Why it matters
IREN's account shows how Microsoft's filed, non-cancellable $9.7B minimum commitment helps finance IREN's chips. On IREN's figures, Microsoft's 20% prepayment and $3,645M of debt, which DBRS rates A (low), leave about 4% of the chip bill for IREN to cover with its own cash. Under the terms IREN reports, a tranche that misses its delivery window can be cancelled unpaid.
Tap a figure for the line in its source.
Microsoft gives IREN
- of fees through 2031, owed whether or not Microsoft uses the capacity
- up front: 20% of each hall's value before delivery, credited back from month 25
IREN gives Microsoft
- of Nvidia GB300 capacity in four 50 halls in Texas; the first delivered Aug 2026
What happened
Microsoft agreed in November 2025 to rent a dedicated block of Nvidia GB300 chips from IREN, a former bitcoin miner turned cloud provider. The chips go in four new liquid-cooled halls on IREN's Childress, Texas campus. The contract is worth about $9.7 billion over roughly five years, payable whether or not Microsoft uses the capacity. Three things make this contract a template. Microsoft pays 20% of each phase up front (about $1.93 billion in all) and gets it back as credits after two years. IREN buys the chips from Dell for about $5.8 billion and does not have to pay for a shipment until 30 days after it ships. And IREN then borrowed $3.645 billion against the contract's cash flows through a subsidiary, at an investment-grade A (low) rating, so that the debt plus Microsoft's prepayment cover about 96% of the chip bill. As of November 2026 the first of the four 50-megawatt halls has been delivered, accepted and is in service. The other three were due in late 2026, with the contract allowing slippage into early 2027. But IREN's latest quarterly report says Microsoft asked for a network design change across the halls. It says that under the contract, delivery dates extend, with no delay credits owed, for delays that change causes. The two sides are still discussing dates, fees and credits. IREN also says some contracted capacity it had aimed to deliver by the end of 2026 is now expected in the quarter after, citing a customer-requested design change, supply timing and third-party delays, without saying which halls or which customer. Everything here comes from IREN's side of the table — its filings and earnings calls, its rating agency, its vendor Dell — plus one trade-press reading of the loan; Microsoft has said nothing.
Sources 19 documents — 13 SEC filings · 2 company releases · 2 transcripts · 1 research note · 1 press report
Research trail Found 324 documents and read 297 of them while checking this deal and related ones.
- States 5 figures: $9.7B contract value · parties and filing · delivery risk · 200 MW capacity · $5.8B dell purchase
- States 4 figures: $9,666,845,337.60 tcv cap · $1,932,839,884.80 prepayment total · 20% prepayment mechanics · take or pay
- States 4 figures: $3645M financing size · $413M drawn at sep 30 · horizon 2 4 schedule · lease accounting
- States 3 figures: 5.96% notes and loan pricing · availability and maturity · security and guarantees
- States 2 figures: 96% capex coverage · 6% blended cost of debt
- States 2 figures: $3.645B rating dbrs · contract as read by the rater
- States 2 figures: $1487.1M GPU collateral · $9.7B customer concentration
- States dell own release
- States 50 MW horizon 1 delivered
- States delivered vs contracted
- States 85% iren project estimates
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: IREN 8-K Item 1.01 + ex-99.1/99.2 (2025-11-03); Q2-FY26 10-Q + ex-10.3 SOW / ex-10.4 Dell purchase agreement / ex-10.5 NCNR terms (2026-02-05); 8-K Items 1.01/2.03 (2026-06-01) + IREN release (GlobeNewswire, 2026-06-01); Morningstar DBRS (2026-06-04); 8-K Item 7.01 ex-99.1 (2026-08-13); FY26 10-K + results release ex-99.1 (2026-08-27); Q1-FY26 (Investing.com) and Q3-FY26 (furnished on EDGAR) call transcripts; FY26 call (Motley Fool); Dell newsroom (2025-11-03); the Energy Mag (2026-06-01); Q1-FY27 10-Q + results release ex-99.1 (2026-11-05) — earlier sources read 2026-09, Q1-FY27 documents read 2026-11 · as of Nov 2026
The evidence 26 sourced figures · 4 disputes
The record's headline Microsoft–IREN: ~$9.7B five-year GB300 at Childress (Horizon 1–4, 200 IT) — 20% of each tranche prepaid, the GPUs bought from Dell for ~$5.8B on 30-day terms, $3,645M of A (low)-rated debt whose maturity is the contract's last service fee; Horizon 1 delivered Aug 2026, three to go
- Size
- ~$9.7B TCV (SOW cap $9,666,845,337.60) · 200 MW IT (4 × 50 MW) · $1,932.8M aggregate prepayment · ~$5.8B Dell GPU purchase · $3,645M contract-backed debt, DBRS A (low) (Fitch A per IREN)
- When
- Nov 2 2025 SOW (8-K Nov 3) → Feb 5 2026 SOW filed → May 29 2026 financing (Jun 1 8-K; Jun 4 DBRS A (low)) → Aug 13 2026 Horizon 1 delivered → Sep 2026 Tranche 1 amortization begins → Nov 5 2026 10-Q: Microsoft-requested network design change, delivery dates extended without delay credits, 'certain contracted capacity' now expected in the quarter after Dec 31 2026 → Horizon 2–4 (FY26 10-K: targeted Q4 2026, contractual grace to early Q2 2027) → service ends 2031
- Status
