Broadcom–Anthropic, second rack financing

Bank of America, Citi, Morgan Stanley and Blackstone announced $63B to fund a lease of Broadcom AI chips and networking gear to Anthropic. Broadcom could owe up to about $43B if Anthropic defaults.

A deal between Broadcom, Anthropic, Northstar Compute (SPV), Blackstone, Lenders & bondholders

Why it matters

Broadcom covers a resale shortfall if Anthropic defaults on its equipment lease. Its October pledge uses 72.5% of the outstanding lease balance, capped at ~$43B on a $63B financing, versus 85% up to ~$29B on $35B in June. Broadcom's release sizes the October support to the first lien.

Tap a figure for the line in its source.

Lenders & bondholders gives Northstar Compute (SPV)

  • of financing announced for the new vehicle by all four financiers, so Blackstone's part sits inside this figure: first-lien loans arranged by Bank of America, Citi and Morgan Stanley and a second lien; no party gives the split, and only part of the second lien is described as committed

Blackstone gives Northstar Compute (SPV)

  • by Bloomberg and the FT, of a second lien they put at about $18B, inside the $63B; the parties say only that Blackstone is sole provider of its committed part

Northstar Compute (SPV) gives

  • buys Broadcom's custom AI accelerators and networking gear, delivered with partners from 2027; how much of the $63B reaches Broadcom is not disclosed → Broadcom
  • disputedof computing capacity leased to Anthropic, by press and counsel only; the parties' release, filing and slide give no gigawatts → Anthropic

Anthropic gives Northstar Compute (SPV)

  • rent on the lease, which the press says repays the vehicle's debt; its amount and length are not disclosed for this vehicle

Broadcom gives Northstar Compute (SPV)

  • residual value support if Anthropic defaults on the lease: the gap between 72.5% of what is owed and what the racks fetch, at most about $43B undiscounted, a contingent liability Broadcom believes has a low probability of occurring

Aug 20, 2026 reported by Bloomberg, as talks to raise more than $60Bupdated Nov 19, 2026announced Oct 26 2026 disclosed by the parties

What happened

In October 2026, Bank of America, Blackstone, Citi and Morgan Stanley announced $63 billion in financing for a new company formed for the deal. Its lawyers call it Northstar Compute. The company will buy Broadcom's custom AI chips and networking equipment and lease them to Anthropic. Deliveries are expected from 2027. Broadcom backs the lease if Anthropic defaults. It would owe the difference between 72.5% of the outstanding balance and what the racks sell for. Broadcom's filing puts the maximum at about $43 billion before any discounting. This is Broadcom's second such promise this year. In June, it made a similar promise at 85%, up to about $29 billion on a $35 billion financing. Broadcom's filing calls the lessee only 'the customer'. Its own release and slide name Anthropic. Broadcom's support is sized to the first-lien loans, which have priority over the riskier second lien. No party has disclosed how the $63 billion is split between them or what the loans cost. Anthropic's IPO filing says a vehicle took on part of its March 2026 Broadcom lease. No party has said whether that vehicle is Northstar Compute.

Sources 33 documents — 11 press reports · 8 SEC filings · 6 other documents · 3 company releases · 3 law-firm notes · 2 research notes

Research trail Found 87 documents and read 79 of them while checking this deal and related ones.

