Why it matters
Amazon's expanded deal with Talen goes through the grid and PJM's capacity market. FERC refused on procedural grounds and without prejudice to let the direct connection grow past 300 . The replacement covers up to 1,920 MW, and Talen describes its '$18B' figure in two incompatible ways.
Tap a figure for the line in its source.
Amazon / AWS gives Talen Energy
- for the data-center campus next to the plant, bought Mar 2024
- disputedover 17 years by Talen's own count, stated two incompatible ways; price never published
Talen Energy gives Amazon / AWS
- of nuclear power through 2042 over the grid, ramping to full volume by 2032
- wired straight from the plant until Apr 2026; regulators rejected raising it to 480
What happened
Amazon bought a data-center campus next to Talen's Susquehanna nuclear plant in Pennsylvania and agreed to buy the plant's power. Amazon paid $650 million for the campus. The original deal called for up to 960 wired straight from the reactors. Federal regulators refused to let the direct connection grow past 300 MW. The rewritten agreement covers up to 1,920 MW through 2042. The power goes through the regional grid. Talen says the contract is worth roughly $18 billion to it over 17 years. Talen's own presentations describe that figure in two incompatible ways. No one has published the price per megawatt-hour. Two other utilities in the PJM grid region, Exelon and AEP, objected at the Federal Energy Regulatory Commission (FERC). They argued that a data center wired directly to a plant avoids paying for the shared grid. The same dispute is playing out across the industry. Regulators rejected the larger hookup on procedural grounds and did not rule on the claim that it shifts costs to others.
Sources 11 documents — 7 SEC filings · 2 regulatory filings · 2 company releases
Research trail Found 169 documents and read 164 of them while checking this deal and related ones.
- States 7 figures: term · full volume date · 480 MW ferc rejection · 148 MW cir restoration · $650M campus sale · 90% plant ownership · $27 production cost
- States 4 figures: 1,680 MW ramp bands · 50–65% shortfall cap · 300 MW delivery structure · 480 MW cap option eliminated
- States 1,920 MW contract quantity
- States fotm transition
- States 960 MW colocated ceiling
- States original PPA
- States campus
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: Talen 8-K exhibits (6/11/2025 PR + deck; 9/9/2025 investor update) + FY24/FY25 10-Ks + Q1/Q2'26 10-Qs; FERC order ER24-2172 (11/1/2024) + PJM filings; Amazon project page + carbon-free-energy project CSV · as of Aug 2026
The evidence 16 sourced figures · 8 disputes
The record's headline Amazon–Talen: Susquehanna PPA expanded to 1,920
- Size
- 1,920 MW → 2042 (from 960 MW behind-the-meter)
- When
- Mar 2024 (sale + 960 MW PPA) → Jun 2025 (1,920 MW revision) → Apr 2026 (FOTM transition)
- Status
- operational — front-of-meter since Apr 2026; ramping to full volume by 2032
- Structure
- campus sale + power purchase agreement (behind-the-meter → front-of-the-meter retail supply)
- Programme
- Time-to-power
- Parties
- Amazon / AWS campus buyer + offtaker (Talen's retail customer after the front-of-meter shift) · Talen Energy campus seller + nuclear-operator + retail electric supplier
- Record
- disclosed / primary source · as of Aug 2026
Flows 3 as the record states them
- Amazon / AWS → Talen Energycampus-purchase$650M gross for the Cumulus / AWS Data Campus, Mar 2024 ($350M at close + $300M escrow released Aug 23 2024 on zoning milestones)
- Talen Energy → Amazon / AWSpowerup to 1,920 MW nuclear through 2042 at full contract quantity (min–max ramp 240–960 MW 2026 → 1,680–1,920 MW 2032); 300 MW behind-the-meter until the Apr-2026 front-of-meter transition
- Amazon / AWS → Talen Energyppa-paymentsprice undisclosed — Talen's own '~$18B' over 17 years, stated on two incompatible bases (see contested revenue-basis); plus separate carbon-free-energy-attribute revenue, unquantified
Resolved figures 16 each with the verbatim line from its document
- contract-quantity1,920 MW1,920 MW at full contract quantity — the revised (Jun 2025) PPA, doubling the original 960 MW ceiling and covering both Susquehanna units. '1.9 GW' / '1.92 GW' / '2 GW' in Amazon's sustainability page, trade press and the CEO's Q2'26 call are roundings of this one number, not a range (Amazon's own carbon-free-energy CSV lists the project as 1,920.00 MW). The 'behind-the-meter' label describes the SUPERSEDED structure — see delivery-structure
“Under the expanded PPA, at the full contract quantity, Talen will provide Amazon with 1,920 megawatts of carbon-free nuclear power through 2042, with options to further extend its duration.”
