Why it matters
A tenant paying its landlord's way in: CoreWeave paid $30M outside the rent for in Blockfusion, most of which went to its secured lenders, and agreed to $50M more toward the power hookup. Blockfusion had $0.1M of cash at the end of June, a going-concern warning and no financing agreed for a build it puts at over $950M. CoreWeave's firm part is 35 ; the 'up to $2.8 billion' headline counts 85, 50 of them only if conditions are met.
Tap a figure for the line in its source.
Blockfusion gives CoreWeave
- of critical IT load, take-or-pay, through its subsidiary North East Data: 25 targeted for February 2028 and 10 MW for August 2028, both ending 15 years after the later one starts, with two five-year renewals
- shares under a at $7.6898 each; if Blockfusion's merger with the listed shell company Blue Acquisition closes, it becomes a seven-year warrant on 2,870,813 shares of the merged company at $7.4643
- more, which CoreWeave has committed to lease only once conditions are met, chiefly firm commitments for more power; plus a right, not an obligation, to up to 215 more through 2030
CoreWeave gives Blockfusion
- rent for 15 years, rising 3% a year, with power passed through at cost. The filed lease keeps its rate confidential; its definitions name $145 a kW a month. Worked back from the landlord's $2.8B estimate for 85 as a flat rate with no yearly rise, the rent comes to about $183. No filing gives the 35 MW lease's total
- one-off charge toward the transmission and electrical capacity the site needs, in two $25M payments: the first received Oct 5 2026, the second expected in November
- cash, not refundable and not counted toward rent, paid Sep 10 2026 for the ; most of it went to paying off Blockfusion's secured loans
What happened
Blockfusion runs a data center for crypto-mining customers on the site of a former power plant in Niagara Falls, New York. It is turning the site into an AI data center while it merges with Blue Acquisition, a listed shell company, to trade on Nasdaq. In September 2026 its subsidiary North East Data leased CoreWeave 35 megawatts there on a take-or-pay basis, for 15 years with two five-year renewals. The two phases are targeted for February and August 2028, later than the 2027 of the June letter of intent, and CoreWeave pays for each only once it is built and powered. CoreWeave also agreed to pay $50 million toward the site's power hookup. It paid $30 million, not counted as rent, for a to buy Blockfusion shares, and most of that went to paying off Blockfusion's secured lenders. Elsewhere the landlord pays: Applied Digital gave CoreWeave warrants with its leases. CoreWeave committed to 50 megawatts more only once conditions are met, chiefly firm power the site has yet to secure, and may take up to 215 more. Blockfusion first gave its estimate of up to $2.8 billion in revenue for a letter promising 85 megawatts of guaranteed take-or-pay. In the proxy the same figure counts 85 megawatts only if the conditions are met, not the 35 signed. Blockfusion had about $0.1 million of cash at the end of June and a going-concern warning. It expects the build to cost over $950 million and had no financing agreed when the proxy went out. Every figure comes from the landlord's side: CoreWeave's own quarterly report names neither Blockfusion nor the site, and no filing prices the 35 megawatts signed. The shareholder vote on the merger, set for November 17, was postponed.
Sources 16 documents — 12 SEC filings · 3 company releases · 1 other document
Research trail Found 100 documents and read 94 of them while checking this deal and related ones.
