Nvidia–IREN

Nvidia agreed to pay IREN about $3.4B over five years for AI chip capacity in Texas for its own use. It pays only after accepting delivery.

A deal between Nvidia, IREN, Dell

Why it matters

IREN describes Nvidia as both its cloud customer and its chip supplier. It says Nvidia agreed to pay about $3.4B for Nvidia's own AI work and IREN is buying the systems from Dell for about $1.6B. Separately, IREN counts Nvidia's rights to buy IREN shares as part of the cost of Nvidia's GPUs, with the rights vesting only as Nvidia delivers GPUs.

Tap a figure for the line in its source.

Nvidia gives IREN

  • over five years for dedicated GPU capacity for its internal AI and research work, in three tranches targeted for 2027; obligations begin only once capacity passes delivery acceptance
  • GPUs, under supply arrangements whose terms are not public; IREN adds the rights' $793.4M grant-date value to the cost of the GPUs it receives from Nvidia

IREN gives

  • of IREN's existing air-cooled data centers at Childress, Texas, filled with Nvidia Blackwell (B200) systems; the GPU count is not disclosed → Nvidia
  • for the B200 servers, storage, networking and services that serve the contract, paid within 30 days of each tranche's shipment; IREN guarantees the purchase → Dell
  • rights to buy IREN shares at $70.00 each until May 7 2031 — up to ~$2.1B if all are exercised — vesting in tranches as Nvidia supplies IREN GPUs, up to 600,000 of them → Nvidia

Dell gives IREN

  • the B200 GPU servers for three Childress buildings; the delivery dates are objectives only, with no penalty if Dell misses them

May 7, 2026 announced by Nvidia and IREN (joint release) and by IRENupdated Nov 21, 2026signed May 7 2026 disclosed by the parties

What happened

In May 2026, Nvidia agreed to rent computing capacity from IREN for its own internal AI and research work. IREN is a bitcoin miner turning itself into a GPU cloud provider. Nvidia agreed to pay about $3.4 billion over five years. The deal calls for about 60 megawatts of capacity in IREN's existing air-cooled halls in Childress, Texas. Three batches are targeted for 2027. To fill those halls, IREN is buying servers built on Nvidia's B200 chips from Dell, along with storage and networking, for about $1.6 billion. IREN pays within 30 days of each shipment. On May 7, the day Nvidia signed, IREN gave Nvidia rights to buy shares under separate arrangements for Nvidia to supply IREN with GPUs. Nvidia can buy up to 30 million new IREN shares at $70 each until 2031. That would bring in about $2.1 billion only if Nvidia exercises the rights in full. The rights unlock in steps only as Nvidia delivers GPUs to IREN, up to 600,000 of them. IREN values the rights at $793.4 million and includes that value in the cost of Nvidia's GPUs. The details come from IREN's filings and releases and the companies' joint release. Nvidia's SEC filings this year do not name IREN, and Dell's have not named it since mid-2025.

Sources 26 documents — 16 SEC filings · 5 company releases · 3 press reports · 1 research note · 1 other document

Research trail Found 324 documents and read 297 of them while checking this deal and related ones.

  1. SEC filingsec.gov
    States 7 figures: $3.4B contract value · investment rights · $2.1B right to invest · $793.4M fair value · rights accounting · two arrangements · up to 5 GW partnership scope
  2. SEC filingsec.gov
    States 4 figures: term · tranches · delivery acceptance · vesting GPUs
  3. SEC filingsec.gov
    States 2 figures: $1.6B dell purchase · dell for this contract
  4. GlobeNewswire · company releaseMay 7, 2026globenewswire.com
    States 60 MW capacity
  5. SEC filingsec.gov
    States $0.7B average annual revenue
  6. IREN · SEC filingsec.gov
    States dell systems
  7. GlobeNewswire · company releaseMay 7, 2026globenewswire.com
    States $2.1B nvidia release
  8. SEC filingsec.gov
    States $4800M nvidia warrants
  9. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  10. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  11. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  12. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  13. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  14. company releaseiren.com
    Cited by the record; no single figure is quoted from it.
  15. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  16. company releasenvidianews.nvidia.com
    Cited by the record; no single figure is quoted from it.
  17. company releasenvidianews.nvidia.com
    Cited by the record; no single figure is quoted from it.
  18. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  19. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  20. SEC filingefts.sec.gov
    Cited by the record; no single figure is quoted from it.
  21. SEC filingefts.sec.gov
    Cited by the record; no single figure is quoted from it.
  22. press report (archived copy)investing.com
    Cited by the record; no single figure is quoted from it.
  23. press reportdatacenterdynamics.com
    Cited by the record; no single figure is quoted from it.
  24. research notenewsletter.semianalysis.com
    Cited by the record; no single figure is quoted from it.
  25. press reportMay 27, 2026thestar.com.my
    Cited by the record; no single figure is quoted from it.
  26. other documentntrszibresearch.com
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: IREN Q3-FY26 10-Q (2026-05-08); FY26 10-K + ex-10.14/10.15 (2026-08-27); 8-K Item 1.01 + ex-99.1 (2026-05-26); Q3-FY26 results release ex-99.1 (2026-05-08) and call transcript (2026-05-11); IREN and Nvidia–IREN releases (GlobeNewswire, 2026-05-07); IREN blog (2026-05-22); Nvidia Q2 FY27 10-Q (2026-08-26) and 13F (2026-08-14); EDGAR full-text searches; Goldman via Investing.com (2026-05-27); IREN Q1-FY27 10-Q + results release ex-99.1 (2026-11-05) — earlier sources read 2026-11, Q1-FY27 documents read 2026-11 · as of Nov 2026

