DTE–Oracle

An Oracle subsidiary will buy the Saline Township campus's power from DTE until February 2045, paying for at least 80% of 1,383 used or not, and for up to 1,383 MW of new batteries.

A deal between Oracle, DTE Electric

Why it matters

The Michigan Public Service Commission approved the Saline Township power deal on condition that DTE Electric alone absorbs anything Oracle's subsidiary leaves unpaid. DTE Electric proposes adding part of the substation cost to its rate base and passes its allocated transmission upgrade costs through a surcharge that all customers pay.

Tap a figure for the line in its source.

DTE Electric gives Oracle

  • of electric service for the campus, from Jan 2027 to full load in Dec 2027 (the customer may push that back up to 12 months), through Feb 28 2045, with two optional 10-year renewals
  • a new substation (~$300M), and transmission upgrades (~$200M) on its transmission provider's system; the campus's landlord pays $40M toward the substation, DTE proposes to put the rest of it in its rates, and the upgrades' cost reaches them through the fuel-and-power surcharge

Oracle gives DTE Electric

  • minimum bill: demand charges on 80% of the contracted capacity even if it uses less — about $19M a month at full ramp in the contract's own example, at the rates of the day it was signed
  • exit payment if the contract ends at full ramp (Dec 2027), falling month by month to two years' minimum bills (~$457M) by Dec 2035, where the contract's own example and DTE's testimony hold it; the clauses give two years' bills only on a customer default
  • of subscription charges, by DTE's estimate, for up to 1,383 of four-hour batteries built or contracted for the load; the customer keeps their market revenues

Oct 30, 2025 announced on DTE's earnings call, customer unnamedupdated Nov 21, 2026approved Dec 18 2025 disclosed by the parties

What happened

DTE Electric, the utility for Detroit and southeast Michigan, signed two contracts with Oracle subsidiary Green Chile Ventures to power the Saline Township campus. The contracts cover up to 1,383 megawatts from 2027 until February 2045. Oracle's subsidiary must pay for at least 80% of that capacity even if it uses less. It also owes a declining exit payment, about $2.26 billion if it leaves at full ramp. It pays for batteries DTE is building or contracting to serve the campus. Michigan's Public Service Commission approved both contracts on December 18, 2025 without a contested hearing. The Attorney General and environmental groups had asked for a contested hearing and have taken the case to the Court of Appeals. DTE says its new customer will save its other customers about $300 million a year once fully ramped. The challengers say the redacted contracts were never tested.

Sources 28 documents — 11 regulatory filings · 6 SEC filings · 3 transcripts · 3 other documents · 2 company releases · 2 press reports · 1 government statement

Research trail Found 446 documents and read 425 of them while checking this deal and related ones.

  1. SEC · SEC filingsec.gov
    States 5 figures: parties · term · $19,030,455 minimum monthly charge · $2,264,624,145 termination payment · $456,730,920 termination floor
  2. Michigan PSC · regulatory filingmi-psc.my.site.com
    States 4 figures: 1.383 GW contract capacity · 80% minimum bill · approval · $3.9B ESA charges
  3. SEC · SEC filingsec.gov
    States 2 figures: $2B dte storage capex · load ramp
  4. investor-relations PDF · transcripts24.q4cdn.com
    States 1.4 GW announced
  5. SEC · SEC filingsec.gov
    States customer renamed
  6. Michigan PSC · regulatory filingDec 18, 2025michigan.gov
    States 1,383 MW cost condition
  7. SEC · SEC filingsec.gov
    States up to 1,383 MW ESA
  8. Michigan PSC · regulatory filingMar 27, 2026michigan.gov
    States 332 MW storage tranches
  9. Michigan PSC · regulatory filingmi-psc.my.site.com
    States $300M substation
  10. Michigan Attorney General · government statementmichigan.gov
    States rehearing appeal
  11. Michigan PSC · regulatory filingadms.apps.lara.state.mi.us
    States 50% d11 comparison
  12. transcripts24.q4cdn.com
    Cited by the record; no single figure is quoted from it.
  13. regulatory filingmi-psc.my.site.com
    Cited by the record; no single figure is quoted from it.
  14. regulatory filingadms.apps.lara.state.mi.us
    Cited by the record; no single figure is quoted from it.
  15. regulatory filingopenmpsc.com
    Cited by the record; no single figure is quoted from it.
  16. regulatory filingopenmpsc.com
    Cited by the record; no single figure is quoted from it.
  17. regulatory filingopenmpsc.com
    Cited by the record; no single figure is quoted from it.
  18. other documentearthjustice.org
    Cited by the record; no single figure is quoted from it.
  19. other documentearthjustice.org
    Cited by the record; no single figure is quoted from it.
  20. regulatory filingmi-psc.my.site.com
    Cited by the record; no single figure is quoted from it.
  21. company releaseoracle.com
    Cited by the record; no single figure is quoted from it.
  22. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  23. company releaserelated.com
    Cited by the record; no single figure is quoted from it.
  24. other documentempoweringmichigan.com
    Cited by the record; no single figure is quoted from it.
  25. transcriptempoweringmichigan.com
    Cited by the record; no single figure is quoted from it.
  26. press reportaol.com
    Cited by the record; no single figure is quoted from it.
  27. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  28. press reportJun 2026wpr.org
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: DTE 10-K for 2025 ex. 10.1 (PSA) + ex. 10.2 (ESA); DTE 8-K, Item 1.01 (Oct 31 2025); MPSC order U-21990 (Dec 18 2025) + releases (Dec 18 2025, Mar 27 2026); MPSC orders U-22054 (Apr 30 2026) and U-22060 (Jul 16 2026) for the later storage tranches; DTE application and testimony; DTE Q3 and Q4 2025 calls; Attorney General's appeal brief (Aug 2026); Applied Digital indenture (ex. 4.1); Oracle affidavit, Wisconsin PSC docket 6630-TE-113 (the rename date); MPSC order U-22058 (Oct 1 2026) for the D11 floors; Oracle, Earthjustice, GLREA and DTE's investor presentation for the contested cells (read 2026-10); DTE's Q3 2026 earnings presentation (8-K ex. 99.2, furnished Nov 5 2026) for the storage capex, the load's status and DTE's rate-case claim · as of Nov 2026