- States 22 figures: 35 MW lease · 25 MW phases · lease term · late delivery · build status · 50 MW site power · up to $2.8B revenue estimate · $50M nrc · $25M nrc received · $30M cash contribution · $30M cash received · $20.4M debt repaid · warrant · pubco warrant · coreweave stake · warrant side letter · $50M guaranty · 50 MW expansion · expansion conditions · up to 215 MW option capacity · $0.1M landlord cash · more than $950M build cost
- States 2 figures: 85 MW LOI · $2.8B LOI estimate
- States $145 design rent
- States 3% escalator
- States merger postponed
- States 25 MW LOI timeline
- States announced
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- GlobeNewswire: Blue acquisition corp announces postponement of the extraordinary general meeting to…Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: Blue Acquisition DEFM14A (filed Oct 23 2026) and the agreements filed with the Sep 2026 S-4/A (the lease, Expansion Capacity and ROFO Agreement, warrants, side letter and completion guaranty); Blue's 8-K/A (Item 8.01; filed Nov 16 2026); Blockfusion's releases of Jun 30 and Sep 16 2026 (the latter under Rule 425), management's Jun 30 2026 remarks (furnished) and the investor presentations of Nov 2025 and Sep 2026; Barrio Energy (Sep 22 2026) · as of Nov 2026
The evidence 29 sourced figures · 3 disputes
The record's headline CoreWeave–Blockfusion, Niagara Falls NY: a 35 take-or-pay lease for 15 years from 2028 (targeted), a $50M charge toward the site's power hookup, and $30M paid outside the rent for a on 2.79M of the landlord's shares — 50 MW more only once conditions are met; the landlord's 'up to $2.8B' counts 85 MW
- Size
- 35 MW of critical IT, take-or-pay (25 MW + 10 MW, targeted Feb and Aug 2028) · 15-year term, both phases ending together, two 5-year renewals · $50M non-recurring charge · $30M for a warrant on 2,786,624 shares at $7.6898 · 50 MW more on conditions, up to 215 MW more at CoreWeave's option · no filed value for the 35 MW; the landlord's estimate is up to $2.8B for 85 MW
- When
- Jun 30 2026 non-binding letter of intent with an unnamed 'leading AI customer' (up to 300 MW, 85 MW of it guaranteed take-or-pay; first 25 MW targeted for 2027) → Sep 4 2026 lease, Expansion Agreement, warrants and guaranty signed → Sep 10 $30.0M received → Sep 16 announced, naming CoreWeave → Oct 5 first $25.0M of the charge received → Oct 22–23 proxy/prospectus effective and filed → Nov 13 merger vote postponed → Feb 2028 Phase 1 (25 MW) and Aug 2028 Phase 2 (10 MW) targeted → initial term ends 15 years after the last phase starts (Aug 2043 on the targets, our arithmetic)
- Status
- lease effective Sep 4 2026 · $30.0M received Sep 10 2026 · first $25.0M of the charge received Oct 5 2026, the second expected in November (no document on file confirms it) · phases targeted Feb and Aug 2028; at the proxy's date the build's design was under way, its construction agreements expected in Oct 2026 and its building permits not yet applied for · no expansion condition shown met · the merger vote set for Nov 17 2026 was postponed on Nov 13 until further announcement, so the Pubco warrant and guaranty have not replaced Blockfusion USA's
- Structure
- a datacenter lease dated Sep 4 2026 between North East Data, LLC (Blockfusion USA's wholly owned subsidiary, the landlord and owner of 5380–5384 Frontier Avenue, Niagara Falls NY) and CoreWeave, Inc., for 35 MW of critical IT load in two phases (Floor 1: 25 MW in data hall 1, 10 MW in data hall 2), take-or-pay, power passed through at cost; an Expansion Capacity and ROFO Agreement of the same day between Blockfusion USA, Inc. and CoreWeave — 50 MW of 'Firm Expansion Capacity' that becomes take-or-pay only on the Tranche 2 Power Conditions, up to 215 MW more at CoreWeave's option through Dec 31 2030, and a right of first offer above 300 MW; a Series A warrant from Blockfusion USA for CoreWeave's $30M cash contribution, with a Pubco warrant held in escrow to replace it at the merger's closing; a warrant side letter; and Blockfusion USA's completion guaranty, to be replaced by Pubco's. CoreWeave secures the lease with standby letters of credit from an A-rated bank, partly replaceable by surety bonds and waived while it is investment grade (§6.1; the amount is redacted); no guaranty from a CoreWeave parent is required at signing. Blockfusion USA is to merge with Blue Acquisition Corp., a Nasdaq-listed SPAC, under Blockfusion Digital Infrastructure, Inc. ('Pubco')
- Programme
- CoreWeave contract web
- Parties
