Why it matters
At the small end of Microsoft's neocloud contracts, ChronoScale signed for the deliveries before it had what delivering takes. In its 10-Q, about four months before the first GB300 batch was due, its building was not yet leased and the deployment was 'subject in part to our ability to obtain financing'. It had $15.2M of cash at the quarter's end, against $2.0B of AI-infrastructure purchase obligations due within a year.
Tap a figure for the line in its source.
Microsoft gives ChronoScale
- fees for the GPU services, at a price no filing states — the 10-Q's $2.7B of contracted revenue covers two customers' agreements and is not split
- upfront payments of undisclosed size, which ChronoScale must refund in full for any tranche not yet accepted, and pro rata for an accepted one, on certain terminations
ChronoScale gives Microsoft
- of dedicated Nvidia GB300 GPU services at a Texas data center, in two roughly equal tranches expected in February and March 2027 (subject to extension), for an approximately three-year term
What happened
In August 2026, Microsoft agreed to buy dedicated computing on Nvidia's GB300 chips from ChronoScale. ChronoScale is a small GPU cloud provider majority-owned by data center developer Applied Digital. The deal covers about 50 megawatts' worth of capacity in a Texas data center for about three years. The two roughly equal batches are expected in February and March 2027. Neither company has disclosed what Microsoft pays. The only dollar figure in the filings, $2.7 billion, covers two customers' contracts together. Microsoft did not mention the deal in its latest quarterly report or on its earnings call. CNBC reported in November that Microsoft is cutting the number of neoclouds it uses but has not decided which. ChronoScale reported in October that the building was still to be leased from a joint venture its parent was forming. The lease was still under negotiation. ChronoScale also reported that the deployment depended in part on raising money beyond its own cash. Late batches cost ChronoScale delay credits. On certain terminations, Microsoft gets its upfront payments back in full for any batch it hasn't accepted. ChronoScale's filings do not name the site, but its November investor presentation puts the Microsoft deployment at a campus in Silverton, Texas. Soluna says ChronoScale signed a non-binding letter of intent to lease a data center Soluna is planning with Applied Digital in Briscoe County, Texas. That site matches the description. No document says it is the same one.
Sources 11 documents — 9 SEC filings · 1 transcript · 1 press report
Research trail Found 64 documents and read 60 of them while checking this deal and related ones.
- States 13 figures: agreement · 50 MW capacity · tranches · refund terms · financing condition · financing need · lease status · $50M fit out term sheet · $2.7B two customer revenue · $2.3B project capex · $2B purchase obligations · $328.2M prepayments received · $70.5M seller liquidity
- States 2 figures: delay credits · first disclosure
- States term
- States hardware
- States parent account
- States 50 MW secured headline
- States parent framing
- States microsoft neocloud review
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: ChronoScale 10-K for FY ended May 31 2026 (filed Aug 19 2026); 8-K Items 7.01/8.01 + ex-99.1 (Aug 27 2026); 10-Q for the quarter ended Aug 31 2026 (filed Oct 14 2026); Q1 FY2027 results release, 8-K Item 2.02 ex-99.1 (furnished Oct 15 2026); Applied Digital 10-Q (signed Oct 7 2026) and Oct 7 call (Motley Fool); Soluna 8-K Item 1.01 + ex-99.1 (Oct 2026); CNBC (Nov 6 2026) — read 2026-11 · as of Nov 2026
The evidence 21 sourced figures · 3 disputes
The record's headline Microsoft–ChronoScale: ~50 of dedicated GB300 GPU services in Texas for about three years from Feb–Mar 2027 — no price or GPU count disclosed; at the 10-Q the building not yet leased and the deployment still subject to financing
- Size
- undisclosed · ~50 MW · ~3 years · two tranches of Nvidia GB300 (the 10-Q's $2.7B covers two customers' agreements, not split)
- When
- Aug 6 2026 signed (two years) → Aug 19 10-K → Aug 21 amendment effective (Applied Digital: extension entered Aug 24) → Aug 27 8-K, three years → Oct 11 fit-out term sheet with Applied Digital → Oct 14 10-Q, lease under negotiation → Oct 20–21 Soluna–Applied Digital JV at Dorothy 3, ChronoScale's letter of intent → Feb–Mar 2027 deliveries expected
- Status
