AIB Data Centers–Nebius, CLT1 (Moore SC)

Nebius has signed for 50 of computing capacity in two halls that AIB Data Centers is building on a former bitcoin-hosting site in South Carolina, for 12 years from each hall's start, with Nebius's parent guaranteeing; Nebius's prepayment, paid into an escrow that AIB draws on for the build, comes back if AIB misses its dates, and no contract value is filed.

A deal between AIB Data Centers, Nebius

Why it matters

AI cloud provider Nebius is helping finance the data halls it is leasing from AIB Data Centers, which has yet to raise construction debt. AIB can draw on Nebius's escrow only to build and only against a pledge of the data hall project company and AIB's guarantee. Nebius can end the lease and recover its money if AIB misses its final delivery deadlines or certain initial permits are not obtained in time.

Tap a figure for the line in its source.

AIB Data Centers gives Nebius

  • of critical IT capacity at CLT1 in Moore, South Carolina, in two 25 halls targeted for Q4 2027 and Q1 2028; 12 years from each hall's rent start, with two five-year renewal options for Nebius
  • rent credits if a hall is late; Nebius may end the agreement and get its prepaid money back if AIB misses the outside dates, or if certain initial permits are not obtained within 90 days of the effective date

Nebius gives AIB Data Centers

  • a monthly charge that rises every year; neither company files the rate or a total. Estimates run from about $1.25B (an analyst's) to about $1.32B (AIB's own deck, a figure first worked out before the lease was signed)
  • a fit-out charge and a security deposit, paid into escrow on Oct 20 2026 in amounts no one discloses, released to AIB only for the build and only against conditions, a pledge of the project company and AIB's own guarantee among them
  • a guarantee of its US subsidiary's obligations by Nebius Group N.V., the listed parent

Sep 30, 2026 announced by AIB Data Centers, naming Nebiusupdated Nov 21, 2026signed Sep 25 2026 · announced Sep 30 disclosed by the parties

What happened

In September 2026, AI cloud company Nebius signed a lease with AIB Data Centers for 50 megawatts of computing capacity at CLT1. AIB, a small developer with a stock-market listing, is rebuilding the former bitcoin-hosting site in Moore, South Carolina, as two 25-megawatt data halls. Each hall's 12-year term begins when its rent starts. The target start dates are late 2027 and early 2028. Nebius's parent company guarantees what its US subsidiary owes. AIB puts the construction cost at about $760–780 million. Nebius has already put a fit-out charge and a deposit into escrow, an account that releases money under agreed conditions. Fit-out means preparing a space for use. AIB draws on the escrow to build. Nebius can end the deal and recover that money if the halls are late or if certain early permits are not obtained. AIB had not arranged its construction loans by mid-November. Neither company has disclosed the rent. The roughly $1.32 billion often quoted as the deal's value comes from an AIB presentation. AIB calculated the figure before the lease was signed.

Sources 17 documents — 10 SEC filings · 4 transcripts · 2 other documents · 1 company release

Research trail Found 103 documents and read 92 of them while checking this deal and related ones.

  1. SEC · SEC filingsec.gov
    States 14 figures: 50 MW agreement · term · renewal options · hall targets · charge · guarantee · termination · escrow · escrow release · status sep 30 · $7,672,000 spend sep 30 · 40 MW site · 65 MW site power · financing status
  2. GlobeNewswire · company releaseNov 10, 2026globenewswire.com
    States 3 figures: first draw · $15.2–15.6M cost per MW · $90.5M stabilized NOI
  3. SEC · SEC filingsec.gov
    States 50 MW announcement
  4. sc-spartanburgcounty.civicplus.com · other documentsc-spartanburgcounty.civicplus.com
    States $400M county agreement
  5. SEC filingsec.gov
    States 50 MW nebius side
  6. wyff4.com · other documentwyff4.com
    States county vote
  7. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  8. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  9. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  10. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  11. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  12. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  13. transcriptstockanalysis.com
    Cited by the record; no single figure is quoted from it.
  14. transcriptstockanalysis.com
    Cited by the record; no single figure is quoted from it.
  15. transcriptstockanalysis.com
    Cited by the record; no single figure is quoted from it.
  16. transcriptstockanalysis.com
    Cited by the record; no single figure is quoted from it.
  17. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: AIB Data Centers Q3 2026 10-Q (Note 10, Notes 2 and 12, MD&A; filed 2026-11-16); AIB releases of Sep 30 (8-K Oct 1, Item 7.01, furnished), Nov 10 and Nov 16 2026; AIB decks of Jul, Aug, Sep 10 and Sep 30 2026 (8-K ex-99.1, furnished); call transcripts of Oct 1, Oct 21, Oct 22 and Oct 29 2026 (Stock Analysis); Nebius Q3 2026 shareholder letter and financial statements (6-K, 2026-11-12); Spartanburg County Council packet (Nov 16 2026); WYFF (Nov 16 2026) (read 2026-11) · as of Nov 2026

