Why it matters
Japan lists AI data centers among the uses for mature chips from the planned GlobalFoundries plants in New York. GlobalFoundries pitches the chips for cars, industry and connected infrastructure, and would run the plants for fees and a share of earnings without putting up capital. Japan's finance ministry had yet to commit loans at the end of September.
Tap a figure for the line in its source.
Japanese government gives US–Japan Malta fabs vehicle (SPV)
- for the first plant, due online in 2029 — Japan's own figure for the project (about ¥1.6 trillion), and GF's; announced but not yet at a loan commitment at the end of September 2026, and whether it goes in as equity or as loans no document says
- for both plants, if a second ≈$10B plant is approved at a go/no-go decision before the end of 2028; GF's two ≈$10B figures leave about $1 billion of it unexplained
GlobalFoundries gives
- its technology (its FDX, BCD and UX platforms) and the building and running of the plants, with no capital of its own; about 900,000 300mm a year per plant at full run rate → US–Japan Malta fabs vehicle (SPV)
- of capital investment at those two existing plants, which GF agreed to expand to as part of the amendment, by Commerce's account → US government
- of GF's shares to the Commerce Department, under a separate agreement still to be entered into on Nov 4 2026 — no price, share count or stated consideration; with the earlier stakes, about 7% in all → US government
US–Japan Malta fabs vehicle (SPV) gives
- of revenue expected in 2027, GF's estimate for the first plant — technology fees from 2027 for at least 20 years, construction- and operations-management fees, cost reimbursement and a share of the plants' EBITDA; no rate disclosed → GlobalFoundries
- of the vehicle's cash flows under the 2025 US–Japan framework — half until Japan has recovered its principal and interest, then 90% (Japan 10%); the two governments are to own the vehicle, in shares no document gives, and no project document applies the split to these plants → US government
US government gives GlobalFoundries
- of GF's existing CHIPS Act award ('up to', in Commerce's words) moved to silicon photonics, silicon-germanium and advanced packaging at Malta and at Burlington, Vermont, from 2027; the award's total is not increased
What happened
On October 14, 2026, contract chipmaker GlobalFoundries said it had been chosen to build and run two new chip plants in Malta, New York. GlobalFoundries said the plants would be on its existing site. It said Japan would fund them under the 2025 US–Japan trade and investment deal. Japan's government puts the project at about $10 billion for one plant. GlobalFoundries expects that plant to start production in 2029. Japan says the project could grow to about $21 billion with a second plant. Japan says the partners are to decide on that plant before the end of 2028. GlobalFoundries says an entity owned by the US and Japanese governments would own the plants. GlobalFoundries says it would put in no money and would receive fees and a share of earnings. Separately, the Commerce Department agreed to redirect up to $955 million of GlobalFoundries' existing CHIPS Act grant. The money would go to silicon photonics, which uses light to carry data, and silicon-germanium, a chipmaking material. It would also go to advanced packaging, which assembles and connects chips. All are technologies used in data centers. The Commerce Department is to receive about 4% of GlobalFoundries. None of the contracts has been published. GlobalFoundries' figures depend on agreements that have yet to be signed. The agreement for the 4% stake had not been entered into by November 4. Japan's finance ministry listed the plant project as announced, with no loan commitment.
Sources 32 documents — 10 government statements · 7 SEC filings · 4 company releases · 3 social posts · 3 press reports · 3 other documents · 2 transcripts
Research trail Found 97 documents and read 90 of them while checking this deal and related ones.
