Why it matters
Google is backing rent at Hawesville on halls where Anthropic must use Google-approved TPUs as its only accelerators, under the form of agreement TeraWulf filed. Google's guarantee starts only once each building's last hall is delivered, leaving completion risk with TeraWulf. It ends once Anthropic holds investment-grade ratings of its own.
Tap a figure for the line in its source.
Anthropic gives
TeraWulf gives
Google gives TeraWulf
- backs Anthropic's rent from each building's last delivered hall until Anthropic is rated investment grade: Google takes the lease over, or after six years (sooner if the TPUs installed can draw under half the halls' power) may pay a shrinking termination fee instead; the amount is not disclosed
What happened
In July 2026 Anthropic signed a 20-year lease with TeraWulf, a former bitcoin miner, for a data-center campus TeraWulf is building on the site of a closed aluminum smelter in Hawesville, Kentucky. TeraWulf will supply about 401 megawatts of computing load in three buildings, in phases from late 2027 into the second quarter of 2028. It says the lease will bring it roughly $19 billion of rent over the first 20 years, up to about $33 billion if Anthropic uses both five-year extensions. It is the first time Anthropic has signed a landlord directly rather than renting through a cloud company, and TeraWulf's filing names it. For four months TeraWulf would say only that an 'investment-grade credit' would stand behind the rent, and its finance chief declined to name it when asked; on November 4 it named Google. Once each building's last hall is delivered, if Anthropic stops paying or goes insolvent, Google steps in to pay the rent and take over the lease. After six years, or sooner if the TPUs installed can draw less than half the halls' power, Google may instead pay a shrinking fee and take a stake in TeraWulf's landlord company. The lasts until Anthropic holds investment-grade ratings of its own. The size of that fee has not been disclosed, and the form of agreement TeraWulf filed also commits Anthropic to use only Google-approved TPU chips as the halls' accelerators. TeraWulf puts its own cost of building the halls at $3.5–4.5 billion, depending on which of its statements you read; it told Kentucky regulators Anthropic would put roughly $10 billion of its own computers inside. The lease itself has not been made public.
Sources 20 documents — 15 SEC filings · 3 regulatory filings · 1 transcript · 1 company release
Research trail Found 500 documents and read 460 of them while checking this deal and related ones.
- States 6 figures: 401 MW critical IT load · lease amendments · credit support provider · backstop window · backstop options · termination fee
- States 5 figures: lease term · delivery · lease status · $200M site acquisition · epc agreement
- States 3 figures: lease documents · backstop six years · TPU only
- States 3 figures: 482 MW power contract · power term · 482 MW power take or pay
- States 2 figures: tenant · credit support
- States 2 figures: 401 MW tenant corroboration · $300M century put
- States 2 figures: building schedule · $800M annualized NOI
- States $19B initial term revenue
- States up to $33B extended term revenue
- States up to 480 MW gross site power
- States $10B tenant compute investment
- States credit support CFO
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: TeraWulf 8-K Item 8.01 + ex-99.1 (2026-07-06), Q2-2026 10-Q + earnings release + call; Century Aluminum Q2-2026 10-Q; Kentucky PSC Case 2026-00115 (order 2026-08-21, TeraWulf Energy Plan, AG data responses); TeraWulf release 2026-08-24 (read 2026-09); TeraWulf 8-K Items 1.01/8.01 + ex-10.1 form of the Google Credit Support Agreement + ex-99.1 release, furnished (2026-11-04); Anthropic S-1/A (2026-11-02), which does not name the lease (updated 2026-11); TeraWulf Q3-2026 release and investor update, furnished (2026-11-06); Century Aluminum Q3-2026 10-Q (2026-11-05) (updated 2026-11-06); TeraWulf Q3-2026 10-Q (2026-11-06) (updated 2026-11-08) · as of Nov 2026
The evidence 28 sourced figures · 1 dispute
The record's headline TeraWulf–Anthropic, Justified Data Campus (Hawesville KY): 20-year lease for ~401 of critical IT, ~$19B over the initial term — Anthropic named in the landlord's own 8-K; Google agreed on Nov 4 2026 to the rent from each building's last hall on (amount unfiled), and the halls' accelerators must be Google-approved TPUs
- Size
- $19B initial term (~$33B with both 5-yr options) · ~401 MW critical IT · Google backstop, amount unfiled
- When
- Jul 2026 lease → Nov 4 2026 Google credit support + lease amendments → delivery late 2027 → Q2 2028, the backstop starting at each building's last hall; 20-year term from delivery + 2 × 5-yr options
- Status
- dated on or around Jul 3 2026, announced Jul 6 — 'had not commenced' as of the Q3-2026 10-Q (Sep 30 2026); amended, and the Google credit support entered into, Nov 4 2026 (effective only from each building's last hall); the leases themselves still unfiled
- Structure