The evidence 21 sourced figures · 10 disputes

The record's headline AIB Data Centers–Nebius, CLT1 (Moore SC): 50 of critical IT in two 25 MW halls, 12 years from each hall's rent start, Nebius Group guaranteeing — a prepayment paid into escrow, refundable if AIB is late, and no contract value filed

Size
50 MW critical IT (two 25 MW halls) · 12-yr initial term per hall + two 5-yr options · contract value not filed (~$1.25–1.32B estimated) · build ~$760–780M
When
Sep 25 2026 signed by AIB CLT1 LLC and Nebius Inc. → Sep 30 announced by AIB, naming Nebius (8-K Oct 1, furnished) → Oct 1 the 65 MW electric service agreement takes effect → Oct 20 Nebius funds the fit-out charge and security deposit into escrow → Nov 10 AIB has its first draw and has ordered generators, UPS systems and switchgear → Nov 12 Nebius's Q3 letter: 'A new 50 MW colocation in South Carolina' → Nov 16 Q3 10-Q filed; the county's CLT1 development agreement passes third reading → Q4 2027 Data Hall 1 target → Q1 2028 Data Hall 2 target → 12 years from each hall's rent commencement, + two five-year options
Status
signed Sep 25 2026 · announced Sep 30 (release furnished under Item 7.01) · first in a filed document in the Q3 10-Q of Nov 16 · escrow funded Oct 20, first draw received by Nov 10 · at Sep 30 no lease commenced and no revenue recognized · project-level debt and preferred equity not arranged (10-Q) · Spartanburg County's development agreement for the site passed third and final reading Nov 16 (WYFF) · halls targeted Q4 2027 and Q1 2028 · Nebius's filings never name AIB
Structure
a Master Colocation Services Agreement and related statement of work, signed Sep 25 2026 by AIB CLT1 LLC, AIB's wholly owned project company, and Nebius Inc., Nebius's US subsidiary, for 50 MW of critical IT capacity in two 25 MW data halls at CLT1, the repurposed 40 MW bitcoin-hosting facility AIB has run in Moore, South Carolina. Rent starts hall by hall, on completion and acceptance; each hall's 12-year initial term runs from its own rent commencement by the 10-Q (from the first hall by the Sep 30 deck — term-start), with two five-year renewal options at Nebius's election. The charge is 'an initial monthly recurring charge, subject to annual escalation' — no rate, escalator or total is filed (contract-value, escalator); power is to be passed through to Nebius once service begins. Nebius Group N.V. guarantees Nebius Inc.'s obligations. Nebius paid a fit-out charge and a security deposit into escrow on Oct 20 2026 (amounts undisclosed), usable only to develop the data center and released to AIB on conditions that include a pledge of AIB CLT1 LLC's equity and assets and a payment guarantee from AIB. AIB must deliver each hall by outside dates (not disclosed): late delivery earns rent credits, and Nebius may terminate and recover its prepaid amounts if the outside dates are missed or certain initial permits are not obtained within 90 days of the effective date. AIB means to fund the rest of the ~$760–780M build with project-level debt and preferred equity, none arranged at Nov 16 2026. The agreement itself is not filed
Programme
AIB Data Centers–Nebius
Parties
AIB Data Centers the provider and landlord, through AIB CLT1 LLC, its wholly owned project company: builds the two halls at CLT1 on a leasehold of about 16 acres, holds the site's 65 MW electric service agreement, pledges AIB CLT1 LLC's equity and assets and gives its own payment guarantee to have the escrowed money released, and owes rent credits — and, past the outside dates, the prepaid money back — if it is late · Nebius the customer, through Nebius Inc.: pays the monthly charge from each hall's rent commencement and paid the fit-out charge and security deposit into escrow; Nebius Group N.V., the listed parent, guarantees Nebius Inc.'s obligations. Its own filings describe 'A new 50 MW colocation in South Carolina' and never name AIB
Record
disclosed / primary source · as of Nov 2026