- States 7 figures: phase 2 decision · vehicle · no gf capital · gf fees · $50M gf 2027 revenue · $3B gf cash flow · project term
- States 6 figures: up to $21B program ceiling · $10B first plant · $10B second plant · capacity · jobs · $955M chips reallocation
- States 3 figures: up to $955M chips commerce · award not increased · $5B gf capex 5b
- States 2 figures: 4% equity 4pct · 7% usg total
- States $10B japan project cost
- States loan commitment
- States japan may decline
- States 90% framework split
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: GF release, Oct 14 2026 (6-K ex-99.1); GF investor webinar (Oct 14) and Q3 2026 call (Nov 4), StockAnalysis transcripts; GF decks (Oct 14, Nov 4); GF Q3 2026 earnings release and interim report (6-Ks, Nov 4 2026); GF 6-K (Sep 8 2026) and F-3ASR (Sep 2026); GF releases (May 21 and Jul 29 2026); Commerce (CHIPS Program Office) release (Oct 14 2026) and NIST's GF award page; GF 20-F FY2025; GAO-26-107882; Japan MOFA/METI/MOF release (Oct 15 2026); Japan MOF FILP materials (Oct 28 2026) and the US–Japan memorandum (Sep 4 2025, MOF copy); JBIC financial statements (SEC); White House fact sheets (Jul 2025, Oct 2026); Truth Social (Oct 14 2026) and Commerce's X posts (Oct 14, Oct 22); Reuters via AOL (Oct 15), Bloomberg via Taipei Times (Oct 16), Times Union (Oct 21), Saratoga Today (Oct 22), ENR and SIA (Oct 2026) — read 2026-11 · as of Nov 2026
The evidence 22 sourced figures · 11 disputes
The record's headline GlobalFoundries–Japan–US government: Japan to fund two new chip plants at GlobalFoundries' Malta, New York site — ≈$10B for the first, due online in 2029, up to $21B if a second is approved — owned by a vehicle of the two governments and run by GlobalFoundries for fees; Commerce reallocates up to $955M of GF's CHIPS award to photonics, SiGe and packaging and is to receive ≈4% of GF
- Size
- up to $21B from Japan for two plants (≈$10B for the first) · up to $955M of GF's CHIPS award reallocated · ≈4% of GF to Commerce
- When
- Sep 4 2025 (US–Japan memorandum) → Oct 14 2026 (announced by GF, Commerce and the President; Japan's ministries Oct 15, Tokyo time) → Oct 21 2026 (Malta event: Commerce Secretary Lutnick's '7%' and '50% of the cash flow profits') → Oct 28 2026 (Japan's MOF: announced, no loan commitment yet) → Nov 4 2026 (GF's Q3: the ≈4% agreement 'will be entered into', ≈7% in all) → 2028 (first plant ready for equipment; go/no-go on the second before year-end) → 2029 (first wafers)
- Status
- announced Oct 14 2026 · definitive agreements unsigned at announcement (GF's CFO) · the ≈4% agreement 'will be entered into' (Nov 4) · Japan's financing announced, not at a loan commitment at end-Sep 2026 (MOF, Oct 28) · first plant: construction 'already underway' (GF, Nov 4), online 2029 · second plant subject to a go/no-go before end-2028
- Structure
- a state-funded build under a trade agreement: Japan funds, through instruments no document names, a vehicle the US and Japanese governments are to own, which pays for and owns the plants' buildings and tools; GF contributes its technology and builds and runs the plants for technology, construction- and operations-management fees, cost reimbursement and an EBITDA share, with no capital of its own. Beside it, two agreements between GF and Commerce: an amendment reallocating $955M within GF's existing CHIPS award, and ≈4% of GF's equity under a separate agreement. No definitive agreement is published, and GF's figures are 'subject to the signing of definitive agreements'
- Parties
- Japanese government funder — ≈$10B for the first plant, up to $21B for both, through instruments no document names; co-owner of the vehicle by GF's account; under the 2025 memorandum it may decline to fund a project the President selects · US–Japan Malta fabs vehicle (SPV) the planned owner of the plants' buildings and tools, funded by Japan and owned by the two governments (GF's account); unnamed, and not shown formed in any document · GlobalFoundries technology provider and operator of the two plants — no capital, paid in fees and an EBITDA share — and, separately, CHIPS awardee and issuer of ≈4% of its shares to Commerce · US government co-owner of the vehicle with Japan (GF's account) and selector of the projects Japan funds under the 2025 memorandum; through Commerce, the CHIPS grantor that reallocates up to $955M and the prospective holder of ≈4% of GF
