Talen Energy
An independent power producer that owns 90% of the Susquehanna nuclear plant in Pennsylvania. It sold Amazon the data-center campus next to the plant and now sells Amazon the plant's power — the deal that started the national fight over whether a data center wired straight into a reactor still has to pay for the shared grid.
1 deal (1 T1) · 2 flows on the money map ·
Where it standsfrom Talen Energy’s 10-Q for the quarter to Sep 30, 2026
Deals 1
- Mar 2024 updated Nov 19
Money in and out 2 ribbons
Who pays Talen Energy (left), and whom it pays (right). Width is a rough size in $B, per year for multi-year deals.
← swipe to see the whole chart →
sourced deal · 1 of 2 estimated size · 1 of 2
As a table · 2 ribbons
Notes in the record on Talen Energy
Susquehanna: two BWR units, 90% Talen / 10% Allegheny Electric Cooperative, NRC licences to 2042 and 2044; ~17 TWh in 2025 at ~$27/MWh all-in (<$24 in 2023–24). AWS: $650M campus sale (Mar 2024) + PPA up to 960 behind-the-meter (Mar 2024) → 1,920 MW through 2042 (Jun 2025), front-of-meter since Apr 2026 (pw-amzn-talen). Fleet size is a time series, not a dispute — Talen's own 'approximately N of power infrastructure' line, in its own words, document by document (the first point is a results release, the rest are filings): 12.4 GW (Mar 2024) → 10.7 GW (FY24/Q1'25, after the 1,710 MW ERCOT portfolio sale to CPS Energy for $785M) → 10.5 GW (Q2'25) → 10.3 GW (Q3'25) → 13.1 GW (FY25/Q1'26: Freedom 1,045–1,049 MW + Guernsey 1,771–1,836 MW gas — summer ratings, low–high; the Q3'25 10-Q announced 1,045 / 1,836 and the FY25 10-K properties table lists 1,049 / 1,771, unexplained — $3.8B gross / $3.5B net of tax benefits, closed Nov 2025) → 15.7 GW (Q2'26; Cornerstone — Lawrenceburg 1,120 + Waterford 875 + Darby 456 MW from ECP for $3.45B = $2.55B cash + 2.4M shares as signed Jan 2026; closed Jun 15 2026 at $3.5B = $2,617M cash + 2,399,998 shares at $386.21 = $927M, $3,544M total (Q3'26 10-Q, which revised the Q2'26 10-Q's $2,615M and $3,542M 'for nonmaterial working capital adjustments'), adding ~2.6 GW, inside the quarter) → 15.5 GW (Q3'26, filed Nov 3 2026: 'approximately 15.5 GW of power infrastructure in the United States, including 2.2 GW of nuclear power', the same 2.2 GW as Q2'26; Cornerstone is the only 2026 acquisition in its Note 17, whose one 2026 divestiture is Talen's 12.34% interest in the Keystone generation facility and certain related assets — agreed in June 2026 for $85M cash, closing expected in the second half (Q2'26 10-Q), sold in Sep 2026 for $73M cash after closing working capital and other purchase price adjustments, a $66M gain, final proceeds subject to a post-closing true-up; the 10-Q gives no MW for that interest and does not say the sale is what lowered the line). The summer-rated fleet tables are a different basis, not further values: 10,665 MW (Jun 2024) / 10,676 MW (Sep 2024); the FY25 10-K table totals 16,757 MW gross / 13,108 MW owned. Two acquisitions with similar price tags (Freedom/Guernsey $3.5B net; Cornerstone $3.5B at close): do not merge. Bought TeraWulf's 25% of the Nautilus cryptomine JV on the campus for $85M cash + ~$7M of miners (Oct 2024; both registrants agree); the revised AWS PPA terminates the Nautilus lease.