The evidence 18 sourced figures · 2 disputes

The record's headline Nvidia–IREN: a ~$3.4B five-year cloud contract for Nvidia's own AI and research work (three tranches targeted for 2027, within ~60 of IREN's air-cooled halls at Childress), ~$1.6B of Dell B200 systems bought to serve it, and rights for Nvidia to buy up to 30M IREN shares at $70 (up to ~$2.1B) that vest on its own GPU deliveries — $793.4M of grant-date value IREN adds to the cost of Nvidia's GPUs

Size
~$3.4B TCV through 2032 (five-year term; three tranches targeted for 2027; ~$0.7B average annual revenue on IREN's estimate) · within ~60 MW (gross) of air-cooled capacity at Childress · rights to up to 30,000,000 IREN shares @ $70.00 (up to ~$2.1B if fully exercised), vesting on up to 600,000 Nvidia GPU deliveries, expiring May 7 2031 — $793.4M grant-date fair value · ~$1.6B Dell purchase of B200 systems (May 19 2026)
When
May 7 2026 (cloud contract, securities purchase agreement, joint release; Q3-FY26 10-Q filed May 8) → May 19 2026 (Dell agreement for B200 systems; 8-K May 26) → Aug 27 2026 (FY26 10-K: the rights' $793.4M fair value; the Dell agreement filed) → 2027 (three tranches targeted; commissioning early 2027) → through 2032 (contract value) · the rights expire May 7 2031
Status
signed May 7 2026 (the cloud contract and the securities purchase agreement), announced the same day and described in the Q3-FY26 10-Q filed May 8; Dell agreement signed May 19 (8-K May 26; filed with the FY26 10-K, Aug 27); tranches targeted for deployment during 2027 (commissioning targeted for early 2027), so none had been delivered by the record's latest filings — the Q1-FY27 10-Q (Sep 30) names the 'NVIDIA Agreement' only among IREN's capital requirements and reports no delivery, and IREN's Nov 5 release says air-cooled retrofits 'continued in Childress and Mackenzie' without tying them to this contract; how many of the rights have vested, no filing says; the partnership's 5 GW is an intention
Structure
two arrangements with Nvidia, which IREN accounts for apart, and a Dell purchase to serve one of them: (1) the NVIDIA Cloud Services Agreement of May 7 2026 — IREN provides 'dedicated GPU services' at Childress over a five-year term in three tranches targeted for deployment during 2027, ~$3.4B through 2032, with GPU quantity and estimated monthly payments 'approximately equal across all three tranches', both sides' obligations starting only after 'a delivery acceptance process'; IREN's release calls it 'managed GPU cloud services', with orchestration software from Mirantis, which IREN has since acquired; (2) the systems — a Dell Marketing L.P. purchase agreement of May 19 2026 with IREN's subsidiary IE US Hardware 4 Inc. (ex-10.14, '(Non-Financed)' in its own title) and NCNR terms (ex-10.15) for ~$1.6B of B200-based GPU server products, storage, networking and services for three Childress buildings, paid within 30 days of each tranche's shipment and unconditionally guaranteed by IREN Limited; (3) the securities purchase agreement of May 7 2026 — rights for Nvidia to buy up to 30,000,000 IREN shares at $70.00 (up to ~$2.1B if fully exercised, subject to regulatory limits), vesting in tranches on the volume of GPUs Nvidia supplies IREN (up to 600,000) and expiring May 7 2031, granted 'in connection with' IREN's GPU-supply arrangements with Nvidia, whose terms are not public. IREN values the rights at $793.4M at grant and recognizes that value — in equity, and in the cost of the GPUs — as Nvidia's GPUs arrive, 'accounted for separately' from the cloud contract. Beside them, a strategic partnership 'intended to support' up to 5 GW of Nvidia DSX-aligned infrastructure across IREN's pipeline over time, which IREN's risk factors give as an example of relationships that are 'non-binding or subject to conditions'. Neither agreement with Nvidia is filed
Programme
Nvidia circular capital
Parties
Nvidia customer — ~$3.4B for capacity for its internal AI and research workloads; GPU supplier to IREN under arrangements not made public; holder of the rights to up to 30M IREN shares, which vest on its own GPU deliveries; its 2026 SEC filings name neither IREN nor the rights, and its 13F for Jun 30 2026 lists no IREN holding · IREN provider — runs the capacity in its existing air-cooled halls at Childress, buys the systems from Dell through IE US Hardware 4 Inc. and guarantees that purchase; grants the rights and adds their grant-date value to the cost of the Nvidia GPUs it receives · Dell systems vendor — Dell Marketing L.P. supplies the B200 GPU servers, storage, networking and services on 30-day post-shipment terms, with delivery dates that are objectives only; Dell's SEC filings since mid-2025 do not name IREN
Capital
the seller's own money or backing comes back as its sales
Record
disclosed / primary source · as of Nov 2026

