost from Google, subject to redacted cost caps on the storage and on overruns from relief events — a redacted renewable cost target limits only which renewables DTE may add on its own; Google also delivers 300 MW of MISO Zone 7 zonal resource credits) — between DTE Electric Company and Google LLC, a wholly owned subsidiary of Alphabet Inc., which backs both by a parent guaranty; two companion agreements of the same date were not submitted for approval: a Rider 12 demand-response agreement, described in testimony, and a line extension agreement for the distribution upgrades, filed only as a confidential exhibit — the new lines connect two distribution substations that Google designs, builds and owns on its site
- Programme
- Time-to-power
- Parties
- Google customer — Google LLC, which plans to have the Van Buren Township data center built and takes its power; its parent, Alphabet, guarantees its payments, with a letter of credit if Alphabet's rating falls below a threshold · DTE Electric utility — supplies the power under Rate D11; develops and owns the renewables, and builds, buys or contracts the storage, that Google pays for, earning its regulated return on the projects it owns; builds the distribution upgrades that connect Google's two on-site substations. The new 345 kV station is ITC's (MISO project 51220), whose cost reaches DTE through MISO charges and its customers through the fuel-and-power surcharge
- Record
- disclosed / primary source · as of Nov 2026
Flows 2 as the record states them
- DTE Electric → Googlepowerelectric service to 1,000 MW of contract capacity at full load (Dec 2028), about 7,884 GWh a year at the ~90% load factor DTE modeled, for 20 years from first service (Dec 2027) plus up to two 5-year renewals that take effect unless either side gives notice; the renewable energy credits of up to 1,600 MW of new solar or wind, and up to 480 MW of storage built or contracted for the load
- Google → DTE Electricpower-paymentsa minimum bill: demand charges on 80% of contract capacity — ~$13.8M a month, ~$165.1M a year at full load at U-21860 D11 rates — plus energy and pass-through charges on actual use; each CCAA project's revenue requirement over its depreciable life, or faster where that life runs past the contract's term, trued up to actual cost and capped only in part (the storage, and overruns from relief events, at redacted levels), less credits capped at the projects' market revenues; 300 MW of zonal resource credits a season, Jun 2028–May 2033, and a financial adder on them; a termination payment of ~$2.48B if the PSA ends at full load, declining after
Resolved figures 20 each with the verbatim line from its document
- announced1 GWfirst public on Mar 17 2026, from both companies the same day: DTE's 8-K, filed that day for its board's Mar 16 approval of the contracts, describing 'Customer’s future 1.0 gigawatt data center to be located in southeast Michigan'; DTE's application to the Commission; and Google's blog — 'Today, we announced plans to develop a new data center in DTE Energy’s service territory in Michigan', adding that 'Google is currently evaluating a site in Van Buren Township'. Before that, DTE had previewed the deal without naming the customer — 'We are expecting to reach final terms of an agreement with an additional customer in the coming weeks' (its chief executive, Joi Harris, on the Feb 17 2026 call) — and the project was public without its customer: Van Buren Township's answers to questions from its Jan 14 2026 planning meeting relayed the developer that the contract between DTE and the client 'will likely be 20+ years' and would be made public in a Commission filing once finalized
“Under the terms of the PSA, DTE Electric will provide electric service at its standard industrial rate to Customer’s future 1.0 gigawatt data center to be located in southeast Michigan (“Project”).”
