Core Scientific–AMD

AMD signed 15-year leases for 377 of data center capacity from Core Scientific and got the right to buy up to 30M Core Scientific shares in return.

A deal between AMD, Core Scientific

Why it matters

AMD uses on both sides of its compute business. It gives its own to OpenAI and Meta to sell chips, and gets warrants from its landlord for renting buildings. The $14B and $24B figures appear only in investor communications, and the leases were never filed as exhibits to support them.

Tap a figure for the line in its source.

Core Scientific gives AMD

  • of data-center capacity in Texas and Oklahoma for 15 years, first delivery est. 2027
  • the right to buy them at $23.47 each, the market price; about 6.5M vested at signing
  • more AMD may lease through Dec 2028, under certain conditions — a right, not a lease

AMD gives Core Scientific

  • rent, amount unstated; Core Scientific's unfiled '>$14B' covers both tenants
  • may cure some defaults on an unnamed tenant's 152 — a right per the 8-K, with unspecified obligations in certain material defaults; 'full credit support' per remarks

Jul 27, 2026 disclosed in Core Scientific's 8-Kupdated Nov 21, 2026signed — first delivery est. 1H 2027 disclosed by the parties

What happened

AMD signed leases for about 380 of data-center space from Core Scientific, the bitcoin miner CoreWeave tried and failed to buy. Another ~150 MW goes to an unnamed 'Neocloud', a specialized cloud provider. Core Scientific gave AMD the right to buy up to 30 million of its shares in exchange for signing. AMD uses its own equity to sell chips to OpenAI and Meta. In this deal, AMD gets equity from its landlord for renting buildings. Core Scientific published its 'more than $14 billion' figure to investors and never formally filed it with the SEC. The 8-K says AMD can step in to fix some failures by the Neocloud to meet its obligations. AMD can choose whether to exercise that right. The same 8-K says AMD has unspecified obligations if the Neocloud defaults in certain material ways. Core Scientific's second-quarter report, filed with the SEC the next day, repeats the 8-K's account of the leases and of AMD's support, but not the $14 billion. Its third-quarter report, filed Nov 5, says none of the leases had started by Sep 30, and revenue is expected to begin in phases from 2027. That report values AMD's at $296.4 million. Core Scientific records it as a lease incentive that will reduce its revenue over the lease terms.

Sources 9 documents — 7 SEC filings · 1 company release · 1 transcript

Research trail Found 691 documents and read 636 of them while checking this deal and related ones.

  1. Core Scientific · SEC filingsec.gov
    States 7 figures: lease term · 530 MW lease aggregate · 1,925 MW reservation right · warrant · warrant vesting · $296.4M warrant fair value · $137.3M warrant liability
  2. Core Scientific · SEC filingsec.gov
    States 2 figures: 385 MW reservation power path · 100% NOI margin
  3. Core Scientific · SEC filingsec.gov
    States 377 MW counterparty split
  4. Core Scientific · SEC filingsec.gov
    States more than $14B revenue headline
  5. Core Scientific · SEC filingsec.gov
    States filed vs furnished
  6. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  7. company releaseinvestors.corescientific.com
    Cited by the record; no single figure is quoted from it.
  8. transcriptd1io3yog0oux5.cloudfront.net
    Cited by the record; no single figure is quoted from it.
  9. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: CORZ 8-K 7/27/2026 (Item 7.01 furnished / Item 3.02 filed) + Q2'26 earnings package (furnished) and prepared remarks + Q2 2026 10-Q (filed 7/28/2026) + Q3 2026 10-Q (filed 11/5/2026) + Q3'26 deck (furnished); AMD Q2 2026 10-Q (its post-June leases and lease guarantees) · as of Nov 2026

The evidence 12 sourced figures · 5 disputes

The record's headline Core Scientific–AMD: 529 leased (377 AMD + 152 Neocloud) + 30M-share to the tenant

Size
529 MW / '>$14B' (company figure, furnished, never filed)
When
Jul 2026 → Nov 5 2026 10-Q: none commenced → full 529 MW by end-2028 (est.)
Status
signed — first delivery est. 1H 2027
Structure
15-yr leases + warrant-for-leases + 1,925 MW reservation right + Neocloud credit support
Programme
Core Scientific–AMD
Parties
AMD anchor tenant (377 MW) + warrantholder + Neocloud cure rights (scope contested) · Core Scientific landlord/developer + warrant-issuer
Capital
the seller's own money or backing comes back as its sales
Record
disclosed / primary source · as of Nov 2026

