Why it matters
A frontier lab's compute contract with STN, expected to bring up to $7.5B for about 65 , now sits in a venture ChronoScale manages and funds. $200M of ChronoScale's $220M loan is directed to Super Micro for GPUs. ChronoScale's papers differ on the rest: its deck calls ~350 MW and ~$43.7bn, options included, contracted; its release lists as a risk that the lab has no commitment to order phases 2 or 3.
Tap a figure for the line in its source.
STN gives OD1 JV Holdings
- in kind, at an agreed value: the GPU Services Agreement with the unnamed lab, the ground sublease of the site and the project's other assets, for 3,900,000 units — the rest of its $390M commitment is cash, owed only after a project financing of at least 75% of the budget
ChronoScale gives
- of value committed for 3,900,000 units, 50%, issued on US antitrust (HSR) clearance: a $220M loan at the closing that converts then, STN's own $30M note, a $10M item the filing redacts and the rest in cash later, as the project needs it — and, until a project financing, whatever more the project needs, with no cap specified → OD1 JV Holdings
- a at $0.001 a share, vesting in three parts on milestones for this project and certain future data-center developments a ChronoScale subsidiary finances, its issue and vesting subject to STN's member funding its contributions → STN
OD1 JV Holdings gives Supermicro
- for GPUs: the note directs that much of ChronoScale's loan straight to Super Micro on the closing date
Lenders & bondholders gives OD1 JV Holdings
- a 90-day loan from Macquarie Equipment Capital at a fixed 10%, secured on the venture's assets, GPUs included, with no recourse to ChronoScale — it repays part of STN's existing Macquarie loan
Applied Digital gives ChronoScale
- STN's own subordinated note, held by Applied Digital's affiliate and assigned to ChronoScale for cash or shares at $8.00; ChronoScale contributes it to the venture as part of its $390M
What happened
STN is a developer building an AI data-center campus in Odessa, Texas. It had a contract to supply GPU computing there to an unnamed frontier AI lab. On Nov 18 2026 it moved that contract into a new venture with ChronoScale, a listed GPU cloud company. STN put in the contract, its lease on the site and the project's assets, at an agreed value of about $252M. ChronoScale lent the venture $220M. The loan's terms direct $200M of it straight to Super Micro to buy GPUs. The loan is to turn into half of the venture's units on US antitrust clearance. ChronoScale manages the venture. Each side is to put in $390M of value for half. Part of each side's share is cash due later. STN owes its cash only after the venture closes project financing for at least 75% of its budget. Until then, ChronoScale must fund whatever the project needs, with no cap specified. Macquarie lent the venture $74.7M for 90 days, without recourse to ChronoScale, to repay part of STN's existing Macquarie loan. The lab's contract covers four batches of capacity, an expected 65 in all, each for about six years. ChronoScale expects it to bring the venture up to $7.5B if everything is delivered and performed. The lab may end the contract for batches that are late or keep missing service levels, though cure rights may apply. Credit support from an unnamed investment-grade technology company a substantial portion of the first phase. ChronoScale is also to give the lab a for up to 8.07M of its shares at a cent each. Half would vest as the four batches are delivered and accepted. The other half needs a new take-or-pay deal for at least 40 MW of critical IT load at a second ChronoScale site, delivered and accepted. The 8-K expects the first batch in late 2026; both companies' releases put the first phase in the first half of 2027. ChronoScale's investor deck calls about 350 MW and about $43.7bn contracted, counting all orders, options and extensions. Its 8-K counts only the four batches, and its release lists among its risks that the lab has no commitment to order phases 2 or 3.
Sources 15 documents — 14 SEC filings · 1 company release
Research trail Found 133 documents and read 113 of them while checking this deal and related ones.