DTE Energy / DTE Electric 8-K (Mar 17 2026), Item 1.01 · sec.gov - partiesthe parties and the dates: an Amended and Restated Schedule Designation D11 Primary Supply Agreement and a Clean Capacity Accelerator Agreement, both entered into on Mar 12 2026 between DTE Electric Company and Google LLC, 'a Delaware limited liability company' whose address is redacted; the PSA restates an original PSA 'dated as of December 17, 2025', three months before the contracts were announced; the PSA's 'Data Center Location' is Van Buren Township, Michigan, where DTE's Foley says the facility will be developed on 'roughly 280 acres'. A Rider 12 capacity release (demand-response) agreement and a line extension agreement of the same date were not submitted for approval; the line extension agreement is filed only as a confidential exhibit. Google LLC is 'a wholly owned subsidiary of Alphabet Inc.', whose parent 'is providing credit support to DTE Electric for both the PSA and CCAA' (the 8-K). DTE Energy's board approved execution on Mar 16, four days after the contract date. Both contracts are filed as exhibits 10.1 and 10.2 to DTE's 10-Q for Q1 2026, with the ramp and energization schedules, the collateral amounts and guaranty form, the sample invoices and termination calculation, the CCAA's cost caps and other passages redacted
“This Amended and Restated Schedule Designation D11 Primary Supply Agreement (this “Agreement”) is entered into on this 12th day of March, 2026 (“Contract Date”), by and between: (1) DTE Electric Company, a corporation organized under the Laws of the State of Michigan with an address of One Energy Plaza, Detroit, Michigan 48226 (“Company”); and (2) Google LLC, a Delaware limited liability company”
DTE Electric–Google Amended and Restated D11 Primary Supply Agreement (DTE 10-Q for Q1 2026, ex. 10.1) — preamble and recitals · sec.gov - contract-capacity1,000 MW1,000 MW at full load — DTE's Foley: 'The maximum load at the facility is 1,000 MW (“max load” or “contract capacity”)'; the Commission's order: 'a 1.0 gigawatt (GW) data center facility'. The load is planned to begin in December 2027 and reach its maximum by December 2028; Google 'can temporarily delay their load ramp or any increase in the scheduled ramp by up to 18 months in the aggregate', so 'the Load Ramp Completion Date could occur as late as June 2030', but it 'cannot reduce their contract capacity' once the ramp is reached (Foley). The PSA dates the Load Ramp Completion Date to the final ramp step or 'December 31, 2028, as such date may be revised', whichever comes first; the ramp table itself (Exhibit B-1) is redacted. MISO lists ITC's project for 'a new station to serve 1000 MW of load for a new industrial customer'. This is utility demand, not a count of the chips inside. MEICEO's witness Shaver also worked from the slowest ramp the PSA allows (Foley's Figure 1), to full load over 2029–2030 — a scenario, not a revised schedule. DTE can hold the ramp back too: ABATE asked the Commission to direct DTE to use its right under the PSA to limit the ramp when resource-adequacy triggers occur, and the Commission declined, finding that the PSA 'already leaves it within DTE Electric’s discretion to delay that date'
“The maximum load at the facility is 1,000 MW (“max load” or “contract capacity”).”
DTE witness Foley, revised direct testimony (MPSC Case U-22058, Apr 2026), A17 · openmpsc.com - term-years20 years20 years from first service: the initial term runs from the Commencement Date, 'the date on which the Customer first receives Electric Service at the Facility', to the twentieth anniversary of that date (§3.1), and 'shall automatically renew for up to two additional five (5) year terms' unless either party gives notice at least 36 months before the end (§3.2). The CCAA runs to the same twentieth anniversary. The Commission's release sets it against 'contract length of 20 years, compared to 5-year contracts normally required under DTE Electric’s large-load D11 rate'; the order notes the term and renewals 'were not disputed'. The contract fixes no calendar end; DTE has projected two different months (contested term-end)
“The term (the “Initial Term”) of this Agreement shall commence upon the Commencement Date and shall continue until 11:59 p.m. EPT on the date which is the twentieth (20th) anniversary of the Commencement Date.”
Primary Supply Agreement §3.1 (DTE 10-Q for Q1 2026, ex. 10.1) · sec.gov - minimum-bill80%an 80% minimum billing demand, in DTE's Foley's words: the minimum demand for each billing period 'will be 80% of the contract capacity applicable for that billing period' — 800 MW once full load is reached — and DTE will calculate all three D11 demand charges on the greater of that 80% or Google's actual billing demand. The contract adds a limit: the minimum charge uses 'the lesser of (A) eighty percent (80%)' of the committed capacity 'and (B) the maximum capacity Company was actually capable of providing Customer in such billing period' (§5.2). It supersedes the standard rate's 65% ratchet on the two power-supply charges and the floor of 50% of contract capacity on the distribution charge (d11-comparison). Even if Google's use 'never reaches the contract capacity', the minimum monthly charge is calculated on it (Foley). The Commission found the 80% reasonable — not on precedent but 'because DTE Electric showed, and the Staff confirmed', that it protects against stranded costs: in the Staff's case of Google paying only the minimum bill, it covers the non-production costs of serving Google every year, at least 116.64% of them (2035) — and found that the Attorney General's 90% 'appears to be arbitrary'
“Under the PSA, the Customer agrees that the minimum demand for a given billing period will be 80% of the contract capacity applicable for that billing period.”
