Fervo–Google

Google will buy 396 of Fervo's Utah geothermal output for 15 years, used or not, first power expected in 2028; Fervo must offer about 600 MW more by June 2030, and the price is undisclosed.

A deal between Google, Fervo Energy

Why it matters

The geothermal power Google committed to buy is meant for a Utah data center Google says it is only beginning to consider. Fervo Energy's Q3 account says the power goes to the grid at first and Google can resell what it doesn't use. The account also says a separate option tied to the data center requires Fervo Energy to offer ~600 more by June 2030 or refund Google's payments for deemed delivered energy.

Tap a figure for the line in its source.

Fervo Energy gives Google

  • of enhanced geothermal output from Cape Station for 15 years, in four 99 sub-tranches with target commercial operation from the third quarter of 2028 — eight new GeoBlocks Fervo now calls Cape Google 400; grid-connected at first, by Fervo's Q3 account
  • more at Cape Station that Fervo must offer, with a guaranteed operation date no later than June 2030 — 'at least 604 ' and ~1,000 MW in all by its 10-Q, a total of 'not less than approximately 950 MW' by its 8-K; Google may decline, and the terms are still to be negotiated
  • repayment of what Google has paid for 'deemed delivered energy' if Fervo fails to make that offer — an amount the 8-K calls not currently estimable

Google gives Fervo Energy

  • payments at a fixed, undisclosed price for 15 years, take-or-pay — owed, Fervo's CEO says, whatever becomes of the data center, which Google can serve or not, since the power can be sold on the grid
  • Alphabet Inc.'s parent guaranty of Google Energy LLC's obligations — beside Fervo's guaranty of its own project company's

Sep 1, 2026 announced by Fervo, in a release and an 8-K, six days after signingupdated Nov 21, 2026signed Aug 26 2026, announced Sep 1 disclosed by the parties

What happened

Fervo Energy signed a 15-year contract to supply Google with 396 megawatts more from its Cape Station geothermal site in Utah. Fervo drills deep wells into hot rock to run geothermal plants. Its first 33-megawatt unit there started commercial operation on September 30, 2026, a month after Fervo signed the Google deal. Fervo now calls the eight new units Cape Google 400. First power from the new units is expected in mid-2028. Alphabet guarantees Google's payments. Google pays whether or not it takes the power. Fervo says the power will go to the grid at first, making it available for resale. The power is meant for a Utah data center that Google says it is only beginning to look at. An option tied to that data center requires Fervo to offer about 600 megawatts more by June 2030. If Fervo does not make the offer, it must repay what Google paid for 'deemed delivered energy', or power counted as delivered. A 2025 Utah law could allow delivery directly to the data center or through the grid, if regulators approve. Neither company gives the price. Fervo's own filing says it holds rights to use the grid for about 300 of the 396 megawatts.

Sources 15 documents — 7 SEC filings · 2 press reports · 2 social posts · 2 other documents · 1 transcript · 1 company release

Research trail Found 137 documents and read 129 of them while checking this deal and related ones.

  1. SEC · SEC filingsec.gov
    States 7 figures: 396 MW capacity · 99 MW tranches · term · guaranties · expansion option · reimbursement · sb 132
  2. SEC · SEC filingsec.gov
    States 4 figures: 396 MW take or pay · backlog change · plant · $5,500 installed cost
  3. SEC · SEC filingsec.gov
    States 3 figures: $11.9B backlog (for context) · 300 MW interconnection · framework
  4. SEC · SEC filingsec.gov
    States 2 figures: 396 MW announced · data center
  5. press reportcanarymedia.com
    States price
  6. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  7. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  8. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  9. transcriptstockanalysis.com
    Cited by the record; no single figure is quoted from it.
  10. company releasefervoenergy.com
    Cited by the record; no single figure is quoted from it.
  11. social postlinkedin.com
    Cited by the record; no single figure is quoted from it.
  12. social postlinkedin.com
    Cited by the record; no single figure is quoted from it.
  13. other documentbeavercountydatacenter.com
    Cited by the record; no single figure is quoted from it.
  14. press reportutilitydive.com
    Cited by the record; no single figure is quoted from it.
  15. other documentmorpheus-research.com
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: Fervo 8-K, Item 8.01, and its Exhibit 99.1 release (Sep 1 2026; filed); Fervo 10-Q for Q3 2026 (Nov 10 2026) and Q2 2026 (Aug 13 2026); 424B4 prospectus (May 2026); Fervo's furnished Q2 and Q3 releases (Aug 12, Nov 9 2026) and Q3 call (StockAnalysis transcript); Fervo's blog (Aug 31 2026) and LinkedIn post as reshared by Google's Lucia Tian and Amanda Peterson Corio; Google's Beaver County data-center page; Canary Media and Utility Dive (Sep 1–2 2026); Morpheus Research (Oct 6 2026) for the contested reallocation (read 2026-11) · as of Nov 2026