- signed Nov 2 2025 (SOW dated; 8-K Nov 3; SOW filed Feb 5 2026 as ex-10.3, [***]-redacted); financing agreements dated May 29 2026 (8-K Jun 1), $938M of $3,645M drawn at Jun 30 2026 — the same $413M of the DDTL and first $525M of notes released at Sep 30, with a further $1,050M of notes issued into escrow, of which $525M was released Oct 1 beside a $388M DDTL borrowing (Q1-FY27 10-Q); Horizon 1 (50 MW IT) 'delivered to and accepted by Microsoft' Aug 13 2026 — 50 of 200 MW — and 'remains in service' at Sep 30, Tranche 1's amortization began in September; Horizon 2–4 'progressed to late-stage construction' (IREN's Nov 5 release; Aug 27: Horizon 2 commissioning, 3–4 in late-stage construction — so Horizon 2 is not shown as further along than in August), 'targeted for delivery in phases in calendar Q4 2026, with grace periods … extending from mid-Q4 2026 to the beginning of Q2 2027' (FY26 10-K, which also admits equipment delays on Horizon 1; the Q1-FY27 10-Q does not restate that schedule) — and the Q1-FY27 10-Q now says Microsoft has asked for a network design change across the Horizon deployments, with delivery dates 'extended, without delay credits' for the delay it causes and discussions on dates, fees, credits and cost reimbursements still under way (10-Q, Nov 5). No Microsoft document on file names IREN
- Structure
- GPU-services offtake: a Partner Statement of Work between Microsoft Corporation and IE US Hardware 3 Inc. (IREN's wholly owned project subsidiary) — four tranches ('GPU Services') of NVIDIA GB300 capacity at Horizon 1–4, Childress TX, each with a [***]-redacted GPU quantity, delivery date and $/GPU/hr price and a Service End Date in 2031; Service Fees capped at the TCV and 'non-refundable, non-cancellable and constitute a firm minimum commitment by Microsoft'; 20% of each tranche's value invoiced before its delivery, interest-free, credited back pro rata from month 25; a tranche that misses its delivery window may be terminated by Microsoft, which then owes nothing for it. Around it, two more contracts signed the same day and one financing: a Dell Marketing L.P. purchase agreement (ex-10.4) plus non-cancellable/non-returnable terms (ex-10.5) for ~$5.8B of GPUs delivered in tranches from March 2026 with installments due 30 days after each shipment, unconditionally guaranteed by IREN Limited; and, six months later, a $3,645M senior secured financing at IE US Hardware 3 LLC ($2,100M 5.96% notes due Dec 31 2031 + $1,545M delayed-draw term loan at term SOFR + 2.25%) secured on the GPUs, the SPV's equity and the contract's cash flows, with limited parent guarantees, rated A (low) by DBRS. The NVIDIA–IREN cloud contract and investment rights of May 2026 are a separate deal, not part of this record
- Programme
- Microsoft–IREN
- Parties
- Microsoft offtaker — a 'firm minimum commitment' regardless of utilisation; pays 20% of each tranche before its delivery; may terminate a tranche that misses its delivery window; has published nothing about the deal · IREN neocloud provider through IE US Hardware 3 Inc. (the contract) and IE US Hardware 3 LLC (the borrower) — designs, builds and owns Horizon 1–4, buys the GB300s from Dell, borrows against the contract; the parent unconditionally guarantees the Dell purchase and gives limited guarantees on the financing · Dell
- Record
- disclosed / primary source · as of Nov 2026
Flows 3 as the record states them
- Microsoft → IRENcompute-spend~$9.7B through 2031 (SOW cap $9,666,845,337.60; four tranches summing to $9,664,199,424.00), non-cancellable firm minimum commitment; 20% of each tranche's value ($1,932,839,884.80 in aggregate) invoiced before that tranche's delivery and credited back pro rata after month 24; estimated monthly payments $161,180,236.80 for months 1–24 of each tranche, $107,199,838.11 thereafter
- IREN → Microsoftcomputededicated NVIDIA GB300 capacity in four tranches at Horizon 1–4, Childress TX — ~200 MW IT load (4 × 50 MW); 50 MW delivered and accepted Aug 2026 (in service at Sep 30), 150 MW targeted Q4 2026 with contractual grace to early Q2 2027 (FY26 10-K) — now subject to a Microsoft-requested network design change under which delivery dates extend without delay credits (Q1-FY27 10-Q); GPU quantity redacted in the filed SOW (management on one call: ~76,000)
- IREN → Dellgpu-purchases~$5.8B of GPUs and ancillary products and services from Dell Marketing L.P., in tranches from March 2026, installments within 30 days of each tranche shipping, unconditionally guaranteed by IREN Limited (dell-purchase)
Resolved figures 26 each with the verbatim line from its document
- contract-value$9.7B~$9.7B through 2031 over 'a five-year average term' — the 8-K's rounding of the filed SOW's exact cap of $9,666,845,337.60 (see tcv-cap); four tranches 'targeted for deployment during 2026 (subject to extension in certain circumstances)'. Restated verbatim in the Q2- and Q3-FY26 10-Qs and in the FY26 10-K; the Q1-FY27 10-Q (Nov 5 2026) no longer states the contract value and speaks only of 'the Microsoft Agreement' and 'Horizons 1–4' (its 'remaining aggregate contracted value of lease arrangements', ~$13,957M, is the aggregate across all of IREN's lease arrangements, not this contract's). Comparable Microsoft neocloud offtakes: Nebius $17.4B / $19.4B with ~$7B upfront (nb-msft), Lambda undisclosed (lam-msft), CoreWeave's unfiled (cw-microsoft)
“The total contract value is approximately $9.7 billion through 2031, with 20% of the contract value for each tranche to be paid prior to the applicable delivery date and credited against the service fees due and payable after the 24th calendar month of the applicable GPU Service term on a pro rata basis.”