  1. Broadcom · company releaseinvestors.broadcom.com
    States 5 figures: $63B announced size · structure · financing roles · rvs sizing · deliveries
  2. SEC filingsec.gov
    States 5 figures: arrangement · backstop · 72.5% backstop formula · $43B backstop cap · backstop remedies
  3. company releaseinvestors.broadcom.com
    States 3 figures: customer named · $43B peak exposure · rvs amortization
  4. SEC filingsec.gov
    States s1a assignment
  5. law-firm notemilbank.com
    States $63B spv name
  6. SEC · SEC filingsec.gov
    States $63B adviser line
  7. Yahoo Finance · press reportfinance.yahoo.com
    States $9B blackstone commitment
  8. company releaseprnewswire.com
    Cited by the record; no single figure is quoted from it.
  9. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  10. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  11. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  12. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  13. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  14. law-firm noteOct 2026lw.com
    Cited by the record; no single figure is quoted from it.
  15. law-firm notesullcrom.com
    Cited by the record; no single figure is quoted from it.
  16. press report (archived copy)investing.com
    Cited by the record; no single figure is quoted from it.
  17. press reportksl.com
    Cited by the record; no single figure is quoted from it.
  18. press reportcommunicationstoday.co.in
    Cited by the record; no single figure is quoted from it.
  19. press reportAug 21, 2026thestar.com.my
    Cited by the record; no single figure is quoted from it.
  20. other documenteconomictimes.indiatimes.com
    Cited by the record; no single figure is quoted from it.
  21. press reportbusinesstimes.com.sg
    Cited by the record; no single figure is quoted from it.
  22. other documentbusinessdesk.co.nz
    Cited by the record; no single figure is quoted from it.
  23. press reportifre.com
    Cited by the record; no single figure is quoted from it.
  24. press report (archived copy)investing.com
    Cited by the record; no single figure is quoted from it.
  25. other documentOct 2026c-level.folha.uol.com.br
    Cited by the record; no single figure is quoted from it.
  26. press report (archived copy)datacenterdynamics.com
    Cited by the record; no single figure is quoted from it.
  27. other documentboerse-global.de
    Cited by the record; no single figure is quoted from it.
  28. press reportitiger.com
    Cited by the record; no single figure is quoted from it.
  29. press reportglobaldatacenterhub.com
    Cited by the record; no single figure is quoted from it.
  30. research notenodiligence.substack.com
    Cited by the record; no single figure is quoted from it.
  31. research notestaringdownthebarrel.substack.com
    Cited by the record; no single figure is quoted from it.
  32. other documentbeatingthebull.com
    Cited by the record; no single figure is quoted from it.
  33. other documentaiinfracredit.com
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: Joint release (Oct 26 2026; Broadcom IR, PR Newswire) + Broadcom 8-K Item 2.03 (Oct 27 2026) and transaction slides + Evercore Q3 release (furnished) + Anthropic S-1 (Oct 26 2026), S-1/A No. 1 (Nov 2) and ex-4.4, its S-1/As of Nov 10 and 17 and its 424B4 of Nov 19 (the October assignment unchanged, no Northstar or support named) + Milbank and Latham notices; Reuters via KSL, Bloomberg via Communications Today (Aug 21 2026), The Economic Times and Yahoo, WSJ via BusinessDesk, IFR, FT via Investing.com and Folha, DCD; No Diligence, Staring Down the Barrel, Beating the Bull, Global Data Center Hub, AI Infra Credit, Börse Global (read 2026-11) · as of Nov 2026

The evidence 17 sourced figures · 9 disputes

The record's headline Broadcom–Anthropic, second rack financing: a $63B vehicle (Northstar Compute) buys Broadcom XPUs and networking and leases them to Anthropic, with Broadcom standing behind the lease up to ~$43B on a 72.5% test (8-K); deliveries expected from 2027, the tranche split and pricing press only

Size
$63B financing (no party splits it; first lien ~$42–43.5B and second lien ~$18B by press) · Broadcom residual value support max ~$43B undiscounted: 72.5% of lease amounts owed, less rack value · deliveries expected from calendar 2027 · ~1.5 GW (press) to >1.6 GW (counsel)
When
Aug 20 2026 Bloomberg: talks to raise more than $60B → Oct 2 Bloomberg: about $60B being syndicated → Oct 16 the FT: 'Project North Star', a 10% junior coupon offered to Blackstone → Oct 26 joint release, and the date of Broadcom's arrangement → Oct 27 8-K (Item 2.03): the ~$43B Backstop → Oct 28 Evercore's results name the deal → Nov 2 Anthropic's S-1/A: an October assignment of part of its March 2026 lease (the tie is unstated) → deliveries expected from calendar 2027
Status
announced Oct 26 2026 (8-K filed Oct 27): deliveries expected from calendar 2027, how much is drawn not disclosed; the first-lien/second-lien sizes, pricing and any bond take-out are press reports only; no filing ties the vehicle to Anthropic's March 2026 lease
Structure
a vendor-backed equipment lease through a special purpose vehicle. A newly formed vehicle (Northstar Compute LLC, per its counsel) raises the $63B — first-lien loans arranged by Bank of America, Citi and Morgan Stanley, a second lien whose committed part Blackstone alone provides, and, in Milbank's words alone, 'debt and equity' — to buy Broadcom XPU AI accelerators and networking gear and lease them to Anthropic. Rent services the vehicle's debt, in the press's account (Bloomberg, WSJ); no party states the lease's rent or length. Broadcom gives the vehicle residual value support: on a lease default, the gap between 72.5% of the lease amounts owed and what the racks fetch in a sale, capped at ~$43B undiscounted, rising as racks are delivered and deployed and falling as Anthropic pays; Broadcom's remedies include taking over the lease, reselling the racks to the seller at a fixed price under certain conditions, or arranging a sale. The second such Backstop in 2026, after the June AI XPV tranche's 85% and ~$29B (anth-fluidstack): the vendor underwrites the resale value of its own hardware, the leg that makes this record circular
Programme
Broadcom–Anthropic
Parties
Broadcom designs the XPU AI accelerators and networking gear the vehicle buys and, with partners, provides that technology to it (its slide's words); arranged the transaction and stands behind the lease with the residual value support (the Backstop, ~$43B maximum, 72.5% test), 'not a direct cash outlay'; also lessor under Anthropic's March 2026 lease, part of which it assigned in October to an unnamed financing entity (which-lease); holds the second such Backstop after June's (anth-fluidstack) · Anthropic lessee of the vehicle's equipment and the customer named in Broadcom's release and slide, not its 8-K; its S-1/A names neither Northstar nor the support, and reports an October 2026 assignment of part of its March 2026 Broadcom lease to an unnamed, newly formed financing entity (which-lease) · Northstar Compute (SPV) the newly formed special purpose vehicle (Northstar Compute LLC, per its counsel) that raises the $63B, buys the hardware and leases it to Anthropic, and receives Broadcom's residual value support · Blackstone one of the four 'Lead Financial Partners'; sole provider of the committed portion of the second lien (release), 'the anchor provider of second lien financing' (slide); about $9B by Bloomberg and the FT (blackstone-commitment), no party's figure · Lenders & bondholders Bank of America, Citi and Morgan Stanley, the other three 'Lead Financial Partners', arrange the first lien — lending about $42B of it in Bloomberg's account, with other banks expected to join; bond buyers if the planned take-out happens (bond-take-out). None has an entity here: `lenders` stands for them, and on the $63B row for all four financiers' whole package, Blackstone's part inside it
Capital
the seller's own money or backing comes back as its sales
Record
disclosed / primary source · as of Nov 2026

