Why it matters
CleanSpark's Sandersville data center is financed in part with junk bonds that come due some sixteen years before the base lease with Meta subsidiary Anviran, LLC ends. A CleanSpark subsidiary sold $2.276B of those bonds at 7.875%, due in 2031, and CreditFlow reported ratings of Ba2/BB-.
Tap a figure for the line in its source.
Meta gives CleanSpark
- of rent over the 20-year lease, by CleanSpark's estimate in documents it furnished, not filed; up to ~$11.6B with two 5-year extensions
- a 'limited parent guarantee' of Anviran's payments under the lease; no document in the record states its limit
CleanSpark gives
- of computing load (critical IT) at Sandersville, Georgia, leased to Anviran, LLC, a Meta subsidiary; first deliveries expected Q4 2027 → Meta
- a promise to fund the build's completion if the bond money and its other available funds, its own earlier equity included, fall short → Lenders & bondholders
- of Texas power sites, 718 acres, under a letter of intent and exclusivity — not a lease → Meta
Lenders & bondholders gives CleanSpark
- of 7.875% bonds due Oct 2031, sold at 98.5 cents on the dollar, for the rest of the build, CleanSpark's earlier spending on it and debt-service reserves
What happened
In July 2026, CleanSpark leased a data center it is building beside its mining site in Sandersville, Georgia, to Anviran, LLC, a Meta subsidiary. CleanSpark is a bitcoin miner that now calls itself a data-center developer. It named Anviran only in its September bond papers. Meta Platforms gives a 'limited' guarantee of Anviran's payments. The lease runs for 20 years and covers 175 megawatts of computing load. CleanSpark estimates the rent at about $6.6 billion over the 20 years, or $11.6 billion with two five-year extensions. CleanSpark gives those estimates only in releases, slides and calls. None of its formal filings gives a rent figure, and Meta's own filings never name CleanSpark, Anviran or the site. A CleanSpark subsidiary sold $2.276 billion of bonds at 7.875% to pay for the build. The bonds come due in 2031, long before the lease ends. CleanSpark promised to pay to finish the building if the bond proceeds and the project's other funds run short. The first space is due in late 2027, when the site starts shifting power from mining to the data center. For CleanSpark's Texas sites, Anviran has signed only a letter of intent.
Sources 26 documents — 12 SEC filings · 5 government statements · 5 press reports · 3 transcripts · 1 other document
Research trail Found 139 documents and read 118 of them while checking this deal and related ones.
- States 8 figures: site · tenant · guarantor · guarantee · dscr target · $327M dsra · more than $15M termination offer threshold · replacement tenant
- States 4 figures: 175 MW lease · lease terms · milestones · 885 MW texas LOI
- States 4 figures: 3% escalator · options deck · tenant parent · $2059M deck illustration
- States 4 figures: $2276M notes · 7.875% coupon maturity · use of proceeds · completion guarantee
- States 3 figures: 175 MW tenant as announced · delivery · construction and mining
- States 3 figures: $6.6B contract value · $11.6B extended value · $330M avg annual NOI
- States 2 figures: power supply · power term
- States 248 MW site power
- States power curtailment
- States meta filings silent
- States $68B meta july leases (for context)
- States CFO no wrapper
- States $2.227B notes proposed
- States $2.276B notes priced
- States security
- States holder filing
- States meta declined
- States 8.25% launch yield
- States 8.245% pricing and ratings
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: CleanSpark 8-K Item 8.01 + ex-99.1 (2026-07-14), Q3 FY26 10-Q (2026-08-06), 8-Ks of 2026-09-17 (Item 8.01 + ex-99.2 filed; ex-99.1 deck furnished), 2026-09-18 (Item 8.01 + ex-99.1) and 2026-09-25 (Items 1.01/2.03 + EX-4.1 indenture); Jul 14 investor-update and Aug 6 Q3 FY26 earnings-call transcripts; H.C. Wainwright panel transcript (Sep 14); City of Sandersville second amendment + council minutes (2026-08-17); Meta Q2 and Q3 2026 10-Qs; State Street N-MFP3 (2026-09-30); Bloomberg via Yahoo (Sep 18) and TBS (Sep 17); CreditFlow; BondTerminal; EDGAR full-text search 2026-10-26 (read 2026-10); Insider Monkey (Jun 9 2026, also on Yahoo Finance) for the June report of Meta's talks (read 2026-11) · as of Oct 2026
The evidence 39 sourced figures · 5 disputes · 1 for context
The record's headline Meta–CleanSpark, Sandersville GA: 20-year triple-net lease of 175 of critical IT to Meta's subsidiary Anviran, LLC under a 'limited parent guarantee' — Meta named by CleanSpark only in its bond papers; ~$6.6B base term (furnished only); $2.276B of 7.875% notes due Oct 2031, rated junk, fund the build
- Size
- 175 MW critical IT · ~$6.6B base term (furnished; ~$11.6B with both 5-yr options) · $2.276B 7.875% senior secured notes due Oct 1 2031, issued at 98.5
- When
- Jul 9–10 2026 lease + Meta's limited parent guarantee (the Texas LOI executed 'in connection with' the lease, undated) → Jul 14 announced, tenant unnamed → Sep 14 CEO: 'a guarantee from the parent' → Sep 17 $2.227B notes proposed; deck names Anviran and Meta → Sep 18 priced, $2.276B at 7.875% → Sep 25 closed, indenture filed → Q4 2027 first deliveries (rent from Nov 30 2027 in the deck) → Oct 1 2031 notes mature; 20-year term (the deck's rent schedule runs to 2047) + 2 × 5-yr options
- Status
- lease signed Jul 2026 (dated as of Jul 9; 'entered into' Jul 10); construction agreement signed alongside; notes closed Sep 25 2026; deliveries expected from Q4 2027 — no rent yet, and no AI revenue at CleanSpark as of Jun 30 2026 (10-Q); neither the lease nor Meta's guarantee is filed; Meta's filings never name CleanSpark, Anviran or Sandersville (EDGAR full-text search, 2026-10-26) — the lease may sit, unnamed, in the ~$68B of July leases its Q2 10-Q reports; the Texas exclusivity's length is undisclosed
- Structure
