Why it matters
A data-center power contract that runs both ways. Google's '100%' stops at the wires: the settlement has it fund all the lines built only for its sites, but of the generation it pays, in OG&E's words, 'its share', through tariff rates and minimum bills. It also sells OG&E 15 years of solar capacity that every customer pays for: about 360 in summer and 120 in winter, a fraction of the roughly 1 load OG&E's executives have described.
Tap a figure for the line in its source.
OG&E gives Google
- electricity for three data center sites, two in Muskogee County and one in Stillwater, one electric service agreement each, billed on OG&E's large-power time-of-use tariff with its fuel charge until a large-load tariff that applies replaces it — demand from 2026, ramping on schedules the filings redact
- disputedof data-center load at full ramp, by OG&E's executives (about 1 by 2031) and a radio report (1.2 GW at peak by 2036); the filings read blank the figure
- a fixed price for the capacity over the 15 years, redacted — about 58% below the cheapest capacity contract OG&E signed from its 2024 solicitation, by OG&E's account — paid by all its customers through the fuel charge, subject to a yearly prudence review
Google gives OG&E
- of the transmission and distribution lines built only to connect its sites, paid up front as contributions in aid of construction — already paid, OG&E's witness told the hearing; the amount is redacted
- monthly minimum charges owed whatever it uses, credit support with Alphabet's guarantees, and a fee to leave or shrink — notice no earlier than the end of the sixth year of each contract's initial term; the levels are redacted
- of accredited summer capacity and ~120 of winter capacity for 15 years, from the Rush Springs and High Spring solar farms, whose capacity Google holds under its purchase agreements with their developer — for all of OG&E's customers, not reserved for Google; the amount moves with the grid operator's accreditation
- an administrative charge per MWh of the two solar farms' output, up to the three sites' measured use, for handling them; the rate is redacted
What happened
OG&E, the electric utility for Oklahoma City and much of Oklahoma, will power three data centers Google is building: two in Muskogee County, one in Stillwater. Google buys the power on OG&E's ordinary large-power rates, with minimum monthly charges it owes even if it uses less, backed by Alphabet's guarantees. Google pays up front for the power lines built only for its sites. In the same deal Google sells OG&E, for 15 years, capacity from two solar farms under construction, whose capacity Google had already contracted. That is about 360 megawatts OG&E can count on in summer and 120 in winter. OG&E needs it for a shortfall across its whole system, and all its customers pay for it through their fuel charge. Google in turn pays OG&E an administrative charge on the farms' output. The rest of what the campuses need falls to the generation OG&E plans for everyone; its resource plan counts Google's load in a winter need of about 1.9 gigawatts by 2031/32. Oklahoma's utility commission approved the package on November 3, 2026, after a settlement with its staff and the Attorney General. Three state lawmakers have asked the Oklahoma Supreme Court to review it. One of them argues that contracts with confidential terms are not the separate tariffs Oklahoma's new law requires. In Arkansas, where OG&E also serves customers, the commission's staff recommends rejecting the solar contracts. How much power the campuses will draw is blanked out of the filings; OG&E's executives have said about a gigawatt. OG&E estimates that the deal saves a typical home $1.83 a month in 2027, rising to $6.84 by 2036. The Attorney General's witness called that model misleading for adding Google's load and none of its cost. The settlement leaves whether other customers come out ahead to each future rate case.
Sources 30 documents — 13 government statements · 10 other documents · 2 regulatory filings · 2 transcripts · 1 press report · 1 SEC filing · 1 company release
Research trail Found 152 documents and read 141 of them while checking this deal and related ones.
