Why it matters
Google's geothermal deal guarantees 50 , and Ormat's CEO says Ormat can build less than the 150 MW ceiling if other buyers pay more. The fixed $107 per megawatt-hour exceeds NV Energy's long-term avoided costs. Ormat and Google say the tariff passes the cost to Google, but the available record does not show the payment terms.
Tap a figure for the line in its source.
Ormat Technologies gives NV Energy
- disputedof new geothermal capacity, sold as each plant reaches commercial operation, from 2028 — a portfolio of up to six plants in northern Nevada (Baltazor, Whirlwind, Dixie Valley West, McGee, Excelsior and Mason), to which Ormat may add or swap others until the build-out ends, Dec 31 2030 at the latest; where it lands between the floor and the ceiling is Ormat's to choose
- of development security once the commission approves ($1.5M from signing), reduced as each plant starts up, then operating security for every running; NV Energy may claim damages if Ormat terminates or falls short
NV Energy gives
- for the energy and its renewable portfolio credits, fixed with no escalation; NV Energy takes all the net energy and owes nothing for output the grid operator curtails — and nothing at all unless the commission approves → Ormat Technologies
- of the energy and renewable energy benefits, passed to Callisto Enterprises, LLC — the customer NV Energy's filings name, Google in Ormat's — under a separate energy supply agreement through the Clean Transition Tariff, filed for approval on Jun 26 2026; the PPA takes effect only with it → Google
Google gives NV Energy
- the portfolio's cost, by both companies' account — the tariff 'fully covers all costs associated with our electric service', Google says; its rate is in that agreement's filings, which the record could not read
What happened
Ormat Technologies, a Nevada geothermal company, signed a contract with NV Energy, Nevada's utility, to build geothermal plants at up to six northern Nevada sites. The contract calls for at least 50 and at most 150 megawatts. The power is for Google. Ormat will sell their power to NV Energy at a fixed $107 per megawatt-hour. Sales begin when the first plant starts, expected from 2028, and continue until 15 years after construction ends. The buildout must end by Dec 31 2030 at the latest. NV Energy passes all the power and its renewable credits to the customer through the Clean Transition Tariff, a utility pricing arrangement. Google and NV Energy first used it in 2024 for a Fervo geothermal plant. NV Energy's filings name the customer as Callisto Enterprises, and Ormat's name Google. Ormat and Google say Google covers the cost. NV Energy's filing puts that cost above the utility's long-term avoided costs. Ormat and Google lead with 150 megawatts. The contract guarantees 50, and NV Energy studied it as a 50-megawatt project. Ormat's chief executive says the range lets Ormat build less if other buyers pay more. Nevada's utility commission has yet to rule. Ormat expects a ruling at the end of 2026 or early 2027.
Sources 19 documents — 9 company releases · 4 SEC filings · 2 government statements · 2 other documents · 1 regulatory filing · 1 transcript
Research trail Found 90 documents and read 72 of them while checking this deal and related ones.
- States 5 figures: parties · supply amount · development period · term · $107 price
- States 3 figures: at least 50 MW capacity min · facilities · $4.25M security
- States 2 figures: announced · cost cover
- States 2 figures: 100% customer · contingent
- States 2 figures: up to 150 MW capacity max · approval
- States ESA
- States $100 market price
- States up to 150 MW tariff
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: Sierra Pacific–OKGP PPA and its appendices, with NV Energy's testimony and narrative, in the 2026 Joint IRP (PUCN Docket 26-05007; Vols 2, 4, 8, 9, 21 and 41); Ormat's 10-K for 2025 and 10-Qs for Q1 and Q3 2026, its release of Feb 17 2026 (8-K ex-99.1, furnished), Q2 2026 deck and call, and its Lone Mountain tax application; the PUCN's docket list and calendar; Google's testimony to Nevada's legislature (Mar 25 2026) and its CTT posts (Jun 11 2024; May 13 2025); RAP (Nov 2026) for the first CTT agreement (read 2026-11) · as of Nov 2026
The evidence 17 sourced figures · 5 disputes
The record's headline Ormat–Google, Nevada: a portfolio PPA for 50 to 150 of new geothermal plants that Ormat sells NV Energy at a fixed $107/MWh and NV Energy passes to Google through its Clean Transition Tariff — first power from 2028, the build-out done by Dec 31 2030, 15 contract years after that; before Nevada's utility commission, with approval expected at the end of 2026 or early 2027
