Why it matters
Anthropic reserved a campus's worth of Nvidia systems without paying up front. It owes fees only after each batch is built, tested and accepted, and can drop late batches without liability. Either side can walk if Nscale misses the financing deadline, and Nscale's S-1 showed no binding financing commitment at filing.
Tap a figure for the line in its source.
Anthropic gives Nscale
- across four agreements, billed per GPU-hour from Anthropic's acceptance of each batch, and only if Nscale meets delivery and availability requirements; Anthropic's own IPO filing gives the same ceiling, over terms extending into 2033
Nscale gives Anthropic
- dedicated, single-tenant Nvidia Vera Rubin NVL72 systems in four batches at the Monarch campus, on a site 'fully dedicated to Anthropic'; counts, capacity, prices, dates and terms blacked out
- the right to drop any batch delivered too late, with no liability
- the option to extend each batch's multi-year term
- best efforts to finance the GPUs and the data center by a deadline, and no offer of the site's capacity to anyone else meanwhile; if the money is not raised, either side may walk
What happened
In August 2026, Anthropic signed four agreements to rent dedicated computers from Nscale, a young London-based AI-cloud company. The computers will use Nvidia's newest Vera Rubin chips and be located at the campus Nscale owns in Mason County, West Virginia. The campus is to run on its own off-grid power plant. Nscale's IPO filing says the agreements will pay it up to about $44.6 billion, only as Nscale delivers. Anthropic pays nothing for each of four batches until it has tested and accepted it. It can cancel a batch that arrives too late. When Nscale filed, it still had to line up financing for the computers and the data center. The contract lets either side walk away if the financing is still missing at the deadline. The press reported about 460 megawatts over six years, citing unnamed sources. The filed contract blacks out the deal's size, price and length. Anthropic's own IPO filing in October states the same up-to-$44.6-billion ceiling. It says the terms extend into 2033 and Anthropic pays only as it receives and accepts capacity. The filing calls Anthropic's commitment non-cancelable except in limited circumstances, such as Nscale missing delivery or availability targets.
Sources 16 documents — 6 SEC filings · 6 press reports · 3 company releases · 1 government statement
Research trail Found 270 documents and read 246 of them while checking this deal and related ones.
- States 7 figures: up to $44.6B contract value · four agreements · tranches and term · termination · financing uncommitted · funding plan · site
- States 3 figures: filed form · pay on acceptance · financing longstop
- States $44.6B buyer account
- States $45B aker notice
- States power permit
- States first capacity
- States who else
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: Nscale S-1 + ex-10.25 (2026-09-18) and DRS/A No. 3 (2026-08-12); Aker ASA MAR notice (Aug 26 2026); WV DEP Division of Air Quality notice (permit R14-0042); Nscale community release (Aug 25 2026) and Monarch page; Bloomberg (bgov and TBS editions), CNBC, Reuters via The Star, TechCrunch (Aug 26 2026); Semafor (Aug 28 2026) — read 2026-10; Anthropic S-1 (Oct 26) and S-1/A No. 1 (Nov 2) (updated 2026-11); Anthropic S-1/As of Nov 10 and 17 and 424B4 of Nov 19 2026, the Nscale paragraph unchanged · as of Nov 2026
The evidence 15 sourced figures
The record's headline Anthropic–Nscale, Monarch Compute Campus (Mason County WV): four GPU-services agreements of Aug 25 2026 for dedicated Vera Rubin NVL72 capacity, up to ~$44.6B to Nscale if it delivers — no fee before each tranche is accepted, and no committed financing behind the build when Nscale filed its S-1
- Size
- up to ~$44.6B across four agreements (Nscale's S-1 and Anthropic's own; Aker: 'around USD 45 billion') · NVIDIA Vera Rubin NVL72 in four tranches at the Monarch Compute Campus, Mason County WV · systems, GPUs, capacity, price, delivery dates and term redacted (EX-10.25)
- When
- Mar 16 2026 (campus announced with Microsoft's 1.35 GW LOI — nscale-msft) → Mar 31 2026 (Nscale completes the AIPCorp purchase) → Aug 25 2026 (four Anthropic Services Agreements) → Aug 26 (Aker's notice, customer unnamed; Bloomberg names Anthropic) → Sep 18 2026 (S-1: up to ~$44.6B, financing not committed) → H1 2028 (Nscale's target for the campus's first 2 GW of power)
