Cohere's contract puts late delivery risk on Boost Run. Cohere owes nothing for a rack until it accepts it, then owes five years of payments regardless of use. If Cohere hasn't accepted the minimum by July 15, 2027, it can get its full prepayment back under a guarantee from Boost Run's listed parent.
Tap a figure for the line in its source.
Cohere gives Boost Run
- over each rack's term of about five years from Cohere's acceptance — 'subject to' delivery and acceptance; no fee on a rack before it is accepted, then owed regardless of actual usage
- a prepayment of undisclosed size, credited against fees; the order form that sets it is not filed
Boost Run gives Cohere
- dedicated racks built to Nvidia's GB300 NVL72 design, with network storage and CPU node services — first acceptance expected in the second quarter of 2027; how many racks, the filings do not say
- a full refund of the prepayment if a minimum is not accepted by July 15, 2027, guaranteed by Boost Run Inc. up to the prepayment not yet used against fees
What happened
In September 2026, Cohere agreed to rent dedicated racks of Nvidia's GB300 GPUs from Boost Run. Cohere is a Canadian maker of AI models for businesses and governments. Boost Run is a small Nasdaq-listed GPU cloud provider in Illinois. Cohere committed about $525.6 million. Each rack's rental runs for about five years from the day Cohere accepts it. The first racks are expected to be accepted in the second quarter of 2027. Cohere owes nothing for a rack until it accepts it. After that, it owes payment for the full term whether or not it uses the rack. Cohere pays part of the money up front. The amount is undisclosed. If Cohere hasn't accepted a minimum amount of capacity by July 15, 2027, it can walk away and get its full prepayment back. The minimum is undisclosed. Boost Run's publicly listed parent guarantees that refund. If Cohere has met the minimum, it can drop the remaining racks and get their share of the prepayment back. Boost Run announced the deal without naming the customer. Its filing that day named Cohere. Cohere's own announcements since then do not mention the deal.
Sources 10 documents — 5 SEC filings · 4 company releases · 1 other document
Research trail Found 298 documents and read 273 of them while checking this deal and related ones.
- States 6 figures: $525.6M commitment · parties · term · acceptance start · outside date · parent guarantee
- States 4 figures: fees on acceptance · hardware · exits · financeable
- States 2 figures: $39.87M seller scale · Q3 10q
- States announced unnamed
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: Boost Run 8-K Item 1.01 (filed Oct 6 2026) and EX-10.1, the Service Agreement; Boost Run Q2 2026 10-Q and Q3 2026 10-Q (filed Nov 12 2026); Boost Run releases (Oct 6 + Oct 26 2026); Stablebread (Oct 2026) — read 2026-11 · as of Nov 2026
The evidence 13 sourced figures · 1 dispute
The record's headline Cohere–Boost Run: ~$525.6M for dedicated Nvidia GB300 NVL72 racks, each for about five years from Cohere's acceptance (Sep 30 2026) — nothing owed on a rack before it is accepted, acceptance expected from Q2 2027, and if a minimum is not accepted by July 15 2027 Cohere may walk away with every prepaid dollar back, a refund Boost Run's listed parent guarantees
- Size
- ~$525.6M over the term, subject to delivery and acceptance (8-K) · each rack ~5 years from its acceptance, acceptance expected from Q2 2027 · GB300 NVL72 racks (EX-10.1), count not filed · 'a portion' prepaid, refundable in full if a minimum is not accepted by Jul 15 2027, parent-guaranteed · ≈ $105M a year once all racks are accepted (the monitor's arithmetic)
- When
- Sep 30 2026 (signed) → Oct 6 2026 (8-K naming Cohere; Boost Run's release naming 'a leading sovereign AI company') → Q2 2027 (first acceptance expected) → Jul 15 2027 (outside date) → ~2032 (five-year rack terms end, on the monitor's arithmetic)
- Status