- States 5 figures: conditions · rates · minimum charges · guarantees · srac
- States 4 figures: 100% ciac · network upgrades · customer impact · precedent
- States 4 figures: 360 MW accredited capacity · cpa recovery · settlement · proposed findings
- States 3 figures: cpas · 120 MW winter capacity · 58% price vs rfp
- States 3 figures: $0.46 cpa bill impact · 976 MW capacity need · load ramp
- States 2 figures: approval · appeal
- States announced
- States esas
- States sites
- States exit
- States signing agenda
- States statute
- States arkansas
- States arkansas hearing
- States 600 MW solar farms
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: OCC Case PUD2026-000031: OG&E's application, Laws's and Schuermann's direct testimony and Thenmadathil's (May 1 2026), PUD's (Givens, Mossburg) and the Attorney General's (Beling) responsive testimony (Aug 5 2026), Laws's testimony summary (Aug 31 2026), the Joint Stipulation and Settlement Agreement (Sep 9 2026), the parties' proposed findings (Entry 152) and testimony summaries (Entry 153, filed Sep 16 2026); the OCC's signing agenda (Nov 3 2026); Laws's testimony in Case PUD 2025-000038 (May 19 2025); HB 2992 as enrolled; OGE Energy / OG&E 10-Q for Q3 2026 (Oct 27 2026) and OGE Energy's Q4 2025 and Q1 2026 calls; OG&E's release and Google's post (Apr 30 2026); the Google–Muskogee announcement (Nov 20 2025); NextEra Energy Resources' project pages; APSC Docket 26-040-U staff testimony (Oct 15 2026) and Order No. 3 (Oct 27 2026); The Oklahoman (Nov 15 2026), The Inference (Nov 8 2026), KOSU (Apr 30 2026), Oklahoma Politics Today (Sep 2026) and KGOU (Jun 18 2026) for the approval, the appeal and the contested cells (read 2026-11) · as of Nov 2026
The evidence 30 sourced figures · 6 disputes
The record's headline OG&E–Google, Oklahoma: three electric service agreements for Google's data centers in Muskogee County and Stillwater — billed on OG&E's large-power tariff with minimum charges, Google funding 100% of the lines built only for them — beside two 15-year contracts under which Google sells OG&E about 360 of summer and 120 MW of winter accredited capacity from two solar farms, its cost recovered from all OG&E's customers through the fuel charge; capacity, not the campuses' load, which the filings redact (about 1 by OG&E's executives); approved Nov 3 2026, its signed order not among the documents read, appealed by three state lawmakers, and the same capacity contracts opposed by Arkansas's staff
- Size
- three ESAs, one per site (two in Muskogee County, one in Stillwater), billed on the LPL-TOU tariff at Service Level 1 with minimum charges; Google funds 100% of the dedicated T&D as CIAC (amount redacted) · two 15-year CPAs: ~360 MW summer / ~120 MW winter of SPP-accredited capacity from the Rush Springs (200 MW) and High Spring (400 MW) solar farms, nameplate 600 MW, at a fixed price that is redacted (~58% below OG&E's least-cost CPA from its 2024 RFP, by its account) · campus load redacted (~1 GW by 2031 by OG&E's executives; 1.2 GW at peak by 2036 by KOSU) · no contract value disclosed
- When
- Jan 2025 (Google first offers OG&E capacity resources) → first half of 2025 (negotiations in earnest) → May 19 2025 (OG&E testimony: 'Customer X', ~1 GW in a little more than five years across multiple sites) → Nov 4 2025 (memorandum of understanding) → Nov 20 2025 (Google's two Muskogee County campuses announced; electric service contracts with OG&E in development) → Feb 18 2026 (OGE Energy: 'finalizing a one gigawatt contract' with Customer X) → Apr 29 2026 (OGE Energy's call names Google as Customer X) → Apr 30 2026 (OG&E's and Google's releases) → May 1 2026 (application, Case PUD2026-000031) → Jul 2026 (Arkansas application, Docket 26-040-U) → Aug 5 2026 (responsive testimony) → Sep 8–9 2026 (public comment; settlement; hearing, the ALJ recommending approval) → Sep 16 2026 (proposed findings) → Oct 15 2026 (Arkansas staff recommends denial) → Nov 3 2026 (OCC approval) → Nov 12 2026 (appeal papers filed) → Dec 17–18 2026 (Arkansas hearing) → summer 2027 (Rush Springs CPA begins) → summer 2028 (High Spring CPA begins) → 2036 (the last contract-demand milestone the filings name, its level redacted)
- Status
- approved by the OCC on Nov 3 2026: its signing agenda that day listed a 'FINAL ORDER APPROVING UNOPPOSED JOINT STIPULATION AND SETTLEMENT AGREEMENT' in Case PUD2026-000031, the three commissioners voted yes (The Inference, from the meeting recording), and the OCC's communications director describes 'The commission's order approving the OG&E-Google arrangement' (The Oklahoman) — but the signed order, revised at paragraph D-3 before the vote by PUD's account, is not among the documents read, the latest text read being the parties' proposed findings of Sep 16. Appealed to the Oklahoma Supreme Court by three state representatives (papers filed in the case on Nov 12 2026). In Arkansas (Docket 26-040-U), where the CPAs need approval too, staff recommended denial on Oct 15 2026; hearing Dec 17–18 2026, order requested by Dec 28; the ESAs' conditions to effectiveness include an Arkansas order 'as may be required' for the CPAs. Rush Springs' capacity runs from the 2027 summer period, High Spring's from 2028's
- Structure
