Zone Frontier–Cerebras, Minnesota

Cerebras has signed for all 40 of IT load at a data center being built in Minnesota, for ten years at about $800M as Zone Frontier puts it; Zone took 79% of the landlord after the contract was signed and says it needs project debt, not yet committed, to fund the build.

A deal between Cerebras, Zone Frontier

Why it matters

Cerebras's 40 in Minnesota depends on a landlord whose 79% owner came in after the contract was signed: Zone Frontier, a former cleaning-products company, joined the developer whose company had signed Cerebras. It values the ten years at about $800M, yet its own 10-Q doubts it can pay for the build without project debt that is not yet committed.

Tap a figure for the line in its source.

Zone Frontier gives Cerebras

  • of critical IT load at a Minnesota campus designed to Tier 3 standards, all of it pre-leased to Cerebras, in five service orders of different sizes; ten years, plus two 10-year renewal options for Cerebras. The provider is Monarch Data Operations, owned by a venture Zone holds 79% of
  • daily credits off the monthly charges when a milestone is missed; the other way, an early-delivery incentive for the venture, its amount not filed
  • a say over the landlord's money: Zone's funding commitment must be on terms Cerebras finds reasonably satisfactory, and no company on Cerebras's list of competitors may lend to or invest in the project

Cerebras gives Zone Frontier

  • disputedover the initial ten years by Zone's estimate in its 8-K (its later words: 'contracted value', 'over $800 million'); more than $3B if Cerebras exercises both renewals. Monthly charges, part prepaid, and one-time charges, with no rate or amount filed

Jul 29, 2026 announced by CleanCore (now Zone Frontier), naming Cerebras disclosed by the parties

What happened

In June 2026, Cerebras signed a ten-year agreement for space and power in a data center being built in Minnesota. Cerebras makes -scale AI chips. The agreement covers 40 megawatts of IT load, the power for Cerebras's own equipment. The whole campus is pre-leased to Cerebras. The provider is Monarch Data Operations, a company tied to the site's developer. In July, Zone Frontier, then called CleanCore Solutions, formed a joint venture with that developer. Zone holds 79% and the developer 21%. Zone had just sold the last of its Dogecoin, and it sold its cleaning-products business in October. Cerebras consented to the new owner in a letter Zone later filed. Zone estimates the first ten years at about $800 million. It later called that figure contracted, and its annual report says over $800 million. Cerebras can renew twice, for ten years each. If Cerebras uses both, Zone puts the total above $3 billion. The contract itself is not filed, so no rate is public. Cerebras pays monthly charges, part in advance, and one-time charges. It gets daily credits when a milestone is late. Zone has committed up to $500 million to the venture. If it falls short, its stake is diluted. It had paid in about $73 million by September 30. In August it had counted about $140 million as funded or committed. The venture's initial approved budget is $479 million. City records for what appears to be the site, in Glencoe, set a floor of $459.9 million for its first phase. Zone says its cash will not cover the next year of building without project debt. In November that debt was in diligence and not yet committed. In July, Zone expected the full capacity in the first quarter of 2027. Its later filings moved that to the second quarter. They expect revenue in the first quarter, or, in one September release, the first half. Cerebras's own filings never name the site or Zone.

Sources 19 documents — 12 SEC filings · 4 other documents · 2 company releases · 1 regulatory filing

Research trail Found 113 documents and read 103 of them while checking this deal and related ones.

  1. SEC · SEC filingsec.gov
    States 6 figures: going concern · project debt · landlord · 40 MW schedule nov · $53.3M build status · land
  2. SEC · SEC filingsec.gov
    States 5 figures: 40 MW agreement · 40 MW pre existing · more than $3B renewal value · 79% zone stake · 20 MW energized
  3. SEC · SEC filingsec.gov
    States 4 figures: nrc as equity · rfs credits · direct competitor · $500M capital commitment
  4. SEC · SEC filingsec.gov
    States 3 figures: service orders · charges · early delivery incentive
  5. SEC · SEC filingsec.gov
    States 2 figures: funding commitment · 100% opco contributed
  6. SEC · SEC filingsec.gov
    States csa date
  7. SEC · SEC filingsec.gov
    States exclusive
  8. glencoemn.org · other documentJul 2026glencoemn.org
    States site
  9. SEC · SEC filingsec.gov
    States first announcement
  10. SEC · SEC filingsec.gov
    States letter of intent
  11. SEC filingsec.gov
    States cerebras filings silent
  12. revolvelabs.ai · other documentrevolvelabs.ai
    States revolve site
  13. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  14. company releasezonefrontier.com
    Cited by the record; no single figure is quoted from it.
  15. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  16. company releasezonefrontier.com
    Cited by the record; no single figure is quoted from it.
  17. other documentAug 2026glencoemn.org
    Cited by the record; no single figure is quoted from it.
  18. other documentrevolvelabs.ai
    Cited by the record; no single figure is quoted from it.
  19. regulatory filingcdn.misoenergy.org
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: CleanCore 8-K Items 1.01/8.01 + ex-99.1 (2026-07-29) and 8-K Item 8.01 (2026-06-08); Zone Frontier 10-Q (2026-11-18) with Ex. 10.6–10.9, FY2026 10-K (2026-09-28), August prospectus (424B5), releases and updates of Aug 13, Sep 29 and Oct 30 2026; City of Glencoe council packet and minutes (Jul 20 2026); Revolve Labs' Glencoe page and presentation (Sep 8 2026); MISO expedited project review (Dec 2 2025); Cerebras Q3 2026 10-Q (read 2026-11) · as of Nov 2026