DTE witness Foley, revised direct testimony (MPSC Case U-22058), A27–A29 · openmpsc.com - d11-comparison50%what the 80% is measured against: under DTE's standard Rate D11 the minimum billing demand is '50% of contract capacity or 65% of the highest monthly peak demand' (the order, citing DTE's rate book); the Commission's release: 'A minimum billing demand of 80%, compared to 50%-65% in the general D11 rate'. This record uses 50–65% for the comparison; the Commission's own Dec 2025 release on the Oracle contracts said '50-60%' (pw-dte-oracle)
“Under Rate D11, the MBD is either 50% of contract capacity or 65% of the highest monthly peak demand.”
MPSC order, Case U-22058 et al. (Oct 1 2026) · adms.apps.lara.state.mi.us - minimum-monthly-charge$13.8Mabout $13.8M a month, $165.1M a year, at full load, at the D11 rates approved in DTE's last rate case (U-21860) — DTE's calculation. Not a fixed price: the charge moves with Rate D11, and the termination payment built on it 'will not be known until the time of termination as it relies, in part, on the then-current Rate D11' (the order)
“Based on the D11 rates approved in Case No. U-21860, the Customer’s MMC will be $13.8 million per month, or $165.1 million per year”
DTE witness Foley, revised direct testimony (MPSC Case U-22058), A28 · openmpsc.com - termination-payment$2.48Babout $2.48B if the PSA ends at full load — the Commission: 'Applying the rates approved in DTE Electric’s most recent rate case, this results in a termination payment as of the load ramp completion date of $2.48 billion'. The clauses (§7.3, as amended): an exit before the fifteenth anniversary of the Load Ramp Completion Date that is neither party's default, or DTE's termination for Google's default before the thirteenth anniversary, pays the minimum monthly charge 'for each month between the Early Termination Date and the fifteenth (15th) anniversary of the Load Ramp Completion Date'; DTE's termination for Google's default after the thirteenth anniversary pays it for 'the lesser of: (a) twenty-four (24) months, and (b) each month between the Early Termination Date and the expiration date of the Term'. The filed PSA keyed the two default cases (§7.3(2)–(3)) to the Commencement Date; a First Amendment (Exhibit A-22) put the Load Ramp Completion Date in its place, correcting what DTE called 'a drafting error'. DTE's Foley, and the order after him, sum it up more broadly: before the fifteenth anniversary, 'the greater of 1) the number of months from the early termination date to the fifteenth anniversary of the Load Ramp Completion Date, or 2) 24 months', and after it '24 months of Minimum Monthly Charges' (Foley) or the lesser of 24 months and the months left (the order) — a two-year floor the clauses give only when Google defaults; a no-fault exit after the fifteenth anniversary carries no termination payment in §7.3. The Staff's check, per the order: 'the total non-production costs of $2.476B' against the payment at full ramp, 'which is also $2.476B'. The Commission found it 'greater than the termination fee approved in the December 18 order' (Oracle's, pw-dte-oracle) and declined the Attorney General's request to base it on 100% of demand for all 20 years. How many years it covers is contested (termination-years). The CCAA has its own termination payment — the projects' charges for the rest of the term — 'triggered only by Google’s default', the order says, though the CCAA also charges it if the agreement ends after a cost-overrun 'Relief Event' (§6.5, §9.3) and counts as Google's default both its own ending of the PSA for any reason other than DTE's default and DTE's ending of it for any reason (§9.1.5)
“Applying the rates approved in DTE Electric’s most recent rate case, this results in a termination payment as of the load ramp completion date of $2.48 billion.”