- 20-year triple-net lease (annual escalators; 3.0% in the deck) of data-center infrastructure for 175 MW of critical IT, on a new ~122-acre parcel beside CleanSpark's Sandersville mining site, from a CleanSpark subsidiary (the indenture's 'Subsidiary Lessor') to Anviran, LLC — 'a wholly owned subsidiary of Meta' (deck) — with Meta Platforms, Inc.'s 'limited parent guarantee' of Anviran's payments (indenture); two 5-year extension options (the deck adds one 12-month option); possible rent abatement or termination if CleanSpark misses financing, construction or delivery milestones. Built by the tenant's preferred contractor under a lump-sum turnkey contract (CEO), on the site's existing 248 MW of city power with no added supply, curtailable by the City in an emergency (since the first amendment, CleanSpark must curtail its load as the City or MEAG directs, by the full amount directed, within 30 minutes of the direction). Financed at CleanSpark's project subsidiary CSDC Finance I, LLC: $2.276B of 7.875% senior secured notes due Oct 1 2031 (Ba2/BB- per CreditFlow), guaranteed by CSRE Properties Sandersville, LLC and secured on the project's assets and the issuer's equity — interest only until full rent starts on every phase, then amortizing to 1.275× coverage; CleanSpark is to provide a completion guarantee; Meta guarantees the lease, not the notes. Beside it: the tenant's letter of intent and exclusivity over CleanSpark's 718-acre Texas portfolio (up to 885 MW) — not a lease
- Programme
- Meta buildout
- Parties
- Meta the tenant's parent and guarantor — the lessee is Anviran, LLC ('a wholly owned subsidiary of Meta', deck); Meta Platforms, Inc. gives a 'limited parent guarantee' of its payments (indenture). Meta's filings never name CleanSpark, Anviran or Sandersville, and it declined to comment to Bloomberg · CleanSpark landlord and developer through subsidiaries — CSDC Finance I, LLC, which issued the notes, and its subsidiary CSRE Properties Sandersville, LLC, which guarantees them (the two are the indenture's 'Company Parties') and is, with CleanSpark, the City's electric customer; the indenture calls the lessor only the 'Subsidiary Lessor' and does not say which company that is — and the completion guarantor, by a guarantee it 'will provide' (closing 8-K); mines bitcoin at the site until the lease commences · Lenders & bondholders bondholders — $2.276B of 7.875% senior secured notes due 2031, sold privately (Rule 144A / Regulation S) through Morgan Stanley as representative of the initial purchasers; orders of about $10B by Bloomberg's sources
- Record
- disclosed / primary source · as of Oct 2026
Flows 6 as the record states them
- Meta → CleanSparklease-payments~$6.6B of expected contract value over the 20-year initial term, ~$11.6B with both 5-year extensions, ~$330M of average annual NOI — CleanSpark's estimates, in its releases, slides and calls, in no filed document; triple net, so the tenant also bears all costs of the premises; the deck's illustrative rent escalates 3.0% a year. Rent begins with the first hall — Nov 30 2027 in the deck; deliveries are expected from Q4 2027 (10-Q)
- Meta → CleanSparkguaranteea 'limited parent guarantee' by Meta Platforms, Inc. of Anviran's payment obligations under the lease, dated as of Jul 9 2026 (indenture) — 'Guarantor of rent and operating expenses' in the furnished deck; no document in the record gives its limit, term or amount
- CleanSpark → Metacapacity175 MW of critical IT load at Sandersville, Georgia (8-K), deliveries from Q4 2027 (10-Q; the release), with the remaining halls into early 2028 (CEO); on the site's 248 MW of existing city power, which is to move from mining to the data center at lease commencement (10-Q)
- CleanSpark → Metaexclusivitya letter of intent and exclusivity over CleanSpark's Texas portfolio — 718 acres with up to 885 MW of secured and planned power (8-K), at Sealy and Brazoria (release); not a lease, its length and terms undisclosed
- Lenders & bondholders → CleanSparkdebt$2,276.0M of 7.875% senior secured notes due Oct 1 2031, issued at 98.500% (about $2.24B before fees, our arithmetic) by CSDC Finance I, LLC — for the rest of the build, reimbursing CleanSpark's earlier spending on it ('prior capital expenditures', indenture) and debt-service reserves ($327.0M at issue); interest only until full rent starts, then amortizing to a 1.275× coverage target
- CleanSpark → Lenders & bondholderscompletion-guaranteeCleanSpark's 'customary completion guarantee', which it 'will provide' (per the closing filing): it is to fund the issuer as needed for the build's timely completion if the notes' proceeds and other available funds, its earlier equity included, fall short — cap and duration undisclosed
Resolved figures 39 each with the verbatim line from its document
- lease175 MW175 MW of critical IT load, under a lease CleanSpark 'entered into' on Jul 10 2026 — the filed Item 8.01 of its Jul 14 8-K (the indenture puts the lease with a CleanSpark subsidiary, the 'Subsidiary Lessor'). CleanSpark builds the data center on a new ~122-acre parcel beside its Sandersville mining site (site); the tenant 'will deploy production-grade infrastructure' of its own inside it (10-Q MD&A). The 8-K's Item 8.01 names no tenant and gives no dollar figure: the tenant's name reached EDGAR two months later, in the bond papers (tenant, guarantor)
“On July 10, 2026, the Company entered into the Lease with the Tenant. Under the Lease, the Tenant will lease data center infrastructure at the Company’s Sandersville, Georgia campus supporting 175 megawatts of critical information technology load.”
CleanSpark 8-K, Item 8.01 (filed 2026-07-14) · sec.gov - tenant-as-announced175 MWhow CleanSpark described the tenant in what it filed before September: 'a leading global technology company' (10-Q Note 16), 'a global technology company' (MD&A), 'a data center customer' (risk factors); the 8-K's furnished Item 7.01 adds 'with a high investment grade credit profile', and its filed Item 8.01 says only 'the Tenant'. The same note puts the lease 'at newly acquired land located adjacent to' the Sandersville campus — the parcel the indenture describes (site). 'While the tenant remains confidential', the July release said; the name came with the bonds
“On July 10, 2026, the Company entered into a 20-year triple-net infrastructure lease agreement (the “Sandersville Lease”), with two five-year extension options, with a leading global technology company for 175 MW of critical information technology load at newly acquired land located adjacent to the Company’s Sandersville, Georgia campus (the “Sandersville AI Campus”).”
