Why it matters
Cerebras is securing data-center capacity of its own, with most of it conditional on financing. Digi Power X calls the ~$1.1B contracted, but the contract lets 25 of the 40 and five-eighths of the monthly fee fall away unless Digi Power X raises financing that Cerebras approves.
Tap a figure for the line in its source.
Digi Power X gives Cerebras
- of IT load at Columbiana, Alabama, under an exclusive license to the whole data center (not a lease): 15 targeted for Dec 15 2026, the other 25 MW by the end of Q1 2027, only if Digi Power X raises financing that Cerebras approves
- first refusal on any new data-center capacity Digi Power X offers on the same land or at a second site, whose name is redacted
Cerebras gives Digi Power X
- a fixed fee on the contracted load whether Cerebras uses it or not, power included, rising 3% a year: about $2.9M a month for the first 15 and $4.9M for the next 25 MW
- over the ten-year initial term by Digi Power X's filed count, both phases included; ~$2.5B with one seven-year extension, though no document shows how the extra ~$1.4B is reached
- one-time construction charges per kW for each phase, paid into escrow or straight to the builders, plus part of the fee in advance; every amount is redacted, and so is who posts the contract's letter of credit
Lenders & bondholders gives Digi Power X
- a commitment letter, not yet a loan, for project debt to finish the Alabama campus, syndicated by Goldman Sachs and expected to close within 90 days of Oct 13 2026; Digi Power X would guarantee it, unsecured, until completion
What happened
In May 2026, Cerebras signed a ten-year agreement for exclusive use of a 40-megawatt data center in Columbiana, Alabama. Cerebras makes -scale AI chips, which use an entire silicon wafer. Digi Power X is a bitcoin miner shifting into data-center operations. It is building the center on land it owns. Cerebras pays $195 per kilowatt a month whether it uses the capacity or leaves it idle. The fee includes power and rises 3% a year. Digi Power X puts the ten years at about $1.1 billion. It estimates about $2.5 billion if Cerebras extends once for seven years. No document shows how Digi Power X arrived at that estimate. Cerebras contributes to construction costs and pays part of the fee in advance. The filed contract blacks out those amounts. Only the first 15 megawatts are firm. Cerebras gets the other 25 only if Digi Power X secures financing on terms Cerebras approves in writing. In October 2026, Digi Power X had a $200 million commitment letter. The letter itself did not constitute a loan. No document in the record shows Cerebras's approval. All the figures come from Digi Power X. Cerebras's chief executive signed the contract, but Cerebras's own filings never name Digi Power X.
Sources 24 documents — 19 SEC filings · 2 other documents · 2 government statements · 1 press report
Research trail Found 37 documents and read 36 of them while checking this deal and related ones.
- States 8 figures: 40 MW agreement · 15 MW phases · 25 MW phase 2 condition · term · extension options · $1.1B contract value · $2.5B potential value · construction payments
- States 5 figures: license not lease · phase 2 approval · rofr · take or pay · phase 1 nrc
- States 4 figures: $195 colocation fee · power ready · status jun 30 · financing sought
- States 2 figures: $200M debt commitment · 40 MW schedule oct
- States 40 MW first announcement
- States $80–100M guidance 2027
- States site
- States backup engines
- States cerebras filings silent
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: Digi Power X 8-K Item 1.01 + Ex. 10.1 MSA + ex-99.1 (2026-05-08), Q1 and Q2 2026 10-Qs, FY2025 10-K, S-3 (2026-07-17) and S-3/A (2026-09-11); releases of May 15, Jul 7, Aug 14 (8-K ex-99.1) and Oct 13 2026 (own PDF); ADEM engineering analysis + public notice (Oct 2026); Cerebras 424B4, Q1, Q2 and Q3 2026 10-Qs and Q2 release; AIB Data Centers decks (Sep and Oct 2026); DCD (Oct 14 2026, Wayback); Bham Now (Jun 29 2026) (read 2026-11) · as of Nov 2026
The evidence 24 sourced figures · 6 disputes
The record's headline Cerebras–Digi Power X, Columbiana AL: a ten-year exclusive colocation license for 40 of IT load at $195/kW-month — ~$1.1B by the operator's filed count, but 25 MW only if Digi Power X raises financing Cerebras approves; Cerebras's own filings never name it