- States 15 figures: GPU services agreement · up to $7.5B contract value · credit support · termination · customer warrant · 40 MW warrant vesting · manager · $390M stn contribution · $251,923,177.23 stn contributed assets · $220M partnership note · funding before financing · $74,687,500 term loan · 10% term loan terms · stn warrant · $30,000,000 stn note
- States 4 figures: 285 MW right of first offer · $20.8M revenue per MW · $500M financing headline · strategic investors
- States 2 figures: 65 MW project capacity · 65 MW power
- States 2 figures: stn deferred cash · $390M chronoscale contribution
- States 2 figures: closing · $153M common placement
- States $200M GPU purchase
- States deck tranches
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: ChronoScale 8-K, Items 1.01/2.03/3.02/5.03/5.07/8.01, with ex-10.4 (Contribution Agreement) and ex-99.1 (release), filed Nov 18 2026; 8-K/A No. 1 (ex-99.2, investor presentation, slide images) and 8-K/A No. 2 (closing; ex-4.2 note, ex-10.5 note assignment, ex-10.6 LLC agreement, ex-10.7 term loan), filed Nov 18 2026; STN release (GlobeNewswire, Nov 18 2026) — read 2026-11 · as of Nov 2026
The evidence 27 sourced figures · 2 disputes
The record's headline ChronoScale–STN, Odessa TX: a venture to be owned half each takes over STN's GPU services contract with an unnamed frontier AI lab — four tranches, an anticipated 65 , expected to bring up to $7.5B over about six years, a substantial portion of the first phase backstopped by credit support from an unnamed investment-grade technology company — on ChronoScale's $220M loan to the venture ($200M of it directed to Super Micro for GPUs), beside a 90-day $74.7M Macquarie loan that repays part of STN's Macquarie debt; ChronoScale is to give the lab a penny , half vesting on deliveries; its investor deck calls ~350 MW and ~$43.7bn, options and extensions included, contracted, while its release lists among its risks that the lab has no commitment to order phases 2 or 3
- Size
- up to $7.5B over about six years (the four tranches, an anticipated 65 MW of gross load; extensions and additional tranches excluded) · $390M of value from each member for half · ChronoScale's $220M convertible note, $200M of it to Super Micro for GPUs · $74,687,500 Macquarie term loan, 90 days · the lab's warrant: up to 8,072,152 ChronoScale shares at $0.01 · the investor deck's ~$43.7bn across ~350 MW counts all orders, options and extensions (contested)
- When
- Oct 9 2026 (STN's $30M note to Applied Digital's affiliate) → Nov 17 (Contribution Agreement) → Nov 18 (8-K, both releases, the investor deck; the closing) → Q4 2026 first tranche expected (8-K) → H1 2027 the other three tranches (8-K) or the first phase (releases) → the term loan due 90 days after the closing → ChronoScale's note converts on HSR clearance
- Status
- signed Nov 17 2026; closed Nov 18 2026 (8-K/A No. 2): the LLC agreement entered, the $220M note issued, the term loan entered, the Partnership the provider under the GPU Services Agreement, the STN warrant issued, the note assignment entered. Still to come at the last filing on file: HSR clearance, on which ChronoScale's note becomes its half of the units; the lab's warrant, which the 8-K says ChronoScale 'will issue' and 8-K/A No. 2 does not list as issued; and a qualifying project financing, none named. The first tranche is expected in Q4 2026 (8-K); no document on file says a tranche has been delivered and accepted. The investor deck says '~1K GPU clusters already live and serving Customer today' and 'Phased delivery has already started' (slide 10, an image); it does not say where those GPUs are, and no document on file ties them to a tranche
- Structure
- a Contribution Agreement of Nov 17 2026 among OD1 JV Holdings LLC (the 'Partnership'), CHRN OD1 Holdings LLC (ChronoScale's subsidiary), STN OD1 Holdings LLC (STN's affiliate), ChronoScale and STN One Incorporated as guarantors, and RXT Power, LLC (STN's indirect subsidiary, the sublandlord of the site). STN's side contributes the GPU Services Agreement (Order #1) with an unnamed 'leading frontier artificial intelligence lab', the project's other assets, a leasehold under a ground sublease and a license to STN's technology, for 3,900,000 common units; ChronoScale's side lends $220M on a note that converts into 3,900,000 units on HSR clearance. The Partnership takes the GPU Services Agreement 'by assignment and novation from STN' and becomes the provider; Macquarie Equipment Capital lends it $74,687,500 for 90 days; ChronoScale issues warrants to STN and to the lab. The 'Project' is the first four tranches of 'Project Landman', 'an anticipated sixty-five (65) megawatts of gross load' (Ex. 10.4). The GPU Services Agreement itself is not filed
- Programme
- ChronoScale–STN
- Parties
- STN developer — contributed the lab contract, the site lease and the project's assets for half the venture; guarantor; leads campus development; holds a warrant on ChronoScale; owes cash for the rest of its $390M only after a qualifying project financing · ChronoScale manager and funder — lent the venture $220M, convertible into half of it on HSR clearance, and must fund the project, with no cap specified, until a qualifying project financing; guarantor; issuer of the lab's and STN's warrants · OD1 JV Holdings the venture — provider under the lab's GPU Services Agreement, borrower of the Macquarie loan and of ChronoScale's note, buyer of the GPUs · Supermicro GPU vendor — $200M of ChronoScale's loan is directed straight to it for the venture's GPUs · Lenders & bondholders Macquarie Equipment Capital Inc., administrative agent and sole lender of the 90-day term loan, and STN's existing lender · Applied Digital ChronoScale's controlling stockholder; its affiliate APLD Intermediate held STN's $30M note and assigned it to ChronoScale
