Why it matters
The financing for an Oracle campus shifted to bonds after bank lenders balked at the size of the construction loan. PIMCO anchored the 7.5% bonds due in 2045. Oracle's rent and guarantee back the bonds, and Fitch says an Oracle downgrade could pull their rating down too.
Tap a figure for the line in its source.
Blackstone gives Related Digital
- equity, alongside Related Digital's own, in the venture that owns the campus — through BREP, Blackstone's family of real-estate funds; no party gives the amount
Lenders & bondholders gives Related Digital
- of 7.5% senior secured bonds due Mar 2045, sold at 98.75 cents on the dollar; PIMCO-managed funds were the biggest buyer
Oracle gives Related Digital
- rent on the whole campus under four triple-net leases, guaranteed by Oracle Corporation; the rent is not disclosed
Related Digital gives Oracle
- campus of three data-center buildings and a core, for Oracle to fill for OpenAI; Oracle expects to start delivering to its customer in 2H27
What happened
Related Digital is building a campus of three single-story data-center buildings in Saline Township, Michigan. It is the data-center arm of the developer Related Companies. Oracle has leased the entire campus for its work for OpenAI. The $16 billion financing closed on April 30, 2026. Related and Blackstone real-estate funds provided equity. Funds managed by PIMCO anchored the $14 billion issue of 7.5% bonds due in 2045. The original plan called for a bank construction loan, but some lenders worried about its size. That led Bank of America, the deal arranger, to turn to PIMCO and long-term bonds in January 2026. Oracle's rent repays the bonds, and their credit rating moves with Oracle's. The bonds sold at 98.75 cents on the dollar and were trading at about 91 by late September 2026.
Sources 38 documents — 12 other documents · 10 press reports · 4 company releases · 4 law-firm notes · 4 research notes · 2 SEC filings · 2 government statements
Research trail Found 446 documents and read 425 of them while checking this deal and related ones.
- States 2 figures: $16B financing · jobs county
- States 2 figures: 974 MW issuer lease · construction support
- States closing
- States $14B notes
- States 7.5% coupon maturity
- States sponsors
- States pimco anchor
- States pimco filed holding
- States 4.5 GW program
- States jobs onsite
- States progress
- States bank to bond
- States issue price
- States secondary price
- States lease term
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: Related Digital/Blackstone release (Apr 24 2026) + Aug 27 2026 release; Kirkland, Gibson Dunn, Paul Hastings, Greenberg Traurig and Simpson Thacher deal notes; KBRA preliminary and final ratings; Fitch disclosure form; Blackstone Q2-2026 presentation (furnished); PIMCO Income Fund N-PORT; NJ PFRS trade file; BofA via BNEF; Bloomberg, Reuters, the FT, MNI, OCBC, Octus, Bommarito, CNBC via Planet Detroit and Epoch for the contested cells (read 2026-10) · as of Sep 2026
The evidence 17 sourced figures · 11 disputes
The record's headline Saline Township, MI: Related Digital and Blackstone's $16B campus for Oracle, financed with $14B of 7.5% bonds anchored by PIMCO instead of a bank construction loan — closed Apr 30 2026; the notes, issued at 98.75, traded at 91.41 by late September
- Size
- $16B campus financing · $14B of 7.5% senior secured notes due Mar 30 2045, issued at 98.75 (≈$13.8B of proceeds) · equity from Related Digital and BREP, unsized by any party (~$2B by Bloomberg's sources) · 974 MW (KBRA) / 'more than a gigawatt' (sponsors)
- When
- Oct 30 2025 (site announced) → Dec 2025 (Blue Owl out; Blackstone in equity talks) → early Jan 2026 (bank loan → bonds with PIMCO) → Apr 24 2026 (financing announced; notes priced) → Apr 30 2026 (closed) → Sep 28 2026 (notes at 91.41)
- Status
- financing closed Apr 30 2026; under construction ('More than 1,800 skilled tradespeople', Aug 27 2026); substantial completions expected Dec 2026–Jan 2028 (KBRA), Oracle's customer delivery from 2H27; notes rated BBB (KBRA, Fitch) and Baa3 (Moody's, as relayed by Octus and Bommarito; its own action is not on file), trading at 91.41 on Sep 28 2026