- direct 20-year data-center leases, tenant = the lab itself (no Fluidstack, no cloud in between) — three, one per building (CB-1, CB-2, CB-3), each a sublease from TeraWulf's Raylan Data LLC, which holds the land under a ground lease from Justified DataPower LLC (the buildings' owner, per the Nov-4 form, and the utility customer); TeraWulf Inc. guarantees certain of the landlord's obligations. Rent starts on delivery of each data hall; two 5-year renewal options at the tenant's election. Credit support since Nov 4 2026: Google LLC, one agreement per building — effective from that building's last hall, ending once Anthropic is investment grade for three months; on a default Google pays the rent and takes the lease over, or (after six years, or sooner if the TPU pods installed can draw less than half the tenant's critical power) pays an amortizing termination fee sized to the project debt and may take equity in Raylan; only Google-approved TPUs as accelerators. Power under a separate 15-year utility contract with the landlord, not the tenant
- Programme
- Anthropic direct leases
- Parties
- Anthropic tenant — named as 'Anthropic PBC' in the landlord's 8-K and 10-Q, and a party to the Nov-4 Google Credit Support Agreements; has not named the lease itself (its S-1 describes partner-guaranteed direct leases, no site named); also, per TeraWulf's PSC filing, the buyer of ~$10B of compute for the halls — its accelerators Google-approved TPUs only, per the agreements' filed form · TeraWulf landlord and developer via Raylan Data LLC / Justified DataPower LLC, with TeraWulf Inc. guaranteeing certain of the landlord's obligations; the utility counterparty for the site's 482 MW; 93.2% of the development entity (Century Aluminum holds 6.8%) · Google credit-support provider since Nov 4 2026 — backs Anthropic's rent from each building's last hall until Anthropic is rated investment grade; may take equity in Raylan if it ever pays the termination fee; not a party to the leases, and no TeraWulf warrants in these filings
- Record
- disclosed / primary source · as of Nov 2026
Flows 3 as the record states them
- Anthropic → TeraWulflease-payments~$19B of contracted lease revenue over the 20-year initial term (TeraWulf's figure, 8-K ex-99.1); up to ~$33B if both 5-year options are exercised (Q2-2026 release, furnished). Rent per MW and escalators are unfiled; nothing is payable before delivery of the first phase in late 2027
- TeraWulf → Anthropiccapacity~401 MW of critical IT load at the Justified Data Campus, in three buildings (CB-1, CB-2, CB-3) delivered in phases from late 2027 to the second quarter of 2028 (Nov-4 8-K; 'early 2028' in the Jul-6 8-K and the 10-Q); on up to 480 MW of gross site power
- Google → TeraWulfguaranteebackstop of Anthropic's obligations under the three Justified Leases — one Credit Support Agreement per building, entered into Nov 4 2026 — effective from the commencement of each building's last data hall and ending once Anthropic (or an affiliate guaranteeing the lease) holds investment-grade ratings for three months. On a payment default or insolvency Google pays the rent due and takes over the lease (on a payment default it may defer instead, paying the rent meanwhile); only after six years, or sooner if the TPU pods installed can draw less than half the tenant's critical power, may it pay an amortizing termination fee instead, and then take equity in Raylan. Amount unfiled: the fee schedule is omitted from the filed form and is sized to project debt not yet raised
Resolved figures 28 each with the verbatim line from its document
- tenantAnthropic PBC, named as tenant by the landlord in its own 8-K (Item 8.01) and again in the Q2-2026 10-Q ('the Anthropic HPC Lease … with Anthropic PBC'). The first of Anthropic's data-center leases where the lab is the lessee on the landlord's paper rather than a cloud operator (contrast the Fluidstack leases at Lake Mariner / Cipher / Hut 8 — goog-anth-backstops). Anthropic itself has not named the lease: its S-1/A (Nov 2 2026), the registration statement as amended, never mentions TeraWulf, Hawesville or Kentucky, though it says Anthropic has 'executed data center leases directly' and has relied on 'partners who guarantee the lease obligations to support the development of data center capacity that is expected to host such partner’s chips or computing infrastructure' — this deal's shape, attributed to no site
“On July 6, 2026, TeraWulf Inc. (the “Company”) announced that its subsidiary Raylan Data LLC (the “Landlord”) entered into a 20-year lease agreement (the “Justified Data Campus Lease”) with Anthropic PBC (“Anthropic”), as tenant.”
TeraWulf 8-K, Item 8.01 (filed 2026-07-06; accession 0001104659-26-080583 — TeraWulf's IR mirror of the same document is among this record's sources as a convenience copy) · sec.gov - tenant-corroboration401 MWthe same tenant, term and capacity restated by an unrelated registrant: Century Aluminum, which sold the Hawesville site and holds a 6.8% put-able interest in the development subsidiary, describes the Jul-6 lease with 'Anthropic PBC' in its own Q3-2026 10-Q (filed Nov 5 2026). The paragraph is word for word the one in its Q2-2026 10-Q (Aug 2026): a restatement of TeraWulf's July announcement, not a fresh account — it still gives delivery as 'concluding in early 2028', the end date TeraWulf's Nov-4 8-K moved to the second quarter of 2028, and it says nothing of Google or the credit support. Interested (it is paid out of the project) but independent — the record's one genuine second source; every press repetition of '$19B' is TeraWulf's release restated
“On July 6, 2026, Terawulf announced that its subsidiary entered into a 20-year lease agreement with Anthropic PBC under which Terawulf’s subsidiary will provide Anthropic with approximately 401 MW of critical IT load for high-performance computing operations at the Hawesville site.”