- Record
- disclosed / primary source · as of Nov 2026
Flows 6 as the record states them
- STN → OD1 JV Holdingsin-kind-contributionthe GPU Services Agreement with the unnamed lab, the ground sublease of the site, the project's other assets and a license to STN's technology, at an agreed value of $251,923,177.23, for 3,900,000 common units; the rest of its $390M obligation, plus the Macquarie Payment Amount and a Project Cost Adjustment Amount, in cash within 90 days of a Qualified Project Financing, and nothing if none occurs (Ex. 10.6)
- ChronoScale → OD1 JV Holdingsjv-capital$220M on an unsecured convertible note at 8% paid in kind, converting on HSR clearance into ChronoScale's 3,900,000 units (50%); with STN's $30M note, a redacted $10M item and deferred cash, $390M in all (Ex. 10.6); and uncapped funding until a Qualified Project Financing
- OD1 JV Holdings → Supermicrogpu-purchase$200M of the note's proceeds, to be disbursed by ChronoScale's member directly to Super Micro on the closing date for the venture's GPUs (Ex. 4.2); GPU count and price not in the note
- Lenders & bondholders → OD1 JV Holdingsdebt$74,687,500 from Macquarie Equipment Capital, sole lender: 90 days at a fixed 10% paid in kind, a first-priority lien on the venture's assets including the GPUs, non-recourse to ChronoScale; the proceeds repay part of STN's existing Macquarie loan and pay fees
- ChronoScale → STNwarrantup to 850,000 ChronoScale shares at $0.001 in three milestone tranches, forfeited if unvested at three years; issued at the closing (8-K/A No. 2)
- Applied Digital → ChronoScalenote-assignmentSTN's $30,000,000 subordinated note of Oct 9 2026, assigned by APLD Intermediate for cash equal to its principal and interest or for shares at $8.00, at ChronoScale's election; contributed to the venture at an agreed value of $30,000,000 (Ex. 10.6)
Resolved figures 27 each with the verbatim line from its document
- gpu-services-agreementan 'Amended and Restated GPU Services Agreement (Order #1)' with 'a leading frontier artificial intelligence lab (the “Customer”)', which STN had signed and the venture took over at the closing: dedicated GPU services at the Project, made available in four tranches, each with its own service term of about six years that the lab may extend. Further tranches are possible only 'if agreed by the parties in writing'. Its other terms, as listed: acceptance testing, service level commitments, delay discounts, change of control and 'provisions relating to the financing of the GPU systems'. No document on file names the lab
“The Partnership will assume the GPU Services Agreement by assignment and novation from STN. Under the GPU Services Agreement, the Partnership will provide the Customer with dedicated GPU services at the Project, with a service term of approximately six years for each tranche (subject to extension at the Customer’s option).”
ChronoScale 8-K, Item 1.01 (filed Nov 18 2026) — GPU Services Agreement · sec.gov - contract-valueup to $7.5Bup to $7.5B to the venture over about six years — a ceiling and a forecast: it assumes 'full performance and delivery of the contracted capacity' and leaves out extensions and any additional tranches. It is the four tranches' value (the release's forward-looking list: 'the expected up to $7.5 billion TCV of the confirmed 65 MW first phase'), not booked revenue; the release's headline drops the 'up to' ('The initial deployment carries a total contract value of $7.5 billion over six years'). Each tranche has its own term of about six years and the tranches arrive months apart, so payments would run somewhat past six calendar years (the record's reading). No price per GPU-hour, payment schedule or prepayment is disclosed
“the GPU Services Agreement is expected to provide up to $7.5 billion in total contract value to the Partnership over approximately six years, assuming full performance and delivery of the contracted capacity and excluding any extension periods and the additional tranches”
ChronoScale 8-K, Item 1.01 (filed Nov 18 2026) — GPU Services Agreement · sec.gov - project-capacity65 MWan anticipated 65 MW of gross load: the four tranches that make up the 'Project', the first phase of STN's 'Project Landman' campus. Gross load, not critical IT load — the warrant's 40 MW test at a second site is set in critical IT load, a different measure. ChronoScale's release: 'The first 65 MW of the planned deployment of this campus'; STN's: 'The first 65 MW phase has been ordered'. The investor deck's four tranches add up to 62.7 MW 'per Deployment' (deck-tranches)
““Project” means the first four tranches of the data center facility known as “Project Landman,” consisting of an anticipated sixty-five (65) megawatts of gross load”
Contribution Agreement, Ex. 10.4 to ChronoScale's 8-K (filed Nov 18 2026) — definitions · sec.gov - right-of-first-offer285 MWa right of first offer, not an order: 285 MW more at the campus for the agreement's second and third phases 'if those are ordered' — 65 + 285 make the release's 'contemplated 350 MW deployment'. Building it depends, the release says, on 'additional customer orders, exercise of the Company’s right of first offer and agreement on terms', on land, permits, power and interconnection, and on 'substantial additional financing'. Whether the lab has committed to those phases is contested below (phases-2-3)
“The Company has a right of first offer on the remaining 285 MW of capacity at the campus, to support the second and third phases of the agreement, if those are ordered.”