- Size
- 40 MW IT (25 MW conditional) · ~$1.1B over the 10-yr initial term (filed; ~$2.5B with one 7-yr extension) · $195/kW-month, +3%/yr
- When
- May 4 2026 signed by both companies → May 5 announced by Digi Power X, naming Cerebras → May 8 8-K + redacted MSA filed; air-permit application at ADEM → Jun 22 county building permit (Bham Now) → Jun 30 'under construction and not ready for use' (10-Q) → Oct 13 $200M commitment letter, schedule 'on target' → Oct 27 ADEM's engineering analysis of the proposed permits → Dec 15 2026 Phase 1 target (15 MW) → end of Q1 2027 Phase 2 target (25 MW, conditional) → ten years from the later phase's start, + extensions of 1, 3, 5 or 7 years at Cerebras's option
- Status
- signed May 4 2026 · under construction and not ready for use at Jun 30 2026 (10-Q) · Phase 1 'on target' for December 2026 by Digi Power X's Oct 13 account · Phase 2 conditional: no document in the record shows its financing in place or Cerebras's approval, and the $200M was a commitment letter at Oct 13 · no fee yet (each phase's fee starts at its ready-for-service date) and none of Cerebras's one-time charges shown paid · Cerebras's filings never name Digi Power X
- Structure
- a colocation and managed-services agreement: an exclusive license to the whole Facility, 'not a lease' (MSA §2.3), for 40 MW of IT load in two phases. Phase 1 is 15 MW, ready for service targeted Dec 15 2026; Phase 2 is 25 MW more by the end of Q1 2027, owed only if Digi Power X secures financing on terms reasonably acceptable to both parties within a 'Financing Period' (length redacted) and Cerebras approves it in writing — silence or disapproval leaves Cerebras with Phase 1 only (§2.2(b)). The fee is $195/kW-month (Q2 10-Q; redacted in the exhibit): all-in with delivered power up to the contracted load, take-or-pay, compounding 3.0% a year from each phase's first anniversary; new government or utility power charges after May 4 2026 are billed on top (§6.8). Cerebras also pays one-time per-kW charges for each phase's build, into escrow or directly to suppliers, and a prepaid part of the fee (§6.2–6.4; all amounts redacted); the prepaid-fee section also has a letter of credit (§6.2(f)), redacted down to who posts it. Term: ten years from the later phase's ready-for-service date, extendable at Cerebras's option by 1, 3, 5 or 7 years; a right of first refusal on new capacity on the land and at a second, redacted site (§3.4); daily delay credits, and Cerebras may end a late phase without penalty past its outside delivery date (§4.3). Digi Power X builds 'at its sole cost and expense' on land it owns in fee simple; Cerebras installs its own racks, servers and liquid cooling
- Programme
- Cerebras–Digi Power X
- Parties
- Cerebras the customer and licensee — 'an exclusive license to access the data center' (8-K) for its own racks, servers and liquid-cooling gear; pays the monthly fee, one-time construction charges and a prepaid part of the fee (MSA §6.2–6.4, amounts redacted; who posts the §6.2(f) letter of credit is redacted too); approves, or does not, the financing for Phase 2 (§2.2(b)). Its CEO, Andrew Feldman, signed the MSA; its filings never name Digi Power X · Digi Power X the operator — owns the land in fee simple, builds the Facility 'at its sole cost and expense' and runs its power, cooling and building services; must use commercially reasonable efforts to finance Phase 2. Its president, Alec Amar, signed the MSA · Lenders & bondholders an unnamed 'major lending institution', Goldman Sachs syndicating: a US$200M commitment letter (Oct 13 2026), not closed, for debt at a project-level SPV with an unsecured Digi Power X guarantee through completion
- Record
- disclosed / primary source · as of Nov 2026
Flows 4 as the record states them
- Cerebras → Digi Power Xcolocation-fees$195.00/kW-month on the contracted load, fixed and take-or-pay, all-in with delivered power, rising 3.0% a year (Q2 10-Q): ≈ $2.925M a month for Phase 1, ≈ $4.875M for Phase 2. ~$1.1B over the ten-year initial term by Digi Power X's filed count, both phases included; Phase 2's share only if Cerebras approves its financing (MSA §2.2(b)). New government or utility power charges after May 4 2026 billed on top (§6.8)