The evidence 19 sourced figures · 7 disputes

The record's headline DTE–Oracle: power for the Saline Township campus to Feb 2045 — 1,383 on an 80% minimum bill, an exit payment of ~$2.26B at full ramp that runs down month by month, and up to 1,383 MW of batteries on Oracle's account; approved without a hearing Dec 18 2025, now before the Court of Appeals

Size
1,383 MW contract capacity · 80% minimum billing demand · minimum monthly charge $19,030,455 at full ramp (Exhibit E, illustrative) · termination payment $2,264,624,145 at full ramp, declining · ESA: up to 1,383 MW of four-hour storage, ~$3.9B of subscription charges (DTE estimate) · term to Feb 28 2045 + two 10-year options
When
Oct 22 2025 (PSA signed) → Oct 28 2025 (DTE's board approves the contracts) → Oct 30 2025 (DTE announces a 1.4 GW hyperscaler agreement) → Oct 31 2025 (DTE's 8-K names the customer as an Oracle subsidiary) → Nov 3 2025 (application) → Dec 18 2025 (approved ex parte) → Jan 15 2026 (conditions accepted) → Mar 27 2026 (rehearing denied; first 332 MW of storage approved) → Apr 17 2026 (Attorney General's appeal) → Apr 30 2026 (570 MW more storage approved) → Jul 16 2026 (300 MW more) → Aug 6–7 2026 (appeal briefs) → Nov 5 2026 (DTE's Q3 deck: construction underway) → Jan–Dec 2027 (load ramp)
Status
approved Dec 18 2025; conditions accepted by DTE Jan 15 2026; rehearing and reopening denied and the first 332 MW of storage approved Mar 27 2026, 570 MW more Apr 30 and 300 MW more Jul 16 2026 (1,202 of 1,383 MW); appeals by the Attorney General and environmental groups pending at the Michigan Court of Appeals; load from Jan 2027, full ramp Dec 2027 (DTE's Nov 5 2026 deck: 'approved and construction underway; expect load to ramp up in 2027')
Structure
two special contracts approved together — a primary supply agreement (PSA: service under DTE's Rate D11 with an 80% minimum billing demand, a termination payment and credit support) and an energy storage agreement (ESA: DTE builds or contracts up to 1,383 MW of storage in MISO Zone 7 and recovers each project's cost from the customer over up to 15 years) — between DTE Electric Company and Green Chile Ventures LLC (since renamed Oracle America Cloud Services LLC), with Oracle guaranteeing the customer's payments by a parent guaranty and, if applicable, a letter of credit; the campus's landlord — the Related–Blackstone venture (related-blackstone-oracle-saline) — advances $40M toward the substation
Programme
Time-to-power
Parties
Oracle customer — Green Chile Ventures LLC, now Oracle America Cloud Services LLC, the same subsidiary that leases the campus; Oracle Corporation guarantees its payments · DTE Electric utility — supplies the power on Rate D11 terms, builds or contracts the storage, and builds the substation and the distribution upgrades (under a line-extension agreement with the landlord); the transmission upgrades are on its transmission provider's system, which allocates their cost to DTE
Record
disclosed / primary source · as of Nov 2026