Flows 2 as the record states them

  • AMD → Core Scientificlease-payments377 MW critical IT across Pecos/Hunt/Muskogee, 15-yr triple-net (structure from remarks; the leases themselves are unfiled)
  • Core Scientific → AMDequitywarrant for up to 30M CORZ shares @ $23.47, vesting 12,222/MW of leased load (~6.5M at signing), expires Jul 27 2031 — the amd-openai/amd-meta geometry reversed; Core Scientific books it at $296.4M, a deferred lease incentive amortized against its revenue (Q3 10-Q)

Resolved figures 12 each with the verbatim line from its document

  • counterparty-split377 MW
    377 MW leased directly to AMD (Pecos, Hunt County, Muskogee) + 152 MW to an unnamed 'Neocloud' (Auburn, Dalton Phase 3) — the 529 MW total is arithmetic on these two stated figures, never itself printed in the 8-K. Every 'AMD secures 500+ MW' headline collapses two counterparties into one; 29% of the signed capacity is not AMD's lease. The company's '~380/~150' is the same split rounded, not a competing measurement. First stated in the Jul 27 8-K's Item 7.01 (furnished); the Q2 10-Q, filed Jul 28, repeats the sentence word for word in its subsequent-events note (Note 15) and in MD&A. The Nov 5 10-Q prints the aggregate itself, rounded ('approximately 530 MW'), and gives no split (attr lease-aggregate)
    “On July 27, 2026, the Company entered into Lease Agreements (collectively, the “AMD Leases”) with Advanced Micro Devices, Inc. (“AMD”) for an aggregate of 377 MW of critical IT capacity at the Company’s Pecos, TX; Muskogee, OK; and Hunt County, TX sites; and Lease Agreements (the “Neocloud Leases,” and collectively with the AMD Leases, the “Leases”) with a Neocloud (“Neocloud”), for 152 MW of critical IT capacity at the Company’s Auburn, AL and Dalton Phase 3, GA sites.”
    CORZ Q2 2026 10-Q, Note 15 (filed Jul 28 2026); first stated in the Jul 27 8-K Item 7.01 (furnished) · sec.gov
  • lease-term15
    15-year initial term with three 5-year renewal options, each lease (the Neocloud's too) — distinguish from CoreWeave's 12-yr + two 5-yr colocation terms at the same landlord. First stated in the Jul 27 8-K's Item 7.01 (furnished); restated in a filed document the next day, the Q2 10-Q (Jul 28, Note 15: 'Each of the Leases is for a fifteen year term with three five-year options', the AMD and Neocloud leases together), and again in the Q3 10-Q (Note 6)
    “Each AMD Lease is for a fifteen-year term with three five-year options.”
    CORZ Q3 2026 10-Q, Note 6 (filed Nov 5 2026); first filed in the Q2 2026 10-Q, Note 15 (Jul 28 2026) · sec.gov
  • lease-aggregate530 MW
    the Q3 10-Q (filed Nov 5) gives the aggregate as 'approximately 530 MW of critical IT capacity across five of the Company's sites' and defines AMD's and the Neocloud's leases together as 'the AMD Leases': no 377/152 split, no dollar value, no credit-support terms, and no lease exhibited (the Q2 10-Q, filed Jul 28, had already restated the 8-K's split, term, reservation and credit support: filed-vs-furnished). As of Sep 30 none had commenced and no lease revenue had been recognized; they are 'expected to commence in phases beginning in 2027' and are left out of the 10-Q's lease tables. 530 agrees with the 8-K's 377 + 152 = 529 to rounding
    “In July 2026, the Company entered into lease agreements with AMD and a Neocloud counterparty (collectively, the “AMD Leases”) for an aggregate of approximately 530 MW of critical IT capacity across five of the Company's sites. AMD was provided with a reservation capacity right to lease from the Company at certain times and circumstances an additional 1,925 MW of critical IT capacity through December 28, 2028. The AMD Leases are expected to commence in phases beginning in 2027 as the contracted capacity is completed and the applicable lease commencement conditions are satisfied, and the Company will determine the classification of each AMD Lease at commencement. Each AMD Lease is for a fifteen-year term with three five-year options. As of September 30, 2026, none of the AMD Leases had commenced, no related lease revenue had been recognized, and amounts related to the AMD Leases are not included in the tables below.”