- three Electric Service Agreements between Oklahoma Gas and Electric Company and Alliance Site & Grid, LLC, a wholly owned Google subsidiary — one per site, substantially the same, each running through a Pre-Commissioning Period, a Commissioning Period, a Load Ramp Period and an Initial Term (its length redacted) on a Contract Demand Schedule; approved as special contracts under OAC 165:35-1-2 and deemed tariffs. Preliminary Agreements, folded into the ESAs once they take effect, under which Google funds the dedicated transmission as CIAC. Two Capacity Purchase Agreements, Rush Springs and High Spring, preapproved under 17 O.S. § 286(C): Google sells OG&E SPP-accredited capacity from two solar projects operated by NextEra Energy Resources, whose capacity rights Google holds under power purchase agreements — the ESAs' 'Supplemental Resources', for which Google pays OG&E a per-MWh administrative charge (SRAC). Credit support includes Alphabet Inc.'s parental guarantees. The Joint Stipulation (Sep 9 2026) adds a customer impact assessment in each general rate case, a CWIP rule, confidential minimum-bill projections, notice of any SPP-identified upgrade, and declares itself no precedent
- Programme
- Time-to-power
- Parties
- Google customer and capacity seller — Alliance Site & Grid, LLC, Google's wholly owned subsidiary, signs the three ESAs and, by OG&E's Arkansas application and Arkansas's staff, the two CPAs (Google LLC, the party in the Oklahoma case, says it 'has entered into' them); pays the tariff bills and minimum charges, funds the dedicated lines as CIAC, pays the SRAC, gives credit support with Alphabet Inc.'s parental guarantees; sells OG&E the accredited capacity of the Rush Springs and High Spring solar farms, which it does not own but holds the rights to under its power purchase agreements · OG&E utility — Oklahoma Gas and Electric Company; serves the three sites from its system, buys the solar farms' accredited capacity toward its SPP resource-adequacy obligations and recovers its cost from all customers through the fuel adjustment clause, administers the capacity for the SRAC, and runs the customer impact assessments the settlement requires
- Record
- disclosed / primary source · as of Nov 2026
Flows 5 as the record states them
- OG&E → Googlepowerretail electric service to three data center sites under three ESAs — demand beginning in 2026 and ramping through 2028 to 2036 at levels the filings redact (about 1 GW by OG&E's executives' account; contested load) — billed on the LPL-TOU tariff at Service Level 1 with the fuel adjustment clause and other riders
- Google → OG&Epower-paymentsmonthly bills on the LPL-TOU tariff, with Minimum Charges owed regardless of use (a Minimum Billing Demand no lower than a redacted share of Contract Demand, and a minimum energy charge); a one-time fee to leave or cut contract demand, prepaying a redacted share of the remaining Minimum Charges; the SRAC per MWh of the solar farms' output, up to the sites' measured use; credit support backed by Alphabet's parental guarantees
- Google → OG&Eciac100% of the dedicated transmission and distribution infrastructure to connect each site, as contributions in aid of construction — already paid, OG&E's Shoop told the hearing; the total redacted
- Google → OG&EcapacitySPP-accredited capacity for 15 years from Rush Springs (200 MW nameplate; from the 2027 summer period) and High Spring (400 MW; from 2028) — about 360 MW summer and 120 MW winter combined, varying with SPP's accreditation; Google must deliver the greater of the accredited capacity and what the farms would earn if fully available, and may substitute alternate facilities under limited conditions
- OG&E → Googlecapacity-paymentsa fixed price for the capacity over the 15-year term, paid only for capacity scheduled and received — redacted; recovered from all OG&E customers through the fuel adjustment clause, subject to annual prudence review, in Oklahoma, and pending before the APSC for Arkansas's share
Resolved figures 30 each with the verbatim line from its document
- announcedfirst public on Nov 20 2025, as contracts in development: the announcement by Google, Muskogee County, the City of Muskogee and Port Muskogee of Google's two campuses near Summit and Council Hill said OG&E and Google were working on them, and quoted OG&E's Alba Weaver ('We’re delighted to expand our collaboration with Google to Muskogee and look forward to serving their facilities'); the parties had signed a memorandum of understanding on Nov 4 2025 (Laws). OG&E had described the load since May 2025 without naming its customer ('Customer X'), and on Feb 18 2026 its parent said it was 'finalizing a one gigawatt contract' with Customer X. OGE Energy's call of Apr 29 2026 named Google ('Google is the customer previously referred to as customer X'), and OG&E's release and Google's post followed on Apr 30
“OG&E and Google are working together to develop long-term contracts under which Google will purchase electric service from OG&E and cover the infrastructure costs required to directly serve them.”
Google, Muskogee County, City of Muskogee and Port Muskogee announcement (Nov 20 2025) · portmuskogee.com - esas3three Electric Service Agreements, one per site, 'substantially similar in form and structure', with site-specific contract demand, timelines and infrastructure (the application) — signed by Alliance Site & Grid, LLC, 'a wholly-owned subsidiary of Google, LLC' (the proposed findings; PUD's Givens: 'a subsidiary of Google Energy, LLC'). Each runs through a Pre-Commissioning Period, a Commissioning Period, a Load Ramp Period and an Initial Term on a Contract Demand Schedule, every length and level redacted (Laws). Negotiated 'in earnest in the first half of 2025', with a memorandum of understanding executed Nov 4 2025 (Laws). Rates: the public LPL-TOU tariff (rates); protections: minimum charges, exit fees, credit support, CIAC (minimum-charges, exit, guarantees, ciac)
“OG&E has executed three Electric Service Agreements (“ESAs”) with Alliance Site & Grid, LLC, a wholly-owned subsidiary of Google (hereinafter “Google”), for the provision of retail electric service to be located within Oklahoma.”