Flows 2 as the record states them

  • DTE Electric → Oraclepowerelectric service to 1,383 MW of contract capacity at full ramp (Dec 2027), about 10.9 TWh a year by DTE's estimate, until Feb 28 2045, plus two optional 10-year renewals; up to 1,383 MW of four-hour storage built or contracted to match the load
  • Oracle → DTE Electricpower-paymentsa minimum bill on 80% of contract capacity — $19,030,455 a month at full ramp in Exhibit E's example (≈$228M a year, our arithmetic) — plus energy and pass-through charges on actual use; subscription charges for the storage, about $3.9B in total by DTE's estimate, against which the customer receives the storage's net MISO market revenues; a termination payment of $2,264,624,145 if the contract ends at full ramp, declining

Resolved figures 19 each with the verbatim line from its document

  • announced1.4 GW
    first public on Oct 30 2025, when DTE's chief executive, Joi Harris, opened its third-quarter call with it: 'we finalized an agreement with a leading hyperscaler to support 1.4 gigawatts of data center load' — the customer unnamed; in the Q&A, 'the 1.4 gigawatts increases our load by 25%' (contested load-share). The same day OpenAI, Oracle and Related Digital announced the Saline Township campus (related-blackstone-oracle-saline). DTE filed for approval on Oct 31, withdrew that filing and refiled on Nov 3 2025 (the order, fn 1). DTE named the customer in its own filing the day after the call: an 8-K dated Oct 31 2025 (Item 1.01) says its board approved the two contracts on Oct 28 with 'Green Chile Ventures LLC (“Customer”) a wholly owned subsidiary of Oracle Corporation'
    “I am pleased to announce we finalized an agreement with a leading hyperscaler to support 1.4 gigawatts of data center load.”
    DTE Energy Q3 2025 earnings call (FactSet transcript, Oct 30 2025) · s24.q4cdn.com
  • parties
    the parties and the date: a Primary Supply Agreement entered into on Oct 22 2025 (the '22st day of October' in the filed text) between DTE Electric Company and Green Chile Ventures LLC, 'a Delaware limited liability company' whose address is redacted, with a companion Energy Storage Agreement (esa). The Commission's order calls GCV 'a subsidiary of Oracle Corporation' that plans to 'lease, operate, and cause to be constructed' the facility; Oracle guarantees all payment obligations under both contracts through 'a combination of a parent guaranty and, if applicable, a letter of credit' (DTE, per the order). Both contracts are filed as exhibits 10.1 and 10.2 to DTE's 10-K for 2025, with prices, collateral and the ramp's early months redacted
    “This Primary Supply Agreement (this "Agreement") is entered into on this 22st day of October, 2025 ("Contract Date"), by and between: (1) DTE Electric Company, a corporation organized under the Laws of the State of Michigan with an address of One Energy Plaza, Detroit, Michigan 48226 ("Company"); and (2) Green Chile Ventures LLC, a Delaware limited liability company”
    DTE Electric–Green Chile Ventures Primary Supply Agreement (DTE 10-K for 2025, ex. 10.1) · sec.gov
  • customer-renamed
    the customer's name now: Green Chile Ventures LLC became Oracle America Cloud Services, LLC — the definition of 'Oracle' in an indenture Applied Digital filed with the SEC for its own Oracle-leased project reads 'Oracle America Cloud Services, LLC (f/k/a Green Chile Ventures LLC)'. So DTE's customer, the campus's tenant (KBRA) and the tax-abatement applicant are one Oracle subsidiary (related-blackstone-oracle-saline); DTE's 2026 planning filings call it OACS. Oracle dates the rename itself, in a sworn affidavit by its VP of infrastructure capacity and sourcing to the Wisconsin PSC (docket 6630-TE-113): 'OACS was formerly named Green Chile Ventures, LLC, but was renamed on December 1, 2025' — before the Dec 18 2025 approval
    “together with its wholly owned subsidiaries, Oracle America, Inc., a Delaware corporation, and Oracle America Cloud Services, LLC (f/k/a Green Chile Ventures LLC), a Delaware limited liability company”
    Applied Digital indenture (SEC exhibit 4.1, 2026) — definitions; Oracle affidavit (Julia Robin), Wisconsin PSC docket 6630-TE-113 · sec.gov
  • contract-capacity1.383 GW
    1,383 MW of contract capacity at full ramp — 'a 1.383 gigawatt (GW) data center facility' in the Commission's order, 1,383 MW in Exhibit E's Dec-27 row; DTE's 'approximately 1.4 gigawatts' is the rounding. The load 'is scheduled to begin materializing in January 2027 with max load being achieved by December 2027' (DTE's application), and the customer may delay the ramp's steps by 'no more than twelve (12) months in the aggregate' (PSA §2.1) — to Dec 2028 at the latest (Foley, per the order). About 10.9 TWh of use a year, by DTE's Bilyeu. Utility demand, not IT load: KBRA rates a 974 MW campus (related-blackstone-oracle-saline, contested capacity)
    “DTE Electric seeks approval of a primary supply agreement (PSA) and energy storage agreement (ESA) (together, the special contracts) with Green Chile Ventures LLC (Customer or GCV), a subsidiary of Oracle Corporation, for supplying electric service to a 1.383 gigawatt (GW) data center facility (facility) in Saline Township, Michigan”