Flows 6 as the record states them

  • Lenders & bondholders → Northstar Compute (SPV)debt-commitments$63B of financing announced for the vehicle (release: 'committed financing from the Lead Financial Partners', all four of them, so Blackstone's second-lien commitment is inside this figure, not on top of it): first-lien loans arranged by Bank of America, Citi and Morgan Stanley and a second lien of which only the 'committed portion' is described; Milbank alone says 'debt and equity' — no split, no drawn amount (first-lien-size, second-lien-size)
  • Blackstone → Northstar Compute (SPV)second-lienabout $9B by Bloomberg and the FT, of a second lien they put at about $18B; the parties say only that Blackstone is 'sole provider of the committed portion of the second lien financing'
  • Northstar Compute (SPV) → Broadcomrack-purchasethe vehicle's purchase of 'Broadcom XPU AI accelerators and networking solutions', delivered by Broadcom 'and partners' (slide) from calendar 2027; how much of the $63B reaches Broadcom is not disclosed (rack-seller) — not drawn as a ribbon
  • Northstar Compute (SPV) → Anthropicfinancing$63B transaction 'to enable the deployment of AI compute capacity … for Anthropic' (release): the vehicle leases the equipment to Anthropic, with expected deliveries starting in calendar 2027; capacity contested (capacity-financed)
  • Anthropic → Northstar Compute (SPV)lease-rentrent on the lease — in the press's account, what repays the vehicle's debt — amount and term not disclosed for this vehicle; Broadcom's slide illustrates five years of lease payments
  • Broadcom → Northstar Compute (SPV)residual-value-supportmaximum ~$43B undiscounted upon the racks' deployment (8-K): on a lease default, the difference between 72.5% of the outstanding lease amounts and the racks' sale value; rises with delivery and deployment, falls as the customer pays