The evidence 27 sourced figures · 8 disputes

The record's headline Zone Frontier–Cerebras, Minnesota: a ten-year colocation agreement for all 40 of IT load — ~$800M as Zone puts it, more than $3B if Cerebras exercises two 10-year renewal options — signed by the developer's company before Zone Frontier, a former cleaning-products company, took 79%; Zone's 10-Q doubts it can fund the build without project debt

Size
40 MW critical IT · 10-yr initial term + two 10-yr options · ~$800M over the initial term by Zone's figures ('estimated' in its 8-K, later 'contracted' and 'over $800 million'; more than $3B if both renewal options are exercised) · under construction: revenue expected in Q1 2027 or the first half, as Zone's statements differ
When
May 7 2026 CleanCore's non-binding letter of intent with a development partner for a 'Midwest Project' (disclosed Jun 8, naming neither Cerebras nor Minnesota) → Jun 10 Colocation Services Agreement, Monarch Data Operations–Cerebras → Jul 23 joint-venture agreements, Zone 79% → Jul 25 the provider's letter asking Cerebras's consent to the change of control → Jul 29 announced by CleanCore, naming Cerebras (8-K + release) → Aug 13 Zone pays off the site's mortgage; the deed transfer still in process at Nov 18 → Aug 31 CleanCore renamed Zone Frontier → Sep 30 ~$73.3M of Zone's equity funded → Oct 30 project debt in confirmatory diligence → Nov 18 10-Q: going-concern doubt; revenue expected from Q1 2027, the full 40 MW by Q2 2027 → a ten-year initial term (start not filed), + two 10-year renewal options
Status
agreement dated Jun 10 2026 · joint venture closed Jul 23 (10-Q) · announced Jul 29 · under construction (10-Q), no revenue yet: ~20 MW of utility power energized at Jul 29; revenue expected from Q1 2027 and the full 40 MW by Q2 2027 (10-Q, Nov 18) · project-level debt in confirmatory diligence, not committed, and going-concern doubt in Zone's 10-Q · land deed still being transferred to the venture at Nov 18 · Cerebras's filings never name Zone, CleanCore, Monarch or Minnesota
Structure
a Colocation Services Agreement dated Jun 10 2026 between Monarch Data Operations, LLC (the provider, 'OpCo', then an affiliate of the developer) and Cerebras Systems Inc. (the client), for 'the baseline 40 MW of critical IT load' at a Minnesota campus designed to Tier 3 standards and 100% pre-leased to Cerebras, in five service orders of varying size, each with milestone dates the agreement's Exhibit A sets (not filed). Initial term ten years; Cerebras holds two 10-year renewal options. Cerebras pays monthly recurring charges under each service order, some prepaid, and one-time non-recurring charges; a missed milestone earns it Daily RFS Credits (§2.6.1–2.6.2), early delivery earns the venture an Early Delivery Incentive (§2.7); no rate, total or amount is filed. On Jul 23 2026 the developer contributed all of OpCo to Monarch SPV HoldCo LLC, 79% Zone Frontier (then CleanCore) and 21% the developer, with Cerebras's consent to the change of control (Ex. 10.9). Zone commits up to $500M ($250M equity + $250M additional, called through February 2027) against a $479M approved budget; a shortfall costs it dilution only. Zone must execute a Funding Commitment the agreement defines, on terms reasonably satisfactory to Cerebras, and none of Cerebras's listed Direct Competitors may lend to or invest in the project. The agreement itself is not filed
Programme
Zone Frontier–Cerebras
Parties
Cerebras the client: takes the campus's whole 40 MW of critical IT load under five service orders; pays monthly recurring charges, some prepaid, and one-time non-recurring charges (no amounts filed); earns daily credits when milestones are missed; holds two 10-year renewal options. It consented to Zone's control of the provider (Ex. 10.9) and has a say over Zone's funding commitment and the project's backers. Its filings never name Zone, CleanCore, Monarch or Minnesota · Zone Frontier the landlord's majority owner: holds 79% of Monarch SPV HoldCo LLC, which owns the provider, Monarch Data Operations, LLC, and consolidates it; commits up to $500M of capital (about $73.3M funded at Sep 30 2026) and is raising the project debt. Called CleanCore Solutions until Aug 31 2026, it left cleaning products and its Dogecoin treasury in 2026. The 21% partner, which develops and runs the project, is unnamed in every filing (partner-identity)
Record
disclosed / primary source · as of Nov 2026