Talen 8-K ex-99.1 (PR 6/11/2025) · sec.gov - term2042through 2042 with extension options — a 17-year contract by Talen's own count (both decks), ending at Susquehanna Unit 1's NRC licence expiry (Unit 2: 2044; up to 20-year extensions possible). Distinct from the superseded original PPA's 18-year initial term + two 10-year AWS extension options (see original-ppa): two different contracts, not a conflict
“In June 2025, the Company and AWS entered into a revised AWS PPA, under which the Company is expected to provide AWS with up to 1,920 MW of power in a “front-of-the-meter” model through 2042.”
Talen FY25 10-K · sec.gov - full-volume-date2032full volume no later than 2032, 'with the potential to meaningfully accelerate' — AWS holds the acceleration option (Sept-2025 deck fn 4: 'AWS has opportunity to further accelerate maximum AWS PPA volumes to full 1,920 MW with notice'); the same deck prices an 'AWS PPA accelerated by 480 MWs' scenario as ~10% FCF/share upside
“The AWS PPA, which has minimum commitments, has a power delivery schedule that ramps up over time, which is expected to achieve the full volume no later than 2032, with the potential to meaningfully accelerate.”
Talen FY25 10-K · sec.gov - ramp-bands1,680 MWminimum–maximum contract volumes (Talen's own ramp table, Jun + Sept 2025 decks): 240–960 MW mid-2026 · 360–960 MW mid-2027 · 480–960 MW mid-2028 · 840–1,200 MW 2029 · 1,680–1,920 MW 2032. Quoting only the minimum leg ('240 MW mid-26') understates near-term contracted volume by up to 4x; both ends are carried — the minimum is what Talen is guaranteed, the maximum is Amazon's option
“shows minimum and maximum contract volumes; opportunity to further accelerate volumes. Price escalators through 2042 1,680 – 1,920MW Ramp7”
Talen 8-K ex-99.2 (deck 6/11/2025, fn 7) · sec.gov - shortfall-cap50–65%50–65% of full impact — Talen's ESTIMATE of the capped make-whole Amazon owes if it draws no power, 'based on market pricing'; repeated verbatim in the Sept-2025 deck. The most important downside term in the deal, and it is an issuer estimate, not contract text: mechanism, trigger and measurement period are undisclosed
“Contract volumes subject to a shortfall ‘make-whole’ with cap; shortfall payment cap, assuming no power drawn, is estimated to range 50-65% of full impact, based on market pricing.”
Talen 8-K ex-99.2 (deck 6/11/2025, fn 3) · sec.gov - delivery-structure300 MWfront-of-the-meter: Susquehanna sells to the PJM grid, Talen is Amazon's retail electric generation supplier, PPL Electric handles transmission and delivery — the structure that 'does not require FERC approval' — with the FERC-accepted 300 MW behind-the-meter arrangement kept in the interim. 300 MW (150 MW behind each unit, Feb-2023 ISA amendment) is the ONLY co-located load FERC ever accepted; 480 MW was rejected (see ferc-rejection) and 960 MW was never more than a stated intent (see colocated-ceiling)
“Shifts campus to retail “Front-of-the-Meter” after grid connection established; maintains 300 MW “Behind-the-Meter” (“BTM”) status in interim period”
Talen 8-K ex-99.2 (deck 6/11/2025) · sec.gov - fotm-transition2026the transition to the revised PPA occurred in April 2026 (Q1 and Q2 2026 10-Qs). The FY25 10-K's 'begin … spring 2026, full transition … spring 2027' and the Jun-2025 release's 'spring 2026, concurrent with the refueling outage' are earlier framings of the same staged event, not a conflict; completion of the full physical reconfiguration by spring 2027 is not separately confirmed
“The transition to the revised AWS PPA occurred in April 2026.”