Resolved figures 17 each with the verbatim line from its document

  • announced-size$63B
    a $63B 'transaction to enable the deployment of AI compute capacity, leveraging Broadcom Inc.'s (NASDAQ: AVGO) technology, for Anthropic', announced Oct 26 2026 by the four 'Lead Financial Partners' — the whole package's headline, not first-lien debt and not cash drawn; the release gives no breakdown. The release, hosted on Broadcom's investor site and credited 'SOURCE Broadcom Inc.', calls it 'part of the strategic compute capacity agreement previously announced by Broadcom'; Milbank, Latham, Sullivan & Cromwell, Evercore and the press restate the same $63B: one announcement, count = 1
    “Bank of America (NYSE: BAC), Blackstone (NYSE: BX), Citi (NYSE: C) and Morgan Stanley (NYSE: MS) (the "Lead Financial Partners") today announced a $63 billion transaction to enable the deployment of AI compute capacity, leveraging Broadcom Inc.'s (NASDAQ: AVGO) technology, for Anthropic.”
    Joint release, Oct 26 2026 (Broadcom IR / PR Newswire) · investors.broadcom.com
  • structure
    the vehicle: 'a newly formed special purpose vehicle' raises committed financing to buy Broadcom's hardware and lease it to Anthropic. The release's only word for the goods is 'Broadcom XPU AI accelerators and networking solutions' — no chip name, no site, no gigawatts, no term or rent. Broadcom's slide draws the same structure: the SPV is 'Borrower / Technology Owner / Lessor', Anthropic the 'Lessee'
    “The transaction will be executed through a newly formed special purpose vehicle ("SPV") with committed financing from the Lead Financial Partners to support the purchase of Broadcom XPU AI accelerators and networking solutions to be leased to Anthropic.”
    Joint release, Oct 26 2026 (Broadcom IR / PR Newswire) · investors.broadcom.com
  • financing-roles
    who does what, in the parties' words, with no amounts: Bank of America, Citi and Morgan Stanley arrange the first lien; Blackstone is 'the sole provider of the committed portion of the second lien financing' ('the anchor provider of second lien financing' on Broadcom's slide). The release says the three banks arrange the first lien, not that they hold it; Bloomberg says they are lending it and that other banks are expected to join. Sizes are first-lien-size and second-lien-size; Blackstone's reported amount is blackstone-commitment
    “The first lien portion of the financing is being arranged by Bank of America, Citi and Morgan Stanley, with Blackstone as the sole provider of the committed portion of the second lien financing.”
    Joint release, Oct 26 2026 (Broadcom IR / PR Newswire) · investors.broadcom.com
  • rvs-sizing
    the release's whole account of the support: residual value support 'for the amount equivalent to the first lien portion of the financing' — sized to a tranche whose size it does not give. It never mentions the 72.5% test, the ~$43B or a lease balance; the 8-K gives both and never mentions a lien. No document reconciles the two (what-rvs-covers)
    “Broadcom is providing residual value support to the SPV for the amount equivalent to the first lien portion of the financing.”
    Joint release, Oct 26 2026 (Broadcom IR / PR Newswire) · investors.broadcom.com
  • deliveries
    deliveries 'starting in calendar 2027' — the parties' only date for the hardware, and 'part of the strategic compute capacity agreement previously announced by Broadcom', its April 2026 collaboration with Google and Anthropic as read in avgo-anth-tpu (the release does not name it further). No schedule: Broadcom's slide uses an 'assumed delivery schedule' (rvs-amortization)
    “This transaction is part of the strategic compute capacity agreement previously announced by Broadcom, with expected deliveries starting in calendar 2027.”
    Joint release, Oct 26 2026 (Broadcom IR / PR Newswire) · investors.broadcom.com
  • arrangement
    the filed account of the Oct 26 event: Broadcom 'arranged for financial partners to take on a portion of certain agreements to purchase AI racks' based on its custom accelerators and the related leases 'with the Company's customer'. 'A portion': what happens to the rest the filing does not say. The 8-K names no customer, financial partner, financing amount, lease term or site — those are the release's and the slide's, and the term is not stated anywhere for this vehicle (rvs-amortization)
    “On October 26, 2026, Broadcom Inc. (the “Company”) arranged for financial partners to take on a portion of certain agreements to purchase AI racks based on custom AI accelerators designed by the Company and the related lease agreements with the Company’s customer that enable the deployment of compute capacity.”
    Broadcom 8-K, Item 2.03 (event Oct 26, filed Oct 27 2026) · sec.gov
  • backstop
    the instrument: residual value support to 'a newly formed special purpose vehicle' (the 8-K's 'Backstop'), filed under Item 2.03, which Broadcom calls 'a contingent liability the Company believes has a low probability of occurring' — its own assessment, 'supported by the expectation of a strong profitability trajectory of the customer and the sustaining value of the underlying assets'. A contingent promise, not a payment: the balance grows as racks are delivered and deployed and falls as the customer pays, and the filing never calls it a guarantee of the lenders' loans. The filing is silent on how it is accounted for (the June Backstop's fair value was 'not material', anth-fluidstack)
    “In connection with this arrangement, the Company is providing residual value support to a newly formed special purpose vehicle (the “Backstop”). The Backstop is a contingent liability the Company believes has a low probability of occurring, supported by the expectation of a strong profitability trajectory of the customer and the sustaining value of the underlying assets. The total amount of the Backstop increases as the AI racks are delivered and deployed and decreases as the customer makes payments on its lease obligations.”
    Broadcom 8-K, Item 2.03 (event Oct 26, filed Oct 27 2026) · sec.gov
  • backstop-formula72.5%
    what Broadcom pays on a lease default: the gap between 72.5% of the lease amounts then owed and what the racks fetch in a sale — the June Backstop's test was 85% (anth-fluidstack). The base is the outstanding lease balance, which no document gives for this vehicle; the percentage does not apply to the $63B
    “The Company’s potential liability under the Backstop will be equal to any difference between 72.5% of the outstanding amounts owed on the lease and the value of the AI racks received upon the sale of the assets at that time.”