- Structure
- a joint venture of Related Digital and Blackstone real-estate funds (BREP) owns RD Michigan Property Owner I LLC, a special-purpose issuer that sold $14B of Rule 144A senior secured notes anchored by PIMCO-managed funds and leases the whole campus to Oracle America Cloud Services LLC (the renamed Green Chile Ventures LLC) under four triple-net leases guaranteed by Oracle Corporation; Walbridge Aldinger builds under a guaranteed maximum price, with a limited construction guaranty from The Related Companies, L.P.; DTE Electric powers the campus under its own contracts with the same Oracle subsidiary (pw-dte-oracle); Oracle fills it for OpenAI (sg-oai-orcl)
- Programme
- Stargate
- Parties
- Related Digital developer and co-owner — Related Digital (founded by Related Companies) formed the joint venture with Blackstone's funds; it stands here for the venture and its issuer, RD Michigan Property Owner I LLC; The Related Companies, L.P. gives a limited guaranty during construction (KBRA) · Blackstone equity co-owner — 'a BREP investment in a joint venture with Related Digital' (its Q2-2026 presentation); the amount is not disclosed · Oracle tenant of the whole campus through Oracle America Cloud Services LLC, on four triple-net leases guaranteed by Oracle Corporation; the campus is developed for its partnership with OpenAI · Lenders & bondholders bondholders — the $14B of 7.5% senior secured notes due 2045, anchored by PIMCO-managed funds
- Record
- disclosed / primary source · as of Sep 2026
Flows 4 as the record states them
- Blackstone → Related Digitaljvequity into the joint venture that owns the issuer, alongside Related Digital's — 'a BREP investment' (Blackstone's Q2-2026 presentation), unsized by any party; about $2B by Bloomberg's sources, read as Blackstone's alone or as both sponsors' (contested equity)
- Lenders & bondholders → Related Digitaldebt$14B of 7.5% senior secured notes due Mar 30 2045 (Rule 144A), issued at 98.75 — about $13.8B of proceeds, our arithmetic — anchored by PIMCO-managed funds, the biggest buyer (about $10B by Bloomberg's and the FT's sources), the rest other institutional investors
- Oracle → Related Digitallease-paymentsrent on the whole campus under four triple-net leases guaranteed by Oracle Corporation, with a date-certain rent start (KBRA) and a 17.5-year initial term plus two 10-year options (MNI); the rent is undisclosed — it is what repays the notes, which fully amortize within the initial term (MNI)
- Related Digital → Oraclecapacity974 MW campus (KBRA) — three single-story data-center buildings and a core building — delivered in stages, substantial completions Dec 2026–Jan 2028 (KBRA); powered by DTE (pw-dte-oracle)
Resolved figures 17 each with the verbatim line from its document
- financing$16B$16B — the sponsors' own figure, announced Apr 24 2026 as 'financing has been secured for Related Digital's $16 billion data center campus': 'equity from Related Digital and funds affiliated with Blackstone, and fixed-rate, long term debt financing anchored by PIMCO-managed funds and accounts', with Bank of America as structuring agent and financial advisor and Goldman Sachs and Wells Fargo also advising Related. The release said the closing was 'subject to the satisfaction of customary closing conditions' (closing). The $16B is the campus, not the equipment Oracle puts in it (contested all-in-cost). The press had the figure three weeks before the release, from sources — Reuters, Apr 1 2026: Related Digital 'is closing in on $16 billion of financing', 'a source familiar with the matter said' (Bloomberg the same day) — and has repeated the release since; the one itemized sources and uses on file is Moody's, $15.975B of total uses, seen second-hand (contested total-financing). sg-oai-orcl's saline-value cites the same release (Blackstone's copy)
“Related Digital, a vertically integrated data center development and investment platform, and Blackstone (NYSE: BX) announced today that financing has been secured for Related Digital's $16 billion data center campus in Saline Township, Michigan, purpose-built for Oracle.”