- CoreWeave tenant under the lease (CoreWeave, Inc.) and party to the Expansion Agreement; pays the $50M charge and paid the $30M cash contribution; holds the warrant. Its Q3 2026 10-Q names neither Blockfusion nor the site · Blockfusion landlord through its wholly owned North East Data, LLC; Blockfusion USA, Inc. signs the Expansion Agreement, issues the warrant and guarantees completion; Blockfusion Digital Infrastructure, Inc. (Pubco), the company the merger would list, issues the replacement warrant at closing
- Record
- disclosed / primary source · as of Nov 2026
Flows 6 as the record states them
- Blockfusion → CoreWeavecapacity35 MW of critical IT load at the Niagara Facility, take-or-pay — 25 MW targeted Feb 2028, 10 MW Aug 2028; 50 MW more committed on conditions (Firm Expansion Capacity); up to 215 MW more at CoreWeave's option through Dec 31 2030, up to 300 MW in all
- CoreWeave → Blockfusionlease-paymentsbase rent per kW a month until 15 years after the later phase starts (two five-year renewals): $145.00 by the lease's definition of its design basis, the rent item itself redacted (contested initial-rent), escalating 3.0% a year compounding; no filing values the 35 MW; the landlord estimates up to $2.8B over the initial terms for 85 MW, assuming the expansion's conditions are met; power passed through at cost
- CoreWeave → Blockfusionnrc$50M non-recurring charge toward transmission and electrical capacity, two $25M installments within 30 and 60 days of signing — $25.0M received Oct 5 2026, the second expected in November 2026; partly refundable if the lease ends for late delivery
- CoreWeave → Blockfusionwarrants$30.0M cash contribution, non-refundable and not applied against rent, received Sep 10 2026 — the consideration for the warrant
- Blockfusion → CoreWeaveequity-rightswarrant on 2,786,624 Blockfusion USA Series A shares at $7.6898 (Sep 4 2026), exercisable from Jan 1 2027 or the merger's termination; at the closing it is replaced by a warrant on 2,870,813 Pubco Class A shares at $7.4643, exercisable for seven years; more warrants if CoreWeave contracts for capacity beyond the 300 MW
- Blockfusion → CoreWeavecompletion-guarantyBlockfusion USA guarantees North East Data's completion obligations, up to $50M initially, until 90 days after Phase 2 commences; Pubco's guaranty replaces it at the closing
Resolved figures 29 each with the verbatim line from its document
- lease35 MW35 MW of critical IT load at the Niagara Facility, delivered to CoreWeave by North East Data ('NED') on a take-or-pay basis — 'meaning CoreWeave must pay for the full contracted load whether or not it uses it', as the proxy puts it; power is passed through at cost and base rent escalates at a fixed rate each year. The lease itself: 'Critical Load Power: 35 megawatts (MW)', Phase 1 '25MW DH1', Phase 2 '10MW DH2'. Every document that states it is the landlord's or the SPAC's; CoreWeave's own Q3 2026 10-Q names neither Blockfusion nor the site
“Under the CoreWeave Lease, NED has agreed to deliver 35 MW of critical IT load capacity at the Niagara Facility to CoreWeave on a take-or-pay basis.”
Blue Acquisition DEFM14A (filed Oct 23 2026), Information About Blockfusion — CoreWeave Agreements · sec.gov - phases25 MWtwo phases, targeted for February 2028 (25 MW) and August 2028 (10 MW) — 17 and 23 months after the Sep 4 2026 effective date, the proxy says; the lease redacts the offsets. Each phase's rent starts only when its conditions are met: the landlord's installations substantially complete and commissioned, a certificate of occupancy from the city, and the phase's full critical load power energized with every utility contract and approval in force. At the letter-of-intent stage the first 25 MW was targeted for 2027 (loi-timeline)
“The CoreWeave Agreements require capacity to be delivered in two phases: (i) 25 MW targeted for February 2028 (“Phase 1”) and (ii) 10 MW targeted for August 2028 (“Phase 2”).”
Blue Acquisition DEFM14A (filed Oct 23 2026), CoreWeave Agreements · sec.gov - lease-term15 years15 years, both phases ending together: the lease's Initial Term runs each phase 15 years from its own commencement but extends the earlier one to be 'co-terminus' with the latest, so all expire 'fifteen (15) years after the Commencement Date for the last Phase to be delivered' — about Aug 2043 on the targets (our arithmetic) — then 'Two (2) Extension Options, each to extend the Term for an Option Term of sixty (60) months' at CoreWeave's election
“The initial term is 15 years from the commencement date of each phase (with both phases expiring co-terminously after the commencement date for the last Phase), with two five-year renewal options exercisable by CoreWeave.”