- signed Aug 6 2026; amended effective Aug 21 2026 to an approximately three-year term (8-K Item 8.01, Aug 27). Nothing delivered: both tranches expected Feb and Mar 2027, 'subject to extension in certain circumstances'. At the 10-Q (Oct 14 2026) the building's lease was under negotiation and the deployment 'subject in part to our ability to obtain financing' (its Microsoft obligations 'will require financing beyond our existing cash resources'); Soluna's joint venture with Applied Digital at Dorothy 3, where ChronoScale signed a non-binding letter of intent to lease (Soluna's release, furnished), was expected to close by Dec 1 2026 (no later than Dec 31) — whether it is Microsoft's site, no document says. CNBC (Nov 6 2026): Microsoft is cutting the number of neoclouds it uses, ChronoScale among those named, which ones undecided
- Structure
- a GPU Services Agreement between ChronoScale and Microsoft Corporation, entered Aug 6 2026 for two years and amended effective Aug 21 2026 to about three; not filed as an exhibit (the 10-K calls it 'ordinary course'). Dedicated NVIDIA GB300 GPU services at one Texas facility, in two tranches of approximately equal GPU quantity and contract value; Microsoft makes upfront payments, refundable in full for a tranche not yet accepted and pro rata for an accepted one on certain terminations; delay credits for late delivery; Microsoft may terminate in certain circumstances, for which cure rights may be available, ChronoScale's own termination rights are 'more limited', and neither party may terminate for convenience. Around it, nothing else was signed at the 10-Q: the facility is to be leased from a joint venture being formed between Applied Digital and the third party that controls the site, the lease 'under negotiation'; an Oct 11 2026 term sheet with Applied Digital covers a $50.0M upfront advance for tenant fit-out; and the deployment is 'subject in part to our ability to obtain financing'
- Programme
- Microsoft–ChronoScale
- Parties
- Microsoft customer — buys dedicated GPU services and makes upfront payments it gets back on certain terminations; has published nothing about the deal · ChronoScale neocloud provider — must buy the GB300s, lease and fit out the building and raise the money to do both, on a fixed delivery schedule with delay credits
- Record
- disclosed / primary source · as of Nov 2026
Flows 2 as the record states them
- Microsoft → ChronoScalecompute-spendundisclosed — service fees over an approximately three-year term plus upfront payments of undisclosed size; the GPU quantity and contract value are 'approximately equal across both tranches'. The 10-Q's $2.7B of aggregate contracted revenue covers GPU services agreements with two customers signed in the quarter, three-year terms, neither named — Microsoft's agreement is one of them on our reading, its share not given
- ChronoScale → Microsoftcomputededicated NVIDIA GB300 GPU services 'supporting approximately 50 MW of AI compute capacity' at one Texas facility, two tranches with deliveries expected Feb and Mar 2027, subject to extension; GB300 NVL72 systems with liquid cooling (Aug 27 release, furnished); GPU count undisclosed
Resolved figures 21 each with the verbatim line from its document
- agreementa GPU Services Agreement with Microsoft Corporation, entered Aug 6 2026 and 'amended effective as of August 21, 2026' — the 'Microsoft Agreement'. ChronoScale's own instrument name; its releases call it a 'partnership' and a 'deployment'. The agreement is not filed: the 10-K describes it as 'a two-year ordinary course GPU services agreement', and the 10-Q's exhibit list does not include it. Microsoft's 10-Q for the quarter to Sep 30 2026 and its Oct 28 2026 earnings call do not name ChronoScale
“On August 6, 2026, we entered into a GPU Services Agreement with Microsoft Corporation, which was amended effective as of August 21, 2026”
ChronoScale 10-Q, quarter ended Aug 31 2026 (filed Oct 14 2026) — MD&A, Microsoft Strategic Partnership · sec.gov - capacity50 MW~50 MW: dedicated GPU services 'at a data center facility in Texas, over an approximately three-year service term, supporting approximately 50 MW of AI compute capacity'. The Aug 27 release's 'North America' is the same deployment in broader words. Planned, not built: no tranche has been delivered. The 50 MW is what the capacity supports, not a figure for the building; the site is contested below
“Under the Microsoft Agreement, we will provide Microsoft with dedicated GPU services at a data center facility in Texas, over an approximately three-year service term, supporting approximately 50 MW of AI compute capacity.”