- signed Sep 30 2026; 8-K and release Oct 6. Acceptance of the first racks 'is currently expected to begin in the second quarter of 2027' (8-K), so no fee accrues before then; outside date Jul 15 2027. Boost Run's Oct 26 release restates it, customer unnamed ('a leading provider of enterprise AI models and solutions'), with no word of delivery. Boost Run's Q3 2026 10-Q (filed Nov 12 2026) has been read: it does not name Cohere and states no delivery or acceptance (q3-10q)
- Structure
- a Service Agreement ('Version 1.6.4') between Boost Run LLC, Boost Run Inc.'s wholly owned subsidiary, and Cohere Inc, with Boost Run Inc. a party 'solely with respect to Section 20', the Parent Guarantee; signed Sep 30 2026, with one order form under it ('together with the order form thereunder, the “Agreement”'). Dedicated GB300 NVL72 racks are delivered in delivery groups, validated against Nvidia's reference architecture and accepted, or deemed accepted, by Cohere; each rack's term runs about five years from its acceptance; fees accrue only from acceptance and are then owed regardless of usage. Outside date Jul 15 2027: below a redacted 'Termination Minimum' Cohere may terminate with a full refund of its prepayment; above it, it may drop the racks not yet accepted with a pro-rata refund — refunds the parent guarantees up to the prepayment not yet applied against fees. Written for project finance: fees assignable to a 'Financing Party', payment 'absolute and unconditional', estoppel certificates on request. The order form, Section 20 and the agreement's exhibits are not in the filed text, which lists the exhibits by title
- Programme
- Boost Run lab contracts
- Parties
- Cohere customer — Cohere Inc, signed for it by its CFO; owes fees only on racks it accepts, then for their full term regardless of use; may walk away with its prepayment if a minimum is not accepted by Jul 15 2027; may not terminate for Boost Run's insolvency while Boost Run or its financing party keeps performing. Its own releases and posts on file (its Series E, Oct 29; its Canada commitment, Oct 30) do not mention Boost Run · Boost Run provider — through its subsidiary Boost Run LLC (Thinking Machines' contract is with the parent itself); builds, finances and delivers the racks and carries the delivery risk to the outside date. Boost Run Inc. signs only for the Parent Guarantee of prepayment refunds (Section 20, not in the filed text)
- Record
- disclosed / primary source · as of Nov 2026
Flows 2 as the record states them
- Cohere → Boost Runcompute-spend~$525.6M over the term, 'Subject to the satisfaction of delivery and acceptance requirements and any termination' (8-K): each rack ~5 years from its acceptance, no fee on a rack before acceptance, then owed regardless of usage; 'a portion' prepaid (size not filed), refundable in full if a minimum is not accepted by Jul 15 2027 — a refund Boost Run Inc. guarantees; ≈ $105M a year once all racks are accepted (the monitor's arithmetic)
- Boost Run → Coherecomputededicated GPU cloud infrastructure — racks built to NVIDIA's reference architecture for the GB300 NVL72 configuration (EX-10.1), with network storage and CPU node services (release); rack and GPU counts, site and megawatts not filed
Resolved figures 13 each with the verbatim line from its document
- commitment$525.6M~$525.6M over the term — Boost Run's FILED figure (8-K Item 1.01, filed Oct 6 2026), and a conditional one: it is subject to delivery, acceptance and the termination rights below, no fee is payable on a rack before it is accepted (fees-on-acceptance), and if a minimum is not accepted by Jul 15 2027 Cohere may leave with its prepayment refunded (outside-date). Spread over five years it is ≈ $105.1M a year once every rack is accepted (the monitor's arithmetic, 525.6 ÷ 5); no fee accrues before Q2 2027 at the earliest. Boost Run's release of the same day gives it as a 'total contract value (TCV) of $525.6 million'
“Subject to the satisfaction of delivery and acceptance requirements and any termination described below, Cohere has committed to pay Boost Run approximately $525.6 million over the term of the Agreement, a portion of which is payable as a prepayment.”
