WhiteFiber–Nscale, NC-1 (Madison NC)

Nscale rents 40 of IT capacity at WhiteFiber's NC-1 data center in Madison, North Carolina, for ten years: about $865M by WhiteFiber's count, yearly price rises and one-time installation charges included and power billed on top. All 40 MW were running by November 2026.

A deal between Nscale, WhiteFiber, Lenders & bondholders

Why it matters

Nscale sells GPU time to Microsoft and Anthropic; at NC-1 it is the colocation tenant underneath, renting a converted factory's power and cooling from a small Nasdaq landlord. Each side's paper sees half. WhiteFiber names Nscale and the ~$865M. Nscale's GPU loan blacks out the landlord and the customer whose payments repay it, and falls due by December 2031, about halfway through the ten-year term.

Tap a figure for the line in its source.

WhiteFiber gives Nscale

  • of IT load at NC-1, a converted manufacturing building in Madison, North Carolina, in two 20 halls, under a license to use the space; all 40 MW running by Nov 10 2026
  • first notice of any new capacity at NC-1 before WhiteFiber offers it to anyone else

Nscale gives WhiteFiber

  • over ten years by WhiteFiber's count, counting the yearly price rises and the one-time installation charges; electricity and some other costs are passed through on top
  • a year more on the recurring fees, by the companies' announcement; the filings give no rate

Lenders & bondholders gives

  • of loans on the building, signed Nov 9 2026 and not yet paid out: the first money waits on Nscale accepting the 40 → WhiteFiber
  • of loans to an Nscale company for the GPUs and equipment it puts in North Carolina (Aug 2026), due by Dec 2031; the loan papers black out the landlord's and the end customer's names → Nscale

Dec 18, 2025 announced by WhiteFiber and Nscale (WhiteFiber's release and 8-K) disclosed by the parties

What happened

In November 2025 Nscale, an AI cloud company that rents out GPU computing, signed a ten-year agreement to use 40 megawatts of IT capacity at NC-1. NC-1 is a former Unifi manufacturing building in Madison, North Carolina, that WhiteFiber bought in 2025 and turned into a data center. WhiteFiber, a Nasdaq-listed company about 60% owned by Bit Digital, counts the deal at about $865 million over the ten years, including yearly price rises and one-time installation charges. Nscale pays for the electricity and some other costs on top. Billing was meant to start in spring 2026, but switchgear trouble pushed it to August for the first 20 megawatts and to November 9 for the second. By November 10 all 40 megawatts were running. Nscale pays for the GPUs inside with its own loan of up to $1.2 billion, whose papers black out the names of the landlord and of the customer using the chips. WhiteFiber has signed a $300 million loan on the building that pays out only once Nscale accepts the capacity.

Sources 29 documents — 15 SEC filings · 5 transcripts · 4 company releases · 4 other documents · 1 research note

Research trail Found 119 documents and read 106 of them while checking this deal and related ones.

  1. SEC · SEC filingsec.gov
    States 7 figures: $865M contract value · 20 MW billing start · 40 MW all operational · $1.1M Q3 revenue · lease receipts · $45M site · $409.3M development costs
  2. SEC · SEC filingsec.gov
    States 4 figures: $865M first announcement · 3% escalator · structure · priority notice
  3. SEC · SEC filingsec.gov
    States 3 figures: 40 MW agreement · license · 20 MW original schedule
  4. SEC · SEC filingsec.gov
    States 2 figures: colocation provider · end customer
  5. SEC · SEC filingsec.gov
    States 2 figures: $300M credit agreement · funding condition
  6. SEC · SEC filingsec.gov
    States msa
  7. SEC · SEC filingsec.gov
    States 20 MW LOI
  8. company releasenscale.com
    States up to 40 MW nscale madison
  9. SEC · SEC filingsec.gov
    States up to $1.2B nscale GPU facility
  10. SEC · SEC filingsec.gov
    States 99 MW duke capacity
  11. SEC · SEC filingsec.gov
    States up to $100M bridge
  12. Stock Analysis · transcriptstockanalysis.com
    States nrc funding
  13. PR Newswire · company releaseprnewswire.com
    States 54 MW power delivered
  14. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  15. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  16. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  17. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  18. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  19. company releaseprnewswire.com
    Cited by the record; no single figure is quoted from it.
  20. company releaseprnewswire.com
    Cited by the record; no single figure is quoted from it.
  21. transcriptNov 10, 2026fool.com
    Cited by the record; no single figure is quoted from it.
  22. transcriptstockanalysis.com
    Cited by the record; no single figure is quoted from it.
  23. transcriptstockanalysis.com
    Cited by the record; no single figure is quoted from it.
  24. transcriptbuzzsprout.com
    Cited by the record; no single figure is quoted from it.
  25. other documentchoate.com
    Cited by the record; no single figure is quoted from it.
  26. other documentaib.us
    Cited by the record; no single figure is quoted from it.
  27. other documentsavrn.com
    Cited by the record; no single figure is quoted from it.
  28. research noteccir.io
    Cited by the record; no single figure is quoted from it.
  29. other documentwhitefiber.com
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: WhiteFiber 8-K Item 1.01 + ex-99.1 (2025-12-18) and its EDGAR filing record, FY2025 10-K + Ex. 10.29 MSA, Q3 2026 10-Q (2026-11-10), 8-Ks of May and Nov 2026 (Item 1.01), Q1–Q3 2026 results releases, Aug 2025 and Jan 2026 decks; Duke Energy letter agreement (S-1 Ex. 10.22); Bit Digital 8-K and sale agreement (2025); Nscale S-1/A (2026-11-12), S-1 Ex. 10.24 and release (2026-08-31); WhiteFiber Q3 2025 and Q3 2026 call transcripts, an investor-conference transcript and a CEO interview (Dec 2025); Choate (deal counsel); AIB Data Centers deck (Oct 2026); SAVRN; CCIR; WhiteFiber's NC-1 blog (read 2026-11) · as of Nov 2026