- Record
- disclosed / primary source · as of Nov 2026
Flows 7 as the record states them
- Japanese government → US–Japan Malta fabs vehicle (SPV)project-funding≈$10B for the first plant (Japan's 'approximately 10 billion USD (approximately 1.6 trillion JPY)', and GF's figure), up to $21B for both if the second is approved; announced but not at a loan commitment at end-Sep 2026; equity, loans or guarantees, no document says (contested: funding-form)
- GlobalFoundries → US–Japan Malta fabs vehicle (SPV)technology-and-operationsits FDX, BCD and UX process platforms, construction management and the running of the plants — workforce, utilities, suppliers, materials — with no capital of its own; ≈900,000 300mm wafers a year per plant at full run rate
- US–Japan Malta fabs vehicle (SPV) → GlobalFoundriesfeestechnology fees from 2027 for at least 20 years, construction-management fees during the build, operating-management fees from ≈2029, shared-services reimbursement and an EBITDA share; ≈$50M of revenue expected in 2027 and ≈$3B of cumulative free cash flow over ten years — GF's estimates, first plant only, subject to definitive agreements; no rate disclosed
- US–Japan Malta fabs vehicle (SPV) → US governmentcash-flow-shareunder the 2025 framework, 50% of available cash flows until Japan has recovered its principal and interest, then 90%; no project document applies it to this vehicle or says where GF's EBITDA share sits in it (contested: project-cash-flow-share)
- US–Japan Malta fabs vehicle (SPV) → Japanese governmentcash-flow-sharethe other 50% until its principal and interest are recovered, then 10% (the same framework, the same caveat)
- US government → GlobalFoundrieschips-reallocationup to $955M of GF's existing CHIPS award reallocated to silicon photonics, SiGe and advanced packaging at Malta and Burlington, the award's total not increased; for R&D and capex from 2027, about 80% to capex by GF's CFO
- GlobalFoundries → US governmentshares≈4% of GF to the Commerce Department under a separate agreement not yet entered into on Nov 4 2026 — no price, share count or stated consideration; ≈7% with the earlier stakes 'when all agreements are finalized'
Resolved figures 22 each with the verbatim line from its document
- program-ceilingup to $21Bup to $21 billion for the two plants — GF's figure for the initiative ('with Japan providing up to $21 billion in funding' in its Q3 interim report), and a ceiling in GF's and Japan's documents and in Commerce's first post: Japan's ministries say the project 'could potentially expand to approximately 21 billion USD', GF's deck says 'Up to $21bn for Phase 1 & 2' and Commerce's Oct 14 post 'up to $21 BILLION'. Whether any of it is committed is contested (commitment)
“at its Malta, New York, site under a U.S.-Japan initiative providing up to $21 billion in funding.”
GF release, Oct 14 2026 (6-K ex-99.1) · sec.gov - first-plant$10B≈$10B for the first plant, a new 300mm fab expected online in 2029 — GF's figure, repeated in its Q3 interim report ('approximately $10 billion of investment in an initial facility expected to become operational in 2029'), and Japan's own figure for the project (japan-project-cost). GF's CEO: ready for equipment during 2028, first wafers out during 2029. GF's Nov 4 release says its construction is 'already underway'
“An initial investment of approximately $10 billion will accelerate construction of a new 300mm semiconductor fab, which is expected to come online in 2029.”
GF release, Oct 14 2026 (6-K ex-99.1) · sec.gov - second-plant$10B≈$10B more 'would fund a second fab' — conditional: GF's decks say 'Phase 2 fab is subject to approval', and its CEO puts the decision before the end of 2028 (phase-2-decision). GF's two ≈$10B figures leave about $1 billion of the 'up to $21 billion' unplaced, and no document explains it; the Times Union's 'another $11 billion' is contested (second-plant-cost)
“An additional investment of approximately $10 billion would fund a second fab.”