OG&E application, Case PUD2026-000031 (Entry 1, May 1 2026) — ¶II.A.1 · public.occ.ok.gov - sites3three new data centers in Muskogee and Stillwater, by OG&E's own release — on Google's and Muskogee's announcement, two campuses near Summit and Council Hill in Muskogee County (Nov 20 2025), and on Google's of Aug 13 2025, one in Stillwater; News 9, as The Inference relays it, reports the same split. No filing among the documents read maps an ESA to a site. Not Google's own list of 'three new locations in development in Tulsa County, Muskogee County and Stillwater' (its Oklahoma page), a different three: it counts Muskogee County once and adds Tulsa County, which OG&E's release does not name
“Today, OG&E, the operating subsidiary of locally-headquartered OGE Energy Corp. (NYSE: OGE), announced that it will power three new data centers that Google announced in Muskogee and Stillwater last year.”
OG&E release (Apr 30 2026) · oge.com - conditionsthe ESAs take effect only once conditions are met or waived: an OCC final order approving each ESA as a special contract, the CPAs signed, and final orders by the OCC and the Arkansas Public Service Commission 'as may be required' for the CPAs (Laws). The CPAs in turn take effect only once the ESAs' conditions are met, and if they are not by the ESAs' long-stop date either side may end the CPAs (Schuermann). Arkansas has not ruled (arkansas)
“These conditions include a final order by the OCC approving each ESA as a special contract; the execution of the CPAs by Google and OG&E; and a final order by the OCC and the Arkansas Public Service Commission, as may be required for the effectiveness and cost recovery in rates of the CPAs.”
Laws direct testimony, Case PUD2026-000031 (Entry 24, May 1 2026) · public.occ.ok.gov - ratesGoogle's rates are OG&E's public Large Power and Light Time-of-Use tariff at Service Level 1, with the fuel adjustment clause and the other riders; if the OCC approves a large-load tariff, a new subset of LPL-TOU or a successor that applies to Google, its rates change to it, the ESAs' other terms staying in force (Laws). OG&E's proposed large-load (XLPL) tariff is a separate case (note). The demand charge is $7.08 per kW-month (PUD's Mossburg)
“the rates for service shall be billed pursuant to the Large Power and Light Time of Use (“LPL-TOU”) tariff at Service Level 1, inclusive of the rider for fuel cost adjustment (“FCA”) and all other applicable riders and modifications.”
Laws direct testimony (Entry 24, May 1 2026) · public.occ.ok.gov - minimum-chargesmonthly Minimum Charges owed whatever Google uses: the customer charge, the winter-event securitization charge, a Minimum Billing Demand charge, a Minimum Billing Energy charge and any base-rate rider, billed on the higher of the minimum or actual demand and energy; the Minimum Billing Demand 'shall never be less than [redacted] of the Contract Demand' (Laws). Within 90 days of a final order OG&E gives PUD and the Attorney General a confidential 12-month projection of minimum-bill revenue per site, updated yearly until each site reaches full Contract Demand (the settlement)
“Google is required to pay a certain monthly minimum charge regardless of the energy consumed in a given monthly period.”
Laws direct testimony (Entry 24, May 1 2026) · public.occ.ok.gov - exitleaving early or cutting demand: Google may end an ESA or make a one-time cut of up to a redacted share of Maximum Contract Demand only by prepaying a redacted share of the remaining Minimum Charges, on written notice no earlier than the end of the sixth year of the Initial Term; the fee is capped at a redacted number of years of Minimum Charges and has a redacted floor (Laws). Either side may end a CPA if all ESAs end, or if some end and Maximum Contract Demand falls below set thresholds — never before the ninth ESA contract year (Schuermann)
“subject to a written notice that cannot be given prior to the end of the sixth year of the Initial Term.”
Laws testimony summary (Entry 121, Aug 31 2026) · public.occ.ok.gov - guaranteescredit support of a redacted share of the Minimum Charges for the Load Ramp Period and Initial Term — cash, a letter of credit or a parental guarantee from a guarantor rated at least BBB-/Baa3; Alphabet Inc. gives the parental guarantees, their initial value redacted, and is rated AA+ by S&P and Aa2 by Moody's (Laws)
“The initial aggregate value of the Parental Company Guarantees being provided by Google’s parent company, Alphabet Inc., in support of the ESAs is approximately”
Laws direct testimony (Entry 24, May 1 2026) · public.occ.ok.gov - ciac100%what Google's '100%' covers, in the binding text: the dedicated transmission and distribution infrastructure, paid as contributions in aid of construction so it never enters OG&E's rate base — first under Preliminary Agreements, folded into the ESAs — and, by OG&E's Shoop at the hearing, Google 'has already paid'; the amounts paid and still due are redacted (Laws). Not generation: Google 'will also pay its share of power generation required to serve these data centers' (OG&E's release) through the tariff's rates, minimum charges and riders, and the capacity it sells OG&E. Not regional or network upgrades (network-upgrades). OG&E's release puts it wider — 'Google is committing to pay 100% of the costs to connect the data center sites to the grid as well as all contracted costs regardless of the company’s energy use' — and Google's witness Kimbrough testified Google 'is prepared to pay the incremental costs directly caused by serving its load' (the proposed findings' summary)
“Google funds 100% of dedicated transmission and distribution infrastructure as CIAC.”