The evidence 26 sourced figures · 2 disputes

The record's headline WhiteFiber–Nscale, NC-1 (Madison NC): a ten-year colocation agreement for 40 of IT load, ~$865M by the landlord's filed count — yearly escalators and one-time installation charges included, power passed through; signed Nov 2025, all 40 MW running by Nov 2026; Nscale's own filings never name WhiteFiber

Size
40 MW of IT load · ~$865M over the 10-yr initial term (filed; escalators and one-time installation charges included, power passed through) · Nscale's own up-to-$1.2B North Carolina GPU loan · WhiteFiber's $300M NC-1 credit agreement, unfunded at Nov 10 2026
When
Aug 2025 NC-1's first phase under a letter of intent with an unnamed AI cloud company (20 MW, ~7 years) → Nov 22 2025 MSA signed → Dec 18 2025 announced (8-K + joint release) → Apr 30 / May 30 2026 the billing dates set at signing → Jun 2026 the 10-K's expected start → May 20 2026 Bit Digital's $100M bridge → Aug 15 2026 billing starts on the first 20 MW → Aug 27 Nscale's $1.2B North Carolina GPU facility (announced Aug 31) → Sep 23 first hall placed in service after a switchgear fault → Nov 9 WhiteFiber's $300M NC-1 credit agreement; full billing on the second hall → Nov 10 Q3 10-Q: all 40 MW operational → ten years from the start (an end date not on file)
Status
signed Nov 22 2025 · billing on the first 20 MW from Aug 15 2026, interrupted by a switchgear fault, the hall placed in service Sep 23 · billing on the second 20 MW from Nov 9, by WhiteFiber's CEO · all 40 MW operational at the Q3 10-Q (Nov 10 2026) · WhiteFiber's $300M NC-1 credit agreement signed Nov 9 2026, nothing funded, its first draw conditioned on Nscale's acceptance of the 40 MW · Nscale's $1.2B North Carolina GPU facility signed Aug 27 2026 · Nscale's filings never name WhiteFiber
Structure
a master services agreement (Ex. 10.29 to WhiteFiber's FY2025 10-K) and an initial Service Order that is not filed. Enovum NC-1 Bidco, LLC, WhiteFiber's wholly owned subsidiary 'doing business as Enovum', grants Nscale Services US Inc. and Nscale Global Holdings Limited, jointly and severally liable, a non-exclusive license to the facility with exclusive use of the halls it designates. The Service Order covers 40 MW of IT load in two 20 MW phases for an initial ten years at ~$865M, escalators and one-time installation charges included; the joint release calls it a 'modified-gross colocation lease' with 3% yearly escalators on the recurring fees and milestone-based installation payments, the customer also paying electricity, PUE overhead and its share of property taxes. WhiteFiber books it as an operating lease (ASC 842). Nscale gets priority notice of new capacity at NC-1. The GPUs inside are Nscale's, financed by an up-to-$1.2B delayed-draw loan to Nscale NC Borrower SPV, LLC, which takes the space from its Nscale affiliate under a sub-colocation agreement
Programme
WhiteFiber–Nscale
Parties
Nscale the customer: Nscale Services US Inc. and Nscale Global Holdings Limited, jointly and severally liable under the MSA its CEO, Josh Payne, signed; pays the fees, the one-time installation charges and the passed-through power; owns the GPUs inside through Nscale NC Borrower SPV, LLC and that company's $1.2B loan. Its filings never name WhiteFiber · WhiteFiber the landlord and operator: Enovum NC-1 Bidco, LLC, a wholly owned subsidiary, owns NC-1 and provides the space, power and cooling, and is the borrower under the $300M NC-1 credit agreement; its sister company Enovum NC-1 Venture, LLC borrowed from Bit Digital Capital (bridge). Its president, Billy Krassakopoulos, signed the MSA · Lenders & bondholders two separate groups: Morgan Stanley Senior Funding and a consortium of lenders for WhiteFiber's $300M (unfunded at Nov 10 2026); Goldman Sachs and JPMorgan among the arrangers and lenders of Nscale's $1.2B North Carolina GPU facility
Record
disclosed / primary source · as of Nov 2026