Flows 3 as the record states them

  • Nebius → AIB Data Centerscolocation-chargesan initial monthly recurring charge from each hall's rent commencement, subject to annual escalation (10-Q): rate, escalator and total all undisclosed. Estimates on file run from ~$1.25B (an analyst, relayed on AIB's Oct 1 call) to ~$1.32B (AIB's Sep 30 deck, implied) over the 12-year initial term; AIB's CFO: 'well over the $1 billion mark' (contract-value). Power passed through on top once service begins
  • Nebius → AIB Data Centersprepayment-escrowa fit-out charge and a security deposit, deposited into escrow on Oct 20 2026 (10-Q), released to AIB only for the build and on conditions; AIB had its first draw by Nov 10. Amounts undisclosed in every document (contested prepayment-amount); refundable to Nebius if AIB misses the outside dates or certain initial permits within 90 days of the effective date
  • AIB Data Centers → Nebiuscapacity50 MW of critical IT capacity at CLT1, Moore SC, in two 25 MW data halls targeted for Q4 2027 and Q1 2028 (10-Q), on 65 MW of contracted utility power; 12 years from each hall's rent commencement, plus two five-year renewal options at Nebius's election

Resolved figures 21 each with the verbatim line from its document

  • agreement50 MW
    50 MW of critical IT capacity in two 25 MW data halls at CLT1, under a Master Colocation Services Agreement and related statement of work signed Sep 25 2026 by AIB CLT1 LLC (AIB's wholly owned project company) and Nebius Inc. (Note 10). Critical IT is the power for Nebius's own equipment, measured at the IT gear; the site's 65 MW is utility power, measured at the connection, and the 10-Q calls the two measures 'not additive' (site-power). The 10-Q is the first filed text of the agreement: the Sep 30 release and deck were furnished (announcement), and the agreement is not among the 10-Q's exhibits
    “On September 25, 2026, the Company’s wholly owned subsidiary, AIB CLT1 LLC, entered into a Master Colocation Services Agreement and related statement of work (the “Colocation Agreement”) with Nebius Inc. (the “CLT1 Customer”) to provide 50 MW of critical IT capacity in two 25 MW data halls at the Company’s CLT1 data center campus.”
    AIB Data Centers Q3 2026 10-Q (filed 2026-11-16), Note 10 — Commitments and Contingencies · sec.gov
  • announcement50 MW
    the day the deal became public: AIB's release of Sep 30 2026 (GlobeNewswire), furnished with an 8-K of Oct 1 under Item 7.01, naming Nebius and putting the site only in 'the southeastern United States'. It quotes Nebius's chief product and infrastructure officer: 'This agreement adds dedicated capacity in the southeastern United States for training and inference workloads.' Its headline, 'Optional Renewals Could Increase Total Contract Value', gives no value
    “today announced that it has entered into a binding agreement with Nebius (Nasdaq: NBIS), the AI cloud company, for 50 MW of critical IT capacity at AIB’s facility located in the southeastern United States.”
    AIB release of Sep 30 2026 (8-K ex-99.1, furnished under Item 7.01, 2026-10-01) · sec.gov
  • term12
    12 years from the rent commencement date of each data hall (Note 10), so the second hall's term ends about a quarter after the first's on the targets (our reading; contested term-start). The MD&A repeats '12 years' and says Nebius holds the renewal options (renewal-options)
    “The Colocation Agreement has an initial term of 12 years from the rent commencement date of each data hall, with two five-year renewal options.”
    AIB Data Centers Q3 2026 10-Q (filed 2026-11-16), Note 10 · sec.gov
  • renewal-options5
    two five-year renewal options, Nebius's to exercise — up to ten more years on each hall. The renewals' price is not disclosed. Spartanburg County's development agreement for the site extends with them (county-agreement)
    “The initial term is 12 years, with two five-year renewal options exercisable by the CLT1 Customer.”
    AIB Data Centers Q3 2026 10-Q (filed 2026-11-16), MD&A — Development Portfolio · sec.gov
  • hall-targets
    target commencement Q4 2027 for Data Hall 1 and Q1 2028 for Data Hall 2 (Note 10). The MD&A gives the same quarters as delivery estimates, 'estimates, not guidance', depending on 'permitting, equipment procurement, construction and financing'; the Nov 16 results release repeats them. AIB's management gave earlier months in October (contested hall-dates)
    “The target commencement dates for the two data halls are Q4 2027 and Q1 2028, respectively.”
    AIB Data Centers Q3 2026 10-Q (filed 2026-11-16), Note 10 · sec.gov
  • charge
    all a filing says of the price: an initial monthly recurring charge that escalates every year. No rate, escalator or total is filed, by AIB or by Nebius (contract-value, escalator); the CFO says Nebius asked that the rate stay private
    “It provides for an initial monthly recurring charge, subject to annual escalation.”
    AIB Data Centers Q3 2026 10-Q (filed 2026-11-16), Note 10 · sec.gov
  • guarantee
    the credit behind the tenant: Nebius Group N.V., the Nasdaq-listed parent, guarantees Nebius Inc.'s obligations. The MD&A expects 'substantially all of our revenue for the foreseeable future to come from a single customer, Nebius Inc.', 'supported by a guaranty from its parent company'. The guaranty's terms, caps and exclusions are not filed; AIB's Sep 30 deck calls it 'Guaranty from Nebius ($50+ billion market cap)'
