Why it matters
Microsoft stepped in on its own contract when OpenAI withdrew from Stargate Norway, taking the GPU capacity OpenAI was lined up to use. That deal is part of up to ~$43.8B in Nscale GPU orders through 2033, conditional on delivery, a figure disclosed only in Nscale's IPO filing.
Tap a figure for the line in its source.
Microsoft gives Nscale
- through Dec 2033 under contracts signed Sep 2025–Apr 2026, if Nscale meets delivery and availability terms; the filing does not split it by site
- upfront payments on each batch of GPUs where the terms are on file (amounts redacted), refunded if Microsoft drops a batch that comes too late
Nscale gives Microsoft
- Nvidia GB300 GPUs announced in Oct 2025 across Texas, Norway, Portugal and the UK; the Texas share was later re-cut
- Rubin GPUs added at Narvik, Norway, for 2027, replacing OpenAI's letter of intent there
- Vera Rubin GPUs at Sines, Portugal, from late 2027
What happened
Microsoft rents large blocks of Nvidia GPUs from Nscale, a young London-based AI-cloud company, at four sites. They are Ward County in Texas, Narvik in Norway, Sines in Portugal and Loughton in England. Microsoft signed the contracts between September 2025 and April 2026. Nscale's IPO filing puts the payments to Nscale at up to about $43.8 billion through 2033. That depends on Nscale delivering the chips on time and keeping them available. This was the first filed figure, after a year in which the press reported $14 billion and then about $23 billion. In Norway, Microsoft also took over the capacity lined up for OpenAI's 'Stargate Norway' project after OpenAI pulled out in April 2026. Microsoft's own SEC filings never mention Nscale.
Sources 34 documents — 17 company releases · 11 SEC filings · 6 press reports
Research trail Found 270 documents and read 246 of them while checking this deal and related ones.
- States 6 figures: up to $43.8B contract value · SOW terms · $1.85B texas financing · $860,340,000 nvidia guarantee · narvik handover · sines sin02
- States 4 figures: oct 2025 announcement · texas announced · narvik 2025 GPUs · sines sin01
- States 3 figures: termination · filed form · customer not owner
- States 3 figures: landlord Q3 2026 · $7M ward county cash rent · 377 MW ward county Q3 power (for context)
- States 2 figures: texas customer · texas sow1
- States 2 figures: $1949M ward county lease (for context) · texas option
- States up to $35B contract value trail
- States $6.2B narvik 2025 contract
- States $6.2B narvik microsoft
- States narvik rubin
- States narvik handover aker
- States $10B sines microsoft investment
- States loughton
- States 1.35 GW monarch LOI
- States 1.35 GW monarch LOI filed
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: Nscale S-1 + ex-10.19 / ex-10.23 (2026-09-18) and DRS/A drafts (2026-05-12, 2026-06-26); Ionic Digital 424B4 (Jul 2026), Q2 2026 10-Q + 8-K ex-99.1 (Aug 19, Sep 10 and Nov 4 2026); Aker ASA MAR release (Sep 17 2025), Q1 2026 letter, 2Q 2026 report; Nscale releases (Sep 2025 – Oct 2026); Microsoft Source EMEA, News Centre Europe, UK blog and UK Stories; Start Campus (Oct–Nov 2025); NVIDIA (Sep 2025); CNBC / Reuters (Oct 2025), Bloomberg via DCD (Nov 2025), Semafor (Aug 2026), the Guardian (Mar, Sep 2026) — sources read 2026-10 · as of Nov 2026
The evidence 27 sourced figures · 11 disputes · 2 for context
The record's headline Microsoft–Nscale: up to ~$43.8B of GPU contracts through 2033, unsplit by site — the number Nscale's S-1 filed after a year of press estimates; GPUs announced in Texas, Norway, Portugal and the UK; in Norway, Microsoft took the capacity OpenAI's Stargate left
- Size
- up to ~$43.8B through Dec 2033 (S-1; ~$35.0B through Dec 2031 in the drafts) · ~200,000 GB300 announced Oct 2025 across four sites · +30,000 Rubin at Narvik (Apr 2026) · +66,000 Vera Rubin at Sines (May 2026) · Narvik's first contract ~USD 6.2B (Sep 2025)
- When
- Sep 16–17 2025 (Loughton commitment; Narvik ~USD 6.2B) → Oct 15 2025 (~200,000 GB300) → Mar 16 2026 (Monarch LOI) → Apr 14 2026 (Narvik +30,000 Rubin, after OpenAI's exit) → May 5 2026 (Sines +66,000 Rubin) → Aug 27 2026 (Texas $1.85B facility) → Sep 18 2026 (S-1)
- Status
- SOWs signed Sep 2025–Apr 2026; Texas live Oct 2026; Loughton delayed; Monarch LOI gone from filings
- Structure
- a programme of GPU-services statements of work on Microsoft's 'Partner Statement of Work' form, not one contract — SOW #1 is Texas (with Nscale US Holdings Inc., amended four times, novated to the borrower SPV); the one form on file is Narvik's Vera Rubin (VR200) SOW of 2026 (Microsoft Ireland Operations Ltd ↔ Nscale Ventures Holdings Norway AS); the Sep 2025 Narvik contract was signed by Nscale, Aker and Microsoft for the then-50/50 Aker–Nscale JV, rolled into Nscale in Mar 2026; Sines runs from Start Campus's SIN01 (Nscale a colocation tenant) and SIN02 (bought by Nscale); Loughton is Nscale's Essex site. In the filed form Microsoft pays per GPU-hour from each tranche's acceptance, plus upfront payments, and owns none of the infrastructure. Beneath it, Nscale leases the Texas site from Ionic Digital (NVIDIA guarantees five years of rent) and borrows $1.85B against SOW #1. A 1.35 GW Monarch (WV) letter of intent of Mar 2026 never became a SOW
- Programme
- Microsoft–Nscale
- Parties