ChronoScale release, 8-K Item 8.01 ex-99.1 (Nov 18 2026) · sec.gov - credit-support'a substantial portion of the first phase' is backstopped by credit support from an investment-grade technology company, which no document on file names; the form and size of the support are not disclosed. The investor deck says more: 'the First 65 MW Backed by Credit Support from an investment-grade technology company', and 'At this time, the Credit Support applies only to Phase 1, and no decision has been made regarding credit enhancement for subsequent phases 2-4' (slide 12, an image)
“A substantial portion of the first phase is backstopped by credit support from an investment-grade technology company”
ChronoScale 8-K, Item 1.01 (filed Nov 18 2026) — GPU Services Agreement · sec.gov - terminationthe lab may terminate 'under certain circumstances', for affected tranches including late delivery and sustained service-level failures, with cure rights that 'may be available'; the venture's own rights are 'more limited', and neither side may terminate for convenience. With the 'delay discounts' among its terms, the $7.5B depends on the venture delivering on time (the record's reading)
“The GPU Services Agreement may be terminated by the Customer under certain circumstances, including, with respect to affected tranches, delayed delivery and sustained service level failures, for which cure rights may be available. The Partnership’s termination rights are more limited, and neither party may terminate for convenience.”
ChronoScale 8-K, Item 1.01 (filed Nov 18 2026) — GPU Services Agreement · sec.gov - customer-warrant8,072,152a penny warrant from ChronoScale to the lab, 'In connection with the GPU Services Agreement and its assignment to the Partnership': up to 8,072,152 ChronoScale shares at $0.01, for cash only, for ten years, with a 4.99% ownership limit the holder may move up to 9.99% and a 19.9% cap; exercise subject to HSR where it applies. ChronoScale 'will issue' it: 8-K/A No. 2 lists the STN warrant among what was done at the closing, not this one, and no filing on file shows it issued. No filing values it
“the Company will issue to the Customer a warrant (the “Services Agreement Warrant”) to purchase up to 8,072,152 shares of Common Stock (the “Services Agreement Warrant Shares”), at an exercise price of $0.01 per share”
ChronoScale 8-K, Item 1.01 (filed Nov 18 2026) — Services Agreement Warrant · sec.gov - warrant-vesting40 MWhalf vests as each of the four tranches is delivered and accepted, in four equal parts (about 1,009,019 shares each, editor's arithmetic); the other half only when the lab signs a take-or-pay agreement with ChronoScale or a subsidiary for at least 40 MW of critical IT load at a second site they own, and that 40 MW is delivered and accepted. Unvested shares lapse if the relevant agreement ends, or on a material payment breach left uncured for 60 days. So the lab earns ChronoScale stock by taking capacity, from this venture and beyond it (the record's reading)
“Fifty percent of the Services Agreement Warrant Shares will vest in four equal sub-tranches upon the delivery and acceptance of each of the four tranches under the GPU Services Agreement, and the remaining fifty percent will vest upon the Customer entering into a take-or-pay offtake agreement with the Company or one of its subsidiaries for at least 40 MW of critical IT load at a second site owned by the Company or one of its subsidiaries (an “Expansion Agreement”) and the delivery to, and acceptance by, the Customer of at least 40 MW of critical IT load from such site”
ChronoScale 8-K, Item 1.01 (filed Nov 18 2026) — Services Agreement Warrant · sec.gov - managerChronoScale's member runs the venture and arranges its project financing; STN's member has consent rights over specified matters and may remove the manager on trigger events such as fraud, gross negligence or bankruptcy. ChronoScale's release: it 'will manage the partnership in cooperation with representatives from STN'; STN's: 'Upon closing, ChronoScale will manage the partnership, while STN will lead campus development.' Distributable cash generally goes to the members pro rata, subject to certain priority payments, a management incentive plan and any project-financing restrictions
“ChronoScale Member serves as manager of the Partnership, subject to consent rights of STN Member over specified matters and STN Member’s right to remove the manager upon certain trigger events, including fraud, gross negligence or willful misconduct in connection with the Project or bankruptcy.”