    “The CLT1 Customer’s obligations are guaranteed by its parent company, Nebius Group N.V.”
    AIB Data Centers Q3 2026 10-Q (filed 2026-11-16), Note 10 · sec.gov
  • termination90 days
    what late delivery costs AIB: AIB must deliver each hall by outside dates (not disclosed); a late hall earns Nebius rent credits, and Nebius may terminate and recover its prepaid amounts if the outside dates are missed or if 'certain initial permits' are not obtained within 90 days of the effective date (which permits, the 10-Q does not say). The MD&A repeats it. AIB's chief executive had called it 'a firm contract with no termination options' (contested termination-rights)
    “The Company is required to deliver each data hall by specified outside dates. If the Company fails to do so, it is subject to rent credits for late delivery, and the CLT1 Customer may terminate the agreement and receive a refund of prepaid amounts if the outside dates are not met or if certain initial permits are not obtained within 90 days of the effective date.”
    AIB Data Centers Q3 2026 10-Q (filed 2026-11-16), Note 10 · sec.gov
  • escrow
    Nebius's prepayment, in the filing's words: on Oct 20 2026 Nebius Inc. paid into escrow 'the fit-out charge and the security deposit' (subsequent events; the Key Milestones table says the same). The July and August negotiation-stage decks had '12 - mo prepaid rent + deposit'; the filing does not call it rent. No document gives either amount (contested prepayment-amount)
    “On October 20, 2026, the CLT1 Customer deposited funds into escrow pursuant to the Colocation Agreement, consisting of the fit-out charge and the security deposit.”
    AIB Data Centers Q3 2026 10-Q (filed 2026-11-16), Note 12 — Subsequent Events · sec.gov
  • escrow-release
    the escrow's terms: the money may be used only to develop the data center, and is released to AIB only on conditions that include a pledge of AIB CLT1 LLC's equity and assets and a payment guarantee from AIB itself. The 10-Q does not say whom the pledge and the guarantee run to; on our reading they secure Nebius, the party that can claim its prepaid amounts back (termination). Nebius Group separately guarantees Nebius Inc. (guarantee). Among AIB's stated priorities is to 'satisfy the conditions for release of the escrowed CLT1 Customer prepayments'
    “Escrowed funds may be used only to develop the data center and are released to us upon satisfaction of specified conditions, including a pledge of the equity and assets of AIB CLT1 LLC, and a payment guarantee from the Company.”
    AIB Data Centers Q3 2026 10-Q (filed 2026-11-16), MD&A — Development Portfolio · sec.gov
  • first-draw
    money moving from the escrow to AIB: by Nov 10 2026 AIB had 'received its first draw' (amount undisclosed, as is what remains), and had ordered backup generators, UPS systems and switchgear ('executed purchase orders ... with delivery scheduled to support the construction timeline'). The Nov 16 results release repeats both. GlobeNewswire's copy of the company's release, so tier 2; the 10-Q does not mention a draw
    “today announced that prepayment obligations were funded into escrow for AIB’s CLT1 campus and that AIB has received its first draw.”
    AIB release of Nov 10 2026 (GlobeNewswire) · globenewswire.com
  • status-sep-30
    the build at the end of the quarter the agreement was signed: halls under development, no lease commenced, no revenue recognized under it; AIB was still deciding how to account for it under ASC 842 (lease and nonlease parts) and may book revenue for the build-out of the halls, 'the timing and accounting treatment of which we are still evaluating'. Its filed spending on CLT1 so far: construction in progress of $2,528,591 (design, engineering and site work) and $7,672,000 of vendor deposits for long-lead equipment (spend-sep-30)
    “As of September 30, 2026, the related data halls were under development, no lease had commenced and no revenue had been recognized under the Colocation Agreement.”
    AIB Data Centers Q3 2026 10-Q (filed 2026-11-16), Note 2 — Lessor Arrangements · sec.gov
  • spend-sep-30$7,672,000
    $7,672,000 of deposits paid to vendors for CLT1's long-lead equipment (generators, medium-voltage switchgear) and environmental services, beside $2,528,591 of construction in progress, at Sep 30 2026 — before the escrow was funded. The only filed figures for what CLT1 has cost so far
    “Deposits on assets and construction were $7,672,000 as of September 30, 2026.”
    AIB Data Centers Q3 2026 10-Q (filed 2026-11-16), Note 2 · sec.gov
  • site40 MW
    CLT1 is the 40 MW bitcoin-hosting facility AIB has run at 389 Tyger River Industrial Drive in Moore, Spartanburg County, on a leasehold of about 16 acres (county-agreement), to be replaced by a single standalone building (the county packet). Hosting was de-energized Jun 5 2026 and its wind-down approved Nov 11 2026
    “CLT1 is the repurposing of our existing 40 MW grid-interconnected facility, which historically provided hosting services to third-party bitcoin miners.”
    AIB Data Centers Q3 2026 10-Q (filed 2026-11-16), MD&A — Overview · sec.gov
  • site-power65 MW