- Microsoft offtaker — GPU services under statements of work signed Sep 2025–Apr 2026, paid per GPU-hour from each tranche's acceptance plus upfront payments (share redacted) in the filed form; may walk away from a tranche not accepted within 60 days of its Delivery Date; owns none of the infrastructure; its SEC filings never name Nscale (its own posts give the Narvik value and its UK and Portugal investment pledges) · Nscale neocloud provider — builds or leases the sites (tenant of Ionic Digital in Texas and of Start Campus at SIN01; owner of SIN02, Kvandal and Loughton), buys the GPUs and borrows against the Microsoft contracts (the $1.85B Ward County facility names Microsoft as its Customer)
- Record
- disclosed / primary source · as of Nov 2026
Flows 2 as the record states them
- Microsoft → Nscalecompute-spendup to ~$43.8B through Dec 2033 for the statements of work signed Sep 2025–Apr 2026, not including optional extensions and subject to delivery and availability of service (S-1) — a ceiling, not a floor; in the filed form billed per GPU-hour from each tranche's acceptance, with two upfront payments per tranche (share redacted). The Narvik contract of Sep 2025 was valued at ~USD 6.2B over five years when signed (Aker; Microsoft: 'an estimated $6.2 billion')
- Nscale → Microsoftcomputededicated NVIDIA capacity at four sites, as announced: Ward County TX (~104,000 GB300 in Oct 2025; by Aug 2026 SOW #1's tranches are 24,192 GB300 + 16,128 and 32,256 VR200 'GPU Servers'), Narvik (~52,000 GB300 from 2026 + 30,000+ Rubin in 2027), Sines (~12,600 GB300 at SIN01 + 66,000+ Vera Rubin at SIN02 from late 2027), Loughton (23,040 GB300 targeted for Q1 2027; power-delayed per press); GPU terms of five to six years from each tranche's acceptance
Resolved figures 27 each with the verbatim line from its document
- contract-valueup to $43.8Bup to approximately $43.8B through December 2033 — the ceiling on the statements of work Microsoft signed with Nscale between September 2025 and April 2026, not including the optional extensions and 'subject to the satisfaction of delivery and availability of service requirements'. A ceiling, not a floor: a tranche that is never accepted can be terminated and its upfront payment refunded (termination). Stated twice in the S-1, which splits it by neither SOW nor site and does not say whether the Sep 2025 Narvik contract signed with the then-JV (narvik-2025-contract) is inside it — never add the two. It is the only filed figure for the relationship: Microsoft's own filings never name Nscale (EDGAR full-text search, Oct 2 2026: no Microsoft filing contains 'Nscale' or 'Narvik'). Daloopa, MostlyMetrics, Superpower Daily and TechCrunch restate this one sentence — not corroboration
“Between September 2025 and April 2026, we entered into statements of work with Microsoft that provide for payments to us of up to approximately $43.8 billion through December 2033, not including the optional extensions, and which are subject to the satisfaction of delivery and availability of service requirements.”
Nscale S-1 (filed 2026-09-18) — Business, Customers · sec.gov - contract-value-trailup to $35Bthe same sentence's earlier value — 'up to approximately $35.0 billion through December 2031' — in Nscale's draft registration statements of Feb 17 2026 ('On September 12, 2025, we entered into agreements with Microsoft that, as of December 2025, providing for payments to us of up to approximately $35.0 billion …'), May 12 2026 and, quoted, Jun 26 2026, by which date the window already read 'Between September 2025 and April 2026'. The Aug 12 2026 draft and the S-1 restate it as $43.8B through December 2033 with the window unchanged; no version explains the step (+$8.8B and two years — editor's arithmetic). A dated series of one issuer's statement: never a range, never averaged.
“Between September 2025 and April 2026, we entered into statements of work with Microsoft that provide for payments to us of up to approximately $35.0 billion through December 2031, not including the optional extensions, and which are subject to the satisfaction of delivery and availability of service requirements.”
Nscale DRS/A No. 2 (2026-06-26) — Risk Factors · sec.gov - sow-termswhat the statements of work contain, per the S-1: 'GPU infrastructure, colocation space, and cloud services'; GPU-service terms of five to six years from acceptance of each tranche, each SOW ending on its last tranche's end date; an optional six-month extension at Microsoft's election and no other renewal; and 'Either party may terminate the statement of work for cause' — on 60 days' notice of a breach, or on insolvency. The S-1 does not say these are the only exits; its risk factors add that, besides Anthropic's, 'certain of our other customer contracts provide the applicable customer with a right to terminate for delays' (customers unnamed). The narrower reading — for cause rather than convenience, plus a per-tranche exit for late delivery or acceptance and a change-of-control trigger — is the one filed form's, Narvik's (termination); the other SOWs are not filed. Nscale's weighted-average contract life across all customers is ~5.7 years (company-wide — nscale entity)
“Each statement of work ends on the last remaining end date of the GPU services provided thereunder, with GPU services terms from five to six years from acceptance of each tranche and an optional six-month extension at Microsoft’s election.”
