OpenAI
The lab behind ChatGPT. It designs and trains frontier models but owns almost none of the computers it runs on — it rents compute at enormous scale from Microsoft, Oracle, Amazon, CoreWeave and others, which is why so many of the largest deals here trace back to it. Two of those landlords, Microsoft and Amazon, are also shareholders — Amazon through the $50B of Series C preferred it bought in 2026, a stake no filing has sized.
21 deals (20 T1 · 1 T2) · 17 flows on the money map
Where it standsprivate — from Epoch AI’s data on AI companies, which gathers the lab’s own statements and press reports
Deals 21
- Nov 16, 2026
- Nov 10, 2026 updated Nov 19
- Jul 22, 2026 updated Nov 21
- Jul 2026 updated Nov 21
- Jan 27, 2026 updated Nov 21
- Jan 14, 2026 updated Nov 19
- Dec 4, 2025
- Nov 3, 2025 updated Nov 21
Loans that finance its contracts 3
Loans to a company that serves OpenAI, paying for the equipment its contracts with OpenAI need. OpenAI is not a party to them: it neither lends nor borrows.
- Apr 30, 2026 updated Nov 19
- Jul 2025 updated Nov 21
- May 2024 updated Nov 20
Reported, not yet checked 1
- Mar 31
OpenAI says it closed a funding round with $122 billion in committed capital, valuing it at $852 billion after the round, anchored by Amazon, NVIDIA and SoftBank, with Microsoft also taking part.
Money in and out 17 ribbons
Who pays OpenAI (left), and whom it pays (right). Width is a rough size in $B, per year for multi-year deals.
← swipe to see the whole chart →
sourced deal · 9 of 17 estimated size · 8 of 17 full amount, no yearly rate · 7 of 17
As a table · 17 ribbons
Timeline 15 dated entries
- Nov 2026TensorWave: a six-year agreement for 457 MW of dedicated IT capacity on AMD MI455X GPUs, announced as part of the AMD partnership — about 8% of its 6 GW, by TensorWave's president; no value disclosed (T2 TensorWave release, Nov 16, quoting OpenAI's CTO for Compute) — tensorwave-openai
- Nov 2026TSMC's board approves buying up to US$500M of OpenAI preferred stock through TSMC Partners — ≤504,000 shares at an expected ~US$992, ≤0.04%; not closed, and no OpenAI statement on it (T1, TSMC's Taiwan filing) — tsmc-openai
- Aug 2026PORTS-Pike, Pike County OH: 17 × 20-yr leases for 8.0 GW-IT from SB Energy; Nvidia guarantees the landlord a declining minimum value on the first 4.25 GW-IT (pays the shortfall on an OpenAI default, $105B cap) and the site runs Nvidia compute exclusively for 20 yrs; OpenAI compensates Nvidia 'under a separate agreement' and indemnifies every dollar paid (T1 8-K + S-1)
- Jun 2026Jalapeño unveiled — first OpenAI-designed accelerator, nine-month tape-out (T1); Broadcom: silicon delivered, 1.3 GW of the 10 GW 'contractual' for 2027 (T2, call transcript)
- Apr 2026Microsoft amendment (Apr 27): Microsoft's license to OpenAI's models and products still runs through 2032 but is no longer exclusive; OpenAI may serve all its products on any cloud, with Azure its primary cloud and first to ship; OpenAI's revenue share to Microsoft runs through 2030 under a total cap (percentage and cap undisclosed), and Microsoft no longer pays one to OpenAI (T1 Microsoft post) — mo-partnership
- Apr 2026Withdraws from Stargate Norway and Stargate UK, both with Nscale (T1 Nscale S-1; of the UK, OpenAI says it will 'move forward' when conditions allow — 'being paused', per CNBC) — never past a ~10,000-GPU LOI in Norway, where Microsoft took the capacity (sg-nscale-europe)
- Feb 2026India: to be the first customer of TCS's HyperVault data-center business, beginning with 100 MW with an option (OpenAI: 'potential') to scale to 1 GW, under its Stargate initiative — no price, term, site or start date published (T1, both parties' announcements) — sg-tcs-india
- Feb 2026$30B of OpenAI's $110B round from Nvidia, by OpenAI's count — no Nvidia filing states the amount or shows it paid; the Sep-2025 up-to-$100B LOI is last mentioned in Nvidia's Nov-2025 10-Q (T1 OpenAI post + Nvidia 10-Q/10-K)
- Feb 2026Amazon: $50B of Series C ($15B + $35B parent-guaranteed commitment; funded in full by Q3 2026 — $13.7B Q2 + $21.3B after Jun 30) ↔ AWS agreement expanded by $100B / 8 yr on the Nov-2025 $38B base, ~2 GW Trainium ramping 2027, AWS the exclusive third-party cloud DISTRIBUTION provider for Frontier — a channel exclusivity on one product, not a compute exclusivity (T1: equity 8-K + ex-10.1 + Q1/Q2 10-Qs; $100B / 8 yr 10-Qs; ~2 GW Q1-2026 earnings ex-99.1; Frontier exclusivity Feb-27 joint release)
- Feb 2026SoftBank: $30B more for preferred shares at $730B pre-money, in three $10B tranches (Apr 1, Jul 1, Oct 1) — all paid, the first two with same-day draws on a $40B bridge loan, the third with BB+ notes at up to 9.75%; cumulative $64.6B for ~13% on SoftBank's own count (T1 SoftBank releases + Q1 FY2026 report) — sb-openai-equity
- Dec 2025SoftBank's $22.5B second closing completes the 2025 round: $41.0B = $30.0B from SoftBank + $11.0B from co-investors, not $41B of SoftBank money; SoftBank at $34.6B since Sep 2024, ~11% (T1 SoftBank release + Q3 FY2025 report) — sb-openai-equity
- Nov 2025AWS $38B multi-year agreement — 'continued growth over the next seven years', hundreds of thousands of GB200/GB300 GPUs via EC2 UltraServers, no count (T1 joint announcement; the 7-yr term is T2 — no filing states it)
- Oct 2025Recapitalization and a new Microsoft agreement (Oct 28): Microsoft holds ~27% of OpenAI Group PBC, valued at about $135B; OpenAI contracts $250B more of Azure, and Microsoft gives up its right of first refusal on OpenAI's computing (T1 Microsoft post + Q1 FY26 10-Q) — mo-partnership
- Oct 2025Broadcom 10GW ASICs · Samsung/SK memory LOIs (T1)
- Sep 2025Oracle: up to 4.5 GW on top of Abilene, a partnership the parties say 'exceeds $300 billion' over five years — no Oracle filing states it (T1 joint release; sg-oai-orcl) · Milam County, Texas named a SoftBank-led Stargate site (T1; sg-oai-sb)
Timeline entries carry no source field yet; some name one inline.
Notes in the record on OpenAI
ARR ~$25B (2026-02); 2025 cloud compute spend ~$16B/yr all providers — Epoch AI Companies, 2026-07 (tier 2)