CleanSpark Q3 FY26 10-Q (quarter to Jun 30 2026, filed 2026-08-06), Note 16 — Subsequent Events · sec.gov - lease-terms20triple net — the tenant pays 'all costs, charges, indemnities and expenses of every kind and nature' — with annual escalators (3.0% a year in the deck: escalator) and a 20-year initial term; two 5-year extension options (the deck adds 'one 12-month option': options-deck). The rent itself and its schedule are in no filed document; the deck's illustrative rent runs from 2027 to 2047
“The Lease is a triple net lease (meaning all costs, charges, indemnities and expenses of every kind and nature will be paid by the Tenant) with annual escalators and an initial term of 20 years. The Tenant has two options to extend the term for five years each.”
CleanSpark 8-K, Item 8.01 (filed 2026-07-14) · sec.gov - milestonesthe landlord's risk, in the filed text: financing, construction and delivery milestones, and missing them may bring rent abatement or termination. The milestones, the abatements and any termination payment are not public — the lease is not an exhibit to the 8-K, to the 10-Q (whose exhibits are certifications) or to the bond closing. If the lease does end and the tenant pays more than $15.0M for it (liquidated damages included), the indenture puts the whole payment into an offer to repay noteholders (termination-offer-threshold)
“The Lease requires the Company to satisfy specified financing, construction and delivery milestones and other covenants and conditions. Failure to timely satisfy applicable milestones may result in rent abatements or termination of the Lease.”
CleanSpark 8-K, Item 8.01 (filed 2026-07-14) · sec.gov - texas-loi885 MWa letter of intent and exclusivity, not a lease: the same tenant over CleanSpark's whole Texas portfolio, 718 acres with 'up to 885 megawatts of secured and planned power capacity' (8-K Item 8.01). The release splits it: 271 acres at Sealy with 'nearly 300 MW', 447 acres at Brazoria with an initial 300 MW and the potential to expand to 600 MW. Its length is undisclosed — 'an exclusivity window, not at a finish line' (CEO, Jul 14 call), 'a short-duration exclusivity' (CEO, Sep 14) — and so are its terms: 'we haven't disclosed any more detail than what you see today' (CEO, Jul 14, asked about pricing). No rent, lease term or contracted IT load is disclosed for the Texas sites
“In connection with the Lease, the Tenant also executed a letter of intent and exclusivity arrangement covering 718 acres of the Company’s Texas portfolio with up to 885 megawatts of secured and planned power capacity.”
CleanSpark 8-K, Item 8.01 (filed 2026-07-14) · sec.gov - contract-value$6.6B~$6.6B of 'expected contract value' over the 20-year initial term — CleanSpark's figure, in the Jul 14 release (furnished under Item 7.01), the Sep 17 deck (furnished), the Jul 14 call and later releases and slides. No filed document — the 8-K's Item 8.01, the 10-Q, the indenture — gives a dollar figure for the lease, and Meta has stated none. The deck's illustrative rent schedule sums to $6,560M over 2027–2047, the same figure unrounded
“$6.6 billion of expected contract value across the initial 20-year term”
CleanSpark release, furnished (8-K ex-99.1 under Item 7.01, 2026-07-14) · sec.gov - extended-value$11.6B~$11.6B if the tenant exercises both 5-year extensions — INCLUSIVE of the $6.6B (the CFO on the Jul 14 call: the extensions 'add another $5 billion, bringing the total lease value over a 30-year term to approximately $11.6 billion'). Option-contingent and furnished only; not drawn
“$11.6 billion of expected contract value if two five-year extension options are exercised”
CleanSpark release, furnished (8-K ex-99.1 under Item 7.01, 2026-07-14) · sec.gov - avg-annual-noi$330M~$330M of average annual NOI at a margin of 'nearly 100%', because the tenant pays the costs — an average of an escalating schedule, not a first-year figure: the deck's illustrative rent is $5M in 2027, $220M in 2028, $254M in 2029 (the first full calendar year after the construction completion the deck expects in March 2028) and $419M in 2046. CleanSpark's projection, furnished only
“Expected cumulative NOI contribution margin of nearly 100%, or an average annual NOI contribution of approximately $330 million”
CleanSpark release, furnished (8-K ex-99.1 under Item 7.01, 2026-07-14) · sec.gov - escalator3%3.0% a year — the Sep 17 deck; the filed 8-K says only 'annual escalators'
“3.0% Annual Rent Escalator”
CleanSpark Sandersville investor presentation, furnished (Sep 17 8-K ex-99.1 under Item 7.01) · sec.gov - options-deck12the deck's version of the term: 20 years plus the two 5-year tenant options of the filed 8-K, 'plus one 12-month option', which appears in no other CleanSpark document. Its terms and value are unstated; the $11.6B counts only the two 5-year options (30 years)
“20 Years Base Lease Term + Two 5-Year Tenant Extension Options (plus one 12-month option)”
CleanSpark Sandersville investor presentation, furnished (Sep 17 8-K ex-99.1 under Item 7.01) · sec.gov - delivery2027first deliveries in the fourth quarter of 2027 — in a filed document, this 10-Q risk factor (the July release's sub-headline: 'deliveries expected to begin in Q4 2027'); the remaining halls follow, 'ramping steadily into early '28' (CEO, Jul 14 call). The first day itself is contested (first-rent): Nov 30 2027 in the deck, December 2027 for the first data hall in the CEO's Sep 14 remarks
“Although deliveries under the Sandersville Lease are expected to begin in the fourth quarter of 2027, our ability to meet that schedule depends on numerous factors, many of which are outside our control, including our ability to obtain financing for and complete the construction of the Sandersville data center project on time.”
CleanSpark Q3 FY26 10-Q (filed 2026-08-06), Risk Factors — Risks Related to Our Data Center Strategy · sec.gov - construction-and-miningtwo more facts from the filed note: a construction agreement signed at the same time — with a builder the tenant put forward ('our tenant actually made a suggestion' and 'we're using the preferred EPCM and GC of our tenant', CEO, Jul 14 call; 'our tenant actually came with a specific request for an EPCM' and 'a lump sum turnkey contract', CEO, Sep 14), not named and not priced in any document in the record — and mining that continues until the lease commences, when the site's power moves to the data center. The MD&A expects 'to fully decommission the existing bitcoin mining operations at the site during fiscal year 2028' (the year to Sep 30 2028)
“Concurrently, the Company also entered into a construction agreement to commence the development and construction of the designed AI data center infrastructure. The Company will continue to utilize the current Sandersville site for bitcoin mining until the lease commencement date, at which time the power will be diverted to the Sandersville AI Campus and bitcoin mining activity will cease.”