Joint Stipulation and Settlement Agreement, Case PUD2026-000031 (Entry 149, Sep 9 2026) — ¶II.C · public.occ.ok.gov - network-upgrades30none identified: OG&E has found no regional or network upgrade caused by Google's load and must tell the Commission and the parties within 30 days if it does; on an SPP determination of one, OG&E and Google negotiate how its cost is handled and OG&E proposes a method in a future case, which any party may challenge. If CWIP is approved for recovery from customers, it is also collected from Google (¶II.D). The Attorney General's Beling had asked that Google pre-fund any future network upgrades (the proposed findings' summary); the settlement does not say so
“OG&E has identified no necessary regional or network upgrades as a direct result of the Google load as determined pursuant to the cost causation principles required by 17 O.S. Sections 900-906, and must notify the Commission and the Stipulating parties within 30 days if it later does.”
Joint Stipulation and Settlement Agreement (Entry 149, Sep 9 2026) — ¶II.C · public.occ.ok.gov - sracmoney the other way round inside the ESAs: besides the capacity payments OG&E makes to Google under the CPAs, Google pays OG&E a Supplemental Resource Administrative Charge, a redacted rate per MWh of energy from each solar farm up to the three sites' measured consumption (Laws); approved, its revenue tracked separately (the settlement, ¶II.E). The Attorney General's Beling found it acceptable 'because it is between Google and OG&E and does not affect other customers’ rates' (the proposed findings' summary)
“Separate from the capacity payment that the Company will make to Google for the capacity rights to the Supplemental Resources under the CPAs, Google will pay the Company a Supplemental Resource Administrative Charge in the amount of per megawatt-hour (MWh) of energy generated by each Supplemental Resource on a monthly basis up to the actual measured energy consumption for all three sites.”
Laws direct testimony (Entry 24, May 1 2026) · public.occ.ok.gov - cpas15two Capacity Purchase Agreements, each 15 years for summer and winter capacity: Rush Springs from the 2027 summer period, High Spring from the 2028 summer period. OG&E pays only for capacity scheduled and received, at a cost fixed over the term (redacted). Google does not own the farms; it holds contracted rights to their accredited capacity under power purchase agreements it signed to get them built, and offered OG&E that capacity in January 2025, during the ESA talks (Laws; Schuermann). Google must deliver the greater of SPP's accreditation and the capacity the farms would earn if fully available, paying the net cost of replacement capacity, any penalties and its share of SPP deficiency payments if it fails — force majeure no excuse — and may substitute alternate facilities only under limited conditions, at no extra cost to OG&E (Schuermann). Arkansas's staff names the seller: 'two 15-year CPAs with Alliance Site & Grid, LLC, a wholly owned subsidiary of Google'
“Each of the CPAs provide both summer and winter capacity for a term of 15 years.”
Schuermann direct testimony, Case PUD2026-000031 (Entry 27, May 1 2026) · public.occ.ok.gov - accredited-capacity360 MWabout 360 MW of accredited summer capacity and 120 MW of winter, the two together — approximately 120 MW summer and 40 MW winter from Rush Springs, 240 MW and 80 MW from High Spring — the amount varying 'depending on the accreditation that is assigned to the resource from the Southwest Power Pool' (Schuermann). Capacity OG&E can count toward its SPP reserve obligations, not energy and not the campuses' load (contested load); 'Although this addition does not fully address the Company’s projected capacity shortfall over the coming years, it does represent an important progression' (Schuermann). How firm the figures are is contested (accreditation)
“He testified that the two 15-year CPAs provide approximately 360 MW of accredited summer capacity and 120 MW of accredited winter capacity and are priced below the capacity alternatives available to OG&E through its 2024 All-Source Request for Proposals.”
Proposed Joint Findings of Fact and Conclusions of Law, Case PUD2026-000031 (Entry 152, filed Sep 16 2026), p. 3 · public.occ.ok.gov - winter-capacity120 MWabout 120 MW in winter, a third of the summer figure. OGE Energy's CFO on the Apr 29 2026 call: 'the rough math from the SPP is it's going to be somewhere around a 20% accreditation on solar in the winter', so the CPAs would move OG&E's ~1.9 GW winter need for 2031/32 to ~1.8 GW
“The CPAs, in combination, would provide approximately 360MW of accredited capacity during the summer resource adequacy periods and approximately 120MW of accredited capacity during the winter resource adequacy periods.”
Schuermann direct testimony (Entry 27, May 1 2026) · public.occ.ok.gov - solar-farms600 MW600 MW of nameplate solar, both under construction: Rush Springs Solar, 200 MW, in Stephens County, and High Spring Solar, 400 MW, on about 4,505 acres in Muskogee County (Schuermann; NextEra's project pages; the Muskogee announcement) — operated by NextEra Energy Resources, their energy bought by Google under the two power purchase agreements announced on Nov 20 2025 ('600 megawatts (MW) of new clean energy'). Not counted as a resource in OG&E's 2026 IRP (the CFO, Apr 29 2026). When they enter service is contested (in-service)
“These facilities will provide 600 megawatts of nameplate capacity, and we will request preapproval from both Oklahoma and Arkansas commissions for these CPAs.”
