Why it matters
Google is both the customer and the lender for its Black Hills power deal. It advanced $398.8 million to reserve equipment and covers the full cost of the gas generation Black Hills will own and earn a return on. The terms that would show whether any costs fall on other customers are undisclosed.
Tap a figure for the line in its source.
Black Hills Corp. gives Google
- of grid-connected energy service under Black Hills' large-load (LPCS) tariff through December 2048 — from new gas generation Black Hills builds at its Cheyenne Prairie station through a non-regulated affiliate, and 26 of market energy and retail service; from late 2027, ramping to the data center's peak load by the end of 2030
- of third-party plants, contracted under long-term PPAs, whose output Black Hills manages for the campus on a privately run microgrid, for microgrid management fees — which plants, Black Hills does not say
- the total resource mix contracted to serve the project — the 590 and the ~2.1 together, reserve margins included and transmission expansion excluded; the load it serves, the contracts keep confidential
Google gives Black Hills Corp.
- of refundable advances for long lead-time generation equipment under the parties' generation reservation agreement, signed Apr 22 2026 — a liability Black Hills expects to repay by their Jun 30 2027 maturity
- all the costs of serving the data center, by Black Hills' account: a return on the generation investment, recovered in full over the contract term and billed to Google, not to Black Hills' other customers, and microgrid management fees on a contracted minimum peak load — backed by collateral and early-termination terms that are not public; Black Hills expects the project to bring it about $150M of net income in 2030
What happened
Black Hills, the Cheyenne-area utility, signed agreements to power Google's planned data center there through 2048. The agreements took effect on September 30, 2026. Black Hills will supply up to 590 megawatts from the grid. Most will come from new gas generators it is spending about $1.8 billion to build at its Cheyenne Prairie plant. The contracts cover that cost in full. Black Hills will also collect a fee to run a private grid, delivering about 2.1 gigawatts from other companies' plants to Google's campus. The combined supply is 2.7 gigawatts, including spare capacity. Before the deal was final, Google advanced $398.8 million so Black Hills could reserve the generating equipment. Black Hills is to repay the advance by June 2027. Black Hills says Google bears all the costs of serving the data center. It expects the project to earn it about $150 million in 2030 and keeps the data center's power demand confidential.
Sources 14 documents — 5 SEC filings · 4 press reports · 2 company releases · 1 transcript · 1 government statement · 1 research note
Research trail Found 348 documents and read 320 of them while checking this deal and related ones.
- States 6 figures: agreements · 2.7 GW resource mix · up to 590 MW grid service · 2.1 GW microgrid · $1.8B generation investment · $398.8M advances
- States 3 figures: cost recovery · $150M net income · $2.4B cash flow
- States announced
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: Black Hills 10-Qs for Q1 (May 7 2026), Q2 and Q3 2026 — the reservation agreement, the advances and Note 3's Google data center agreements; Black Hills release (Oct 6 2026; 8-K ex. 99.1, furnished) and Q3 2026 release (8-K ex. 99) and call (Earnings Whispers transcript); Wyoming DEQ siting notice; Google's post (Nov 5 2026); POWER, Cowboy State Daily (Jun 11 and Jul 8 2026), Measured AI and everydatacenter for the contested cells and the note (read 2026-11) · as of Nov 2026
The evidence 10 sourced figures · 3 disputes
The record's headline Black Hills–Google: power for Google's planned Cheyenne data center through Dec 2048 — up to 590 of grid service, most of it from new gas generation Black Hills builds for ~$1.8B, and ~2.1 of third-party plants it manages on a private microgrid, 2.7 GW in all with reserves; Google advanced $398.8M for the equipment, to be repaid by Jun 30 2027
- Size
- up to 590 MW grid-connected (new company-owned gas generation, 564 MW nameplate by Black Hills, + 26 MW market/retail) · ~2.1 GW third-party resources managed on a private microgrid · 2.7 GW total with reserves · ~$1.8B generation investment, 2027–2029 · $398.8M refundable advances from Google, due Jun 30 2027 · through Dec 2048
- When