The evidence 16 sourced figures · 5 disputes · 1 for context

The record's headline Fervo–Google: a 15-year, take-or-pay PPA for 396 of enhanced geothermal at Cape Station, Beaver County UT — four 99 MW sub-tranches from 2028, Alphabet guaranteeing Google's side — for a Utah data center Google still calls potential; Fervo must offer ~600 MW more by June 2030 (to 'not less than approximately 950 MW' in the 8-K, ~1,000 MW in the 10-Q) or repay Google's payments for deemed delivered energy; no price is disclosed, and Fervo's contracted revenue rose ~$4.7B in the quarter this was its only addition

Size
396 MW for 15 years, take-or-pay, fixed terms (four 99 MW sub-tranches; eight GeoBlocks, 'Cape Google 400') · an expansion offer of ~600 MW ('at least 604 MW' in the 10-Q) by June 2030, Google's to accept · price undisclosed · Fervo's binding backlog 658 MW / ~$7.2B (Jun 30) → 1,054 MW / ~$11.9B (Sep 30): +396 MW and ~$4.7B, our difference
When
Mar 19 2026 (Geothermal Framework Agreement with Google Energy) → Aug 12 2026 (Q2 release: Cape Phase II, eight 50 MW GeoBlocks, toward a 2028 delivery date) → Aug 26 2026 (PPA signed) → Aug 31 2026 (Fervo's blog: the CAISO delivery point for its ~400 MW of California contracts 'is being retired in 2027') → Sep 1 2026 (announced; 8-K filed) → Sep 30 2026 (Cape Phase I's first 33 MW GeoBlock in commercial operation) → Nov 9–10 2026 (Q3 release, call and 10-Q: 'Cape Google 400') → mid-2027 (project-finance debt for Cape Google 400 expected) → Mar 19 2028 (either party may end the GFA if no definitive offtake agreement is signed) → mid-2028 (first power) → Q3 2028 (target commercial operation dates begin) → year-end 2028 (full 396 MW targeted) → 1H 2030 (SB 132 'expanded delivery capability' targeted) → Jun 2030 (the expansion's guaranteed commercial operation date)
Status
signed Aug 26 2026, announced Sep 1; under construction by Nov 9 — the first 50 MW turbines past factory acceptance tests, major equipment including over 60% of the air-cooled condensers delivered, drilling about 18% complete (Q3 release); project-finance debt expected about mid-2027 (CFO); first power mid-2028, target commercial operation from Q3 2028, the full 396 MW by year-end 2028; the expansion offer not yet made, the SB 132 approvals not yet granted, and interconnection rights for about 300 of the 396 MW (Q3 10-Q)
Structure
a 15-year power purchase agreement between Cape Generating Station 6 LLC, Fervo's wholly owned subsidiary, and Google Energy LLC, Alphabet's, for 'energy products' from a 396 MW enhanced geothermal project, each side backed by its parent's guaranty (Fervo Energy Company; Alphabet Inc.); grid-connected, take-or-pay, on terms fixed for its life (Fervo). Beside it, a capacity expansion option Fervo must offer — Google's to accept, a definitive agreement still to be negotiated — on pain of reimbursing Google's payments for deemed delivered energy; the expansion would be the first qualifying project under the Geothermal Framework Agreement of Mar 19 2026 (cost-plus pricing with caps, floors and escalating discounts on expansions; Google's audit and first-refusal rights), which the 396 MW sits outside of by Fervo's 10-Q (contested gfa-relation)
Programme
Time-to-power
Parties
Google buyer — Google Energy LLC, a subsidiary of Alphabet Inc., which guarantees its obligations; pays take-or-pay for 15 years, holds the expansion option and, under the GFA, rights of first refusal over parts of Fervo's pipeline. Also a Fervo shareholder (note) · Fervo Energy seller — through Cape Generating Station 6 LLC, its wholly owned subsidiary, under Fervo's parent guaranty; builds the eight GeoBlocks of Cape Google 400; must offer the expansion or reimburse Google's payments for deemed delivered energy
Record
disclosed / primary source · as of Nov 2026