Flows 6 as the record states them

  • Nvidia → IRENcompute-spend~$3.4B through 2032 over a five-year term, in three tranches targeted for deployment during 2027 with GPU quantity and estimated monthly payments approximately equal across them; obligations start only after delivery acceptance; ~$0.7B of average annual revenue on IREN's estimate
  • IREN → Nvidiacomputededicated GPU services ('managed GPU cloud services' in IREN's release) on air-cooled Blackwell (B200-based) systems within ~60 MW (gross, per IREN's co-CEO) of IREN's existing data centers at Childress TX; GPU count and IT load undisclosed
  • IREN → Dellgpu-purchases~$1.6B for B200-based GPU server products with storage, networking, ancillary equipment, integration services and warranties, for three Childress buildings; installments within 30 days of each tranche shipping; unconditionally guaranteed by IREN Limited
  • Dell → IRENsystemsB200-based GPU server products for three Childress data center buildings, with Dell ProSupport services; delivery dates are 'delivery objectives only'
  • IREN → Nvidiaequity-rightsrights to buy up to 30,000,000 ordinary shares at $70.00 (up to ~$2.1B if fully exercised, subject to regulatory limits), vesting in tranches on the volume of GPUs Nvidia supplies, up to 600,000; expiring May 7 2031; six-month lock-up from issue; $793.4M grant-date fair value
  • Nvidia → IRENgpu-supplyGPUs 'acquired from NVIDIA' under supply arrangements whose terms are not public; the rights' $793.4M grant-date value is capitalized into their cost as they are received. Whether GPUs that arrive inside Dell's systems count as 'supplied by NVIDIA' for vesting, no filing says