Nscale S-1 — Business, Customers · sec.gov - terminationfor cause, not convenience. The filed SOW form attaches Microsoft's standard PO Terms (Feb 2025), whose clause 14 reads 'Microsoft may terminate these PO Terms or the applicable SOW with or without cause' — and its §6.10 deletes that clause and replaces it with termination by either party for a material breach left uncured for 60 days, or for insolvency (the S-1: 'Either party may terminate the statement of work for cause'). Daloopa's 'with or without cause' reads the PO Terms without the override. Microsoft's other exits in the form: a tranche not accepted within 60 days of its Delivery Date may be terminated — that tranche only, never 'any other SOW' — with the refund of its upfront payment 'the sole remedy'; and if a change of control hands more than 50% of the supplier to a 'Restricted Party' — 'Amazon, Google, Tencent or Alibaba' — Microsoft 'will either consent to the Change of Control or terminate this Agreement'. This is the Narvik form (filed-form); the other SOWs are not filed
“6.10 Termination a.Clause 14 (Termination) of the PO Terms shall be deleted and replaced by the following provision: “14.Termination a.Termination by Either Party for Cause: Without affecting any other right or remedy available to it, either Party may terminate any SOW with immediate effect by giving written notice to the other Party if the other Party:”
S-1 ex-10.19, Partner Statement of Work — §6.10 Termination · sec.gov - filed-formthe one Microsoft contract text on file is a Narvik form. The S-1's exhibit index calls it 'Form of Partner Statement of Work between Microsoft MSA Corporation and Nscale US Holdings Inc.', but the document is between Microsoft Ireland Operations Limited and Nscale Ventures Holdings Norway AS for NVIDIA VR200 GPUs at Kvandal North — the form of the Vera Rubin expansion announced Apr 14 2026 (narvik-rubin); Texas's SOW #1 is the one with Nscale US Holdings Inc. (texas-customer). Its terms: three VR200 tranches; a price row 'NVIDIA VR200 Kvandal North, Norway 6 years' with separate Years 1–5 and Year 6 prices per GPU-hour; 6 MW of air-cooled colocation space for Microsoft's CPU, storage and networking; two upfront payments per tranche ('Upfront Payment 1' no earlier than 15 days after execution, 'Upfront Payment 2' no earlier than 90 days before each Delivery Date — the one unredacted schedule date sits in a worked example, Tranche 2's September 28, 2027); a credit of 100% of the daily bill for each day a tranche is late, except delays 'directly caused by Nvidia'. Every price, GPU quantity, tranche MW, Delivery and end date, fee cap and upfront share is [***]; left in the clear are the 6-year term, the 6 MW of colocation power and that worked example's date
“The Data Center Location shall be the data center facilities located at the land at Kvandal North in the municipality of Narvik, Norway at Nordmoveien 301, 8530 Bjerkvik, Narvik, Norway.”
S-1 ex-10.19, Partner Statement of Work — §1.1 GPU Services · sec.gov - customer-not-ownerMicrosoft buys services and owns none of the infrastructure — the filed form's words, and the reading of Microsoft's role this record takes; other documents word it differently. Aker calls the Sep 2025 Narvik deal 'a binding five-year customer agreement' and Microsoft's English page 'a landmark deal … worth an estimated $6.2 billion' (narvik-microsoft), while Microsoft News Centre Europe (Norwegian, Nov 2025) writes 'Microsoft har investert 66 milliarder kroner i prosjektet' ('has invested NOK 66 billion') — Microsoft's own word and currency, carried as its phrasing, never converted into a second figure or read as Microsoft capex. No document on file shows Microsoft funding construction at any Nscale site
“Nothing in the agreement (including without limitation this SOW and the PO Terms) shall be construed to grant or convey to Microsoft (and/or any Authorised User) any ownership interest in the Infrastructure.”
S-1 ex-10.19, Partner Statement of Work — ownership of the Infrastructure · sec.gov - oct-2025-announcement200,000~200,000 GB300 across four countries as announced Oct 15 2025 (Microsoft's Jon Tinter quoted; 'This work is in collaboration with Dell Technologies'): Texas ~104,000 + Narvik ~52,000 + Loughton ~23,000 + Sines ~12,600 ≈ 191,600 — 'approximately 200,000' is the rounded total, not a fifth site. About 75,000 (Norway and the UK) had been announced before (CNBC) and ~116,600 (Texas + Sines) was new that day — DCD's 'additional 100,000' headline and '116,000' are that increment, and its May 2026 '116,000 … across its entire partnership' is wrong. Announced, not delivered: the Texas share was re-cut by Aug 2026 (texas-sow1). No dollar figure anywhere in the release.
“Nscale today announced it has signed an expanded deal with Microsoft to approximately 200,000 NVIDIA GB300 GPUs of hyperscale NVIDIA AI infrastructure across Europe and the U.S. in one of the largest AI infrastructure contracts ever signed.”