OGE Energy Q1 2026 call (Apr 29 2026; transcript) · fool.com - price-vs-rfp58%the price is redacted; OG&E's comparison is public: about 58% below the least-cost CPA it executed from its 2024 All Source RFP, and roughly 26% below the lowest-cost bid first offered into that RFP, a bid later withdrawn (Schuermann). One origin, Schuermann, repeated by PUD's Givens and Arkansas's staff, who dispute what it shows, not the arithmetic (prudence). The capacity was never bid: 'Because these projects were not bid in to the RFP, the complete scoring process was not conducted' (Schuermann)
“When compared to the least‑cost CPA the Company ultimately executed through the RFP, this price is approximately 58% lower.”
Schuermann direct testimony (Entry 27, May 1 2026) · public.occ.ok.gov - cpa-recoverywho pays for the capacity: all of OG&E's customers, through the fuel adjustment clause, subject to annual prudence review (the settlement, ¶II.A); the capacity serves the whole system, not Google alone (Shoop at the hearing). OG&E's estimate of the cost on an Oklahoma home's bill: about $0.13 a month in 2027, $0.41 in 2028 and $0.46 in 2029 (cpa-bill-impact)
“Mr. Shoop further testified that the Rush Springs and High Spring CPAs will help meet OG&E’s capacity obligations, were negotiated at prices below those reflected in OG&E’s recent RFP, will benefit all customers rather than being dedicated solely to Google, and are proposed for recovery through the Fuel Adjustment Clause.”
Proposed Joint Findings of Fact and Conclusions of Law (Entry 152, filed Sep 16 2026), p. 5 · public.occ.ok.gov - cpa-bill-impact$0.46OG&E's estimate (Thenmadathil) of the CPAs' cost on a residential bill in Oklahoma, using the production demand allocator from its last rate case: about $0.13 a month in 2027, $0.41 in 2028 and $0.46 in 2029, about $0.60 a month less in 2029 than the least-cost CPA from its RFP would have cost — a cost every customer bears, beside the benefit OG&E models from Google's load (contested customer-savings)
“resulting in a monthly bill impact for residential customers of approximately $0.13 per month in 2027, $0.41 per month in 2028, and $0.46 per month in 2029.”
Testimony summaries, Attachment B to the proposed findings (Entry 153, filed Sep 16 2026) · public.occ.ok.gov - capacity-need976 MWwhy OG&E wants the capacity: even with every project from its 2024 RFP in service, a summer need of 976 MW in 2028 rising to nearly 2,800 MW in 2034, and a winter need of almost 1,200 MW in 2028 rising to over 3,000 MW in 2034 (Shoop); the 2025 IRP Update's summer need was 1,083 MW in 2028 and 2,223 MW in 2031. Google's load is counted in those needs (the Q4 2025 call); the CPAs do not close them. The parties' proposed findings would find a need; Arkansas's staff finds one too
“He stated that even after all projects contracted from the 2024 All Source RFP are placed in service, OG&E still has significant needs in both summer and winter, with the summer need at 976 MW in 2028 alone, growing to nearly 2,800 MW in 2034,”
Testimony summaries, Attachment B to the proposed findings (Entry 153, filed Sep 16 2026) · public.occ.ok.gov - load-rampGoogle's demand starts in 2026 and ramps through 2028 to 2036 — the years are public, every level blanked: 'ramping to over [ ] in 2028 and then to over [ ] by 2036' (Shoop); 'The aggregate contract demand across the New Oklahoma Data Centers reaches approximately [ ] by 2036, with the ability to scale further from that point' (Laws). How big it gets is contested (load)
“Mr. Shoop testified that Google is developing three data center sites that will add significant demand to OG&E’s system beginning in 2026”
Testimony summaries, Attachment B to the proposed findings (Entry 153, filed Sep 16 2026) · public.occ.ok.gov - settlementsettled on Sep 9 2026 by OG&E, PUD (the Commission's utility staff), the Attorney General and Google; the Oklahoma Industrial Energy Consumers did not sign but did not oppose, and the Oklahoma Sustainability Network was excused from the hearing. It recommends approving the ESAs and preapproving the CPAs with fuel-clause recovery, and adds a customer impact assessment in each rate case (customer-impact), the CWIP rule and the upgrade notice (network-upgrades), the confidential minimum-bill projections (minimum-charges), separate tracking of the SRAC, and confidential forecasts of the large-load class in resource planning. It promises no savings (Oklahoma Politics Today: 'The settlement does not promise customers a specific amount of savings')
“Following the filing of Direct, Responsive, and Rebuttal Testimony, OG&E, the Public Utility Division of the Oklahoma Corporation Commission (“PUD”), the Office of the Oklahoma Attorney General (“Attorney General”), and Google submitted a Joint Stipulation and Settlement Agreement (“Joint Stipulation”)”
Proposed Joint Findings of Fact and Conclusions of Law (Entry 152, filed Sep 16 2026), p. 1 · public.occ.ok.gov - customer-impactthe check on cost-shifting the settlement substitutes for a savings promise: in each general rate case during the contracts' life OG&E compares its costs with and without Google (Base Case / What-If), under a Customer Impact Review Protocol (Exhibit A) that the parties call a starting framework, not binding on the Commission's method; Google acknowledged that any adverse rate impact on other classes will be reviewed in each rate case and each annual fuel-clause review (Laws)
“OG&E shall perform Customer Impact Assessments under the prescribed Base Case / What-If methodology. This Assessment shall be conducted in each general rate case conducted during the life of the contract.”