Resolved figures 18 each with the verbatim line from its document

  • contract-value$3.4B
    ~$3.4B — the total contract value of a five-year cloud services contract for Nvidia's 'internal AI and research workloads', in IREN's filed words; 'approximately $3.4 billion through 2032' in the Q3-FY26 10-Q (tranches). IREN's own estimate of the yearly rate, ~$0.7B of average annual revenue (average-annual-revenue), is the same figure spread over the five years ($3.4B ÷ 5 = $0.68B, editor's arithmetic). With Microsoft's ~$9.7B (iren-msft) it makes up 'a substantial majority of our contracted revenue' (10-K risk factors). The figure is IREN's alone: no Nvidia SEC filing of 2026 names IREN (nvidia-warrants)
    “In May 2026, we entered into a five-year cloud services contract with NVIDIA to support its internal AI and research workloads representing approximately $3.4 billion of total contract value.”
    IREN FY26 10-K (filed 2026-08-27) — MD&A, AI Cloud Services Contracts · sec.gov
  • term5 years
    five years, signed May 7 2026 — the 'NVIDIA Cloud Services Agreement', for dedicated GPU services at IREN's Childress, Texas campus. IREN described it in its Q3-FY26 10-Q, filed the next day (Part II, Item 5 'Other Information', and the subsequent-events note), not in an 8-K of its own, and neither the 10-Q nor the FY26 10-K attaches it. Beyond the tranches, the value and the acceptance process (tranches, delivery-acceptance), the 10-Q says it 'contains customary termination rights (including certain cure periods)' and 'service level commitments, service credits' among other customary provisions
    “On May 7, 2026, the Group entered into an agreement with NVIDIA Corporation (the “NVIDIA Cloud Services Agreement”), pursuant to which we will provide NVIDIA Corporation with dedicated GPU services at the Group’s data center facilities located in Childress, Texas over a five-year term.”
    IREN Q3-FY26 10-Q (filed 2026-05-08) — Part II, Item 5, NVIDIA Cloud Services Agreement · sec.gov
  • tranches3
    three tranches, targeted for deployment during 2027 'subject to extension in certain circumstances', of roughly equal size and monthly payment, with the value running 'through 2032' — consistent with a five-year term from deployment in 2027 (whether the term is counted per tranche, the 10-Q does not say). IREN's releases target the ramp 'from early 2027' (Q3-FY26 results release, furnished) and commissioning of the Dell systems 'for early 2027' (May 26 release, furnished). The 10-K (Aug 27 2026) restates the contract with no word on its progress, and the FY26 results release of the same day does not mention it
    “The GPU services will be made available to NVIDIA Corporation in three tranches targeted for deployment during 2027 (subject to extension in certain circumstances). The total contract value is approximately $3.4 billion through 2032. The GPU quantity and the estimated monthly payments are expected to be approximately equal across all three tranches.”
    IREN Q3-FY26 10-Q (filed 2026-05-08) — Part II, Item 5, NVIDIA Cloud Services Agreement · sec.gov
  • delivery-acceptance
    neither side's obligations start until delivered capacity passes acceptance — the trigger Microsoft's tranches have too (iren-msft). For this contract the filings state no delivery window, no prepayment and no specific right to end it for late delivery, only 'customary termination rights (including certain cure periods)'; whatever the agreement says on them is not public
    “The commencement of the parties’ obligations under the NVIDIA Cloud Services Agreement is subject to a delivery acceptance process.”
    IREN Q3-FY26 10-Q (filed 2026-05-08) — Part II, Item 5, NVIDIA Cloud Services Agreement · sec.gov
  • capacity60 MW
    ~60 MW of IREN's existing air-cooled data centers at Childress, on 'air-cooled Blackwell platform systems'. IREN's co-CEO calls it '60MW of gross data center capacity' (IREN blog, May 22 2026), and on the Q3-FY26 call (transcript on EDGAR, furnished) puts it inside the 250 MW of existing air-cooled capacity IREN plans to retrofit at Childress in 2027: 'Of that 250 megawatts, approximately 60 megawatts will be deployed to support the NVIDIA AI Cloud contract.' No IREN document gives the IT load; Goldman's ~45 MW is an assumed ratio (contested gpu-count). The CFO on the same call: the capex for retrofitting the air-cooled halls 'is pretty modest in the scheme of things'
    “The agreement will be serviced by air-cooled Blackwell platform systems to be deployed within approximately 60MW of IREN's existing data centers at its Childress, Texas campus.”
    IREN release, May 7 2026 (GlobeNewswire) · globenewswire.com
  • average-annual-revenue$0.7B
    ~$0.7B a year — IREN's estimate of what the contract adds once running, the share of its '$3.1bn' of 'ARR under contract' at May 2026 (with Microsoft's $1.9B and $0.5B at Prince George), which 'includes amounts that are not yet revenue-generating'; the May 26 release counts it again, ARR rising 'from $3.7bn to $4.4bn' once the contract is commissioned. IREN's own estimate in its own release, furnished, not filed (tier 1, read from its own copy on EDGAR, as iren-msft's furnished releases are), consistent with the filed ~$3.4B over five years
    “ARR under contract of $3.1bn represents expected $1.9bn average annual revenue under Microsoft contract, expected $0.7bn average annual revenue under NVIDIA contract, plus $0.5bn ARR under contract from GPU deployments at Prince George.”
    IREN Q3-FY26 results release, 8-K ex-99.1 (furnished 2026-05-08), note 3 · sec.gov
  • dell-purchase$1.6B