MPSC order, Case U-22058 et al. (Oct 1 2026) — termination payments · adms.apps.lara.state.mi.us - collateralthe credit support: 'a PG from Google’s parent company (Alphabet Inc.) that escalates to an LoC if the parent’s credit rating falls below a certain threshold' (the order); a qualifying letter-of-credit bank must be rated at least A-/A3 with a net worth of at least $10 billion (the PSA's definitions). The amounts are redacted, and DTE acknowledged a gap between the collateral and the termination payment. The Commission's condition: 'All risk associated with the sufficiency of the collateral shall be borne by DTE Electric', and costs it finds attributable to serving Google may not be recovered from other customers 'even after termination of the PSA and CCAA'. DTE must apply within three years of the load ramp completion date for a review of the termination payments and the collateral (ordering paragraph M)
“The collateral is provided via a PG from Google’s parent company (Alphabet Inc.) that escalates to an LoC if the parent’s credit rating falls below a certain threshold.”
MPSC order, Case U-22058 et al. (Oct 1 2026) — collateral · adms.apps.lara.state.mi.us - approvalconditionally approved on Oct 1 2026 by the three-member Commission (unanimously, Planet Detroit reports), after a fully contested case — testimony from 18 witnesses, an evidentiary hearing on Jun 30 and briefs through Aug 3, in which the Staff, the Attorney General, ABATE (industrial customers), GLREA and two coalitions of environmental and clean-energy groups (MNS; MEICEO) took part. DTE filed it as a contested case while asserting that it qualified for approval without one (the order); the Attorney General said Google had committed to her, the day before the announcement, to pursue a contested case. The ruling: 'DTE Electric Company’s March 17, 2026 application for approval of special contracts consisting of a primary supply agreement and a clean capacity accelerator agreement with Google LLC is conditionally approved.' The conditions include: Google's payments must cover all costs of serving it, and DTE files a letter accepting all the conditions within 30 days (B); operating parameters updated as grid regulators require (C); no cap on what Google or DTE contributes to the line extension or other infrastructure for the site (D, lea-cap); the financial adder on the capacity credits booked as ordinary income (E); renewable credits transferred to Google retired in the same year (F); supplements, within 21 days, to DTE's integrated resource plan, including modeling an extension of the capacity credits and the demand response past May 31 2033 (G), and to its renewable energy plan (H); and an application for updated interconnection procedures and a battery import and export tariff within 120 days (I) — and, in the order's discussion, treating the 1,600 MW and 480 MW as 'minimums to be reached, and, if possible, exceeded', which 'must be a condition of approval'. The order also directs a review of the termination payments and collateral within three years of full load (M) and reporting from Apr 15 2027 (N)
“DTE Electric Company’s March 17, 2026 application for approval of special contracts consisting of a primary supply agreement and a clean capacity accelerator agreement with Google LLC is conditionally approved.”
MPSC order, Case U-22058 et al. (Oct 1 2026) — ordering paragraph A · adms.apps.lara.state.mi.us - cost-conditionthe condition the Commission's release leads with: other customers are not to bear any cost of the project. The release then sums up the PSA in its own words — 'A contract length of 20 years, compared to 5-year contracts normally required under DTE Electric’s large-load D11 rate', 'A minimum billing demand of 80%, compared to 50%-65% in the general D11 rate', 'An early termination payment requiring Google to ultimately pay for at least 15 years of minimum monthly charges', and 'Credit and collateral requirements' — and attributes the benefit claim to DTE: 'DTE Electric contends that approval of the data center special contracts will result in a $1.7 billion benefit' (affordability). The order sets one limit on the promise: other customers here do not include customers who buy their power elsewhere (choice customers), who, the Staff found, 'will pay more'
“The Michigan Public Service Commission today approved special contracts between DTE Electric Co. and Google LLC for the utility to provide electricity for a data center in Wayne County’s Van Buren Township, conditioned on mandatory protections to prevent other customers from having to bear any costs associated with the project (Case No. U-22058).”