Century Aluminum Q3-2026 10-Q (MD&A — Hawesville) · sec.gov - critical-it-load401 MW~401 MW of critical IT load — the leased quantity, in the Jul-6 8-K, the release, the 10-Q ('approximately 401 MW of critical IT load at the Justified Data Campus', Note 18) and Century's 10-Q alike, restated unchanged in the Nov-4 8-K (Item 1.01) and again in the Q3-2026 10-Q (Note 8: 'approximately 401 MW of critical IT load at the Justified Data Campus'), the 8-K giving the premises as three buildings, CB-1, CB-2 and CB-3, with a lease each. Other documents give 384 MW (Q1-2026 investor deck, May) and 370 MW (TeraWulf's sworn Jun-11 answer to the Kentucky AG, repeated verbatim in the Aug-14 Energy Plan) — read here as a DATED DESIGN SERIES, not a dispute: 370 and 384 are pre-lease site plans, 401 is the executed lease, and no document claims the earlier numbers still hold. The regulator was shown 370; the tenant contracted 401
“in July 2026, the Company’s subsidiary Raylan Data LLC (“Raylan”) entered into a 20-year lease agreement with Anthropic, PBC (“Anthropic”), as tenant, to provide Anthropic with approximately 401 MW of critical IT load for high-performance computing (“HPC”) operations at the Company’s data center campus located in Hawesville, Kentucky.”
TeraWulf 8-K, Item 1.01 (filed 2026-11-04) · sec.gov - lease-term20 years20 years, plus two successive five-year renewal options at Anthropic's election (up to 30 years) — and the Q3-2026 10-Q says what the 20 years are counted from: the leases 'commence in phases upon delivery of the applicable leased premises', 'with all phases under the respective agreement expiring 20 years after its final phase commences'. So each lease's 20 years run from its LAST phase, not from each phase's own delivery; on that reading an earlier phase runs past 20 years from its own start (our reading), and no document says whether the ~$19B (initial-term-revenue) counts the extra time. The Jul-6 8-K had put it as rent that 'will commence upon the delivery of the applicable leased premises and continue for a term of 20 years thereafter', which can be read either way. Delivery is phased across the three buildings (the Nov-4 8-K's CB-1, CB-2 and CB-3, a lease each), so each lease's 20 years run from its own building's last phase — the latest due by the second quarter of 2028 — not from signing; no filed document dates the other two buildings' last phases (the furnished building-schedule gives a target for each building and does not say whether it is a first hall or a last). The 15-year term elsewhere in this record is the POWER contract's, not the lease's
“The Anthropic HPC Leases commence in phases upon delivery of the applicable leased premises and satisfaction of the related commencement conditions, with all phases under the respective agreement expiring 20 years after its final phase commences. Anthropic may extend each agreement for two additional five-year terms.”
TeraWulf Q3-2026 10-Q, Note 8 — Leases · sec.gov - initial-term-revenue$19B~$19B of contracted lease revenue over the 20-year initial term — TeraWulf's projection, stated in the Jul-6 release (8-K ex-99.1, filed under Item 9.01), the Q2 release, the 10-Q's MD&A and the CFO's 'approximately $19 billion of contracted revenue over the initial term' on the Q2 call; the Nov-4 release repeats it as the lease Google's credit support serves ('approximately $19 billion of contracted lease commitments', furnished) — the lease's value, not the backstop's — and the Nov-6 results release restates it unchanged ('approximately $19 billion of contracted revenue over the initial term', furnished). The 8-K BODY carries no dollar figure, nor does the Nov-4 8-K's; the 10-Q's Note 18 carries none either. No per-MW rent or escalator is disclosed anywhere (the Nov-6 deck's ~$800M average annual NOI, annualized-noi, is a projection net of costs, not a rent), and the lease is not an exhibit — so $19B is a party headline the documents on file cannot decompose
“The lease is expected to generate approximately $19 billion of contracted lease revenue over the initial term and is expected to be supported by an investment-grade credit.”
TeraWulf 8-K ex-99.1 (press release, filed 2026-07-06) · sec.gov - extended-term-revenueup to $33Bup to ~$33B if Anthropic exercises both five-year options — INCLUSIVE of the $19B, never additive. Not in the Jul-6 8-K, its release or the 10-Q (the 10-Q's only '$33' figures are buybacks and cost-to-mine): it first appears a month later in the Q2-2026 earnings release and deck, both furnished under Item 2.02/7.01, never filed. Tier 1 all the same: TeraWulf's own release, read from its own copy on EDGAR. The Q2 deck's '~$33B of total revenue over 30-years' is the same figure
“The lease represents approximately $19 billion of contracted revenue over the initial term and up to approximately $33 billion if Anthropic exercises both five-year extension options.”