- Size
- 50–150 MW of new geothermal (the PPA's Development Period Minimum and Maximum Capacity), up to six named plants in northern Nevada, others addable until the build-out ends · $107.00/MWh for energy and portfolio credits, no escalation · first-year supply amount 437,623 MWh (≈50 MW around the clock, our arithmetic) · term from the first plant's commercial operation to 15 Contract Years after the development period ends (Dec 31 2030 at the latest) · development security $1.5M → $4.25M on approval; operating security $294,000 per MW · 100% of the energy and renewable benefits sleeved to Callisto Enterprises, LLC (Google, by Ormat's account) under the Clean Transition Tariff; Google's rate unread
- When
- Jun 11 2024 (Clean Transition Tariff announced by Google and NV Energy, with Fervo's 115 MW) → May 13 2025 (the tariff's first agreement approved) → Jan 29 2026 (the PPA's Effective Date) → Feb 2026 (entered into, by Ormat's filings) → Feb 17 2026 (announced by Ormat) → Mar 25 2026 (Google tells Nevada's legislature) → May 7 2026 (NV Energy's IRP filed with the PPA, Docket 26-05007) → Jun 26 2026 (NV Energy and Callisto's joint application, Docket 26-06023) → Aug 6 2026 (Ormat: Lone Mountain to join) → Nov 5 2026 (Ormat's 10-Q: approval expected end-2026 or early 2027) → Nov 16 2026 (IRP hearing opens) → Jan 26 2027 (continued prehearing conference, Docket 26-06023) → 2028 (first deliveries expected) → Dec 31 2030 (the development period's outside date) → Dec 31 2045 (the term's end if the development period runs to that date)
- Status
- pending before the PUCN: the PPA in NV Energy's IRP (Docket 26-05007, filed May 7 2026; hearing from Nov 16 2026), the Callisto energy supply agreement in its own docket (26-06023, filed Jun 26 2026; continued prehearing conference Jan 26 2027). Ormat expected approval 'in the second half of 2026' (Feb 2026) and now 'at the end of 2026 or early 2027' (Q3 10-Q, Nov 5 2026). The PPA's PUCN Approval Deadline is 270 days after NV Energy's filing — about Feb 1 2027 if that is the IRP of May 7 2026 (our count) — after which NV Energy may end it without liability. No plant is in commercial operation; four of the six have signed interconnection agreements and two have finished cluster studies (Vol 21). Ormat said in Aug 2026 that Lone Mountain will join the portfolio (contested lone-mountain)
- Structure
- a Long-Term Renewable Portfolio Power Purchase Agreement, effective Jan 29 2026, between Sierra Pacific Power Company d/b/a NV Energy (Buyer, in its merchant function) and OKGP LLC (Supplier), a Delaware subsidiary of Ormat Nevada, Inc. — filed in NV Energy's 2026 Joint IRP (Technical Appendix REN-15-NGP, Vol 21; PUCN Docket 26-05007), whose approval order is the PUCN Approval it needs (§16.2) — and beside it the 'Callisto Energy II ESA', an energy supply agreement between NV Energy and Callisto Enterprises, LLC under the Clean Transition Tariff, filed for approval on Jun 26 2026 (Docket 26-06023): the PPA is sleeved through it, Callisto receiving 100% of the energy and renewable energy benefits, and takes effect only once it does (§2.1). Each plant (a Facility, on land Ormat has leased) sells from its own commercial operation; together they form one Project, whose capacity must reach 50 MW and may not exceed 150 MW by the end of the development period, and Ormat may designate further greenfield plants on NV Energy's grid, binding six months after notice, without changing those bounds or dates (§8.12.1)
- Programme
- Time-to-power
- Parties
- Ormat Technologies seller — OKGP LLC, a subsidiary of Ormat Nevada, Inc., which develops, builds and runs the plants on land Ormat has leased, sells their net energy and portfolio credits to NV Energy at $107/MWh, and posts development and operating security · NV Energy buyer and utility — Sierra Pacific Power Company d/b/a NV Energy, which buys all the net energy under the PPA and passes 100% of the energy and renewable energy benefits to Callisto under the Clean Transition Tariff · Google customer — Callisto Enterprises, LLC in NV Energy's filings, Google in Ormat's and in Google's own account of the deal; it brought the project to NV Energy 'as a dedicated resource to serve their load', takes all its energy and renewable benefits through the tariff and, by its own account, covers the cost
- Record