- Status
- signed Aug 25 2026; nothing delivered; financing uncommitted at the S-1 (Sep 18 2026); the campus power plant's air permit still a draft (comments to Oct 30 2026); delivery dates redacted
- Structure
- four GPU Services Agreements of Aug 25 2026, one per tranche, each between Anthropic PBC and a wholly owned Nscale subsidiary — split 'at Provider’s request to facilitate Provider’s and Parent’s efforts to secure Qualifying Financing', with all four tranches 'operated together' and 'the entire Site … fully dedicated to Anthropic'. In the filed form (EX-10.25; provider Nscale GPU MCC B1.1 LLC) Nscale supplies dedicated, single-tenant Vera Rubin NVL72 systems and the data center around them at an all-in price per GPU-hour; Anthropic pays nothing until it accepts a tranche, then hours × GPUs × price less service credits and late-delivery discounts; each tranche term runs from acceptance (months redacted) and Anthropic may extend it or swap in a later GPU generation. Nscale must use best efforts to obtain 'Qualifying Financing' for the GPUs and the facility by a redacted Longstop Date — after which either party may terminate — and may offer the site's capacity to no one else until it does. The campus is Nscale's own (the AIPCorp purchase, completed Mar 31 2026), on an off-grid power plant still in permitting
- Programme
- Anthropic–Nscale
- Parties
- Anthropic customer — dedicated GPU services under four agreements with Nscale subsidiaries; pays per GPU-hour only from its acceptance of each tranche; may drop a late tranche without liability, terminate an agreement for sustained uptime shortfalls, extend tranche terms and swap in a later GPU generation; its own S-1 (Oct 26; S-1/A Nov 2) states the up-to-$44.6B ceiling and 'terms extending into 2033', and it declined to comment on the press reports (Reuters) · Nscale provider and site owner — four wholly owned subsidiaries (the filed form's: Nscale GPU MCC B1.1 LLC) on the Monarch campus it bought with AIPCorp; must build the data center and its off-grid power plant, buy the GPUs and raise 'Qualifying Financing' for both — none committed at the S-1
- Record
- disclosed / primary source · as of Nov 2026
Flows 2 as the record states them
- Anthropic → Nscalecompute-spendup to ~$44.6B in aggregate across the four agreements, 'subject to our satisfaction of specified delivery and service availability requirements' (Nscale's S-1; Anthropic's S-1/A: 'an aggregate of up to approximately $44.6 billion over terms extending into 2033, with fees accruing only as capacity is delivered to and accepted by us') — a ceiling: hours × GPUs × price per GPU-hour each month, less service credits and late-delivery discounts, from Anthropic's written acceptance of each tranche (EX-10.25); no fee before acceptance and no upfront payment in the filed form
- Nscale → Anthropiccomputededicated, single-tenant NVIDIA Vera Rubin NVL72 systems (72 GPUs / 36 CPUs each) in four tranches at the Monarch Compute Campus, Mason County WV, on a site 'fully dedicated to Anthropic'; systems, GPUs, total capacity, delivery dates and tranche terms redacted
Resolved figures 15 each with the verbatim line from its document
- contract-valueup to $44.6Bup to approximately $44.6B in aggregate across the four Anthropic Services Agreements of Aug 25 2026, 'subject to our satisfaction of specified delivery and service availability requirements' — a ceiling, not a floor: no fee is due on a tranche before Anthropic accepts it (pay-on-acceptance), a late tranche can be dropped without liability (termination), and either side may walk if the build's financing is not in place by a deadline (financing-longstop). Stated three times in Nscale's S-1; Anthropic's own S-1 (Oct 26; S-1/A Nov 2) states the same figure from the buyer's side (buyer-account), and it declined to comment on the press reports (Reuters). The '$45 billion' of the press (Bloomberg, CNBC, Reuters, TechCrunch, Semafor; Aug 26–28 2026) and Aker's 'around USD 45 billion' (aker-notice) are this figure rounded, not a second one.
“On August 25, 2026, we entered into the Anthropic Services Agreements, which provide for aggregate payments to us of up to approximately $44.6 billion, subject to our satisfaction of specified delivery and service availability requirements.”