    ~$1.6B, signed May 19 2026 by IREN's subsidiary IE US Hardware 4 Inc. with Dell Marketing L.P., payable tranche by tranche within 30 days of shipment and unconditionally guaranteed by IREN Limited — the subsidiary is now IE US Hardware 4 LLC ('f/k/a IE US Hardware 4 Inc.' in the Q1-FY27 10-Q); the agreement (ex-10.14, '(Non-Financed)' in its title) and its NCNR terms (ex-10.15) are filed with the FY26 10-K. The furnished release scopes the price: 'inclusive of GPUs, servers, storage, networking, ancillary equipment, integration services, and warranties, with payment terms structured on a post-shipment basis', and says IREN 'is advancing GPU financing in connection with the agreement' — no financing tied to it is on the record yet. Dell's other figure-bearing purchase agreements with IREN — ~$5.8B for Microsoft (iren-msft), ~$2.3B + ~$1.2B in March 2026 and, new in the Q1-FY27 10-Q, ~$6.7B of purchase orders of Sep 28 2026 (IE US Hardware 5 and 6; deliveries from the second half of calendar 2027; no customer named) — are the dell entity's, not this deal's. Those orders do ride on this agreement: each 'adopts, with applicable modifications, the terms of' this May 19 Purchase Agreement, which 'contains customary representations, warranties, covenants, indemnities and termination rights', so its terms now also underlie the September orders
    “On May 19, 2026, IE US Hardware 4 Inc. (“IE US Hardware”), a wholly owned subsidiary of IREN Limited (the “Company”), and Dell Marketing L.P. (“Dell”) entered into purchase documentation (the “Dell Purchase Agreement”) pursuant to which Dell will supply to IE US Hardware GPUs and ancillary products and services (“GPUs”) for an aggregate purchase price of approximately $1.6 billion payable in installments within 30 days of each tranche shipping.”
    IREN 8-K Item 1.01 (filed 2026-05-26) — Dell Purchase Agreement · sec.gov
  • dell-for-this-contract
    the filing that ties the Dell systems to this contract — 'managed services AI cloud contract' is the 8-K's name for it, beside the 10-Q's 'dedicated GPU services' (contested service-model). IREN's co-CEO, in the furnished May 26 release: 'Our relationship with Dell ensures access to hardware at the scale and speed the market demands'
    “The GPUs will be deployed at the Company’s Childress, Texas campus to service its previously announced $3.4 billion managed services AI cloud contract.”
    IREN 8-K Item 1.01 (filed 2026-05-26) — Dell Purchase Agreement · sec.gov
  • dell-systems
    what Dell ships: 'B200 based GPU server products' — the Blackwell model the releases leave unnamed — for three Childress data center buildings, one per tranche of the contract on our reading (the filing does not say so); the purchase order is 'CHD_NV_DELL_B200_051526'. Quantities, dates and the order value are redacted, and the dates bind no one: 'The listed Delivery Dates are delivery objectives only, and no penalties, liquidated damages, credits, or other remedies shall apply due to Dell’s failure to meet the Delivery Dates.' Dell supports the systems under 'ProSupport One for Data Center'
    “Dell shall use commercially reasonable efforts to deliver the quantity of B200 based GPU server products (the “GPU Server Products”) to the Customer location listed in the Order by the final shipment end delivery date (the “Delivery Date”) associated with three Customer data center buildings, each as outlined in the table below (each, a “Building”) and accelerate the Delivery Dates where possible.”
    Dell NCNR and Supplemental Terms Agreement, May 19 2026 — FY26 10-K ex-10.15, §3.A Delivery Dates for the Order · sec.gov
  • investment-rightsup to 30,000,000
    up to 30,000,000 IREN ordinary shares at $70.00 each, granted May 7 2026 'in connection with' IREN's arrangements with Nvidia 'for the supply of GPUs' — sold under a securities purchase agreement as a private placement, 'for aggregate gross proceeds of up to approximately $2.1 billion (if fully exercised and subject to any regulatory limitations)' (Q3-FY26 10-Q). Against the 394,058,648 shares outstanding on Aug 14 2026 (10-K cover) that is 7.6% before exercise and 7.1% of the enlarged count (editor's arithmetic; 7.9% / 7.3% on the Jun 30 balance-sheet count of 380,193,608 — analysts' published figures differ by the count they use). The 424B7 of Aug 4 2026 lists them among shares 'issuable to NVIDIA Corporation'. The FY26 EPS note lists 4,520,548 Investment Rights among the anti-dilutive securities it leaves out — the 30M weighted for the 55 days from grant to Jun 30 (editor's arithmetic), not a vested count. The Q1-FY27 10-Q's EPS note lists 'Investment Rights 30,000,000' among the anti-dilutive securities for the whole quarter — the same 30M, now outstanding for all three months — and, like the 10-K, gives no vested count
    “In connection with its arrangements with NVIDIA Corporation (“NVIDIA”) for the supply of GPUs, on May 7, 2026 the Group granted NVIDIA rights to acquire up to 30,000,000 of the Company’s Ordinary shares at an exercise price of $70.00 per share (the “Investment Rights”).”
    IREN FY26 10-K (filed 2026-08-27) — Note 24, Investment Rights · sec.gov
  • vesting-gpus600,000
    the rights vest in tranches only as Nvidia's GPUs arrive — 'based on the volume of GPUs supplied by NVIDIA to the Group' (10-K), 'certain volumes of deliveries of up to 600,000 NVIDIA GPUs' (10-Q); the thresholds per tranche are not public. They expire May 7 2031, and for six months from issue Nvidia may not sell or pledge the rights or the shares. IREN's own phrasings differ on what counts: the co-CEO on the call, 'only vest as NVIDIA GPU infrastructure is deployed across IREN campuses and only fully vest upon deployment of 600,000 GPUs'; his blog, 'tied to the delivery of up to 600,000 NVIDIA GPUs across our platform'. None says whether GPUs inside Dell's systems (dell-systems) count. For scale: IREN put its fleet at ~150,000 GPUs installed or on order at Mar 31 2026 (Q3-FY26 10-Q)
    “The Investment Rights will be exercisable in tranches that vest based on achieving certain volumes of deliveries of up to 600,000 NVIDIA GPUs, and may be exercised by the Purchaser at any time and from time to time on or after the issue date, subject to certain conditions, and will expire on May 7, 2031.”
    IREN Q3-FY26 10-Q (filed 2026-05-08) — Part II, Item 5, NVIDIA Private Placement · sec.gov