TeraWulf Q2-2026 earnings release (8-K ex-99.1, furnished 2026-08-05) · sec.gov - delivery2028phased, across three buildings: the first halls in late 2027, the last in the second quarter of 2028 — in the Q3-2026 10-Q's MD&A, in the Nov-4 8-K (Item 1.01: 'beginning in late 2027 and concluding in the second quarter of 2028') and in the Nov-4 release's construction schedule ('phased ready-for-service completions are expected to begin in late 2027 and continue through the second quarter of 2028', repeated in the 10-Q's Fluor paragraph). The Q3 10-Q's Note 8 words the same window more loosely — initial capacity 'in the second half of 2027' and full delivery of the 401 MW 'in the first half of 2028' — windows that contain the MD&A's dates. The end date moved: the Jul-6 8-K had delivery 'beginning in late 2027 and concluding in early 2028', and the Q2 10-Q 'full delivery of the 401 MW of critical IT load expected in early 2028' — the landlord restating its own schedule, not two sources disagreeing; the start is unchanged. Rent follows delivery of each data hall, so no cash moves before late 2027, and Google's backstop starts only at each building's last hall (backstop-window). The Q2 10-Q's site plan: 'construction is expected to commence in 2026, with a phased buildout extending through 2027, subject to site planning and permitting approvals'; the landlord's builder is Fluor (epc-agreement)
“Initial capacity is expected to be delivered in late 2027, with phased deliveries continuing through the second quarter of 2028.”
TeraWulf Q3-2026 10-Q, MD&A — Justified Data Campus · sec.gov - lease-status'had not commenced' as of September 30, 2026 — the accounting statement that no rent, no lease asset and no revenue exist yet. The Q2-2026 10-Q said it as of its August issue date ('The Anthropic HPC Lease had not commenced'); the Q3-2026 10-Q (filed Nov 6) says it again at quarter-end and now speaks of the 'Anthropic HPC Leases', plural, matching the three leases of the Nov-4 8-K. Still unfiled: not an exhibit to the Jul-6 8-K (Items 8.01/9.01, press release only) or to either 10-Q (the Q2 exhibit index: capped calls, RRAs, employment letters, incentive plans; the Q3 one files only Amendment No. 1 to the parent's revolving credit agreement, Oct 23 2026, beside the certifications), and the Nov-4 8-K files only a FORM of the credit support agreements, whose Schedule B-1 ('LEASE') is omitted under Item 601(a)(5) of Regulation S-K. The form does say what the paper is (lease-documents), and the leases were amended on Nov 4 (lease-amendments). Termination rights, delay remedies, deposits and rent per MW: unknown
“The Anthropic HPC Leases had not commenced as of September 30, 2026.”
TeraWulf Q3-2026 10-Q, Note 8 — Leases · sec.gov - lease-documentswhat the paper is, from the recitals of the filed form: Anthropic's lease is a 'Sublease Agreement dated on or around July 3, 2026' from Raylan Data LLC, which holds the land under a ground lease of the same date from Justified DataPower LLC (the form's 'Master Landlord', which it says owns the building); TeraWulf Inc. has guaranteed certain of Raylan's obligations to Anthropic (the 'Landlord Guaranty'); and a 'Superior Lessor Recognition Agreement' binds Justified DataPower, Raylan and Anthropic to one another. One set per building — the 8-K's three agreements for CB-1, CB-2 and CB-3 — where the Jul-6 8-K had announced 'a 20-year lease agreement'. No guaranty by Anthropic or a parent is among the documents the form lists; Google's backstop is the tenant-side credit
“Tenant is the tenant of Landlord under that certain Sublease Agreement dated on or around July 3, 2026 (attached hereto as Schedule B-1, as amended from time to time, the “Lease”), pursuant to which Landlord leases to Tenant the Premises, as defined therein.”
TeraWulf 8-K ex-10.1, Form of Credit Support Agreement, Recitals (filed 2026-11-04) · sec.gov - lease-amendmentsthe leases were amended on Nov 4 2026 'in connection with the Justified Google Backstop' — Item 8.01, terms undisclosed, the amendments unfiled. From here on the form gives Google a say: a non-ministerial amendment made without its consent does not bind Google if it ever takes the lease over (an 'Unapproved Amendment'), and Google may refuse, at its sole discretion, any amendment that raises Anthropic's payments or extends the term
“On November 4, 2026, in connection with the Justified Google Backstop, Raylan and Anthropic entered into amendments to the Justified Leases.”
TeraWulf 8-K, Item 8.01 (filed 2026-11-04) · sec.gov - credit-supportwhat the landlord said in July, and the record's central gap for four months: Anthropic's payment obligations 'are expected to be supported by an investment-grade credit' — no provider, no amount, no date, no signature, and the phrase is absent from the 10-Q's Note 18 (the 10-Q uses 'investment-grade credit support' only generically and names Google only for the Abernathy/Fluidstack lease). 'Expected' was the operative word, and it held until Nov 4 2026, when Google LLC entered into three Credit Support Agreements (credit-support-provider) — still with no filed amount (termination-fee), and effective only from each building's last hall (backstop-window). Riot's parallel lease had the same hole ('while the investment-grade credit backstop is finalized'; anth-riot-rockdale)
“Anthropic’s payment obligations under the Justified Data Campus Lease are expected to be supported by an investment-grade credit.”