    the site's power: an amended electric service agreement (executed May 27 2026) for 65 MW of contract demand, effective Oct 1 2026 for an initial 15 years, with a minimum demand charge of $400,000 a month — $200,000 payable now and $200,000 deferred, without interest, until the earlier of demand reaching 40,000 kVA and Dec 31 2027. Until Nebius's service begins it is a cost with no revenue against it. Power costs are to pass through to Nebius once service commences (the 10-Q: 'we expect power costs to be passed through to the CLT1 Customer once service commences')
    “The amended ESA, effective October 1, 2026, provides 65 MW for an initial 15-year term and carries a minimum monthly demand charge of $400,000”
    AIB Data Centers Q3 2026 10-Q (filed 2026-11-16), MD&A · sec.gov
  • cost-per-mw$15.2–15.6M
    AIB's Nov 10 estimate of the build, per MW of critical IT: ~$15.2–15.6M, of which $12.6–12.9M construction and $2.6–2.7M land, contingency and financing — the ~$760–780M total over 50 MW (contested build-cost). On the 65 MW of utility power the same total is ~$11.7–12.0M per MW (our arithmetic), the basis of the CEO's 'about $800 million' ÷ 65 on Oct 1. Estimates 'subject to changes in project scope, procurement pricing, financing terms, and construction timing'. GlobeNewswire's copy of the company's release, so tier 2
    “On the 50 MW critical IT capacity basis used in this update, this equates to approximately $15.2-$15.6 million per IT MW: $12.6-$12.9 million for construction and $2.6-$2.7 million in land, contingency, and financing costs.”
    AIB release of Nov 10 2026 (GlobeNewswire), Development Costs · globenewswire.com
  • stabilized-noi$90.5M
    ~$90.5M a year of projected stabilized net operating income, 'based on Year 5 of the executed customer agreements' — AIB's underwriting, a non-GAAP measure with no reconciliation, 'not current earnings or cash available to common shareholders'. The release says 'across all contracted sites', but the 10-Q has CLT1 as the only site with a customer agreement, so it is this lease's figure. The Sep 10 deck's ~$79–84M was a pre-lease illustration at stabilization, before any rent was agreed. GlobeNewswire's copy of the company's release, so tier 2
    “Across all contracted sites, the Company’s underwriting projects approximately $90.5 million in annual stabilized net operating income (NOI), a non-GAAP financial measure, based on Year 5 of the executed customer agreements.”
    AIB release of Nov 10 2026 (GlobeNewswire) · globenewswire.com
  • financing-status
    the rest of the money is not raised: AIB means to fund CLT1 'primarily with the escrowed Colocation Agreement prepayments and project-level debt and preferred equity', and none of the project-level financing is arranged (MD&A). The Nov 16 results release adds that Northland Capital Markets is advising on that financing. Management expected the debt 'by mid-December, early January' (CFO, Oct 21) — an expectation, not a fact on file (contested capital-stack, equity-need)
    “We have not arranged any project-level financing, and its availability and terms are not assured.”
    AIB Data Centers Q3 2026 10-Q (filed 2026-11-16), MD&A — Key Factors · sec.gov
  • county-agreement$400M
    Spartanburg County's development agreement with AIB CLT1 LLC for the site (the proposed form in the council's Nov 16 2026 packet): 'a leasehold interest on approximately sixteen (16) acres located at 389 Tyger River Industrial Dr. in Moore', not more than 50 IT MW with a 65 MW maximum facility cap, a company investment of at least $400M and, with its tenant, $1.2B anticipated, and at least 28 jobs. A 12-year term from its own effective date, extended twice by five years 'should the third-party tenant/lessee of the Company renew its lease'. The $1.2B includes the tenant's own investment, so it is not AIB's build cost (cost-per-mw). The executed agreement is not on file (county-vote)
    “in an amount of not less than $400 million (the “Company Investment”) and, along with its tenant, anticipates investing a total of $1.2 billion.”
    Spartanburg County Council agenda packet, Nov 16 2026 — Development Agreement with AIB CLT1 LLC (proposed form) · sc-spartanburgcounty.civicplus.com
  • county-vote
    the county's approval: the council passed the CLT1 development agreement on third and final reading on Nov 16 2026, unanimously; WYFF: 'The 50-megawatt project represents an anticipated $1.2 billion investment and is expected to create 28 jobs.' Local press, so tier 2; no minutes or signed agreement are on file. Whether the county's approvals are the 'certain initial permits' of the 90-day condition (termination), no document says
    “The agreements for AIB CLT1 LLC and 300 Jones Road Associates LLC both passed unanimously.”
    WYFF, Nov 16 2026 · wyff4.com
  • nebius-side50 MW
    the customer's side: Nebius's Q3 2026 shareholder letter (Nov 12; furnished with a 6-K) lists 'A new 50 MW colocation in South Carolina, our eighth US site' among capacity added since the quarter began; it never names AIB or CLT1, and nor does Nebius's Q3 financial report, its operating review or its Nov 12 call (read 2026-11-19). That it is this agreement is our reading of the two companies' documents. Nebius's statements put leases signed but not yet commenced at $13,862.3M of undiscounted payments at Sep 30 2026, 'primarily for data center facilities', with terms up to twelve years, commencing 2026–2029 — a Nebius-wide total; whether CLT1 is inside it is not stated. A furnished letter
    “A new 50 MW colocation in South Carolina, our eighth US site, is expected to come online in 2027;”
    Nebius Q3 2026 shareholder letter (6-K ex-99.2, furnished, 2026-11-12) · sec.gov