    CORZ Q3 2026 10-Q, Note 6 (filed Nov 5 2026) · sec.gov
  • reservation-right1,925 MW
    an ADDITIONAL 1,925 MW reservation-of-capacity right through Dec 28, 2028 — conditional ('at certain times and under certain circumstances' in the 8-K) and, in the Q3 10-Q, 'not a binding lease commitment': a right to lease, not contracted capacity. Fully exercised it would take AMD-plus-Neocloud capacity to 'approximately 2,455 MW' (the 10-Q's own sum, 530 + 1,925; from the 8-K's 529 it is 2,454) ≈ the 'up to 2.5 GW' headline, which is INCLUSIVE of the signed MW. No source, the 10-Q included, discloses what AMD pays (if anything) for the reservation
    “In connection with the AMD lease agreements executed in July 2026, AMD was granted a reservation right to lease up to an additional 1,925 MW of critical IT capacity from the Company through December 28, 2028. The reservation right is not a binding lease commitment, and if fully executed, could result in total contracted capacity with AMD and the Neocloud counterparty of approximately 2,455 MW.”
    CORZ Q3 2026 10-Q, MD&A (filed Nov 5 2026); first stated in the Jul 27 8-K Item 7.01 (furnished) · sec.gov
  • reservation-power-path385 MW
    the Q3 deck (furnished) sorts the 1,925 MW reservation by how its power is secured: ~385 MW on grid connections the company already holds (Hunt ~192, Muskogee ~192), ~600 MW under utility load study (Pecos ~200, Muskogee ~400) and ~940 MW behind-the-meter, 'on-site generation evaluated alongside grid supply' (Pecos ~615, Muskogee ~325). The Q2 deck gave the same ~385 and one ~1,540 MW for the rest (600 + 940 here): no total moved. So ~385 of the 1,925 MW has secured grid power today; the rest is under study or evaluation
    “POWER PATHWAYS UNDER AMD RESERVATION 1 SECURED GRID-CONNECTED ~385 MW Power secured through existing grid connections Hunt, TX Batch Zero, Base Load ~192 MW Muskogee, OK ~192 MW 2 POWER UNDER LOAD STUDY ~600 MW Additional grid capacity progressing through load study review Pecos, TX Batch Zero, Studied Load ~200 MW under load study Muskogee, OK ~400 MW under load study 3 BEHIND-THE-METER ~940 MW On-site generation evaluated alongside grid supply Pecos, TX ~615 MW BTM pathway Muskogee, OK ~325 MW BTM pathway”
    CORZ Q3'26 earnings deck, slide 5 (furnished Ex-99.2 to the Nov-5 8-K) · sec.gov
  • warrantup to 30,000,000
    up to 30M CORZ shares (~5.9% of the decks' ~508M–509M fully diluted) at $23.47 — a market-price strike (5-day VWAP pre-execution), not the penny strike of AMD's own OpenAI/Meta warrants; issued Jul 27 under the 8-K's Item 3.02 (filed, not furnished) and restated unchanged in the Q3 10-Q; expires July 27, 2031
    “On July 27, 2026, in connection with the execution of the AMD Leases as described in Note 6 — Leases, the Company issued AMD a warrant (the “AMD Warrant”) to purchase up to 30 million shares of the Company's common stock at an exercise price of $23.47 per share, representing the five-day volume-weighted average price of the Company's common stock on Nasdaq prior to execution. The AMD Warrant expires on July 27, 2031.”
    CORZ Q3 2026 10-Q, Note 8 (filed Nov 5 2026); first stated in the Jul 27 8-K Item 3.02 (filed) · sec.gov
  • warrant-vesting12,222