Flows 2 as the record states them

  • Cerebras → Zone Frontiercolocation-feesmonthly recurring charges under each of five service orders, some prepaid, and one-time non-recurring charges, as the venture's papers name them; no rate, total or schedule is filed. ~$800M over the initial ten years by Zone's estimate in the filed 8-K ('contracted value' in its Aug 13 update, 'over $800 million' in its 10-K: initial-value); more than $3B if both 10-year renewals are exercised. Paid to Monarch Data Operations, LLC, which Zone consolidates at 79%; the one-time charges count as Zone's equity in the venture (nrc-as-equity)
  • Zone Frontier → Cerebrascapacitythe baseline 40 MW of critical IT load at a Minnesota campus designed to Tier 3 standards, 100% pre-leased to Cerebras, in five service orders of varying size: ~20 MW of utility power energized at Jul 29 2026, supporting an initial 15 MW; the full 40 MW expected by Q2 2027 (10-Q). Daily ready-for-service credits if milestones are missed; two 10-year renewal options

Resolved figures 27 each with the verbatim line from its document

  • agreement40 MW
    a 10-year Colocation Services Agreement for 'the baseline 40 MW of critical IT load', the power for Cerebras's own equipment, at a Minnesota campus designed to Tier 3 standards and '100% pre-leased to Cerebras'. The provider is Monarch Data Operations, LLC ('OpCo'), wholly owned by the venture Zone Frontier, then CleanCore, holds 79% of (zone-stake). The agreement itself is not on file: the 8-K said copies would be filed with a 10-Q, and the Nov 18 10-Q files the venture's agreements and Cerebras's consent (csa-date) but not the agreement. Cerebras's filings never name it (cerebras-filings-silent)
    “OpCo is party to a 10-year Colocation Services Agreement with Cerebras, pursuant to which OpCo will provide Cerebras with colocation services with respect to the baseline 40 MW of critical IT load, with the data center campus designed to Tier 3 standards and 100% pre-leased to Cerebras”
    CleanCore 8-K, Item 1.01 (filed 2026-07-29) · sec.gov
  • pre-existing40 MW
    Zone bought into a contract already signed: the venture was formed for the campus 'including a baseline 40 MW compute lease deployment under a pre-existing colocation services agreement between OpCo and Cerebras'. The developer's affiliate signed with Cerebras on Jun 10 2026 (csa-date) and contributed all of OpCo to the venture at closing (opco-contributed). Zone's own release has CleanCore 'entered into' the agreement (first-announcement), and its August prospectus 'also entered into a colocation services agreement with Cerebras'; the 8-K's account is the one followed here
    “to form and capitalize a joint venture for the purpose of financing, developing, constructing, commissioning, owning, operating, and commercializing an approximately 55 MW data center facility located in Minnesota (the “Project”), including a baseline 40 MW compute lease deployment under a pre-existing colocation services agreement between OpCo and Cerebras Systems Inc.”
    CleanCore 8-K, Item 1.01 (filed 2026-07-29) · sec.gov
  • csa-date
    the agreement's own date and parties: dated Jun 10 2026, between Monarch Data Operations, LLC ('Provider') and Cerebras Systems Inc. ('Client'), with service orders and a 'Guaranty' whose guarantor is unnamed. The provider's letter, dated Jul 25 2026 and filed as the 10-Q's Ex. 10.9, asks Cerebras to consent to the 'Change of Control' (§18.3) of Zone's taking 79% of the provider's new parent, and to waive the 30-day notice; it takes effect only when the transaction closes. Cerebras's signature block shows '/s/' with no name or date. The letter calls the transaction proposed two days after the Jul 23 closing the 10-Q reports; no document explains the order
    “Re: Consent to Change of Control under the Colocation Services Agreement, dated June 10, 2026, by and between Monarch Data Operations, LLC (“Provider” or “we”) and Cerebras Systems Inc. (“you” or “Client”)”
    Zone Frontier 10-Q Ex. 10.9, consent to change of control under the Colocation Services Agreement (letter of 2026-07-25; filed 2026-11-18) · sec.gov
  • exclusive
    one tenant: 'leased exclusively to one customer, Cerebras, in a binding ten year contract' (FY2026 10-K); the 10-Q, 'exclusive pre-leased occupancy'. The 8-K calls the agreement colocation services; whether Cerebras books it as a lease is not stated (cerebras-filings-silent)
    “The Minnesota campus is leased exclusively to one customer, Cerebras, in a binding ten year contract with the option for two addition ten-year renewal periods.”
    Zone Frontier FY2026 10-K (filed 2026-09-28), Business — Sales, Marketing, and Customers · sec.gov
  • renewal-valuemore than $3B
    more than $3B in all if Cerebras exercises both of its two 10-year renewal options: a floor ('more than'), the initial term included, on options no one has exercised. Renewal pricing is not disclosed, so no document shows how it is reached; the release: 'the potential to exceed $3 billion, including renewal terms'. Not drawn
    “The initial 10-year term of the Colocation Services Agreement has an estimated contract value of approximately $800,000,000, and Cerebras holds two additional 10-year renewal options that, if exercised, would bring the aggregate potential contract value under the Colocation Services Agreement to more than $3,000,000,000.”
    CleanCore 8-K, Item 1.01 (filed 2026-07-29) · sec.gov