Contested figures 22 not reconciled — every position side by side, with its source and tier

contract-value3 positions, side by side
not disclosed: no AIB or Nebius filing gives a value, rate or escalator (charge). AIB's chief executive, Oct 1: 'because of customer confidentiality, we cannot disclose the exact total contract value', and Nebius 'do not want to release the TCV'; he put the rate 'higher than all three' of his comparables at $1.87–2.16M per MW a year and said 'in the worst-case analysis, you take that $2.16 million multiplied by 50 MW, multiplied by 12 years' — ≈ $1.296B (our arithmetic). The CFO, Oct 21: above the typical '$1.8 million-$2.1 million', 'just outside of that range', and 'well over the $1 billion mark' over the contract's life AIB Q3 2026 10-Q; call transcripts of Oct 1 and Oct 21 2026 (Stock Analysis)
~$1.32B: AIB's Sep 30 deck (8-K ex-99.1, furnished), 'AIB implied rate: $1.32B ÷ 12 years ÷ 50 MW' — ≈ $2.2M per MW a year, an average with the escalators in it — under a slide whose own note says 'Contract value and prepayments per the Company's Form 8-K', where no 8-K on file states either. The same ~$1.32B is in AIB's Sep 10 deck, two weeks before signing, as 'Illustrative only. AIB has not executed a tenant lease', from an assumed $1.86M per MW a year (≈ $1.32B over 12 years at 3% a year; the same deck's '$1.8M ... with 3% escalators' gives ≈ $1.28B — our arithmetic). Whether the signed rent reproduces the illustration, no document says AIB decks of Sep 10 and Sep 30 2026 (8-K ex-99.1, furnished)
~$1.25B: Lucid Capital Markets' estimate 'of approximately $1.25 billion over the next 12 years', read out by the moderator on AIB's Oct 1 call; the note itself is not on file, and the CEO answered with his worst-case arithmetic (≈ $1.296B) rather than confirm it. An analyst's figure, known second-hand AIB investor update call, Oct 1 2026 (Stock Analysis transcript)
term-start2 positions, side by side
from each hall's own rent commencement: 'an initial term of 12 years from the rent commencement date of each data hall' (Note 10 of the 10-Q, Nov 16 — filed, and the later document) AIB Q3 2026 10-Q (filed 2026-11-16), Note 10
from the first hall: 'Rent commences hall by hall; the 12-year initial term runs from the first hall.' (AIB's Sep 30 deck, furnished). On the targets the difference is about a quarter of the second hall's rent; neither document mentions the other, and the agreement is not filed AIB Q3 2026 investor deck (8-K ex-99.1, furnished, 2026-09-30)
hall-dates2 positions, side by side
Q4 2027 and Q1 2028: Note 10's target commencement dates and the MD&A's delivery estimates ('estimates, not guidance'), repeated in the Nov 16 results release. Nebius's Nov 12 letter: the South Carolina colocation 'is expected to come online in 2027', with no hall dates (nebius-side) AIB Q3 2026 10-Q (filed 2026-11-16) and results release (2026-11-16); Nebius Q3 2026 letter
August and December 2027: AIB's chief executive on Oct 22, 'The timeline for Data Hall in CLT1 is 10 months from this week, essentially. So you're talking about August 2027. For Data Hall 2, that's 14 months. That would be December 2027' (the escrow was funded Oct 20). The Sep 30 deck has '~Month 10' and '~Month 14' 'measured from the start of ESA service' (Oct 1); the CFO on Oct 21 gave the 10- and 14-month clocks and, earlier in the same talk, the second hall 'within three months' of the first. Three weeks later the 10-Q's quarters came; whether they measure delivery or rent commencement differently, no document says AIB call transcripts of Oct 21 and Oct 22 2026 (Stock Analysis); Q3 2026 investor deck (furnished)
termination-rights2 positions, side by side
none: 'It's a firm contract with no termination options. If there were termination options, it would be fully paid.' — AIB's chief executive on Oct 1, the day after the announcement AIB investor update call, Oct 1 2026 (Stock Analysis transcript)
termination for late delivery: the 10-Q's right to terminate and recover the prepaid amounts if the outside dates are missed or initial permits are not obtained within 90 days (termination); the CFO on Oct 21: 'a 30-day grace period' and 'termination optionality if that was to exceed six months, if we were six months delivery delayed', with force majeure carved out. The CEO may have meant no termination for convenience; he did not say so, and the filing's right is the one on paper. No document gives the outside dates AIB Q3 2026 10-Q (filed 2026-11-16), Note 10; LD Micro conference, Oct 21 2026 (Stock Analysis transcript)
prepayment-amount2 positions, side by side