GF release, Oct 14 2026 (6-K ex-99.1) · sec.gov - japan-project-cost$10BJapan's own figure, from the one release its foreign, trade and finance ministries issued (Oct 15 2026, Tokyo time): 'approximately 10 billion USD (approximately 1.6 trillion JPY)', construction 'scheduled to begin by the end of 2026', and the project 'could potentially expand to approximately 21 billion USD in the future through the expansion of production facilities'. The release names no company — 'a semiconductor manufacturing project in the State of New York', the first under the initiative — and lists 'AI data centers' among the uses of its mature-node chips, beside automobiles, industrial machinery and smartphones; GF's release names 'automotive, industrial and connected infrastructure markets'
“The estimated total project cost under the Initiative will be approximately 10 billion USD (approximately 1.6 trillion JPY), with construction scheduled to begin by the end of 2026.”
Japan MOFA release (joint with METI and MOF), Oct 15 2026 · mofa.go.jp - loan-commitmentnot yet committed on Japan's side: the finance ministry's materials for its Fiscal Investment and Loan Program subcommittee (Oct 28 2026) table JBIC's co-financing commitments under the initiative at the end of September 2026 — five projects, each with a signing date and amount — and place the New York project, at up to $21 billion, only in a footnote to the row '承諾には至っていないが発表済の案件を含めた場合' (including projects announced but not yet at a commitment). The same materials put it at '約3兆円' (about ¥3 trillion). The translation is ours; the quote is the footnote's own words
“②ニューヨーク州における半導体製造プロジェクト(最大210億ドル)がある。”
Japan MOF, FILP subcommittee materials (Oct 28 2026) · mof.go.jp - japan-may-declinethe framework lets Japan decline: under the US–Japan memorandum of Sep 4 2025 (MOF's copy), Japan funds an investment no less than 45 business days after it is told the President has selected it, may 'elect not to fund' it — and then takes a reduced share of distributions until the US has caught up on the unfunded amount, and may face tariffs 'at the rate determined by the President' — and the memorandum 'does not create legally binding rights and obligations'. It sets the initiative's terms, not this project's: no project agreement is in any document
“Japan may, in its sole discretion, elect not to fund an Investment Amount for an Investment and will consult with the United States prior to any decision to not so fund.”
US–Japan memorandum on strategic investment (Sep 4 2025), as published by Japan's MOF (Oct 16 2025) · mof.go.jp - phase-2-decision2028the second plant waits on a go/no-go decision 'between the stakeholders before the end of 2028' — before the first plant's first wafers in 2029. If approved, it 'would follow the same sequence, beginning with engineering studies and permitting'. GF's decks: 'Phase 2 fab is subject to approval'. Bloomberg's report that the second plant goes ahead after the first, depending on demand, describes the same gate. Who the stakeholders are and what decides it, no document says
“The second fab will proceed after a go/no-go decision between the stakeholders before the end of 2028.”
GF investor webinar, CEO Tim Breen (Oct 14 2026; StockAnalysis transcript) · stockanalysis.com - capacity900,000about 900,000 300mm wafers a year from the first plant at full operation, and 'approximately the same amount' from a second — up to ~1.8M a year for both, on GF's 300mm-equivalent basis. GF's figures alone; the Times Union's 1.3 million is a campus total (malta-capacity)
“The first fab is expected to add approximately 900,000 300mm wafers of annual U.S. manufacturing capacity when fully operational.”