Flows 4 as the record states them

  • WhiteFiber → Nscalecapacity40 MW of IT load at NC-1, 805 Island Drive, Madison NC, in two 20 MW halls: a non-exclusive license to the facility with exclusive use of designated halls; the first hall billing from Aug 15 2026 (in service Sep 23), the second from Nov 9; priority notice of new capacity at NC-1
  • Nscale → WhiteFibercolocation-fees~$865M over the ten-year initial term by WhiteFiber's filed count: recurring fees rising 3% a year (release) plus one-time installation charges paid at milestones, the split not disclosed; electricity, PUE overhead and pro rata property taxes passed through on top
  • Lenders & bondholders → WhiteFiberdebt-commitment$300.0M of term-loan commitments (Nov 9 2026: $200.0M initial + $100.0M delayed draw) at Term SOFR + 6.00%, five years from first funding, to Enovum NC-1 Bidco; nothing funded at Nov 10 2026, the first draw conditioned on Nscale's acceptance of the first 40 MW
  • Lenders & bondholders → Nscalegpu-financingup to $1.2B of delayed-draw loan commitments ($370.0M fixed, $830.0M floating at three-month Term SOFR + 2.375%) to Nscale NC Borrower SPV, LLC (Aug 27 2026), for GPU infrastructure in North Carolina, maturing in December 2031