Nscale S-1 (filed 2026-09-18) — Business, Customers and Business Model · sec.gov - buyer-account$44.6Bthe buyer's own account, the first Anthropic has filed — 'In August 2026, we entered into GPU services agreements (collectively, the “Nscale Services Agreements”) with wholly owned subsidiaries of Nscale Global Holdings Limited', 'to access compute powered by NVIDIA GPUs', and 'we agreed to spend an aggregate of up to approximately $44.6 billion over terms extending into 2033, with fees accruing only as capacity is delivered to and accepted by us' — the same ceiling as Nscale's S-1 (contract-value), said by the payer. It adds an end, 'into 2033', and no term; it names no site (no Monarch, no West Virginia), capacity, GPU count or price per GPU-hour. It restates the financing condition — 'Nscale is required to use best efforts to obtain qualifying financing for the NVIDIA GPUs and data center infrastructure within a specified period following the effective date of such agreements (or such later date as may be mutually agreed by the parties and subject to additional negotiation)' (financing-longstop) — and then calls its commitment, 'Otherwise', 'non-cancelable except in limited circumstances, including Nscale’s failure to meet specified delivery or service availability requirements or an uncured material breach by the applicable Nscale entity'. That sums up the exits more briefly than Nscale's account of Anthropic's (termination): its examples are Nscale-side failures only, and it says nothing here of what follows if the financing is missed, which the filed form answers (either party may terminate). The paragraph sits in the S-1/A's list of 'Infrastructure Service Arrangements', beside Microsoft, Google, Amazon, SpaceXAI, AMD and Lambda. The S-1/As of Nov 10 and 17 and the final prospectus of Nov 19 2026 repeat it word for word — the same ~$44.6B ceiling, the same 2033 end, the same financing condition and exits
“Under the Nscale Services Agreements, we agreed to spend an aggregate of up to approximately $44.6 billion over terms extending into 2033, with fees accruing only as capacity is delivered to and accepted by us.”
Anthropic 424B4 (Nov 19 2026) — MD&A, Infrastructure Service Arrangements (the same paragraph in S-1/A No. 1) · sec.gov - aker-notice$45Bthe first company statement on the record: Aker ASA — for which Nscale is its 'second largest portfolio holding' — announced 'a major contract with an undisclosed customer to provide AI compute capacity at its Monarch site in the United States', 'around USD 45 billion' of total contract value, submitted 'pursuant to the Securities Trading Act § 5-12 and MAR' at 18:46 CEST on Aug 26 2026. The customer is unnamed; the S-1's Anthropic agreements, signed the day before at Monarch for up to ~$44.6B, are the only Monarch customer contract in the S-1, so the record reads the two as one. Not independent of Nscale — Aker relays its holding's news — and the same notice on the investis and inderes feeds is one source, not three
“August 26, 2026 – Aker ASA announces that its second largest portfolio holding, Nscale, has signed a major contract with an undisclosed customer to provide AI compute capacity at its Monarch site in the United States. The contract represents a total contract value of around USD 45 billion.”
Aker ASA notice under MAR, Aug 26 2026 (via MFN) · mfn.se - four-agreementsfour agreements, one per tranche, each with its own Nscale subsidiary — split, the filed form says, 'at Provider’s request to facilitate Provider’s and Parent’s efforts to secure Qualifying Financing', while all four tranches are run together (filed-form). Each provider must stay under Nscale's control for the whole term, and Anthropic may terminate if one leaves it; a default under one of the other three agreements is not by itself a default under this one. The filed form's provider is Nscale GPU MCC B1.1 LLC ('MMC' in the S-1's exhibit index)
“The Anthropic Services Agreements are structured as four separate agreements, each between Anthropic and a wholly owned subsidiary of Nscale Limited.”
Nscale S-1 — Business, Customers and Business Model · sec.gov - tranches-and-termfour tranches of Vera Rubin NVL72, each on 'a multi-year service term commencing on acceptance', extendable at Anthropic's election. The form fixes the mechanics and blacks out the numbers: a 'Tranche Term' that begins on Acceptance and lasts 'the number of months specified above' — that cell is [***] — shortened at Anthropic's option by any unexcused delay beyond a redacted period; Anthropic may extend a tranche so that it ends with the last tranche under the other agreements, and extend again 'on the same terms and pricing' bar a redacted change to the GPU-hour price; the agreement runs to the 'Last Tranche Date'. The press's six years — 'The commitment is over six years' (Bloomberg, Aug 26 2026, people familiar), repeated by Reuters — has no filed source and is not adopted: Anthropic's S-1/A gives an end only, 'terms extending into 2033' (buyer-account), and no term. Nscale's weighted-average contract life rose from ~5.5 to ~5.7 years between Jul 31 and Aug 31 2026: a company-wide average that cannot date this contract
“Pursuant to the Anthropic Services Agreements, we will provide Anthropic with dedicated GPU infrastructure services at our Monarch Compute Campus, deploying NVIDIA Vera Rubin NVL72 GPUs across four tranches, each with a multi-year service term commencing on acceptance of the applicable tranche and subject to extension options exercisable at Anthropic’s election.”