    vests at 12,222 shares per MW of critical IT load under the leases ('contemplated by' them in the 8-K, 'contracted under' them in the 10-Q) — the Neocloud's 152 MW vests AMD's warrant too; 12,222 × 529 ≈ 6.47M ≈ the ~6.5M vested at signing, and the rest 'will vest as additional capacity is contracted under the AMD Leases', i.e. as the reservation is taken up. Full 30M vesting requires ~2,455 MW — the 10-Q's own total for full exercise, essentially the entire 2.5 GW; the circulating '$704M warrant proceeds' is 30M × $23.47 assuming exactly that
    “Warrant shares vest at a rate of 12,222 shares per one MW of critical IT load under the AMD Leases. Upon issuance on July 27, 2026, approximately 6.5 million warrant shares vested and became immediately exercisable based on the MW contracted under the AMD Leases. The remaining warrant shares will vest as additional capacity is contracted under the AMD Leases.”
    CORZ Q3 2026 10-Q, Note 8 (filed Nov 5 2026); first stated in the Jul 27 8-K Item 3.02 (filed) · sec.gov
  • warrant-fair-value$296.4M
    the Q3 10-Q books the warrant at $296.4M on issuance — $90.1M for the vested ~6.5M shares (equity, to additional paid-in capital) and $206.4M for the unvested rest (a liability, remeasured each quarter) — as a 'deferred lease incentive' that will be amortized as a reduction of revenue over the lease terms, 'beginning at lease commencement' (none had commenced by Sep 30). The landlord's own accounting policy (Note 2) describes warrants issued with customer leases as 'an incentive for the customer to enter into long-term lease arrangements'
    “The vested portion of the AMD Warrant meets the criteria for equity classification, and its issuance date fair value of $90.1 million was recorded as a component of additional paid-in capital. The remaining unvested portion does not meet the criteria for equity classification and was initially recognized as a warrant liability at its issuance date fair value of $206.4 million. The aggregate issuance date fair value of $296.4 million was recognized as a deferred lease incentive that will be amortized as a reduction of revenue over the term of the related leases. … The warrants are issued as an incentive for the customer to enter into long-term lease arrangements, which are expected to generate future lease revenue. The deferred lease incentive is included within “Other current assets” and “Deferred lease incentive, net of current portion” in the condensed consolidated balance sheets and is amortized as a reduction of revenue over the term of the related customer leases, beginning at lease commencement.”
    CORZ Q3 2026 10-Q, Notes 2 and 8 (filed Nov 5 2026) · sec.gov
  • warrant-liability$137.3M
    the unvested part is marked to market each quarter: $206.4M at issuance → $137.3M at Sep 30, a $69.1M gain in the quarter, with the stock at $15.98 on Sep 30 (the 10-Q's valuation input) against the $23.47 strike. The deferred lease incentive itself, per the 10-Q's MD&A, 'is not adjusted for subsequent changes in the fair value of the warrant liability'
    “As of September 30, 2026, the AMD Warrant liability was $137.3 million. During the three and nine months ended September 30, 2026, the Company recognized a gain of $69.1 million from changes in its fair value. … The deferred lease incentive is amortized as a reduction of revenue over the term of the related leases and is not adjusted for subsequent changes in the fair value of the warrant liability.”
    CORZ Q3 2026 10-Q, Notes 8–9 and MD&A (filed Nov 5 2026) · sec.gov
  • revenue-headlinemore than $14B