Resolved figures 26 each with the verbatim line from its document

  • agreement40 MW
    40 MW of IT load at NC-1, WhiteFiber's data center in Madison, North Carolina, in two 20 MW phases, under the initial Service Order of a master services agreement that Enovum NC-1 Bidco, LLC (WhiteFiber's wholly owned subsidiary) signed on Nov 22 2025 with Nscale Services US Inc. and Nscale Global Holdings Limited. Item 1.01 is filed, not furnished, and names Nscale. IT load is the power for Nscale's own equipment, not for cooling or the building; the utility's power to the site is counted in gross MW (power-delivered). The Service Order, which carries the prices, is not on file (msa)
    “The initial Service Order provided pursuant to the Services Agreement covers 40 megawatts (“MW”) of information technology load, to be deployed in two 20 MW phases, at the NC-1 Facility and represents an expected $865 million in total contracted revenue over the initial 10-year term, including contractual annual rate escalators and non-recurring installation services.”
    WhiteFiber 8-K, Item 1.01 (filed 2025-12-18) · sec.gov
  • msa
    the contract on file: the master services agreement, filed as Ex. 10.29 to WhiteFiber's FY2025 10-K with details redacted. Its customer is two Nscale companies, jointly and severally liable: Nscale Services US Inc. ('US Customer') and Nscale Global Holdings Limited. It was signed on Nov 22 2025 by Billy Krassakopoulos, Enovum's president, and by Josh Payne, Nscale's chief executive, for both Nscale signatories, though the signature block reads 'NSCALE US HOLDINGS INC.' where the first page names Nscale Services US Inc.; no document explains the difference. As filed, with its blacked-out passages, the MSA shows no price, term or capacity: its fees are 'the amounts stated' in the Service Orders, its term clause is blacked out, and the 8-K puts the MW, the term and the expected revenue in the initial Service Order, which is not filed. WhiteFiber's Q3 2026 10-Q lists among its risks 'our dependence on Nscale as the sole contracted tenant at our NC-1 campus'
    “(together with, and jointly and severally liable with, US Customer, “Customer”)”
    WhiteFiber FY2025 10-K, Ex. 10.29 (Master Services Agreement, dated 2025-11-22) · sec.gov
  • license
    a license plus services, in the contract's form: a non-exclusive license to the facility and exclusive use of the halls and cabinets Enovum designates (MSA §1(a)). The joint release calls the same arrangement a 'modified-gross colocation lease' (structure), and WhiteFiber accounts for it as a lease: its Q3 2026 10-Q books NC-1's revenue as lease income under ASC 842 and keeps its future payments out of the ASC 606 backlog (lease-receipts). A contract form, a press description and an accounting label for one arrangement
    “The Services Agreement provides the customer a non-exclusive license to access the NC-1 Facility and exclusive access to use and occupy designated areas for placing, installing, upgrading, adding, maintaining, repairing and operating the Customer’s equipment.”
    WhiteFiber 8-K, Item 1.01 (filed 2025-12-18) · sec.gov
  • first-announcement$865M
    the day the deal became public, Dec 18 2025: the release headed 'WhiteFiber and Nscale Announce …', on PR Newswire at 16:30 ET and furnished with the 8-K (Item 7.01) that EDGAR accepted the same afternoon. The 8-K's Item 7.01 says the release was issued on 'December 16, 2025'; the release itself, its exhibit heading and EDGAR's filing record all say Dec 18. The release adds what the filed text does not: the 3% escalator (escalator), the structure (structure), Nscale's priority on new capacity (priority-notice), that WhiteFiber had invested 'approximately $150 million of equity into the site', and that 'Nscale is deploying this capacity to power the AI infrastructure of leading, global investment grade technology customers' (end-customer). Its figure excludes 'electricity and certain other costs passed through to the customer'. Choate, Enovum's counsel, puts the agreement at 'more than $800 million in revenue over an initial 10-year term', a floor the ~$865M meets
    “The contract represents approximately $865 million in contracted revenue over the initial 10-year term, including contractual annual rate escalators and required non-recurring installation services, but excluding electricity and certain other costs passed through to the customer.”
    WhiteFiber–Nscale release of Dec 18 2025 (WhiteFiber 8-K ex-99.1, furnished under Item 7.01) · sec.gov
  • loi20 MW
    where it began, unnamed: WhiteFiber's August 2025 investor deck had NC-1's first phase 'Under LOI' with 'a private company providing cloud computing for AI companies' valued at '$3B+': 20 MW of IT load for an expected seven years. On the Q3 2025 call (Nov 2025) its president said 'The deal basically upsized and doubled within the last couple of weeks/months'; the order signed on Nov 22 2025 was 40 MW for ten years. That the LOI's counterparty was Nscale is our reading; the deck names no one. A furnished deck
    “NC - 1 99 Gross MW Capacity: Under LOI (2) Customer: Pending Contract (2) IT Load: 20 MW (2) Expected Average Term: 7 years (2)”
    WhiteFiber investor presentation, Aug 2025 (8-K ex-99.1, furnished) · sec.gov
  • contract-value$865M
    ~$865M over the ten-year initial term: WhiteFiber's figure for the initial Service Order, 'inclusive of contractual annual rate escalators and non-recurring installation services', so it counts the one-time installation charges as well as the monthly fees, and no filing splits the two (per-mw-year). Electricity and certain other operating costs are passed through to Nscale on top. Stated in the filed 8-K ('an expected $865 million', Item 1.01), the FY2025 10-K and each 2026 10-Q, most recently the Q3 10-Q of Nov 10 2026 (this quote). No Nscale document states a value for it, and its filings never name WhiteFiber (colocation-provider). Divided evenly, it is ≈ $2.16M per MW a year, ≈ $86.5M a year for the 40 MW (our arithmetic), installation charges and escalators included
    “The initial Service Order pursuant to the Services Agreement represents approximately $865 million in total contracted revenue over a 10-year term, inclusive of contractual annual rate escalators and non-recurring installation services (“NRCs”).”
    WhiteFiber Q3 2026 10-Q (filed 2026-11-10), Nscale Services Agreement · sec.gov
  • escalator3%
    3% a year on the recurring service fees, in the companies' joint release only: the 8-K and the 10-Qs say 'contractual annual rate escalators' and give no rate. The release does not say whether the 3% compounds or when each step falls
    “Term: 10 years with 3 percent annual rate escalators on recurring service fees”
    WhiteFiber–Nscale release of Dec 18 2025 (8-K ex-99.1, furnished), Key Terms · sec.gov
  • structure
    the release's account of the payments: a 'modified-gross' arrangement, rent plus pass-throughs, in which Nscale pays the rent, the power with its cooling overhead (PUE) and its share of property taxes, and pays the installation charges at milestones. WhiteFiber's CEO, interviewed that week: 'the customer pays rent and also covers power, cooling efficiency costs, and certain site expenses'. No milestone amount is on file
    “Structure: Modified-gross colocation lease with expense passthrough and milestone-based installation payments. In addition to the rent, the customer pays PUE, electricity and pro rata property taxes.”
    WhiteFiber–Nscale release of Dec 18 2025 (8-K ex-99.1, furnished), Key Terms · sec.gov
  • nrc-funding