CleanSpark Q3 FY26 10-Q (filed 2026-08-06), Note 16 — Subsequent Events · sec.gov - site122a new ~122-acre parcel at 2200 Deepstep Road, 'adjacent to' the existing mining campus (10-Q) and bought before the lease by CleanSpark's account ('We closed on an additional 122 acres earlier this year', CEO, Jul 14 call; 'newly acquired land', 10-Q). The City's minutes hold two accounts: on Jul 20 the county development authority's Jayson Johnston told the council, in the minutes' summary, that 'The Development Authority holds 122 acres in Industrial Park West and Cleanspark approached them to purchase that land' and that 'Negotiations started last year to sell the property to them'; on Aug 17 the City Manager 'stated they have already purchased it'. The City's electric-contract amendment gives the parcel as 122.52± acres, Tax Parcel 076 004A (power-supply). A separate build next to the miners, fed by the mining site's power
““Datacenter Facility Site” means that certain land located at 2200 Deepstep Road, Sandersville, Georgia, 31082, and initially consisting of approximately 122 acres as of the Issue Date”
CSDC Finance I indenture (EX-4.1 to CleanSpark's 8-K, filed 2026-09-25), definitions · sec.gov - site-power248 MWthe site's power: a 248 MW maximum load under its city electric contract — 'the 248MW of power that they have now', in the minutes' paraphrase of an attorney reviewing the new terms with the council (Keith Porterfield of Cook and Associates). The contract's own number since its first amendment (Jul 2025), which rewrote every '230 MW' in the Jan 2024 contract to '248 MW' and '150 MW' to '168 MW' — a .docx in the City's packet, read when this record was built, though the copy on file has no extractable text. CleanSpark rounds it: 'nearly 250 megawatts of gross capacity', 'all 250 megawatts are currently energized and live' (CEO, Jul 14 call). The first amendment was not read when 230 / 248 / 250 MW were still disputed; it settles the dispute over one quantity and its history. 175 MW of IT on 248 MW is ~1.4 at the meter (our arithmetic)
“Keith said they couldn’t exceed the 248MW of power that they have now.”
City of Sandersville, council working-session minutes (2026-08-17) · sandersvillega.org - power-supplythe power side, on the City's paper: a second amendment to CleanSpark's electric contract with the City of Sandersville (effective Jan 24 2024, first amended Jul 21 2025) makes the new parcel a second delivery point within the contract's existing limits — the data center is to run inside the power the mining site already has. The amendment takes effect when both parties sign it. CleanSpark pays for the distribution lines and for 'additional substation infrastructure', and may pass power costs through to tenants 'on a nonprofit basis'. The council voted 3–2 on Aug 17 2026 to execute this second amendment (minutes); the copy in its meeting packet is unsigned
“CUSTOMER is not requesting, and CITY is not agreeing to provide, any increase in contracted supply obligations by reason of the inclusion of the NEW PREMISES.”
City of Sandersville, second amendment to the contract for electric service with CleanSpark (council packet, 2026-08-17) · sandersvillega.org - power-term10 yearsthe power contract runs ten years from the amendment — to about 2036 — then year to year unless either side gives notice of non-renewal at least 180 days before a term ends: a decade or so short of the 20-year lease it powers, though a clause commits the parties to negotiate a longer term if state law comes to permit one. From Nov 30 2027, the day the deck gives for first rent, the City's margin becomes a flat $579,328 a month for years 1–5 and $672,020 for years 6–10, 'regardless of CUSTOMER usage', in place of 3 mills per kWh — cut pro rata for the time the supply is 'interrupted or not served to the Premises by CITY', except for 'EXCUSED FAILURES': failures caused by an act or omission of CleanSpark or its agents or contractors (a shut-down or a failure to start operating at either premises included) or by Section 7 curtailment (power-curtailment). Hawesville has a smaller gap of the same kind (anth-terawulf-hawesville: a 15-year power contract, with automatic renewals, under a 20-year lease). 'often (10)' is the document's own typo for 'of ten (10)'
“remain in effect for an initial “TERM” often (10) years, from the date of this Second Amendment. Thereafter, this AGREEMENT shall continue on a year-to-year basis”
City of Sandersville, second amendment to the contract for electric service with CleanSpark (council packet, 2026-08-17), §11 · sandersvillega.org - power-curtailmentthe power is not firm on paper: the City may curtail it in an emergency, in its or MEAG Power's reasonable judgment, to protect essential uses such as hospitals, schools and residences, or the grid's integrity, and owes nothing for the lost revenue (the Jan 2024 contract, Section 7). The first amendment (Jul 2025; a .docx read when this record was built, with no extractable text) makes CleanSpark curtail within 30 minutes of a City or MEAG direction, with 'no compensation'. The second amendment leaves Section 7 standing and counts its curtailment as an 'EXCUSED FAILURE', so the City's flat margin is still owed. Whether the lease passes this risk to the tenant is not public; CleanSpark's 10-Q warns that interruptions 'could disrupt the Tenant’s operations'
“The electrical energy supplied by the CITY may be curtailed in whole or in part by the CITY at any time that an emergency exists, in the reasonable judgment of the CITY or MEAG Power”
City of Sandersville, contract for electric service with CleanSpark (council packet copy, undated; effective 2024-01-24 per the amendments' recitals), Section 7 · sandersvillega.org - tenantthe tenant named, at last, in a filed document: Anviran, LLC — in the indenture for the bonds that fund the build (EX-4.1 to the Sep 25 8-K). The July 8-K and the 10-Q never name it, and EDGAR's full-text search finds 'Anviran' in exactly two documents, both CleanSpark's: this indenture and the Sep 17 deck (search run 2026-10-26). That Anviran is Meta's is the deck's statement (tenant-parent); the indenture gives Meta's role (guarantor)
““Datacenter Tenant” means Anviran, LLC and any successor pursuant to the terms thereof.”