ChronoScale 10-Q, quarter ended Aug 31 2026 (filed Oct 14 2026) — MD&A, Microsoft Strategic Partnership · sec.gov - term3 yearsabout three years, after one year was added: the 10-K (Aug 19) called it two-year, and the Aug 27 8-K, under Item 8.01 (filed), says the parties 'have agreed to extend the term from two years to three years'; the 10-Q says 'approximately three-year service term'. A sequence, not a disagreement. ChronoScale's later shelf filings — the draft S-3 of Sep 29 and the S-3 of Oct 6 2026 — still say 'two-year' (stale text; the 10-Q of Oct 14 is the later filed statement). When the extension took effect is contested below (extension-date)
“The Company previously disclosed it entered into a two-year strategic partnership with Microsoft to support the Deployment. The Company and Microsoft have agreed to extend the term from two years to three years.”
ChronoScale 8-K, Item 8.01 (filed Aug 27 2026) · sec.gov - tranchestwo tranches of NVIDIA GB300 GPUs, deliveries expected February and March 2027, 'subject to extension in certain circumstances', with GPU quantity and contract value 'approximately equal across both tranches'. No document gives the GPU count, a tranche's megawatts or a tranche's price; that each tranche is ~25 MW is arithmetic the filing does not do. The 10-K (Aug 19) had 'projected completion in the first calendar quarter of 2027' — the same quarter, before the months were given
“tranches of NVIDIA GB300 GPUs, with the respective deliveries expected to occur in February and March of 2027 (subject to extension in certain circumstances). The GPU quantity and contract value are expected to be approximately equal across both tranches.”
ChronoScale 10-Q, quarter ended Aug 31 2026 (filed Oct 14 2026) — MD&A, Microsoft Strategic Partnership · sec.gov - hardwareGB300 NVL72 rack systems with liquid cooling, networking, storage and software in 'purpose-built data center infrastructure' — the release's detail; the filings say only 'NVIDIA GB300 GPUs'. The release quotes an NVIDIA vice president on ChronoScale's 'deployment of NVIDIA GB300 NVL72 systems'; it names no supplier contract, and the 10-K's risk factor speaks of 'a sole-source GPU supplier' it does not name
“The deployment will feature NVIDIA GB300 NVL72 systems and advanced liquid-cooling infrastructure designed for high-density AI workloads.”
ChronoScale release, 8-K Item 7.01 ex-99.1 (furnished Aug 27 2026) · sec.gov - refund-termsMicrosoft's upfront payments are at risk to ChronoScale, not to Microsoft: on certain terminations ChronoScale refunds them in full for any tranche not yet accepted and pro rata for an accepted one, and neither party may terminate for convenience. Microsoft may terminate 'under certain circumstances, for which cure rights may be available'. The size of the upfront payments and when they fall due are not disclosed. The 10-K (Aug 19, before the amendment) put it as a full refund of 'any upfront payments received in respect of that tranche', with no pro rata language
“Upon certain terminations, we are required to refund the upfront payments in full for any tranche not yet accepted and on a pro rata basis for any accepted tranche. Our termination rights are more limited, and neither party may terminate for convenience.”
ChronoScale 10-Q, quarter ended Aug 31 2026 (filed Oct 14 2026) — MD&A, Microsoft Strategic Partnership · sec.gov - delay-creditslate delivery costs ChronoScale: 'daily delay penalties' credited to Microsoft for a tranche delivered after its required date (10-K), and in the 10-Q's list of the agreement's provisions 'excluded delays, delay credits'. In the 10-K, Microsoft may 'terminate a tranche entirely if the tranche is not accepted within a specified period or upon the occurrence of nonperformance', and in other circumstances the whole agreement. No rate or window is disclosed
“Under the terms of the Microsoft Deployment, if we fail to deliver a tranche of GPU capacity by the applicable required delivery date, we are obligated to credit Microsoft with daily delay penalties.”
ChronoScale 10-K for FY ended May 31 2026 (filed Aug 19 2026) — Risk Factors · sec.gov - financing-conditionthe deployment is conditional on ChronoScale raising money: 'subject in part to our ability to obtain financing' and to construction and operating milestones. The 10-Q's risk factors are blunter — the Microsoft agreement requires it to buy the GPUs and 'complete a dedicated data center facility on a fixed delivery schedule, obligations that will require financing beyond our existing cash resources' (financing-need). The Oct 15 release's 'Secured a 50 MW AI compute deployment' (secured-headline) does not lift the condition
“The deployment is subject in part to our ability to obtain financing and to satisfy customary development, construction and operational conditions and milestones.”