- Cerebras → Digi Power Xconstruction-paymentsone-time Non-Recurring Charges per kW for each phase's build, into escrow or paid straight to Digi Power X's suppliers and capped at each phase's total, plus a prepaid part of the fee (MSA §6.2–6.4): every amount redacted, and the Q2 10-Q names no payment from Cerebras. The same section's letter of credit is redacted down to who posts it
- Digi Power X → Cerebrascapacity40 MW of IT load at Columbiana, Alabama, under an exclusive license to the whole Facility (not a lease): Phase 1 15 MW, ready for service targeted Dec 15 2026; Phase 2 25 MW more by the end of Q1 2027, conditional; and a right of first refusal on new capacity on the land and at a second, redacted site (§3.4)
- Lenders & bondholders → Digi Power Xdebt-commitmenta US$200M commitment letter (Oct 13 2026) for debt at a project-level SPV 'to support completion of the Alabama project', expected to close within 90 days subject to documentation, conditions and the lender's diligence. No money has moved, and whether it is the Phase 2 financing Cerebras must approve is not stated
Resolved figures 24 each with the verbatim line from its document
- agreement40 MW~40 MW of IT load for AI computing at Digi Power X's Columbiana, Alabama campus, under a Data Center Colocation and Master Services Agreement both companies signed on May 4 2026: Digi Power X's president Alec Amar and Cerebras's CEO Andrew Feldman (the redacted MSA, filed as the 8-K's Ex. 10.1). 'Total Contracted Power 40 MW IT Load', in the MSA's summary of terms; IT Load is the power for Cerebras's own equipment, not cooling or the building. Cerebras 'will hold an exclusive license to access the data center for the duration of the Agreement' (8-K) — the entire Facility (MSA recitals). Item 1.01 is filed, not furnished, and names Cerebras; Cerebras's own filings never name Digi Power X (cerebras-filings-silent)
“On May 4, Digi Power X Inc. (the “Company”) entered into a Data Center Colocation and Master Services Agreement (the “Agreement”) with Cerebras Systems Inc. (“Cerebras”) to deploy at total of approximately 40 megawatts (“MW”) for AI computing at the Company’s AI data center campus in Columbiana, Alabama (the “Facility”).”
Digi Power X 8-K, Item 1.01 (filed 2026-05-08) · sec.gov - first-announcement40 MWthe day the deal became public: Digi Power X's release of May 5 2026, issued 'through an approved Canadian newswire service' and filed with the SEC on May 8 inside a Canadian material change report (8-K ex-99.1, furnished under Item 7.01). Its headline names only a 'Leading AI Compute Company'; its first sentence names Cerebras. It adds what the filed text does not: 'up to $2.5 billion inclusive of renewal terms', an 'Upside: Customer expansion option for an additional $1.4 billion' (upside-mechanism), and 'Phase 1 construction is being self-funded by the Company' (phase-1-funding). Ten days later Digi Power X's Q1 results release called the customer only 'a leading AI infrastructure company'
“MIAMI, FL – May 5, 2026 – Digi Power X Inc. (Nasdaq: DGXX / Cboe Canada: DGX) (the “Company” or “Digi Power X”), an AI data center infrastructure operator, today announced the execution of a Master Services Agreement (the “Agreement”) with Cerebras Systems (the “Customer”) for the colocation of a purpose-built, 40 megawatt (“MW”) AI data center campus located in Columbiana, Alabama (the “Facility”).”
Digi Power X release of May 5 2026, in its material change report (8-K ex-99.1, furnished under Item 7.01, 2026-05-08) · sec.gov - license-not-leasea license plus managed services, 'not a lease': Digi Power X keeps 'ownership, possession, and control of the Land and Facility at all times' (§2.1) and builds and runs the power and cooling; Cerebras brings its own racks, servers, networking and liquid-cooling equipment (§5.2). The same license form as cw-corz-colocation's. Whether Cerebras books it as a lease, and so among the data-center leases its Q2 and Q3 10-Qs total, is not stated (cerebras-filings-silent)
“The parties expressly acknowledge and agree that this Agreement constitutes a license for the Colocation Space within the Facility and a services agreement for the provision of managed infrastructure services to the Colocation Space for the benefit of Customer, and not a lease or any other transfer of an interest in real property.”