GF release, Oct 14 2026 (6-K ex-99.1) · sec.gov - jobs27,000about 27,000 construction and ecosystem jobs for the whole two-plant project, not per plant, and separately more than 1,000 manufacturing jobs — GF's projection, not a count. The Times Union's '27,000 construction workers would be needed to build each factory' is not supported by any party's document, and Commerce's '28,000 American jobs' (Oct 22) is the two figures added. Whether the 1,000+ covers both plants is contested (manufacturing-jobs-scope)
“The project is expected to create about 27,000 construction and ecosystem jobs and more than 1,000 high-skilled manufacturing jobs in New York's Capital Region.”
GF release, Oct 14 2026 (6-K ex-99.1) · sec.gov - vehiclea vehicle owned by the US and Japanese governments is to fund and own the plants' buildings and tools, and its obligations 'encompass the entirety of the funding requirements, project development, construction, ramp operations, technology, and management fees' — GF's fees come out of it. GF's decks: 'Special Purpose Vehicle (SPV) Owned by the U.S. & Japanese Governments'; the White House (Oct 2026): 'jointly owned by the United States and Japan'. No document names the vehicle or gives the split; only Commerce Secretary Lutnick says 'evenly co-owned' (Saratoga Today). The CFO's figures are 'subject to the signing of definitive agreements'
“In terms of the core structure, a dedicated special purpose vehicle or SPV, owned by the U.S. and Japanese governments, will fully fund and own the fab infrastructure and the tooling capacity.”
GF investor webinar, CFO Sam Franklin (Oct 14 2026; StockAnalysis transcript) · stockanalysis.com - no-gf-capitalGF puts in no capital: 'Japan will provide the investment' (GF's release); Reuters: 'Japan will provide all of the investment capital under the deal'. GF's CEO on the webinar: the technology scope is its 'FDX, BCD, and UX platforms' — BCD 'in very high demand for power management, with particular growth for powering tomorrow's AI data centers'
“As Tim has outlined, the distinguishing feature of this structure is that GF will be enabling significant incremental manufacturing capacity here in the U.S. without directly incurring the associated capital investment.”
GF investor webinar, CFO Sam Franklin (Oct 14 2026; StockAnalysis transcript) · stockanalysis.com - gf-feeswhat GF is paid, in four parts: technology fees 'expected to commence in 2027 and run for a minimum of 20 years'; construction-management fees during the build; operating-management fees from about 2029, as the first plant comes online; and an EBITDA share 'eligible from first production' — plus reimbursement of shared services, 'funded as part of the SPV's annual operating budget'. No rate or percentage is disclosed. GF's Q3 release: 'compensated through management and technology fees over the life of the project'
“In exchange for undertaking these services, GF will earn construction and operations management fees, technology fees, as well as a share of the future EBITDA generated by the SPV.”
GF investor webinar, CFO Sam Franklin (Oct 14 2026; StockAnalysis transcript) · stockanalysis.com - gf-2027-revenue$50M≈$50M of revenue for GF in 2027, upon final close — the CFO's estimate for the first plant only, non-IFRS and subject to definitive agreements. GF gives no figure for later years: only margin accretion (gross 30–50 basis points in 2027, 100–200 long term) and EPS accretion ($0.10–$0.15 in 2027, $0.50–$0.75 long term)
“Upon final close of the agreements, we expect revenue contribution of approximately $50 million in 2027.”
GF investor webinar, CFO Sam Franklin (Oct 14 2026; StockAnalysis transcript) · stockanalysis.com - gf-cash-flow$3B≈$3B of cumulative free cash flow to GF over ten years from the fees — the CFO's estimate for the first plant, which he says is structured so GF's 'profit per wafer' is 'comparable to what GF would have earned had the capacity been built internally'. A projection, not a contract
“Given the capital efficiency of this structure, we expect the technology and fab management services model to generate approximately $3 billion of cumulative free cash flow over the next 10 years.”
GF investor webinar, CFO Sam Franklin (Oct 14 2026; StockAnalysis transcript) · stockanalysis.com - project-termat least 20 yearsat least 20 years, GF's CEO; the technology fees run 'for a minimum of 20 years' from 2027. Not the memorandum's own 20-year figure, which is a term in its allocation formula
“The term of the project will be for a minimum period of 20 years.”