ChronoScale 10-Q, quarter ended Aug 31 2026 (filed Oct 14 2026) — MD&A, Microsoft Strategic Partnership · sec.gov - financing-needChronoScale's own words on what the deal asks of it. At Aug 31 2026 it had $15.2M of cash and a working-capital deficit of ~$70.5M (seller-liquidity); the 10-Q lists the financing it may seek — equity or debt, equipment financing, joint ventures — and says that if financing is late it 'may be unable to place equipment orders, complete construction or deliver capacity on schedule', with credits, penalties, termination and 'repayment of upfront payments' to follow
“For example, our agreement with Microsoft requires us to procure large-scale GPU capacity and complete a dedicated data center facility on a fixed delivery schedule, obligations that will require financing beyond our existing cash resources.”
ChronoScale 10-Q, quarter ended Aug 31 2026 (filed Oct 14 2026) — Part II, Risk Factors · sec.gov - lease-statusthe building is not yet ChronoScale's: it expects to lease space from a joint venture 'being formed' between Applied Digital (its ~96% parent) and an unnamed third party that controls the site, and the lease 'remains under negotiation' — the lease that is to 'provide the compute capacity necessary to fulfill our deployment agreement with Microsoft'. So at the 10-Q (Oct 14 2026), about four months before the first tranche was due, the landlord was still being formed and the lease was unsigned (editor's reading of the two quoted clauses). Which site this is, is contested below
“We expect to lease space at the facility from a joint venture being formed between Applied Parent and a third-party who currently has site control, to develop the data center. The lease remains under negotiation and is expected to include customary TFO provisions and provide the compute capacity necessary to fulfill our deployment agreement with Microsoft.”
ChronoScale 10-Q, quarter ended Aug 31 2026 (filed Oct 14 2026) — MD&A, Tenant Fit-Out Funding Advance · sec.gov - fit-out-term-sheet$50M$50.0M — a term sheet of Oct 11 2026 with Applied Digital, approved by ChronoScale's related-party committee, for an upfront advance toward tenant fit-out at the Texas facility: a term sheet, not a funded advance, and no document says it has been paid. Which way the money runs is contested below (fit-out-advance-direction). Applied Digital's 10-Q, signed Oct 7, predates it
“On October 11, 2026, we entered into a term sheet with Applied Parent, a related party, to provide a $50.0 million upfront advance for tenant fit-out”
ChronoScale 10-Q, quarter ended Aug 31 2026 (filed Oct 14 2026) — MD&A, Tenant Fit-Out Funding Advance · sec.gov - two-customer-revenue$2.7B$2.7B of aggregate contracted revenue for GPU services agreements with two customers entered in the quarter to Aug 31 2026, both on three-year committed terms. The note names neither customer. The Microsoft agreement (entered Aug 6, ~three years after the amendment) is one of the two on the record's reading, so Microsoft's contract value is part of the $2.7B, by an amount no document gives. Baseten's three-year partnership of Aug 28 (~4 MW) would fit as the other, but the 10-Q calls it a 'strategic partnership', not a GPU services agreement, and does not say. The $1 billion 'annualized run-rate revenue' ChronoScale expects by calendar Q3 2027 (Oct 1 and Oct 15 releases) is company-wide, includes agreements signed after the quarter, and is not a figure for this deal
“During the three months ended August 31, 2026, the Company entered into GPU services agreements with two separate customers, both providing for a three-year committed service term, with aggregate contracted revenues of $2.7 billion.”
ChronoScale 10-Q, quarter ended Aug 31 2026 (filed Oct 14 2026) — Note 16, Commitments: Customer Contracts · sec.gov - project-capex$2.3B~$2.3B of project-specific capital expenditure ChronoScale is 'contractually committed to' over the next twelve months to deliver the same two customers' deployments, including the purchase obligations below — against $2.7B of contracted revenue over three years. Two-customer figures; the note does not split them by customer, and the record does not set one against the other as a margin
“In order to fulfill the deployments under these customer contracts, the Company is contractually committed to project-specific capital expenditures of approximately $2.3 billion during the twelve-month look-forward period, which includes the purchase obligations as described below.”
ChronoScale 10-Q, quarter ended Aug 31 2026 (filed Oct 14 2026) — Note 16, Commitments: Customer Contracts · sec.gov - purchase-obligations$2B$2.0B of binding purchase obligations, 'primarily for purchases of its AI infrastructure', at Aug 31 2026, due within a year — inside the ~$2.3B above, not added to it. Company-wide; the note names no supplier and does not tie any part of it to Microsoft's tranches
“The Company had purchase obligations primarily for purchases of its AI infrastructure totaling $2.0 billion as of August 31, 2026, which are expected to be paid within one year.”