    'more than $14 billion of POTENTIAL base contracted revenue' — never FILED: the figure reaches EDGAR only as furnished material (Ex-99.1 to the Jul-28 earnings 8-K, Items 2.02/7.01, same not-deemed-'filed' legend as the lease 8-K) — the same species of disclosure as the 8-K's account of the leases it prices, though that account was restated in the filed Q2 10-Q the next day and the dollar figure was not. The lease 8-K states no dollar value, the leases were never exhibited, and no AMD-side disclosure confirms it. It spans BOTH counterparties over 15 years; the AMD-direct share is undisclosed. Every downstream number ($1.76M/MW, both banks' targets, the '$24B+' portfolio backlog it nests inside) is arithmetic on this one furnished figure. Same-day prepared remarks drop the word 'potential'. Not in the Q2 10-Q (filed Jul 28), whose MD&A highlight gives the announcement without it, and still unfiled after the Q3 10-Q (Nov 5), whose lease note and July-announcement highlight carry no dollar value; the Q3 deck (furnished) shows only the portfolio-wide '$24B+' and '$1.8B' of average annual GAAP revenue, CoreWeave's included. AMD's own figure is for all its new leases: its Q2 10-Q says that after Jun 27 2026 it 'entered into long-term data center leases with aggregate future payments of $9.5 billion over lease terms of up to 16 years', to commence in 2027 and 2028. The timing fits these leases, but the 10-Q names no landlord, and 'up to 16 years' is not the 15-year term here, so it is not tied to Core Scientific by name
    “Announced a partnership with AMD with the potential to support up to 2.5 GW of leasable capacity, anchored by 15-year agreements for approximately 530 MW across five sites and more than $14 billion of potential base contracted revenue.”
    CORZ Q2'26 earnings release (furnished Ex-99.1 to the Jul-28 8-K, never filed); AMD Q2-2026 10-Q (context: its post-June leases, no landlord named) · sec.gov
  • noi-margin100%
    the Q3 deck (furnished) gives the company's NOI margin by counterparty: 100% on the AMD-direct leases, 85% on the 'AMD-backed' Neocloud lease, 80–85% on CoreWeave's, 90% blended — 'all numbers are approximate'. An operating-economics figure for the AMD leases that is not derived from the unfiled '>$14B'; the leases behind it are unfiled
    “80–85% CoreWeave lease 85% AMD-backed neocloud lease 100% AMD direct lease 90% blended NOI margin Note: All numbers are approximate.”
    CORZ Q3'26 earnings deck, slide 4 (furnished Ex-99.2 to the Nov-5 8-K) · sec.gov
  • filed-vs-furnished7.01
    the record's load-bearing distinction, in the 8-K's own words: there is NO Item 1.01 (entry into a material definitive agreement) in the filing — its only item headers are 3.02, 7.01 and 9.01 — the 377/152/1,925 lease description and the credit-support account sit under Item 7.01 (Reg FD), which the legend below strips of 'filed' status; only the warrant (Item 3.02) is filed. A 529 MW, 15-year, self-described '>$14B' lease package therefore entered the SEC record first as investor communication. The next day the Q2 10-Q (filed Jul 28) restated the 8-K's account word for word in its subsequent-events note (Note 15) and in MD&A: the 377/152 split, the 15-year term and options, the 1,925 MW reservation and the three-part Credit Support Agreements — so the lease description is filed after all. What stays unfiled is the dollar value: neither the Q2 10-Q nor the Q3 10-Q (Nov 5) carries the '>$14B' or the '$24B+', and neither exhibits a lease or a Credit Support Agreement (the Q2 10-Q's Item 6 lists the May 2026 indenture and global note, the Polaris merger agreement, the certifications and the XBRL; the Q3's, the Aug 25 credit agreement, the certifications and the XBRL). The Q3 10-Q adds the rounded aggregate (~530 MW) and that none had commenced (attrs lease-aggregate, lease-term, reservation-right)
    “The information in Item 7.01 of this Current Report on Form 8-K, including Exhibit 99.1 and Exhibit 99.2, is furnished and shall not be deemed “filed” for purposes of Section 18 of the Securities Exchange Act of 1934, as amended (the “Exchange Act”), or otherwise subject to the liabilities of that section”
    CORZ 8-K Item 7.01 legend (Jul 27 2026) · sec.gov