Nscale S-1 — Business; S-1 ex-10.25, §5 and §7 · sec.gov - filed-formEX-10.25 is the form of one of the four orders — Anthropic PBC with Nscale GPU MCC B1.1 LLC, under the terms of service, security requirements and service-level agreement attached to it — for 'dedicated (single-tenant), exclusive access' to NVIDIA Vera Rubin NVL72 systems (72 GPUs / 36 CPUs each) plus 'the physical datacenter infrastructure (including facility, power, cooling, and network connectivity)', at an all-in price per GPU-hour. Everything that would size it is [***]: the site's name and address, the number of systems, total GPUs, 'Total Capacity', the expected delivery date, the price, the term in months, the estimated monthly fees, the payment terms and 'The estimated total value of this Order'. The press's 'about 460 megawatts' (Bloomberg, Reuters; CNBC: 'around 460 megawatts'; Semafor: 'the first of three buildings, covering 460 megawatts') has no filed source and is not adopted: the S-1's portfolio table lists one unnamed United States site — owned, 460 MW of IT capacity, contracted — but names neither site nor customer, so the record does not map it. Anthropic may also swap any tranche for a later NVIDIA or other-vendor GPU generation at a re-agreed price (§8)
“Accordingly, Provider will coordinate and align with Parent and the Other Providers to ensure that (i) all four (4) tranches at the Site are operated together in accordance with this Order and that the entire Site is fully dedicated to Anthropic”
S-1 ex-10.25, Order for GPU Services — §1 Background · sec.gov - pay-on-acceptanceAnthropic pays nothing for a tranche until it accepts it — then 'Monthly Payment = [(number of hours in the month) * (number of GPUs in the Tranche) * (price per GPU/hour)]' less service credits and late-delivery discounts, and the terms of service repeat that 'no payment obligation will begin, unless and until the entirety of such Tranche has been Accepted'. While a tranche is late Anthropic owes nothing for it, and a tranche accepted late carries discounted fees for a time (rates redacted). The form shows no upfront payment — Microsoft's filed statement of work schedules two per tranche (nscale-msft filed-form) — though its 'Payment Terms' cell is redacted. Nscale's book moved the same way: its weighted-average prepayment fell from 47% of active-and-contracted TCV at Jul 31 2026 (Aug 12 draft) to 23% at Aug 31 (S-1) while TCV rose from $51.3B to $103.4B — 0.47 × $51.3B ≈ $24.1B and 0.23 × $103.4B ≈ $23.8B, so the contracts added in August, Anthropic's among them, brought little or no prepayment (editor's arithmetic on company-wide averages; the S-1 states no Anthropic prepayment term). Anthropic's own S-1/A agrees on the mechanic: 'fees accruing only as capacity is delivered to and accepted by us' (buyer-account)
“To avoid doubt, no fees will be payable for a Tranche until after Anthropic’s Acceptance of that Tranche in writing.”
S-1 ex-10.25, Order for GPU Services — §5 Pricing; Fees · sec.gov - terminationAnthropic's exits, per the S-1: a tranche not delivered within a specified period after its expected delivery date can be terminated 'without liability'; delays are excused only for industry-wide supply constraints on the GPU systems and only if Nscale placed binding orders with its supplier within a specified period — and if even excused delays pass a threshold, Anthropic may still terminate the tranche; Anthropic may terminate a whole agreement 'if monthly uptime falls below specified thresholds for sustained periods'; and either side may terminate for an uncured material breach, insolvency or 'a change of control involving a disqualified person'. The S-1 calls the service levels 'more stringent than those contained in our other customer agreements' and offers 'only limited relief' for supply-chain delays. In the form, Anthropic owes nothing during a delay and, past the 'Further Delay' threshold, 'may terminate that Tranche in its entirety, without any payment or other obligation or liability of any kind' (§6(d)); every period and percentage is redacted. Anthropic's own S-1/A sums its exits up as 'non-cancelable except in limited circumstances, including Nscale’s failure to meet specified delivery or service availability requirements or an uncured material breach by the applicable Nscale entity' (buyer-account)
“If we fail to deliver any tranche within a specified period after its expected delivery date, Anthropic is entitled to terminate that tranche without liability.”