ChronoScale 10-Q, quarter ended Aug 31 2026 (filed Oct 14 2026) — Note 16, Purchase Obligations · sec.gov - prepayments-received$328.2M$328.2M of prepayments received after Aug 31 2026 'under its existing customer contracts' — an aggregate, by customer and date unallocated. Whether any of it is Microsoft's upfront payments, no document says; the Oct 15 release repeats the figure, still unattributed. If it is, the refund terms above apply to it
“Following the fiscal quarter ended August 31, 2026, the Company received $328.2 million in aggregate prepayments under its existing customer contracts.”
ChronoScale 10-Q, quarter ended Aug 31 2026 (filed Oct 14 2026) — Note 19, Subsequent Events · sec.gov - seller-liquidity$70.5Mthe seller's balance sheet at the quarter-end before deliveries: a working-capital deficit of ~$70.5M and $15.2M of cash at Aug 31 2026. The 10-Q says the deficit 'raised substantial doubt' about ChronoScale as a going concern, then concludes the doubt is 'alleviated' on management's plans to collect its customers' remaining upfront milestone payments and to match the capex its customer agreements require with financings. Its parent's Grid Note had $85.0M undrawn after a Sep 15 draw (chronoscale entity)
“The Company had a working capital deficit of approximately $70.5 million as of August 31, 2026 which raised substantial doubt about the Company's ability to continue as a going concern.”
ChronoScale 10-Q, quarter ended Aug 31 2026 (filed Oct 14 2026) — Note 1, Liquidity · sec.gov - first-disclosurethe first public word of the deal, in ChronoScale's 10-K filed Aug 19 2026: a two-year partnership signed Aug 6, ~50 MW of GB300 systems with liquid cooling, 'projected completion in the first calendar quarter of 2027', subject to financing. The Aug 27 8-K calls the partnership 'previously disclosed', and no earlier report is on file; an EDGAR full-text search (Nov 16 2026) of ChronoScale's filings since Jul 1 2026 finds 'Microsoft' in none between the Aug 6 signing and the 10-K
“On August 6, 2026, we entered into a two-year strategic partnership with Microsoft to support the planned deployment of approximately 50 megawatts of AI compute capacity.”
ChronoScale 10-K for FY ended May 31 2026 (filed Aug 19 2026) — Business · sec.gov - parent-accountApplied Digital's own filed account of its subsidiary's deal: 'On August 6, 2026, ChronoScale entered into a two-year strategic partnership with Microsoft to support the planned development of approximately 50 MW of AI compute capacity', then the extension, dated Aug 24 (contested extension-date). Parent and ~96% subsidiary: two filers, one source of knowledge, so it confirms ChronoScale's wording rather than corroborating it independently
“On August 24, 2026, ChronoScale entered into a one-year extension of such strategic partnership, resulting in a total of a three-year service term.”
Applied Digital 10-Q, quarter ended Aug 31 2026 (signed Oct 7 2026) — MD&A · sec.gov - secured-headline50 MWthe results release's headline, 'Secured a 50 MW AI compute deployment with Microsoft in North America', filed the day after a 10-Q that keeps the deployment 'subject in part to our ability to obtain financing' and the building's lease 'under negotiation'. The 10-Q is the governing statement
“Secured a 50 MW AI compute deployment with Microsoft in North America, which is expected to integrate NVIDIA GB300 NVL72 systems with liquid cooling”
ChronoScale Q1 FY2027 results release, 8-K Item 2.02 ex-99.1 (furnished Oct 15 2026) · sec.gov - parent-framingApplied Digital's CEO Wes Cummins on the Oct 7 2026 call: the deployment expands ChronoScale's business 'with a Tier 1 investment-grade customer', and ChronoScale's capacity strategy is separate from Applied Digital's own large campuses — sites like 'the first Microsoft side of 50 megawatts', '50 to 100-megawatt sites that have been passed over' because they are too small for gigawatt-scale builds. He names no site. Spoken, via a third-party transcript
“This deployment is expected to significantly expand ChronoScale's existing business with a Tier 1 investment-grade customer and represents another important step in scaling the platform.”
