Microsoft–Nebius

Microsoft committed to pay Nebius up to $17.4B to rent AI chip capacity through 2031, even if unused after delivery. It paid about $7B up front.

A deal between Microsoft, Nebius

Why it matters

Microsoft's contract accounts for half of Nebius's contracted backlog. Microsoft owes payment regardless of use once Nebius delivers the capacity from a single leased campus. Separately, Nebius's 20-F puts Customer D, which it does not identify by name, at 83% of receivables.

Tap a figure for the line in its source.

Microsoft gives Nebius

  • of fees through Oct 2031, owed once delivered, even if unused; up to $19.4B if Microsoft buys more
  • of that paid up front; the rest billed monthly

Nebius gives Microsoft

  • the GPU capacity, in nine batches from a leased New Jersey campus; in Nov 2026 Nebius expects over half delivered by year-end and the rest in Q2 2027

Sep 2025 announced by Nebiusupdated Nov 19, 2026operational disclosed by the parties

What happened

Microsoft agreed to rent GPU capacity from Nebius through 2031. It committed up to $17.4B, or up to $19.4B with add-ons, with about $7B paid up front. Once Nebius delivers the capacity, Microsoft owes payment whether or not it uses it. This is Nebius's anchor contract and accounts for roughly half its order book. Nebius delivers the capacity from a single leased campus in New Jersey. In November 2026 Nebius said it expects to have delivered more than half of that capacity by the end of the year. The remaining batches are now scheduled for the second quarter of 2027, after the campus operator, DataOne, began retiring some of the site's temporary power ahead of a move to permanent power. CoreWeave faces scrutiny for the same kind of dependence on one customer.

Sources 7 documents — 7 SEC filings

Research trail Found 593 documents and read 569 of them while checking this deal and related ones.

  1. SEC filingsec.gov
    States $17.4B contract value
  2. SEC filingsec.gov
    States $6958.1M committed fees precise
  3. SEC filingsec.gov
    States financing condition
  4. SEC filingsec.gov
    States delivery to date
  5. SEC filingsec.gov
    States delivery schedule
  6. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  7. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: Nebius 6-K (Sep 2025) + 424B5 + FY25 20-F (SOW filed as ex-4.4, Addendum 1 as ex-4.5) + Q2'26 and Q3'26 shareholder letters (6-K ex-99.2) · as of Nov 2026

The evidence 5 sourced figures · 2 disputes

The record's headline Microsoft–Nebius: $17.4B GPU services through 2031 (up to $19.4B)

Size
$17.4B base / up to $19.4B
When
Sep 2025 → Jan 2026 expansion
Status
operational
Structure
GPU-services offtake (SOW + Jan-2026 Addendum 1)
Programme
Microsoft–Nebius
Parties
Microsoft offtaker · Nebius neocloud provider
Record
disclosed / primary source · as of Nov 2026

Flows 1 as the record states them

  • Microsoft → Nebiuscompute-spend$17,392.9M committed through Oct 2031 incl. ~$6,958.1M upfront; up to ~$19.4B with additional purchases