Digi Power X 8-K Ex. 10.1, the MSA (filed 2026-05-08), §2.3 Nature of Agreement · sec.gov - phases15 MWtwo phases: Phase 1, 15 MW, ready for service targeted for Dec 15 2026; Phase 2, 25 MW more (40 MW in all), targeted by the end of Q1 2027 — targets as filed, not dates achieved; the MSA's Exhibit A, which sets the delivery dates, is omitted from the filing. This record follows the filed schedule; other figures that have been cited include the pre-deal 2025 plan (22 + 33 MW, in the note) and the site's power readings (site-power), which are different quantities. The later releases keep 'December 2026' and 'March 2027' (schedule-oct); the roadmap line in the 10-K and both 10-Qs puts 40 MW of critical load at Q4 2026 (contested full-load-date)
“The Agreement requires the Company to construct, equip, and commission two phases of the colocation space at the Facility, with Phase 1 (15 MW) ready-for-service date targeted at December 15, 2026 and with full deployment in Phase 2 (40 MW) targeted by the end of the first fiscal quarter of 2027.”
Digi Power X 8-K, Item 1.01 (filed 2026-05-08) · sec.gov - phase-2-condition25 MWthe 8-K's condition on Phase 2: Digi Power X must secure 'adequate financing' for it. Copied into both 10-Qs; the Q2 10-Q's Note 20 calls it 'a conditional Phase 2 (25 MW)'. The MSA it summarizes adds a second key, Cerebras's written approval of that financing (phase-2-approval)
“The additional 25 MW of load capacity in Phase 2 is conditioned on the Company securing adequate financing for Phase 2 operations.”
Digi Power X 8-K, Item 1.01 (filed 2026-05-08) · sec.gov - phase-2-approvalthe contract is stricter than the 8-K's summary of it. Within a 'Financing Period' (length redacted) from May 4 2026, Digi Power X must use commercially reasonable efforts to raise Phase 2's financing, debt or equity, 'on terms and conditions reasonably acceptable to both Operator and Customer'; Cerebras then has a redacted number of days to approve it in writing (a 'Phase 2 Approval Notice') or to disapprove. Only an approval obliges Digi Power X to deliver Phase 2, and Cerebras to pay for it: the Phase 2 fee is 'Subject to Section 2.2(b)' (§6.1(b)) and its one-time charge 'Expressly conditioned on Section 2.2(b)' (§6.4(a)). Silence counts as no. No document in the record shows the financing in place or a notice either way; at Oct 13 2026 the $200M was a commitment letter (debt-commitment)
“Should Customer deliver the Phase 2 Disapproval Notice (or fail to deliver any notice to Operator), Operator shall have no obligation to deliver Phase 2 and Customer shall only have rights and obligations with respect to Phase 1.”
Digi Power X 8-K Ex. 10.1, the MSA (filed 2026-05-08), §2.2(b) Conditional Phase 2 Delivery · sec.gov - term10 yearsten years from the later of the two Phase Commencement Dates, a phase's being 'the date of such notice', its ready-for-service notice (MSA §2.2(c)), so Phase 1's fees, which start first, run a little over ten years (our reading). The MSA's §3.1(a) says the same, the agreement itself running from signing. How the term runs if Phase 2 never commences, leaving no 'later' date, is not stated
“The Agreement has an initial term of ten (10) years (the “Initial Term”) from the later of the two phase commencement dates (as described below).”
Digi Power X 8-K, Item 1.01 (filed 2026-05-08) · sec.gov - extension-options7Cerebras's options to extend: one or more periods of 1, 3, 5 or 7 years, on the same terms unless the parties agree otherwise (MSA §3.1(b)); its notice period is redacted. The ~$2.5B case assumes one seven-year extension (potential-value)
“Additionally, the Agreement grants Cerebras the right to extend the Initial Term for one or more additional periods of one (1), three (3), five (5), or seven (7) years (each, an “Extension”).”