ChronoScale 8-K, Item 1.01 (filed Nov 18 2026) — A&R LLCA · sec.gov - stn-contribution$390M$390M of value from STN's side for 3,900,000 units, half the venture's common equity once ChronoScale's units are issued. At the closing those units are 100% of the units outstanding: ChronoScale's 3,900,000 come only when its note converts on HSR clearance. ChronoScale's side puts in the same $390M (chronoscale-contribution); the release: 'Each of the Company and STN will contribute $390 million in value to the partnership in exchange for a 50% interest, subject to HSR clearance.'
“STN Member has agreed to make an initial capital contribution of $390 million in exchange for 3,900,000 common units, representing 50% of the common equity of the Partnership.”
ChronoScale 8-K, Item 1.01 (filed Nov 18 2026) — A&R LLCA · sec.gov - stn-contributed-assets$251,923,177.23~$252M ($251,923,177.23): the value the parties agreed for the lab contract, the site's ground lease and the project's assets — an agreed number, not an appraisal or a price paid; the schedule that details it is not filed. The rest of STN's $390M is cash, due only after a 'Qualified Project Financing', and 'If no Qualified Project Financing occurs, STN Member has no obligation to fund such cash balance' (stn-deferred-cash)
“STN Member’s contribution consists of the GPU Services Agreement, the ground lease for the Project site and related Project assets having an agreed value of $251,923,177.23, with the balance payable in cash within 90 days following the closing of project financing for at least 75% of the project budget (a “Qualified Project Financing”).”
ChronoScale 8-K, Item 1.01 (filed Nov 18 2026) — A&R LLCA · sec.gov - stn-deferred-cashSTN's cash, if it comes: $390,000,000 less the $251,923,177.23 contributed, plus the 'Macquarie Payment Amount' — what the venture then owes on the Macquarie loan, paid from the first project financing — plus a 'Project Cost Adjustment Amount' the filed agreement does not quantify. It is due within 90 days of a Qualified Project Financing (one whose principal, with earlier project financings, is at least 75% of the effective-date budget), and is not owed at all if none occurs. The base gap is $138,076,822.77 (editor's arithmetic). Not adopted: press reports' $138.1M as the payment, which leaves out the two amounts the agreement adds
“equal to (i) $390,000,000 (which equals 10.0% of the Project Budget as of the Effective Date), less (ii) $251,923,177.23 (which is the aggregate agreed value of the Subject Lease, the Offtake Agreement and the Other Contributed Assets contributed at the Closing pursuant to Section 3.04(b)(ii)(A)), plus (iii) the Macquarie Payment Amount, plus (iv) the Project Cost Adjustment Amount.”