TeraWulf 8-K, Item 8.01 · sec.gov - credit-support-cfoasked point-blank by KBW's Stephen Glagola 'where you stand with securing credit support on the Anthropic lease at Hawesville and who that counterparty is', CFO Patrick Fleury re-stated the filing language and declined to name anyone — on the record, Aug 5 2026 (transcript dated Aug 12); KBW's published read of the same call called 'the lack of finalized investment-grade credit support' the deal's key overhang. Three months later the Nov-4 8-K named Google (credit-support-provider): the newsletters' 'Google', an inference from the Lake Mariner precedent, turned out right, but no party document said so before then
“I would just reiterate what we said in that the Hawesville lease will be supported by an investment-grade credit.”
TeraWulf Q2-2026 earnings call, Q&A (Motley Fool transcript) · fool.com - credit-support-providerGoogle LLC — named in TeraWulf's 8-K of Nov 4 2026 under Item 1.01, a material definitive agreement: three Credit Support Agreements, one per building (CB-1, CB-2, CB-3), among TeraWulf, Raylan, Justified DataPower, Anthropic and Google (TeraWulf Inc. joins the form only as the landlord's guarantor, for §13.e). Until this filing the record carried the provider as contested — unnamed in every party document, 'Google' only as newsletter inference from Lake Mariner, and not finalized per KBW — and the filing settles all three readings. Unlike Lake Mariner (73,580,000 penny warrants), neither the 8-K, its release nor the form gives Google any TeraWulf shares or warrants; its upside is an option on equity in Raylan if it ever pays the termination fee (backstop-options). No amount is filed (termination-fee). The release (furnished) adds that Google LLC is 'a subsidiary of Alphabet Inc.' and that 'Alphabet’s senior unsecured debt is rated AA+ by S&P Global Ratings and Aa2 by Moody’s'. TeraWulf's Q3-2026 10-Q (Note 18, a subsequent event) restates the agreements — 'the Company, certain of its subsidiaries and Anthropic entered into credit support agreements with Google in connection with each of the Anthropic HPC Leases' — and, like the 8-K, files no amount
“In connection with the Justified Leases, on November 4, 2026, the Company entered into three Credit Support Agreements for CB-1, CB-2 and CB-3, respectively (each a “Google Credit Support Agreement” and collectively, the “Google Credit Support Agreements”), with Raylan, Justified DataPower LLC, a wholly owned subsidiary of the Company, Anthropic and Google LLC (“Google”), pursuant to which Google agreed to backstop (the “Justified Google Backstop”) certain obligations of Anthropic under the Justified Leases.”
TeraWulf 8-K, Item 1.01 (filed 2026-11-04) · sec.gov - backstop-windowwhen Google stands behind the rent: each agreement takes effect only at the commencement of the LAST data hall of its building's lease — so it covers none of that building's construction or the ramp of its halls, and a tenant default before then waits for the halls (the form lets the landlord finish the premises and treats a default still running on that date as the trigger). It ends, among other conditions, once Anthropic — or an affiliate that guarantees the lease — holds investment-grade ratings for at least three months; the form leaves the thresholds blank ('[investment grade] or higher by S&P or Fitch'). Google backs the rent only until Anthropic's own credit can
“The Justified Google Backstop under each Google Credit Support Agreement will become effective as of the commencement date for the final data hall under the corresponding Justified Lease and will terminate upon the conditions described in the Google Credit Support Agreements, including Anthropic (or its affiliate, if such affiliate has agreed to guarantee Anthropic’s obligations under the applicable Justified Lease) achieving and maintaining certain investment grade credit ratings for a period of at least three months.”
TeraWulf 8-K, Item 1.01 (filed 2026-11-04) · sec.gov - backstop-optionswhat Google does on a default: on a payment default or Anthropic's insolvency, after notice from Raylan, Google either pays the rent due and takes over the lease as tenant, or — 'under certain circumstances' (backstop-six-years) — pays a termination fee, after which it may take an equity interest in Raylan. The filed form sizes that interest as the fee divided by the total cost to develop the land and build the building, financing costs included, and caps Google's liability on that path at the fee. On a payment default (not an insolvency) Google may also defer the choice, paying all unpaid rent meanwhile. Google's equity upside comes only if it pays — not as warrants up front, as at Lake Mariner
“The Justified Google Backstop provides that in the event of a payment default under a Justified Lease, or if Anthropic becomes subject to an insolvency event, following notice from Raylan, Google will have the option to (i) pay all rent currently due under the applicable Justified Lease and assume the Justified Lease as the tenant thereunder, or (ii) under certain circumstances, pay a certain termination fee pursuant to the applicable Google Credit Support Agreement; provided that upon payment of such termination fee, Google would be entitled to acquire an equity interest in Raylan.”
TeraWulf 8-K, Item 1.01 (filed 2026-11-04) · sec.gov - backstop-six-years6the 'certain circumstances', from the filed form: for six years after its agreement takes effect Google may NOT walk away from a default by paying the fee — it takes the lease over (or keeps paying the rent while it defers), and a Google that stays silent is deemed to have taken the lease over — unless the 'Equipment Capacity Trigger' occurs: the TPU pods installed in the building can draw less than half of the tenant's critical power. After six years a silent Google is deemed to have rejected the lease, and the fee path opens. So the strongest part of the backstop holds only while TPU pods can draw at least half the critical power (tpu-only). A form, not the executed agreements (their schedules are omitted); the 8-K files it as the form of all three and incorporates it by reference. The Q3-2026 10-Q (Note 18) restates the rule without the percentage: 'Within the first six years following the effectiveness of the applicable credit support backstop, Google may elect for the lease to be terminated only under limited circumstances relating to the installed equipment capacity in the relevant building'
“Notwithstanding the foregoing, Google shall not exercise the Google Rejection Option within the first six (6) years after the CSA Effective Date unless the Equipment Capacity Trigger occurs. “Equipment Capacity Trigger” means that the TPU Pods installed within the Building, when in operation, are capable of consuming less than fifty percent (50%) of the Tenant Critical Power.”