Resolved figures 5 each with the verbatim line from its document

  • contract-value$17.4B
    $17.4B base through 2031 / up to $19.4B ONLY if Microsoft acquires additional services or capacity — a base/ceiling structure, not a range dispute. Press 'flat $19.4B' flattens the option into the commitment
    “Subject to the satisfaction of deployment and availability of the GPU clusters, the total contract value is about $17.4 billion through 2031. Microsoft may also acquire additional services and/or capacity under the agreement, which would increase the total contract value to about $19.4 billion.”
    Nebius 424B5, Sep 2025 · sec.gov
  • committed-fees-precise$6958.1M
    filed base $17,392.9M payable irrespective of utilization, incl. ~$6,958.1M aggregate upfront; invoiced monthly through October 2031. Delivery: nine tranches during 2025-26 from the Vineland NJ (DataOne) campus — same 20-F sentence cluster
    “Microsoft has committed to pay the Group fees under the Microsoft Agreement estimated to be up to $17,392.9, irrespective of actual utilization of the GPU capacity, including aggregate upfront payments of approximately $6,958.1, with the remaining consideration invoiced monthly over the service terms of the respective tranches through October 2031.”
    Nebius FY25 20-F · sec.gov
  • financing-condition
    a precondition: the contract's obligations 'will commence upon the confirmation by Nebius to Microsoft that it has secured any additional financing required' for its capital expenditures (6-K), and no fee is payable until then. The statement of work (§1.1A) gives two 'Completion Scenarios': '(i) Nebius obtains the financing related to this Agreement and evidences it to Microsoft', or '(ii) Nebius can finance this Agreement’s capital expenditure without the need for financing related to this Agreement, and notifies Microsoft in writing'; if neither is met within a redacted number of days, the agreement is 'considered not to have come into effect'. The first delivery could not come before one was met, and Nebius delivered the first tranche in November 2025 (20-F): one was met by then, eight months before its first secured loan (nb-secured-2026). Which one, no document on file says. The contract may be pledged: Nebius and any assignee may 'pledge, assign, collaterally assign, hypothecate, sell, convey, or grant a lien or security interest' in the agreement, its receivables and their proceeds, including under a loan from third-party lenders (§26(b)). The 6-K adds that the agreement's cash flow 'will be utilized to finance part of the capital expenditure associated with the Agreement'
    “The obligations of the parties under the Agreement will commence upon the confirmation by Nebius to Microsoft that it has secured any additional financing required in respect of the capital expenditures under the Agreement.”
    Nebius 6-K (Sep 2025); statement of work §1.1A and §26(b), FY25 20-F ex-4.4; FY25 20-F for the first delivery · sec.gov
  • delivery-to-date
    as of Nebius's Q2'26 letter (Aug 12 2026): 'all capacity tranches' delivered to Microsoft 'to date', two of them in the month before. The Jul 17 financing release said the same of the 'latest planned capacity tranche', with Nebius 'on track to deliver the remaining tranches consistent with the terms of the contracted schedule'. Neither says how many of the nine tranches that was, or which were still to come; the Nov 12 letter (delivery-schedule) then moves the rest to Q2 2027, and no letter reconciles the Aug 12 'all capacity tranches' with that
    “To date, we’ve delivered all capacity tranches to Microsoft under the contract, including two tranches over the past month.”
    Nebius Q2'26 shareholder letter (6-K ex-99.2), Aug 12 2026 · sec.gov
  • delivery-schedule
    a slip, in Nebius's own words: by year-end 2026 'more than half of the capacity contracted with Microsoft' delivered, the remaining tranches 'now scheduled for 2Q27'. The cause it gives is the campus operator's: 'In late Q3, DataOne started to retire some of the site’s temporary generation ahead of the move to permanent power. That decision reset the schedule for the remaining tranches. Microsoft has been part of the planning process.' Bloom Energy fuel cells are to be the site's main power (Bloom generation 'already online', being scaled). Its heading: 'Shifts in colocation timelines do not reflect structural change'. The letter says nothing about whether the contract's schedule, the $17.4B, or the ~$7B upfront changed, and none of the three is restated
    “In New Jersey, we now expect to have delivered more than half of the capacity contracted with Microsoft by the end of the year, with the remaining tranches now scheduled for 2Q27.”
    Nebius Q3'26 shareholder letter (6-K ex-99.2), Nov 12 2026 · sec.gov

Contested figures 2 not reconciled — every position side by side, with its source and tier

gpu-countone entry, in its own words
>100,000 GB300s — an unattributed industry estimate repeated by two trade outlets; the filed agreement names nine tranches but NO GPU count DCD / Data Center Frontier
vineland-rampone entry, in its own words
the contracted campus's operational state vs its 300-400MW target is disputed (~2MW operational early 2026 per one tier-3 site analysis; energy plan 'pending/on hold' late May 2026); Nebius reported delivery to Microsoft on track through 2026 (Q4'25 letter; Jul 17 and Aug 12 2026) until its Nov 12 letter moved the remaining tranches to Q2 2027 and named the site's temporary power and the move to Bloom fuel cells as the cause (delivery-schedule) northwiseproject (tier 3) vs Nebius Q4'25 letter and Q3'26 letter (tier 1)

More between Microsoft and Nebius

The record holds no other deal between them.

Everything between Microsoft and Nebius →