A&R LLC agreement of OD1 JV Holdings, Ex. 10.6 to ChronoScale's 8-K/A No. 2 (filed Nov 18 2026) — Section 3.04(b)(ii)(B) · sec.gov - chronoscale-contribution$390M$390M from ChronoScale's side, made up as the agreement lists it: $220M in cash at the closing for the convertible note; STN's own $30M bridge note, bought from Applied Digital's affiliate and exchanged into the venture (stn-note); a $10M item whose description is redacted; and the balance — $130M by subtraction (editor's arithmetic) — in cash as the project needs it, due no later than STN's deferred cash. All 3,900,000 of its units are issued when the note converts. The $390M 'equals 10.0% of the Project Budget as of the Effective Date', which puts the Project's budget at about $3.9B (editor's arithmetic; the budget itself is not filed, and the Project is the four tranches, ~65 MW)
“the ChronoScale Holdings Group shall make the ChronoScale Holdings Initial Contribution and the Deferred ChronoScale Contribution in an aggregate amount of $390,000,000 (which equals 10.0% of the Project Budget as of the Effective Date)”
A&R LLC agreement of OD1 JV Holdings, Ex. 10.6 to ChronoScale's 8-K/A No. 2 (filed Nov 18 2026) — Section 3.04(b)(i)(A) · sec.gov - partnership-note$220M$220M lent at the closing (the note issued Nov 18, 8-K/A No. 2) at a fixed 8% paid in kind monthly, subordinated to the Macquarie loan. On HSR clearance its principal converts, the accrued interest is cancelled and ChronoScale's 3,900,000 units, half, are issued for its whole $390M package (chronoscale-contribution). If clearance has not come, the note matures 91 days after the Macquarie loan does. Until it converts, ChronoScale's member has a member's rights except distributions
“ChronoScale Member will fund a $220 million loan to the Partnership in exchange for an unsecured convertible promissory note (the “Partnership Convertible Note”), which will automatically convert into common units of the Partnership upon clearance under the Hart-Scott-Rodino Antitrust Improvements Act of 1976”
ChronoScale 8-K, Item 1.01 (filed Nov 18 2026) — STN Contribution Agreement · sec.gov - gpu-purchase$200M$200M of ChronoScale's $220M loan goes from ChronoScale's member straight to Super Micro Computer, Inc. ('or the applicable Affiliate thereof', the 'GPU Vendor'), 'solely to fund the purchase of GPUs', on the venture's behalf; the other $20M goes to the venture for general purposes. The note gives no GPU count, model or price, and no filing on file confirms the payment. Whether Super Micro finances anything in return, no document says
“Company hereby irrevocably authorizes and directs the Lender to disburse the proceeds of the Loan on the Closing Date as follows: (x) $200,000,000 of the proceeds of the Loan directly to the GPU Vendor”
Convertible promissory note of OD1 JV Holdings, Ex. 4.2 to ChronoScale's 8-K/A No. 2 (filed Nov 18 2026) — use of proceeds · sec.gov - funding-before-financingthe open-ended part of ChronoScale's side: until a Qualified Project Financing it must fund what the project needs, with no cap specified, and gets it back with interest — at the lesser of SOFR plus 8% and the legal maximum (Ex. 10.6) — from STN's deferred cash or, failing that, with priority from the venture's distributable cash. ChronoScale arranges the project financing; no lender, size or date for it is on file. The 8-K's risks include 'the Company’s obligation to fund the Project prior to a Qualified Project Financing'
“Until a Qualified Project Financing occurs, ChronoScale Member is required to fund such additional amounts as are necessary to fund the Project, without a specified cap”
ChronoScale 8-K, Item 1.01 (filed Nov 18 2026) — A&R LLCA · sec.gov - term-loan$74,687,500$74,687,500 from Macquarie Equipment Capital Inc., administrative agent and sole lender, entered at the closing (8-K/A No. 2). The proceeds 'repay a portion of the outstanding obligations of STN under its existing term loan agreement with Macquarie' and pay the deal's fees; the rest of that facility stays STN's. Secured by a first-priority lien on substantially all the venture's assets, the GPUs included, and guaranteed by its subsidiaries; non-recourse to ChronoScale, which gives no guarantee. An event of default if STN and ChronoScale together stop owning all of the venture. The Contribution Agreement had capped it at $75,000,000. The first project financing repays it (the Macquarie Payment Amount, stn-deferred-cash)
“Under the Term Loan Agreement, Macquarie will make a single term loan to the Partnership on the closing date in an aggregate principal amount of $74,687,500, constituting the Term Loan.”
ChronoScale 8-K, Item 1.01 (filed Nov 18 2026) — Term Loan Agreement · sec.gov - term-loan-terms10%90 days at a fixed 10%, the interest paid in kind and due at maturity, with mandatory prepayment from asset sales, new debt and equity — a bridge to the project financing ChronoScale must arrange (the record's reading). ChronoScale's $220M note matures 91 days after this loan if HSR clearance has not come
“The Term Loan matures on the date that is 90 days after the closing date, or earlier upon acceleration, and bears interest at a fixed rate of 10% per annum, computed on the basis of a 360-day year.”
ChronoScale 8-K, Item 1.01 (filed Nov 18 2026) — Term Loan Agreement · sec.gov - stn-warrantup to 850,000up to 850,000 ChronoScale shares at $0.001, vesting in three roughly equal parts on milestones for this project and 'certain future data center developments financed by the Company’s subsidiary', forfeited if unvested by the third anniversary; its issue and vesting depend on STN's member funding its capital contributions. Issued at the closing (8-K/A No. 2). STN agreed not to short or hedge ChronoScale stock for three years
“the Company will issue to STN a warrant (the “STN Warrant”) to purchase up to 850,000 shares of Common Stock (the “STN Warrant Shares”) at an exercise price of $0.001 per share, subject to customary adjustments.”