TeraWulf 8-K ex-10.1, Form of Credit Support Agreement §4.e (filed 2026-11-04) · sec.gov - termination-feethe backstop's size is not filed. The fee 'amortizes over a defined term' from the expected start of each agreement, per a schedule the form omits (Schedule C-1). The form ties it to the landlord's project debt: the schedule 'has been prepared based on the anticipated amount of indebtedness' to finance the build, may only be reduced to the debt actually raised, and any update is capped at the lesser of a blank dollar amount (footnoted 'Corresponds to anticipated maximum Project Debt amount') and a blank share of the build's 'Uses of Funds'. So the fee — Google's price for walking away — tracks project debt that is still 'anticipated' (the release). Contrast Lake Mariner ($3.2B) and Abernathy ($1.3B), whose backstop amounts TeraWulf disclosed. The release's headline '$19 Billion Anthropic Lease' is the lease, not the backstop. The Q3-2026 10-Q (Note 18) says it in one sentence and adds no number: the fee 'decreases over time and is subject to limits, including based on the amount of the related project financing'
“The termination fee payable under the Justified Google Backstop amortizes over a defined term following the anticipated effectiveness of the corresponding Google Credit Support Agreement.”
TeraWulf 8-K, Item 1.01 (filed 2026-11-04) · sec.gov - tpu-onlythe halls are TPU-only: the filed form binds Anthropic and its affiliates to 'use only Google-approved tensor processing units for accelerator processors in the Premises' for the agreement's whole term — an obligation of the tenant alone, the form says, not the landlord. The agreement ends, among other ways, when the lease does or once Anthropic is investment grade for three months, and §2.k is not among the sections §12.c says survive. So the accelerators in the ~$10B of compute TeraWulf told the Kentucky PSC Anthropic would fund (tenant-compute-investment) must be Google-approved TPUs. Whose they are is not said: the form also provides for 'Google Property' — 'equipment or property owned by Google (or its affiliate) that is located in the Premises', which Google may inspect and remove — without saying whether any is there, and none of these filings says whether Anthropic buys its TPUs (from Google, or from Broadcom — avgo-anth-tpu) or rents them
“Tenant (and any Affiliate thereof) shall use only Google-approved tensor processing units for accelerator processors in the Premises for the entire term of this Agreement.”
TeraWulf 8-K ex-10.1, Form of Credit Support Agreement §2.k (filed 2026-11-04) · sec.gov - gross-site-powerup to 480 MWup to 480 MW of gross power availability at the site (10-Q; the Q2 release says 'up to approximately 480 MW of gross power capacity') — this record uses that figure over the 482 MW in the utility contract: two quantities, not a conflict. 480 is TeraWulf's rounding of the site's capability; 482 is the contracted Maximum Contract Demand and take-or-pay floor below. 401 MW critical IT on ~480 MW gross is an ~84% IT-to-grid ratio. The Q3-2026 10-Q does not repeat the 480 MW sentence: it gives the site's power only as the PSC-approved 'up to 482 MW of electric service' (MD&A), so 480 stands on the Q2 10-Q and the Q2 release, and none of TeraWulf's Nov 4–6 documents repeats it
“The Justified Data Campus has up to 480 MW of gross power availability; construction is expected to commence in 2026, with a phased buildout extending through 2027, subject to site planning and permitting approvals.”
TeraWulf Q2-2026 10-Q, MD&A — Justified Data Campus · sec.gov - power-contract482 MW482 MW Maximum Contract Demand under a Retail Electric Service Agreement between Big Rivers Electric (wholesale), Kenergy (retail delivery) and Justified DataPower LLC, a TeraWulf subsidiary — approved by the Kentucky PSC Aug 21 2026 (Case 2026-00115), which had been shown the 370 MW / $3.5–4.0B pre-lease plan. Market pass-through pricing (energy, capacity, transmission, congestion, uplift, credit support all for TeraWulf's account) plus negotiated demand adders that escalate annually. The 482 MW is 'existing transmission capability at the former Century Hawesville smelter site' — reused, not new. Anthropic is not named anywhere in the docket: the power layer is the landlord's, tenant-agnostic. amd-anthropic's note had quarantined this docket as 'customer unnamed' — it is this lease's site
“The planned facility has a Maximum Contract Demand of 482 megawatts (MW).”
Kentucky PSC final order, Case 2026-00115 (2026-08-21) · psc.ky.gov - power-term15-year initial term from the Construction Completion Date with automatic five-year renewals — SHORTER than the 20-year lease it powers (plus the lease's two 5-year options): not a contradiction (different counterparties, different instruments) but the record does not imply the power is contracted for the tenancy's full term. Renewal is automatic unless terminated, so the mismatch is a renewal-pricing exposure, not a cliff
“The RESA has an initial term of fifteen years following the Construction Completion Date and provides for automatic five-year renewal terms unless terminated in accordance with the agreement.”