Blue Acquisition DEFM14A (filed Oct 23 2026), CoreWeave Agreements; the lease (S-4/A ex. 10.51), Basic Lease Information, Item 7 · sec.gov - late-delivery180 daysthe landlord's risk: rent credits that grow with any delay, and CoreWeave may terminate if a phase is more than 180 days past its original target (extended for delays CoreWeave causes and, up to 90 days, for force majeure), getting back the refundable part of the $50M charge and owing no fee. The credits' size is not disclosed
“If delivery is late (subject to certain permitted extensions), CoreWeave receives rent credits that increase with the duration of the delay and may terminate if the delay extends beyond 180 days after the original target commencement date for the applicable Phase (subject to extension for delays caused by CoreWeave and, for up to 90 days, force majeure events), in which case the refundable portion of the non-recurring charge is returned to CoreWeave and no termination fee is owed.”
Blue Acquisition DEFM14A (filed Oct 23 2026), CoreWeave Agreements · sec.gov - build-statusat the proxy's date no building permit had been applied for: Blockfusion had engaged Gensler and JB&B for planning and preliminary design, expected to finalize its architecture, engineering and construction agreements in October 2026, and said completing the landlord's installations 'depends on Blockfusion obtaining substantial additional financing'. Its existing state environmental review and local land-use approvals cover the site's footprint for up to 50 MW (site-power)
“Landlord’s Installations for each Phase will also require building and electrical permits from the City of Niagara Falls, and each Phase will require a certificate of occupancy or equivalent approval before it can be delivered. NED has not yet applied for these permits.”
Blue Acquisition DEFM14A (filed Oct 23 2026), Landlord's Installations — Current Status · sec.gov - site-power50 MWabout 50 MW of gross power at the site today, enough under its current business, the proxy says, to deploy about 46 MW to its digital-asset mining clients; the 35 MW lease is measured as critical IT load, a different basis. The two phases' power must be energized on a firm basis before each starts (phases)
“Based on current Company operational infrastructure, the approximate gross power capacity of the Niagara Facility as of the date of this proxy statement/prospectus is 50 MWs, which at current gross to net power capacity ratios, enables Blockfusion to deploy approximately 46 aggregate MWs of power pursuant to client agreements under its current business model.”
Blue Acquisition DEFM14A (filed Oct 23 2026), Niagara Facility Location and Power Access · sec.gov - design-rent$145$145.00 per kW a month — the rate the lease's definitions say its Base Rent was calculated at, on the Base Design Specifications (Exhibit F). The rent item itself is redacted ('The initial Base Rent for Phase 1 shall be [***] per kW per month'; Phase 2 starts at Phase 1's then-escalated rate), so no filing states the rent in force outright (contested initial-rent). On our arithmetic, $145 on 85 MW rising 3% a year for 15 years comes to ≈ $2.75B, the landlord's 'up to $2.8 billion' (revenue-estimate); on the 35 MW leased, ≈ $1.1B. Before it had a tenant, Blockfusion's November 2025 forecasts assumed a '$150/kW Leasing rate', 'assumed to be equal to prevailing market rate based on Management’s knowledge of the market' (investor presentation, Nov 2025, furnished; it gives no period) — a market assumption, not a rate for this lease
““Base Design Specifications” means the design specifications for the Premises on which the Base Rent of $145.00 per kW per month was calculated, as more particularly described in Exhibit F attached hereto.”
The lease (S-4/A ex. 10.51, filed Sep 2026), §1.5 'Base Design Specifications' · sec.gov - escalator3%3.0% a year, compounding — the lease redacts its own escalator ('shall escalate by [***] cumulative and compounding, upon each anniversary'), and the Expansion Agreement gives it when it sets the expansion's starting rent at 'the then-escalated Base Rent under the Lease (at 3.0% per annum, cumulative and compounding)'
“the starting Base Rent for each Phase of the Additional Expansion Capacity will be the same as the then-escalated Base Rent under the Lease (at 3.0% per annum, cumulative and compounding) in effect for Phase 1 of the Lease as of the date of delivery of such Phase of the Additional Expansion Capacity”
Expansion Capacity and ROFO Agreement (S-4/A ex. 10.51.1, filed Sep 2026) · sec.gov - revenue-estimateup to $2.8Bup to $2.8B over the initial terms, or up to about $5.4B over 25 years with every renewal — Blockfusion's own estimate, and for 85 MW: the 35 MW leased plus the 50 MW whose take-or-pay waits on conditions (expansion-conditions). It assumes both sides perform, the leases stay unchanged and later leases mirror this one. It is the figure Blockfusion first gave in June for a letter of intent promising 85 MW of guaranteed take-or-pay (loi-estimate). No filing gives a figure for the 35 MW alone
“Assuming satisfaction of applicable conditions, the aggregate contracted take-or-pay capacity would total 85 MW, which the Company estimates could represent potential revenues to Blockfusion of up to $2.8 billion, assuming the accuracy of the CoreWeave Lease Assumptions described below (or up to approximately $5.4 billion in revenues if CoreWeave executes all potential extensions of all relevant leases for a total of 25-year lease terms).”