- Jul 24 2025 (Crusoe and Tallgrass announce a 1.8 GW campus in southeast Wyoming) → Apr 22 2026 (generation reservation agreement with a prospective customer, unnamed) → May 7 2026 (Q1 10-Q: ~$201M of advances) → Jun 30 2026 ($285M received) → Jul 2026 (amended: $377M, due Aug 31) → Q3 2026 (amended: $398.8M, due Jun 30 2027) → Sep 30 2026 (definitive agreements effective) → Oct 6 2026 (announced, naming Google) → late 2027 (energy service begins) → 2027–2029 (generation built) → end-2030 (peak load) → Dec 2048 (agreements end)
- Status
- agreements effective Sep 30 2026, announced Oct 6 2026; energy service from late 2027, peak load by the end of 2030; the generation built 2027–2029, in service in phases 'through the latter half of 2029' (Q3 call); the advances due Jun 30 2027. Permits: the Robinson substation's certificate approved May 2026, the Cheyenne Prairie expansion's air permit approved Aug 2026, its industrial siting permit filed Jul 2026 (the release)
- Structure
- two agreements effective Sep 30 2026, both through December 2048 — a Large Power Contract Services Agreement (LPCSA), under Black Hills' Wyoming large-load (LPCS) tariff, and a Generation Facilities Agreement (GFA) — between Black Hills and Google, entered into 'with Google and other third-party partners' (Q3 10-Q). Black Hills' non-regulated affiliate builds and owns new gas generation at the Cheyenne Prairie Generating Station and supplies it to the regulated utility (Cheyenne Light, Fuel and Power, d/b/a Black Hills Energy) under a PPA, earning a return billed directly to Google; the utility manages ~2.1 GW of third-party resources, supplied under long-term PPAs, through a private microgrid for management fees. Before them, a generation reservation agreement of Apr 22 2026 between the utility and the then-unnamed customer — 'a bridge agreement to support long lead-time items' — under which Google advanced the money for the equipment, amended twice
- Programme
- Time-to-power
- Parties
- Google customer — the planned Cheyenne data center's owner (googlecheyenne), which takes the service, bears the costs of serving it by Black Hills' account, and advanced the money for the generating equipment · Black Hills Corp. utility and microgrid manager — its Cheyenne utility serves the campus under the LPCS tariff; a non-regulated affiliate builds and owns the new gas generation; it manages the ~2.1 GW of third-party resources for fees
- Site
- Google Cheyenne
- Record
- disclosed / primary source · as of Nov 2026
Flows 3 as the record states them
- Black Hills Corp. → Googlepowerup to 590 MW of grid-connected energy service (new company-owned gas generation, 564 MW nameplate by Black Hills' count, and 26 MW of market energy and retail service) and the managed output of ~2.1 GW of third-party resources on a private microgrid — 2.7 GW with reserve margins — from late 2027, ramping to peak load by the end of 2030, through December 2048
- Google → Black Hills Corp.power-paymentsall costs of serving the data center, by Black Hills' account: a return on and full recovery of the ~$1.8B generation investment over the contract term, billed directly to Google; microgrid management fees on a contracted minimum peak load; the market energy and retail service — no rate or total is public
- Google → Black Hills Corp.financing$398.8M of refundable advances under the parties' generation reservation agreement (Apr 22 2026, amended twice), for milestone payments on long lead-time generation equipment — a liability Black Hills expects to repay by Jun 30 2027 (the Q2 10-Q files the agreement under short-term debt)
Resolved figures 10 each with the verbatim line from its document
- announcedfirst public on May 7 2026, without the customer's name: Black Hills' Q1 10-Q disclosed that on Apr 22 2026 its Cheyenne utility had entered into a generation reservation agreement with 'a prospective new customer seeking to construct a 1.8 GW data center', and had received 'approximately $201 million in refundable CIAC payments' — the agreement the Q3 10-Q and the Oct 6 release call 'the parties' generation reservation agreement', under which, the release says, 'Google has provided Black Hills with $399 million of refundable advances'. In June, after Crusoe left the campus, Black Hills said the project 'has not been paused' and that the customer 'has provided over $200 million in refundable contributions' (Cowboy State Daily). The definitive agreements, effective Sep 30 2026, were announced on Oct 6 2026, naming Google
“On April 22, 2026, Wyoming Electric entered into a generation reservation agreement with a prospective new customer seeking to construct a 1.8 GW data center under Wyoming Electric's LPCS Tariff.”