CSDC Finance I indenture (EX-4.1 to CleanSpark's 8-K, filed 2026-09-25), definitions · sec.gov - guarantorMeta Platforms, Inc. — the 'Datacenter Lease Guarantor' in the same filed indenture, the only filed document that names Meta in the deal. Meta guarantees the lease, not the bonds: the notes' guarantor is CleanSpark's subsidiary CSRE Properties Sandersville, LLC (security)
““Datacenter Lease Guarantor” means Meta Platforms, Inc. and any successor pursuant to the terms thereof.”
CSDC Finance I indenture (EX-4.1 to CleanSpark's 8-K, filed 2026-09-25), definitions · sec.gov - guaranteewhat Meta gives: a 'limited parent guarantee', dated as of Jul 9 2026 like the lease, 'relating to the Datacenter Tenant’s payment obligations'. 'Limited' is the indenture's word, and the limit is stated nowhere it mentions the guarantee; the guarantee is not an exhibit. The deck describes it without the word (contested guarantee-scope). The noteholders' hold on it binds CleanSpark's side only: the issuer and CSRE Properties (the indenture's 'Company Parties') may not terminate, amend or replace the lease or the guarantee without holders of at least 75% of the notes (§4.16(a)) — except, under §4.16(b), changes that in the issuer's own good-faith judgment are not materially adverse to holders (§4.16(c) deems 'Permitted Development Changes' neither materially adverse nor materially less favorable to them), facilitate a move to a qualifying replacement tenant or lease, make way for an additional project or shared facilities while the lease, taken as a whole, stays not materially less favorable to holders, or give effect to a termination for cause or an amendment in its place; and changes the law requires — and the guarantee being terminated or otherwise ceasing to be in force is a 'Datacenter Lease Termination Event'
““Datacenter Lease Guarantee” means the limited parent guarantee dated as of July 9, 2026, provided by the Datacenter Lease Guarantor relating to the Datacenter Tenant’s payment obligations under the Datacenter Lease.”
CSDC Finance I indenture (EX-4.1 to CleanSpark's 8-K, filed 2026-09-25), definitions · sec.gov - tenant-parentthe link from Anviran to Meta, said outright only here: a footnote of the Sep 17 deck, furnished (not filed) with the 8-K that launched the bonds; the filed indenture's 'parent guarantee' by Meta implies the same. Bloomberg reported it the same day, citing CleanSpark's materials (「クリーンスパークの資料によると」 in TBS's Japanese edition of the Sep 17 story: meta-declined), and again on Sep 18, 'according to a CleanSpark presentation'; Meta's filings never name Anviran (meta-filings-silent)
“The Tenant (Anviran, LLC) is a wholly owned subsidiary of Meta”
CleanSpark Sandersville investor presentation, furnished (Sep 17 8-K ex-99.1 under Item 7.01), footnote 2 · sec.gov - meta-declinedBloomberg's Sep 17 story ('Meta-Tied Data Center Taps US Junk Bonds for the First Time', in TBS's Japanese edition, dated Sep 18 02:23 Japan time): CleanSpark and Morgan Stanley did not immediately respond to requests for comment; Meta declined to comment. The story gives Anviran as Meta's subsidiary and Meta's guarantee of rent and operating expenses, citing CleanSpark's materials (in Japanese, 「クリーンスパークの資料によると」) — the deck again. Nowhere in the record does Meta speak about Sandersville
“クリーンスパークとモルガン・スタンレーはコメントの要請に直ちに応じなかった。メタはコメントを控えた。”
Bloomberg (Gowri Gurumurthy), Sep 17 2026, via TBS CROSS DIG with Bloomberg (Japanese) · newsdig.tbs.co.jp - meta-filings-silentthe counterparty's silence, re-openable: Meta's Q3 2026 10-Q — its first report for a quarter that includes the lease (the Q2 10-Q, filed at the end of July, carries only the unnamed ~$68B of July leases: meta-july-leases) — totals the leases it has signed but not begun ($355.73B at Sep 30) without naming a landlord — the only lessors it identifies anywhere are its own data-center ventures in Louisiana and Texas — and never names CleanSpark, Anviran or Sandersville. EDGAR full-text search, run 2026-10-26: 'CleanSpark' and 'Sandersville' in Meta's filings (CIK 1326801), any date from 2001 → 0 hits each (the same search finds 'Hyperion' twice: Meta's 2026 proxy and a shareholder's filing under its CIK); 'Anviran' in anyone's → 2, both CleanSpark's — https://efts.sec.gov/LATEST/search-index?q=%22Anviran%22 . Meta's side of this record is described entirely by its landlord
“In addition to the lease liabilities that are included on our balance sheet, we have operating and finance leases that have not yet commenced as of September 30, 2026.”
Meta Q3 2026 10-Q (meta-20260930), Note 10 — Commitments and Contingencies · sec.gov - cfo-no-wrapperthe landlord's financing choice, in July, before the notes were sold: no credit wrapper. The guarantees in the record are Meta's limited guarantee of the lease (guarantee), CleanSpark's completion guarantee (completion-guarantee) and its subsidiary CSRE Properties Sandersville's guarantee of the notes (security). Only Meta's comes from outside CleanSpark's group, and it backs the tenant's payments under the lease, not the notes (the indenture lists the lease and its guarantee among its 'Project Documents'); nothing in the record has Meta guaranteeing the notes. The same call named the 'High yield bond market' as one route (the CFO, in Q&A); on Sep 14 the CEO was 'targeting right now high yield' and, after listing investors' questions ('who is the guarantor? What is the credit wrap?'), said 'We have got a guarantee from the parent'. The notes were sold as junk (pricing-and-ratings)
“I also want to point out that with a direct lease and a high investment-grade tenant, we have intentionally avoided using credit wrappers, which in our view, keeps our cost of capital low.”