Related Digital/Blackstone release, Apr 24 2026 · related.com - closingclosed Apr 30 2026 — Gibson Dunn, Related Digital's counsel on 'the formation of a joint venture with funds affiliated with Blackstone' (May 4 2026); Kirkland, its counsel on the lease and the financing, the same day: 'The financing, which closed today' (Apr 30). Six days after the Apr 24 announcement, whose closing was still 'subject to the satisfaction of customary closing conditions'; Bloomberg's Apr 8 terms had expected Apr 17
“The transaction closed on April 30, 2026.”
Gibson Dunn firm news, May 4 2026; Kirkland release, Apr 30 2026 · gibsondunn.com - notes$14B$14B of 7.500% senior secured notes due 2045, issued by RD Michigan Property Owner I LLC — 'owned by a joint venture between Related Digital and Blackstone' — and bought by BofA Securities, Goldman Sachs, Wells Fargo Securities and Crédit Agricole as initial purchasers for resale (Paul Hastings, their counsel). A Rule 144A private placement — 'they can only be bought by large institutional investors' (Bloomberg) — so the issuer files nothing with the SEC. Gibson Dunn, which lists PIMCO as 'the anchor investor' on the same offering, gives identical terms; Greenberg Traurig, also for PIMCO, calls it 'a $14 billion private-debt package'. The notes fund construction and the long term at once: there is no bank construction loan to refinance (bank-to-bond)
“Paul Hastings LLP advised Bank of America Securities, Goldman Sachs & Co., Wells Fargo Securities and Credit Agricole Securities in connection with the offering of $14 billion of 7.500% senior secured notes due 2045 by RD Michigan Property Owner I LLC, owned by a joint venture between Related Digital and Blackstone”
Paul Hastings release (counsel to the initial purchasers), May 5 2026 · paulhastings.com - coupon-maturity7.5%7.5% coupon, final maturity Mar 30 2045, CUSIP 74941YAA0, rated BBB with a Stable Outlook — Fitch's Dodd-Frank disclosure for its final rating (May 1 2026). The same coupon, date and CUSIP appear in SEC-filed fund holdings, PIMCO's under the name 'Road Michigan Property Owner I LLC' (pimco-filed-holding), so the instrument is on file even though the issuer is not. Fitch's first downgrade trigger: 'A downgrade of Oracle Corporation's rating could lead to a similar rating action for RD Michigan' — the notes are rated as Oracle's lease. KBRA: BBB (preliminary Apr 24, final May 1 2026); Moody's: Baa3, negative outlook, by Bommarito's draft review, and 'rated BBB/Baa3' by Octus — Moody's own action is not on file
“USD 14 bln 7.5% bond/note 30-Mar-2045 74941YAA0 New Rating Long Term Rating BBB/Rating Outlook Stable”
Fitch Dodd-Frank rating information disclosure form (final rating, May 1 2026) · assets.fitchratings.com - issuer-lease974 MWwhat the notes finance and what repays them, by KBRA's final rating (May 1 2026): a special-purpose issuer formed by Related Digital and Blackstone to build 'a 974MW data center campus' of four buildings — a core and three compute buildings — 'fully leased under four triple-net-leases (NNN) to Oracle America Cloud Services LLC, guaranteed by Oracle Corporation'. Oracle America Cloud Services is the renamed Green Chile Ventures LLC, the customer on DTE's power contracts (pw-dte-oracle). KBRA: each lease has a date-certain rent commencement, 'limited termination rights and rent abatement opportunities', and the tenant bears all operating costs; assignment to an Oracle affiliate needs no consent. The 974 MW is KBRA's campus figure (critical IT, by Moody's breakdown as relayed — contested capacity); the sponsors say 'more than a gigawatt', DTE contracts 1,383 MW
“Related Digital and Blackstone (the sponsors) have formed the special-purpose entity RD Michigan Property Owner I LLC (the issuer) to finance the construction of a 974MW data center campus in Washtenaw County, Michigan, consisting of four buildings: the Core (Building 1), Compute 1 (Building 2), Compute 2 (Building 3), and Compute 3(Building 4). The campus is fully leased under four triple-net-leases (NNN) to Oracle America Cloud Services LLC, guaranteed by Oracle Corporation.”