Kentucky PSC final order, Case 2026-00115 · psc.ky.gov - power-take-or-pay482 MWfor the first six years TeraWulf pays demand charges on the full 482 MW whether or not it draws it — the ratepayer protection the PSC leaned on. After year six it may reduce its Maximum Contract Demand, with the adders adjusted. So the landlord carries a six-year fixed power obligation against a tenant whose rent starts only on delivery and whose credit support is not yet in place — the landlord-side exposure the $19B headline hides
“During the first six years of the agreement, TeraWulf’s Maximum Contract Demand is 482 MW, and its monthly Billing Demand is the greater of its Maximum Contract Demand or its actual monthly peak demand.”
Kentucky PSC final order, Case 2026-00115 — Risk Allocation · psc.ky.gov - tenant-compute-investment$10B~$10B of compute (server racks etc.) 'will be funded by Anthropic' — TeraWulf's representation to the Kentucky PSC in its Aug-14 Energy Plan, affirmed under its COO's name in the Jun-11 AG response ('an additional approximately $10 billion investment', 'likely to exceed $10 billion'). Tier 1 for what TeraWulf told the regulator; NOT an Anthropic commitment — Anthropic has stated no figure. Kept separate from the landlord's own capex (contested): the '$14B Hawesville data center' headline is one aggregator adding the two, a number no company states
“The compute infrastructure (e.g., server racks) will be funded by Anthropic at a cost of approximately $10 billion.”
TeraWulf Energy Plan, attachments (Kentucky PSC Case 2026-00115, filed 2026-08-14) · psc.ky.gov - site-acquisition$200Mthe ground under the lease: TeraWulf bought the Hawesville site from Century Aluminum on Feb 2 2026 for $200.0M cash plus a 6.8% non-dilutive minority interest in the development subsidiary (total fair-value consideration ~$301.9M). TeraWulf holds the other 93.2% — 'As of September 30, 2026, the Company holds a 93.2% controlling interest in the Justified Data Campus Developer' (Q3-2026 10-Q, Note 11), which it consolidates as a variable interest entity. Century holds a put on that interest from the first anniversary of operations — which is why its 10-Q discloses the tenant. The seller's interest sits on the edge of the tenant corroboration above
“Total consideration in the Justified Data Campus asset acquisition consisted of (i) $200.0 million in cash and (ii) a 6.8% non-dilutive minority equity interest in the Company’s subsidiary formed to develop and own an AI/HPC data center on the property.”
TeraWulf Q3-2026 10-Q, Note 3 — Justified Data Campus · sec.gov - building-schedulethe three buildings as the deck for TeraWulf's Q3-2026 results sets them out (Nov 6 2026; furnished under Item 7.01): 137.6 MW of critical IT in CB-1 (target delivery Q4 2027), 137.6 MW in CB-2 (Q1 2028) and 125.6 MW in CB-3 (Q2 2028) — 400.8 MW together (the sum is ours), the leased ~401 MW. The slide's text lists the buildings as CB-3, CB-2, CB-1 and the figures and quarters in that same order, so the pairing rests on the table's layout. It fits the Nov-4 8-K's phasing (late 2027 to the second quarter of 2028) and splits it by building; whether a building's target is its first hall or its last, the slide does not say
“CB-3 CB-2 CB-1 Building 125.6 MW 137.6 MW 137.6 MW Critical IT Q2 2028 Q1 2028 Q4 2027 Target delivery”
TeraWulf Q3-2026 investor update (8-K ex-99.2, furnished 2026-11-06) · sec.gov - annualized-noi$800M~$800M a year of average annualized net operating income once operational for the Justified campus — TeraWulf's projection on the deck for its Q3-2026 results (Nov 6 2026; furnished). The deck's own definition makes NOI non-GAAP, 'lease revenue for a specific lease less cost of revenue', before capex, G&A and depreciation. Against ~$19B over 20 years (~$0.95B a year) it is about 84% — close to the deck's '~85% target NOI margin on contracts' (the division is ours). The deck gives the portfolio's average annualized NOI as ~$1.5B and splits it between the two campuses (~$800M here, ~$700M at Lake Mariner). Until this slide this record said no NOI was disclosed anywhere (see initial-term-revenue); rent per MW and escalators still are not
“JUSTIFIED DATA | Hawesville, KY 401MW CONTRACTED CRITICAL IT ~$19B CONTRACTED REVENUE ~$800M AVG. ANNUALIZED NOI ONCE OPERATIONAL (1) Tenant Anthropic Lease term 20-year initial term + two 5-year extensions Credit support Google backstop; Alphabet Aa2 / AA+ Status Fluor EPC; phased delivery late 2027 – Q2 2028”