Digi Power X 8-K, Item 1.01 (filed 2026-05-08) · sec.gov - rofra right of first refusal for the whole term: before offering any third party new data-center capacity on the Columbiana land or at a second site named in the contract (redacted), Digi Power X must offer it to Cerebras, which has a redacted number of business days to take it; if Cerebras does not answer, its right to that capacity lapses. A capacity right, separate from the extension options, and the clause the May 5 release's 'expansion option' (the Aug 14 release's 'option to expand') may refer to (upside-mechanism); it sets no price
“During the Term, before Operator offers to any third party any new data center capacity located or to be located (a) on the Land (i.e., [***]), and (b) at the site located at [***], that Operator or its Affiliates develops, owns, leases, or controls, Operator shall first notify Customer in writing”
Digi Power X 8-K Ex. 10.1, the MSA (filed 2026-05-08), §3.4 Future Capacity Right of First Refusal · sec.gov - contract-value$1.1B~$1.1B over the ten-year initial term: Digi Power X's figure, in the filed Item 1.01 of its May 8 8-K and repeated in its Q1 and Q2 10-Qs (with 'the Corporation' for 'the Company'), 'subject to the Company meeting its obligations under the agreement'. It counts both phases, so it includes the 25 MW that may never be delivered (phase-2-approval). The disclosed fee reproduces it: 40,000 kW × $195 × 12 = $93.6M a year, and ten years at 3% compounding come to ≈ $1.07B (our arithmetic, both phases from one day, leaving out Phase 1's earlier start and the redacted one-time charges). Phase 1 alone, on the same arithmetic, is ≈ $0.40B over ten years. No Cerebras document states a value
“Pursuant to the Agreement, the total contract value to the Company is approximately $1.1 billion in the initial term of the contract, with a total potential contract value to the Company of approximately $2.5 billion, assuming one seven (7)-year Extension, in each case subject to the Company meeting its obligations under the agreement.”
Digi Power X 8-K, Item 1.01 (filed 2026-05-08) · sec.gov - potential-value$2.5B~$2.5B of 'total potential contract value', 'assuming one seven (7)-year Extension': INCLUSIVE of the $1.1B (the May 5 release: 'up to $2.5 billion inclusive of renewal terms'), so ~$1.4B of upside. Option-contingent; not drawn. What the upside is made of is contested (upside-mechanism): on the disclosed fee, seven more years of 40 MW, still rising 3% a year, come to ≈ $0.96B, for ≈ $2.0B in all (our arithmetic), not $2.5B, and no document shows the calculation
“Pursuant to the Agreement, the total contract value to the Company is approximately $1.1 billion in the initial term of the contract, with a total potential contract value to the Company of approximately $2.5 billion, assuming one seven (7)-year Extension, in each case subject to the Company meeting its obligations under the agreement.”
Digi Power X 8-K, Item 1.01 (filed 2026-05-08) · sec.gov - colocation-fee$195$195.00 per kW per month, fixed and take-or-pay, rising 3.0% a year: ≈ $2.925M a month for Phase 1's 15 MW and ≈ $4.875M for Phase 2's 25 MW, so $7.8M a month and ≈ $93.6M a year for all 40 MW at the starting rate (our arithmetic). Only the Q2 10-Q (filed Aug 14 2026, Note 20 — Commitment) states the rate; the MSA exhibit redacts it and the escalator ('$[***] per kW per month', '[***]% per annum, compounding'), which starts on each phase's own first anniversary. The rate is all-in: it 'includes the cost of delivered electrical power up to the contracted IT Load' (take-or-pay)
“In exchange, the Corporation will receive a fixed, take-or-pay colocation fee of $195.00 per kW per month (approximately $2,925,000 and $4,875,000 per month for Phase 1 and Phase 2, respectively), escalating 3.0% annually over the term.”
Digi Power X Q2 2026 10-Q (filed 2026-08-14), Note 20 — Commitment · sec.gov - take-or-payCerebras pays for the contracted load whether it draws it or not, an obligation the MSA calls 'unconditional', reduced only for force majeure or service credits. The fee is 'an all-in rate that includes the cost of delivered electrical power up to the contracted IT Load'; taxes and 'Energy Pass-Throughs' (new or increased government or utility charges on the power after May 4 2026) are billed on top, while 'fluctuations in the commodity price of electricity that are within the range of normal market volatility' are not (§6.8). On our reading of §6.1(c) and §6.8, the price of ordinary power stays with Digi Power X
“For the avoidance of doubt, the Colocation Fee is a take-or-pay obligation payable in full based on the contracted IT Load capacity for each Phase, regardless of Customer’s actual power utilization or draw during any month.”