  • right-to-invest$2.1B
    the '$2.1 billion' is the most IREN would receive if Nvidia exercised every right at $70.00 (30,000,000 × $70.00 = $2.1B, editor's arithmetic) — a conditional right to invest, gated on GPU deliveries and regulatory conditions, not money paid. IREN's co-CEO calls it 'The $2.1 billion NVIDIA investment' and says it is 'not a passive financial investment'; trade press wrote that Nvidia 'will also invest up to $2.1bn in Iren, funding the deployment of up to 5GW' (DCD), which no filing supports. Not the $2,100M of notes in IREN's Microsoft financing (iren-msft) — the same number twice.
    “Pursuant to a securities purchase agreement, we granted NVIDIA the right to invest up to $2.1 billion in Ordinary shares, subject to delivery of up to 600,000 GPUs and certain regulatory conditions.”
    IREN FY26 10-K (filed 2026-08-27) — Recent Developments, NVIDIA Strategic Partnership · sec.gov
  • fair-value$793.4M
    $793.4M at grant (Black-Scholes: 67.5% volatility, a five-year term, a 3.96% risk-free rate, a 15% discount for lack of marketability, no dividend), classified in stockholders' equity and 'not remeasured following the grant date'. The value is recognized as Nvidia's GPUs arrive (rights-accounting); the FY26 equity statement carries no line for the rights, so little or none of it had been recognized by Jun 30 2026 — our reading, as the 10-K gives no amount
    “The grant-date fair value of the Investment Rights, determined using a Black-Scholes option-pricing model, was approximately $793.4 million.”
    IREN FY26 10-K (filed 2026-08-27) — Note 24, Investment Rights · sec.gov
  • rights-accounting
    the rights are part of what IREN pays for Nvidia's GPUs: their grant-date value goes into the GPUs' cost, unit by unit as they arrive, so it is depreciated with the hardware rather than expensed. The terms of the supply arrangements themselves — volumes, prices, whether they run directly or through OEMs such as Dell — are not public
    “This amount will be capitalized as part of the cost of the GPUs acquired from NVIDIA and is recognized as the underlying GPUs are received by the Group, on a per-unit basis.”
    IREN FY26 10-K (filed 2026-08-27) — Note 24, Investment Rights · sec.gov
  • two-arrangements
    the circle in IREN's own words: Nvidia is a GPU supplier on one side of IREN's books and a customer on the other, and IREN keeps the two apart. The risk factors add that IREN 'may consider entering into similar strategic arrangements with counterparties, including customers and OEMs, in the future'
    “The Investment Rights relate to the Group’s supply arrangements with NVIDIA and are accounted for separately from the Company’s cloud services agreement with NVIDIA, under which NVIDIA is a customer of the Group.”
    IREN FY26 10-K (filed 2026-08-27) — Note 24, Investment Rights · sec.gov
  • nvidia-release$2.1B
    Nvidia's own words, in the joint release it issued on May 7 2026 (GlobeNewswire, 'Source: NVIDIA'): the rights, the 'up to 5 gigawatts' partnership, and IREN's '2-gigawatt Sweetwater campus in Texas' as the expected 'flagship deployment for NVIDIA’s DSX architecture'. It does not mention the cloud contract. Nvidia's newsroom has named IREN since: among the cloud partners deploying its DSX platform (May 31 2026), and among the partners of an Australian buildout (Sep 9 2026), where IREN's co-CEO speaks of 'our 800-megawatt Bundey campus in South Australia' — not of this contract
    “As part of the partnership, IREN issued to NVIDIA a five-year right to purchase up to 30 million shares of ordinary stock at an exercise price of $70 per share, resulting in a right to invest up to $2.1 billion, subject to certain conditions including regulatory.”
    Nvidia–IREN joint release, May 7 2026 (GlobeNewswire; issued by Nvidia) · globenewswire.com
  • partnership-scopeup to 5 GW
    up to 5 GW of Nvidia DSX-aligned infrastructure 'over time' across IREN's pipeline — an intention with no volumes, capex or prices, which the 10-K's risk factors file among relationships that are 'non-binding or subject to conditions': 'the scope, timing and volume of any deployments under this partnership are subject to a number of factors, and there can be no assurance as to the extent to which such deployments will occur.' A different 5 GW from IREN's ~5 GW of secured power, the same number twice (the iren entity)
    “In May 2026, we entered into a strategic partnership with NVIDIA intended to support the deployment over time of up to 5GW of NVIDIA DSX-aligned AI infrastructure across our global data center pipeline.”
    IREN FY26 10-K (filed 2026-08-27) — Recent Developments, NVIDIA Strategic Partnership · sec.gov
  • nvidia-warrants$4800M
    Nvidia's side, unnamed: in its quarter to Jul 26 2026 — the one IREN's May 7 grant falls in — Nvidia 'received warrants to purchase shares of publicly-traded common stock with terms of three to five years', $4,800M in notional value at quarter-end (nil at Jan 25 2026), carried at a Level 3 fair value of $824M, 'with the corresponding benefit substantially deferred'. It names no issuer. IREN's 30,000,000 × $70.00 = $2,100M would be 44% of that notional (this record's arithmetic); one reading attributes the rest to Corning's warrant, which Nvidia does not state either. Nor do the 10-Q's two cloud-commitment lines name a provider: $29B of 'Cloud service agreements' at Jul 26 2026 ('the cloud infrastructure to support our research and development of our open models'), and $36B of 'AI cloud agreements' under a business model Nvidia 'introduced' that quarter; whether either holds this contract, the 10-Q does not say. Nvidia's 13F for Jun 30 2026 lists eight holdings and no IREN, and an EDGAR full-text search finds no 2026 Nvidia filing that names IREN — nor a Dell filing since Jun 2025
    “Public company warrants $ 4,800 $ —”
    Nvidia Q2 FY27 10-Q (filed 2026-08-26) — Note 8, Derivative Financial Instrument Notional Values · sec.gov