Black Hills 10-Q for Q1 2026 (May 7 2026) · sec.gov - agreements2048an LPCS agreement and a generation facilities agreement, effective Sep 30 2026, 'both of which extend through December 2048' — entered into 'with Google and other third-party partners', who are not named (Q3 10-Q); the release: 'definitive agreements effective Sept. 30, 2026, with terms through 2048'. Service 'to begin taking energy service in late 2027' and ramp to the data center's projected peak load 'by the end of 2030' (Q3 10-Q; the release: 'in 2030'). Before the agreements, in June 2026, service to the data center was 'targeted for early 2028' (Cowboy State Daily)
“The negotiated agreements include a LPCS agreement and a generation facilities agreement, both of which extend through December 2048.”
Black Hills 10-Q for Q3 2026 (Nov 2026) — Note 3 · sec.gov - resource-mix2.7 GW2.7 GW in all, 'including reserve margins' and 'exclusive of additional transmission system expansion investments' (the release) — the 590 MW and the ~2.1 GW. Black Hills' own measure of supply, not the campus's load, which it keeps confidential (load); not the '2.7 GW' of the Crusoe-era press of Jan 2026, which described the campus's planned gas generation (note)
“The project is contracted to be served through a total resource mix of 2.7 GW, including reserve margins, and is expected to begin taking energy service in late 2027 and ramp to the data center’s projected peak load by the end of 2030.”
Black Hills 10-Q for Q3 2026 — Note 3 · sec.gov - grid-serviceup to 590 MWup to 590 MW of grid-connected service: new company-owned gas generation (contested new-generation: 564 MW nameplate by Black Hills, 552 MW added by the state's siting notice) and 'The remaining 26 MW', from 'a combination of market energy purchases and retail utility service provided under the company’s applicable industrial tariff' (the release). On the Q3 call the company-owned generation is 'supplied by our non-regulated affiliate to our regulated utility under a PPA', its return 'billed directly to Google'. For scale: the Cheyenne utility's all-time peak was 439 MW, set Jul 20 2026 (Q3 10-Q)
“We expect to provide up to 590 MW of grid-connected energy service through company-owned generation and market energy.”
Black Hills 10-Q for Q3 2026 — Note 3 · sec.gov - microgrid2.1 GW~2.1 GW of 'Wyoming-based, third-party contracted resources' (the release) whose output Black Hills manages through a privately managed microgrid, earning microgrid management fees — 'a negotiated rate based upon a contracted minimum peak load', from late 2027 and rising on 'a contractually defined ramp schedule' (the release). On the Q3 call: 'third-party co-located resources', '2.1 gigawatts of third-party generation supplied under long-term PPAs, with our regulated utility, and Google'. Black Hills names none of them (in-microgrid); Google names its suppliers as AEP's fuel cells and 'gas generators operated by Tallgrass Energy and Black Hills Energy'
“In addition, we expect to manage the output of approximately 2.1 GW of third-party contracted resources through a privately managed microgrid under the Company’s LPCS tariff.”
Black Hills 10-Q for Q3 2026 — Note 3 · sec.gov - generation-investment$1.8B~$1.8B, 2027–2029, through a non-regulated affiliate at the existing Cheyenne Prairie Generating Station; construction from 2027 and in service 'in multiple phases through the latter half of 2029' (Q3 call), earning 'a risk-adjusted, utility-like return on a rate-based model' from the start of construction; 'the GFA provides for full recovery of all generation capital investment over the contract term' (the release). To be financed 'through a combination of project-generated cash flow and debt and equity instruments' (Q3 10-Q). Its long lead-time equipment was reserved with Google's advances (advances)
“To provide 590 MW of grid-connected service, the Company expects to invest approximately $1.8 billion to construct 564 MW (nameplate capacity) of new company-owned natural gas generation between 2027 and 2029 through a non-regulated affiliate, which will be located at the Company's existing CPGS facility.”