Flows 4 as the record states them

  • Fervo Energy → Googlepowerenergy products from a 396 MW enhanced geothermal project at Cape Station for a 15-year delivery term, in four 99 MW sub-tranches — first power mid-2028, target commercial operation dates from Q3 2028, all 396 MW by year-end 2028 (contested first-delivery); grid-connected at first by Fervo's Q3 account (contested delivery-path)
  • Google → Fervo Energyppa-paymentstake-or-pay at a fixed, undisclosed price over the 15 years, guaranteed by Alphabet Inc.; by the difference in Fervo's own backlog, about $4.7B over the term (Fervo's Q3 2026 release; our arithmetic)
  • Fervo Energy → Googleexpansion-optionan offer of ~600 MW more at Cape Station ('at least 604 MW', 10-Q), guaranteed commercial operation no later than June 2030, delivered under Utah's SB 132 if approved — behind the meter by Fervo's Q3 account, 'either front-of-the-meter or behind-the-meter' by its 8-K; Google's to accept, terms to be negotiated (contested expansion-size)
  • Fervo Energy → Googlereimbursementcontingent: if Fervo does not make the offer, it repays Google's payments for deemed delivered energy — depending on the volume Google has paid for by then and on the market price against the PPA price; 'not currently estimable'

Resolved figures 16 each with the verbatim line from its document

  • capacity396 MW
    396 MW — the contract's own figure, in every Fervo filing and release; 'approximately 400 MW' and 'nearly 400 MW' (the Q3 release, Google's Lucia Tian and Amanda Peterson Corio on LinkedIn, Canary Media) round it. The seller is Cape Generating Station 6 LLC ('CGS 6'), a wholly owned Fervo subsidiary; the buyer Google Energy LLC, a subsidiary of Alphabet Inc. What it sells is 'energy products', which the 8-K does not itemize; Fervo's Sep 1 release calls it 'carbon-free energy'. Fervo calls it 'the largest enhanced geothermal power purchase agreement to date'
    “On August 26, 2026, Cape Generating Station 6 LLC ("CGS 6"), a wholly owned subsidiary of Fervo Energy Company ("Fervo" or the "Company"), entered into a Power Purchase Agreement (the "PPA") with Google Energy LLC ("Google"), a subsidiary of Alphabet Inc., for the sale of energy products from a 396 MW enhanced geothermal systems (“EGS”) project located at Cape Station in Beaver County, Utah.”
    Fervo 8-K, Item 8.01 (event Aug 26 2026, filed Sep 1 2026) · sec.gov
  • tranches99 MW
    four successive 99 MW sub-tranches (4 × 99 = 396), target commercial operation dates beginning in the third quarter of 2028 — the contract's split. The plant is split differently: eight GeoBlocks of about 50 MW, GeoBlocks 4 through 11 (plant). When first delivery comes is contested (first-delivery)
    “The project will be delivered in four successive 99 MW sub-tranches with target commercial operation dates beginning in the third quarter of 2028.”
    Fervo 8-K, Item 8.01 (Sep 1 2026) · sec.gov
  • term15
    15 years of delivery — the 8-K, the Q3 10-Q ('a 15-year PPA') and the Q3 release ('15-year, grid-connected, take-or-pay'). From first delivery in 2028 that runs to about 2043, our arithmetic; no document dates its start or end, or mentions an extension
    “The PPA has a 15-year delivery term.”
    Fervo 8-K, Item 8.01 (Sep 1 2026) · sec.gov
  • guaranties
    both parents stand behind their subsidiaries: Fervo Energy Company for CGS 6, Alphabet Inc. for Google Energy LLC. Fervo's CEO on the Q3 call: 'For Fervo, it is a firm, binding, and financeable contract that we can build against today, with parent guarantees from both Fervo and Alphabet behind it.' Neither guaranty's cap, if any, is disclosed
    “Fervo has provided a parent company guaranty in support of CGS 6's obligations under the PPA, and Alphabet Inc. has provided a parent company guaranty in support of Google's obligations under the PPA.”
    Fervo 8-K, Item 8.01 (Sep 1 2026) · sec.gov
  • announced396 MW