    MPSC order, Case U-21990 (Dec 18 2025) · mi-psc.my.site.com
  • term2045
    the initial term runs from the Commencement Date — first electric service — 'until 11:59 p.m. EPT on February 28, 2045', and the customer may extend it 'for an additional ten (10) year term up to two (2) times' on 24 months' notice (§3.2). The contract fixes the end date, not a number of years: about 19 years counted from approval (DTE, the Commission), 17+ from first service (Oracle), up to about 39 with both renewals — contested term-duration
    “The term (the "Initial Term") of this Agreement shall commence upon the Commencement Date and shall continue until 11:59 p.m. EPT on February 28, 2045.”
    Primary Supply Agreement §3.1 (DTE 10-K for 2025, ex. 10.1) · sec.gov
  • minimum-bill80%
    an 80% minimum billing demand, in DTE's Foley's own testimony: the 80% replaces the floors under Rate D11's three demand charges — a 65% ratchet on the two power-supply charges, and the greater of actual maximum demand or 50% of contract capacity on the distribution charge — and 'the Company will calculate all three demand charges using the greater of' 80% of the contract capacity for the billing period or the actual billing demand above it. The Minimum Monthly Charge rises with the ramp and 'will be held constant at the contracted capacity once the max load is achieved, notwithstanding changes to the D11 rate'; it is calculated on contract capacity even if usage never reaches the max load, which 'cannot be reduced during the term of the PSA'. (The order's summary has the MBD superseding the three charges themselves; Foley's text has it superseding their floors.) Measured against standard D11's floors of 50% of contract capacity or 65% of peak demand (d11-comparison)
    “According to Mr. Foley, the PSA provides that the MBD will be 80% of the contract capacity applicable for that billing period”
    MPSC order, Case U-21990 (Dec 18 2025) — summary of DTE's Foley testimony; Foley direct testimony (A24–A26) · mi-psc.my.site.com
  • minimum-monthly-charge$19,030,455
    $19,030,455 a month at full ramp (1,383 MW, Dec 2027) — Exhibit E's illustration, 'based on the current Schedule D11 rates and assumed load ramp, each of which is subject to change'; × 12 ≈ $228M a year (our arithmetic), Foley's 'approximately $230 million per year'. The exhibit's column headers read '($M)' but the cells are dollars: $19.03M a month is what squares with Foley's $230M a year. The ramp months before Dec 2027 are redacted
    “Dec-27 1,383 19,030,455 2,264,624,145 <-- Full Ramp Achieved (Dec 1, 2027)”
    Primary Supply Agreement, Exhibit E (DTE 10-K for 2025, ex. 10.1) · sec.gov
  • termination-payment$2,264,624,145
    $2,264,624,145 if the contract ends at full ramp in Dec 2027 — Exhibit E's illustration of §7.4.1, which charges 'the sum of the Minimum Monthly Charge for each month between the Early Termination Date and the tenth (10th) anniversary of the Load Ramp Completion Date' for an early termination that is neither party's default (§7.4.2 charges the same on DTE's termination for a customer default before the eighth anniversary of the Commencement Date): 119 months of $19,030,455 (our division). The exhibit then takes one month's charge off each month, down to two years' worth in Nov 2035, and holds it there (termination-floor). The Commission's 'approximately $2.3 billion' and Foley's '$230 million per year for 10 years, or $2.3 billion' (as the order summarizes him) are this row, rounded. 'no Termination Payment shall be payable by Customer hereunder if this Agreement is terminated as a result of a Company Event of Default' (§7.4.6); the customer's own termination right (§7.3.2) is redacted
    “Dec-27 1,383 19,030,455 2,264,624,145 <-- Full Ramp Achieved (Dec 1, 2027)”
    Primary Supply Agreement §7.4 + Exhibit E (DTE 10-K for 2025, ex. 10.1) · sec.gov
  • termination-floor$456,730,920
    the floor in Exhibit E: the payment loses one month's charge a month until it reaches two years of minimum bills in Nov 2035; from Dec 2035, '8 Years Post Full Ramp Achieved', a '24-month MMC Termination fee in effect' — $456,730,920 — holds every month to Feb 2043, after which the exhibit charges only the months left in the term (zero at Feb 2045). The exhibit, 'A sample calculation of the Termination Payment' (§7.4.3), names no cause of termination, and DTE's own summary (Foley, per the order) keeps the same floor without one: the payment is the minimum demand times 'the greater of' the months to the tenth anniversary 'or 2) 24 months', and 24 months' charges after that anniversary. The clauses are narrower: two years' charges appear only in §7.4.3, on DTE's termination for the customer's default after the eighth anniversary of the Commencement Date (first service), as the lesser of 24 months' charges and the months left in the term; a no-fault exit under §7.4.1 is charged the months to the tenth anniversary of full ramp, with no two-year minimum — contested termination-years