Boost Run 8-K Item 1.01 (filed Oct 6 2026) · sec.gov - partiesBoost Run LLC, the Illinois operating subsidiary — not the listed parent, which signed Thinking Machines' MSA itself (boostrun-tml parties) — and Cohere Inc. The agreement (EX-10.1, 'Version 1.6.4') is signed for Boost Run by its CEO and for Cohere by its CFO, dated 9/30/2026, and by Boost Run Inc. 'solely for purposes of the Parent Guarantee set forth in Section 20' (parent-guarantee). Filed under Item 1.01 on Oct 6 2026, six days after signing, with parts of the exhibit and its schedules left out ('Portions of the exhibit have been omitted'; 'Schedules (or similar attachments) have been omitted')
“On September 30, 2026, Boost Run LLC (“Boost Run”), a wholly owned subsidiary of Boost Run Inc. (the “Company”), entered into a Service Agreement (together with the order form thereunder, the “Agreement”) with Cohere Inc (“Cohere”), pursuant to which Boost Run will provide Cohere with access to dedicated GPU cloud computing infrastructure and related services.”
Boost Run 8-K Item 1.01 (filed Oct 6 2026) · sec.gov - term5 yearsabout five years per rack, each from its own acceptance — not from signing. The agreement has each rack's term run 'for the number of months specified in the applicable Order' (not filed), and a late delivery or acceptance 'defers, and does not shorten, the contracted number of months of Service for that rack' (EX-10.1 §5.1(c)). With every rack due to be accepted by the Jul 15 2027 outside date, the terms run side by side to about 2032 (the monitor's arithmetic). Boost Run's release calls it 'a five-year AI cloud services agreement'
“The term for each rack of infrastructure delivered under the Agreement is approximately five years, commencing upon Cohere’s acceptance of that rack.”
Boost Run 8-K Item 1.01 (filed Oct 6 2026) · sec.gov - acceptance-startwhen the fees start: acceptance of the first racks is expected from the second quarter of 2027 — 'early Q2 2027' in Boost Run's release of the same day — and no fee accrues on a rack before its acceptance. Amounts due at signing are the exception: they 'are payable at signing and are not subject to this Article 10' (EX-10.1 §10.5), which the filing does not size
“Acceptance of the initial infrastructure is currently expected to begin in the second quarter of 2027.”
Boost Run 8-K Item 1.01 (filed Oct 6 2026) · sec.gov - fees-on-acceptancethe commitment binds rack by rack, at acceptance: before it, no fee; after it, the full term 'regardless of actual usage', and Cohere's obligation to pay undisputed fees is 'absolute and unconditional' (§4.4). A rack is accepted on Cohere's notice, or deemed accepted if Cohere sends neither an acceptance nor a non-acceptance notice within the seven-business-day validation period, or 'places any production workload on the applicable rack' (§10.2–10.3); a rack that fails gets up to two remediation periods of twenty business days. The test is conformance with 'the NVIDIA reference architecture' for the configuration in the order, Boost Run's validation suite and the service levels (§10.4). Thinking Machines' fees, by contrast, accrue from Boost Run's ready-for-use notice (boostrun-tml fees-accrue)
“Customer shall remain obligated to pay all Fees for the full duration of the Term in respect of each accepted or deemed accepted rack, regardless of actual usage; provided that no Fees shall be payable in respect of any rack prior to its acceptance or deemed acceptance.”
Boost Run LLC Service Agreement v1.6.4 §5.1 — Boost Run 8-K EX-10.1 (filed Oct 6 2026) · sec.gov - outside-datethe delivery risk is Boost Run's: if the 'specified minimum amount' — the agreement's 'Termination Minimum', its size redacted (EX-10.1 §10.6(d) is printed '[*]') — has not been accepted by the Jul 15 2027 'Outside Date', Cohere may end the whole agreement and get back everything it prepaid; if the minimum has been accepted, it may drop the racks not yet accepted, owe nothing on them, and get back their share of the prepayment, pro rata by GPUs, in three equal monthly instalments starting 30 days after termination (§10.6(e)). The outside date holds 'Notwithstanding … any Force Majeure Event' (§10.6(c)), and the refund is Cohere's 'sole and exclusive remedy' for missed acceptance; meanwhile it keeps paying for the racks it has accepted (§10.6(f))
“In addition, if a specified minimum amount of infrastructure has not been accepted by July 15, 2027, Cohere may terminate the Agreement and receive a refund of all amounts prepaid, and if such minimum amount has been accepted, Cohere may terminate the order with respect to any infrastructure not accepted by that date and receive a refund of the related prepaid amounts.”