GF investor webinar, CEO Tim Breen (Oct 14 2026; StockAnalysis transcript) · stockanalysis.com - framework-split90%the framework's split of cash flows, from JBIC's SEC-filed financial statements: 50% to the US and 50% to Japan 'until the principal and interest, including guarantee fees, funded by the Japan Investment Entities, have been fully recovered', then 90% to the US and 10% to Japan. The memorandum (paragraph 13, MOF's copy) sets the same two stages. It is the initiative's rule; whether and how it applies to this vehicle, and where GF's EBITDA share sits, is contested (project-cash-flow-share)
“In addition, available cash flows generated by investees of the Japan Investment Entities from investments in the United States are distributed 50% to the United States and 50% to Japan until the principal and interest, including guarantee fees, funded by the Japan Investment Entities, have been fully recovered. Thereafter, such cash flows are distributed 90% to the United States and 10% to Japan, taking into account the various contributions made by the United States.”
JBIC consolidated financial statements, notes (SEC exhibit 99.2, 2026) · sec.gov - chips-reallocation$955M$955 million of GF's existing CHIPS Act award, reallocated by agreement with Commerce to silicon photonics, SiGe and advanced packaging at Malta and Burlington, Vermont — 'up to $955 million' in Commerce's own release (chips-commerce). GF's CEO on the webinar: 'towards R&D and capital expenditures beginning in 2027', to 'strengthen U.S. supply security for AI data centers'; its CFO on Nov 4: 'About 80% of that $955 million we expect we'll allocate towards CapEx', most of it in 2027. GF's Q3 release adds 'including the first U.S.-based source of silicon interposers' (tsmc-globalfoundries); no document says how much of the $955M goes to which line
“GF has also agreed with the U.S. Department of Commerce to amend its existing CHIPS and Science Act award to reallocate $955 million and accelerate the company’s investments in silicon photonics, silicon-germanium (SiGe) and advanced packaging at its facilities in Malta, New York, and Burlington, Vermont.”
GF release, Oct 14 2026 (6-K ex-99.1) · sec.gov - chips-commerceup to $955MCommerce's side of the same amendment: 'up to $955 million', which 'will increase the portion of an existing CHIPS Program award allocated to' GF's Malta and Burlington facilities; the investment, it says, 'will expand domestic manufacturing capacity for technologies increasingly critical to communications infrastructure and data centers, including silicon photonics, silicon-germanium and the first U.S.-based source of silicon interposers supporting advanced packaging technologies'. Commerce's release names neither Japan nor the equity
“The Department of Commerce’s CHIPS Program Office has agreed with GlobalFoundries to amend its existing award and reallocate up to $955 million in incentives under the CHIPS and Science Act.”
Commerce (CHIPS Program Office) release, Oct 14 2026 (nist.gov) · nist.gov - award-not-increasednot new money: the $955M moves within GF's existing award — up to $1.587B of direct funding, on NIST's award page — whose total does not change. GAO's table of award lines (Commerce data as of July 2025) lists 'GlobalFoundries New York Fab 8.2' at $955,000,000, the same sum; no document says the reallocated money is that line (fab-8-2-overlap). The President's post reads it as new money — 'My Commerce Department will invest 955 Million Dollars' — and adds a total (federal-total)
“The total amount of the existing CHIPS Program award will not be increased.”
Commerce (CHIPS Program Office) release, Oct 14 2026 (nist.gov) · nist.gov - gf-capex-5b$5B$5B of capital investment by GF at its existing Malta and Burlington facilities, which GF agreed to as part of the amendment — Commerce's figure, in its release's subheading too ('GlobalFoundries’ $5 billion investment at its existing facilities'); GF's own documents on file do not restate it. GF's own money, separate from the CHIPS award and from Japan's
“As part of the amendment, GlobalFoundries has agreed to expand its capital investment in these facilities to $5 billion.”