  • service-orders5
    the 40 MW in five service orders of different sizes, each due on a date in the agreement's Milestone Schedule (its Exhibit A, not filed); the megawatts and date of each are not on file. From the Development Services Agreement's Exhibit A, on the partner's early-delivery bonus
    “The parties recognize and agree that there are currently five (5) separate service orders totaling forty (40) megawatts, but with varying megawatts per service order.”
    Zone Frontier 10-Q Ex. 10.7, Development Services Agreement (2026-07-23), Exhibit A · sec.gov
  • charges
    what Cerebras pays, in the agreement's terms as the venture's papers name them: monthly recurring charges ('MRCs') under each service order, some of them prepaid, and one-time non-recurring charges ('NRCs'), either of which can be refunded to Cerebras in cases the agreement sets. No rate, total or schedule is filed; the ~$800M is the only dollar figure for the fees (initial-value)
    “(ii) any refund of non-recurring charges or prepaid monthly recurring charges payable to the Tenant under the Colocation Agreement”
    Zone Frontier 10-Q Ex. 10.7, Development Services Agreement (2026-07-23), limitation of liability · sec.gov
  • nrc-as-equity
    Cerebras's one-time charges count as Zone's money: NRC proceeds received under the agreement 'will be treated as an Equity Capital Contribution by ZONE' (the LLC Agreement's funding schedule). So part of what Zone reports as funded equity may come from its tenant (our reading); how much, and whether any has been paid, is not stated. The LLC Agreement also lets the venture amend the agreement on 'the payment timing of NRCs'
    “Any NRC proceeds received under the Colocation Agreement will be treated as an Equity Capital Contribution by ZONE.”
    Zone Frontier 10-Q Ex. 10.8, LLC Agreement of Monarch SPV HoldCo LLC (2026-07-23), Schedule B Part 3 — Funding Schedule · sec.gov
  • rfs-credits
    credits for lateness: when a service order misses its Milestone Service Date, the monthly charges Cerebras pays are cut by 'Daily RFS Credits' (ready-for-service, §2.6.1–2.6.2 of the agreement); the LLC Agreement settles between the partners who bears those for Milestones 1 and 2. Their rates and the milestone dates are not filed
    ““Allocated MRC Credit” means, with respect to Milestone 1 or Milestone 2 under the Colocation Agreement, the aggregate dollar amount by which MRCs actually received by OpCo or Provider under the applicable Service Order are reduced as a result of Daily RFS Credits applied pursuant to Section 2.6.1 or Section 2.6.2 of the Colocation Agreement”
    Zone Frontier 10-Q Ex. 10.8, LLC Agreement of Monarch SPV HoldCo LLC (2026-07-23), definitions · sec.gov
  • early-delivery-incentive
    and a reward for being early: the agreement's §2.7 gives the venture an 'Early Delivery Incentive' for service orders delivered early; the partner's bonus is paid only to the extent the venture receives it. The incentive's amount is not filed, and the venture's papers give two different per-MW rates for bonuses tied to it (contested early-delivery-rate)
    “(For the avoidance of doubt, the Early Delivery Bonus is payable if and to the extent the Company receives the Early Delivery Incentive pursuant to Section 2.7 of the Colocation Agreement).”
    Zone Frontier 10-Q Ex. 10.7, Development Services Agreement (2026-07-23), §8.3 · sec.gov
  • funding-commitment
    the tenant's say over the landlord's money: within five business days of the post-closing conveyances, Zone must execute the 'Funding Commitment' the agreement defines, 'on terms reasonably satisfactory to Cerebras and ZONE'. Whether it has been executed is not stated; closing itself required Cerebras's consent and the agreement in force with no party in default (Contribution Agreement §7.02(g)–(h))
    “ZONE shall have executed the Funding Commitment (as defined in the Colocation Agreement), on terms reasonably satisfactory to Cerebras and ZONE, as required pursuant to an in accordance with the terms and conditions of the Colocation Agreement.”
    Zone Frontier 10-Q Ex. 10.6, Contribution Agreement (2026-07-23), §3.02(e)(iv) · sec.gov
  • direct-competitor
    and over its backers: the agreement lists Cerebras's 'Direct Competitors' (§18.3.3, its Exhibit F, not filed), none of which may lend to or invest in the venture's project financing or take a pledge over a member's interest; the consent letter has the provider confirm that neither the new parent nor Zone is one. Who is on the list is not filed
    “Notwithstanding the foregoing, a Direct Competitor (as described in Section 18.3.3 of, and listed on Exhibit F to, the Colocation Agreement) shall not be a lender or investor in any Project Financing or other financing process for the Company.”
    Zone Frontier 10-Q Ex. 10.8, LLC Agreement of Monarch SPV HoldCo LLC (2026-07-23), §6.3 · sec.gov
  • zone-stake79%
    Zone Frontier holds 79% of Monarch SPV HoldCo LLC, which owns all of the provider; the unnamed development partner holds 21% and runs the build under a Development Services Agreement (partner-identity). Zone consolidates the venture (10-Q). Its release rounded the stake to 'nearly 80%'. A missed capital call costs Zone dilution, not damages: 'The Company’s sole exposure for a funding shortfall is dilution' (8-K)