Blue Acquisition DEFM14A (filed Oct 23 2026), CoreWeave Agreements · sec.gov - nrc$50M$50M, a non-recurring charge toward the transmission and electrical capacity for the leased space, in two equal installments within 30 and 60 days of signing (the lease's §4.1.3 redacts the amount). Part of it, the share for capital equipment, is refundable on some terminations (the schedule is redacted). Blockfusion records it as deferred lease income until the lease commences
“CoreWeave has agreed to pay NED a $50 million non-recurring charge toward the cost of installing and delivering transmission and electrical capacity for the leased premises, payable in two equal installments within 30 and 60 days after execution of the CoreWeave Lease.”
Blue Acquisition DEFM14A (filed Oct 23 2026), CoreWeave Agreements · sec.gov - nrc-received$25Mthe first $25.0M received Oct 5 2026; the second expected in November 2026 — 'on or about November 3, 2026', the same proxy says elsewhere. No document on file shows it arrived. The proxy adds that 'These payments from CoreWeave are not, alone, sufficient to fund those requirements'
“Blockfusion received the first installment of $25.0 million on October 5, 2026 and expects to receive the second installment of $25.0 million in November 2026.”
Blue Acquisition DEFM14A (filed Oct 23 2026), pro forma notes and liquidity · sec.gov - cash-contribution$30M$30.0M from CoreWeave, outside the rent, in consideration for the warrant (warrant). The lease's own words (§4.1.6): 'In addition to the NRC, Tenant shall pay to Landlord a cash contribution in the amount of Thirty Million Dollars ($30,000,000)', due within three business days, 'non-refundable' and 'not applied against Base Rent or any other Rent'. The proxy's pro forma balance sheet adds it to paid-in capital, where the $50M charge goes to deferred lease income
“In connection with Blockfusion’s entry into the CoreWeave Agreements, on September 4, 2026 (“CW Signing Date”), in consideration of a $30.0 million contribution to Blockfusion (which is not applied against rent), Blockfusion issued CoreWeave a warrant to purchase 2,786,624 shares of Company Class A Common Stock (the “CoreWeave Conditional Warrant”)”
Blue Acquisition DEFM14A (filed Oct 23 2026), CoreWeave Agreements; the lease, §4.1.6 · sec.gov - cash-received$30Mreceived Sep 10 2026, 'a portion of which was used to repay outstanding obligations' (debt-repaid) — the September investor presentation (furnished) says 'majority of which has been utilized to pay down BF indebtedness'
“In addition, the Company received a $30.0 million cash contribution from CoreWeave on September 10, 2026 in connection with the issuance of the CoreWeave Conditional Warrant, a portion of which was used to repay outstanding obligations.”
Blue Acquisition DEFM14A (filed Oct 23 2026), liquidity · sec.gov - debt-repaid$20.4M$20.4M of long-term and $0.2M of short-term notes repaid in September 2026, the month the $30.0M arrived, including the XBTO loan ($9,135,942.14) and two Insight Investments notes ($10,498,079.89), paid off on Sep 14 2026, four days after it, their liens on the site released. The proxy says 'The funds used to payoff the XBTO loan and the Insight Investment Loans were received in connection with Blockfusion’s entrance into the CoreWeave Lease' — ≈ $19.6M (our sum), about two-thirds of the $30.0M, the September deck's 'majority'
“In September 2026, Blockfusion repaid certain long-term and short-term notes payable in the aggregate principal amount of $20.4 million and $0.2 million, respectively, resulting in a gain on extinguishment of less than $0.1 million.”