not disclosed: the 10-Q names the fit-out charge and the security deposit and gives no amount (escrow); no release states one AIB Q3 2026 10-Q (filed 2026-11-16); releases of Nov 10 and Nov 16 2026
more than ~$100M: AIB's chief executive on Oct 1, 'all I can say is it is larger than the $100 million equity requirement for the project' (the equity slice of the deck's illustrative ~$800M stack, capital-stack). The CFO on Oct 21 put prepayments 'typically' at 'one to two years of prepaid rent' — 'You are in that $100 million-$200 million range for prepayments' — as what customers usually pay, not as this contract's figure. The July negotiation-stage deck: '12 - mo prepaid rent + deposit' AIB call transcripts of Oct 1 and Oct 21 2026 (Stock Analysis); July 2026 investor deck (furnished)
escalator2 positions, side by side
3% a year: AIB's CFO on Oct 29, after the signing — 'I can say that there's a 3% escalator', the rate itself private at Nebius's request. The 10-Q says only 'subject to annual escalation' (charge) Emerging Growth Conference, Oct 29 2026 (Stock Analysis transcript)
the greater of 3% or CPI: 'Escalator: 3% or CPI, annual', in AIB's July and August decks, for a 'LEASE UNDER NEGOTIATION' of 50 MW, on a '10 - yr term' with two five-year options — terms before the signing, whose initial term then came to 12 years AIB investor decks of July and August 2026 (8-K ex-99.1, furnished)
lease-form2 positions, side by side
modified gross: the CFO on Oct 29 — 'It's a modified gross, so power is a complete pass-through, but we're responsible for property management, insurance, and property taxes' Emerging Growth Conference, Oct 29 2026 (Stock Analysis transcript)
modified net: 'Modified net · credit - backed' in the July and August negotiation-stage decks. Both agree power passes through, as the 10-Q has it (site-power); they differ on who pays taxes and insurance, which moves the NOI (stabilized-noi). Nothing filed says AIB investor decks of July and August 2026 (8-K ex-99.1, furnished)
build-cost3 positions, side by side
~$760–780M including land: AIB's Nov 10 estimate, ~$630–645M of construction and $130–135M of land, contingency and financing (cost-per-mw) AIB release of Nov 10 2026 (GlobeNewswire)
~$800M: the Sep 30 deck's 'Illustrative' '~$800M build'; the CEO's 'Total budget ... is about $800 million' (Oct 1); the CFO's '$800 million' 'just for round figures' (Oct 22) AIB Q3 2026 investor deck (furnished); call transcripts of Oct 1 and Oct 22 2026 (Stock Analysis)
~$850M: 'Total project cost, 65 MW ~$850M' in AIB's Sep 10 deck, before the signing, on 65 MW of utility load. No budget is filed; the county agreement's $400M minimum and $1.2B with the tenant measure other things (county-agreement) AIB investor deck of Sep 10 2026 (8-K ex-99.1, furnished)
capital-stack2 positions, side by side
the Sep 30 deck's illustration: 'How the ~$800M build is funded Construction debt $560M 70.0% Equity $100M 12.5% Preferred equity $140M 17.5%', with 'AIB common equity: funded with prepayments' — 'Illustrative example from the Company's consolidated cash flow model; not a projection or guidance'; the CEO gave the same stack on Oct 1 AIB Q3 2026 investor deck (8-K ex-99.1, furnished, 2026-09-30); Oct 1 2026 call
the CFO on Oct 22: on '$800 million', 'about $500 million-$600 million would be a debt portion, or a private debt portion' and '$100 million-$150 million in the preferred equity position', the rest equity, which 'is already in the project from our follow-on offering' (AIB's June share sale) rather than from the prepayment. None of it is arranged (financing-status) AIB investor update, Oct 22 2026 (Stock Analysis transcript)
equity-need2 positions, side by side
none: 'we do not need to raise any equity. I'll say that again, we do not need to raise any equity, full stop.' — the CEO on Oct 1, on the strength of 'a material amount of prepayment from the client'; the 10-Q, too, 'based on our current plan, do not expect to require corporate-level common equity for CLT1' AIB investor update call, Oct 1 2026 (Stock Analysis transcript); Q3 2026 10-Q
possibly: the 10-Q, 'If prepayments are delayed or not released, or project financing is unavailable on acceptable terms, we may need to raise additional corporate-level capital, including equity that would dilute stockholders', since the escrow's release is conditional and 'amounts reconcile to actual cost'; the Sep 30 deck: 'there may be a need to raise equity for the project depending on final capital stack'. AIB had $15.3M of unrestricted cash at Sep 30 (the aib entity) AIB Q3 2026 10-Q (filed 2026-11-16), MD&A; Q3 2026 investor deck (furnished)