    Broadcom 8-K, Item 2.03 (event Oct 26, filed Oct 27 2026) · sec.gov
  • backstop-cap$43B
    Broadcom's maximum exposure: approximately $43B undiscounted once the racks are deployed — a contingent ceiling ('RVS is not a direct cash outlay', Broadcom's slide), and larger than the June Backstop's ~$29B (anth-fluidstack). Whether the two ceilings can be reached together, no filing says (combined-peak)
    “The Company’s maximum potential liability under the Backstop upon the deployment of the AI racks, on an undiscounted basis, is approximately $43 billion.”
    Broadcom 8-K, Item 2.03 (event Oct 26, filed Oct 27 2026) · sec.gov
  • backstop-remedies
    Broadcom's ways out before it pays include taking over the lease, reselling the racks 'back to the seller at a fixed price under certain conditions', or arranging a sale — the same three remedies its 10-Q lists for the June Backstop (anth-fluidstack). The seller is unnamed (rack-seller) and the conditions are not disclosed
    “In the event of a lease default by the customer, the remedies to limit the Company’s liability exposure include the assumption of the applicable lease, reselling the AI racks back to the seller at a fixed price under certain conditions, or arranging a sale of the applicable AI racks.”
    Broadcom 8-K, Item 2.03 (event Oct 26, filed Oct 27 2026) · sec.gov
  • customer-named
    who the 8-K's unnamed 'customer' is: Anthropic, on Broadcom's own transaction slide — 'SPV leases the technology to Anthropic', 'Broadcom provides residual value support (“RVS”) to the SPV', with the 72.5% test and the $43B (peak-exposure) on the deck's next page. The joint release also names Anthropic as lessee. A party statement posted on Broadcom's investor site, not an SEC filing: the only SEC filing naming Anthropic beside this transaction is Evercore's furnished release (adviser-line), and Anthropic's S-1/A names neither the vehicle nor the support (which-lease)
    “SPV leases the technology to Anthropic”
    Broadcom transaction slides (investors.broadcom.com, Oct 2026) · investors.broadcom.com
  • peak-exposure$43B
    the slide's wording of the ceiling: 'Peak exposure expected to be $43 billion and decline to zero' (the 8-K: 'approximately $43 billion'), beside 'RVS is not a direct cash outlay' and 'Low probability of RVS occurring', Broadcom's own assessment. William Blair's 'in the first year' (Dow Jones via iTiger) reads a schedule Broadcom footnotes as illustrative (rvs-amortization); the 8-K gives no timing
    “Peak exposure expected to be $43 billion and decline to zero”
    Broadcom transaction slides (investors.broadcom.com, Oct 2026) · investors.broadcom.com
  • rvs-amortization5 years
    the support's run-off, as an illustration only: straight-line to zero over five years of lease payments, footnoted 'Illustrative only. Reflects an assumed delivery schedule and lease payment profile; actual RVS balances and timing may differ.' Not a stated lease term: the 8-K gives none; the FT's 'five-year chip lease payments' (via Investing.com) and IFR's Sep 30 2033 loan maturity are press
    “RVS Amortizes to Zero on a Straight-line Basis Over 5 Years of Lease Payments”
    Broadcom transaction slides (investors.broadcom.com, Oct 2026) · investors.broadcom.com
  • spv-name$63B
    the vehicle's name, from its own counsel alone: Northstar Compute LLC, 'a new compute finance and lease platform', and the only word that the $63B includes equity ('debt and equity', no split). The next paragraph of the notice repeats 'a newly formed special purpose vehicle' without saying that is Northstar Compute; read here as one vehicle, which no party document states. 'Project North Star' is the press's name for the deal (FT, WSJ, DCD). Tier 2: counsel's notice, as avgo-anth-tpu's orders-total reads Sullivan & Cromwell's
    “Milbank LLP represented Northstar Compute LLC, a new compute finance and lease platform, in its inaugural capital raise, comprised of $63 billion in debt and equity from a combination of funding sources arranged by Bank of America (NYSE: BAC), Blackstone (NYSE: BX), Citi (NYSE: C) and Morgan Stanley (NYSE: MS).”
    Milbank notice (counsel to Northstar Compute), Oct 26 2026 · milbank.com
  • adviser-line$63B
    the one SEC document that names Anthropic beside this transaction: Broadcom's financial adviser's Q3 release, ex-99.1 to an 8-K under Item 2.02 — furnished, not filed, and an adviser's, not a party's, so tier 2 for the document. 'Enabling the deployment of $63 billion of AI compute capacity' is the adviser's gloss on the same headline
    “Broadcom on a transaction enabling the deployment of $63 billion of AI compute capacity to Anthropic”
    Evercore Q3 2026 earnings release (8-K ex-99.1, Item 2.02, furnished Oct 28 2026) · sec.gov
  • blackstone-commitment$9B
    Blackstone's amount, by the press alone: about $9B of the second lien — Bloomberg, Oct 2 ('committing US$9 billion from various funds', of 'an US$18 billion tranche of Class B junior debt') and restated Oct 27 (this quote); the FT via Investing.com, Oct 16 ('expected to invest $9 billion in junior debt'); the WSJ, Oct 27 ('half of which will be financed by Blackstone'). No party states an amount (financing-roles). Tier 2: anonymous sources, separate newsrooms
    “Blackstone Inc. is anchoring the rest of the financing, committing $9 billion, Bloomberg previously reported.”
    Bloomberg via Yahoo Finance, Oct 27 2026 · finance.yahoo.com
  • s1a-assignment
    what Anthropic's S-1/A, filed a week later, says happened that month: Broadcom assigned part of the equipment under the March 2026 lease to 'a newly formed special purpose financing entity'. The S-1 of Oct 26 still said Broadcom 'intends to assign to a designated financial partner'; the S-1/A names no entity, no amount and no support, and says 'These assignments did not increase our aggregate rent payments under the Lease Arrangements'. The S-1/As of Nov 10 and 17 and the final prospectus of Nov 19 2026 say the same, and still name neither Northstar, the $63B nor Broadcom's support. The tie to this vehicle is which-lease; the lease itself is avgo-anth-tpu's
    “In October 2026, Broadcom assigned to a newly formed special purpose financing entity its rights and obligations with respect to a portion of the equipment under the 2026 Lease Arrangement.”
    Anthropic 424B4 (Nov 19 2026) — MD&A, Infrastructure Equipment Leases (the same sentence in S-1/A No. 1) · sec.gov