Talen Q2'26 10-Q · sec.gov - cap-option-eliminated480 MWthe revision removed Amazon's one-time option to cap commitments at 480 MW (the S-1's '480 MW Case') and terminated the Nautilus cryptomine lease on the campus. 480 MW therefore appears in this record with opposite status depending on date — a live buyer option before Jun 2025, a dead one after — and, unrelatedly, as the co-located load FERC rejected
“De-risks PPA delivery – does not require FERC approval, establishes grid connection, eliminates Amazon option to cap commitments at 480 MW, and terminates Nautilus lease”
Talen 8-K ex-99.2 (deck 6/11/2025) · sec.gov - ferc-rejection480 MWFERC rejected the amended ISA (co-located load 300 → 480 MW) on Nov 1 2024, 2–1 — Christie and See to reject, Chairman Phillips dissenting. A procedural holding under Order No. 2003, not a merits ruling on co-location: 'PJM has failed to meet the high burden to demonstrate the non-conforming provisions are necessary'; the order says the filing 'leaves multiple important questions unresolved' and declines to reach them; Christie's concurrence: 'I emphasize that PJM's filing is rejected without prejudice'. It made no finding on the cost-shift dollar claims (see contested cost-shift). Rehearing parked Dec 2024 and Apr 2025; Talen's 5th-Circuit appeal transferred to the 3rd Circuit Nov 2025 and voluntarily dismissed Jan 2026 once the CIR waiver was granted — 'This matter is now closed.' The existing 300 MW ISA was never disturbed
“As previously disclosed, in November 2024, the FERC issued an order denying an Amended Interconnection Service Agreement (the “ISA Amendment”) between PJM, a subsidiary of PPL Corporation, and Susquehanna that would have permitted Susquehanna to decrease by up to 480 MW the amount of power it would have otherwise supplied to the grid and instead supply that power directly to AWS in a co-located “behind-the-meter” arrangement.”
Talen FY25 10-K (Item 3) · sec.gov - colocated-ceiling960 MW960 MW was a stated 'ultimate intent' and campus build-out ceiling (also the original PPA's maximum and the $100M escrow-release zoning threshold), NEVER an approved co-located load: PJM's own filing says the ISA does not authorize it, and FERC rejected even 480 MW. '960 MW' appears in the sources as a bare figure meaning five different things — PPA ceiling, PJM-filing intent, campus capability, zoning trigger, substation redundancy rating (NEI); only the PPA ceiling and the zoning trigger are contractual
“Specifically, it describes Susquehanna’s ultimate intent to physically transfer 960 MW of power to the transmission facilities of co-located load – but to be clear, the Third Co-Located Load ISA is not authorizing such a configuration.”
PJM filing, FERC docket ER24-2172-001 (9/3/2024) · pjm.com - cir-restoration148 MW148 MW of capacity interconnection rights restored to Susquehanna after the front-of-meter revision (PJM waiver Oct 29 2025; FERC approved; available for the 2027/28 BRA in Dec 2025) — the same 148 MW the 2024 amended ISA would have REDUCED at one unit; corroborated by three genuinely distinct parties (PJM's filing, the Independent Market Monitor's comments, Talen's 10-K). The regulatory point of the revision: the campus load goes into PJM's forecast and the generation goes back into the capacity market
“Following this revision, the load that was previously behind-the-meter was moved into PJM’s load forecast and, as a result, in October 2025, PJM filed a waiver request at the FERC to restore 148 MW of capacity interconnection rights (“CIRs”) to Susquehanna and add the corresponding generation back into the capacity auction.”
Talen FY25 10-K · sec.gov - campus-sale$650M$650M gross (the executed purchase agreement reads 'Purchase Price: $650,000,000'; $90M of it allocated to real property) — $350M at close (Mar 1 2024) + $300M escrow released Aug 23 2024 on zoning milestones ($200M at ≥540 MW, $100M at ≥960 MW; Salem Township approved May 2024). Book gain $324M. Downside never triggered: had the 540 MW zoning missed Mar 1 2025, AWS could revert the escrow and leave Talen a one-time right to repurchase the property for $355M — a strike price, not consideration. Amazon has never confirmed the price in any document on file; net proceeds are contested (see sale-net-proceeds)
“AWS Data Campus Sale. In March 2024, AWS purchased substantially all the assets related to the AWS Data Campus and certain other assets for gross proceeds of $650 million, of which $350 million were received at closing with the remaining $300 million held in escrow until August 2024.”
Talen FY25 10-K · sec.gov - original-ppa18the Mar-2024 PPA (superseded Jun 2025): up to 960 MW of behind-the-meter power, fixed-price commitments rising 120 MW a year (or faster at AWS's option), a one-time AWS option to cap at 480 MW, each step fixed-price for an initial 10-year term then renewable at a fixed margin over PJM prices; initial term 18 years + two 10-year extensions tied to the 2042/2044 licence renewals. The '10-year PPA' in two trade outlets is the per-step price window misread as the contract term; the '15-year' in Data Center Frontier sits in a sentence that also calls the fuel 'natural gas and renewable' (see contested ppa-term-reporting)
“The initial term of the AWS PPA is 18 years, with two 10-year extensions at AWS’s option.”