Joint Stipulation and Settlement Agreement (Entry 149, Sep 9 2026) — ¶II.B · public.occ.ok.gov - precedentno precedent, by its own terms: neither the settlement nor an order approving it may be cited as precedent in another case — while OG&E's chief executive calls the agreement 'a model for future data center partnerships' that 'forms the basis for a new large-load tariff' (OG&E's release), which is pending in its own case (note)
“that neither this Joint Stipulation nor any Commission order approving the same shall constitute or be cited as precedent or deemed an admission by any Stipulating Party in any other proceeding”
Joint Stipulation and Settlement Agreement (Entry 149, Sep 9 2026) — ¶III.E · public.occ.ok.gov - proposed-findingsthe document of Sep 16 2026 the record's figures rest on: the parties' Proposed Joint Findings of Fact and Conclusions of Law (Entry 152), drafted as the Commission's findings and order ('THE COMMISSION FURTHER FINDS…'), with a placeholder for the procedural history and the ALJ's signature unsigned — a proposal, not an order. It summarizes the testimony, records that the ALJ recommended approval at the hearing on Sep 9, and proposes findings that the ESAs comply with HB 2992's customer protections (statute), that OG&E needs the capacity, and that the CPAs, compared against its 2024 RFP and market alternatives, are reasonable and prudent. OGE Energy's 10-Q of Oct 27 2026: 'At the hearing on the merits, the ALJ recommended approval of the special contract and the two CPAs'
“The foregoing findings, conclusions, and order are the Report and Recommendation of the undersigned Administrative Law Judge.”
Proposed Joint Findings of Fact and Conclusions of Law (Entry 152, filed Sep 16 2026), p. 9 · public.occ.ok.gov - signing-agendathe OCC's own record of the decision among the documents read: its 24-hour signing agenda for Nov 3 2026 lists a final order approving the settlement in this case. The vote and the order's text are known here only as others report them (approval)
“Case Number PUD2026-000031 Order Type Final RSO OKC Parties OKLAHOMA GAS AND ELECTRIC COMPANY (Applicant) Relief In Caption IN THE MATTER OF THE APPLICATION OF OKLAHOMA GAS AND ELECTRIC COMPANY FOR COMMISSION APPROVAL OF ELECTRIC SERVICE AGREEMENTS AND PREAPPROVAL OF CAPACITY PURCHASE AGREEMENTS PURSUANT TO 17 O.S. § 286(C) Order Title FINAL ORDER APPROVING UNOPPOSED JOINT STIPULATION AND SETTLEMENT AGREEMENT”
OCC 24-hour signing agenda (proposed orders), Nov 3 2026 · oklahoma.gov - approvalapproved on Nov 3 2026. The OCC's communications director, Jack Damrill, to The Oklahoman: the order requires Google to fund 100% of the dedicated lines, customer impact assessments, Google's share of any CWIP and reporting of certain revenues, and the Commission keeps its authority over cost allocation in future rate cases. The Inference, from the meeting's recording: the clerk called 'a proposed final order approving unopposed joint stipulation and settlement agreement'; PUD's Mike Ryan said the judge recommended it 'in its entirety' and 'the order would be effective immediately'; all three commissioners voted yes, none asking a question on the record; and the order 'had just been revised at paragraph D-3', a change that 'involves the Ratepayer Protection Act' but 'does not change the ultimate result of the case' (Ryan). The signed order was not public as of Nov 7 (The Inference) and is not among the documents read, so its final text, paragraph D-3 included, is not carried here
“The commission's order approving the OG&E-Google arrangement contained several provisions designed to protect existing OG&E customers from costs associated with Google's additional electricity demand, Damrill said.”