- disclosed / primary source · as of Nov 2026
Flows 5 as the record states them
- Ormat Technologies → NV Energypowerthe net energy and portfolio credits of 50 to 150 MW of new geothermal plants, each from its commercial operation (from 2028) through the Term — a first-year supply amount of 437,623 MWh, at most 60.8 MWh in any hour for the six named plants
- NV Energy → Ormat Technologiesppa-payments$107.00/MWh for energy and portfolio credits, fixed with no escalation, for the Term; nothing for transmission-curtailed output, and no payment owed unless the PUCN approves (§2.2)
- NV Energy → Googlepower100% of the portfolio's energy and renewable energy benefits, sleeved to Callisto Enterprises, LLC under the Callisto Energy II ESA through the Clean Transition Tariff
- Google → NV Energyctt-paymentsthe charges of the Callisto Energy II ESA under the Clean Transition Tariff — by Google's account covering 'all costs associated with our electric service'; the rate is in Docket 26-06023's filings, unread (image scans)
- Ormat Technologies → NV Energysecuritydevelopment security of $1.5M from signing and $4.25M from PUCN approval to the end of the build-out, reduced by $85 per kW of each plant that starts up; then operating security of $294,000 per MW of the Project Capacity running; damages for termination or production shortfalls
Resolved figures 17 each with the verbatim line from its document
- announcedannounced by Ormat on Feb 17 2026 (its release, furnished as an 8-K exhibit, with a statement from Google's Briana Kobor, Head of Energy Market Innovation) — the first public word of the deal on file. It said the PUCN's approval was 'expected in the second half of 2026' and the projects were 'expected to come online from 2028 to 2030'. Ormat's 10-K for 2025, filed later that month, carries the same paragraph, the first periodic-report disclosure (Ormat's 10-Qs repeat it). A furnished release; the filed 10-Q names Google too (capacity-max)
“Ormat Technologies Inc. (NYSE:ORA) (the “Company” or “Ormat”), a leading geothermal and renewable energy company, today announced that it has entered into a long-term geothermal Power Purchase Agreement (PPA) with NV Energy to support Google’s operations in Nevada with up to 150MW of new geothermal capacity.”
Ormat release (8-K ex-99.1, furnished Feb 17 2026) · sec.gov - partiesthe paper: a Long-Term Renewable Portfolio Power Purchase Agreement between Sierra Pacific Power Company d/b/a NV Energy, as Buyer, and OKGP LLC, as Supplier — a Delaware company that NV Energy's appendix calls 'a subsidiary of Ormat, Nevada Inc.' — made 'as of January 29, 2026'. Ormat says it entered into the PPA in February 2026 (contested signing-date). Filed redacted as Technical Appendix REN-15-NGP(a) of NV Energy's 2026 Joint IRP, with its due diligence, NAC-NRS compliance and key-provisions appendices (Vol 21). Google is not a party to the PPA: it takes the output through a separate energy supply agreement with NV Energy (customer)
“This Long-Term Renewable Portfolio Power Purchase Agreement (this “Agreement”) is made and entered into as of January 29, 2026 (the “Effective Date”) by and between SIERRA PACIFIC POWER COMPANY, a Nevada corporation, d/b/a NV Energy acting in its merchant function capacity (“Buyer”), and OKGP LLC, a Delaware limited liability company (“Supplier”).”
Sierra Pacific–OKGP PPA, preamble (NV Energy 2026 IRP, Vol 21, REN-15-NGP(a)) · nvenergy.com - customer100%who the power is for: NV Energy names Callisto Enterprises, LLC, which 'will receive 100% of the energy and renewable energy benefits' and brought the project 'as a dedicated resource to serve their load' — it was not bid into NV Energy's 2024 RFP (Vol 8), and 'because the PPA is part of a sleeved customer agreement with Callisto Enterprises, LLC, pricing was not a deciding factor in the bilateral negotiations' (Vol 4). Ormat's filings and release, and Google's own statements (tariff, cost-cover), name Google; no text the record reads says in so many words that Callisto is Google's, but Callisto is the party to both of NV Energy's energy supply agreements of this kind on the PUCN's docket list — 24-06014 (Jun 10 2024), the agreement for Fervo's plant that Google announced that month and that RAP cites as Google's, and 26-06023 (esa) — so the record reads Callisto as Google, as Ormat's filings do
“The PPA is being sleeved through customer agreement for Callisto Enterprises, LLC (“Callisto”), who will receive 100% of the energy and renewable energy benefits from the project.”