Contested figures 14 not reconciled — every position side by side, with its source and tier

first-lien-size2 positions, side by side
about $42B — 'The banks are lending about $42 billion of the amount', 'The $42 billion portion of the debt is senior secured' (Bloomberg, Oct 27 2026, people with knowledge, the day after the announcement); the $42B Class A of its Oct 2 report; 'Mais de US$ 42 bilhões (R$ 228,71 bilhões) em empréstimos seniores têm garantia da Broadcom', more than $42B of senior loans (the FT via Folha, Oct 30); 'US$42bn of senior secured loans' split evenly into two US$21bn tranches at syndication (IFR, Oct 10–16). The parties give no size: 'The release did not disclose the breakdown of the loans' (Reuters) Bloomberg via Yahoo Finance (Oct 27 2026) and via The Economic Times (Oct 2 2026); FT via Folha (Oct 30); IFR (Oct 10–16)
about $43.5B — 'The size of the first lien loans or senior debt is about $43.5 billion, according to two sources familiar with the matter, or 69% of total financing' (Reuters, Oct 26 2026, the day of the release); a German summary of Fitch's Oct 27 note puts Broadcom's residual-value guarantee at $43.5B (Börse Global, tier 3, Fitch's own page available on file only as a stub). IFR's $42bn of loans plus its separately syndicated $1.5bn term loan would come to $43.5bn (our sum, and unconfirmed: IFR does not call the term loan first lien, and Börse Global lists a 'Term Loan über 1,5 Milliarden Dollar' beside the guarantee, as separate items). The 8-K's ~$43B is the Backstop's ceiling, a different quantity: reading it as the first lien's size is an inference no source states, and AI Infra Credit warns against it ('$43bn is an expected peak support exposure, not a disclosed first-lien tranche') Reuters via KSL / Investing.com (Oct 26 2026); Börse Global on Fitch (Oct 28); IFR; AI Infra Credit
second-lien-sizeone entry, in its own words
the rest of the $63B, which no party sizes. The press's number is $18B of junior debt, half of it Blackstone's: Bloomberg's 'US$18 billion tranche of Class B junior debt' (Oct 2 2026), the WSJ's 'another US$18b in riskier debt that won’t carry a Broadcom guarantee' (Oct 27, after the announcement), the FT's 'half of the planned $18 billion junior financing' (via Investing.com, Oct 16) and 'Outros US$ 18 bilhões (R$ 98 bilhões) em dívida subordinada', the junior debt rated BB+ (via Folha, Oct 30). Against that: $42B + $18B = $60B and $43.5B + $18B = $61.5B, neither reaching $63B; IFR's $61.5bn package adds a $1.5bn term loan to the $42bn and the $18bn. The $1.5B–$3B left is unexplained, and a $19.5–21B second lien follows only by subtraction, which no source states and AI Infra Credit warns against ('Subtracting it from $63bn does not reveal $20bn of second-lien debt'). Milbank's '$63 billion in debt and equity' is the only word of equity, with no split Bloomberg via The Economic Times (Oct 2 2026) and Business Times; WSJ via BusinessDesk (Oct 27); FT via Investing.com (Oct 16) and Folha (Oct 30); IFR; Milbank; AI Infra Credit
capacity-financed2 positions, side by side
approximately 1.5 GW of Google's TPUs: 'would support Anthropic’s acquisition of approximately 1.5 gigawatts of Google’s custom tensor processing units' (the FT via Investing.com, Oct 16, on the then-$60B package); 'de 1,5 gigawatt em semicondutores do Google' (the FT via Folha, Oct 30, after the deal closed in the FT's words). Press only; the Oct 30 report does not say what perimeter the 1.5 GW has FT via Investing.com (Oct 16 2026) and Folha (Oct 30)
more than 1.6 GW — 'the transaction supporting the deployment of more than 1.6 gigawatts of AI compute capacity for Anthropic' (Latham & Watkins, counsel to the lead financial partners, Oct 26 2026): a single line in a law-firm notice. The joint release, the 8-K and Broadcom's slide give no gigawatt figure. IFR's '15GW of chips to be delivered over the next two years' is the whole order, never this financing Latham & Watkins notice (Oct 26 2026)
bond-take-outone entry, in its own words
a planned sale of bonds to refinance part of the banks' debt, confirmed by no party: 'as much as about $21 billion of high-grade bonds as soon as early next year' and 'in the first quarter of 2027' (Bloomberg, Oct 27 2026, people with knowledge) vs 'half of their debt, around US$22b', not until 'later next year when the chips are delivered' (the WSJ, Oct 27). Bloomberg: 'The final size of the bond issuance, and the timing, will depend on market conditions'. Half of $42B is $21B and half of $43.5B is $21.75B (our arithmetic), so the gap may inherit first-lien-size's. Not additional money: a refinancing of the banks' first-lien debt Bloomberg via Yahoo Finance; WSJ via BusinessDesk (both Oct 27 2026)
pricingone entry, in its own words