    “Dec-35 1,383 19,030,455 456,730,920 <-- 8 Years Post Full Ramp Achieved (December 1, 2035); 24-month MMC Termination fee in effect”
    Primary Supply Agreement, Exhibit E (DTE 10-K for 2025, ex. 10.1) · sec.gov
  • approval
    approved on Dec 18 2025, ex parte — without the contested hearing the Attorney General, ABATE, GLREA and others had asked for, all denied: 'DTE Electric Company's November 3, 2025 application for ex parte approval of special contracts, consisting of a primary supply agreement and energy storage agreement with Green Chile Ventures LLC, is conditionally approved' (the three-member Commission, at its Dec 18 meeting). The conditions include: DTE files a letter accepting them within 30 days (it did on Jan 15 2026, per the Attorney General's brief); applies within 90 days to change its emergency procedures so that, in a grid emergency, the data center's firm load is shed before any other customer's (or is reduced under an agreement with it instead); files an amended renewable energy plan with its next integrated resource plan; provides quarterly and annual reports; and bears any cost of serving the customer it cannot recover from it, a shortfall in the collateral included (cost-condition); the Commission may reopen the case if DTE's claimed affordability benefit 'fails to materialize'. This record gives Dec 18; Latitude Media's 'December 19' is a slip
    “DTE Electric Company's November 3, 2025 application for ex parte approval of special contracts, consisting of a primary supply agreement and energy storage agreement with Green Chile Ventures LLC, is conditionally approved.”
    MPSC order, Case U-21990 (Dec 18 2025) — ordering paragraph A · mi-psc.my.site.com
  • cost-condition1,383 MW
    the condition the Commission's release leads with, the same day: DTE is responsible for any cost of serving the data center that it cannot recover from Green Chile Ventures — other customers are not to pay for the customer's service if the customer does not. The release also sums up the contract's protections in its own words: 'A minimum billing demand of 80%, compared to 50-60% in the general D11 tariff', 'A minimum contract duration of 19 years', and 'A termination payment of up to 10 years' worth of minimum billing demand' (contested term-duration, termination-years)
    “Among those protections, the Commission conditioned approval on requiring DTE Electric to be responsible for any costs to serve the 1,383- megawatt (MW) data center in Saline Township that it is unable to recover from Green Chile Ventures LLC, a subsidiary of the tech company Oracle Corp.”
    MPSC release, Dec 18 2025 · michigan.gov
  • esaup to 1,383 MW
    the Energy Storage Agreement: the customer 'desires to procure up to 1,383 MW of energy storage capacity' in MISO Zone 7, each project rated on four hours of continuous delivery and built, owned or contracted by DTE; each project's cost is recovered from the customer over a period that 'shall not exceed fifteen (15) years' from its commercial operation, and the agreement runs until the fifteenth anniversary of the final project's operation or Feb 28 2045, whichever comes first. 'the Customer will receive 100% of the incremental market revenues from the Midcontinent Independent System Operator, Inc. (MISO), net of charging costs' (DTE, per the order). The portfolio is to be 'approximately 65% company-owned and 35% third-party-owned' (Foley, per the order) — storage-tranches. The sponsors' release: 'a new battery storage investment financed entirely by Oracle'
    “Customer desires to procure up to 1,383 MW of energy storage capacity from Company in MISO's Zone 7 to facilitate the receipt of Electric Service in an amount equal to the Customer Committed Capacity Ramp within the accelerated timeframe requested by Customer.”
    DTE Electric–Green Chile Ventures Energy Storage Agreement, recital B (DTE 10-K for 2025, ex. 10.2) · sec.gov
  • esa-charges$3.9B
    about $3.9B: DTE's estimate of the total subscription charges under the ESA, 'accounting for both Company and third-party owned energy storage projects' — and its termination payment is 'an acceleration of the remaining payments that the Customer would have made', not a fixed fee. The Commission called the two exits 'the minimum termination amounts of approximately $2.3 billion under the PSA and $3.9 billion under the ESA'. A lifetime charge over each project's recovery period, before the MISO revenues the customer keeps; not DTE's capital spending (dte-storage-capex)
    “Total subscription charges under the ESA, accounting for both Company and third-party owned energy storage projects, are estimated at roughly $3.9 billion.”
    MPSC order, Case U-21990 (Dec 18 2025) — DTE's response to the motions · mi-psc.my.site.com
  • storage-tranches332 MW