Nscale S-1 — Business, Customers and Business Model · sec.gov - financing-uncommittedthe build is not financed: at the S-1 'we have not obtained binding commitments for any of the financings required to fund performance', and Nscale is 'developing a plan involving multiple financing sources'. The agreements oblige it to use 'best efforts to obtain qualifying financing for the required GPU equipment and data center infrastructure at the Monarch Compute Campus within a specified period following the effective date' (financing-longstop). Contrast Microsoft's Texas statement of work, against which a $1.85B delayed-draw facility with investment-grade ratings was signed on Aug 27 2026 (nscale-msft texas-financing)
“As of the date of this prospectus, we have not obtained binding commitments for any of the financings required to fund performance under the Anthropic Services Agreements, and all such financings remain in process.”
Nscale S-1 — Risk Factors · sec.gov - funding-planhow Nscale says it will pay for the build — not with Anthropic's money up front: the sentence sits in a risk factor that says 'While we have historically been able to fund capital expenditures from cash generated from operations including meaningful customer prepayments' and warns of 'a reduction in the proportion of contract value that customers provide as prepayments'. With no fee before acceptance (pay-on-acceptance), the GPUs and the data center must be financed before any of Anthropic's fees arrive, and the form writes the financing test against 'customers having a credit and risk profile comparable to Anthropic’s' (financing-longstop)
“For example, we expect to fund the deployment required under the Anthropic Services Agreements through external financing and cash flows from operations.”
Nscale S-1 — Risk Factors · sec.gov - financing-longstopthe deadline that makes the whole contract conditional on Nscale's money: 'Qualifying Financing' means financing for the GPU systems plus 'financing and credit support for the data center facility', on terms no worse than market for 'customers having a credit and risk profile comparable to Anthropic’s'; Nscale must use best efforts to secure it 'as soon as possible and in any event no later than by the Longstop Date', report on it to Anthropic, and until then 'not offer, negotiate, or enter into any agreement, arrangement, or understanding with any third party to sell, lease, allocate, or otherwise make available any GPU capacity at the [***] Site'. Once the Longstop Date passes without it, either party may terminate, and 'neither party will have any further obligation or liability under this Order'. The period is [***]; the S-1 gives it as 'a specified period following the effective date (or such later date as may be mutually agreed and subject to additional negotiation)'
“If Provider has not obtained Qualifying Financing within [***] after the Effective Date, or such later date as the parties may mutually agree in writing (the “Longstop Date”), each party may terminate this Order on written notice given within [***] after the Longstop Date.”
S-1 ex-10.25, Order for GPU Services — §9 Financing · sec.gov - sitethe campus is Nscale's own: the AIPCorp purchase, completed Mar 31 2026; 'an approximately 2,250-acre site' with behind-the-meter power 'scalable to over 6.5 GW of IT load power and over 8 GW of gross power'. Nscale expects 'up to 2 GW of gross power generation capacity by the first half of 2028' — a first phase whose IT load the S-1 puts at 1.37 GW and the Aug 12 draft and Nscale's Monarch page at 1.35 GW, unreconciled — and ~8 GW of gross capacity 'planned for 2031'. Anthropic's share of the first phase is in no filing. The campus was first announced with Microsoft as its customer (a 1.35 GW letter of intent, Mar 16 2026 — nscale-msft monarch-loi); the S-1 names Anthropic at Monarch and Microsoft nowhere there (who-else)
“The Monarch Compute Campus expands our U.S. footprint with an approximately 2,250-acre site which can deliver up to 8GW of gross behind-the-meter power.”
Nscale S-1 — Business, Our Data Centers · sec.gov - power-permitthe campus has no grid to fall back on: Nscale's Monarch Cloud Campus, LLC applied in April 2026 for 'an off-grid electric power generation facility to support a dedicated data center campus', and West Virginia's Division of Air Quality, having found on a preliminary evaluation that the plant would meet air rules, put permit R14-0042 out for comment — public meeting Oct 20, written comments until Oct 30 2026 — with the applicant anticipating 'a facility startup date of April 2027'. The data center the plant is to supply is the campus Anthropic's tranches sit on; the permit was still a draft when Nscale filed its S-1
“On April 20, 2026, Monarch Cloud Campus, LLC (MCC) applied to the West Virginia Department of Environmental Protection, Division of Air Quality (DAQ), for a permit to construct an off-grid electric power generation facility to support a dedicated data center campus located at 30 Monarch Way”
West Virginia DEP, Division of Air Quality — notice of intent to issue permit R14-0042 (comments to Oct 30 2026) · apps.dep.wv.gov - first-capacitywhen Anthropic's capacity comes online, per the press only: the facility 'is expected to come online at the end of 2027' (CNBC, Aug 26 2026, two people with knowledge of the matter); the capacity is to start powering Anthropic's services in 'late 2027' (TechCrunch, the same day, one source); the Monarch campus 'is aiming to come online next year' (Semafor, Aug 28 2026). Anonymous throughout, and no filing confirms it: EX-10.25 redacts every expected delivery date (filed-form). Nscale's own dates are campus milestones, not a date for any of Anthropic's tranches: the power plant's 'facility startup date of April 2027' (power-permit), the first phase 'targeted for completion in early 2028' (Nscale, Aug 25 2026, the day the agreements were signed) and up to 2 GW of gross power by the first half of 2028 (site). They bracket the press's date rather than dispute it
“Anthropic will leverage Nvidia's advanced Vera Rubin chips through the facility, which is expected to come online at the end of 2027, the people said.”