IREN 8-K Item 1.01 (filed 2025-11-03) — Commercial Agreement with Microsoft · sec.gov - parties-and-filingsigned November 2, 2025 by IE US Hardware 3 Inc. (IREN's project subsidiary) and Microsoft Corporation; 8-K'd November 3 under Item 1.01 (filed, not furnished); the executed SOW itself was filed three months later as ex-10.3 to the Q2-FY26 10-Q ('Partner Statement of Work, dated as of November 2, 2025, between IE US Hardware 3 Inc. (a wholly owned subsidiary of IREN Limited) and Microsoft Corporation'), with GPU quantities, prices, delivery dates and payment windows [***]-redacted. The contract itself is on the record, beside IREN's 8-K — Nebius filed its Microsoft SOW as a 20-F exhibit; CoreWeave's Microsoft contracts are unfiled
“On November 2, 2025, IE US Hardware 3 Inc. (“IE US Hardware 3”), a wholly owned subsidiary of IREN Limited (the “Company”), and Microsoft Corporation (“Microsoft”) entered into a Partner Statement of Work (the “Microsoft Agreement”) , pursuant to which IE US Hardware 3 will provide Microsoft access to dedicated GPU infrastructure capacity in tranches (each, a “GPU Service”) at “Horizon” data center facilities located in Childress, Texas over a five-year average term.”
IREN 8-K Item 1.01 (filed 2025-11-03) · sec.gov - tcv-cap$9,666,845,337.60$9,666,845,337.60 — the contractual fee cap, reduced tranche by tranche if Microsoft terminates a late GPU Service. The same exhibit's Table 1 totals the four Tranche Values at $9,664,199,424.00, $2.65M less; the per-tranche values are redacted so the gap cannot be reconciled from the document, and at the $9.7B level it is immaterial — both figures are carried, neither is promoted to 'the' exact value. Pricing is per GPU-hour: 'Price (USD $/GPU/hr) … NVIDIA GB300 Childress, TX 5 years [***]'
“The total fees for the Services (“Service Fees”) will not exceed $9,666,845,337.60 USD (“TCV”); provided, however, that in the event that all or a portion of any GPU Service is terminated in accordance with the terms of this Agreement, the TCV will be reduced by an amount equal to the portion of the Tranche Value attributable to such terminated GPU Service(s).”
Partner Statement of Work, Q2-FY26 10-Q ex-10.3 — §3.2 Service Fees · sec.gov - prepayment-total$1,932,839,884.80$1,932,839,884.80 aggregate Upfront Payment across Horizon 1–4 = 20% of the $9,664,199,424.00 Tranche Value total (the text as downloaded prints the last digit of each figure split off, as quoted). IREN rounds it to '$1.9bn' (Feb 2026 release: 'Microsoft prepayment ($1.9bn)') and, in the Jun 1 2026 financing footnote, to the '$1.94bn customer prepayment' — the same $1.94bn the Nov 2025 deck uses for AVERAGE ANNUAL REVENUE, because on a five-year average term 20% of the TCV and one-fifth of it are the same number: a coincidence of the contract's shape, not a mis-assignment (the 'misattribution' reading is half right — the two substacks that print '$1.94bn prepaid at signing' get the TIMING wrong, see prepayment-mechanics). Nebius's comparable: ~$6,958.1M on $17.4B, i.e. ~40%
““Tranche Value” [***] [***] [***] [***] USD $9,664,199,424.0 0 “Upfront Payment ” [***] [***] [***] [***] USD $1,932,839,884.8 0”
Partner Statement of Work, Q2-FY26 10-Q ex-10.3 — Table 1 · sec.gov - prepayment-mechanics20%per tranche, pre-delivery, interest-free, credited back pro rata from month 25 of that tranche's term — NOT paid in full at signing (a tier-3 reading the exhibit refutes). The credit is visible in Table 1's estimated monthly payments: $161,180,236.80 for the first 24 months of each tranche, $107,199,838.11 from month 25 to the Service End Date (both marked estimates; the $53,980,398.69 monthly step-down is the prepayment being returned — editor's arithmetic on the two cells). FY26 10-K: 'The GPU quantity and the estimated monthly payments are expected to be approximately equal across all four tranches'
“Upfront Payment: Partner shall invoice an upfront payment for each GPU Service no earlier than [***] before the Delivery Date of each GPU Service; being an amount equal to 20% of the applicable Tranche Value provided in Table 1 (“Upfront Payment”) and Microsoft shall pay each Upfront Payment to Partner within [***] of receipt of such invoice. The Upfront Payments will not bear interest and will be credited against the Service Fees due and payable by Microsoft after the twenty-fourth (24th) calendar month of each Service Term on a pro-rata basis.”