Nscale release, Oct 15 2025 · nscale.com - texas-announced104,000~104,000 GB300 at a ~240 MW campus on Ionic Digital's Ward County property in West Texas (Ionic's 'Cedarvale'), services phased in from Q3 2026 — with 'Nscale plans to scale its footprint to 1.2GW over time, with Microsoft holding an option on a second phase of 700MW starting in late 2027' (contested texas-option-size). Aker's 3Q25 deck: '>100,000 GPUs with Microsoft' at 'Barstow, Texas'. Re-cut by Aug 2026 — texas-sow1 and contested texas-gpus
“Nscale will deliver approximately 104,000 NVIDIA GB300 GPUs in a ~240MW hyperscale AI campus in Texas, supporting the phased delivery of NVIDIA AI infrastructure services to Microsoft from Q3 2026.”
Nscale release, Oct 15 2025 · nscale.com - texas-customerthe filed proof that Texas is Microsoft's: the Ward County credit agreement defines its 'Customer' as Microsoft Corporation and its 'Customer Contract' as Partner Statement of Work #1 between Microsoft and Nscale US Holdings Inc., 'as amended by' Amendments No. 1–4 and assigned to the borrower SPV by a Novation Agreement — every date [***]. Microsoft's upfront payment for each tranche goes to a 'Customer Contract Prepayment Account'; a tranche Microsoft terminates for non-acceptance starts a refund-or-remarket regime (the 'RVG Triggering Event'). Moody's, as relayed by CCIR (tier 3), described the offtaker only as a hyperscaler 'rated at least Aa3'; the agreement names it
““Customer” shall mean Microsoft Corporation. “Customer Contract” shall mean that certain Partner Statement of Work #1, effective as of [***], between Customer and Nscale US Holdings Inc.”
S-1 ex-10.23, Ward County GPU credit agreement (Aug 27 2026) — Definitions · sec.gov - texas-sow124,192SOW #1's tranches as the lenders define them (Aug 27 2026): an 'Initial Tranche' of 24,192 GB300 'GPU Servers', 'Tranche 2' of 16,128 VR200 and 'Tranche 3' of 32,256 VR200 — so the ~104,000 GB300 announced in Oct 2025 became one GB300 tranche and two Vera Rubin tranches across four amendments, and no document says why (contested texas-gpus). 'GPU Servers' is defined as 'any graphics processing units servers and ancillary components', not as GPUs: the record quotes the unit, does not convert it, and never adds GB300 and VR200 into one count. Read as GPUs, the three tranches fill 1,008 NVL72 racks, and 1,008 × 200 kW = 201.6 MW — exactly the 'Assumed Utilization' the same agreement requires to be power-hedged (our arithmetic, not a document's statement)
““Initial Tranche” shall mean that certain tranche under the Customer Contract consisting of 24,192 GB300 GPU Servers.”
S-1 ex-10.23, Ward County GPU credit agreement — Definitions · sec.gov - texas-financing$1.85B$1.85B of delayed-draw term loans ($630.0M fixed-rate + $1.22B floating) to Nscale Ward County Borrower SPV, LLC, Aug 27 2026, JPMorgan and Goldman Sachs among the arrangers, with 'investment-grade ratings with a stable outlook' — lent against SOW #1 (texas-customer) at up to 90% of each tranche's GPU capex and maturing at the earlier of Microsoft's final scheduled payment and Feb 27 2033: as with IREN's (iren-msft), the debt's life is the contract's. Nscale (Aug 31): the loans fund 'NVIDIA GB300 (Blackwell Ultra) and VR200 (Vera Rubin) systems supporting approximately 200 MW of IT load'. Moody's '$1.831 billion' (CCIR's relay of an Aug 12 rating) predates closing; the executed agreement governs. Dell Financial Services also leases equipment to this SPV and its North Carolina twin — '~$2.54 billion' of initial-term rent across both, never Texas alone
“The Ward County GPU Credit Agreement provides for delayed draw term loan commitments in an aggregate principal amount up to $1.85 billion, consisting of $630.0 million of fixed-rate delayed draw loan commitments and $1.22 billion of floating-rate delayed draw loan commitments (together, the “Ward County GPU Facility”).”
Nscale S-1 — Description of Certain Indebtedness · sec.gov - nvidia-guarantee$860,340,000NVIDIA — Nscale's GPU supplier and a >5% shareholder — guarantees Nscale's Ward County rent for the first five Lease Years, up to $860,340,000 (Ionic: 'up to a maximum amount of $860.3 million'; Nscale's parent guarantees from year six): the tenant and the landlord, two filers, state it independently. The direction matters: Nscale pays NVIDIA for the guarantee, in warrants over 9,476,700 Series B preferred shares 'with an aggregate value of $60,000,000' at $0.01, plus contingent warrants exercisable on a lease default. The drafts' 'NVIDIA purchased warrants … for an aggregate purchase price of $60,000,000' is superseded wording, and measuredai's 'NVIDIA bought $60 million of Nscale warrants' inverts the flow. A vendor backstopping the neocloud's rent under Microsoft's Texas capacity; the NVIDIA–Nscale circularity as a whole (supplier, holder, customer, convertible investor) sits on the nscale entity and nv-nscale
“In consideration for the warrants, NVIDIA agreed to guarantee up to $860,340,000 of our obligations under the lease agreement for the facility in Ward County, Texas.”