    built in tranches: the first 332 MW — three DTE-owned projects, Fish Creek 132 MW, Cold Creek 100 MW and Pine River 100 MW, with batteries from LG Energy Solution Vertech — approved Mar 27 2026 as 'the first 332 MW of 1,383 MW'; a second of 570 MW, '175 megawatts (MW) of third-party owned projects and 395 MW of company-owned projects' (the Coldwater River and Tuscola II tolling agreements, DTE's Isabella and Meridian projects), approved Apr 30 2026 (U-22054); and a third of 300 MW under the KCE MI 2 and Redstart tolling agreements, approved Jul 16 2026 (U-22060) — both times denying the Attorney General's request for a contested proceeding. That is 1,202 of the 1,383 MW approved (our sum); DTE 'intends to file additional company-owned projects to fulfill the remaining capacity' (the U-22060 order). The Mar 27 release calls all 1,383 MW 'company-owned', against the 65/35 split the filings carry (contested storage-ownership)
    “The data center battery storage projects approved today are the first 332 MW of 1,383 MW of company-owned energy storage facilities that Green Chile Ventures must foot the bill to develop to match the data center's contracted demand.”
    MPSC release, Mar 27 2026 · michigan.gov
  • dte-storage-capex$2B
    DTE's own capital behind the load: 'nearly $2 billion energy storage investment' — in the Oracle column of the data-center slide in DTE's Nov 5 2026 investor deck (furnished with its Q3 results), beside 'Oracle 1.4 GW (approved and in plan)' and '15-year energy storage contract covers capital investment'. The same figure DTE gave on its Q4 2025 call as 'nearly $2 billion of incremental storage investment' in its five-year plan (the deck drops the word 'incremental') — spending on the company-owned share of the storage, which the subscription charges repay; a different measure from the ~$3.9B of lifetime charges (esa-charges)
    “Load ramp supported by existing capacity and nearly $2 billion energy storage investment”
    DTE Energy Q3 2026 earnings presentation (8-K ex. 99.2, furnished Nov 5 2026) · sec.gov
  • substation$300M
    the new industrial substation DTE builds to serve the campus — about $300M of capital by its own testimony (Foley), initially about $35M a year of revenue requirement — and, beside it, transmission upgrades of about $200M (about $30M a year) to connect the facility and the storage, on 'initial estimates provided by the Company's transmission provider'. 'the Customer's landlord has agreed to pay a $40 million non-refundable construction advance' toward the substation — the landlord being the venture that owns the campus (related-blackstone-oracle-saline) — and DTE 'will propose adding the net cost (i.e., actual costs less the $40 million construction advance) to its rate base' in a future rate case; transmission costs, which the transmission provider allocates to DTE, are recovered through the PSCR. Who ends up paying is contested (who-pays-grid)
    “It expects that approximately $300 million of capital investment will be needed to construct the substation.”
    DTE application, Foley direct testimony (MPSC Case U-21990) · mi-psc.my.site.com
  • rehearing-appeal
    after approval: the Attorney General petitioned for rehearing (Jan 8 2026) and moved to reopen (Jan 20); DTE filed its letter accepting the conditions (Jan 15); on Mar 27 2026 the Commission denied the petition and the motion and approved DTE's acceptance — and the same day approved the first 332 MW of storage (storage-tranches). The Attorney General filed her claim of appeal on Apr 17 2026; her appeals and those of the Michigan Environmental Council, NRDC, Sierra Club and GLREA share one caption in the Court of Appeals, and the environmental groups filed their opening brief on Aug 7 2026 (Earthjustice). No decision is among the documents read
    “On March 27, 2026, the Commission denied the Attorney General's petition for rehearing and motion to reopen and approved DTE's letter of acceptance to the Commission-imposed conditions (AG Appendix E).”
    Attorney General's appeal brief, Court of Appeals (filed Aug 6 2026) — statement of jurisdiction · michigan.gov
  • load-ramp2027
    where DTE says the load stands on Nov 5 2026: '1.4 GW Oracle agreement approved and construction underway; expect load to ramp up in 2027' — the schedule its application gave (load from Jan 2027, full ramp by Dec 2027; contract-capacity), now with 'construction underway'. The line does not mention the customer's right to push the ramp back up to 12 months, and does not say whose construction it means — the campus's or DTE's own. DTE's words, in a furnished deck
    “1.4 GW Oracle agreement approved and construction underway; expect load to ramp up in 2027”
    DTE Energy Q3 2026 earnings presentation (8-K ex. 99.2, furnished Nov 5 2026) — data-center slide · sec.gov
  • d11-comparison50%
    what the 80% is measured against: under DTE's standard Rate D11 the minimum billing demand is '50% of contract capacity or 65% of the highest monthly peak demand' — the Commission, in its Oct 1 2026 order on DTE's Google contracts (U-22058), citing DTE's rate book. This record uses 50–65% for the comparison; the Commission's own Dec 2025 release says '50-60%' (cost-condition)
    “Under Rate D11, the MBD is either 50% of contract capacity or 65% of the highest monthly peak demand.”
    MPSC order, Case U-22058 et al. (Oct 1 2026) · adms.apps.lara.state.mi.us