Partner Statement of Work, Q2-FY26 10-Q ex-10.3 — §3.2.a.iii Upfront Payment · sec.gov - take-or-paytake-or-pay in the contract's own words — the clause the lenders and the rating agency lend against (DBRS: 'the take-or-pay contract with Microsoft with no exposure to volume risk'). The 'except as otherwise provided' is §3.3: a tranche that misses its Delivery Date and its Delivery Delay Window may be terminated by Microsoft, which then 'will have no obligation to pay for that GPU Service'; a tranche 'delivered and accepted' must be paid for through its Service End Date. Nebius's equivalent wording: 'irrespective of actual utilization'
“The Service Fees are non-refundable, non-cancellable and constitute a firm minimum commitment by Microsoft to Partner regardless of whether Microsoft utilises any or all of the Services, except as otherwise provided for in this Agreement.”
Partner Statement of Work, Q2-FY26 10-Q ex-10.3 — §3.2.a.v · sec.gov - delivery-riskthe risk the structure concentrates on IREN: SOW §3.3.b — if the Minimum GPU Quantity is not delivered for acceptance within the Delivery Delay Window plus [***] days, 'Microsoft may elect in writing to Partner to terminate the applicable GPU Service with immediate effect or the parties may agree to an updated delivery date'; §3.3.d — a terminated tranche is unpaid and its Upfront Payment refunded. The financing mirrors it: the limited parent guarantees cover amounts 'attributable to a tranche of GPU services that Microsoft does not accept or terminates' net of remarketing, and the FY26 10-K's grace-period language (horizon-2-4-schedule) is this clause seen from the delivery side
“The Microsoft Agreement contains customary termination rights (including certain cure periods), including, subject to a cure period, a right for Microsoft to terminate if IE US Hardware 3 fails to meet agreed delivery dates and other remedies.”
IREN 8-K Item 1.01 (filed 2025-11-03) · sec.gov - capacity200 MW~200 MW of IT load in four 50 MW phases ('4 x 50MW (IT load) phases at Childress through 2026', Nov 2025 deck; 'four 50-megawatt (MW) data centers (DCs) (totaling 200MW)', DBRS) on IREN's 750 MW Childress campus, whose remaining 450 MW ('Horizon 5 - 10') the same deck's p.6 carries as 'IMMEDIATE EXPANSION POTENTIAL — Advancing design workstreams for potential conversion of entire 750MW Childress campus to liquid-cooled AI deployments — 450MW additional capacity available' (a workstream, not a commitment). The '300MW' IREN also prints for Horizon 1–4 is a power-side figure no filing labels — see contested capacity-basis. Direct-to-chip liquid-cooled halls IREN designs, builds and owns ('no third-party colocation costs or counterparty risk', deck)
“The GPU Services will comprise NVIDIA GB300 GPUs and will be installed across four data center facilities at Childress known as “Horizon 1,” “Horizon 2,” “Horizon 3,” and “Horizon 4”, representing a combined IT load of approximately 200MW.”
IREN 8-K Item 1.01 (filed 2025-11-03) · sec.gov - dell-purchase$5.8B~$5.8B ('$5.81bn' at one more digit in the Jun 2026 release) — the whole GPU capex of the contract, bought from Dell in tranches from March 2026 and paid 'within 30 days of each tranche shipping', with IREN Limited agreeing 'to unconditionally guarantee the obligations of IE US Hardware 3 under the Dell Purchase Agreement'. Signed the same day as the SOW; filed as ex-10.4 (purchase agreement, '(Non-Financed)' in its own title) and ex-10.5 (Non-Cancellable Non-Returnable and Supplemental Terms Agreement) to the Q2-FY26 10-Q, dollar figures redacted. Management on the Q1-FY26 call: 'an inbuilt financing mechanism in that contract where we don't have to pay for any GPUs until 30 days after they're shipped'. The vendor leg is a payment TERM, not a loan — 30 days of Dell credit per tranche, bridged by the prepayment and the DDTL draws. The $1.6B Dell purchase of May 19 2026 (IE US Hardware 4) serves other contracts, not this one
“On November 2, 2025, IE US Hardware 3 and Dell Marketing L.P. (“Dell”) entered into a Purchase Agreement (together with any ancillary agreements, the “Dell Purchase Agreement”) pursuant to which Dell will supply to IE US Hardware 3 GPUs and ancillary products and services, scheduled to be delivered in several tranches from March 2026, for an aggregate purchase price of approximately $5.8 billion payable in installments within 30 days of each tranche shipping.”
IREN 8-K Item 1.01 (filed 2025-11-03) — Dell Purchase Agreement · sec.gov - dell-own-releasethe only counterparty document on file for this record (Dell's other words on IREN are on the dell entity): Dell confirms the supply relationship and the Microsoft link ('IREN will provide Microsoft with access to the NVIDIA GPUs over a five-year term and across four data centers in Childress, Texas') and states NO dollar figure — the $5.8B is IREN's number alone. The purchase lives here, on the structure line and, with the dell entity now on the map, on an iren→dell ribbon
“Today, IREN announced that Dell Technologies will supply racks of NVIDIA GB300 GPUs along with other data center equipment to the AI cloud service provider. These solutions and services will support new work between IREN and Microsoft also unveiled today.”
Dell Technologies newsroom, Nov 3 2025 · dell.com - capex-coverage96%96% at financial close — $3.645B of debt + the ~$1.93B prepayment ≈ $5.59B of the $5.81B GPU bill, leaving ~$0.22B (≈4%) to IREN's own cash. The earlier '95%' (Feb 5 2026 Q2-FY26 release, at the $3.6B underwriting-commitment stage) is the same measure a stage earlier, not a competing value; the '90%' in IREN's FY26 release belongs to the separate $2.8B non-investment-grade financings (Blue Owl / PIMCO $2.4B at 9.0% for Mackenzie) and is excluded.