    Nscale pays toward the build: WhiteFiber's CEO, on the Q3 2026 call, put NC-1's development cost at 'just below $9 million per gross megawatt', 'within our original budget range of $7 million-$9 million', a figure that excludes the land and is net of the charges Nscale funds. So the one-time installation charges inside the ~$865M offset part of the construction; how much is not on file. What WhiteFiber has spent is in development-costs. Stock Analysis's transcript of the call, so tier 2
    “That figure excludes the site acquisition costs and is net of customer-funded non-recurring costs.”
    WhiteFiber Q3 2026 earnings call, Nov 10 2026 (Stock Analysis transcript) · stockanalysis.com
  • priority-notice
    Nscale's first call on more space: priority notice of future capacity at NC-1 before WhiteFiber markets it to others, a notice right with no price or quantity, stated in the release only. WhiteFiber's CEO in the same release: 'We look forward to working closely with Nscale as we plan for the potential expansion of this deployment toward double its initial size by the end of 2027.' On the Q3 2026 call its president said 'we would like for it to be Nscale for the expansion, but we're open to other users'. No expansion order is on file
    “Additional Capacity: Nscale will receive priority notification of future capacity availability at NC-1 before such capacity is marketed to other customers.”
    WhiteFiber–Nscale release of Dec 18 2025 (8-K ex-99.1, furnished), Key Terms · sec.gov
  • original-schedule20 MW
    the schedule at signing: billing from Apr 30 2026 for the first 20 MW and May 30 2026 for the second. It slipped. The FY2025 10-K (Mar 2026) expected billing 'for the 40 MW phase' in June 2026; the Q2 2026 release (Aug 2026) expected 'full contracted run-rate billing across the 40 megawatts of contracted IT load later this month'; billing began on Aug 15 for the first hall and Nov 9 for the second (billing-start, all-operational). WhiteFiber's CEO on the Q3 call: 'Shipping disruptions related to the Middle East conflict delayed our original switchgear', and the replacement equipment then needed commissioning fixes; 'we do not expect late delivery penalties related to these issues'. No filing gives the contract's delay terms
    “Billing for the initial 20 MW is anticipated to commence on April 30, 2026, with the remaining 20 MW anticipated to commence on May 30, 2026.”
    WhiteFiber 8-K, Item 1.01 (filed 2025-12-18) · sec.gov
  • billing-start20 MW
    the first hall: billing from Aug 15 2026, placed into service on Sep 23 2026 — two events, not two readings of one. WhiteFiber's CEO on the Q3 call: 'Billing for the first 20 MW hall began in mid-August. A switchgear software issue later interrupted service and billing. Both resumed on September 23rd.' (Stock Analysis's transcript; the Motley Fool's renders 'Billing' as 'Building'.) NC-1's revenue in the quarter is in q3-revenue
    “On August 15, 2026, the Company commenced billing for the initial 20 MW of contracted capacity at its NC-1 facility, which was subsequently placed into service on September 23, 2026.”
    WhiteFiber Q3 2026 10-Q (filed 2026-11-10), Nscale Services Agreement · sec.gov
  • all-operational40 MW
    all 40 MW operational 'as of date of this report', the Q3 10-Q filed Nov 10 2026. The second hall came later: 'Further switchgear commissioning issues delayed the second hall, including the final 5 MW', and 'Full billing for the second 20 MW hall has begun on November 9th' (WhiteFiber's CEO on the Q3 call; a transcript, tier 2). The Q3 release: WhiteFiber 'has issued the commencement notice for the remaining capacity, and has begun billing for the full contracted capacity'
    “As of date of this report, the remaining 20 MW became operational, bringing all 40 MW of contracted IT capacity at NC-1 into operation.”
    WhiteFiber Q3 2026 10-Q (filed 2026-11-10), Nscale Services Agreement · sec.gov
  • q3-revenue$1.1M
    the first revenue: $1.1M of lease income from NC-1 in the quarter to Sep 30 2026, inside WhiteFiber's $5.6M of colocation revenue, which also counts MTL-3, its Cerebras site in Québec. Only the first hall had started
    “The increase was primarily due to the MTL-3 site becoming fully operational and generating revenues beginning November 2025 and the commencement of revenue at the NC-1 facility, which contributed $1.1 million of lease income.”
    WhiteFiber Q3 2026 10-Q (filed 2026-11-10), MD&A — Revenue from colocation services · sec.gov
  • lease-receipts
    how WhiteFiber's books carry it: in the third quarter it classed the NC-1 and MTL-3 agreements as leases, so their future payments left its ASC 606 backlog ($728,982K of remaining performance obligations at Sep 30 2026) for its lessor table, $421,490K of future receipts from all its operating leases, data-center leases and subleases together, not split by customer. Its CFO on the Q3 call: that figure 'excludes the second 20-megawatt at NC-1 as that lease has not yet commenced as of September 30' (Motley Fool transcript). So no filed figure isolates what Nscale still owes
    “The following table illustrates the future lease payments to be received by the Company under its operating lease arrangements, including data center leases and subleases, as of September 30, 2026:”
    WhiteFiber Q3 2026 10-Q (filed 2026-11-10), Note 6 — Leases, Leases as Lessor · sec.gov
  • nscale-madisonup to 40 MW
    Nscale's own word on the site: 'a 96-acre colocation site with up to 40 MW of IT load capacity' in Madison, in its Aug 31 2026 release on two GPU loans, up to $1.2B of it for Madison, which 'will fund site retrofit capital expenditures, GPU infrastructure and associated networking' (nscale-gpu-facility). It names no landlord
    “Madison, North Carolina: A 96-acre colocation site with up to 40 MW of IT load capacity.”
    Nscale release, Aug 31 2026 (nscale.com) · nscale.com
  • nscale-gpu-facilityup to $1.2B
    how Nscale pays for what it puts inside: up to $1.2B of delayed-draw loans ($370.0M fixed-rate, $830.0M floating at three-month Term SOFR + 2.375%) to Nscale NC Borrower SPV, LLC under a credit agreement of Aug 27 2026, with Nscale Services US Inc. as guarantor and Goldman Sachs and JPMorgan among the arrangers; rated investment grade, and 'used to finance GPU infrastructure capital expenditures in North Carolina'. It 'matures in December 2031' (the credit agreement: the earlier of the Customer's last scheduled payment and Dec 27 2031; end-customer), about five years into a ten-year term whose billing began in Aug 2026 (our arithmetic). The Dell equipment schedules of Nscale's North Carolina and Ward County companies are reported together (~$2.54B of initial-term rent, no North Carolina split) and are not carried. Commitments, not draws: no ribbon
    “The North Carolina GPU Credit Agreement provides for delayed draw term loan commitments in an aggregate principal amount of $1.2 billion, consisting of $370.0 million of fixed-rate delayed draw loan commitments and $830.0 million of floating-rate delayed draw loan commitments (together, the “North Carolina GPU Facility”).”
    Nscale S-1/A (filed 2026-11-12), Description of Certain Indebtedness — North Carolina GPU Facility · sec.gov
  • colocation-provider
    the landlord in Nscale's papers, unnamed: the North Carolina GPU credit agreement (Ex. 10.24 to Nscale's S-1) defines the 'Colocation Provider' as '[***], doing business as [***], in its capacity as data center provider under the Master Services Agreement', an MSA among Nscale Services US Inc. (the loan's guarantor), Nscale Limited and the Colocation Provider, and the data center as one it owns; the lenders' engineering review is titled 'Technical Due Diligence Madison NC Data Center' (Jul 28 2026). The borrower takes its space through a sub-colocation agreement with its Nscale affiliate. That the provider is WhiteFiber's Enovum NC-1 Bidco, 'doing business as Enovum' in WhiteFiber's MSA, is our matching of the town, the form and Nscale Services US Inc.; the parent named differs (Nscale Limited here, Nscale Global Holdings Limited in WhiteFiber's MSA). Nscale's S-1, S-1/A and draft registration statement on file never name WhiteFiber or Enovum