Digi Power X 8-K Ex. 10.1, the MSA (filed 2026-05-08), §6.1(c) All-In Rate · sec.gov - construction-paymentsCerebras pays toward the build as well as the fee: one-time charges for each phase's construction and a fee 'a portion of which is to be prepaid'. The MSA sets the charges per kW (phase-1-nrc), paid at Cerebras's choice into escrow or straight to the invoices of Digi Power X's suppliers, capped at each phase's total; the prepaid-fee section adds a letter of credit (§6.2(f)), its text redacted down to who posts it. Every amount is redacted. The Phase 1 charge falls due once Cerebras approves the general contractor; Phase 2's, once Phase 2 is approved and Cerebras approves its final plans. The charges are non-refundable unless Digi Power X's material breach ends the agreement before Phase 1 commences (§6.5), and unapplied ones come back if Cerebras ends a late phase past its outside delivery date (§4.3). The Q2 10-Q names no payment from Cerebras, and has Digi Power X building 'at its sole cost and expense' (contested phase-1-funding)
“The Agreement provides for certain one-time payments by Cerebras in connection with Phase 1 and Phase 2 construction, as well as a monthly colocation fee to paid by Cerebras for Phase 1 and Phase 2 (a portion of which is to be prepaid), based upon the number of kilowatts delivered.”
Digi Power X 8-K, Item 1.01 (filed 2026-05-08) · sec.gov - phase-1-nrcthe Phase 1 charge in the contract's words: a one-time 'Non-Recurring Charge' at a redacted dollar rate per kW of Phase 1's contracted load, 'as consideration for the design, procurement, and construction' of Phase 1's infrastructure; conditioned only on 'Customer’s approval of the general contractor for the Phase 1 Buildout' (§6.3(d)). Phase 2's (§6.4) has the same form
“As consideration for the design, procurement, and construction of the infrastructure required for Phase 1 (the “Phase 1 Buildout”), Customer shall be responsible for payment of a one-time Non-Recurring Charge (“Phase 1 NRC”) equal to $[***] per kilowatt (kW) of the contracted IT Load for Phase 1”
Digi Power X 8-K Ex. 10.1, the MSA (filed 2026-05-08), §6.3(a) Phase 1 NRC Obligation · sec.gov - guidance-2027$80–100MDigi Power X's forecast for the agreement's first full year: ~$80–100M of revenue in fiscal 2027, 'a full year of Phase 1 operations and a partial year of Phase 2' (Q1 results release, May 15 2026; the Jul 7 update repeats it). The disclosed fee bears it out: 15 MW for all of 2027 is $35.1M and 25 MW from April ≈ $43.9M, ≈ $79M in cash (our arithmetic, before the 3% steps and the one-time charges), and it counts the conditional Phase 2. The Aug 14 release no longer breaks the agreement out: it expects 'approximately $140 million of annualized contracted revenue run-rate during 2027' across its contracts, of which this agreement at the full 40 MW is ≈ $93.6M a year at the starting rate (our arithmetic)
“AI colocation revenue from the Colocation Agreement is expected to contribute approximately $80-$100 million, reflecting a full year of Phase 1 operations and a partial year of Phase 2 following its targeted commissioning (40 MW)”
Digi Power X Q1 2026 results release (8-K ex-99.1, 2026-05-15), 2027 Outlook · sec.gov - sitethe site: ~160,000 sq ft of office and industrial warehouse space at 130 Industrial Parkway, Columbiana, Alabama, bought on Jun 14 2022 and owned outright (the MSA: Digi Power X is 'the fee simple owner'). The MSA has it build there 'a purpose-built, high-density data center capable of delivering up to forty megawatts (40 MW) of IT load power', 'at Operator’s sole cost and expense'. This 10-K's power figures for the site (28 MW at first, up to 55 MW) are among the site-power readings
“The Columbiana facility is located at 130 Industrial Parkway, Columbiana, Alabama. The Corporation acquired the property on June 14, 2022. The site consists of approximately 160,000 square feet of office and industrial warehouse space with initial access to 28 MW of power with a total capacity of up to 55 MW.”
Digi Power X FY2025 10-K (filed 2026-03-31) · sec.gov - power-readypower for Phase 1, in the filed 10-Q: the substation is built, grid interconnection finalized and a power delivery agreement with the utility in place (Alabama Power, by the May 5 release). No document in the record gives that agreement's capacity or terms, and Digi Power X's own figures for the site's power differ (site-power)
“The dedicated on-site substation serving Phase 1 of the Columbiana Facility has been completed, grid interconnection has been finalized, and a power delivery agreement with the local utility is in place.”