“Together with customer prepayments, the facility funds $5.59bn of the $5.81bn (approximately 96%) of GPU capex under the Microsoft contract at an average financing cost of 3.31%3 and strengthens IREN’s capital structure as the Company continues to execute on its expansion to 480MW of AI Cloud capacity by the end of 2026.”
IREN release, Jun 1 2026 (GlobeNewswire) · globenewswire.com - financing-size$3645M$3,645M = $2,100M of notes + $1,545M DDTL — one number at three roundings across IREN's documents: '$3.6 billion' (Jun 1 8-K; FY26 release), '$3.65bn' (Jun 1 release), '$3,645.0 million' (10-K), '$3,645 million' (Q1-FY27 10-Q, which reports 'no changes to the terms' of the DDTL and the notes in the quarter), 'USD 3.645 billion' (DBRS); not a range dispute. Committed Feb 2026 ('$3.6bn of underwriting commitments'), agreements dated May 29 2026, announced Jun 1; the credit agreement, note purchase agreement, common terms agreement and two limited parent guarantees are filed as FY26 10-K ex-10.35–10.38 / 10.54. Goldman Sachs Bank USA and JPMorgan Chase Bank, N.A. joint lead arrangers
“GPU Financing 1.0 — Our financing subsidiary, IE US Hardware 3, LLC secured financing commitments totaling $3,645 million for GPUs and related infrastructure supporting the Microsoft Agreement at Horizons 1–4. These comprise a $1,545 million senior secured delayed draw term loan (the “DDTL Facility”), bearing interest at one-month Term SOFR plus 2.25%, and $2,100 million of senior secured notes (the “USPP Senior Notes”), bearing interest at 5.96% per annum.”
IREN Q1-FY27 10-Q (filed 2026-11-05) — MD&A, GPU Financing 1.0 · sec.gov - notes-and-loan-pricing5.96%$2.1B of 5.96% senior notes due December 31, 2031 — a U.S. private placement ('the first GPU financing in the U.S. private placement market', IREN; 'a fixed rate equivalent to SOFR+2.13%') — plus ~$1.5B of delayed-draw term loan at term SOFR + 2.25% with a 0.40% undrawn fee, hedged. The credit agreement's margin grid steps 2.5% → 2.375% → 2.25% with the SPV's public rating (A (low) / A- / A3 earns the 2.25%). A PGIM fund's N-PORT marks the notes at par, Level 3
“Borrowings under the DDTL bear interest at a per annum rate equal to term SOFR plus a margin of 2.25%. The Borrower is also required to pay a commitment fee of 0.40% per annum on the undrawn portion of the DDTL commitments during the Delayed Draw Availability Period. The Notes bear interest at a fixed rate of 5.96% per annum.”
IREN 8-K Items 1.01/2.03 (filed 2026-06-01) — Interest, Commitment Fees and Amortization · sec.gov - availability-and-maturitydrawn tranche by tranche as the GPUs are delivered (DBRS: 'stringent draw conditions' that keep debt off a tranche 'before its destination DC is ready'), available to May 29 2027; matures Dec 31 2031 or when Microsoft's last service fee is paid — the debt's life IS the contract's life. Principal amortises per tranche; the Common Terms Agreement requires a 1.05:1.00 DSCR quarterly, and a cash sweep starts if DSCR is below 1.10:1.00 for six consecutive months, the projected third/fourth-tranche DSCR is below 1.20:1.00, or loan-to-cost exceeds 65%
“Borrowings under the DDTL and issuances of Notes will be made in tranches, and are available until May 29, 2027, subject to certain extensions (the “Delayed Draw Availability Period”). The maturity date for borrowings under the DDTL and the Notes is December 31, 2031, or such earlier date as the final service fee with respect to all tranches under the Microsoft Contract shall have been paid in full.”
IREN 8-K Items 1.01/2.03 (filed 2026-06-01) — Availability and Maturity · sec.gov - security-and-guaranteesproject-finance geometry: a bankruptcy-remote SPV (DBRS's words) owns the GPUs and the contract; the lenders hold the GPUs, 100% of the SPV's equity and the receivables. IREN Limited's exposure is 'Limited Parent Guarantees' of May 29 2026 covering the manager's performance and amounts 'attributable to a tranche of GPU services that Microsoft does not accept or terminates, to the extent not satisfied through Hardware 3's exercise of a right to dispose of, or remarket, the relevant GPU infrastructure' — the parent stands behind delivery risk and residual value, not the debt as such (filed as 10-K ex-10.38, MSA, and ex-10.54, Remarketing Right). At Jun 30 2026 the SPV's pledged GPUs carried $1,487.1M (gpu-collateral). Contrast Hut 8's project bonds, non-recourse to the parent outright (nv-hut8-beacon-point)
“The obligations of Hardware 3, in its capacities as Borrower and Issuer, are secured by all its assets, including the GPUs acquired by Hardware 3 to service the Microsoft Contract, a pledge of 100% of the equity interest in Hardware 3, and the cash flows to be generated from the Microsoft Contract.”