no party discloses a price. At syndication launch, IFR: 'One tranche of the loan pays a margin of 187.5bp over SOFR while the second pays 150bp over. Both tranches mature on September 30 2033.' Then the WSJ (Oct 27 2026): Broadcom's CEO 'agreed to higher interest rates on the loans', no figure given, and the FT via Investing.com (Oct 16): Blackstone was 'offered a 10% coupon, with total returns exceeding that level after accounting for issuance discounts and fees' on the junior debt. No final margin, coupon or fee is in any document here IFR (Oct 10–16 2026); WSJ via BusinessDesk (Oct 27); FT via Investing.com (Oct 16)
what-rvs-covers3 positions, side by side
a shortfall test on the lease, in Broadcom's filing: 'any difference between 72.5% of the outstanding amounts owed on the lease and the value of the AI racks received upon the sale of the assets at that time' (8-K), at most ~$43B — measured against the lease balance, net of what the racks fetch Broadcom 8-K, Item 2.03 (Oct 27 2026)
a tranche, in Broadcom's release: residual value support 'for the amount equivalent to the first lien portion of the financing' (joint release, repeated by Milbank), with no number, no percentage and no mention of a lease balance. No primary document reconciles this with the 8-K's test, and the support agreement is not public, so its triggers, its valuation mechanics and whether it travels with bonds sold later are unknown Joint release (Oct 26 2026); Milbank
a guarantee of the debt, in the press: 'partially guarantee senior debt issued by a special purpose vehicle' (IFR); 'guarantee that lenders will get their money back' and 'guarantees from Broadcom that will protect them from losses in case Anthropic defaults on the loans' (the WSJ); 'effectively providing a significant guarantee' (Reuters). Shorthand that drops the 8-K's 72.5% and its netting of rack value; no party document calls it a guarantee of the debt IFR (Oct 10–16 2026); WSJ via BusinessDesk (Oct 27); Reuters via KSL (Oct 26)
which-lease2 positions, side by side
the S-1/A's October assignment is this vehicle, by timing and wording: Anthropic's S-1/A (Nov 2 2026) says that in October 2026 Broadcom assigned part of the March 2026 lease to 'a newly formed special purpose financing entity' (s1a-assignment), the month and near the words of the 8-K's 'newly formed special purpose vehicle'; and the Oct 26 2026 amendment to its Broadcom note agreement (S-1/A ex-4.4) defines a master equipment lease of that date between a redacted lessor and AI Infrastructure OpCo II, LLC and widens its 'Lease Agreement' to that lease and any later novation or assignment of the Broadcom Master Lease. Consistent, but no document says it Anthropic S-1/A No. 1 (Nov 2 2026) and its ex-4.4; Broadcom 8-K; joint release
unconfirmed: the joint release and the 8-K describe their vehicle and leases without naming the 2026 Lease Arrangement, and the S-1/A names no vehicle, no $63B and no support; neither filing cites the other. 'The public record also does not confirm that the October vehicle finances the same leases the S-1 describes' (Global Data Center Hub, Nov 2 2026). The size of the assigned portion is undisclosed, as is how much of Anthropic's ~$161.2B of rent on its Broadcom leases (avgo-anth-tpu) this vehicle carries Broadcom 8-K; joint release; Anthropic S-1/A; Global Data Center Hub (Nov 2 2026)
combined-peakone entry, in its own words
$72B = $43B + $29B, a sum no filing states: 'If both peaked together, that is up to $43bn + $29bn = $72bn' (No Diligence, Oct 28 2026), and the same figure without its condition elsewhere ('Broadcom’s filings show backstops of up to about $72bn', Staring Down the Barrel; Beating the Bull). The two ceilings run on separate schedules: the June vehicle's compute was expected to deploy from mid-2026 and was under way by Broadcom's September call (anth-fluidstack), this one's deliveries start in 2027, and each balance falls as rent is paid, so the two need not peak together. Carried so it never enters a cell; neither ceiling is a current balance No Diligence (Oct 28 2026); Staring Down the Barrel (Nov 3); Beating the Bull (Nov 1); Broadcom 8-K and 10-Q
rack-sellerone entry, in its own words
who sells the racks to the vehicle, and so how much of the $63B reaches Broadcom: undisclosed. The release says 'the purchase of Broadcom XPU AI accelerators and networking solutions'; the slide, 'Broadcom and partners develop and provide technology to the SPV' and 'Deliver Technology (With Partners)'; the 8-K, 'reselling the AI racks back to the seller', in the third person. The press calls the chips Broadcom-developed Google TPUs (DCD) or chips 'designed by Broadcom and Google' (the WSJ); the release never says Google; and Anthropic's March 2026 lease has Broadcom buying its TPU8i pods from Google to lease them on (avgo-anth-tpu's tpu8i-seller). So the $63B is not Broadcom's revenue from this deal; what Broadcom books is avgo-anth-tpu's broadcom-revenue Joint release; Broadcom 8-K and slides; Anthropic S-1 ex-10.11; DCD; WSJ via BusinessDesk