CleanSpark investor update call on the Sandersville lease, CFO Gary Vecchiarelli (S&P Global transcript on CleanSpark's IR site, 2026-07-14) · s21.q4cdn.com - notes-proposed$2.227B$2.227B proposed on Sep 17 — the filed Item 8.01 (and the offering release, filed as ex-99.2): senior secured notes due 2031 from CSDC Finance I, LLC, sold privately under Rule 144A and Regulation S. The same 8-K furnished the deck, the first CleanSpark document to name the tenant and Meta. Upsized by $49M to $2.276B at pricing (notes-priced)
“On September 17, 2026, the Company issued a press release announcing the intention of CSDC Finance I, LLC, its wholly owned indirect subsidiary, to offer, subject to market conditions and other factors, $2.227 billion aggregate principal amount of senior secured notes due 2031”
CleanSpark 8-K, Item 8.01 (filed 2026-09-17) · sec.gov - notes-priced$2.276Bpriced Sep 18: $2.276B of 7.875% senior secured notes due 2031 at 98.500% of principal — filed Item 8.01, with the pricing release filed as ex-99.1 and incorporated. Bloomberg's 'almost $2.28 billion', from people familiar with the matter, rounds it
“On September 18, 2026, CleanSpark, Inc. (“CleanSpark” or the “Company”) issued a press release announcing that CSDC Finance I, LLC, its wholly owned indirect subsidiary, priced its offering of $2.276 billion aggregate principal amount of 7.875% senior secured notes due 2031 (the “Offering”) at a price equal to 98.500% of their principal amount.”
CleanSpark 8-K, Item 8.01 (filed 2026-09-18) · sec.gov - notes$2276Mclosed Sep 25: $2,276.0M sold under a purchase agreement with Morgan Stanley & Co. LLC as representative of the initial purchasers, under an indenture with U.S. Bank Trust Company as trustee and collateral agent (its 'Initial Notes' are '$2,276,000,000'). Issued at 98.500%: about $2.24B of proceeds before fees (our arithmetic)
“The aggregate principal amount of Notes sold in the offering was $2,276.0 million.”
CleanSpark 8-K, Items 1.01/2.03 (filed 2026-09-25) · sec.gov - coupon-maturity7.875%7.875% a year, paid Apr 1 and Oct 1 from Apr 1 2027; maturity Oct 1 2031 — five years, against a lease whose base term runs twenty. About $179M of interest a year on the full $2,276M (our arithmetic) before any principal is repaid; the first three coupons are prefunded from the bond's own proceeds (dsra)
“The Notes are senior secured obligations of CSDC Finance and bear interest at a rate of 7.875% per year payable semiannually in arrears on April 1 and October 1 of each year, beginning on April 1, 2027. The Notes will mature on October 1, 2031, unless earlier redeemed or repurchased in accordance with their terms.”
CleanSpark 8-K, Items 1.01/2.03 (filed 2026-09-25) · sec.gov - use-of-proceedswhat the money is for: (1) the rest of the build, (2) reimbursing CleanSpark for equity it has already put into Sandersville — a payment the indenture permits 'on or about the Issue Date' 'to reimburse Parent for prior capital expenditures' (§4.05(b)(xvi)), in an amount not disclosed — and (3) debt-service reserves, $327.0M at issue, which pay the bond's own first coupons (dsra)
“The Notes were issued at a price equal to 98.500% of their principal amount. CSDC Finance intends to use the net proceeds from the offering to (1) finance the remaining cost of the Sandersville Facility, a data center facility located in Sandersville, Georgia (the “Sandersville Facility”), (2) reimburse the Company for certain prior equity contributions made in respect of the Sandersville Facility and (3) fund debt service reserves.”
CleanSpark 8-K, Items 1.01/2.03 (filed 2026-09-25) · sec.gov - securitywho stands behind the notes: CleanSpark's property subsidiary CSRE Properties Sandersville, LLC guarantees them, and they are secured by first-priority liens on substantially all of the issuer's and CSRE Properties' assets, other than certain excluded property, and on the issuer's equity held by CSDC Holdings I, LLC (the offering release, filed with Item 8.01; the pricing release says the same). Meta is not a guarantor of the notes; its guarantee is of the tenant's payments under the lease (guarantee)
“The Notes will be fully and unconditionally guaranteed by CSRE Properties Sandersville, LLC, a wholly owned direct subsidiary of the Issuer (“CSRE Properties”).”
CleanSpark offering release (Sep 17 8-K ex-99.2, filed with Item 8.01) · sec.gov - completion-guaranteeCleanSpark's own support of the build: a 'customary completion guarantee', which the 8-K filed at closing says CleanSpark 'will provide' — it is to fund the issuer as needed for the facility's timely completion if the notes' proceeds and other available funds, its earlier equity included, fall short. The guarantee itself is not filed, and the indenture mentions completion guarantees only in general terms; its cap and duration are not disclosed
“CleanSpark will provide a customary completion guarantee with respect to the Sandersville Facility, under which it will fund the Issuer as necessary to ensure the timely completion of the Sandersville Facility in the event that the proceeds of the Notes and the available funds (including prior equity contributions by CleanSpark relating to the Sandersville Facility) are insufficient to do so.”
CleanSpark 8-K, Items 1.01/2.03 (filed 2026-09-25) · sec.gov - dscr-target1.275how principal comes back: semi-annually 'following the Final Commencement Date', in whatever amount brings coverage to 1.275× (8-K and indenture). The Final Commencement Date is when rent on every phase has begun to accrue in full — a trigger with no calendar date; until then the notes pay interest only. When amortization starts is contested (amortization-start)
““Target Project Debt Service Coverage Ratio” means a Project Debt Service Coverage Ratio of 1.275 to 1.00.”