Scope note what this record leaves to other records

NOT this record (carried elsewhere or left out): Nebius's company-wide figures — 2026 customer prepayments of '$10 billion' (Q3 letter, from 'over $9 billion' in August), debt carried at $14,162.8M at Sep 30 2026, cash, remaining performance obligations, contracted power, the Citi bridge and the July secured loan, the Microsoft and Meta contracts, the Nvidia warrant (its 21,065,396 vs 21,065,936 share count) and the Meta order's first-tranche month → the nebius entity and its records (nb-msft, nb-meta, nb-secured-2026, nb-citi-bridge-2026, nv-nebius-2026), not refreshed here. Nebius's revenue per MW of capacity ('ACV per MW >$25M' in its letter; '$20M per 1 MW' in a newsletter) is what Nebius earns selling computing, not AIB's rent → not carried. AIB's company figures (sites, cash, the June offering, the DFW1 purchase and its closing payment, the legacy hosting wind-down) → the aib entity; its other disputed company measures — 'energized' MW (65 in the June prospectus, 40 in the Q2 10-Q, 15 'in Texas, energized at closing' in the Sep 30 deck), pipeline totals (200 → ~715 → ~485 → ~570 → ~345 MW), market cap per energized MW against peers, and the $6.56B illustrative value of sites with no customer → not carried. AIB's March 2026 letters of intent (5 MW and 20 MW, 'over $100 million' and 'over $400 million') predate this agreement and name no counterparty; whether either was Nebius, no document says → not carried. Spartanburg County's CLT2–CLT4 agreements for other AIB projects (first reading Nov 16) and the Valara and 300 Jones Road agreements in the same packets → not carried. AIB's anchor-lease comparables (WhiteFiber–Nscale, Applied Digital–CoreWeave, Host Digital) are other deals; the Digi Power X row of the Sep 10 deck is on cerebras-digipowerx. Yield on cost (the CEO's '11%+', the CFO's 'low double digits', a newsletter's 11.6–11.9% from $90.5M ÷ $760–780M) and the 85–90% margins rest on the undisclosed rent → not carried. The 'certain initial permits' 90 days: from a Sep 25 effective date that would be about Dec 24 2026 (our arithmetic); whether they are met, no document says. Not adopted: '$1.32 billion deal' headlines that state the deck's implied figure as the contract's value; one transcript's '$675' price target and build costs 'between 10 million to 40 million on utility load' on the Oct 1 call, where the other transcript of the same call reads '$6.75' and '$10 million - $14 million'; a newsletter's 'Q3 and Q4 2027' and two research pages' delivery of both halls in Q4 2027, their own readings of the month clocks and the October deck; a project table's 65 MW for the customer (utility power, not the contracted 50 MW of IT); preferred-equity figures of '$100–130M' and 'up to $150M', which are Globes's and Calcalist's prices for Nebius's purchase of Inferize, not AIB's preferred.