NV Energy 2026 IRP, Vol 4 — Spitzer direct testimony, Q57 · nvenergy.com - esaGoogle's side of the deal, the 'Callisto Energy II ESA' (PPA §1.23: an Energy Supply Agreement for the energy, 'dated on or about the Effective Date'), went to the PUCN on Jun 26 2026 as a joint application of NV Energy and Callisto, Docket 26-06023 — 'in a separate docket at the same time as this 2026 Joint IRP filing', as NV Energy's testimony expected. Its continued prehearing conference is set for Jan 26 2027 (the PUCN's calendar). Five of its filings — described, unverified, as the joint application, a staff economist's testimony, NV Energy's rebuttal, a procedural order and an intervenor's opposition — are on file, and all five are image scans with no text, so their contents are unread: Google's rate, what the staff and the intervenor argue, and the docket's schedule beyond the calendar are not in this record
“26-06023 06/26/2026 Joint Application of Sierra Pacific Power Company d/b/a NV Energy and Callisto Enterprises LLC for approval of an Energy Supply Agreement.”
PUCN docket list (read Nov 2026) · pucweb1.state.nv.us - contingentthe PPA hangs on Google's agreement: it 'shall become effective on the later of' its Effective Date and the date the Callisto Energy II ESA 'has been fully executed by the parties thereto and all conditions to its effectiveness have been satisfied or waived' (§2.1), and NV Energy may end it 'without payment or penalty or liability of any kind to either Party' if that has not happened 60 days after the last condition precedent to the ESA is finally disposed of (§2.3.4); NV Energy's narrative: 'in the event of non-receipt of PUCN approval of the customer agreement, then the PPA may be terminated with no liability to either party' (Vol 8)
“In addition to the requisite approval from the Commission, the PPA is not effective until all conditions to the effectiveness of the customer agreement between Sierra and Callisto, have been satisfied.”
NV Energy 2026 IRP, Vol 4 — Spitzer direct testimony, Q58 · nvenergy.com - capacity-maxup to 150 MWup to 150 MW — the PPA's Development Period Maximum Capacity (§1.55: 'one hundred fifty (150) MW'), the figure Ormat's filings, its release and Google lead with. Only new plants: 'it covers only new projects' (Ormat's chief executive, in an interview). The schedule as Ormat files it: deliveries 'anticipated to commence between 2028 and 2030 as projects reach commercial operations'. Ormat counts the deal at its ceiling — 'up to 150 MW under the Google portfolio agreement' in its ~200 MW of 2026 geothermal PPAs (Q2 2026 deck). What will be built is contested (expected-size)
“In February 2026, we entered into a long-term geothermal portfolio PPA to supply up to 150MW of new geothermal capacity to support Google’s data center energy needs, through NV Energy’s Clean Transition Tariff program.”
Ormat 10-Q for Q3 2026 (Nov 5 2026) — MD&A, recent developments · sec.gov - capacity-minat least 50 MWat least 50 MW: the PPA's Development Period Minimum Capacity and its Guaranteed Minimum Project Capacity are both 'fifty (50) MW' (§1.56, §1.86); if the plants running at the end of the development period total less, Ormat pays daily delay damages on the shortfall for up to 180 days, after which NV Energy may terminate (§8.5.1), and whatever capacity is then running becomes the Project Capacity for the rest of the Term (§8.5.2). NV Energy's IRP carries the deal as 'A 50 MW geothermal project associated with a customer agreement' (Vol 2) and studied it at 50 MW, the up-to-150 MW provision 'not captured in the economic analysis' (Vol 9). Ormat's filings and release give no minimum; its chief executive spoke of 'the minimum and maximum targets in the portfolio' (Q2 2026 call)
“The portfolio will allow for a minimum of 50 MW and up to 150 MW of geothermal resources, with an expected COD of December 31, 2030.”