    announced Sep 1 2026, six days after signing, in Fervo's release (GlobeNewswire) and its 8-K the same day; the 8-K attaches the release as Exhibit 99.1 under Item 8.01 and incorporates it by reference, so the release is filed, not furnished. Google's side: Lucia Tian, its director of advanced energy technologies ('nearly 400 MW of power from Fervo's Cape Station project'), and Amanda Peterson Corio on LinkedIn, each resharing Fervo's post; Michael Terrell, Head of Advanced Energy, is quoted in the release. Canary Media: Fervo's shares 'jump 15%' that morning
    “HOUSTON, September 1, 2026 (GLOBE NEWSWIRE) – Fervo Energy (Nasdaq: FRVO), a global pioneer of next-generation geothermal energy, today announced a 396-megawatt (MW) power purchase agreement (PPA) with Google”
    Fervo release, 8-K Exhibit 99.1 (Sep 1 2026) · sec.gov
  • take-or-pay396 MW
    take-or-pay, grid-connected, on fixed terms — Fervo's account, in its furnished Q3 release; its CEO on the call: 'It is a 15-year take-or-pay agreement, meaning Google is committed to paying for this power irrespective of the Beaver County data center plans, on terms that are fixed for the life of the contract', and 'For Google, we believe grid connectivity means the power they are buying has value regardless of how much of the power they consume, as Google can monetize power in the broader market.' Its CFO: 'Our goal when we wrote that PPA was to have a 400 MW PPA that looks and feels like most PPAs and is financeable'. The 8-K itself names neither take-or-pay nor a fixed price; the PPA is not public
    “The agreement is a 15-year, grid-connected, take-or-pay contract for 396 megawatts across eight GeoBlocks, with fixed terms.”
    Fervo Q3 2026 release, 8-K Exhibit 99.1 (Nov 9 2026; furnished) · sec.gov
  • price
    undisclosed — no document on file states the PPA's price or the contract's value. The 8-K mentions 'the PPA price' only inside the reimbursement formula (reimbursement). The record's only gauge of its size is the rise in Fervo's backlog (backlog-change). Fervo's one disclosed contract price, $107/MWh for the 115 MW Corsac PPA in Nevada that NV Energy filed, is a different contract (note)
    “The companies did not disclose PPA terms.”
    Canary Media (Sep 1 2026) · canarymedia.com
  • backlog-change
    what the contract added, by difference: Fervo ties the change to this agreement, and the 396 MW is the whole of the change in megawatts (1,054 − 658), so ~$11.9B − ~$7.2B ≈ $4.7B is Fervo's own estimate of the contract's revenue over its 15 years — our subtraction of two rounded figures, not a disclosed contract value. William Blair's note the day after the announcement had it the same way: the PPA 'increases contracted revenue across Fervo’s portfolio by about 65%' (Utility Dive; 4.7 ÷ 7.2 ≈ 65%). Over 396 MW × 8,760 hours × 15 years it would be about $90 per MWh if the plant ran at full output every hour, more at any lower output (our arithmetic; no price is disclosed). The est ribbon draws the $4.7B. No figure stands beside this entry: the change is our subtraction, which no document states, and the quote's two figures are the book's ends, not the change
    “With the signing of the Google agreement, Fervo now has 1,054 megawatts of capacity under binding power purchase agreements, representing approximately $11.9 billion in contracted revenue, compared to 658 megawatts and approximately $7.2 billion at the end of the second quarter of 2026.”
    Fervo Q3 2026 release, 8-K Exhibit 99.1 (Nov 9 2026; furnished) · sec.gov
  • expansion-option