IREN 8-K Items 1.01/2.03 (filed 2026-06-01) — Guarantees and Security · sec.gov - rating-dbrs$3.645BA (low), Stable, on the issuer, the DDTL and the notes — the one rating on file stated by the agency itself (base-case DSCR 1.20x; 'a bankruptcy-remote special-purpose vehicle'). Fitch's 'A' appears in the sources on file only through IREN's Jun 1 release ('Fitch and DBRS ratings of A and A(low) respectively') and a ccir.io summary; Fitch's own report could not be read (the agency's pages block automated downloads), so 'rated A (Fitch)' is carried as IREN's statement. 'The highest publicly rated investment-grade GPU financing announced' is IREN's superlative; the comparators are Hut 8's Baa2 project bonds (nv-hut8-beacon-point) and CoreWeave's unrated DDTLs (cw-ddtl4-2026)
“DBRS Limited (Morningstar DBRS) assigned an Issuer Rating of A (low) to IE US Hardware 3 LLC (the Issuer) and credit ratings of A (low) to the Issuer's Delayed Draw Term Loan (the Senior Term Loan) in the amount of USD 1.545 billion and 5.96% Senior Secured Notes (the Senior Notes; together with the Senior Term Loan, the Senior Debt) in the amount of USD 2.100 billion, for a total of USD 3.645 billion Senior Debt (with delay draw capabilities), which begins to amortize after stabilization of the graphics processing unit (GPU) portfolio, with a maturity on December 31, 2031.”
Morningstar DBRS press release, Jun 4 2026 — IE US Hardware 3 LLC · dbrs.morningstar.com - contract-as-read-by-the-raterthe rating agency's reading of the redacted contract, consistent with the SOW's §3.2.a.v and §3.3: 'highly stable cash flows predicated on the take-or-pay contract with Microsoft with no exposure to volume risk'; the residual risk is delivery, which the draw conditions and the parent guarantees are built around. Tier 2: a third party's description of a document whose operative dates are [***] in the public copy
“which allows Microsoft to cancel individual tranches that are delayed beyond certain timelines but requires Microsoft to accept and continue to make lease payments on tranches that are delivered and accepted.”
Morningstar DBRS press release, Jun 4 2026 — Credit Rating Rationale · dbrs.morningstar.com - blended-cost-of-debt6%6.00% — IREN's blended figure across the fixed 5.96% notes and the hedged floating DDTL ('at 6.0%' in the FY26 release). The same release's '3.31% … all-in financing cost … including customer prepayments' is a DIFFERENT quantity, the Energy Mag's 5.94% a third-party recompute, and the 10-Q's 7.22% / 7.09% effective interest rates an accounting measure — see contested financing-cost; none is averaged with another
“IREN achieved a blended cost of debt of 6.00% notwithstanding higher base rates since the initial DDTL underwriting commitment.”
IREN release, Jun 1 2026 (GlobeNewswire) · globenewswire.com - drawn-at-sep-30$413M$413M of the DDTL funded and $1,575M of the notes issued at Sep 30 2026 against $3,645M committed, with $1,132M of the DDTL and $525M of the notes still unfunded — but 'the proceeds of $1,050 million (Tranches 2 and 3)' of those notes were 'held in the escrow account' 'pending satisfaction of the release conditions', and the notes 'bear interest from their respective issue dates, including while the proceeds remain in escrow'. So the money released for use is the same $413M + $525M = $938M as at Jun 30 (editor's arithmetic; the FY26 cash-flow line 'Proceeds from financing facility 938.0'), roughly one tranche's worth, consistent with Horizon 1 being the only phase delivered; Note 19 carries $409M of DDTL and $1,571M of notes as principal outstanding ($1,980M, after Tranche 1's amortization began in September; $938M at Jun 30). After the quarter, on Oct 1 2026, 'the Tranche 2 proceeds of $525 million were released from escrow and $388 million was borrowed under the DDTL Facility'; the 10-Q reports no release of Tranche 3's $525M of notes, and the remaining draws follow Horizon 2–4
“As of September 30, 2026, $413 million of the DDTL Facility had been funded and $1,575 million of the USPP Senior Notes had been issued. Unfunded commitments of $1,132 million and $525 million, respectively, remained available subject to conditions precedent.”
IREN Q1-FY27 10-Q (filed 2026-11-05) — MD&A, GPU Financing 1.0 · sec.gov - gpu-collateral$1487.1M$1,487.1M of GPUs and related infrastructure sat in the financing SPV at Jun 30 2026, pledged to the lenders — the Horizon 1 tranche and shipments in transit — against $938M drawn, i.e. the lenders were ~63% loan-to-carrying-value on the first tranche (editor's arithmetic; the covenant ceiling is 65% loan-to-cost). The Dell tranches still to ship are not in this figure. The Q1-FY27 10-Q no longer isolates the SPV: its pledged-GPU line is $4,769M at Sep 30 2026 ('June 30, 2026: $1,487 million') 'owned by wholly owned subsidiaries' and 'pledged as collateral under the Group’s financing facilities' (Note 19's secured instruments are GPU Financing 1.0, 2.0 and 3.0) — so this SPV's own carrying amount after Horizon 1's acceptance is not stated, and the $4,769M is not it
“Included within “GPU Hardware” above are GPUs and related infrastructure with an aggregate net carrying amount of $1,487.1 million as of June 30, 2026 (June 30, 2025: nil) that are owned by IE US Hardware 3, LLC (a wholly owned subsidiary of the Company), the Company's financing subsidiary, and are pledged as collateral under the Group’s GPU Financing facility.”