Contested figures 21 not reconciled — every position side by side, with its source and tier

term-duration3 positions, side by side
about 19 years — the PSA runs 'for approximately 19 years, commencing with approval of the PSA by the Commission and concluding on February 28, 2045' (DTE, per the order); the Commission's release: 'A minimum contract duration of 19 years' MPSC order (Dec 18 2025); MPSC release
17+ years of service — 'DTE will provide Oracle electric service under an existing rate schedule for the next 17+ years' (Oracle, Dec 18 2025) Oracle blog (Dec 18 2025)
up to about 39 years — the ~19-year initial term plus both optional 10-year renewals (our arithmetic); the contract counts its term from first service and fixes only the end date Primary Supply Agreement §3 — arithmetic
termination-years4 positions, side by side
at least 10 years — 'a termination fee for the PSA that collects at least 10 years of the MBD' (DTE, per the order); Foley's testimony: the payment 'was designed such that the Company will recover at least 10 years of Minimum Monthly Charges' MPSC order (Dec 18 2025); Foley direct testimony (A29)
up to 10 years — 'A termination payment of up to 10 years' worth of minimum billing demand if the facility stops operating earlier than contracted to operate' (the Commission's release) MPSC release (Dec 18 2025)
a maximum of 11 years — 'A maximum 11-year duration for calculating an exit fee is much lower than the 15-year-or-longer duration the Commission ordered less than two months prior in Case U-21859' (the Attorney General's appeal brief) Attorney General's appeal brief (Aug 2026)
119 months at full ramp — Exhibit E's $2,264,624,145 ÷ $19,030,455 (our arithmetic), counted from full ramp, not from first service: §7.4.1 runs to the tenth anniversary of the Load Ramp Completion Date, and the payment loses a month's charge each month until it reaches the exhibit's two-year floor (termination-floor) Primary Supply Agreement §7.4.1 + Exhibit E — arithmetic
affordability4 positions, side by side
about $300M a year for existing customers once the load is fully ramped — 'Oracle data center provides ~$300 million of annual affordability benefits for existing customers once fully ramped' (DTE's investor presentation, May 2026, furnished); Oracle: 'approximately $300 million annually' by 2029–2030 (Dec 18 2025) DTE presentation (8-K exhibit, May 2026); Oracle blog (Dec 2025)
rising to it: the Commission read DTE's chart as showing 'an affordability benefit of approximately $150 million in 2027, ramping up to $300 million in 2029'; DTE argued that its cost-of-service model shows '$109 million in base rate benefits to residential customers' at full load, before the fuel-clause savings it also claims — DTE's own modelling throughout MPSC order (Dec 18 2025)
untested: the Commission approved 'behind an extraordinary wall of redactions, without putting the key evidence into the record or allowing it to be tested in a full hearing' (Sierra Club, with Earthjustice, Aug 2026); the order itself reserves the right to reopen the case if the benefit 'fails to materialize' Earthjustice release (Aug 7 2026); MPSC order
a rate-case pause, not a dollar figure — DTE's Nov 5 2026 deck: 'Oracle load ramp could allow us to delay the next DTE Electric rate case filing until at least 2028; Google ramp could extend ability to stay out', on a slide that says 'Data center load growth helps drive unprecedented affordability benefits for existing customers as excess capacity is sold and fixed costs are spread over a larger base'. The deck does not repeat the $300 million a year; 'could allow' is DTE's own forecast, and the press version is the pledge the note reports from WLNS DTE Q3 2026 earnings presentation (8-K ex. 99.2, furnished Nov 5 2026)