    “The Company holds a 79% ownership interest in the JV Company (a “Percentage Interest”) as the majority equity holder and capital partner, and PartnerCo holds a 21% Percentage Interest as the minority equity holder and development/operating/execution partner (the “Development Partner”).”
    CleanCore 8-K, Item 1.01 (filed 2026-07-29) · sec.gov
  • opco-contributed100%
    how Zone came to the contract: at closing the partner assigned all of the membership interests in OpCo, the provider under the agreement, to the venture. The Contribution Agreement values everything the partner contributes at $45M (its 'Agreed Asset Value'), against Zone's cash commitment of up to $500M (capital-commitment)
    “At Closing, [***] shall assign, transfer, convey, and deliver to the Company, and the Company shall accept from [***], all of [***]’ right, title, and interest in and to one hundred percent (100%) of the limited liability company membership interests in OpCo”
    Zone Frontier 10-Q Ex. 10.6, Contribution Agreement (2026-07-23), §2.02 · sec.gov
  • capital-commitment$500M
    Zone's commitment: $250M of Equity Capital Commitment and $250M of Additional Capital Commitment, called as needed on a funding schedule from July 2026 through February 2027 (8-K) whose dates the filed LLC Agreement redacts; the first $40M tranche at closing ($25M then, up to $15M more). It is not a promise of cash: 'no party may seek damages or compel funding from the Company' (8-K). What Zone had paid in is contested (zone-equity)
    “The aggregate Capital Commitment is $500,000,000, comprised of $250,000,000 Equity Capital Commitment and $250,000,000 Additional Capital Commitment, subject to the Funding Schedule set forth in Part 3 below.”
    Zone Frontier 10-Q Ex. 10.8, LLC Agreement of Monarch SPV HoldCo LLC (2026-07-23), Schedule B · sec.gov
  • going-concern
    the landlord's own warning: Zone's 10-Q finds 'substantial doubt' about its ability to continue as a going concern, because its resources will not fund the Minnesota build over the next 12 months without project-level debt, which 'has not yet been committed'. At Sep 30 2026 it had $72,934,931 of cash and no debt beyond $2,696,456 of insurance-premium financing at the venture
    “Despite these completed financings, management believes that currently available resources will not be sufficient to fund the Company’s planned capital expenditures for the Minnesota campus over the next 12 months without project-level debt financing.”
    Zone Frontier 10-Q for the quarter to Sep 30 2026 (filed 2026-11-18), Note 1 — Organization and Business, Liquidity · sec.gov
  • project-debt
    the missing piece: project-level debt for the rest of the cost, 'in the confirmatory diligence phase' at the 10-Q and in the Oct 30 update, to be raised at the project vehicle; no lender, amount or terms are disclosed. If it fails, Zone would look to other debt, outside equity in the project or selling part or all of its stake (10-Q). Lenders on Cerebras's list of competitors are barred (direct-competitor)
    “Management’s plan is to fund the remaining Minnesota project costs through project-level debt financing, which is in the confirmatory diligence phase, as of the release date of this report.”
    Zone Frontier 10-Q for the quarter to Sep 30 2026 (filed 2026-11-18), Note 1 — Organization and Business, Liquidity · sec.gov
  • landlord
    who the landlord's owner is: CleanCore Solutions, Inc. until Aug 31 2026, a seller of aqueous-ozone cleaning products that ran a Dogecoin treasury from September 2025; it sold the last of its Dogecoin on Jul 20 2026 for ~$33.4M and the cleaning business on Oct 7 2026. Its 10-K: 'We have limited experience in the development, acquisition, construction, or operation of data centers'
    “With the sale, the Company has fully exited the cleaning products business and now operates solely as an AI infrastructure developer focused on power-enabled compute campuses.”
    Zone Frontier 10-Q for the quarter to Sep 30 2026 (filed 2026-11-18), Note 1 — Organization and Business · sec.gov
  • energized20 MW
    power, not compute: about 20 MW of the site's utility power was energized at Jul 29 2026, 'supporting an initial 15 MW of critical IT load', with the rest of the capacity and the first revenue expected in Q1 2027 (later moved: full-load-date). No document says any Cerebras equipment is running
    “As of the date of this Current Report, approximately 20 MW of the Project’s utility power capacity is already energized, supporting an initial 15 MW of critical IT load, with the Project’s remaining capacity expected to come online, and associated revenue expected to commence, in the first quarter of 2027.”
    CleanCore 8-K, Item 1.01 (filed 2026-07-29) · sec.gov
  • schedule-nov40 MW
    the latest filed schedule, Zone's expectation: revenue from Q1 2027 and the full 40 MW of IT load, on ~55 MW of utility power, by Q2 2027, the campus 'on track'. The Oct 30 update has 'vertical construction of the data hall and chiller building' advancing and deposits on 'all major long-lead equipment'. No lender, engineer or Cerebras document checks it
    “The campus remains on track to commence revenue in the first calendar quarter of 2027 and to deliver its full 40 megawatts of critical IT load, supported by approximately 55 megawatts of utility power capacity, by the second calendar quarter of 2027.”
    Zone Frontier 10-Q for the quarter to Sep 30 2026 (filed 2026-11-18), MD&A · sec.gov