CSDC Finance I indenture (EX-4.1 to CleanSpark's 8-K, filed 2026-09-25), definitions · sec.gov - dsra$327M$327.0M held back at issue for debt service: the interest due on the first three payment dates (Apr 1 2027, Oct 1 2027, Apr 1 2028) plus the first principal installment, less what the deposits earn meanwhile. $100.0M is the floor during construction and, initially, the requirement after it (the next coupon plus the next installment). Three half-year coupons at 7.875% on $2,276M come to roughly $270M (our arithmetic), so the bond's own proceeds pay its interest into spring 2028, past the first rent (Nov 30 2027 in the deck)
“(1) on the Issue Date, an amount (the “Initial Debt Service Reserve Required Amount”) initially equal to $327.0 million, which represents (a) the amount of scheduled interest due on the next two Payment Dates immediately following the Issue Date, plus (b) the amount of scheduled interest due on the third Payment Date immediately following the Issue Date, plus (c) the Installment due on the First Installment Payment Date”
CSDC Finance I indenture (EX-4.1 to CleanSpark's 8-K, filed 2026-09-25), definitions · sec.gov - termination-offer-thresholdmore than $15Mif the lease ends and the tenant pays more than $15.0M for it, the whole payment funds an offer to buy notes back at par plus accrued interest (pro rata with any pari passu debt whose terms require or permit it), made within 15 business days after the later of a qualifying replacement lease and the end of the re-leasing window — six months, or twelve if, among other conditions, a Qualified Tenant signs a letter of intent within the six (replacement-tenant). What holders decline, the company parties may use in any manner the indenture does not prohibit (§4.09(d)). No qualifying replacement by the window's end is an Event of Default
“(a) If any Datacenter Lease Termination Amount in an amount greater than $15.0 million is received by any Company Party, no later than 15 Business Days following the later of (i) the entry into a Qualified Datacenter Lease in respect of the Datacenter Lease subject to the Datacenter Lease Termination Event, and (ii) the last day of the Datacenter Lease EoD Period, the Issuer will make an offer to all Holders”
CSDC Finance I indenture (EX-4.1 to CleanSpark's 8-K, filed 2026-09-25), Datacenter Lease Termination Offer · sec.gov - replacement-tenantthe bar a replacement tenant must clear — rated by two agencies at least a 'Qualified Rating', which the indenture defines as the lesser of Meta's own rating as guarantor and AA- (S&P, Fitch) / Aa3 (Moody's); or pre-approved; or a listed hyperscaler, cloud or technology company worth at least $100.0B with a rating-agency confirmation; or guaranteed by Meta or a qualified guarantor; or approved by a majority of holders. The rating route sets the bar at whichever is lower, Meta's rating or AA-/Aa3; the notes themselves are rated Ba2/BB- (pricing-and-ratings)
““Qualified Tenant” means any (a) Person that has a corporate credit rating from any two Rating Agencies equal to or better than a Qualified Rating, (b) Pre-Approved Tenant, (c) Person who is a publicly listed hyperscaler, cloud provider or technology company with a Market Capitalization of at least $100.0 billion and for whom the Issuer obtains a Rating Agency Confirmation with respect to such Replacement Datacenter Lease”
CSDC Finance I indenture (EX-4.1 to CleanSpark's 8-K, filed 2026-09-25), definitions · sec.gov - deck-illustration$2059MCleanSpark's own path for the debt runs past the bond. The deck's 'post-construction illustrative' schedule — on the $2.227B first proposed and a '7.5% coupon being shown for illustrative purposes' — starts amortizing at construction completion ('expected in March 2028') at 1.275× and ends 2031 with $2,059M still owed (about 92%), reaching zero only in 2044. The notes mature Oct 1 2031 (coupon-maturity), so on this path about $2.06B would be due at maturity. No rerun at the priced 7.875% on $2.276B is in the record, and no document in the record says how the 2031 balance is to be paid. The maturity and the illustration's 2031 balance were disputed as one question; they are two facts, not two values of one
“Ending 2,227 2,227 2,204 2,165 2,117 2,059 1,990 1,908 1,814 1,705 892 664 409 126”
CleanSpark Sandersville investor presentation, furnished (Sep 17 8-K ex-99.1 under Item 7.01) — Debt Summary, ending balance by year · sec.gov - launch-yield8.25%Bloomberg (Gowri Gurumurthy, Sep 18): 'the first junk-bond offering for a data center tied to Meta', launched at 98.5 to yield 8.25% — 'roughly 1.75 percentage points more than the average for debt issued by BB rated firms tracked by Bloomberg' — on orders of about $10B, more than four times the deal; 'Similar financings backed by investment-grade tenants were sold at yields as low as below 6% earlier this year.' The yield's steps are moments, not a dispute: about 8.5% initial talk (Bloomberg, Sep 17, TBS edition) → '8.375% area' price talk → 8.25% at launch → 8.245% priced (CreditFlow). Unnamed sources; no bookrunner record
“The five-year notes launched at a price of 98.5 cents on the dollar to yield 8.25%, a separate person said, asking not to be identified because they are not authorized to speak publicly.”
Bloomberg via Yahoo Finance, Sep 18 2026 (Wayback 2026-09-24) · web.archive.org - pricing-and-ratings8.245%CreditFlow's deal-flow lines: priced at 98.50 to yield 8.245%, five-year non-call-two ('5NC2'), filed under high yield ('HYC'); rated Ba2 by Moody's and BB- by Fitch on the $2.227B proposal (its 'RATED' lines, Sep 18) — below investment grade. The agencies' own reports are not readable in the record: the two Fitch pages on file (by their addresses, an expected rating on Sep 18 and a final one on Oct 15) returned empty page shells. 'Green notes' is CreditFlow's label, in no CleanSpark document
“PRICED: CleanSpark (CSDC Finance I) $2.276bn 5NC2 sr sec green notes 7.875% at 98.50, yield 8.245% Sep 18, 2026”
CreditFlow (FINSIGHT) sponsor page, CleanSpark Inc — Deal Flow, PRICED line, Sep 18 2026 · creditflowresearch.com - holder-filing7.875the one SEC filing in the record by someone other than CleanSpark that shows the notes: a State Street money-market fund's N-MFP3 at Sep 30 2026 lists CSDC FINANCE I LLC — CUSIP 126315AA8, 7.875%, maturing 2031-10-01 — among the collateral of a Mizuho tri-party repo. It confirms the coupon and the maturity, not the size. The same repo's collateral includes Black Pearl Compute (6.125%, 2031), Cipher Compute (7.125%, 2030), Core Scientific Finance (7.75%, 2031) and Galaxy Helios Data Cntr (9.875%, 2031) notes
“<nameOfCollateralIssuer>CSDC FINANCE I LLC</nameOfCollateralIssuer> <LEIID>N.A.</LEIID> <CUSIPMember>126315AA8</CUSIPMember> <maturityDate> <date>2031-10-01</date> </maturityDate> <coupon>7.875000</coupon>”
N-MFP3 (CIK 1107414, State Street Institutional Investment Trust), report date 2026-09-30 — repurchase-agreement collateral · sec.gov
Contested figures 12 not reconciled — every position side by side, with its source and tier
For context, not this deal's figures 1 kept beside the deal so they are not mistaken for its numbers
- meta-july-leases$68BMETA-WIDE, NOT A SANDERSVILLE FIGURE: in July 2026 Meta signed 'additional data center leases with lease obligations of approximately $68 billion', expected to commence in 2027–28, with 18- to 20-year terms. Sandersville (dated as of Jul 9, a 20-year term, deliveries from Q4 2027) fits that description, but the filing names no landlord — a match, not a filed statement, and no share of the $68B is attributed here. The same figure sits on meta-blackrock-elpaso (meta-july-leases-context), which reads El Paso's lease as outside it (the same Q2'26 10-Q still said Meta 'will enter into' El Paso's leases)
“In July 2026, we entered into additional data center leases with lease obligations of approximately $68 billion, which are expected to commence in 2027 and 2028, with lease terms of 18 to 20 years.”