Blue Acquisition DEFM14A (filed Oct 23 2026), pro forma — other material events · sec.gov - warrant2,786,624a warrant on 2,786,624 Blockfusion USA Series A shares at $7.6898 a share, dated Sep 4 2026 — the warrant's own text calls $7.6898 'the lowest effective price per share' at which shares were issued or agreed in the merger. It becomes exercisable on the earlier of Jan 1 2027 or the merger agreement's termination; on our arithmetic, CoreWeave paid about $10.77 a warrant share ($30.0M ÷ 2,786,624) for the right to buy at $7.6898
““CoreWeave Conditional Warrant” means that certain Series A Common Stock Purchase Warrant, dated as of September 4, 2026, issued by Blockfusion to CoreWeave to purchase 2,786,624 shares of Company Class A Common Stock at an initial exercise price of $7.6898 per share, issued in connection with the CoreWeave Lease.”
Blue Acquisition DEFM14A (filed Oct 23 2026), defined terms; the warrant (S-4/A ex. 4.6) · sec.gov - pubco-warrant2,870,813at the merger's closing the warrant is cancelled for one on 2,870,813 Pubco Class A shares at $7.4643, exercisable for seven years from the closing, in cash or cashless, capped so CoreWeave holds no more than 19.99% of the class after exercise, and transferable without Pubco's consent; Pubco executed it and put it in escrow on Sep 4 2026. If the merger does not close, the Blockfusion USA warrant stands
“The terms of the CoreWeave Pubco Warrant entitle CoreWeave to purchase 2,870,813 shares of Pubco Class A Common Stock at an exercise price of $7.4643 per share (the “Original Exercise Price”), subject to certain adjustments further described below, during a seven (7) year exercise period (“Exercise Period”) ending on the seventh anniversary of the Closing.”
Blue Acquisition DEFM14A (filed Oct 23 2026), CoreWeave Agreements; the Pubco warrant (S-4/A ex. 4.7) · sec.gov - coreweave-stake2,870,813what the warrant would make CoreWeave, by the proxy's ownership table after the merger: 4.9% of the merged company's Class A stock if no public holders redeem, 7.6% if all do (3.8% and 5.3% of all its common stock), but 0.7–0.8% of the votes, since its Class B shares carry 20 votes each. The table counts the warrant shares as owned
“CoreWeave 2,870,813 4.9 % — — 3.8 % 0.7 % 2,870,813 7.6 % — — 5.3 % 0.8 %”
Blue Acquisition DEFM14A (filed Oct 23 2026), post-business combination beneficial ownership table · sec.gov - warrant-side-lettermore warrants to come if CoreWeave or its affiliates contract for data-center capacity beyond the up to 300 MW the lease and Expansion Agreement cover; the side letter ends on a change of control of Blockfusion USA, Pubco or CoreWeave. Each further warrant would be issued when the agreement for the added capacity is signed; its exercise price is redacted in the filed side letter ('Each Additional Warrant shall have an exercise price per share equal to: (i) [***] (ii) [***]')
“Additionally, Blockfusion USA, Inc., Pubco and CoreWeave entered into a warrant side letter (the “CoreWeave Warrant Side Letter”) that provides for the issuance of additional warrants if CoreWeave or its affiliates contract for data center capacity other than the up to 300 MW of capacity covered by the CoreWeave Lease and the Expansion Agreement and that terminates upon a change of control of Blockfusion USA, Inc. or Pubco or CoreWeave.”
Blue Acquisition DEFM14A (filed Oct 23 2026), CoreWeave Agreements; the side letter (S-4/A ex. 10.51.2) · sec.gov - guaranty$50MBlockfusion USA guarantees North East Data's obligations to finish the landlord's installations and meet each phase's conditions, up to $50M initially, until 90 days after Phase 2 commences or the lease ends; Pubco's guaranty replaces it at the closing. A contingent liability, separate from the $50M charge (nrc)
“The maximum aggregate liability of Blockfusion USA, Inc. under the CoreWeave Guaranty is initially $50 million but following consummation of the Business Combination, will be replaced with a guaranty from Pubco.”