    ““DC” shall mean the data center facility with address [***], which is owned by the Colocation Provider and with respect to which colocation rights and access are provided to the Affiliate Guarantor.”
    Nscale S-1 Ex. 10.24, North Carolina GPU Credit Agreement (dated 2026-08-27), §1.01 Definitions · sec.gov
  • end-customer
    whose computing this is, blacked out: the North Carolina GPU loan is repaid from a 'Cloud Services Agreement' between a 'Customer', '[***]', and Nscale US Holdings Inc., and it runs until 'the earlier of (a) the date on which the Customer pays the final scheduled payment under the Customer Contract to the Borrower, and (b) December 27, 2031'. WhiteFiber calls the deployment 'backed by an investment-grade hyperscaler offtake' (Q1 2026 release) and Nscale's customers 'leading, global investment grade technology customers' (first-announcement). No document on file names the end user, and the record does not guess
    ““Customer Contract” shall mean that certain Cloud Services Agreement, effective as of [***], between Customer and Nscale US Holdings Inc., together with that certain Vendor Services Order #1, each as dated [***]”
    Nscale S-1 Ex. 10.24, North Carolina GPU Credit Agreement (dated 2026-08-27), §1.01 Definitions · sec.gov
  • site$45M
    the building: NC-1, 805 Island Drive, Madison NC, 946,586 sq ft of gross building area on ~94.83 acres in the sale agreement (Nscale's release: '96-acre'), bought from Unifi Manufacturing, Inc. on May 20 2025 for $45.0M in cash, cut from the $53.2M first agreed (the amendment, in Bit Digital's 8-K). More is owed to the seller if the site gets 99 MW soon: $8M within two years of the purchase or $5M within three, and $200,000 per MW above 99 MW within four years, up to $5M; none was payable at Sep 30 2026, when WhiteFiber had no electric service agreement for 99 MW
    “The total consideration consisted of $45.0 million in cash, including the initial deposit of $2.2 million.”
    WhiteFiber Q3 2026 10-Q (filed 2026-11-10), Note 4 — Acquisitions; Note 18 — Commitments and Contingencies · sec.gov
  • duke-capacity99 MW
    the power promised: Duke Energy's letter agreement for the site, filed by WhiteFiber, sets 24 MW of permanent service on or about Sep 1 2025, 40 MW on or about Apr 1 2026 and 99 MW within four years of its effective date, May 16 2025, on commercially reasonable efforts; gross MW, the Q3 10-Q says, measured at the utility, not IT load. WhiteFiber's Jan 2026 deck put the April step at 44.0 MW; no document reconciles the two. Beyond 99 MW the site's potential is contested (site-potential)
    “The first phase of permanent service (24 MW) to be delivered on or about September 1, 2025, with the second phase of permanent service (40 MW) to be delivered on or about April 1, 2026, and the final phase of permanent service (99 MW) to be delivered within four (4) years of the effective date of this Letter Agreement.”
    Duke Energy Carolinas letter agreement for 805 Island Drive, Madison NC (WhiteFiber S-1, Ex. 10.22) · sec.gov
  • power-delivered54 MW
    the power in place: Duke had finished the work to deliver 54 gross MW to the site by WhiteFiber's Q1 2026 results release (May 14 2026), the utility side of the 40 MW of IT load. The same sentence's 'backed by an investment-grade hyperscaler offtake' is WhiteFiber's description of Nscale's customer, unnamed (end-customer). PR Newswire's copy of the company's release, so tier 2
    “Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the site, supporting the Company's planned initial 40 MW IT load deployment under its colocation agreement with Nscale Global Holdings, which is backed by an investment-grade hyperscaler offtake.”
    WhiteFiber Q1 2026 results release (2026-05-14, PR Newswire) · prnewswire.com
  • development-costs$409.3M
    what WhiteFiber has spent on the build: $409.3M of development costs for NC-1's construction in the nine months to Sep 30 2026 alone; by the Dec 18 2025 release it had put 'approximately $150 million of equity into the site'. No total project cost is on file; the CEO's 'just below $9 million per gross megawatt' is net of the charges Nscale funds (nrc-funding)
    “Compared with December 31, 2025, the balance as of September 30, 2026 increased by $428.2 million, mainly due to $409.3 million of development costs for the construction of NC-1 facility”
    WhiteFiber Q3 2026 10-Q (filed 2026-11-10), MD&A — Property, plant and equipment · sec.gov
  • bridgeup to $100M
    the money that carried the build: a delayed-draw loan of up to $100M (to $150M by mutual agreement) from Bit Digital Capital, Inc., a subsidiary of Bit Digital, which owns about 59.7% of WhiteFiber (Q3 10-Q), to Enovum NC-1 Venture, LLC, signed May 20 2026 and guaranteed by White Fiber Operating Partnership LP, for uses that 'may include' finishing NC-1's first phase. 9.5% a year, stepping to 8% once the 40 MW first phase is substantially complete and at least 80% leased at market rates; each advance funded at a 3% discount and repaid at no less than 1.1 times its principal. A further $70.0M was advanced on Oct 27 2026, after a Sep 30 carrying value of $29.4M (Q3 10-Q). A parent lending to its subsidiary, not money from Nscale
    “The Term Loan provides for loans in an aggregate principal amount of up to $100 million, which may be increased to $150 million (the “Facility Size”) upon mutual agreement of the parties.”
    WhiteFiber 8-K, Item 1.01 (May 2026) · sec.gov
  • credit-agreement$300M
    WhiteFiber's long-term loan on the building: $300.0M of term-loan commitments ($200.0M initial + $100.0M delayed draw) signed Nov 9 2026 by Enovum NC-1 Midco and Enovum NC-1 Bidco, Nscale's landlord and the borrower, with Morgan Stanley Senior Funding as agent and lead arranger and a consortium of lenders. Term SOFR (2.00% floor) + 6.00%, or base rate (3.00% floor) + 5.00%; five years from first funding, amortizing 2.50% a quarter; secured on the borrower's assets with a mortgage on NC-1, a completion guarantee from WhiteFiber's operating partnership, and no guarantee from WhiteFiber, Inc. The money may pay for Phase 1 construction, reserves and costs, and 'permitted distributions to equity holders'. No loan was funded as of the 8-K or the 10-Q; the CFO expected first funding 'later in November or in December' (Q3 call). Drawn as no ribbon until it funds
    “The Credit Agreement provides for $300.0 million of term loan commitments, consisting of a $200.0 million initial term loan facility and a $100.0 million delayed-draw term loan facility.”
    WhiteFiber 8-K, Item 1.01 (Nov 2026; event of 2026-11-09) · sec.gov
  • funding-condition
    where the two sides' money meets: WhiteFiber's first draw waits on Nscale, on 'readiness and customer acceptance of the first 40 megawatts', and its delayed draw on 'final completion of the first 40-megawatt phase'. First funding is due within 30 days of closing, extendable twice by 30 days. The Q3 10-Q: 'funding remains subject to project-readiness, customer-acceptance and other conditions'
    “Initial funding is subject to satisfaction or waiver of conditions relating to readiness and customer acceptance of the first 40 megawatts of capacity at the Borrower’s NC-1 data center and other customary conditions.”
    WhiteFiber 8-K, Item 1.01 (Nov 2026; event of 2026-11-09) · sec.gov