NV Energy 2026 IRP, Vol 8 — Supply Plan narrative, Renewables, Nevada Geothermal Portfolio (OKGP) · nvenergy.com - facilitiesthe plants: up to six, each 'designed to deliver approximately 7 MW of net geothermal generating capacity' on Ormat's binary OEC units, all fluids reinjected, on land where Ormat holds geothermal leases (Vol 8) — Baltazor and McGee in Humboldt County, Whirlwind in Lander, Dixie Valley West in Churchill, Excelsior in Esmeralda and Mineral, Mason in Lyon; none in commercial operation. Baltazor and McGee have executed interconnection agreements 'within HEC territory', Mason and Whirlwind with Sierra, and Dixie Valley West and Excelsior have completed cluster studies (Vol 21). Ormat may designate further greenfield plants on NV Energy's grid before the development period ends — binding six months after notice, 'without requiring an amendment of this Agreement' — and the minimum, maximum and dates do not change (§8.12.1). Their sizes differ across the filing (expected-size); whether Lone Mountain has joined is contested (lone-mountain)
“The Nevada Geothermal Portfolio (OKGP) includes up to six geothermal generation facilities, as follows: Baltazor, Whirlwind, Dixie Valley West, McGee, Excelsior, and Mason.”
NV Energy 2026 IRP, Vol 8 — Supply Plan narrative, Key Project Characteristics · nvenergy.com - supply-amount437,623the energy schedule: 437,623 MWh in the first Contract Year (Exhibit 13) — about 50 MW around the clock (437,623 ÷ 8,760 ≈ 49.96 MW, our arithmetic), the PPA's floor; the Yearly PC Amount equals it (Exhibit 18). At most 60.8 MWh in any Delivery Hour for all six plants (the Delivery Point Maximum Amount, Exhibit 13), which the PPA's definitions instead set at the Project Capacity for the hour × 1.65 — the two are not reconciled in the filing. After the build-out Ormat may cut the Average Annual Supply Amount, once a year, to no less than 85% of its level at the end of the development period (supply degradation)
“Yearly Supply Amount (Contract Year 1) 437,623 MWh [Exhibit 13]”
NV Energy 2026 IRP, Vol 21 — REN-15-NGP(d), Key Provisions · nvenergy.com - development-periodthe build-out window: plants join the portfolio as they reach commercial operation until the Development Period Completion Date — the earlier of Ormat's notice that it will add no more and Dec 31 2030. NV Energy: the portfolio 'is required to reach commercial operation on or before December 31, 2030', each plant with its own commercial operation date (Vol 21); Ormat: projects added 'beginning as early as 2028 and expected to continue through 2030' (its release); its chief executive: 'Right now, it runs through the close of 2030' (Feb 2026 call)
““Development Period Completion Date” means the earlier of (a) the date on which Supplier provides written notice to Buyer that Supplier will not declare Commercial Operation for any additional Facilities, and (b) December 31, 2030.”
Sierra Pacific–OKGP PPA, §1.54 (NV Energy 2026 IRP, Vol 21) · nvenergy.com - term15 yearsthe PPA's clause: the Term runs from the first plant's commercial operation to 15 Contract Years after the Development Period Completion Date, each plant delivering from its own Operation Date — so up to about two more years of deliveries before the 15, if the first plant starts in 2028 (our arithmetic) — and NV Energy owes nothing for any Product unless the PUCN approves. NV Energy's own summaries: 'a 15‑year term following completion of the project development period' (Vol 8); 'the contract term extends for 15 Contract Years following completion of the Development Period' (Vol 21); 'the term of the PPA is 15 years' (Vol 4). How Ormat words it, and the end date, are contested (term-end)
“The Term shall commence on the First COD and shall continue for a period of fifteen (15) Contract Years after the Development Period Completion Date, subject to earlier termination of this Agreement pursuant to the terms hereof (the “Term”)”
Sierra Pacific–OKGP PPA, §2.2 (NV Energy 2026 IRP, Vol 21) · nvenergy.com - price$107$107.00/MWh for energy and portfolio credits, flat — 'The Product Rate (for each of the six (6) geothermal projects) ... shall be $107 per MWh' (key provisions); Vol 4: 'fixed at $107.00 per MWh for the 15-year term'. Provisional energy earns 75% of it, and test energy and energy above the supply schedule the lesser of 50% and the Mead price (§4.1); output NV Energy itself curtails for economic reasons is paid at the rate, plus the lost production tax credit during the PTC Period (§4.1.2.2); NV Energy 'has no obligation to pay for transmission-provider curtailed product or for generation in excess of the contractual Maximum Amount'. Above NV Energy's own costs: 'the blended rate for energy and PCs is greater than the annualized average long-term avoided costs in years 2030 through 2050' (Vol 21). Ormat calls it 'above $100/MWh' (its decks) and does not state the figure. Its 'calculated cost' is contested in the same appendix (calculated-cost). The rate does not move if Ormat's tax credits fail or lapse: it bears that risk (§4.3). What Google pays NV Energy is a different number, unread (esa)
“The price for renewable energy and PCs set forth in this contract is $107.00 MWh with no escalation for the 15-year term of the contract.”