    an offer Fervo is bound to make, not a commitment by Google: 'Any capacity expansion is subject to Google’s acceptance of the offer and the negotiation of a mutually acceptable definitive agreement' (the 8-K); the 10-Q: 'subject to Google’s acceptance and the negotiation of a definitive agreement'. How big it is depends on the document (contested expansion-size); its date does not — no later than June 2030 in the 8-K and the releases. What triggers it is unclear by Fervo's own account: the CFO, on the call, 'that is more tied to the outcome on the data center. The trigger for the option is not quite as clear as any kind of specific permit', and Google is expected to keep 'making progress on that into 2027'. If accepted, it would be the first qualifying project under the GFA (framework), priced cost-plus
    “In connection with the PPA, the Company has also agreed to offer Google a capacity expansion option of approximately 600 MW at Cape Station, such that total contracted enhanced geothermal capacity would be not less than approximately 950 MW, with a guaranteed commercial operation date no later than June 2030.”
    Fervo 8-K, Item 8.01 (Sep 1 2026) · sec.gov
  • reimbursement
    the option's backstop: if Fervo does not make the offer, it repays what Google has paid CGS 6 for 'deemed delivered energy' under the PPA — an amount that 'would depend on the volume of deemed delivered energy for which Google has made payment at the time the obligation arises and the difference between the market price and the PPA price, and is not currently estimable'. What 'deemed delivered energy' covers, and when the obligation arises, the 8-K does not say; it is the only flow in the record from Fervo to Google in money
    “If the Company does not make the required capacity expansion offer, the Company is obligated to reimburse Google for amounts previously paid by Google to CGS 6 in respect of deemed delivered energy under the PPA.”
    Fervo 8-K, Item 8.01 (Sep 1 2026) · sec.gov
  • data-center
    a data center Google has not committed to: Fervo's release, 'a potential data center in Utah', and 'Final data center plans remain subject to a variety of factors including engineering feasibility, state and local approvals, and commercial conditions'; its Q3 release, 'a potential regional data center in Beaver County, Utah'. Google's own page for it: 'Google is in the very early stages of reviewing this opportunity and evaluating options to determine if Beaver County is the right fit'. Canary Media, on the announcement day: 'Google said it hasn’t determined where it will build the Utah data center that will run on Cape Station’s power.' Fervo's CEO: 'We build Cape Station on our schedule, Google can develop a potential data center on their schedule, and neither party is waiting on the other.' No document names, sizes or dates it
    “Under the agreement, Google will purchase carbon-free energy designed to serve as a foundational building block for a potential data center in Utah.”
    Fervo release, 8-K Exhibit 99.1 (Sep 1 2026) · sec.gov
  • sb-132
    the delivery Fervo is pursuing beside the grid: Utah's Senate Bill 132 (2025) lets generation serve a large load directly, through a 'closed private generation system'. The 8-K: the project 'is being developed in a manner intended to utilize flexible power delivery pathways authorized under Utah Senate Bill 132' but 'remains subject to receiving relevant regulatory approvals required under SB 132', with 'target commercial operation for this expanded delivery capability in the first half of 2030'; 'additional energy resources' — developed by others, Fervo's Aug 31 blog says — would supplement the geothermal. The CEO: 'Our joint work to seek regulatory approval is underway'. Which megawatts it would carry is contested (delivery-path)
    “Under the framework established by SB 132, it is anticipated that the Company's EGS, supplemented by additional energy resources, would deliver generating capacity through a closed private generation system, which may be configured for either front-of-the-meter or behind-the-meter interconnection to serve data center load subject to further engineering feasibility and agency approvals.”
    Fervo 8-K, Item 8.01 (Sep 1 2026) · sec.gov
  • interconnection300 MW