Scope note what this record leaves to other records

NOT this record (carried elsewhere or not carried): the June AI XPV first tranche — $35B, Big Sky, the A1/A2/B notes and coupons, Athene's 15% guarantee, Broadcom's ~$29B Backstop at 85% → anth-fluidstack; no document ties that vehicle to this one. Anthropic's Broadcom leases as a whole (~$161.2B of rent, ~$125.2B under the March 2026 lease), the up-to-$42.0B convertible note facility and how a note settles rent, the 3.5/5/10 GW capacity path and what Broadcom books → avgo-anth-tpu. Anthropic's company figures (leases not yet commenced at Jun 30 2026, $266.2B in the Oct 9 draft vs $321.4B in the S-1; ~$451.2B at Sep 30; ~$895.4B of committed spend; liquidity and covenants; its other compute commitments) → the anthropic entity at most; Broadcom's company figures (borrowings, cash, free cash flow, RPO, AI-revenue guidance, customer concentration) → the broadcom entity at most. Also carried elsewhere with those figures, unresolved and not this deal's: the $36.0B remainder of the lease rent; Athene's holdings; 'dollars per gigawatt', different quantities side by side. Not adopted: the $72B as a filing figure (combined-peak); 'peak exposure … in the first year' (William Blair via Dow Jones — Broadcom's schedule is footnoted as illustrative); IFR's 15GW read as this financing (the whole order); the $60B and $80B headlines of Yahoo's related-stories sidebar, which can be misread as this deal's size; Soon Parted's $30B backstop (the June deal's senior debt, not a cap); Blackstone Credit North Star Fund LP's Form D (Oct 8 2026, a fund's name, no mention of Broadcom, Anthropic or this financing — a name is not a tie). Fitch's Oct 27 note is available on file only as a stub, so its figures here come through Börse Global's summary. The August talks' numbers (more than $60B, a $60–70B senior tranche and a roughly $30B junior one, up to $100B in all; Bloomberg's report of Aug 20 2026, the date Reuters' relay of it carries (via The Star), read here in Communications Today's reprint of Aug 21) are superseded pre-deal sizing, out of every cell; whether this is a tranche of the AI XPV platform no party says, and no party document names Apollo in it.

More between these companies

  1. Nov 9, 2026 updated Nov 19
  2. Dec 17, 2025 updated Nov 20
  3. Dec 2025 updated Nov 20
  4. Nov 12, 2025 updated Nov 21
  5. Oct 23, 2025 updated Nov 21
  6. Sep 4, 2025 updated Nov 21

Everything between Broadcom and Anthropic → · Everything between Broadcom and Blackstone → · Everything between Anthropic and Blackstone → · Everything between Anthropic and Lenders & bondholders → · Everything between Blackstone and Lenders & bondholders →