  • build-status$53.3M
    what the money had bought by Sep 30 2026: $53.3M of equipment deposits and work in progress on the venture's books, which 'relate to the Minnesota project under construction' and are 'expected to be placed into use in 2027' (Note 9), beside $4.0M of its cash; Zone had also committed $5,962,011 of equipment deposits not yet on its balance sheet (10-Q)
    “As of September 30, 2026, the Company’s consolidated balance sheet included $4.0 million of Cash, $3.9 million of Prepaid expenses and other current assets, $53.3 million of deposits on equipment and capital work in progress, $5.5 million of Accounts payable and other liabilities, $2.7 million in current notes payable, and ($2.5) million of Noncontrolling interest related to Monarch.”
    Zone Frontier 10-Q for the quarter to Sep 30 2026 (filed 2026-11-18), Note 11 — Joint Venture · sec.gov
  • land
    the land was not yet the venture's: Zone paid off the site's mortgage on Aug 13 2026, and the partner 'is in the process of transferring the land deed' (10-Q, Nov 18). The Contribution Agreement sets that conveyance at 30 days after closing in one section and 90 in another, with a possible extension; the record holds no deed
    “On August 13, 2026, the Company paid off the mortgage on the land for the Minnesota project. The Monarch JV Partner is in the process of transferring the land deed to the joint venture.”
    Zone Frontier 10-Q for the quarter to Sep 30 2026 (filed 2026-11-18), Note 15 — Related Party Transactions · sec.gov
  • site
    where it is, on our reading: Glencoe, in McLeod County. Glencoe's development agreement with Revolve Labs, Inc., a Delaware corporation (effective 7/17/2026; approved by the council as Resolution 2026-20 on Jul 20), lets Revolve assign it without the city's consent to 'Monarch Data Operations, LLC', the agreement's provider. Revolve describes a new AI data center at 670 11th Street West, in a town where it runs crypto mining today (revolve-site). No Zone or Cerebras document names Glencoe or Revolve; the agreement's 'up to approximately 800,000 square feet' is a ceiling for the whole campus
    “Notwithstanding the foregoing, the Company may assign the Agreement to an affiliate of the Company at any time without the City’s consent, where "affiliate" means Monarch Data Operations, LLC, a Delaware limited liability company”
    City of Glencoe council packet, Jul 20 2026: development agreement with Revolve Labs, Inc. (effective 2026-07-17) · glencoemn.org
  • revolve-site94,100
    the developer's own description, on the reading that Revolve's project is this one (site): a 94,100 sq ft facility across three buildings (a data center, an ancillary and a generator component) at 670 11th Street West, ~45 MW of expected power draw (site-power) and April 2027 as its current completion target (full-load-date). Revolve's page names neither Zone nor Cerebras
    “94,100 sq ftAcross three buildings”
    Revolve Labs, Glencoe project page (read 2026-11) · revolvelabs.ai
  • first-announcement10 years
    the day it became public: CleanCore's release of Jul 29 2026, filed with the 8-K under Item 8.01, naming Cerebras. It has CleanCore itself 'entered into' the agreement, which the 8-K describes as OpCo's and pre-existing (pre-existing). The Jun 8 8-K had disclosed only a non-binding letter of intent for a 'Midwest Project' (letter-of-intent)
    “OMAHA, NEB, July 29, 2026 /PRNewswire/ – CleanCore Solutions, Inc. (NYSE American: ZONE) (“CleanCore” or the “Company”) today announced that it has entered into a 10-year Colocation Services Agreement with Cerebras Systems (NASDAQ: CBRS) for its data center campus in Minnesota.”
    CleanCore release of Jul 29 2026 (8-K ex-99.1, Item 8.01, filed 2026-07-29) · sec.gov
  • letter-of-intent
    the first step on file: a non-binding letter of intent of May 7 2026 with 'a development partner' to take a majority of a new vehicle for 'a data center project in the midwestern United States', disclosed on Jun 8 without naming Cerebras or Minnesota. The August prospectus describes the July venture in the same words; the letter predates the Cerebras agreement by a month
    “on May 7, 2026, the Company entered into a non-binding letter of intent with a development partner under which the Company may acquire a majority ownership interest in a newly formed special purpose vehicle formed for the purposes of developing and operating a data center project in the midwestern United States (the “Midwest Project”).”
    CleanCore 8-K, Item 8.01 (filed 2026-06-08) · sec.gov
  • cerebras-filings-silent
    the customer's side: Cerebras's filings never name Zone Frontier, CleanCore, Monarch, Glencoe or Minnesota as a site — not its 424B4, its Q1, Q2 or Q3 10-Q, or its Q1, Q2 and Q3 results releases (read 2026-11-20). Its Q3 10-Q, signed Nov 12, reports data-center leases executed but not commenced at Sep 30 2026, 'with lease commencement dates in 2026 and 2027', at about $8.5B of undiscounted payments, with no landlord named; whether this agreement is among them is not stated. Cerebras's side of this record is described by Zone and by the venture's papers
    “As of September 30, 2026, the Company executed non-cancelable lease agreements for additional data center capacity with lease commencement dates in 2026 and 2027.”
    Cerebras Q3 2026 10-Q (signed 2026-11-12), Note 15 — Leases, Leases Not Yet Commenced · sec.gov