Contested figures 4 not reconciled — every position side by side, with its source and tier

per-mw-year2 positions, side by side
$2.16M per MW a year: AIB Data Centers' October 2026 investor deck lists 'WhiteFiber / Nscale Dec 2025 40 MW $865M / 10 yr $2.16M' among disclosed anchor leases, and SAVRN's lease table puts it at $180.20 per kW-month. Both are the total ÷ 40 MW ÷ ten years ($2.1625M; $180.21 a kW-month, our arithmetic), so both count the one-time installation charges and the escalators as rent AIB Data Centers investor presentation (Oct 2026); SAVRN wholesale lease table (read 2026-11)
over $2M per MW of recurring revenue: WhiteFiber's CEO in an interview the week of the announcement, 'it averages out to over $2 million per megawatt on annualized recurring revenue per megawatt'. No filing splits the ~$865M between recurring fees and one-time charges; if both readings hold, the one-time charges come to at most ≈ $65M ($865M − $2.0M × 40 MW × 10 years, our arithmetic). No document states a rent per MW or per kW WhiteFiber CEO interview, Dec 2025 (podcast transcript)
site-potential2 positions, side by side
up to 200 MW (gross): 'Management believes based upon its review of the site and a Duke Energy preliminary transmission study, that NC-1 may receive and support up to 200 MW (gross) of total electrical supply over an extended period of time, subject to infrastructure upgrades' (Q3 2026 10-Q; the Dec 18 2025 release says the same). The study itself is not on file WhiteFiber Q3 2026 10-Q (filed 2026-11-10), Business; release of Dec 18 2025
approximately 300 gross MW: 'the potential to scale toward approximately 300 gross megawatts over time' (WhiteFiber's CEO in its Q2 2026 results release, Aug 2026). Neither figure is contracted: Duke's letter agreement reaches 99 MW (duke-capacity), and on the Q3 call management put NC-1's next power at the end of 2027. Nscale holds priority notice of any new capacity (priority-notice) WhiteFiber Q2 2026 results release (PR Newswire, corrected), Aug 2026