Applied Digital Q1 FY2027 earnings call (Oct 7 2026), Motley Fool transcript · fool.com - microsoft-neocloud-reviewCNBC (Nov 6 2026), on two unnamed sources: Microsoft is shrinking the number of neoclouds it uses, naming Chronoscale among its neocloud relationships, and 'hasn't decided which neoclouds it will stop using'. Nothing in the article says this deal is affected. Bloomberg's report the day before (via Yahoo, Nov 5) names Nebius, IREN and Nscale as the projects under tighter oversight and does not mention ChronoScale — which says nothing either way. Microsoft's on-record comment is general
“Microsoft has forged relationships in recent years with a number of neoclouds, including CoreWeave, Nebius, Chronoscale, IREN, Lambda and Nscale, as well as with Oracle, which is pouring money into building out AI infrastructure.”
CNBC, Nov 6 2026 · cnbc.com
Contested figures 6 not reconciled — every position side by side, with its source and tier
“Equity for GPUs and site fit-out at the purpose-built Silverton, TX campus”ChronoScale 10-Q (Oct 14 2026); 10-K (Aug 19 2026); investor deck, 8-K/A ex-99.2, slide 8 (Nov 18 2026, filed) · sec.gov
Scope note what this record leaves to other records
NOT this record (carried elsewhere or not carried): the Soluna–Applied Digital joint venture at Dorothy 3 beyond what places the site — the subscription amounts ($18.75M of ground sublease in kind, $19,515,306 of cash), the 75 MW gross power allocation and 100 MW firm / 150 MW potential at Oncor's Tule Canyon substation, the 80% / $45M termination reimbursement and its 49% / 31% installment drafting, the Applied warrant over 7,644,444 Soluna shares, Briscoe Wind (150 MW, $53M), the 397 / ~400 / 403.397 acres, the 'up to 300 MW' campus, Reinvestment Zone #6's 'more than $8,000,000,000' of estimated improvements, the podcast's $600M / $10–12M-per-MW illustration, Soluna's Generate payoff ($28.7M vs Terrain's $27.5M; $9.2M vs $10.4M) and its 192 MW / >200 MW and 6.3 GW / >1.5 GW footprints → not carried here (Soluna is not an entity; the JV has no record until it closes and a lease is signed). ChronoScale's company figures — ownership series (97% → 96% → 95.8%), the May 2026 combination ($57.6M consideration) and PIPE (1,311,407 shares at $12.01 vs the release's 'approximately 1.4 million'), FY2026 revenue $71.6M (its decline $12.8M by its 10-K, $12.4M by Applied's, with two different causes), Q1 FY2027 results, the H100 fleet, the Grid Note, Baseten, the Oct 1 agreements and the $1 billion run-rate → the chronoscale entity; its website's 2,784–2,924 MW pipeline → not adopted. Applied Digital's own leases and portfolio (~1.41 GW, ~$36B; the 210 MW / ~$5.2B lease to an unnamed 'high investment-grade hyperscaler', nothing ties it to Microsoft) → nothing here. Microsoft-wide figures (Q1 FY2027 capex $45.2B, 'some third-party capacity deliveries we expected in Q1 were delayed'; $364.6B of leases not yet commenced; $677B commercial RPO) → microsoft / hyperscaler-capex; they name no neocloud. William Blair's comparisons (Nebius, IREN and Nscale contract values; IREN's 20% prepayment, CoreWeave's 15–25%, Nebius's 50–60% of capex; $25–35M capex per MW) → not this deal's terms; no ChronoScale prepayment rate is disclosed and IREN's 20% is not carried over. Bloomberg's Nscale cancellation (~$3B UK; a 1.35 GW West Virginia LOI) → nscale-msft's territory, not touched. Not disagreements, so not listed as disputed: the deployment's timing (10-K: completion 'in the first calendar quarter of 2027'; 10-Q: deliveries Feb and Mar 2027; the website: 'First sites ready for service, from February' 2027; Soluna's CEO on a podcast, of the Dorothy facility: 'we will need to deliver this data center in 2027') — different events, one season — and CNBC naming ChronoScale where Bloomberg does not. Not adopted: 'two-year' in the Sep 29 draft S-3 and Oct 6 S-3, after the extension (stale text); DCD's 'Net loss for the quarter was $26.4m' (continuing operations only; the quarter's total was $42.5M); DCD's 'annual revenues to $1 billion by Q3 2027' (the source's metric is an annualized run-rate, a quarter × 4); the 10-K's 'approximately 6.1 GPUs' (6,144 in thousands); reading Note 16's $2.7B as Microsoft's contract value (it is two customers', not split); press 'secured' without the financing condition.