Contested figures 19 not reconciled — every position side by side, with its source and tier

initial-value2 positions, side by side
an estimate: 'an estimated contract value of approximately $800,000,000' for the initial ten years (8-K Item 1.01, filed); the release: 'expected to generate approximately $800 million of contract value over the initial 10-year term'. The agreement is not filed and no rate or escalator is disclosed, so no document shows how the figure is reached CleanCore 8-K Item 1.01 + ex-99.1 (2026-07-29)
contracted, or more: 'approximately $800 million of contracted value over the initial 10-year term' (Aug 13 update); 'The initial contract value is over $800 million dollars for a ten-year commitment' (FY2026 10-K, Sep 28). The same company's later words; its Oct 30 update and Nov 18 10-Q give no figure. The size agrees, the kind of figure does not, and neither reading is picked CleanCore shareholder update (2026-08-13); Zone Frontier FY2026 10-K (2026-09-28)
site-power4 positions, side by side
~55 MW of utility power capacity behind the 40 MW of IT load: 'an approximately 55 MW data center facility' (8-K), 'approximately 55 MW of utility power capacity and 40 MW of critical IT load upon full buildout' (release), 'approximately 55 megawatts of utility power capacity' (10-Q); the 10-K's 'approximately at least 55-megawatts' CleanCore 8-K + ex-99.1 (2026-07-29); Zone Frontier FY2026 10-K and Nov 18 10-Q
~60 MW: the Contribution Agreement's recital, 'an approximately 60 MW Minnesota data center facility for high-performance computing, cloud, and related uses', with no measure named Zone Frontier 10-Q Ex. 10.6, Contribution Agreement (2026-07-23)
~45 MW: 'Expected facility power draw' on Revolve Labs' Glencoe page, the developer the record reads as the partner (partner-identity), not named in any filing Revolve Labs, Glencoe project page (read 2026-11)
40 MW of grid load: MISO's expedited review of a new Glencoe Light & Power substation 'to serve a 40 MW load' on the McLeod–Armstrong 115 kV line, $6.5M, expected in service Oct 31 2026 (Dec 2 2025). It names no customer: that this substation serves this campus is the record's reading of the site (site), and a 40 MW grid load is not the 40 MW of IT load. No document reconciles the four MISO Expedited Project Review results, West Glencoe, project 50780 (2025-12-02)
full-load-date3 positions, side by side
Q1 2027: 'The remaining capacity is expected to come online by Q1 of 2027' (Jul 29 release); the 8-K, 'expected to come online, and associated revenue expected to commence, in the first quarter of 2027' CleanCore 8-K Item 1.01 + ex-99.1 (2026-07-29)
Q2 2027: 'fully online by the end of the second calendar quarter of 2027' (10-K, Sep 28), 'by the second quarter of 2027' (Oct 30 update) and 'by the second calendar quarter of 2027' (10-Q, Nov 18), each calling the campus on track. Zone's later words put the full 40 MW a quarter after its July date without saying why Zone Frontier FY2026 10-K; shareholder update (2026-10-30); Nov 18 10-Q
April 2027: 'Our current target is April 2027' for completion, on Revolve Labs' Glencoe page and in its Sep 8 2026 community presentation ('Target completion: April 2027'): the developer's date for finishing construction, not for Cerebras's acceptance Revolve Labs, Glencoe project page and community presentation (2026-09-08)
revenue-start2 positions, side by side
Q1 2027: the 8-K and release (Jul 29), the Oct 30 update ('commence revenue with Cerebras Systems Inc. (NASDAQ: CBRS) in the first quarter of 2027') and the Nov 18 10-Q ('in the first calendar quarter of 2027') CleanCore 8-K + ex-99.1 (2026-07-29); Zone Frontier shareholder update (2026-10-30) and Nov 18 10-Q
first half of 2027: 'the Company expects to generate revenue beginning in the first half of 2027, consistent with previous guidance' (Sep 29 release); the 10-K, 'Revenue is expected to steadily increase in the first half of 2027'. The same company's looser window between the July and October statements Zone Frontier release (8-K ex-99.1, 2026-09-30); FY2026 10-K (2026-09-28)
project-cost2 positions, side by side
$479M: 'The initial approved budget for the Project is $479,000,000' (8-K; the LLC Agreement's 'Approved Budget'). Inside it, the LLC Agreement sets a $467M capital-expenditure cap for 'Baseline Project Delivery' and the Development Services Agreement a $440M 'Capex Budget' for the partner's bonus; no document reconciles the three, and no sources and uses are filed CleanCore 8-K Item 1.01 (2026-07-29); Zone Frontier 10-Q Ex. 10.7 and 10.8 (2026-07-23)
at least $459,930,802 for the first phase: 'the first Phase of the Project will involve at least $459,930,802 of capital investment by the Company and its affiliates' (Glencoe's development agreement with Revolve Labs, approved Jul 20 2026). A floor the developer gave the city, with no breakdown; that it is the same project is the record's reading (site) City of Glencoe council packet, Jul 20 2026: development agreement with Revolve Labs, Inc.
zone-equity2 positions, side by side
~$140M 'funded or committed': 'the Company has approximately $140 million of project equity capital funded or committed for the Minnesota data center campus, including net proceeds of the equity raise and proceeds from the completed sales of its Dogecoin holdings' (Aug 13 update): a count that mixes money paid in with money committed CleanCore shareholder update (2026-08-13)
~$73.3M funded: 'funded approximately $73,270,733 as of September 30, 2026' of what the 10-Q calls 'its equity commitment to the Minnesota joint venture' (Zone commits up to $500M in all: capital-commitment); which of the LLC Agreement's two $250M parts it counts against is not stated. A different measure on a later date; no document bridges the $140M and the $73.3M Zone Frontier 10-Q for the quarter to Sep 30 2026 (filed 2026-11-18), Note 1 — Organization and Business, Liquidity
partner-identity2 positions, side by side
unnamed: every filing redacts the 21% holder ('[***]', 'PartnerCo', 'a Delaware corporation', 'the Monarch Partner'), and the release calls it 'an experienced data center development partner' CleanCore 8-K + ex-99.1 (2026-07-29); Zone Frontier 10-Q and Ex. 10.6–10.9
Revolve Labs, Inc., on our reading: Glencoe's development agreement with Revolve Labs, Inc., a Delaware corporation like the 8-K's PartnerCo, lets it assign to its affiliate Monarch Data Operations, LLC, the agreement's provider (site). No filing names Revolve, and Revolve's page names neither Zone nor Cerebras, so which Revolve entity holds the 21%, if any, is not shown our reading of the Glencoe development agreement (Jul 20 2026 council packet) and Revolve Labs' Glencoe page
early-delivery-rate2 positions, side by side
$100,000 per MW: the LLC Agreement's 'Early Delivery Bonus' is '$100,000 for each megawatt that is delivered on an Early Milestone Service Date for Milestone 3, Milestone 4 or Milestone 5 pursuant to Section 2.7 of the Colocation Agreement'; per the 8-K, an earned Early Delivery Bonus reduces the ZONE Priority Return Zone Frontier 10-Q Ex. 10.8, LLC Agreement (2026-07-23), definitions
$37,500 per MW, up to $1.5M: the 8-K's Early Delivery Bonus for the partner, 'calculated at $37,500 per MW for early-delivered service orders'; the Development Services Agreement redacts its own rate and pays only to the extent the venture receives the agreement's Early Delivery Incentive. One defined term, two rates and two scopes; what Cerebras pays for early delivery is not filed CleanCore 8-K Item 1.01 (2026-07-29); Zone Frontier 10-Q Ex. 10.7, §8.3 + Exhibit A