The Oklahoman, via AOL (Nov 15 2026) · aol.com - appealappealed to the Oklahoma Supreme Court by state Reps. Tom Gann, Rick West and Kevin West, who argue that the procedural schedule came out after its own deadline to intervene, so no one not already in the case could join it; that customers had no direct notice until August; that Gann's public comments never reached the record; that 'The sheer secrecy of the resulting OCC order' shows the OCC failed to 'regularly pursue its authority'; and that Commissioner Todd Hiett unlawfully took part in the vote. Gann, to the paper, also says the contracts violate HB 2992 (contested hb-2992). The OCC's spokesman: the June 1 deadline was set in an order nine days earlier. Papers in the appeal were filed in the OCC case on Nov 12 2026 (Entries 160, 162 and 165 — scans with no readable text)
“Republican state Reps. Tom Gann, Rick West and Kevin West asked the Oklahoma Supreme Court to review a decision made this year by the state's utility regulator, the Oklahoma Corporation Commission.”
The Oklahoman, via AOL (Nov 15 2026) · aol.com - statute10Oklahoma's 2026 large-load law, HB 2992 (17 O.S. §§ 900–906): for data centers and AI facilities contracting to add 75 MW or more after July 1 2026, separate terms, conditions and tariffs, credit requirements, and a term of service of at least ten years. The proposed findings would find that the ESAs 'comply with the customer-protection requirements of House Bill 2992 (2026)', as PUD's Givens and the Attorney General's Beling testified; whether special contracts satisfy its call for separate tariffs is what the appeal disputes (contested hb-2992)
“The term of service for a large load customer shall be at least ten (10) years.”
Enrolled House Bill 2992 (2026), Section 4 · oklegislature.gov - arkansasOG&E's Arkansas customers pay a share of the capacity too, so the CPAs need the APSC's approval (Docket 26-040-U, filed Jul 2026). Staff's Roberts (Oct 15 2026): OG&E met one of the five statutory tests, need, but not the cost test, since it 'did not ascertain current market conditions through an RFP process when it elected to select an unsolicited bid', so staff recommends the Commission 'Deny OG&E’s request for CPAs for a term of more than five (5) years'. OG&E filed rebuttal on Nov 2; hearing Dec 17–18 2026, order requested by Dec 28 (Order No. 3). The ESAs' conditions include an Arkansas order 'as may be required' (conditions)
“On October 15, 2026, the APSC Staff filed direct testimony recommending denial of the CPAs, stating that OG&E did not provide sufficient evidence that the pricing is reasonable and prudent.”
OGE Energy / OG&E 10-Q for Q3 2026 (Oct 27 2026) · sec.gov - arkansas-hearingthe Arkansas schedule: staff surrebuttal Nov 20, OG&E sur-surrebuttal Dec 2, a settlement or issues list Dec 7, the hearing Dec 17–18 and an order requested by Dec 28 2026; the Attorney General, also a party, does not intend to file direct testimony
“The public hearing is hereby set to begin at 9:30 a.m. on December 17, 2026, in the Commission Hearing Room located in the Arkansas Public Service Commission Building, 1000 Center Street, Little Rock, Arkansas.”
APSC Order No. 3, Docket 26-040-U (Oct 27 2026) · apps.apsc.arkansas.gov
Contested figures 14 not reconciled — every position side by side, with its source and tier
Scope note what this record leaves to other records
Not this record: the solar farms' own deal — Google's power purchase agreements with NextEra Energy Resources for Rush Springs and High Spring, announced Nov 20 2025 with no price or term, which give Google the capacity it sells OG&E (on the nextera entity: 'two Oklahoma PPAs adding 600 MW'), and NextEra's investment estimates for each ($280M and $530M on its pages); the campuses themselves — Google's $9 billion two-year Oklahoma investment (Aug 13 2025), the Stillwater and Muskogee project plans, incentive agreements and franchise fees, and the state environmental permits and generator applications for the sites, most filed under other companies' names; Stillwater's Nov 5 2024 vote letting OG&E, not the city's own utility, serve a data-center project the city calls only 'a U.S.A. based Fortune 100 Company'. OG&E's separate large-load (XLPL) tariff case (PUD 2026-000046; hearing Jan 12 2027) — its proposed $2.50 per kW-month customer affordability charge, 85% minimum billing demand and 15-year minimum term, and Google's counter-positions there — which OG&E says this agreement formed the basis for, but whose monthly fee credited to other customers Google's contracts do not carry (OG&E's Christi Woodworth to KGOU, Jun 18 2026). OG&E's company-wide plans and filings — its IRPs, its 2032 capacity plan, the Horseshoe Lake units, its Sep 30 2026 rate review, OGE Energy's capital plan, guidance and equity offerings (on the oge entity, or not carried). Google's March 2026 pledge to pay '100% of the power our data centers use and any new infrastructure costs directly driven by our growth', which names no project. Not adopted: KOSU's 'Google is also building two solar farms that will connect to OG&E’s grid' — NextEra operates them and Google does not own them (Schuermann: 'No, Google does not own the generation facilities'); The Oklahoman's 'a plan to buy electricity from two solar farms in Oklahoma — electricity that would then be specially designated for data centers', where the CPAs buy capacity only, for all customers; SPP's interconnection request GEN-2018-055 (252 MW of solar in Grady County, at the Terry Road substation the Rush Springs wind farm shares) as the Rush Springs CPA's plant, which no document read establishes; Google's 'three new locations in development' as the three sites served (sites).