Digi Power X Q2 2026 10-Q (filed 2026-08-14), MD&A · sec.gov - status-jun-30the last filed word on the build: under construction and not ready for use at Jun 30 2026, in the same note that gives the rate. No fee was yet due: each phase's fee starts on its ready-for-service date (MSA §6.1)
“As at June 30, 2026, the facility remained under construction and not ready for use.”
Digi Power X Q2 2026 10-Q (filed 2026-08-14), Note 20 — Commitment · sec.gov - financing-soughtDigi Power X's own filed account of the gap: the Columbiana build needs money it did not yet have; the same section expects that 'additional financing will be required' for its data-center plans. Its releases before this had Phase 1 'self-funded' (phase-1-funding); the commitment letter came two months later (debt-commitment)
“Specifically, the build-out of the Corporation’s data center facility in Columbiana, Alabama requires specific funding in connection with the Cerebras Agreement. Accordingly, the Corporation is currently seeking out project-level financing for the Columbiana, Alabama data center facility.”
Digi Power X Q2 2026 10-Q (filed 2026-08-14), MD&A — Liquidity and Capital Resources · sec.gov - debt-commitment$200Ma commitment letter, not a loan: US$200M of debt 'to support the development of its 40 MW AI data center in Columbiana', from an unnamed 'major lending institution', syndicated by Goldman Sachs and 'expected to close within 90 days, subject to definitive documentation and satisfaction of various conditions, including the lender's completion of its diligence efforts'. To be raised at a project-level special purpose vehicle 'with an unsecured Company guarantee through project completion and other limited matters'; proceeds 'to support completion of the Alabama project'. In Digi Power X's release of Oct 13 2026 only (its own PDF; the record holds no 8-K for it). The release does not say whether this is the Phase 2 financing the MSA requires, or whether Cerebras has approved it (phase-2-approval). DCD's headline, 'Digi Power X secures $200m in debt financing', says more than its text, which calls it a commitment
“today announced that it has received a commitment letter from a major lending institution for US$200 million in debt financing to support the development of its 40 MW AI data center in Columbiana, Alabama.”
Digi Power X release, Oct 13 2026 (ACCESS Newswire; the company's own PDF) · thankful-miracle-1ed8bdfdaf.media.strapiapp.com - schedule-oct40 MWthe latest schedule in the record, on Digi Power X's word only: Phase 1 in December 2026, Phase 2 in March 2027 (the Aug 14 release: Phase 1 'to be delivered in December 2026, followed by Phase 2, representing an additional 25 MW, in March 2027, for up to 40 MW of IT load'). No lender, engineer or Cerebras document checks it. The outside traces of the build are a Shelby County building permit of Jun 22 2026, $7,024,000 to Dunn Building Company for 130 Industrial Parkway (Bham Now, from Report Construction's permit list), and ADEM's proposed air permits for its backup engines (backup-engines)
“Construction at the 40 MW Alabama campus remains on target, with Phase 1 expected to be completed in December 2026 and Phase 2 in March 2027.”
Digi Power X release, Oct 13 2026 (ACCESS Newswire; the company's own PDF) · thankful-miracle-1ed8bdfdaf.media.strapiapp.com - backup-engines42the regulator's view of the site: Alabama's environmental agency (ADEM) received Digi Power X's air-permit application for the data center at 130 Industrial Parkway (public notice) on May 8 2026, the day the 8-K was filed — forty-two emergency diesel engines with fuel tanks, each held to 'an operational limit of 90 hours per unit during any consecutive 12-month period' so that the site stays a 'synthetic minor source'. An addendum of Aug 13 completed the application; in late October the permits were still proposed, open for comment for 15 days (the engineering analysis is dated Oct 27 2026). Backup power for the data center, not a source of it
“On May 8, 2026, the Air Division received an initial application from DigiPower X (DPX) for the proposed construction and operation of a new data center that would include a group of forty-two (42) emergency compression ignition internal combustion engines (CI ICE) with associated fuel tanks, to be located in Columbiana, Shelby County.”