Blue Acquisition DEFM14A (filed Oct 23 2026), CoreWeave Agreements; the completion guaranty (S-4/A ex. 10.51.3) · sec.gov - expansion50 MW50 MW more that CoreWeave has committed to lease, on the lease's terms (15-year initial term, renewals, the starting rent Phase 1's then-escalated rate), only once conditions are met (expansion-conditions); and a right, not an obligation, to up to 215 MW more (option-capacity) — up to 300 MW in all 'at and near' the site. No further charge or cash contribution applies to an expansion lease
“Under the Expansion Agreement, CoreWeave has committed, subject to the conditions described below, to lease an additional 50 MW of capacity and has the right, but not the obligation, to lease up to a further 215 MW, such that the CoreWeave Agreements together establish a framework under which CoreWeave may lease up to 300 MW of IT load capacity at and near the Niagara Facility.”
Blue Acquisition DEFM14A (filed Oct 23 2026), CoreWeave Agreements · sec.gov - expansion-conditionsthe 50 MW is take-or-pay only once firm power, CoreWeave's approval of the power plan, the absence of a moratorium and a conforming expansion package by a longstop date are all in place. The Expansion Agreement itself: 'no take-or-pay obligation of Tenant with respect to the Firm Expansion Capacity shall arise, or have any force or effect, unless and until all Tranche 2 Power Conditions have been actually satisfied or waived in writing by Tenant.' No document on file shows them met
“This commitment becomes a binding take-or-pay obligation once specified conditions are met, including the Company having obtained firm commitments for sufficient additional power capacity, CoreWeave’s approval (which may be withheld only on specified grounds relating to reliability, cost of power and consistency with CoreWeave’s design standards) of the power infrastructure plan for the applicable phase, the absence of any data center moratorium or similar governmental action that would prevent or prohibit the development or operation of the applicable expansion capacity, and the Company’s delivery of a conforming expansion package for the applicable phase by a specified longstop date.”
Blue Acquisition DEFM14A (filed Oct 23 2026), CoreWeave Agreements; Expansion Capacity and ROFO Agreement, §1 · sec.gov - option-capacityup to 215 MWup to 215 MW more, at the site or nearby, which CoreWeave has the exclusive right but no obligation to lease through Dec 31 2030; if it declines, Blockfusion may offer the space to others but must re-offer it to CoreWeave if it gives a third party materially better terms within 12 months. Above 300 MW, CoreWeave holds a right of first offer
“The CoreWeave Agreements also provide CoreWeave an exclusive right to lease up to an additional 215 MW at the Niagara Facility or nearby vicinity. This capacity is not a take-or-pay obligation.”
Blue Acquisition DEFM14A (filed Oct 23 2026), CoreWeave Agreements · sec.gov - landlord-cash$0.1Mthe landlord at signing: about $0.1M of cash and a $28.1M working-capital deficit at Jun 30 2026, with a going-concern warning, and — at the proxy's date — no definitive agreement for any of the financing the merger sought ('neither Blue nor Blockfusion has entered into a definitive agreement for any Financing Transaction')
“As of June 30, 2026, Blockfusion had cash of approximately $0.1 million and a working capital deficit of approximately $28.1 million, and its financial statements state that these conditions raise substantial doubt about its ability to continue as a going concern.”
Blue Acquisition DEFM14A (filed Oct 23 2026), risk factors · sec.gov - build-costmore than $950Mover $950M for the conversion's core construction, infrastructure and engineering, by management's estimate — 'excluding costs associated with expansion opportunities', the risk factors add — with the caution that actual costs may be materially greater. When the money is spent is given two ways in the same proxy (contested capex-schedule)
“These key activities will be among the most capital intensive aspects of the HPC/AI Transition, which Company management currently estimates may cost over $950 million”
Blue Acquisition DEFM14A (filed Oct 23 2026), Information About Blockfusion — HPC/AI Development Plans · sec.gov - merger-postponedBlue Acquisition postponed its shareholders' vote on the merger, set for Nov 17 2026, on Nov 13 — 'until further announcement', its release of that day says, with a new date to be set 'as soon as practicable'; shares already submitted for redemption are to be returned. The warrant swap and the guaranty's replacement wait on that closing
“On November 13, 2026, Blue Acquisition Corp., a Cayman Islands exempted company (“Blue”) issued a press release (the “Press Release”) announcing that it has postponed the Meeting that had been scheduled at 10:00 a.m. ET on November 17, 2026 for the consideration of all proposals included in its definitive proxy statement/prospectus filed with the Securities and Exchange Commission (the “SEC”) on October 23, 2026.”