TeraWulf Q3-2026 investor update (8-K ex-99.2, furnished 2026-11-06) · sec.gov - century-put$300Mwhat Century, the seller, can demand: to require the majority holder of Raylan Data Holdings LLC — the joint venture that, Century says, intends to develop and own the data center, and in which Century keeps 6.8% — to buy its interest for $300.0M, starting on the first anniversary of the data center's commencement of operations. Century's Q3-2026 10-Q says it as its Q2 one did, with one difference: the Q2 note added 'defined as delivering at least 375 MW of critical IT load to data center customers' to the commencement of operations, and the Q3 sentence no longer carries that definition. The filing gives no reason, so what starts the clock is not stated here. TeraWulf's own Q3-2026 10-Q (Note 11) describes the same put without the figure or the 375 MW definition — the seller 'has the right to request the redemption of its minority interest' 'starting on the first anniversary of the data center’s commencement of operations', for 'a fixed amount, less the amount of any distributions received by the Justified Data Campus seller' — so neither filer says what 'commencement of operations' means. A contingent payment by the majority holder, beside the $200.0M TeraWulf paid for the site (site-acquisition) — not a term of Anthropic's lease
“We also have the right to require the majority holder to purchase the Minority Interest for $300.0 million starting on the first anniversary of the data center’s commencement of the data center's operations”
Century Aluminum Q3-2026 10-Q, Note 4 — Sale of Hawesville · sec.gov - epc-agreementthe landlord's builder is named and the price is not: in October 2026 TeraWulf signed an engineering, procurement and construction agreement with Fluor Enterprises for the three buildings, 'with guaranteed maximum pricing to be established as engineering and procurement progress' — so TeraWulf's SEC filings fix no price for the build (landlord-capex holds the ranges it gave the regulator and its shareholders), and the ready-for-service dates the paragraph gives ('begin in late 2027 and continue through the second quarter of 2028') match the lease's delivery window (delivery). The Nov-4 release announced it in furnished form ('a definitive EPC agreement with Fluor'; 'Guaranteed maximum pricing is being established'); neither the Nov-4 8-K's body nor the Q2 10-Q mentions it, so the Q3 10-Q is the first filed statement. Fluor is the landlord's contractor, not a party to the lease or to Google's credit support
“In October 2026, the Company entered into an engineering, procurement and construction agreement with Fluor Enterprises, Inc. for three data center buildings at the Justified Data Campus. The agreement covers engineering, procurement, construction, testing and commissioning, with guaranteed maximum pricing to be established as engineering and procurement progress.”
TeraWulf Q3-2026 10-Q, Note 18 — Subsequent Events · sec.gov
Contested figures 2 not reconciled — every position side by side, with its source and tier
Scope note what this record leaves to other records
NOT this record (carried elsewhere): everything Lake Mariner / Abernathy / CB-5 — the three Akela Fluidstack leases (378 MW critical IT after the July 2026 amendment), Core42's 72.5 MW, the $3.2B + $1.3B Google backstops and 73,580,000 penny warrants, the Abernathy JV's 168 MW / ~$9.5B / $1.3B notes and its 50.1% sale to a Fluidstack-led group for ~$530M (the same Jul-6 8-K's other item; siliconangle's '$450M' is TeraWulf's invested capital, not the price) → goog-anth-backstops; Google's equity percentage in TeraWulf (~8% / 14% / 'does not own any equity' — a live FERC dispute, EC26-58) and Alphabet's aggregate backstop exposure ($28.4B + $9B at Mar 31 2026; up to $33.3B future) → goog-anth-backstops; Muskie (Grayson KY, 1 GW Kentucky Power, $30M + $50M) and Morgantown MD (210 vs ~216 MW; FERC order Jul 29 2026) → the terawulf entity; TeraWulf's capital structure ($3.2B 7.750% notes, converts, the $500M bridge, the April equity raise) is covered separately; Anthropic-wide aggregates ('$517B in eleven months' / 14.8 GW via The Decoder relaying The Information; $965B post-money; $47–65B ARR) → the anthropic entity, none primary. Kentucky community layer (300 jobs, $536.8M local tax, >$1B state+local tax over 20 years, Anthropic's electricity-price-increase pledge) is TeraWulf's projection in the same Energy Plan — not carried. Not adopted: '$14B' is constructionreviewonline's own sum (and it places the site in Louisville — it is Hancock County); measuredai's '$197/kW/month' is TCV ÷ MW ÷ months with no ramp; 'over $12.8B' vs '~$27B+' contracted HPC revenue are TeraWulf portfolio totals at two dates with an undefined perimeter; the Nov-6 2026 deck defines the perimeter of its current '~$27B': ~$19B Justified (this lease) plus ~$8B Lake Mariner (438 MW — Core42's 60 MW and Fluidstack's 378 MW), 839 MW in all. Also not carried (Nov 2026 update): Alphabet's own account of the Hawesville backstop, if it gives one → goog-anth-backstops. (The Fluor EPC agreement the Nov-4 release announced, furnished and without a price, is carried since the Q3-2026 10-Q files it: epc-agreement.) Not carried (Nov 8 2026 update): the Q3 10-Q's HPC lease revenue and rent lines (Core42's and one Fluidstack lease's, nothing of this lease), its Muskie, Morgantown and Abernathy notes (the terawulf entity, fs-terawulf-abernathy) and Amendment No. 1 to the parent's revolving credit agreement, a corporate loan that names no tenant.