Nscale S-1 — Certain relationships (Transactions with NVIDIA) · sec.gov - landlord-q3-2026the Texas landlord now names the demand behind the lease. Ionic Digital's CFO, in its Q3 2026 results release (Nov 4 2026): 'we believe we are well positioned with our Nscale lease supported by Microsoft demand and a guarantee from Nvidia'. Before it, Ionic's registration statements and prospectus name Microsoft only as the holder of an option on more power (texas-option), the prospectus's step-in clause says only 'its anchor customer' (ward-county-lease), and its Q2 10-Q and its Q2 and Sep 10 releases name Microsoft nowhere. A landlord describing its own lease, in a release furnished under Item 2.02 — tier 2, as the landlord is not a party here — with no figure: the document that names Microsoft as the Customer stays Nscale's credit agreement (texas-customer), and the NVIDIA guarantee is the one in nvidia-guarantee, restated here without an amount. The release names Microsoft once, in this sentence, and says nothing of the option
“Given the capital needs to develop AI infrastructure and data centers, we believe we are well positioned with our Nscale lease supported by Microsoft demand and a guarantee from Nvidia, and a strong balance sheet that gives us clear visibility to funding the development of our existing sites.”
Ionic Digital 8-K ex-99.1 (Nov 4 2026; Item 2.02, furnished) — CFO remarks · sec.gov - ward-county-cash-rent$7MIonic's CFO, in the Q3 2026 release (Nov 4 2026): '$44 million of digital infrastructure leasing revenue, or $7 million on a cash basis, with cash rent continuing to ramp through February 2028'. That sentence does not name the lease: the tie to Nscale is the Q2 10-Q's, which calls the same revenue line 'the recognition of revenue associated with the Nscale Agreement', so $7M is the cash side of Nscale's rent on that tie, not on this release's word. The release does not split the gap between $44M and $7M either. The Q2 10-Q books the lease 'on a straight-line basis'; the release's own note speaks of 'differences between the timing of lease revenue recognition and cash receipts', and its balance sheet carries a 'Deferred rent receivable' of $85,176 thousand (nil at Dec 31 2025). Straight-line revenue ahead of a ramping rent is this record's reading of those, not a line of the release. 'Deferred digital infrastructure leasing revenue' (nil, from $39,793 thousand at Dec 31 2025) is not a second cause in Q3: the Q2 10-Q already has it at nil on Jun 30 2026, so none was left to recognize. February 2028 is the month after the 18-month first Lease Year ends (Aug 1 2026 – Jan 31 2028 in the prospectus and the lease's rent table; the lease's own definition prints Jan 31 2027 — ward-county-lease). The release's statement of operations, unaudited, puts the quarter's line at $43,884 thousand; it gives no cash-rent schedule. Rent is Nscale's payment to its landlord, not Microsoft's to Nscale
“Our third quarter results were in line with our expectations, including $44 million of digital infrastructure leasing revenue, or $7 million on a cash basis, with cash rent continuing to ramp through February 2028”
Ionic Digital 8-K ex-99.1 (Nov 4 2026; Item 2.02, furnished) — CFO remarks · sec.gov - texas-optionMicrosoft holds an option on more Ward County power from 2H 2027 — in the landlord's final prospectus, which no longer sizes it. The size is contested (texas-option-size): Nscale's Oct 2025 release said 'a second phase of 700MW', which Ionic's first draft prospectus repeated in Oct 2025 and its final one dropped. The S-1 does not mention the option
“Additionally, Nscale has granted Microsoft an option for additional power at the Ward County property, if it becomes available, starting in the second half of 2027.”
Ionic Digital 424B4 (Jul 2026) — Business · sec.gov - narvik-2025-contract$6.2Bthe first Microsoft contract: 'a binding five-year customer agreement' signed Sep 17 2025 by Nscale, Aker and Microsoft for the Aker–Nscale JV's Kvandal campus in Narvik, ~USD 6.2B, 'staged deployments beginning in 2026' — Aker's MAR inside-information release (Aker is Oslo-listed); ~52,000 GB300 (narvik-2025-gpus); 'Cash flow generated under the agreement will support funding of the project’s capital expenditures.' Whether it sits inside the S-1's $43.8B is not stated (the S-1 window opens the same month) — never add the two. Not the S-1's unrelated '$6.2 billion' of equipment purchase commitments at Dec 31 2025. The JV was rolled into Nscale in Mar 2026, so the contract is now wholly Nscale's
“At a contract value of approximately USD 6.2 billion, the agreement secures Microsoft’s access to high-performance AI compute capacity to be delivered in staged deployments beginning in 2026.”
Aker ASA MAR release, Sep 17 2025 · news.cision.com - narvik-microsoft$6.2BMicrosoft's own number — the one dollar figure Microsoft itself has published about its Nscale contracts: 'worth an estimated $6.2 billion', 'a five-year agreement that will begin to deliver services in stages, commencing in 2026' (Microsoft Source EMEA, Sep 17 2025). Its Norwegian page of Nov 2025 restates the deal as 'Microsoft har investert 66 milliarder kroner i prosjektet' (customer-not-owner). Microsoft's SEC filings carry neither
“Microsoft, Nscale and Aker have entered into a landmark deal that sees an ambitious new build out of renewable, scalable next generation AI infrastructure in the town of Narvik, worth an estimated $6.2 billion.”