Boost Run 8-K Item 1.01 (filed Oct 6 2026); EX-10.1 §10.6 · sec.gov - parent-guaranteeBoost Run Inc., the listed parent, stands behind the refund — capped at the prepayment received and not yet credited against fees, and covering the refund only, not delivery. The guarantee's own text, the agreement's Section 20, is not in the filed exhibit, whose text runs to Section 11 and lists its exhibits by title; this 8-K sentence is what is public. Thinking Machines' contract needs no counterpart: the parent signed it directly
“The Company has guaranteed Boost Run’s obligation to pay any refund of prepaid amounts under the Agreement, up to the amount of the prepayment received by Boost Run and not applied against fees.”
Boost Run 8-K Item 1.01 (filed Oct 6 2026) · sec.gov - hardwarewhat Cohere rents: racks built to Nvidia's GB300 NVL72 reference architecture — the agreement's validation report checks each delivery group against it — with network storage and CPU node services (Boost Run's Oct 6 release: 'compute capacity powered by NVIDIA GB300 NVL72 GPUs, along with network storage and CPU node services'). The 8-K says only 'dedicated GPU cloud computing infrastructure'. How many racks or GPUs, where, at what power or price — none is filed: the order form that states them is omitted. An NVL72 rack holds 72 GPUs, but with the rack count unknown no GPU total or price per GPU-hour can be derived
“the results of the architecture board review confirming conformance of the applicable Delivery Group with the NVIDIA reference architecture for the GB300 NVL72 configuration specified in the Order”
Boost Run LLC Service Agreement v1.6.4 §10.1 — Boost Run 8-K EX-10.1 (filed Oct 6 2026) · sec.gov - exitsno renewal, and few exits beside the outside date: either party may terminate for cause after a 30-day cure (Cohere's failure to pay undisputed fees within ten business days of notice counts as a material breach, §5.2) or on the other's insolvency (§5.3) — but Cohere may not terminate for Boost Run's insolvency 'for so long as Boost Run, or a receiver, trustee, assignee or Financing Party acting in respect of Boost Run, continues to perform'. The 8-K adds that Cohere 'may also terminate in certain other circumstances specified in the Agreement', which it does not list. Thinking Machines' orders renew a year at a time unless either side gives notice (boostrun-tml term-and-renewal)
“This Agreement shall not automatically renew under any circumstances.”
Boost Run LLC Service Agreement v1.6.4 §5 — Boost Run 8-K EX-10.1 (filed Oct 6 2026) · sec.gov - financeablethe contract is written to be borrowed against, as Boost Run says its deals are (its financing is 'raised against specific multi-year customer-backed agreements', Oct 26 release): Boost Run may assign the fees to a 'Financing Party', after which Cohere pays as that party directs (§4.3); Cohere's duty to pay undisputed fees is 'absolute and unconditional', free of set-off against any other agreement between them, and enforceable by any Financing Party (§4.4); on request Cohere must confirm to Boost Run's lenders, within ten business days and to its knowledge, that the agreement stands and that it 'has the financial ability to pay the Fees as and when due' — though nothing obliges it to make a statement it believes 'in good faith to be inaccurate' (§4.5); and title to the equipment stays with Boost Run, its lessors, vendors or Financing Parties, with no lien for Cohere's prepayment (§4.6). Which lender, if any, finances these racks, no document on file says
“Customer acknowledges that Boost Run finances the equipment, facilities and working capital required to deliver the Services in part against this Agreement and the Orders.”