NV Energy 2026 IRP, Vol 21 — REN-15-NGP(c), NAC-NRS Compliance · nvenergy.com - market-price$100the price beside Ormat's older contracts: new and renewed US geothermal PPAs 'above $100 per MWh', against $60–$80 'during the prior five years' (Ormat's FY2025 10-K); Ormat's decks list this deal as 'up to 150 MW Portfolio PPA with 15-Year above $100/MWh'. Ormat's chief executive: 'Today every PPA we sign is above $100' (interview), and its range lets Ormat 'in case pricing goes up, to go to the lower level' (Q2 2026 call; expected-size)
“and for existing capacity renewal across its U.S. geothermal fleet at prices above $100 per MWh, compared to PPAs executed at levels generally between $60 per MWh and $80 per MWh during the prior five years.”
Ormat 10-K for 2025 — Increased PPA Prices in the U.S. · sec.gov - tariffup to 150 MWup to 150 MW, in Google's own words — the same ceiling as capacity-max, not a second figure: Google's Tyler Huebner told Nevada's legislature that, working with Ormat, 'our power purchase agreement will enable up to 150 megawatts of new capacity from 2028 through 2030', one of what he called 'three new CTT deals'. The mechanism it runs through: NV Energy's Clean Transition Tariff, which Google launched with NV Energy on Jun 11 2024 ('a new clean transition rate — also referred to as a “Clean Transition Tariff” (CTT)'), its first agreement — 115 MW of Fervo's enhanced geothermal power — approved by the PUCN on May 13 2025 (Google's posts). Of Fervo's plant, Huebner said that 'NV Energy, through the Clean Transition Tariff, can basically send all of those costs directly to Google'. Ormat's release: the tariff lets 'large energy users like Google' invest in clean electricity 'while fully covering all costs associated with their electric service'. Fervo's own release (Sep 1 2026) says its 2024 PPA 'helped pioneer' it
“In Nevada, we announced another advanced geothermal project in February. Working with Ormat Technologies, our power purchase agreement will enable up to 150 megawatts of new capacity from 2028 through 2030.”
Nevada Legislature, Joint Interim Standing Committee, Mar 25 2026 — draft minutes, Google's Tyler Huebner · leg.state.nv.us - cost-coverwho pays, in Google's words: the tariff 'fully covers all costs associated with our electric service' and 'insulates other ratepayers' (Kobor, in Ormat's release); Huebner, of the first CTT deal: 'Google bears all premium costs of this technology, fully protecting other ratepayers' (Nevada legislature). The amount is not stated anywhere the record reads: Google's charges are set in the Callisto Energy II ESA (esa), unread. RAP's reading of the first agreement, for Fervo's plant: Google pays 'a premium, fixed price for energy provided by the Fervo facility based on the rate provided in the purchased power agreement', NV Energy buys any excess at avoided cost, and Google pays bundled rates for grid power — not checked against this one. A furnished release
“By adding up to 150MW of new clean-firm geothermal capacity in Nevada, we are utilizing a repeatable framework that fully covers all costs associated with our electric service, ensuring the CTT insulates other ratepayers while strengthening the reliability of the local power system.”
Ormat release (8-K ex-99.1, furnished Feb 17 2026) — Briana Kobor, Google · sec.gov - security$4.25Mwhat Ormat puts up: $1.5M of development security (letter of credit or cash) within five business days of the Effective Date, $4.25M from the PUCN's approval to the end of the development period, reduced by $85 per kW of each plant reaching commercial operation, never below $0; then operating security of $294,000 per MW of the Project Capacity in operation — about $14.7M at 50 MW and $44.1M at 150 MW (our arithmetic) — from five business days before the first plant's start (Vol 21, key provisions). NV Energy may 'collect damages due to termination or production shortfalls' (Vol 4)
“Specifically, the developer is required to post $1.5 million in development security upon execution of the PPA, which increases to $4.25 million upon receipt of PUCN approval of the PPA.”