Black Hills 10-Q for Q3 2026 — MD&A · sec.gov - advances$398.8M$398.8M, recorded at Sep 30 2026 'as a liability' that Black Hills 'expects to repay … by their June 30, 2027 maturity date' (Q3 10-Q); '$399 million of refundable advances for the procurement of long lead-time equipment' in the release. A series, not a dispute: ~$201M 'to date' at the Q1 10-Q (then 'refundable CIAC') → $285M received by Jun 30 → in July, the agreement amended 'to increase the total refundable advances to $377 million with a new maturity date of August 31, 2026' (Q2 10-Q, which files it under short-term debt) → in Q3, amended again 'to increase the permitted advances to $398.8 million and extend the repayment date to June 30, 2027', the ceiling the recorded liability reaches. The cash went to 'milestone payments for long lead-time generation equipment for the Google data center project' (Q3 10-Q). Money lent, not paid: refundable, recorded as a liability
“As of September 30, 2026, the Company had recorded $398.8 million of refundable customer advances as a liability on its Consolidated Balance Sheets and expects to repay such advances by their June 30, 2027 maturity date.”
Black Hills 10-Q for Q3 2026 — Note 3 · sec.gov - cost-recoveryBlack Hills' account: Google bears all the costs of serving the data center — 'Cost pass-through mechanisms', 'Stranded asset risk protection – the GFA provides for full recovery of all generation capital investment over the contract term', 'Early termination protection' and 'Credit protections – strong collateral and financial assurance requirements back the data center’s long-term commitments' (the release; the Q3 10-Q files the same four, 'intended to prevent cost shifting to existing retail customers', but not the sentence that Google bears all costs); the terms of each are not public. Google's own pledge: 'We will pay for 100% of the power we use'
“Importantly, these agreements and supporting regulatory mechanisms are structured so that Google bears all costs associated with serving the planned data center throughout the life of the project.”
Black Hills release (Oct 6 2026; 8-K ex. 99.1, furnished) · sec.gov - net-income$150M~$150M of net income in 2030, from the return on the generation investment and the management fees, 'contracted to begin contributing to earnings in 2027' — Black Hills' forecast, furnished, not filed; the split between returns and fees is not given
“The project is expected to provide approximately $150 million of net income in 2030.”
Black Hills release (Oct 6 2026; 8-K ex. 99.1, furnished) · sec.gov - cash-flow$2.4B~$2.4B of unlevered free cash flow through 2048, after the $1.8B of generation investment — Black Hills' forecast, furnished, not filed; the est ribbon adds the two (link comment)
“The project is expected to deliver approximately $2.4 billion of unlevered free cash flow, net of $1.8 billion of generation capital investment.”
Black Hills release (Oct 6 2026; 8-K ex. 99.1, furnished) · sec.gov
Contested figures 6 not reconciled — every position side by side, with its source and tier
Scope note what this record leaves to other records
Not this record: AEP's fuel-cell plant for the same campus (pw-aep-google); the campus and Tallgrass's Cheyenne Power Hub, ~1,150 MW of gas turbines in its first phase (the googlecheyenne site); Black Hills' transmission for this and other large loads — CPCNs requested for $686M of Wyoming transmission expansion, which with the $1.8B makes the ~$2.5B Black Hills calls 'significant upside to our current plan' (Q3 release); the pending merger with NorthWestern (the blackhills entity). Not adopted: '2.7 GW' is two numbers — Black Hills' resource mix, and the Crusoe-era Jan 2026 figure for the campus's planned gas generation (POWER's headline then: 'Includes 2.7 GW of New Natural Gas-Fired Generation'); the 600 MW cap on output from the Cheyenne Power Hub onto Black Hills' transmission (Measured AI, from the FERC waiver application) is not the 590 MW; '$399 million' rounds the filed $398.8M, and the series of advances ($201M → $285M → $377M → $398.8M) is one agreement amended, never a sum.