Microsoft Source EMEA, Sep 17 2025 · news.microsoft.com - narvik-2025-gpus52,000~52,000 GB300 under the Sep 2025 contract (Nscale, Oct 15 2025); Aker: '>50,000' and '~52,000 GPUs signed with Microsoft' (3Q25 deck). Aker's '~62,000 Nvidia GPUs announced w/Microsoft & OpenAI' adds OpenAI's ~10,000-GPU letter of intent, which never became a contract (sg-nscale-europe)
“This builds on the recent announcement that the Aker-Nscale Joint Venture signed a multi-year agreement to deliver approximately 52,000 NVIDIA GB300 GPUs to Microsoft from its hyperscale AI campus in Narvik, Norway.”
Nscale release, Oct 15 2025 · nscale.com - narvik-rubinmore than 30,000the 2026 expansion, announced Apr 14: more than 30,000 NVIDIA Rubin GPUs at Narvik for 2027 ('Today, Nscale expanded its agreement with Microsoft to deliver even more high-performance AI compute capacity in Norway in 2027'), Microsoft's Jon Tinter quoted; 'a project solely managed by Nscale' after the JV roll-up. The release never mentions OpenAI — the hand-over is the next two cells. Aker, 2Q 2026: 'two contracts with Microsoft during the period for more than 66,000 NVIDIA Rubin GPUs at the Sines site in Portugal, and more than 30,000 NVIDIA Rubin GPUs at the Narvik site in Norway'. The '230 MW' is the campus's grid reservation under Kvandal transformer station (Norway's energy minister to the Storting, Aug 2025), not a contracted IT load; Aker: 'The initial 230MW in Narvik now fully contracted'. The separately financed Kvandal South building (108 MW; $725.0M term loan + $65.0M VAT facility; offtaker '[***]') and the SOW form's 'Kvandal North' are different parcels — never mapped onto each other. Epoch models the Rubin GPUs online in Q4 2026; the parties say 2027 (the model is not carried here)
“Expanding Nscale and Microsoft’s previous deal, the 230 MW Nscale Narvik campus will add more than 30,000 NVIDIA Rubin GPUs in deployment, making it one of the largest onshore infrastructure projects in Norway.”
Nscale release, Apr 14 2026 · nscale.com - narvik-handoverthe issuer's own account of the hand-over, in every draft from May 12 2026 and in the S-1: OpenAI withdrew in April 2026, and Microsoft 'subsequently' expanded its agreement 'to take the extra compute capacity at Stargate Norway'. Bilateral, not Stargate: the capacity sits on Microsoft's own statement of work (filed-form), not under OpenAI's programme — Aker's 3Q25 deck heading Microsoft's Narvik and Loughton GPUs 'Stargate Norway' and 'Stargate UK' is a site label, not membership. Whether OpenAI now gets any of it from Microsoft is not filed; sg-nscale-europe carries that question, and no cell here moves Microsoft's capacity onto OpenAI
“In April 2026, OpenAI withdrew from the Stargate Norway and Stargate UK partnerships, with Microsoft subsequently expanding its agreement with us to take the extra compute capacity at Stargate Norway.”
Nscale S-1 — Risk Factors · sec.gov - narvik-handover-aker30,000the JV partner's account: Microsoft 'contracted the full capacity at Kvandal', 30,000 Vera Rubin GPUs on top of its USD 6.2B commitment — Nscale's contract 'replacing the previous LOI with Open AI (Stargate Norway)' (Aker Q1 2026 results); 'The result is a larger contract with one of the world’s most creditworthy counterparties' (same letter). Dating: the letter says 'during the quarter' (Q1 2026), while Aker's Q1 deck dates the contract 'Apr 2026' — the month in which the S-1 places OpenAI's withdrawal, with Microsoft's expansion 'subsequently'. The record dates it by the announcement, Apr 14 2026
“Originally positioned under “Stargate Norway,” with OpenAI as the intended anchor customer, the site had already attracted a USD 6.2 billion commitment from Microsoft. During the quarter, Microsoft contracted the full capacity at Kvandal, adding a further 30,000 NVIDIA Vera Rubin GPUs to its existing commitment.”
Aker ASA shareholder letter, Q1 2026 · akerasa.com - sines-sin0112,600~12,600 GB300 for Microsoft in Start Campus's SIN01 building at Sines, Nscale the colocation tenant: 'set to be live by Q1 2026' (Start Campus, Oct 15 2025 — a target; no document on file records acceptance). The S-1: 'the deployment of over 12,600 NVIDIA Grace Blackwell Ultra GPUs at the first building of the SINES Data Campus for Microsoft'. Nscale's H1 2026 revenue came 52% from Portugal and 45% from Norway, and separately 52% from its largest customer — the S-1 never names that customer, so the record does not equate it with Microsoft at SIN01
“From Q1 2026, Nscale will deliver approximately 12,600 NVIDIA GB300 GPUs at the Start Campus data centre in Sines, Portugal.”
Nscale release, Oct 15 2025 · nscale.com - sines-sin0266,000the May 2026 expansion: 66,000+ Vera Rubin NVL72 GPUs for Microsoft from late 2027 at SIN02, which Nscale bought on Apr 24 2026 — 'a 200 MW powered land site' in the S-1 (Start Campus called it '180MW' in Oct 2025 — contested sin02-mw) — announced May 5 with Nscale's '€230 million in shared infrastructure and €465 million in a second 200MW building'. The purchase price is stated two ways in the same S-1 (contested sin02-consideration). Aker, 2Q 2026: 'more than 66,000 NVIDIA Rubin GPUs at the Sines site'; Aker's Q1 deck: 'Sines: 78,600 GPUs (~230MW)' — the two buildings together
“The project will support the expansion of our collaboration with Microsoft through the deployment of over 66,000 NVIDIA Vera Rubin NVL72 GPUs, starting in late 2027.”