    Fervo's own risk factor: about 300 MW of interconnection and transmission rights for the project, against 396 MW contracted to Google. If no more rights or other delivery arrangements come in time, 'our original PPAs would remain in effect; however, we may be unable to deliver the additional megawatts of contracted capacity, which could result in reduced revenues, payment of liquidated damages, contract modifications or terminations'. The same risk factor in its prospectus and Q1 and Q2 10-Qs had set ~290 MW of rights against 384 MW contracted to Southern California Edison and Clean Power Alliance for Phase II (reallocation)
    “For example, for our next project at Cape Station, we currently have approximately 300 megawatts of interconnection and transmission rights, which is insufficient to support the 396 megawatts of capacity contracted under our Google PPA.”
    Fervo 10-Q for Q3 2026 (Nov 10 2026) — Risk Factors · sec.gov
  • plant
    Cape Google 400: GeoBlocks 4 through 11, eight units of about 50 MW on Fervo's '3.0' well design (longer laterals, larger casing, deeper target) — the Q3 release's 'approximately 400 megawatts' for 396 contracted. Beside Cape Station Phase I, three 33 MW GeoBlocks, the first in commercial operation on Sep 30 2026 and the other two expected by Jan 1 2027. By Nov 9: the first set of 50 MW turbines through factory acceptance tests, recuperators and 'over 60 percent of air-cooled condensers' delivered, drilling 'approximately 18 percent complete'. The CFO expects project-finance debt for it 'probably in mid-2027', at about 70% loan-to-value. The same eight units were Cape Phase II until the Q3 release renamed them (reallocation)
    “In connection with this agreement, Fervo progressed construction across Cape Station GeoBlocks 4 through 11, now referred to as Cape Google 400.”
    Fervo Q3 2026 release, 8-K Exhibit 99.1 (Nov 9 2026; furnished) · sec.gov
  • installed-cost$5,500
    $5,500 per kW, Fervo's target for Cape Google 400 ($3,000 its long-term goal), against about $7,000 per kW expected for Phase I's GeoBlocks 1–3 — a target, not a cost incurred. At 396 MW it would come to about $2.2B (our arithmetic; Canary Media: Fervo 'is investing over $2 billion'). Fervo's investment, not Google's payments
    “Fervo continues to target an installed cost of $5,500 per kilowatt for Cape Google 400, on the path to its long-term target of $3,000 per kilowatt.”
    Fervo Q3 2026 release, 8-K Exhibit 99.1 (Nov 9 2026; furnished) · sec.gov
  • framework
    the Geothermal Framework Agreement, dated Mar 19 2026, with Google Energy LLC (the 424B4): Fervo must propose projects of at least 1 GW within two years and up to 3 GW over its term (through 2033, the Q3 release); 'it does not obligate Google to accept any project, execute any power purchase agreement or provide us with any project financing', and either party may end it 'if no definitive offtake agreement has been executed by March 19, 2028' (the 424B4). It prices projects 'on a cost-plus targeted return basis, subject to caps, floors, and escalating discounts on expansion projects', gives Google audit rights over costs and pricing and 'certain rights of first refusal over portions of our project pipeline', and restricts Fervo's taking investment or financing from 'a broad category of entities defined as competitors under the GFA' (the 10-Q). The 10-Q calls it 'a non-binding agreement' in a heading and 'a binding framework under which we may propose' projects in the text. Its own agreement, with no record here; whether the 396 MW falls under it is contested (gfa-relation)
    “We recently entered into the GFA, a framework agreement with Google Energy LLC under which we have committed to propose geothermal development projects representing at least one gigawatt of geothermal capacity to Google within two years and up to three gigawatts over the term of the agreement.”
    Fervo 10-Q for Q3 2026 (Nov 10 2026) — Risk Factors · sec.gov