Meta Q2 2026 10-Q (meta-20260630), Note 9 — Commitments and Contingencies (leases not yet commenced) · sec.gov
Scope note what this record leaves to other records
NOT this record (carried elsewhere or not carried): CleanSpark's corporate figures — one confirmed figure, '$917MM of total liquidity as of 6/30/26' (about $202.6M of cash and 12,205 BTC on hand; the deck's '~14,000 BTC' also counts 1,719 BTC posted as collateral, which the $917M leaves out on the 10-Q's figures, though the deck and the CFO put all ~14,000 in it), the Q3 FY26 results, the $1.15B and $650M convertibles and the ~$400M of unused BTC-backed credit lines, contracted power (~1,817 MW at Jun 30 in the 10-Q) and BTC holdings → the cleanspark entity; the Aug 10 update deck's 2,110 MW (a wider count that adds Brazoria's second phase, still awaiting ERCOT) and hashrate → not carried. The Texas sites' own detail (Sealy's 207–209 MW first phase and later tranches; 'Sealy power is fully approved' in the July and August decks vs ERCOT's conditional 'batch zero' classification of both Texas sites, which rests on CleanSpark's word alone — its Sep 8 operational update, which the press relays; Brazoria's 447 acres vs 'up to 477 acres' on the Feb 5 call; 885 vs '890 MW' in the Jan–Feb releases and 'nearly 900 MW' in the CEO's Jul 14 quote) → carried only as the July release's split in texas-loi, which sums to the 8-K's 718 acres; nothing beyond the 8-K's 718 acres / 885 MW. Meta's Q3 10-Q 'Texas Venture' (20%, $14B of development cost, a $1.04B distribution) matches the El Paso venture of meta-blackrock-elpaso: no Meta filing names CleanSpark, and the LOI is not a venture. The mining site's annual interruptible-power contract with MEAG Power and the City (2027: a 110 MW planning load at 2015 George Lyons Parkway, renewed unanimously Oct 5 2026 — .docx files in the City's packet, read when this record was built, with no extractable text) → not carried: it governs the miners' load, and no document applies it to the data center. Site history (the 2022 purchase from Mawson — ~$34.3M at closing vs 'just over $40 million' and '$43M' in July 2026 retrospectives; the $2.0M earn-out suit, settled Jul 24 2026; 16.35 vs 40 vs 50 acres; '80 MW and 2.4 EH/s' in the 2026 decks vs 560 PH/s added at closing in the 2022 release) → not carried. Local-impact claims (wacodatacenterfacts.com: '$7 billion' of investment, ~470,000 sq ft, ~1,200 workers, 2025 taxes — one promotional site that contradicts itself on sales tax, and whose 'No new substation is required', credited to the county's development authority, sits uneasily with the City's amendment: 'additional substation infrastructure will be required') and the CEO's 494,000 sq ft and 400-person construction team (May 11 2026 call, before the lease) → not carried. Market colour: high-yield data-center issuance year to date ('more than $3 billion' in the English Sep 18 story via Yahoo; ~$39B in the Japanese edition of the Sep 17 story and in InvestNews's Portuguese version dated Sep 18, which leads with the pricing but follows the Sep 17 story further down — a difference that remains unresolved), CLSK's Jul 14 share move (22% intraday / 9.7% / 8.8% — three windows), BondTerminal's 97.91 / 8.39% yield to worst on Oct 23 → not carried. The deck's model metrics (2.9× 'Lease Support Coverage Ratio', $2,692M of cash after debt service, $1,746M of net interest — all at the illustrative 7.5% on $2.227B) and Terrain's 1.8× NOI/interest → not carried. CleanSpark's leverage target for the build ('about 80%, 85% LTV over time' and 'maybe at a 60% to 70% LTV for the first project or 2' in pre-lease remarks on the Nov 25 2025 call; 'finance in excess of 90% loan to cost is very common, and that's our target', the CFO on the Aug 6 2026 call — different measures, with the question left open; with no all-in cost the realized ratio cannot be computed) → not carried. The tenant leaked before the lease was announced: on Jun 6 2026, Insider Monkey wrote three days later, 'TheFly reported that Meta is in discussion with data center developer CleanSpark (CLSK) to secure space in the latter's data center facility', adding 'According to Green Street News Infrastructure, Meta is seeking to lease space at CleanSpark's Sandersville, Georgie facility, which has a capacity of roughly 250 Megawatts' (Insider Monkey, Jun 9 2026, also on Yahoo Finance; tier 2). The ~250 MW is the site's capacity as reported, not the 175 MW leased. TheFly's own brief returns 403 with no archived copy, and Green Street's story is not on file, so news gives the day the deal was public by, not its first day. Not adopted: stockanalysis.com titling the Sep 14 H.C. Wainwright panel, which seated several companies, a CleanSpark earnings call, so Core Scientific's, Soluna's and MARA's figures ($4.5M → $12–13M per MW, AMD's 500 MW, 80% debt, a 10% yield on cost) sit on a CleanSpark page — the record credits none of them to CleanSpark; earningsapi.io titling the Jul 14 investor update an earnings call; Holland & Hart's '$6.6B … Construction' headline (the $6.6B is lease revenue); Davis Polk's '$2.27 billion' (a truncation of $2.276B); the CEO's '$0.12 a kilowatt hour' (FY25 call, Nov 25 2025: an anecdote about Meta, not a price in this deal); the FY25 call transcript's '240-megawatt tranches' (likely two 40 MW tranches). Not errors: the deck's '3.56 billion daily active people' for Meta is Meta's own average for March 2026 (its Q1 2026 10-Q, cited on meta-capex-ramp), a quarter old by the deck's date (3.60B for June in the Q2 10-Q) — not carried; and the deck's 'Guarantor of rent and operating expenses', without the indenture's 'limited', is a position in contested guarantee-scope, not an error.