Nscale S-1 — Prospectus Summary · sec.gov - sines-microsoft-investment$10BMicrosoft's own INVESTMENT pledge, not Nscale's contract value: Brad Smith at Web Summit (Nov 11 2025) — Microsoft 'irá investir mais de 10 mil milhões de dólares a partir do início de 2026' (Microsoft Source EMEA, Portuguese) — relayed by the landlord, which says it 'results from strategic discussions between Microsoft, Nscale, and Start Campus' covering SIN01 'and the following phase'. Nscale's share is undisclosed; never add it to the $43.8B. measuredai's '$46 billion in commitments', which books this as an Nscale contract, is kept out.
“Lisbon, 11 November 2025 - Following remarks made by Brad Smith, Vice Chair and President of Microsoft, during the opening of the Web Summit in Lisbon, Start Campus welcomes Microsoft’s announcement to invest $10 billion in the company’s SINES data center campus.”
Start Campus release, Nov 11 2025 · startcampus.pt - loughton23,040Nscale and Microsoft 'have entered a commitment' on Nscale's Loughton campus in Essex (Sep 16 2025): 50 MW scalable to 90 MW, 23,040 GB300 initially, delivered in Q1 2027, for Azure services in the UK. Announced in the same release as Stargate UK but 'Separately' from it (the S-1 later names Microsoft among the partners of its UK initiative, 'Stargate UK' — sg-nscale-europe uk-separate); no document hands Microsoft any of OpenAI's UK offtake. The UK GPU facility (S-1 ex-10.14) finances a 'Partner Statement of Work #3, dated effective as of September 12, 2025' with Nscale Services UK LTD whose counterparty is '[***]' — Microsoft's form name and the date of its first agreements, but the record does not name the customer from them. Count, date, Microsoft's role and its $15B are all contested (loughton-*)
“The site will deliver 50MW of AI capacity, scalable to 90MW, and will initially house 23,040 NVIDIA GB300 GPUs delivered in Q1 of 2027.”
Nscale release, Sep 16 2025 · nscale.com - monarch-loi1.35 GWa letter of intent, never a statement of work — never inside the $43.8B: 1.35 GW of Vera Rubin NVL72 capacity at Nscale's Monarch Compute Campus in Mason County, West Virginia, in tranches from late 2027, under 'an initial multi-year compute services term alongside a long-term data centre lease structure' (Microsoft's Jon Tinter quoted). Aker's same-day notice: 'approximately 430,000 NVIDIA Vera Rubin GPUs' (a single source); Aker's annual report: an LOI 'as a customer for the first phase of the Monarch facility'. The campus went to Anthropic in Aug 2026 (another record) — monarch-loi-filed and contested monarch-loi-status
“Nscale has signed a letter of intent with Microsoft to provide 1.35 gigawatts of AI compute capacity, setting up the West Virginia Monarch AI campus as a global flagship deployment of NVIDIA’s next-generation Vera Rubin GPUs as Vera Rubin NVL72 systems engineered with the NVIDIA Vera Rubin DSX AI Factory reference design.”
Nscale release, Mar 16 2026 (GTC) · nscale.com - monarch-loi-filed1.35 GWthe LOI's whole life in Nscale's filings: it appears in one draft registration statement (May 12 2026) and is gone from the Jun 26 draft on — no version says it lapsed, was terminated or was assigned. The S-1 names Anthropic as Monarch's customer (up to ~$44.6B, Aug 25 2026) and Microsoft nowhere at Monarch
“Concurrently, we announced a strategic collaboration with Microsoft, NVIDIA, and Caterpillar, including a letter of intent with Microsoft for up to 1.35 GWs of IT load power capacity at the Monarch Compute Campus using NVIDIA Vera Rubin NVL72 GPUs, with deployment expected to occur in multiple tranches beginning in late 2027.”
Nscale DRS/A No. 1 (2026-05-12) — Prospectus Summary · sec.gov
Contested figures 20 not reconciled — every position side by side, with its source and tier
For context, not this deal's figures 2 kept beside the deal so they are not mistaken for its numbers
- ward-county-lease$1949Mbeneath the Microsoft contract, Nscale's RENT — not Microsoft's payments: a 126-month triple-net lease (Oct 2025, amended Feb 2026) of Ionic Digital's Ward County property, 'the full amount of the 234 megawatts', with rent from Aug 1 2026 reaching $182.5M a year at 234 MW after an 18-month ramp (Q3 2026's cash-basis figure, tied to this lease by the Q2 10-Q: ward-county-cash-rent). The lease runs 'ten (10) Lease Years' from that date, the first 'eighteen (18) months' long (its printed end date, Jan 31 2027, is six months on — an inconsistency inside the lease that no filing corrects): 126 months in Ionic's filings, a '10-year' lease in its Oct 2025 release. $1,949.0M of fixed payments in all — Ionic's 'approximately $1.95 billion', '$1.9 billion' in its 10-Q and 'approximately $2 billion' in its Oct 2025 release: one figure, three roundings — rising to 'approximately $2.6 billion' if the further 89 MW Nscale must lease 'when such capacity becomes available' is energized in 2H 2027 ('there is no penalty' if it is not). NVIDIA guarantees the first five Lease Years' rent (nvidia-guarantee), and 'if Nscale were to become insolvent, its anchor customer may elect within 30 days to step-into the Nscale Agreement' — the clause names no customer; Ionic's July prospectus names Microsoft only as the holder of an option on more power (texas-option), and its Nov 4 2026 results release speaks of 'our Nscale lease supported by Microsoft demand and a guarantee from Nvidia' (landlord-q3-2026). Not the S-1's unrelated '$2.6 billion' of active TCV
“Fixed lease payments are allocated to the combined lease components under the arrangement and total $1,949.0 million.”