Contested figures 12 not reconciled — every position side by side, with its source and tier

expansion-size3 positions, side by side
~600 MW, to a total 'not less than approximately 950 MW' — the 8-K: 'a capacity expansion option of approximately 600 MW at Cape Station, such that total contracted enhanced geothermal capacity would be not less than approximately 950 MW, with a guaranteed commercial operation date no later than June 2030' (a total that implies an option of about 554 MW or more, our subtraction) Fervo 8-K, Item 8.01 (Sep 1 2026)
at least 604 MW, to ~1,000 MW — the Q3 10-Q, twice: 'the Company also agreed to offer Google an expansion of at least 604 MW of additional capacity, which would increase the combined project capacity to approximately 1,000 MW' Fervo 10-Q for Q3 2026 (Nov 10 2026)
~600 MW, 'for a total of nearly 1 GW, by June 2030' — Fervo's Sep 1 release (filed with the 8-K), its Q3 release and call ('which would bring the total to 1 GW'), and Fervo's LinkedIn post as Google's Lucia Tian and Amanda Peterson Corio reshared it. DCD's 'expand its offtake to 996MW by June 2030' is 396 + 600 stated as a term. The PPA and the offer are not public, so nothing settles whether ~950 MW or ~1,000 MW is the floor Fervo release, 8-K Exhibit 99.1 (Sep 1 2026; filed) — support: Q3 release (Nov 9 2026; furnished) and call, Fervo's LinkedIn post as Google staff reshared it, DCD (Wayback)
first-delivery2 positions, side by side
target commercial operation dates 'beginning in the third quarter of 2028' — the 8-K, the only document to give a quarter for the contract's dates Fervo 8-K, Item 8.01 (Sep 1 2026)
first power in mid-2028, the full 396 MW by year-end 2028 — the Q3 release ('First power is expected from these GeoBlocks in mid-2028, with full capacity in operation targeted by year-end 2028'); the CEO on the call, 'with commercial operation targeted again in mid-2028'. The 10-Q ('four 99 MW sub-tranches beginning in 2028') and the Sep 1 release ('expected to come online in 2028') give only the year, which fits either row. Whether mid-2028 first power and Q3-2028 target CODs are one milestone or two, no document says Fervo Q3 release, 8-K Exhibit 99.1 (Nov 9 2026; furnished), Q3 call
delivery-path3 positions, side by side
all 396 MW grid-connected; SB 132 only for the expansion — the Q3 release calls the PPA 'grid-connected' and pursues 'behind-the-meter, direct-to-load delivery under Utah's SB132 framework' 'For the 600-megawatt expansion'; the CEO: 'The signed 396 MW is the first layer, and it is initially grid connected' and 'The second layer, the 600 MW expansion option, is behind the meter' Fervo Q3 release, 8-K Exhibit 99.1 (Nov 9 2026; furnished), Q3 call
the project under SB 132 — the 8-K's paragraph follows the one describing the 396 MW PPA and the option, and says 'The project is being developed in a manner intended to utilize flexible power delivery pathways authorized under Utah Senate Bill 132', front- or behind-the-meter, 'to serve data center load', with 'target commercial operation for this expanded delivery capability in the first half of 2030'; Fervo's Sep 1 release: SB 132 'is anticipated to provide Fervo and Google with optionality on direct-to-load contracting'. The CEO's 'initially grid connected' fits either reading Fervo 8-K, Item 8.01 + Exhibit 99.1 (Sep 1 2026)
not yet deliverable in full over the grid — the 10-Q's risk factors: about 300 MW of interconnection and transmission rights for the 396 MW; without more, 'we may be unable to deliver the additional megawatts of contracted capacity'. No document says how the other ~96 MW (our subtraction) would reach the grid before an SB 132 path is approved Fervo 10-Q for Q3 2026 (Nov 10 2026)
gfa-relation2 positions, side by side
outside it — the 10-Q: 'The 396 MW PPA is in addition to the capacity contemplated under the GFA; the proposed 604 MW expansion, if accepted by Google, would be the first qualifying project under the GFA'; the Q3 release says the same of the 600 MW expansion Fervo 10-Q for Q3 2026 (Nov 10 2026) — support: Q3 release (Nov 9 2026; furnished)
under it — Fervo's LinkedIn post on the announcement, reshared by Google's Lucia Tian and Amanda Peterson Corio: 'Building on Fervo's longstanding partnership with Google, this agreement marks the first contracted capacity converted under our Geothermal Framework Agreement.' It matters to the GFA's own clock — either party may end the GFA if 'no definitive offtake agreement' is signed by Mar 19 2028 (the 424B4) — and whether this PPA counts as one, no document says Fervo's LinkedIn post (Sep 1 2026), as reshared by Google staff
reallocation2 positions, side by side
the same eight units once meant for California — Fervo's Q2 release (Aug 12 2026): 'Fervo's second phase of development at Cape Station, 400 megawatts across eight 50-megawatt GeoBlocks, continues to advance toward its 2028 delivery date'; its prospectus dates Phase II's contracts (Southern California Edison, Clean Power Alliance) to a Jun 1 2028 COD deadline, with a counterparty's right to terminate six months after; its Aug 31 blog: 'For the roughly 400 MW of subsequent capacity contracted for delivery into CAISO, the delivery picture has changed since those agreements were signed', the Utah delivery point 'being retired in 2027', and 'We are actively exploring contracts with prospective data center customers to meet Cape’s near-term development timeline'; the Q3 release: GeoBlocks 4 through 11 'now referred to as Cape Google 400'. A Wolfe Research analyst on the call: 'the roughly 400 MW of PPAs that I think got kind of reshuffled'; Morpheus Research, a short seller: 'it has reassigned this capacity to Google' Fervo Q2 and Q3 releases (Aug 12, Nov 9 2026; furnished), blog (Aug 31 2026), Q3 call — the 424B4 (filed) only for Phase II's contracts and deadline; support: Morpheus Research (Oct 6 2026), a short seller
a separate matter, the California contracts intact — the 10-Q: 'Separately, we are currently renegotiating the delivery timing under certain of our existing Cape Station Phase II PPAs, with delivery expected to occur in the early 2030s'; its CFO, answering the 'reshuffled' question: 'we're working through those amendments as we speak' and 'we're still kind of circling 2032 for delivery of those PPAs'. No executed amendment, utility statement or regulator's approval of new dates is among the documents read; until one, the prospectus's 2028 deadline stands Fervo 10-Q for Q3 2026 (Nov 10 2026) — support: Q3 call (CFO)