Contested figures 4 not reconciled — every position side by side, with its source and tier

gpu-count2 positions, side by side
~26,000 B200 GPUs — Goldman Sachs's estimate (analyst Michael Ng), relayed by Investing.com in an article it says was 'generated with the support of AI and reviewed by an editor': the 60 MW taken as ~45 MW of critical IT at an assumed PUE of ~1.3, ÷ 14 kW per DGX B200 rack × eight GPUs per rack; at ~$500,000 a rack it is 'consistent with the disclosed $1.6 billion purchase price'. Every input but the 60 MW and the price is assumed Goldman Sachs via Investing.com, May 27 2026 (Wayback)
undisclosed — IREN's chief commercial officer on the Q3-FY26 call: 'we haven't disclosed the specific amount of GPUs'; the Dell order (ex-10.15) redacts the quantity per building; the 10-Q says only that the GPU quantity is expected to be 'approximately equal across all three tranches'. No IREN document states a count or the IT load IREN Q3-FY26 call (transcript furnished on EDGAR); Dell NCNR ex-10.15; Q3-FY26 10-Q
service-model2 positions, side by side
dedicated GPUs — 'dedicated GPU services' at Childress (Q3-FY26 10-Q). The 10-K's lease note classifies agreements 'to provide customers with access to dedicated GPU computing capacity' as operating leases with IREN as lessor (~$11.4B of lease contract value at Jun 30 2026, beside $5.1B of RPO), but names no contract; the Q1-FY27 10-Q puts the two at ~$13,957M ('remaining aggregate contracted value of lease arrangements') and $6,347M at Sep 30 2026 and does name one contract among its lease-accounted arrangements — the Microsoft Agreement — and none of this one, in either its lease or its revenue-contract lines, so whether this one is in them is still not said IREN Q3-FY26 10-Q; FY26 10-K Note 4; Q1-FY27 10-Q Note 4 and MD&A
a managed service — 'managed GPU cloud services for its internal AI and research workloads, including orchestration and cluster management software in collaboration with Mirantis' (IREN release, May 7); 'managed services AI cloud contract' (8-K, May 26); 'this is a managed services deployment' (IREN's chief commercial officer on the call) IREN release (May 7 2026); 8-K Item 1.01 (filed 2026-05-26); Q3-FY26 call (transcript furnished on EDGAR)