MPSC release, Oct 1 2026 · michigan.gov - renewablesup to 1,600 MWup to 1,600 MW of renewables, each a 'Company owned and operated utility-scale solar photovoltaic or wind energy project' (the CCAA's definition), with DTE targeting at least half of the capacity through build-transfer agreements (§4.1.1) — DTE proposed 500 MW in 2030, 700 MW in 2031 and 400 MW in 2032 (Bilyeu) — enrolled in DTE's voluntary green pricing program so their renewable energy credits go to Google. Google 'will pay the full cost (i.e., revenue requirement) of the projects over each project’s depreciable life' (Foley), calculated for each DTE-owned project as in a renewable energy plan, 'The Company’s prevailing authorized rate of return' included, and in a shorter time where a project's life runs past the CCAA; Google receives credits for the projects, never more than their market revenues. The filed contract bounds that cost only in part. DTE may add a project on its own only if it keeps the portfolio's levelized cost under a 'Renewable Cost Target' per kWh, but the target is used 'solely' for that choice and 'shall not be used to determine or otherwise affect or limit' what DTE recovers from Google for a project in the portfolio, which follows actual cost (§4.1.10, §4.2.2); if DTE finds the portfolio cannot be built within the target and the parties cannot agree on measures to fix it, Google reimburses DTE's incremental cost of meeting Michigan's renewable portfolio standard, to the extent its load causes it (§4.1.10.2, whose trigger is partly redacted). What the contract caps is a cost increase from a force majeure, change in law or similar 'Relief Event' once a project is in service: past a 'Relief Event Cost Cap', the parties have 30 days to renegotiate, failing which DTE may drop or replace the project, keep it and bear the excess itself, or end the agreement (§6.5); the target and the cap are redacted. The Commission found the 'up to' must not act as a cap — 'up to' could mean 1 MW of each — and made treating the amount as a minimum to be reached a condition of approval; it declined to set the ownership split or the sourcing, asking that procurement follow its competitive guidelines 'to the maximum extent practicable' and that DTE's system needs be met first, and encouraging DTE to exceed the 35% limit on third-party-owned resources whenever that saves its other customers money. Whether the farms will be solar, wind or both is open (see note)
“Customer desires to procure RECs from the generation of one or more Renewable Energy Projects of up to 1,600 MW in aggregate consistent with the Settlement (collectively, the “Renewable Portfolio RECs”) from the project(s) described in the Renewable Portfolio.”
DTE Electric–Google Clean Capacity Accelerator Agreement, recital D (DTE 10-Q for Q1 2026, ex. 10.2) · sec.gov - storageup to 480 MWup to 480 MW of storage at Google's cost: up to 425 MW of four-hour storage, lithium-ion in Foley's words, and up to 55 MW of long-duration storage of at least eight hours, which 'can be lithium-ion or a different technology' (the CCAA's Exhibit F; Foley); the CCAA defines each as a utility-scale battery 'or other energy storage system'. DTE builds it, buys it under build-transfer agreements or contracts it from third parties under tolling agreements — each DTE-owned project's revenue requirement calculated as in a general rate case, a contracted one's as 'the annual cost of the TA or PPA plus any authorized financial incentive' (Foley) — and recovers it from Google over a 15-year depreciable life, or within the contract's term where that life would run past it (§3.1.7). Exhibit F gives each storage type a cost cap per kW-month, redacted: the four-hour portfolio's levelized cost 'shall not exceed' the '4-Hour Cost Cap' unless the parties agree otherwise (§3.2.2), and the relief-event terms apply here too (§6.5). The Commission made treating the cap on megawatts as a floor ('minimums to be reached') a condition of approval; DTE had modeled 450 MW (contested storage-amount)
“Under the terms of the CCAA, DTE Electric will, at Customer’s cost, deploy up to 480 megawatts of energy storage capacity and 1,600 megawatts of renewable generation to support its electric service to the Project.”
DTE Energy / DTE Electric 8-K (Mar 17 2026), Item 1.01 · sec.gov - capacity-credits300 MW300 MW of MISO Zone 7 zonal resource credits — accredited capacity, not power — that Google delivers to DTE 'at no cost' (the 8-K) for each MISO season of the 'ZRC Delivery Term', Jun 1 2028 to May 31 2033 (the CCAA). The filed contract names no technology or seller for them (the clauses and the definition around them are partly redacted); Google calls them '300 megawatts of a bilateral, clean resource in partnership with other Michigan utilities' (Huebner, to Nevada legislators). Google receives credits for them, capped at their market revenues, and pays DTE a financial adder on them — 'the ZRCs transferred to the Company multiplied by MISO Cost of New Entry [CONE] multiplied by the Company’s pre-tax weighted average cost of permanent capital' — which DTE asked to book as non-refundable income; the Commission ordered it treated as ordinary income passed through for all ratepayers (E) and declined to dictate the credits' source. A capacity-credit transfer, not a contracted clean-power purchase
““ZRC Product” means MISO Zone 7 Zonal Resource Credits in an amount equal to 300MW.”