KBRA final rating, May 1 2026 · privatecredit.kbra.com - construction-supportwhat stands behind the bondholders until the buildings are done (KBRA): Walbridge Aldinger builds under a guaranteed maximum price; The Related Companies, L.P. gives 'a limited parent guaranty' during construction; rent starts on a fixed date ('a date certain rent commencement'), and the tenant has no option to terminate for late delivery. KBRA puts total contingency at 'approximately 12.4% of the project budget' and a replacement contractor at 7%–13% of the GMP; MNI's '4% budgeted cost contingency' sits beside the GMP, a different scope nothing on file reconciles. KBRA: a downgrade could come 'if construction does not progress according to schedule'
“However, the project benefits from a limited parent guaranty from The Related Companies, L.P. during construction, a date certain rent commencement, no termination option for late delivery afforded to the tenant, and substantial schedule cushion relative to the expected lease timeline.”
KBRA final rating, May 1 2026 · privatecredit.kbra.com - sponsorsthe equity side, in Blackstone's own words: its real-estate segment's capital deployed in Q2 2026 included 'a BREP investment in a joint venture with Related Digital to develop a data center campus in Michigan' — BREP being the fund family the same presentation lists under Real Estate. No amount for the venture (the $5.8B is the segment's whole quarter, France included). An earnings presentation furnished as an 8-K exhibit. Gibson Dunn: 'the formation of a joint venture with funds affiliated with Blackstone'; Blackstone Real Estate's global head of digital infrastructure is quoted in the parties' Aug 2026 release (progress). How much equity, and how it splits — 90% Blackstone-affiliated funds / 10% Related Digital by Moody's, as relayed — is contested (equity)
“Capital Deployed: $5.8 billion in the quarter, including a BREP investment in a joint venture with Related Digital to develop a data center campus in Michigan and a BREP investment in a large logistics platform in France, and $21.9 billion over the LTM.”
Blackstone Q2-2026 earnings presentation (8-K ex-99.1, furnished) · sec.gov - bank-to-bondhow the debt was raised, in the arranger's own account (Karen Fang, BofA's global head of infrastructure and sustainable finance, to BNEF, Aug 6 2026): the deal 'originated last July' and executed in April; 'the sponsor initially favored a syndicated construction loan'; BofA assembled a bank syndicate, but 'some lenders expressed concerns about capacity'; 'In early January, we pivoted to bond discussions with Pimco', so the debt could be long-term 'from the outset', with no three-year construction loan to refinance — 'an innovative 19-year term financing structure with callability starting in year three' (contested tenor). Bloomberg had the same switch on Apr 1 2026: $14B of debt first meant as a construction loan that 'is now expected to be structured as a bond offering' (via Reuters). Tier 2: a party's words in an interview. This is the Saline-specific half of the reports of banks retreating; TD Cowen's is about Oracle-linked lending in general (contested financing-path)
“We assembled a bank syndicate, but given the significant size of the financing, some lenders expressed concerns about capacity.”
BloombergNEF Q&A with Bank of America, Aug 6 2026 · about.bnef.com - pimco-anchorPIMCO's part, from its counsel (Greenberg Traurig, May 5 2026): funds and accounts managed by PIMCO acquired 'a significant portion' of the $14B and 'were the biggest buyer of the bonds' — the only party statement on PIMCO's share, and it gives no number (contested pimco-allocation: ~$10B by Bloomberg's and the FT's sources). Gibson Dunn's structured-finance page also lists PIMCO 'as the anchor investor' on this offering; nothing on file says why two firms name the same client on one deal. The sponsors' release has the debt 'anchored by PIMCO-managed funds and accounts'
“Global law firm Greenberg Traurig, LLP represented funds and accounts managed by Pacific Investment Management Company LLC (PIMCO) in acquiring a significant portion of a $14 billion private-debt package that will finance the development of Oracle's data center project in Saline Township, Michigan.”