Scope note what this record leaves to other records

NOT this record (carried elsewhere or left out): Zone Frontier's West Texas campus with HST Technologies (99% through Brickplant SPV HoldCo; a ~4,077-acre ground lease; phases up to 200 MW; a $100M initial contribution scheduled for Apr 2 2027) → the zonefrontier entity's note; the 200 MW and 500 MW figures DCD printed in its story on this deal are Texas's. The partner's own pay under the Development Services Agreement ($4.8M of Milestone Participation in 20 monthly installments of $240,000, a Capex Management Bonus of 20% or 30% of savings against the $440M Capex Target, $1M of Upfront Stock), the venture's waterfall (93%/7% until the ZONE Priority Return) and its governance (three managers to two) are the venture's internal terms → not carried, except the $440M in project-cost. Zone's corporate figures (the August offering, ~$100M gross; the Dogecoin sales; the Oct 7 sale of the cleaning business; the reverse split) → the zonefrontier entity. Site details on file but not carried: acreage, the site's place in town, jobs, water, a 2024 pre-deal investment estimate, the Contribution Agreement's two conveyance deadlines (in land), and Monarch Data Operations' state of formation (Delaware in the filings). Cerebras-side context: the OpenAI MRA → cerebras-openai; Cerebras's other data-center sites on file, WhiteFiber's MTL-3 in Quebec (5 MW of IT load, in WhiteFiber's filings) and Digi Power X's Columbiana (cerebras-digipowerx) → not carried here; Cerebras's '700 gross megawatts of data center capacity for delivery by the end of 2027' (Q3 release), which may or may not include this site → not carried; its results and product timing → not carried. This Monarch is Monarch Data Operations, LLC, in Minnesota; it is unrelated to the Monarch Compute Campus in West Virginia (anth-nscale-monarch). Not adopted: '15MW of compute capacity is available' (DCD, Jul 31), which turns energized power into running compute; 'up to $3 billion' (a cloudnews headline; the filing says 'more than'); a third-party summary's '15 MW in December 2026 + 25 MW in March 2027' and '$200M debt commitment', both Digi Power X's Alabama figures; the August prospectus's 'we also entered into a colocation services agreement with Cerebras', which the 8-K's 'pre-existing' agreement between OpCo and Cerebras corrects.

More between Cerebras and Zone Frontier

The record holds no other deal between them.

Everything between Cerebras and Zone Frontier →