DTE Electric–Google Clean Capacity Accelerator Agreement, Exhibit A definitions (DTE 10-Q for Q1 2026, ex. 10.2) · sec.gov - firm-service-level650 MWthe demand-response agreement under DTE's Rider 12, signed the same day and not submitted for approval: when called, Google must cut its load to a firm service level of 650 MW — 65% of the committed capacity during the ramp — from Jun 1 2027 to May 31 2033, with MISO's non-performance penalties passed to Google (Burgdorf). How many megawatts of response that is depends on the baseline (dr-size). ABATE's witness dates the agreement from Jun 1 2028, but the pages he cites (Foley NTF-6; Burgdorf SDB-21 to SDB-23) say June 2027, and the order recites June 2027
“The contract term begins 6/1/2027 and ends 5/31/2033 and requires a firm service level of 650 MW”
DTE's application and direct testimony, MPSC Case U-22058 (Mar 17 2026) — Burgdorf, A40 · openmpsc.com - load-factor90%about 90%: the load factor DTE modeled on Google's own estimate, 7,884 GWh a year on 1,000 MW — DTE's witness Bilyeu, in a discovery answer, corrects the 88.5% in his own testimony's footnote ('stated in error'). A modeling input, not a commitment: the order, with the Staff, says the load DTE assumed for modeling and the 80% minimum bill 'are not connected'.
“The correct load factor corresponding to an annual load of 7,884 GWh is approximately 90%, calculated as 7,884 GWh divided by 8,760 hours.”
DTE discovery response AGDE-2.50b, in MEICEO's official exhibits (MPSC Case U-22058) · openmpsc.com - system-peak11,017 MWthe yardstick: DTE Electric's service-area peak was 11,017 MW in 2025, so Google's 1,000 MW is about 9% of it, and with Oracle's 1,383 MW (pw-dte-oracle) the two contracts come to about 22% (our arithmetic). DTE's 2026 resource plan forecasts the peak at 13,228 MW by 2046, 'mainly due to the large load growth'.
“As shown in Exhibit A-7.1, the service area peak demand in 2021 was 11,358 MW and 2025 peak demand was 11,017 MW, representing a CAGR of -0.8%.”
DTE witness Sirwaitis, direct testimony in DTE's 2026 IRP (MPSC Case U-22168, Sep 24 2026), A49 · openmpsc.com - capacity-gap-2033677 MWthe gap the contracts leave: with Google's load and the resources above, DTE's system is adequate in 2029 but not in 2033, after the capacity credits and the demand response lapse on May 31 2033, and 677 MW of 'perfect capacity' is needed (Brooks's PowerGEM study, Exhibit A-4). DTE priced the fill as a proxy gas plant with carbon capture — 'a new 727 MW CCGT with CCS' in its cost model, 'a nameplate capacity of 646 MW in the Summer Season' in its accreditation comparison (Burgdorf; the two ratings are not reconciled) — whose costs it nets out of its $1.7B claim (affordability) and whose life runs 35 years, with '74% of the cost of this asset' paid off, on a present-value basis, when the contract ends (Burgdorf). The Commission accepted the proxy for the analysis but approves no plant here: 'the ZRCs and the Rider 12 DRA terminate just as the need for additional resources commences', so it ordered DTE to model extending both past May 31 2033 (G). DTE's investor decks: 'additional ~700 MW of longer-term generation will be identified through the IRP process' — planned generation, not the analysis's proxy (dte-capex). One MEICEO question gives '637 MW', which none of the DTE documents on file does, and the ~600 MW in DTE's 2026 resource plan comes from a different study
“To rectify the resource adequacy problem identified in 2033, 677 MW of perfect capacity were required to bring the system back to the threshold of 0.1 LOLE.”