Commerce (CHIPS Program Office) release, Oct 14 2026 (nist.gov) · nist.gov - equity-4pct4%≈4% of GF to the US government under 'a separate agreement' — 'approximately four percent' in GF's Oct 14 release, which says the Commerce Department 'will receive' it; on Nov 4 the agreement was still to 'be entered into'. No document gives its price, share count or what GF receives for it: GF's CEO gives 'recognition of the growing role that GF is playing'. GF's CFO guides ≈575M diluted shares for Q4 2026, 'which reflects the expected issuance of equity to the U.S. government', and ≈600M from 2027, subject to the timing of the remaining issuances. What the stake is consideration for is contested (equity-consideration)
“In recognition of the growing role that GF is playing in the U.S. semiconductor ecosystem, a separate agreement will be entered into to issue 4% equity to the U.S. government, which provides a vehicle for the American people to share in GF's future success.”
GF Q3 2026 earnings call, CEO Tim Breen (Nov 4 2026; StockAnalysis transcript) · stockanalysis.com - usg-total7%≈7% in all once every announced agreement is final — the ≈4% here plus the earlier quantum, silicon-photonics and advanced-packaging stakes (according to GF's CEO, after every tranche was announced). A forward total, not a holding: the shares issued by Sep 30 2026 are 9,907,399 (usg-stake-before). GF's CEO adds that its board and 'our U.S. government partners do not plan on any further government equity position beyond these announced equity stakes'. An outside model's ≈5% leaves out the photonics stake
“Combined with previous announcements across our quantum, silicon photonics, and advanced packaging investments, we anticipate the total equity ownership of the U.S. government to be approximately 7% when all agreements are finalized.”
GF Q3 2026 earnings call, CEO Tim Breen (Nov 4 2026; StockAnalysis transcript) · stockanalysis.com
Contested figures 11 not reconciled — every position side by side, with its source and tier
Scope note what this record leaves to other records
NOT this record (not carried here): New York State's $570M for GF's Fab 8 projects (its 2025 agreement) and the earlier figures for GF's own US investment plan ($11.6B → more than $12B → about $13B → about $14B → $16B, 2024–2025) — GF's CHIPS-era expansion, which this deal may or may not overlap (fab-8-2-overlap); the quantum ($375M, final Sep 2026) and silicon-photonics ($300M, letter of intent Jul 2026) R&D awards and the equity tied to each (only the ≈7% total and the shares already issued are here); an outside model's 2030 fee scenarios ($150M / $320M / $400M, one dossier's bear, base and bull cases, with no primary behind them); GF's quarterly results; the St. Louis Fed's and Breakingviews' analyses of the $550 billion framework. The TSMC interposer agreement is its own record (tsmc-globalfoundries); this record holds the CHIPS money GF ties to interposers. Not circular: Japan funds a vehicle that pays GF fees, and GF puts no money back in; Japan's ministries name Tokyo Electron and SCREEN as interested tool suppliers and Renesas as an interested buyer, and GF's CEO told Reuters some of Japan's capital 'will flow back' to toolmakers such as Tokyo Electron (Reuters' paraphrase) — Japanese suppliers selling to a Japan-funded plant, not money returning to its funder. Not adopted: the White House's and Commerce's unhedged '$21 billion' (commitment); Lutnick's 7% 'because of the scale of this investment', against GF's ≈4% for this agreement and ≈7% in all (equity-consideration); Reuters' 'previously held a 3% stake' (usg-stake-before); the President's 'will invest 955 Million Dollars' and '1.63 Billion Dollars' (award-not-increased, federal-total); the Times Union's '27,000 construction workers … to build each factory', where GF's 27,000 is for the project (jobs); Commerce's '28,000 American jobs', GF's 27,000 and 1,000+ added together.