ChronoScale 8-K, Item 1.01 (filed Nov 18 2026) — STN Warrant · sec.gov - stn-note$30,000,000STN's own debt, moved into ChronoScale's contribution: Applied Digital's affiliate APLD Intermediate held STN's $30M subordinated note of Oct 9 2026, assigns it to ChronoScale for cash or for shares at $8.00, at ChronoScale's choice, and ChronoScale contributes it to the venture, where the LLC agreement counts it at $30,000,000 toward ChronoScale's $390M. Applied Digital controls ChronoScale, so the board's related-party committee approved it. Entered at the closing (8-K/A No. 2); which form of payment ChronoScale chose, no filing on file says
“issued by STN One Incorporated to APLD Intermediate in the original principal amount of $30,000,000 (the “STN Note”), in exchange for, at the Company’s election, either (i) a cash payment equal to the outstanding principal of, and accrued and unpaid interest on, the STN Note as of the effective date of such assignment or (ii) a number of shares of Common Stock (the “Note Shares”) equal to such amount divided by $8.00 (the “Note Assignment”).”
ChronoScale 8-K, Item 1.01 (filed Nov 18 2026) — STN Note Assignment · sec.gov - power65 MW65 MW of firm power to the site's substation, all of it allocated to the Project with first priority, over Oncor's lines with retail supply from Ammper Power — STN's representation in the Contribution Agreement, made 'only for purposes of that agreement' (8-K). The sublandlord 'has not entered into any wholesale supply agreements to purchase behind-the-meter generation'. STN's release says the campus also uses 'on-site power generation and battery storage'; the investor deck puts phases 2 and 3 on 'off-grid gas turbine' (slide 14, an image). No document on file sizes the on-site generation
“The Sublandlord has obtained all necessary agreements and approvals to receive 65 megawatts of power delivered to the substation at the Project, and such 65 megawatts of delivered capacity is firm, available and not subject to the completion of any further interconnection studies, approvals or other conditions.”
Contribution Agreement, Ex. 10.4 to ChronoScale's 8-K (filed Nov 18 2026) — Section 3.12(a) · sec.gov - closingclosed the day after signing: the venture has been the lab's provider since Nov 18 2026. The list does not include the lab's warrant (customer-warrant) or HSR clearance, which ChronoScale's units await
“on November 18, 2026, the Contribution Closing occurred and, in connection therewith, (i) ChronoScale Member and STN Member entered into the A&R LLCA, (ii) the Partnership issued the Partnership Convertible Note to ChronoScale Member, (iii) the Partnership entered into the Term Loan Agreement with Macquarie, (iv) the Partnership became the provider under the GPU Services Agreement, (v) the Company issued the STN Warrant to STN and (vi) the Company entered into the Note Assignment Agreement with APLD Intermediate.”
ChronoScale 8-K/A No. 2, Item 8.01 (filed Nov 18 2026) · sec.gov - revenue-per-mw$20.8Mabout $20.8M a year per MW, blended across all three phases — two of which the lab has not ordered (phases-2-3) — with 'GPU configurations vary by phase'. It squares with the investor deck's all-phase figure: 20.8 × 350 MW × 6 years ≈ $43.7B (editor's arithmetic). The first phase alone works out lower: $7.5B ÷ 6 years ÷ 65 MW ≈ $19.2M, the division several press reports made, which takes the full 'up to' value and a flat six years. The release's forward-looking list speaks of 'the Company’s expected share' beside it; the deck gives partnership figures 'at 100%'
“On a blended basis across all three phases, the agreement represents approximately $20.8 million of annual revenue per megawatt.”