who-pays-grid3 positions, side by side
Oracle pays: 'Oracle will pay 100% of the energy costs to power the Saline Township campus, including battery storage. Oracle will also pay for new transmission lines to the campus and an onsite substation.' (Dec 18 2025) Oracle blog (Dec 18 2025)
everyone's rates, with the customer's share inside them: DTE's own testimony has the landlord advancing $40M of the ~$300M substation, the rest proposed for rate base in a future rate case, and the ~$200M of transmission recovered through the fuel-and-power clause, while DTE says serving the customer will not raise other customers' cost of service (substation) DTE application, Foley testimony; MPSC order
other customers, up front: the approval 'exposed customers to nearly half a billion dollars in up-front costs' (Earthjustice, Aug 2026, for the appellants) Earthjustice release (Aug 7 2026)
load-share3 positions, side by side
25% — 'the 1.4 gigawatts increases our load by 25%' (DTE's chief executive, Q3 2025 call) DTE Q3 2025 call (Oct 30 2025)
about 27% of forecast bundled sales — the load 'will increase DTE's forecast of bundled sales to retail customers by approximately 27%' (GLREA's motion to intervene) GLREA petition and motion, MPSC Case U-21990
more than 10% of peak demand and possibly more than 25% of energy sales — 'an increase of more than 10 percent to DTE's peak demand and potentially more than 25 percent to its total energy sales' (Earthjustice, Dec 2025) Earthjustice release (Dec 2025)
renewables2 positions, side by side
443 MW by 2032, or up to 3.2 GW — DTE's Bilyeu: the requirement 'could technically reach up to 3.2 GW, but may be as low as 443 MW by 2032 if the Company fully leverages its estimated REC bank' MPSC order (Dec 18 2025) — Bilyeu testimony
1,800 MW — the incremental solar DTE assumed in its affordability model, by GLREA's account: 'DTE Electric used 1,800 MW of incremental solar generation in its affordability modeling' (per the order) MPSC order (Dec 18 2025) — GLREA's motion
storage-ownership2 positions, side by side
all company-owned — the Commission's release: 'the first 332 MW of 1,383 MW of company-owned energy storage facilities' MPSC release (Mar 27 2026)
mixed — 'approximately 65% company-owned and 35% third-party-owned' (Foley, per the order); the second tranche is 'Company-owned projects and 175 MW of third-party owned projects' (395 + 175 MW) and the third is 300 MW third-party-owned MPSC order (Dec 18 2025); DTE applications U-22054, U-22060

Scope note what this record leaves to other records

Not this record: the campus's financing, lease and tenant (related-blackstone-oracle-saline) — the PSA's 'Landlord' is that venture; DTE's ~1 GW Google contracts (U-22058) are a sibling deal with their own record (pw-dte-google); DTE's company-wide capital plan, equity issuance and rate cases — WLNS (via AOL) reports DTE's pledge not to seek rate increases for at least two years if the campus is online by the end of 2027, as it prepared to ask the Commission for $474.3M for grid modernization (Apr 2026) — and DTE's 'nearly $9 billion' from its two data-center contracts through 2045 (its own projection, both contracts together — on the dte entity); the IRP and its gas plants. Not adopted: '14 gigawatts' of signed load (a transcript slip in a moderator's question; DTE's answer says 1.4 gigawatts); SemiAnalysis's at-least-$3.65B Oracle commitment behind the 1.4 GW (derivation not shown in the free part of a paid post, and it matches no filed figure — not the PSA's $2.26B, the ESA's ~$3.9B or DTE's ~$2B of storage capital); Google's contract terms read as Oracle's.

More between Oracle and DTE Electric

The record holds no other deal between them.

Everything between Oracle and DTE Electric →