Greenberg Traurig release, May 5 2026 · gtlaw.com - pimco-filed-holding1,762,848a filed floor under PIMCO's position: PIMCO Income Fund alone held 1,762,848 thousand (≈$1.76B) of par at Jun 30 2026, marked at 1,757,990 thousand (≈99.7, our division) — its schedule of investments, amounts in thousands, where the issuer appears as 'Road Michigan Property Owner I LLC' with the same coupon and maturity. Other PIMCO funds carry smaller lines; PIMCO's separate accounts file no schedule, so no filing can add up to PIMCO's total, and the ~$10B (contested) is neither confirmed nor ruled out. The url is the SEC's own copy of the filing (PIMCO Funds, accession 0001410368-26-090247); Yahoo's mirror of it carries the same line
“Road Michigan Property Owner I LLC 7.500% due 03/30/2045 1,762,848 1,757,990”
PIMCO Income Fund N-PORT schedule of investments, Jun 30 2026 (SEC filing, PIMCO Funds) · sec.gov - issue-price98.75issued below par: the notes 'were priced at 98.75 cents on the dollar' — Bloomberg (Apr 25 2026), from people with knowledge of the matter and Bloomberg-compiled data. No issuer, sponsor or counsel document on file gives the price, so the figure is tier 2. A buyer's own record matches it: New Jersey's Police and Firemen's Retirement System bought $370,000 of the notes from BofA Securities, one of the initial purchasers, in April 2026 at 98.75, for $365,375 (its published trade file) — one purchase at that price, in a file with no trade dates, so it agrees with Bloomberg's issue price without stating one. $14B at 98.75 ≈ $13.8B of proceeds before fees (our arithmetic). The FT's version: PIMCO bought its share 'at a discount' (contested pimco-allocation)
“The notes, which mature in 2045, were priced at 98.75 cents on the dollar and carry a 7.5% coupon, according to some of the people and Bloomberg-compiled data.”
Bloomberg via Gulf Times (Apr 25 2026) · gulf-times.com - secondary-price91.41how the market has priced the notes since: 'traded down from par to the mid-90s in July', 93.7 on Sep 21 and 91.41 on Sep 28 2026 — Octus, citing IHS Markit, in a piece on Oracle's force-majeure notice for its New Mexico campus (Project Jupiter; sg-oai-orcl), which lists RD Michigan among 'other deals where Oracle backs debt service through a triple net lease'. 'From par' is loose: the notes were issued at 98.75, and PIMCO Income Fund marked them ≈99.7 at Jun 30 (pimco-filed-holding). A falling price on fixed-rate paper backed by Oracle's lease is the market's charge for Oracle risk, not a missed payment
“The bonds traded down to 91.41 today from 93.7 on Sept. 21 and traded down from par to the mid-90s in July, according to IHS Markit.”
Octus, Sep 28 2026 (prices from IHS Markit) · octus.com - lease-term17.5 yearsa 17.5-year initial lease term with two 10-year extension options, and notes that fully amortize within the initial term, so repayment does not rely on a renewal — MNI (Jun 5 2026); KBRA, likewise, credits the 'absence of reliance on lease renewal for note amortization', and Bommarito's draft review gives the same lease ('17.5-year initial term plus two 10-year renewals'). No lease document is on file. Not DTE's contract term (Feb 28 2045, pw-dte-oracle), and not Oracle's generic 15-to-19-year terms for its data-center leases (sg-oai-orcl lease-commitments)
“ORCL signed a 17.5- year NNN with 2 ten-year extension options.”
MNI US Credit Sector Overview, 'Hyperscalers: Bespoke Data Center Financing' (Jun 5 2026) · media.marketnews.com - program4.5 GWthe site sits in OpenAI and Oracle's July 2025 agreement for up to 4.5 GW of 'additional Stargate capacity' (sg-oai-orcl), developed 'exclusively for Oracle' — the announcement of Oct 30 2025 by OpenAI, Oracle and Related Digital. Not an asset of the SoftBank–OpenAI–Oracle–MGX joint venture: no document on file shows Stargate LLC equity, debt or a contract at Saline; the capital is Related's and Blackstone's equity and the PIMCO-anchored notes, the tenant Oracle, the end user OpenAI. Bridge's 'part of the $500 billion Stargate plan' and thenextweb's 'the joint venture announced in January 2025 with SoftBank' are the umbrella error (note).