IREN FY26 10-K (filed 2026-08-27) — Property, plant and equipment · sec.gov - horizon-1-delivered50 MW50 MW IT 'delivered to and accepted by Microsoft' — announced August 13, 2026 (not Aug 17: the release is dated Aug 13 and the 8-K furnishes it the same day), confirmed in the filed FY26 10-K ('delivered to, and accepted by, Microsoft in August 2026'). Acceptance is the contractual trigger: it starts the tranche's Service Term, the monthly fees and, under the financing, the debt service. 'Delivered' and 'accepted' are IREN's words; Microsoft has published nothing. Also 'NVIDIA Exemplar Cloud status … following NVIDIA's testing of its NVIDIA GB300 NVL72 deployment at Horizon 1'. The Q1-FY27 10-Q repeats the acceptance — 'Horizon 1 was delivered to and accepted by Microsoft in August 2026 and remains in service' — and both the first lease revenue under the Microsoft Agreement and Tranche 1's amortization start from it (lease-accounting, drawn-at-sep-30)
“today announced that Horizon 1 has been delivered to and accepted by Microsoft, and that IREN has achieved NVIDIA Exemplar Cloud status on NVIDIA GB300 NVL72. Horizon 1 is the first of four 50MW (IT load) direct-to-chip liquid cooled AI Cloud deployments scheduled for delivery to Microsoft at IREN’s Childress, Texas campus in 2026 under a five-year, $9.7bn cloud services contract announced in November 2025.”
IREN 8-K Item 7.01 ex-99.1 (furnished 2026-08-13) · sec.gov - delivered-vs-contractedthe phase tracker as of Nov 5 2026: Horizon 1 — 50 MW, delivered and accepted Aug 2026 and, per the 10-Q, 'remains in service'; Horizon 2–4 — 'progressed to late-stage construction' in IREN's Nov 5 release (on Aug 27: Horizon 2 'commissioning underway', Horizon 3-4 'in late-stage construction', 'targeting delivery in Q4 2026'), so Horizon 2 is not shown as further along than in August: the Nov 5 line puts it under one label with Horizon 3–4 and drops 'commissioning underway', either a broader label or an earlier stage, and the release does not say which; neither document reports another hall delivered. 50 of 200 MW contracted (25%) is delivered, 150 MW (75%) is not, against the Nov 2025 plan of all four 'during 2026' (the 50 MW is horizon-1-delivered's figure; this cell carries the status, with no number of its own since the Nov 5 release gives none). Company statements in a furnished release and the filed 10-Q; the schedule behind them is the next cell
“Horizon 1 delivered to Microsoft, Horizon 2-4 progressed to late-stage construction”
IREN Q1-FY27 results release, 8-K ex-99.1 (furnished 2026-11-05) · sec.gov - horizon-2-4-schedulethe schedule has moved, and no new date is filed. The FY26 10-K (Aug 27) had Q4 2026 targets with contractual grace running to 'the beginning of Q2 of calendar 2027' — the SOW's Delivery Delay Windows, whose dates are redacted, read back to us as a season — and the Nov 2025 8-K had every tranche 'targeted for deployment during 2026'. The Q1-FY27 10-Q (Nov 5) says Microsoft asked for a network design change 'across the Horizon deployments'; that 'delivery dates are extended, without delay credits, for delays resulting from a Microsoft-requested change'; and that the change 'is being implemented in parallel with discussions regarding delivery dates and the application and payment of fees, credits and cost reimbursements' — so the extension's length, and who pays what, are still under discussion. Separately its MD&A says 'certain contracted capacity that we had targeted to deliver by December 31, 2026 is now expected to be delivered during the following quarter, as a result of a customer-requested design change, supply timing and third-party delays', naming neither customer nor halls (both passages point to the same risk factor, 'Our business is subject to customary risks in developing infrastructure projects'). IREN's release of the same day moves its company-wide 'More than $4 billion' ARR target from year-end 2026 to 'January 31, 2027', possibly 'the end of February 2027', after 'a customer-requested design change and supplier timing'. Delivery had slipped once already: the 10-K's risk factors admit that supply-chain issues 'resulted in delayed delivery of certain equipment required to meet our obligations with respect to the delivery of Horizon 1 under the Microsoft Agreement, and we may experience similar or other delays in the future', and the Q3-FY26 call (May 2026) had 'Horizon 1 … scheduled for Microsoft handoff in Q3'
“At Microsoft’s request, we are implementing a network design change across the Horizon deployments. Under the Microsoft Agreement, delivery dates are extended, without delay credits, for delays resulting from a Microsoft-requested change.”
IREN Q1-FY27 10-Q (filed 2026-11-05) — MD&A, Recent Developments, Customer Delivery · sec.gov - lease-accountingthe Microsoft Agreement is accounted for as a lease, IREN the lessor, and its revenue began in the quarter to Sep 30 2026: the 10-Q's AI Cloud Lease revenue — $65M, nil a year earlier — came from 'AI Cloud arrangements accounted for as leases during the period, including under the Microsoft Agreement'. The 10-Q gives no Microsoft-only amount: the $65M is $49M of 'fixed and in-substance fixed lease revenue' and $16M 'subject to availability-related conditions' across all of IREN's lease arrangements, and advance payments on such arrangements 'are recognized as deferred lease revenue' ($2,096M non-current at Sep 30, $1,623M at Jun 30), which by that policy is where Microsoft's upfront payments (prepayment-total) sit, though no figure for them is given. IREN's three largest customers were 28%, 24% and 18% of the quarter's revenue; the note names none and none is decoded here. The FY26 10-K's lease note, as nv-iren reads it, named no contract
“The increase primarily reflected the commencement of revenue recognition under AI Cloud arrangements accounted for as leases during the period, including under the Microsoft Agreement following Microsoft’s acceptance of Horizon 1 in August 2026.”