Boost Run LLC Service Agreement v1.6.4 §4.5 — Boost Run 8-K EX-10.1 (filed Oct 6 2026) · sec.gov - announced-unnamedhow it became public: on Oct 6 2026 Boost Run's release announced the contract without naming Cohere ('a leading sovereign AI company'; on Oct 26, 'a leading provider of enterprise AI models and solutions'), while its 8-K, accepted by EDGAR at 8:00 a.m. the same day, named Cohere Inc. The agreement lets Boost Run disclose the customer where 'reasonably required by applicable law' or an exchange's rules (§8.2), and has the two sides agree a first joint announcement within 30 days of the Termination Minimum's acceptance (§8.1). Cohere's own release and post on file — its Series E (Oct 29) and its Canada commitment (Oct 30) — do not mention Boost Run. An unfiled company release
“today announced it has signed a five-year AI cloud services agreement with a leading sovereign AI company.”
Boost Run release, Oct 6 2026 (IR page) · investors.boostrun.com - seller-scale$39.87Mwhat the contract is to Boost Run: its whole revenue in its latest filed quarter, the one to Sep 30 2026, was $39.87M (it was $31.14M in the quarter before, per the Q2 10-Q), while this contract, once every rack is accepted, is ≈ $26M a quarter (the monitor's arithmetic, 525.6 ÷ 20) — none of it before Q2 2027; its revenue for all of 2025 was $26.89M (S-1; boostrun entity)
“Total revenue was $39.87 million for the three months ended September 30, 2026, an increase of 492% compared to $6.74 million for the three months ended September 30, 2025.”
Boost Run Q3 2026 10-Q — MD&A, Financial Summary · sec.gov - q3-10qwhat Boost Run's Q3 2026 10-Q (filed Nov 12 2026) says near this contract, none of it naming Cohere: the quarter ended Sep 30, the day the agreement was signed, so no revenue from it is in the quarter; its commitments note describes 'multiple long-term customer agreements' entered in September 2026, terms 'extending through 2032' (this contract's five-year rack terms end about 2032 on the monitor's arithmetic), 'in excess of $700,000' thousand in total — more than this contract's $525.6M alone, and the note names no customer, so whether Cohere's is among them the filing does not say. It says the September agreements 'include customer prepayments' but gives no amount and no customer, and states no acceptance date or refund term; its balance sheet carries customer deposits of $182.8M at Sep 30 (current $45.8M, non-current $137.0M), $18.97M of them the unnamed June 8 order's and none tied to Cohere, so the prepayment's size (contested, below) stays undisclosed
“The total contractual value of the arrangements are in excess of $700,000, subject to the terms and conditions of the agreements.”
Boost Run Q3 2026 10-Q — Note 18, Commitments and Contingencies · sec.gov
Contested figures 2 not reconciled — every position side by side, with its source and tier
Scope note what this record leaves to other records
NOT this record: Thinking Machines' contract → boostrun-tml; Boost Run's company-wide figures (its 'TCV' of 'over $2.6 billion' after this signing, a metric that counts LOIs and renewal options; revenue, financing, other orders) → the boostrun entity or not carried here, as listed in boostrun-tml's note. Cohere's other compute — CoreWeave (cw-ddtl5-2026 names it in its text), Bell AI Fabric's C$309M partnership and HIVE/BUZZ HPC's US$220M contract 'with Bell AI Fabric for Cohere Inc.', whose relation the documents on file do not settle — and its Series E and the Government of Canada's investment → the cohere entity. Not adopted: the per-year and per-GPU arithmetic newsletters run on the $525.6M beyond the straight line above, and GB300 NVL72 rental-rate and rack-cost estimates (gpurentals, Wing VC, CCIR) — with the rack count not public, none can be tied to this contract. On one reading, EX-10.1's 'three (3) equal monthly instalments' are a payment Cohere owes on termination; the exhibit makes them Boost Run's partial refund of prepayments for racks dropped after the minimum is met (§10.6(e)), and that is how outside-date carries it.