Scope note what this record leaves to other records

NOT this record (carried elsewhere or not carried): IREN's other Dell agreements — Nov 2025's ~$5.8B for Microsoft (iren-msft) and Mar 4 2026's ~$2.3B (Dell Canada) + ~$1.2B (Dell USA) for 'over 50,000 NVIDIA B300 GPUs', bought ahead of any named customer ('as customer agreements progress') — Dell Financial Services' $199.8M lease of Nov 2025 and the ~$6.7B of Dell purchase orders of Sep 28 2026 (IE US Hardware 5 and 6, which adopt this record's May 19 agreement's terms; Q1-FY27 10-Q) → the dell entity; the Microsoft contract, its $3,645M financing, its exact TCV and the 96% → iren-msft; IREN's ARR constructs (which the May and August figures include or exclude Nvidia's ~$0.7B), GPU-fleet counts, secured power, the $2.4B Mackenzie financing, cost-of-debt definitions, Mirantis (~$625M at signing, ~$544M at closing) and the converts (19.4553 conversion rate) → the iren entity or not carried here; Nvidia's company-wide figures in the same 10-Q (the $29B and $36B cloud commitments, named in nvidia-warrants only as the unnamed lines; a $3.5B maximum exposure on its lease guarantees; $25B of equity-investment commitments) — none attributable to IREN → no cell of their own; ACIE revenue ($32,196M recast) → nowhere. Not carried here: per-MW prices ($11.3–11.7M per gross MW-year; $18.2–18.7M per IT MW-year at an assumed 1.6 ratio) and IT-load estimates (~37.5–45 MW), analysts' arithmetic on IREN's two inputs; dilution percentages on other share counts (7.3%–9.0%); the after-hours move on May 7 (+9% to +27% in different outlets) and JPMorgan's $46 target. Not adopted: DCD's 'funding the deployment of up to 5GW'; SemiAnalysis's 'the $2.1B investment from NVIDIA'; The Star's 'contract with Dell' for the $3.4B (the counterparty is Nvidia); ntrszib's $10.9B of Dell purchases tied to the Mar 31 2026 fleet count (the sum includes the May order); the peer figures listed under IREN (AMD–Core Scientific's warrant at $23.47, Nvidia's $2.0B in CoreWeave at $87.20, Nscale's $1.2B, Lambda's $1.5B, Sharon AI's $4.9B). Kept off service-model: the same SemiAnalysis review (ClusterMAX 3.0) recommends 'that IREN stop pretending to offer managed clusters and inference endpoints in public marketing and investment materials, and focus on their bare metal offerings' — a view of IREN's cloud and its marketing in general, not of this contract, so it sits on neither side.