Scope note what this record leaves to other records

NOT this record (carried elsewhere or left out): Nscale's company-wide figures in its S-1/A of Nov 12 2026 — $105.8B of active and contracted TCV ($6.4B active), the ~20% weighted-average prepayment, the Series C ($1.64B in the S-1 and S-1/A, ~$2.0B in an earlier draft, for the same shares), the UK GPU facility (~$1.4B) and the reported IPO valuations → not carried here; the nscale entity carries the S-1's Aug 31 figures. Microsoft's statements of work (up to ~$43.8B, one $3.22B Loughton SOW since terminated) → nscale-msft; the Anthropic agreements (up to ~$44.6B) → anth-nscale-monarch; the $3.36B pre-IPO convertible with Nvidia's $1.0B → nv-nscale. WhiteFiber's other business → the whitefiber entity or not carried: MTL-3's Cerebras contract, its GPU cloud, its 2031 and 2032 convertible notes and the $120.0M zero-strike call, its IPO proceeds, NC-2/NC-3 in Yadkinville ($60.0M in cash per the Q3 10-Q, closed Oct 28 2026, no customer on file; one write-up of the Q3 call has $50 million), the ~1,500 MW pipeline and its year-end capacity targets. Site details not carried: the $3M surety bond to Duke and the electric service agreement's minimum bill; the acreage of one county parcel (94.53 GIS acres) against the sale agreement's ~94.83; the 'over $1 billion' NC-1 investment of the economic-development announcements, which WhiteFiber's blog says 'is based on the anticipated receipt of up to 200MW of power over an extended period of time'; development cost guidance per gross MW ('~$8M to $10M' in the Sep 2026 deck; the Q3 call's figure is in nrc-funding). Not adopted: '$865M' cited without its qualifier that it includes the escalators and the installation charges; 'We have the first 50 MW online for NC1' at an investor conference (the speaker: 'I am rounding some numbers up'; filed: 40 MW of IT load, 54 gross MW); CCIR's 'Madison County' for the GPU loan (Madison is a town in Rockingham County); sell-side models, among them B. Riley's NC-1 value of $1.56 billion on $78 million of estimated annual NOI (both banks underwrote WhiteFiber's IPO).