NV Energy 2026 IRP, Vol 8 — Supply Plan narrative, Nevada Geothermal Portfolio (OKGP) · nvenergy.com - approvalpending, and later than first said: 'expected in the second half of 2026' (Ormat's release, Feb 17 2026, and its 10-K and Q1 10-Q) → 'at the end of 2026 or early 2027' (its Q3 10-Q, Nov 5 2026) — one filer's dated series, not a disagreement. The PPA's approval is the PUCN's order on NV Energy's IRP (§16.2: a final order on the IRP approving the PPA's terms as just and reasonable and its costs as prudent), Docket 26-05007, filed May 7 2026, its hearing set for Nov 16 and 17 2026 (the PUCN's calendar); Google's agreement is in Docket 26-06023 (esa). The PUCN Approval Deadline is 270 days after NV Energy's regulatory filing (§1.162) — about Feb 1 2027 if that filing is the IRP of May 7 2026 (our count; the PPA does not date it); if approval has not come by then, or comes in a form NV Energy will not accept, NV Energy may terminate within 30 days with no liability to either side (§16.3)
“The agreement and related energy supply arrangements are subject to approval by the Nevada PUC, at the end of 2026 or early 2027.”
Ormat 10-Q for Q3 2026 (Nov 5 2026) — MD&A, recent developments · sec.gov
Contested figures 14 not reconciled — every position side by side, with its source and tier
Scope note what this record leaves to other records
Not this record: Ormat as a company — its generating portfolio (1,853 MW, 1,358 MW of it geothermal and solar, at Nov 4 2026, with the dated series behind it and the 1.6–1.8 GW totals of its filings), 2028 and later targets, fleet prices ($92.6/MWh in 2025; the ~$86/MWh of its 2031–2034 recontracting book; Prime Movers Lab's $78 and the Analyst Day's $68), capex plans, debt, liquidity, EGS program and acreage (Enverus's ~182,000 federal acres against its own ~170,000 acres of EGS potential), NV Energy's share of its revenue — on the ormat entity or not carried here; its other 2026 contracts — Switch's 20-year, ~13 MW Salt Wells PPA (its optional solar ~17 MW in filings, ~7 MW in a deck), the Jersey Valley solar and battery PPA with NV Energy (its battery price $13,950 against $18,950/MW-month across the IRP's volumes), the NGP Blue Mountain Third Amendment ($105/MWh, through 2046; the plant 20, 22, 30 or 49.5 MW by measure) and two blend-and-extend contracts; the older 120 MW Ormat Western Geothermal Portfolio (two plants cancelled, Lone Mountain delayed); Lone Mountain's own schedule (end-2027 to Oct 2028 across Ormat's decks, its tax application, fiscal note, testimony and NV Energy's plan), its Nevada tax abatement ($18,375,826 over 20 years), capital figure ($178,446,043 in the order, $178,450,621 of taxable value in the fiscal note), 37-mile line and injection permits — a plant, not a term of this deal (lone-mountain); NV Energy's other sleeved portfolio, the 100 MW North Nevada Geothermal Portfolio for another customer agreement (Vol 2), which Prime Movers Lab attributes to Zanskar and Amazon, and its solar and battery projects for Amazon; NV Energy's load forecasts and data-center inquiries; Fervo–Google — the 115 MW Corsac Station agreement under the first CTT and the 396 MW Cape Station PPA in Utah — its own record. Not adopted: Reuters via The Star printing Ormat's share price as '$1243.54' on Feb 17 (about ten times the €104.50 Stuttgart close the next day: read here as a misprint); the IRP's '150 MW of geothermal projects' across its sleeved PPAs (Vol 6), which is this deal at its 50 MW study size plus North Nevada's 100 MW (Vol 2's two figures, our reading), not this deal's 150; Prime Movers Lab's '$107.00 a megawatt-hour, flat for 15 years', which is Fervo's Corsac contract, not this one; the Analyst Day's '6 sites in 2 states', which are EGS interconnection requests, not these six plants; LBNL's $1M-a-year Google contribution, which is Minnesota Power's contract; and the 150 MW headlines that drop the 'up to' (expected-size).