Blue Acquisition 8-K/A (Item 8.01; filed Nov 16 2026) · sec.gov - loi85 MWJun 30 2026: a non-binding letter of intent with 'a leading AI customer' it did not name, for up to 300 MW, 85 MW of it 'guaranteed take-or-pay', each phase 15 years with two five-year renewals. The signed agreements keep the 300 MW but make 35 MW take-or-pay and 50 MW conditional (lease, expansion-conditions)
“Under the proposed lease terms, the offtaker would commit to up to 300 MW of total critical IT capacity at the campus, anchored by 85 MW of guaranteed take-or-pay capacity to be delivered in tranches, subject to due diligence and definitive lease terms.”
Blockfusion and Blue Acquisition release (Jun 30 2026) · globenewswire.com - loi-estimate$2.8Babout $2.8B over the initial 15-year term (about $5.4B with both renewals) — the June estimate, made on 85 MW of guaranteed take-or-pay. The October proxy gives the same figures on 85 MW 'assuming satisfaction of applicable conditions' (revenue-estimate)
“Based on the up to 85 MW of guaranteed take-or-pay capacity, the Company estimates that the potential aggregate lease revenue, assuming terms consistent with the LOI, could be approximately $2.8 billion over the initial 15-year lease term”
Blockfusion and Blue Acquisition release (Jun 30 2026) · globenewswire.com - loi-timeline25 MWthe June target for the first 25 MW: during 2027, in management's remarks on the letter of intent (furnished with Blue's Jun 30 2026 8-K). The signed lease targets February 2028 (phases)
“Our project timeline indicates that the first 25MW is targeted for delivery during 2027.”
Blockfusion management remarks (Jun 30 2026; Blue 8-K ex. 99.2, furnished) · sec.gov - announcedSep 16 2026: Blockfusion's release names CoreWeave and says the signed lease and Expansion Agreement are the June letter of intent made definitive — so the unnamed customer of June was CoreWeave. The release gives no capacity, rent or payment; those came in the S-4/A filed two days later and the proxy
“The Lease and the Expansion Agreement convert the non-binding letter of intent announced on June 30, 2026, into definitive agreements. The Lease has a 15-year initial term with two five-year renewal options.”
Blockfusion release (Sep 16 2026; filed under Rule 425) · sec.gov
Contested figures 6 not reconciled — every position side by side, with its source and tier
Scope note what this record leaves to other records
NOT this record (carried elsewhere or not carried): the Blue Acquisition–Blockfusion merger itself — its equity value and the enterprise value implied, the earnout (up to 15,000,000 shares since the Sep 21 2026 amendment), the exchange ratio (assumed at 1.0350, set at closing), the minimum cash condition waived Sep 21 2026, the trust account, Houlihan Capital's fairness opinions and the pro forma share counts and ownership → not carried; the financing it sought — the June 2026 non-binding Sona term sheet for $175M of convertible notes and the ~$33M non-redemption proposal, the $100M illustrative convertible of September, the 'over $200 million' of hoped-for proceeds — none definitive at the proxy's date → not carried; Blockfusion's legacy debts (the XBTO loan: $7,355,705 at origination in 2022, restated as $8,267,885 in 2024; the Insight $6M and $4M notes; the Brady Electric and officer notes; the Oct 2025 Robert Scott note of $135,535.73) → not carried, except that the September repayments are where part of CoreWeave's $30M went (debt-repaid); utilities as 90.8% of Blockfusion's 2025 cost of sales, its bitcoin-mining results and its litigation with Bit Digital, a former hosting customer → not carried; management's revenue and EBITDA forecasts and older capex figures (~$900M and ~$920M, $10.5M per MW) → not carried; the site's interconnection request for up to 500 MW more (NYISO's large-load queue, Aug 2025), its earlier 56 MW request, New York's Executive Order 62 pause on data centers of 50 MW or more and whether it reaches the expansion, and the site's acreage, given on different parcel definitions → site facts, not carried. Not adopted: the June presentation's ~$9.7B / ~$19B for a full 300 MW lease on the letter of intent's terms, which the signed agreements did not adopt; Barrio Energy's 'signed ... on Sept 16' (the release's date; the lease is dated Sep 4); a tracker's 'most likely May 2030' for the first building in service, its own model; and the 140 MW and $1.48B in the city planning board's Dec 2025 packet, which belong to another developer's Niagara Digital Campus, not Blockfusion's site.