ADEM Air Division, engineering analysis for DigiPower X Columbiana, Facility No. 411-0078 (Oct 27 2026) · adem.alabama.gov - cerebras-filings-silentthe customer's side: Cerebras's filings never name Digi Power X, Digihost, Columbiana or Alabama — not its 424B4 (May 14 2026, ten days after the signing), its Q1, Q2 or Q3 10-Q, or its Q2 and Q3 results releases (the Q3 10-Q and release read 2026-11-19). Its Q2 10-Q reports data-center leases signed in the quarter, not yet commenced, 'with lease commencement dates in 2026', at about $1.5B of undiscounted payments over their terms, with no landlord named; its Q1 10-Q, signed on Jun 23 before that quarter ended, had put the same quarter's leases at about $1.6B (subsequent events), and neither filing explains the difference. Its Q3 10-Q, signed Nov 12, reports leases executed and not yet commenced at Sep 30 2026, 'with lease commencement dates in 2026 and 2027', at about $8.5B of undiscounted payments, and a further about $217.8M signed in Q4 — again with no landlord named, and without saying how the $8.5B relates to the Q2's $1.5B. All are Cerebras-wide totals, and whether the Columbiana license is among them is not stated: Phase 1 is due in 2026, but the MSA calls itself 'not a lease'. Cerebras's side of this record is described by Digi Power X, and by the contract Cerebras's CEO signed
“As of September 30, 2026, the Company executed non-cancelable lease agreements for additional data center capacity with lease commencement dates in 2026 and 2027.”
Cerebras Q3 2026 10-Q (signed 2026-11-12), Note 15 — Leases, Leases Not Yet Commenced · sec.gov
Contested figures 13 not reconciled — every position side by side, with its source and tier
Scope note what this record leaves to other records
NOT this record (carried elsewhere or left out): Digi Power X's corporate figures → the digipowerx entity, or not carried: one item from an official document, New York's Jul 14 2026 executive order on hyperscale data centers (which bears on its New York sites); quarter-end cash ($128,121,977 in the Q2 10-Q against '$142.4 million' in the release, which adds the digital currencies; $57,813,811 against '$73 million' at Mar 31); the at-the-market program and its unreconciled third quarter (2,850,000 shares after Jun 30 by the 10-Q, none in Q3 by the Oct 13 release; the CEO's 'last ATM draw was at $7.25 or $7.50 a share'); the US Data Centers stake (51% → ~48% in the 10-Qs, '55%' in the May release and on the Aug 14 call); the $250–300M 2027 target, which measures total revenue in May, an annualized run rate in July and a run rate 'by Q3 2027' in August; the 40–50 MW of other colocation it targets for 2027; its GPU-rental business; its New York, North Carolina and West Virginia plans. The pre-deal Columbiana plan (22 MW + 33 MW = 55 MW for $440M, '$176 million' + '$264 million' in DCD's Feb 2025 story, 'around $175 million' + '$265m' in its May 2025 one, repeated as current by Bham Now on Jun 29 2026) predates the agreement by fifteen months, counts site power rather than IT load and has no primary source on file → not carried; no post-deal budget is disclosed. The site's 2022 price ('from Grede II, LLC for $2.75 million', DCD only) and Columbiana's '12-month sales and use tax abatement' and '$3.5 million' 'community impact payment' (WBRC, Jul 24 2026; no council record on file) → not carried. Cerebras-side context: the OpenAI MRA → cerebras-openai; Cerebras's March 2026 data-center lease in Canada (~$2.2B of minimum payments over ten years, its lessor buying 168,509 Class N shares) is with another company, not Digi Power X → not carried; its Q2-2026 data-center lease total, still disputed (≈ $1.5B in the Q2 10-Q, ≈ $1.6B for the same quarter's leases in the Q1 10-Q's subsequent-events note), is Cerebras-wide and names no landlord → both figures in cerebras-filings-silent as context, not one of this deal's disputes; its '600 MW of data center capacity now under contract' (Q2 release) and '700 megawatts of data center capacity now under contract' (Q3 release, Nov 12 2026), which may or may not include Columbiana → not carried. AIB's other comparables and its own project → not carried. Not adopted: the US$200M financing headline in the 'Related News' sidebar of ACN's copy of the May 5 release, which is the Oct 13 release's, not a May fact; a 'reaffirms $1.1 billion Alabama contract' headline in finviz sidebars, not in the pages' articles; '$2.38' on the call-transcript page, a live share-price widget; DCD's 'secures' headline over a text that says commitment; the AIB deck under two CIK spellings, one document; '63%' of Cerebras's Q1 revenue, which is MBZUAI's, not G42's.