Ionic Digital 424B4 (Jul 2026) — lease accounting note · sec.gov - ward-county-q3-power377 MWwhat the landlord says is left of the campus's added power. Of the 466 MW tranche that would bring Ward County to its 'full aggregate demand of 700 MW' (Ionic, Sep 10 2026), the Q3 2026 release counts '377 gross MW' among the capacity it is looking to lease (the CEO: 'our priority of leasing the remaining capacity across our Ward County and Midland sites') — 'expected to energize in late 2027, subject to remaining regulatory approvals and completion of utility infrastructure projects' — and sets 'the remaining 89 gross MW at our Ward County site' apart as 'already under contract and therefore not available for new customers'. The 89 is the figure the lease obliges Nscale to take 'when such capacity becomes available' (ward-county-lease); the release does not name the tenant. ERCOT's classification of the 466 MW is still provisional ('Batch Zero Baseload Pathway (b)', September 2026): 'We continue to expect energization in late 2027 as ERCOT completes its final classification process in December'. The footnote's other two figures, 112 and 10 gross MW, are Ionic's Midland sites — not this deal. The release says nothing of how much of the 377, if any, Microsoft's option would take (texas-option-size)
“Consists of 499 gross MW: (i) 377 gross MW of the 466 gross MW of provisional Baseload capacity at our Ward County site, expected to energize in late 2027, subject to remaining regulatory approvals and completion of utility infrastructure projects; (ii) 112 gross MW across our Midland sites, which are energized; and (iii) additional 10 gross MW at one of our Midland sites, expected to energize in 2027. Excludes the remaining 89 gross MW at our Ward County site, which is already under contract and therefore not available for new customers.”
Ionic Digital 8-K ex-99.1 (Nov 4 2026; Item 2.02, furnished) — footnote 1 · sec.gov
Scope note what this record leaves to other records
NOT this record (carried elsewhere): OpenAI's own Stargate Norway / Stargate UK partnerships with Nscale (a ~10,000-GPU LOI and an 'explore offtake', withdrawn Apr 2026) → sg-nscale-europe; Anthropic–Nscale at Monarch (Anthropic Services Agreements, Aug 25 2026, up to ~$44.6B — now on two tier-1 primaries, Nscale's S-1 and Aker's MAR notice of 'around USD 45 billion' with an 'undisclosed customer') → anth-nscale-monarch; NVIDIA–Nscale as a relationship (supplier, >5% holder, $1.2B MSA customer, $1.0B convertible investor, Ward County rent guarantor) → the nscale entity and nv-nscale — only the guarantee under Microsoft's Texas site is a cell here; Nscale's company-wide book ($103.4B TCV, $56.4B RPO, the 23% weighted-average prepayment, the unnamed 52%/73% largest customer) → the nscale entity, never Microsoft's figures; North Carolina (WhiteFiber NC-1 — its credit agreement's 'Customer' is '[***]' under a 'Cloud Services Agreement', not Microsoft's form), Iceland, Figure AI, ByteDance → entity note. Not carried here: the Ionic lease's internal arithmetic ($250.5M vs $251.94M a year at 323 MW — the prospectus vs the lease's monthly clauses × 12; the first Lease Year's printed dates vs its '18 months', flagged in ward-county-lease); SIN01's MW (26 vs 30, no primary); the S-1 portfolio table (17 rows naming no site or customer — mapping rows to Microsoft sites is a reading); Moody's Baa1 and '$1.831 billion' (CCIR relays); Statnett's northern-Norway grid statistics; Epoch's Narvik model (265k H100-equivalents, 92 MW, $3.5B, Rubin online Q4 2026 — a model; the parties say 2027). Not adopted: Techzine's 'up to $24 billion'; measuredai's '$46 billion in commitments' (books Microsoft's $10B Sines investment as an Nscale contract); TechTimes' '$51 billion' contracted revenue; Fortune's '$3.1 billion from Nvidia' (the S-1 splits a $3.1B minimum into $2.1B of notes + NVIDIA's $1.0B); measuredai's inverted warrant flow; DCD's May 2026 '116,000 … across its entire partnership'; Observador's ~$1.5bn for the 12,600 Sines GPUs (the paper's arithmetic); CCIR's '$2.72/GPU-hr' (a derivation); CoreWeave's 62%/67% Microsoft concentration (CoreWeave's own, not Nscale's); Network World's anonymous 'will then provide compute power to OpenAI' (carried as contested on sg-nscale-europe, never a cell here); the same digits on different quantities — the S-1's '$6.2 billion' and '$24.0 billion' of equipment purchase commitments, its '$2.6 billion' of active TCV, Ionic's '$43.8 million' of Q2 2026 lease revenue (and its $43,884 thousand, '$44 million', for Q3).