“The multi-billion dollar investment in the project, which is expected to begin construction in early 2026, is part of OpenAI and Oracle's previously announced partnership to deliver 4.5 gigawatts of additional Stargate capacity.”
OpenAI/Oracle/Related Digital announcement, Oct 30 2025 (Related Digital copy) · related-digital.com - jobs-onsite450450 permanent jobs on site, in three shifts of 150 — the developer's own projection, in its wastewater-permit narrative to Michigan's environment department (Nov 11 2025); the release's '450+ jobs onsite' is the same figure. The Sun Times' 'approximately 150 employees' is one shift's worth, and the Citizens Research Council's 'fewer than 100 permanent jobs' is its general benchmark for the largest data centers, not a figure for this one
“The proposed facility will employee 450 workers over 3 shifts (150 per shift).”
Related Digital, wastewater treatment plant narrative to EGLE (Nov 11 2025) · mienviro.michigan.gov - jobs-county1,500'1,500+ jobs county-wide' — Washtenaw County, not the nation: this record follows the original wording over Planet Detroit's 'over 1,500 jobs nationwide', a misparaphrase of this line. The release's three counts — 2,500+ construction, 450+ on site, 1,500+ in the county — are the developer's projections; how they overlap is not stated, so they are not to be added. The Oct 30 2025 announcement (program) gave the same two counts in its body, 'more than 450 jobs onsite, and 1,500 jobs county-wide', and in its subheading '2,000 permanent jobs county-wide', without saying how the 2,000 relates to them
“2,500+ union construction jobs, 450+ jobs onsite, and 1,500+ jobs county-wide”
Related Digital/Blackstone release, Apr 24 2026 · related.com - progress1,800where construction stood on Aug 27 2026, by the parties' joint release (Related Digital, Oracle, Walbridge and Blackstone, whose Blackstone Real Estate head of digital infrastructure speaks in it): 'more than 1,800 skilled tradespeople' on site and one million craft hours logged. Not a completion milestone (contested completion)
“More than 1,800 skilled tradespeople are currently building the project, which will support more than 2,500 construction jobs.”
Related Digital release, Aug 27 2026 · related.com
Contested figures 33 not reconciled — every position side by side, with its source and tier
Scope note what this record leaves to other records
Not this record — carried elsewhere or not carried: DTE's power and storage contracts → pw-dte-oracle; the OpenAI–Oracle capacity agreement the campus serves, and Oracle's delivery guidance for all its sites → sg-oai-orcl (its saline-value carries the same $16B release); the Township's tax abatement (the PA 198 application at $43.1B, approved by the Township Board three days after it had capped the abatement at $4.8B — the Sun Times), the release's '$14 million in direct benefits' for the fire department and community, the acreage (250 of 575 acres in Saline Township developed, per Oracle), the generators, the water and the competing tax-revenue estimates — local paper with no bearing on the financing; Oracle's corporate disclosures (backlog, lease commitments, and a guarantee of up to $3.3B of one unnamed lessor's borrowing maturing Sep 2026, which cannot be these 2045 notes) → sg-oai-orcl. The other Oracle-site debt Bloomberg sets beside this deal — 'A $38bn debt deal to build facilities in Texas and Wisconsin, and $18bn for a New Mexico site', both bank-assembled — is on sg-oai-orcl's note; of the sources on file, only the press reports the $38B package as lent and largely sold down to other lenders (Business Insider, Jan 2026; Bloomberg, Apr 2026), and no party document confirms it. Not adopted: thenextweb's '$16.3 billion data centre financing closed this week' (the Apr 8 proposal relabelled as closed) and '$72 billion in total data centre partner debt' (this deal's equity summed with other sites' loans); 'part of the $500 billion Stargate plan' (Bridge) and the site as the SoftBank joint venture's (thenextweb) — no Stargate LLC money or contract here (program); 'Pimco held $18 billion of the debt when it priced' (Meta's Hyperion bonds, not these) and a 6.58% / 2049 line beside these notes in PIMCO's filings (Beignet Investor's, Hyperion again); Applied Digital's $2.15B 6.75% notes (another Oracle-tenant project — only its definition of Oracle America Cloud Services is used, on pw-dte-oracle).