DTE's application and direct testimony, MPSC Case U-22058 (Mar 17 2026) — Exhibit A-4, Brooks (PowerGEM) · openmpsc.com - transmission-upgrade$308MITC's network upgrade — a new 345 kV station into which ITC cuts its Brownstown–Wayne #1 and #2 345 kV lines (MISO) — at about $308M, 'based on initial estimates provided by the Company’s transmission provider' (Burgdorf); MISO lists it as project 51220, 'Current Cost $308M', expected in service Dec 5 2028. ITC recovers it through MISO Schedule 9 from DTE, among others, and DTE passes its share through its fuel-and-power surcharge, Google's bills included; in DTE's 2029 model it is $49.2M of a $91M rise in transmission expense. Separately, DTE builds the distribution upgrades, which it estimates at $29.1M to $44.3M, to connect two distribution substations that Google designs, builds and owns on its site (Benyard). Who ends up paying is contested (who-pays-grid); the Commission ordered annual reports of the actual ITC costs, their recovery and Google's share
“Based on initial estimates provided by the Company’s transmission provider and as discussed by Witness Benyard, the Company expects that approximately $308 million of capital investment by ITC will be needed to upgrade the transmission system to connect the Customer to the electric grid.”
DTE's application and direct testimony, MPSC Case U-22058 (Mar 17 2026) — Burgdorf · openmpsc.com - dte-capex$5BDTE's own capital behind the load: about $5.0B of generation and storage spending through 2032, now inside DTE Electric's five-year plan. The Q1 and Q2 2026 10-Qs called it 'incremental to' that plan; the Q3 10-Q (Nov 5) says it is 'included in DTE Electric's 5-year capital investment plan' — $39 billion for 2027–2031, where the earlier 10-Qs gave $30 billion for 2026–2030 — and that 'DTE Electric secured MPSC approval in the fourth quarter of 2026'. DTE's decks moved with it: Sep 28, 'Google 1.0 GW (upside to plan)', with ~$5 billion that 'could drive' 'incremental' capital investment, footnoted 'Preliminary'; Nov 5, 'Google 1.0 GW (approved and in plan)' and 'Generation and storage requirements drive ~$5 billion capital investment through 2032'. Not all of it is the CCAA's: DTE's chief executive, Joi Harris, tied 'roughly $5 billion of incremental generation and storage investment through 2032' to renewables, storage, demand response 'and additional longer term generation that will be identified through the IRP process' (Q1 2026 call), which DTE's decks size at 'additional ~700 MW'. Google pays the CCAA projects' costs directly; the rest is longer-term generation DTE said it would identify through its resource plan — and the plan it filed Sep 24 2026, whose forecast counts Google's load, proposes two CCS-ready gas plants of about 1,400 MW (2031) and 700 MW (2032). The 10-Qs' paragraphs on it name no customer ('a 1.0 gigawatt data center agreement'); the Q1 10-Q's exhibit index names Google LLC as DTE Electric's counterparty in the two contracts it files (exhibits 10.1 and 10.2)
“In March 2026, DTE Electric entered into a 1.0 gigawatt data center agreement. Generation and storage requirements related to this agreement are expected to increase capital expenditures by approximately $5.0 billion through 2032 which are included in DTE Electric's 5-year capital investment plan in the "Capital Investments" section above. DTE Electric secured MPSC approval in the fourth quarter of 2026.”
DTE Energy / DTE Electric 10-Q for Q3 2026 — MD&A (DTE Electric outlook) · sec.gov
Contested figures 28 not reconciled — every position side by side, with its source and tier
Scope note what this record leaves to other records
Not this record: the campus itself — its developer (Panattoni), site plan, water, jobs, tax abatement and township agreements, which are documented on file but which are not terms between DTE and Google; Google's $10M Energy Impact Fund for Michigan, announced with the deal; DTE's 'nearly $9 billion' from its two data-center contracts through 2045 (its own projection, both contracts together — on the dte entity); DTE's company-wide capital plan, rate cases and 2026 resource plan (Case U-22168). What kind of renewables: the CCAA allows solar or wind; DTE's resource model used solar ('The renewable resources were modeled as 1,600 MW of solar', MEICEO's Hotaling), and Google calls it '1,600 megawatts of solar'. Not adopted: '2,700 MW' of electricity demand for the site (a LinkedIn post reading the resource package as load); '350 gigawatts' for an unrelated behind-the-meter project in DTE's own Q1 transcript (the Motley Fool's copy says megawatts); MEICEO's brief quoting the application as 'including 50 MW of long duration storage' where it says 55 (though DTE's own Burgdorf writes that the 'CCAA specifies approximately 50 MW'); 'Google is paying $50M for transmission upgrades' (GLREA's testimony; the $50M is for distribution); a press '230-acre' site against the ~282 acres the township's development agreement describes.