IREN Q1-FY27 10-Q (filed 2026-11-05) — MD&A, AI Cloud Lease revenue · sec.gov - customer-concentration$9.7BIREN's own statement: Microsoft ($9.7B) and NVIDIA ($3.4B) are 'a substantial majority of our contracted revenue'. Against IREN's whole FY26 (Jun 30 2026) — $707.0M of revenue, $128.8M of it AI Cloud — this contract alone is ~$1.9B a year of revenue IREN had not yet booked at Jun 30 (its first lease revenue under it came in the Sep 30 quarter: lease-accounting), from a customer for whom it is a rounding error of capex; the concentration is one-directional, the neocloud pattern (Nebius: Customer D = 83% of receivables). The NVIDIA contract and NVIDIA's investment rights are a separate deal (nv-iren), not cells here
“five-year agreement with Microsoft in November 2025, which includes GPU acquisitions and the development of the “Horizon 1,” “Horizon 2,” “Horizon 3” and “Horizon 4” data center facilities representing approximately $9.7 billion of total contract value. In addition, in May 2026 we entered into a five-year cloud services contract with NVIDIA to support its internal AI and research workloads representing approximately $3.4 billion of total contract value. Together, these arrangements represent a substantial majority of our contracted revenue.”
IREN FY26 10-K (filed 2026-08-27) — Risk Factors, customer concentration · sec.gov - iren-project-estimates85%IREN's own projections, labelled as such and never observed economics: '$1.94bn average annual revenue under Microsoft contract' ($9.7B ÷ 5, 'assuming on-time delivery and commissioning of GPUs'); 85% 'Estimated Project EBITDA Margin' ('after power, repairs and maintenance, and other direct operating costs … but before corporate overhead, financing costs' — a project margin, not a company margin); 'Estimated all-in capex $14-16m per MW (IT load): $9-11m: data center infrastructure … $3m: deployment of 100MW supercluster … $2m: acceleration' — the halls, not the GPUs, so at 200 MW the IREN-funded build is ≈$2.8–3.2B on top of the $5.81B of GPUs the financing covers (editor's arithmetic). Sell-side levered-IRR figures (25–35%) and the May 2025 '$6-7m/MW' (a different, undefined perimeter) are not carried here
“85% Estimated Project EBITDA Margin3 $1.94bn $9.7bn total contract value $5.8bn estimated GPU capex, including ancillaries1 5-year average term targeting phased starts in 2026 20% prepayment, credited to years 3-5”
IREN investor presentation, 8-K ex-99.2 (furnished 2025-11-03) · sec.gov
Contested figures 10 not reconciled — every position side by side, with its source and tier
Scope note what this record leaves to other records
NOT this record (carried elsewhere): the Microsoft-side Bloomberg figures (~$60B / ~$33B neocloud totals; Nscale $23B / $14B / $6.2B; '>38GW by 2032') — reported, unconfirmed, Microsoft context only; Nebius–Meta ~$27B and CoreWeave–Meta ~$21B → nb-meta / cw-meta; IREN's FY27 capex guidance ($25–30B), cumulative-funding series ($9.2B → $9.3B → ~$19B, different windows), ARR and GPU-fleet targets ($3.4B → $3.7B → >$4B / $4.4B; 140k → 150k — dated series, entity prose), the $2.8B non-investment-grade financings and the Jul–Aug 2026 contracts (Prometheus, Perplexity, Together AI, an unnamed 'leading frontier AI lab'), the NVIDIA–IREN deal of May 7 2026 (~$3.4B contract + rights to 30M shares at $70 / up to ~$2.1B / 600,000-GPU vesting / $793.4M fair value — nv-iren), Sweetwater / ERCOT Batch Zero, Kiowa OK, the Childress County Chapter 312 abatements (eight scanned PDFs with no extractable text — site context only), the Dec 2025 and May 2026 converts/offerings → the iren entity or their own records. Not adopted: '$1.94bn' = prepayment AND average annual revenue (same number by construction: 20% of TCV = TCV ÷ 5); '$2.1bn' = NVIDIA's investment rights AND the notes' principal; '$14bn' = IREN's cash + committed financing AND Bloomberg's Nscale-Texas figure; '300MW' unlabelled gross; 95% / 96% / 90% three perimeters of 'capex coverage'; '$3.6bn / $3.645bn / $3.65bn' one financing; 'Aug 17' (the release is Aug 13) and 'rated A (Fitch)' (IREN's statement; the agency document on file is DBRS's A (low)). Dell was not a node when this record was built, so the purchase was carried on the structure line and two cells; the dell entity is now on the map, and the purchase also draws as an iren→dell ribbon. Q1-FY27 disclosures (Nov 2026), NOT this record: the Sep 28 2026 ~$6.7B Dell purchase orders (IE US Hardware 5 and 6; no customer named), GPU Financing 2.0 and 3.0, the Mirantis acquisition, IREN-wide aggregates (RPO, lease contracted value, revenue backlog, the three-customer revenue shares) and the post-quarter contracts with unnamed customers → the dell and iren entities, or deals not yet recorded separately.