CNBC, Aug 26 2026 · cnbc.com - who-elsethe site had other suitors: 'Google and Microsoft were both in talks' for the capacity that went to Anthropic — 'Microsoft walked away over the summer amid a review of its data center portfolio and its share of on-site power generation', Google after 'an internal review of the tech giant’s computing needs and capex management' (Semafor, Aug 28 2026, one person familiar; Microsoft declined to comment, Google did not respond). Bloomberg's Japanese edition (Aug 27) likewise has Microsoft, once expected to use the facility, pulling out early in the summer and Anthropic taking its place. On Nscale's paper Microsoft's 1.35 GW letter of intent of Mar 16 2026 drops out of the filings after the May 12 draft with no word on why — contested on nscale-msft (monarch-loi-status), not decided here
“Google and Microsoft were both in talks with Nscale to rent AI computing capacity from the company’s massive data center project in West Virginia — a lease that ultimately went to Anthropic, a person familiar with the matter told Semafor.”
Semafor, Aug 28 2026 · semafor.com
Scope note what this record leaves to other records
NOT this record (carried elsewhere): Nvidia's roles at Nscale — GPU maker, >5% shareholder, $1.2B customer, Ward County rent guarantor and $1.0B of the Sep 2026 pre-IPO convertible → nv-nscale; Microsoft's Monarch letter of intent and its fate → nscale-msft (monarch-loi, monarch-loi-filed, contested monarch-loi-status); Nscale's company-wide book ($103.4B TCV and the 23% prepayment average) → the nscale entity, used here only for the arithmetic in pay-on-acceptance; the S-1's '$52.5 billion' of GPU-cluster contracts signed after Jun 30 2026, also company-wide and not broken down by customer → the nscale entity. Whether Monarch's capacity counts toward Anthropic's Nov 2025 commitment of up to 1 GW on Nvidia systems (nv-msft-anthropic) or toward the '2.6 GW to date' Nvidia's Sep 2026 investor deck credits to Anthropic, no party says — never added. Not carried here: the power plant's permit detail (engines, nameplate, potential emissions, heat-rate limits; a January 2027 startup in the Sep 16 revised application vs April 2027 in the notice), the campus's acreage beyond the S-1's, its capex ('$20B+' on Nscale's Monarch page vs '$69.2 billion in planned expenditures' for Phase One in the EY study Nscale commissioned, and Bloomberg's ~$71B for the campus and its power plant), the AIPCorp price ($87.5M vs $99.6M of cash in two S-1 notes), NGO emissions models and Hope Gas's pipeline. Not adopted: the press's 'about 460 megawatts' and 'six years' (people familiar; the S-1 table's unnamed 460 MW row is not mapped — filed-form); Bloomberg's 'Anthropic PBC has agreed to spend $45 billion', firmer than the filing's 'up to … subject to'; TNW's 'Anthropic agreed on 26 August to pay Nscale $45B' and Observer's 'six-year, $45 billion lease', the anonymous terms restated as fact; DCD's 'more than 400MW' and its 'Microsoft signed on for 1.35GW'; Somen's 'Microsoft and Anthropic together carry 86 percent of the backlog' (the filed inputs give ~85.5% — ($43.8B + $44.6B) / $103.4B, editor's arithmetic on two 'up to' ceilings); Nvidia's 'selective credit enhancement for nearly 2 gigawatts of compute' for 'another frontier AI lab' (Q2 FY27 call), which names no lab. The $2.36B notes tranche is not carried on nv-coreweave-equity, and the 20-year PORTS-Pike leases are not carried on cw-openai; the $2.36B is on nv-nscale, and the $1.85B Ward County facility is already on nscale-msft.