ChronoScale release, 8-K Item 8.01 ex-99.1 (Nov 18 2026) · sec.gov - deck-tranchesthe only GPU counts on file, from the investor deck (an image): the first phase's four tranches (T1–T4) are 4,096, 8,192 and 12,288 NVIDIA B300 and 18,144 GB300, 42,720 GPUs, at 5.5, 11.1, 16.6 and 29.5 MW 'per Deployment' (62.7 MW in all, editor's arithmetic, against the Contribution Agreement's 65 MW of gross load); phase 2 (T5–T8) adds 118,080 GB300 and phase 3 (T9) 72,000 'Vera Rubin/ GB300', marked 'Future Expansion Opportunity', for 232,800. Its source line: 'Landman Site Model (03-Nov-2026)'. A slide, not an order: the 8-K gives four tranches and no GPU count
“Customer | Leading OEM Partnership Supports Deployment of ~233,000 GPUs Across Three Phases”
ChronoScale investor presentation, 8-K/A No. 1 Item 8.01 ex-99.2 (filed Nov 18 2026), slide 13 — an image; no text on file · sec.gov - common-placement$153MChronoScale's money for its side: ~19.1M shares at $8.00 for $153.0M gross, closed Nov 18, the net proceeds 'to fund its capital commitment to the Partnership', the Odessa build and its GPUs included, 'and for general corporate purposes' (8-K). With Applied Digital's $97.0M note — no interest, converting at $8.00 once the stockholder approval takes effect — it is the release's '$250 million in equity'. The 8-K names none of the purchasers; the release names some strategic investors (strategic-investors)
“the Company closed the transactions contemplated by the previously announced Common Stock Purchase Agreement and issued (i) to the Common Stock Purchasers approximately 19.1 million shares of Common Stock for aggregate gross proceeds of $153.0 million and (ii) the Convertible Note to APLD.”
ChronoScale 8-K/A No. 2, Item 8.01 (filed Nov 18 2026) · sec.gov - financing-headline$500Mthe release's 'Up to $750 million financing' is $250M of equity raised at the closing plus a Series C preferred facility of up to $500M that ChronoScale may draw on until Nov 18 2030, up to $50M a put unless the investor waives it, and only while its stock trades at or above 110% of the floor price (initially $12.00) — for working capital and general corporate purposes, not the venture (8-K). It delivered a $10.0M initial put at the closing (8-K/A No. 2). The investor deck splits the $750M across the Microsoft deployment, this venture and general purposes, its 'Allocation to be finalized'
“The financing consists of $250 million in equity and an up to $500 million convertible preferred facility.”
ChronoScale release, 8-K Item 8.01 ex-99.1 (Nov 18 2026) · sec.gov - strategic-investorsthe release's list of the financing's strategic investors, beside 'other institutional investors'. It does not say whether this frontier AI lab is the customer, what any of them bought, or who holds the preferred facility (the 8-K: 'the investor signatory thereto'). Not adopted: one press report's reading that the customer is among the four
“Four strategic investors are participating in the financing: a leading frontier AI lab, Nutanix, Empery Digital Inc., and a storage infrastructure company.”
ChronoScale release, 8-K Item 8.01 ex-99.1 (Nov 18 2026) · sec.gov
Contested figures 4 not reconciled — every position side by side, with its source and tier
“the customer having no commitment to order Phases 2 or 3, without which the partnership’s total contract value will be substantially lower”ChronoScale 8-K Item 1.01 and release (ex-99.1), Nov 18 2026; STN release, Nov 18 2026 · sec.gov
“Customer | ~$43.7bn¹ GPU Services Agreement Across ~350 MW and Three Phases”ChronoScale investor presentation, 8-K/A No. 1 Item 8.01 ex-99.2 (filed Nov 18 2026), slides 10, 11 and 14 — images; no text on file · sec.gov
“The first tranche is expected to be delivered in the fourth quarter of calendar 2026, and the remaining tranches are expected to be delivered in the first half of calendar year 2027 (subject to extension in certain circumstances).”ChronoScale 8-K, Item 1.01, Nov 18 2026 · sec.gov
“The agreement contemplates AI infrastructure capacity across three phases with the first phase ordered and scheduled for deployment in the first half of calendar year 2027.”ChronoScale release (ex-99.1) and STN release, Nov 18 2026 · sec.gov
Scope note what this record leaves to other records
NOT this record (carried elsewhere or not carried): the campus beyond the venture's Project — STN's 1.4 GW (its site) or 1.6 GW (its LinkedIn post), its '400MW initial deployment', its 400 acres (its site) and 'Twelve EDCs are already standing in Phase 1' → the stn entity; Project Landman's job counts and local tax projections → not carried (local estimates; no signed incentive or tax agreement on file); STN's GPU One list prices and its CoreSite cluster → not carried; ChronoScale's quarter, share counts, the placement's price against the market's, the preferred's conversion terms and its Grid Note → the chronoscale entity or not carried; the Oct 1 '$1 billion' annualized run-rate target (two other agreements) → the chronoscale entity; the deck's revenue and EBITDA by year (~95% margins, 'Landman Site Model (03-Nov-2026)') → not carried, a model; the deck's slide 8, which puts Microsoft's 49.5 MW at a 'Silverton, TX' campus → chronoscale-msft's site question, not this record.