Talen FY24 10-K · sec.gov - plant-ownership90%Talen 90% (via Susquehanna Nuclear LLC, the operator) / Allegheny Electric Cooperative 10% — the co-owner states its own 10% on its site, the one genuinely independent check in the record. Two BWR units, licensed to 2042 and 2044. Talen's attributable share is its own 2,228 MW (Sept 2025) → 2,245 MW (FY25) — see contested plant-capacity
“We own and operate over 5.7 GW of low- and zero-carbon baseload generation, including a 90% interest in, the 2.5 GW Susquehanna facility, the seventh largest nuclear-powered generation facility in the U.S.”
Talen FY25 10-K · sec.gov - production-cost$27~$27/MWh all-in in 2025 on ~17 TWh (<$24/MWh in 2023 and 2024 on ~18 TWh/yr) — the only cost-side anchor in the record and the closest thing to a floor under the undisclosed PPA price; the 10-K calls the PPA's prices 'anticipated premium prices' and gives no number
“In 2025, we produced approximately 17 TWh of reliable, zero-carbon power from Susquehanna at a low all-in cost of approximately $27 per MWh, while also maintaining excellent safety and operational performance (when measured by standards adopted by the nuclear industry).”
Talen FY25 10-K · sec.gov - campus1,000the asset Amazon bought: 1,200 acres in Salem Township, Luzerne County (Amazon's own project page — this record follows it over the ~1,600-acre township rezoning overlay and the ~1,700-acre Blackstone/QTS assemblage nearby, which are different parcels), ~1,000 permanent jobs at full build (supersedes the 'up to 600' from the 2024 15-building rezoning coverage). The building count itself stays contested (see campus-buildings). Tier 2: a developer's project page, not a permit
“When fully constructed, Amazon anticipates that the campus will contain 20 data centers and support approximately 1,000 permanent jobs.”
Amazon Pennsylvania project page (amazoninnovationinpa.com) · amazoninnovationinpa.com
Contested figures 8 not reconciled — every position side by side, with its source and tier
Scope note what this record leaves to other records
Not this deal — carried elsewhere or not carried: Amazon's 'at least $20B' / 1,250-job Pennsylvania commitment (Jun 10 2025 — one coordinated Amazon + Governor announcement, statewide, tier 2; the $26B vs '>$40B' cumulative-investment pair on Amazon's own newsroom is unresolvable and also statewide); the campus's SRBC water permits (60,000 → 129,000 gpd consumptive use approved vs 277,000 requested; a 1.5 MGD 'average' vs 1.0 MGD 'peak' withdrawal quote is self-contradicting) and diesel-generator permits (72 in 2025, 84 in 2026 — sequential, same site; a 280-engine Falls Township permit is a different Amazon project); the Nautilus cryptomine's pre-sale PPAs (300/150/650 MW under the Coin and Data PPAs; TeraWulf's 50→100 MW share) — the buyout lives on the talen entity and the revised PPA ends the lease; the Independent Market Monitor's $7.3B–$29.4B data-center capacity-cost scenarios (one analyst, five numbers, none Talen-specific); Talen's Freedom/Guernsey ($3.8B) and Cornerstone ($3.45B) acquisitions (talen entity); FERC's Dec-18-2025 generic co-location order (193 FERC ¶ 61,217, docket EL25-49) and PJM's Feb-23-2026 compliance filing — the regime the front-of-meter structure now lives under, in which Amazon–Talen is evidence and precedent, not a party; the FY25 10-K's Item 3 summarises it. Adjacent facts that ARE sourced: the agreement 'supports the jobs of more than 900 employees' at Susquehanna (Jun-2025 release); the 2026/27 PJM BRA cleared at the $329.17/MW-day cap and Talen cleared 6,702 MW; a separate CFE-attribute agreement pays Talen for carbon-free energy sold to the grid, unquantified. Every deal figure — price, volume, term, revenue — is Talen-sourced; Amazon's only quantitative contribution to the deal terms in 120 documents is the '1,920.00' CSV line; its own campus page (1,200 acres, 20 data centers, ~1,000 jobs) and statewide totals are the rest.