For context, not this deal's figures 1 kept beside the deal so they are not mistaken for its numbers

  • backlog$11.9B
    Fervo's whole book, not this contract: 1,054 MW of binding PPAs 'representing approximately $11.9 billion in potential revenue backlog' at Sep 30 2026, against 658 MW and ~$7.2B at Jun 30 (Q2 10-Q: 'As of June 30, 2026, we had signed 658 megawatts of binding power purchase agreements … representing approximately $7.2 billion in potential revenue backlog'). Utilities hold ~$5.7B of it at both dates (Q3 10-Q: 'approximately $5.7 billion of our approximately $11.9 billion contracted backlog revenue'), so the rise is outside the utilities' contracts. Google's post (resharing Fervo's) counts the same 1,054 MW
    “As of September 30, 2026, we had signed 1,054 megawatts of binding power purchase agreements and other arrangements for the sale of power and related attributes (“PPAs”) with credit-worthy utility and corporate buyers, representing approximately $11.9 billion in potential revenue backlog.”
    Fervo 10-Q for Q3 2026 (Nov 10 2026) — MD&A overview · sec.gov

Scope note what this record leaves to other records

Not this deal — on the fervo entity or not carried: Google's other ties to Fervo — the 2021 corporate agreement behind the Project Red pilot in Nevada (online 2023; the release: it 'delivers power to the local grid, including Google's data centers in the state'), the 115 MW Corsac PPA among Fervo, NV Energy and Google under Nevada's Clean Transition Tariff (June 2024; $107/MWh in the NV Energy filing; target operation 2030), its participation in Fervo's $462M Series E (Dec 2025, Utility Dive) and the Fervo shares Alphabet reports on its 13F; the GFA itself (framework), whose 3 GW is a ceiling on proposals, not contracted power; Google's planned data center, of which no document gives a size, site or date; Fervo's company-wide matters covered in the documents — its May 2026 IPO, Cape Phase I and its financing, the Project Red pilot's output, thermal decline and water loss (disputed between Fervo and Morpheus Research, a short seller), Cape's resource estimates (4.3 GW, then ~8.4 GW), its capex per kW and its 2027 revenue outlook. Cape Station's induced seismicity — the three largest events, in Sep 2026, measured about M3.0–3.3 on Fervo's vendor network and M2.6–3.1 in the University of Utah and USGS catalogs (Fervo, Oct 2026) — is a fact about the site, not the contract. Not read: Jefferies' note calling the PPA a 're-optimization' (a Reuters wire on Stockopedia, download refused with a 403) and the Benzinga transcript (403); the call is read from StockAnalysis's. Not adopted: DCD's 'expand its offtake to 996MW' (396 + 600 as a term) and its Google 'leading its Series B' (the $462M round was Series E, led by B Capital); the Salt Lake Tribune's 'Fervo committed to provide at least 1 gigawatt', where every filing says propose; Canary Media's right of first refusal 'to purchase up to 3 GW', where the filings scope it to 'portions of our project pipeline'.