Fluidstack

A UK-registered, New York-headquartered AI cloud company that, since 2025, has leased whole data-center buildings from former bitcoin miners to fill with computing capacity for AI labs. Google guarantees much of that rent, and in November 2025 Anthropic named it the builder of its $50 billion US data-center programme. It is private: its last published accounts, for 2024, describe a business far smaller than the leases it has since signed, and no filing names the customers behind them.

5 deals (5 T1) · 4 flows on the money map ·

Deals 5

sort: · · ·
  1. Dec 17, 2025 updated Nov 20
  2. Nov 12, 2025 updated Nov 21
  3. Oct 28, 2025 updated Nov 21
  4. Sep 25, 2025 updated Nov 20
  5. Aug 14, 2025 updated Nov 20

Money in and out 4 ribbons

Who pays Fluidstack (left), and whom it pays (right). Width is a rough size in $B, per year for multi-year deals.

← swipe to see the whole chart →

sourced deal · 3 of 4 estimated size · 1 of 4 full amount, no yearly rate · 1 of 4

As a table · 4 ribbons
Timeline 7 dated entries
  1. Jul 2026Series A announced (Jul 20): '$830M … at a $7.5B valuation, led by Situational Awareness', raised in January (T1 company post; Forbes: $750M) · a Fluidstack-led group agrees to buy TeraWulf's 50.1% of its Abernathy landlord for ~$530M (T1 8-K) — fs-terawulf-abernathy
  2. Jun 2026AI XPV: $35B chip-financing tranche for Anthropic's >1 GW 'expected to deploy in Fluidstack-based sites starting in mid-2026' (T1 Broadcom release) — anth-fluidstack
  3. Dec 2025River Bend LA: 15-yr lease from Hut 8 (Fluidstack USA IV), 245 MW, $7.0B base; Google backstops all base-term rent; Hut 8 calls it a partnership 'for Anthropic' (T1) — fs-hut8-river-bend
  4. Nov 2025Anthropic names Fluidstack the builder of its $50B US programme, Texas and New York (T1 both posts) — anth-fluidstack · Barber Lake expanded to 207 MW / ~$3.8B; Google backstop to $1.73B (T1 Cipher) — fs-cipher-barber-lake
  5. Oct 2025Abernathy TX: JV with TeraWulf (Fluidstack CS I 49.9%) leases 168 MW to Fluidstack USA III for 25 years, ~$9.5B; Google backstop $1.3B, no TeraWulf warrants (T1 8-K), but Fluidstack warrants for up to 7,786,250 of its shares to Google, pledged to the noteholders during construction (T1 notes indenture, Dec 2025) — fs-terawulf-abernathy
  6. Sep 2025Barber Lake TX: lease from Cipher (Fluidstack USA II), 168 MW critical IT, ~$3B over 10 years; Google backstops $1.4B for ~5.4% of Cipher in penny warrants (T1 8-K; values furnished) — fs-cipher-barber-lake
  7. Aug 2025Lake Mariner NY: three 10-yr leases from TeraWulf (Fluidstack USA I), ~$3.7B → ~$6.7B with CB-5 (furnished); Google backstop $1.8B → ~$3.2B for 73,580,000 TeraWulf penny warrants (T1 8-Ks) — fs-terawulf-lake-mariner

Timeline entries carry no source field yet; some name one inline.

Notes in the record on Fluidstack

Fluidstack Ltd (England & Wales, Companies House 10985545; 'New York Headquartered' per its Nov 2025 post). Tenant of record, through one US subsidiary per campus, in every lease of this monitor's Fluidstack ledger: Fluidstack USA I (Lake Mariner NY, TeraWulf — fs-terawulf-lake-mariner), USA II (Barber Lake TX, Cipher — fs-cipher-barber-lake), USA III (Abernathy TX, TeraWulf JV — fs-terawulf-abernathy, where Fluidstack CS I Inc. also owned 49.9% of the landlord), USA IV (River Bend LA, Hut 8 — fs-hut8-river-bend); anth-fluidstack is the $50B umbrella. Accounts (the last published): FY2024 group revenue £52.7M (2023: £21.9M), a £556k loss, 'over £44 million in compute hardware', a £19.7M SAFE round — GBP; the USD figures in press ($66M etc.) are Forbes' conversions. Funding: Series A '$830M … at a $7.5B valuation, led by Situational Awareness', raised January 2026, announced Jul 20 2026 (company) — Forbes says $750M, Bloomberg reported talks for ~$700M at $7B (Dec 2025): a spread no source reconciles; a '$1.5 billion round led by … Jane Street' at 'over $18 billion' rests on Forbes alone (Sep 2026; Bloomberg had talks for ~$1B at $18B in Apr 2026). over Fluidstack's own shares: Companies House resolutions (25 Nov 2025, 2 Apr 2026) authorise and ratify them — image scans that name no holder; nothing on the record says who holds them. Own sites, no Anthropic named: Cameron County TX ('$4B first phase', 'up to 1.5 '), Okmulgee OK ('The data center’s first tenant will be Jane Street'), Wythe County VA, Glendale AZ. Meridian Arc (Sullivan County IN — 'a joint venture between Next Frontier and Fluidstack' per Bloomberg's relay; $5.7B 6.25% 144A notes per deal counsel; ~430 ; Google support reported; lease unfiled, no SEC filer) is a follow-up item, not a record. Not adopted: SemiAnalysis's revenue mis-read as Fluidstack's; Sacra's '$180M ARR'; TechTimes' '$50B of contracted revenue'.