Contested figures 5 not reconciled — every position side by side, with its source and tier

headline-capacityone entry, in its own words
529 MW (8-K lease sum) vs 'approximately 530 MW' (company headline, and the basis of the $14B / ~$6B / $1.76M-per-MW derivations) vs 'more than 500 MW' (joint PR — which also attributes all of it to AMD). A rounding-and-attribution split, not a measurement dispute: adopting 529 breaks the published derivations, adopting 530 misstates the 8-K. This record carries 529 in its title and size because it is the sum of the two counterparty figures the 8-K actually states; the derived numbers below are left on their published bases rather than recomputed (~530 under the company's $14B/~$6B round numbers, 529 in the banks' $1.76M restatement), so the bases are not reconciled. Nov 5: the Q3 10-Q (filed) uses the company's 'approximately 530 MW' for the aggregate and 'approximately 2,455 MW' for the total at full exercise, and the Q3 deck calls its figures 'approximate' — neither splits AMD from the Neocloud 8-K vs Q2'26 package vs joint release vs Q3 10-Q
2.5-gw-statusone entry, in its own words
'AMD to secure up to 2.5 gigawatts' (joint PR headline) vs 'reservation of capacity right … at certain times and under certain circumstances' (8-K) — the PR itself uses both framings in adjacent sentences. The filed 10-Qs carry both too: the Q2 10-Q (Jul 28) restates the 8-K's reservation wording in its notes while its MD&A highlight gives 'the potential to support up to 2.5 GW of leasable capacity'; the Q3 10-Q (Nov 5) then takes the second side outright: the right 'is not a binding lease commitment', and 'if fully executed, could result in total contracted capacity … of approximately 2,455 MW'; the same 10-Q describes the July announcement as one with 'the potential to support up to 2.5 GW of leasable capacity'. What stays unsettled is whether the 2.5 GW is economically 'secured': no consideration or trigger conditions for the reservation are disclosed, the 10-Q included joint release vs 8-K Item 7.01 vs Q2 and Q3 10-Qs
credit-support-scopeone entry, in its own words
'AMD will provide full credit support throughout the full 15-year lease term' (prepared remarks, echoed by trade press) vs the 8-K's description: (i) equipment protections, (ii) the right, BUT NOT THE OBLIGATION, to cure Neocloud defaults, and (iii) clauses 'establishing AMD’s rights and obligations in the event of certain material defaults by a Neocloud' — obligations it names but does not describe — with auto-termination triggers. The credit story on 152 MW — 29% of signed capacity, counterparty unnamed — turns on which reading is right; the Credit Support Agreements themselves are not exhibited anywhere, and the 8-K's account of them, furnished under Item 7.01, is repeated word for word in the filed Q2 10-Q (Jul 28, Note 15 and MD&A). Remarks add: no equity step-in rights. Nov 5: the Q3 deck (furnished) calls the Neocloud's lease 'AMD-backed' ('85% AMD-backed neocloud lease', in its NOI-margin table) and says 'over 50% of cash flows' are 'backed by investment-grade credit' (it does not say whose); the Q3 10-Q (filed) describes no credit support, cure right or Credit Support Agreement and exhibits none — the contest stands. AMD's side: its Q2 10-Q books its support of partners' leases as guarantees — 'a maximum gross exposure of $4.1 billion from guarantees issued in connection with certain commercial partner data center lease obligations with terms up to 15 years' at Jun 27 2026, which 'may be issued in exchange for warrants'. That date is before the Jul 27 agreements, so it says nothing directly about the Neocloud's support
“The remaining approximately 150 megawatts across Auburn and Dalton will support a neocloud through a modified-gross lease for which AMD will provide full credit support throughout the full 15-year lease term.”
2Q26 prepared remarks (the link and quote) vs 8-K Item 7.01 and CORZ Q2 10-Q vs CORZ Q3 deck and 10-Q; AMD Q2-2026 10-Q (context) · d1io3yog0oux5.cloudfront.net
build-cost-scopeone entry, in its own words
$11–12M/MW company build-cost estimate (the '~$6B' initial capex is this × ~530, rounded, expected to be financed by project-level bonds — a plan, not committed funding) — same-day materials disagree on whether tenant fit-out (another $1–2M/MW) is inside the range, and who bears fit-out is undisclosed. Nov 5: neither the Q3 10-Q (filed) nor the Q3 deck (which drops the build-cost slide) restates a per-MW cost; the 10-Q puts all purchase and construction commitments at ≈ $4.4B, with 'the construction and delivery of contracted capacity under the AMD Leases, including fit out costs' one of three buckets (AMD's share not split; $202.2M of the $4.4B passes through to CoreWeave), says the company 'expects to complete project-level bond financing within the next twelve months' and that the AMD and Neocloud build-out 'will require additional external financing', with no assurance of acceptable terms — the bonds are still a plan 2Q26 prepared remarks + call coverage + Q3 10-Q
revenue-per-mwone entry, in its own words
$1.76M/MW labeled 'average annual revenue' (Needham) AND 'blended trended NOI' (KBW) — contradictory labels for the identical figure because both are $14B ÷ 529 ÷ 15 restated, not independent evidence; KBW's $1.69M AMD-direct variant adds an assumed 10% Neocloud premium (split undisclosed). Confidence = confidence in the unfiled $14B; both banks' notes are on file only through one syndicated summary each Needham + KBW via single syndicated summaries (notes not on file)

Scope note what this record leaves to other records

Site split (furnished deck Ex-99.2, Q2 and again Q3 — unchanged; reconciles to the 8-K without residual): AMD-direct Pecos ~185 + Hunt ~110 + Muskogee ~82 = 377 MW; Neocloud Dalton ~120 + Auburn ~32 = 152 MW. Delivery est. (unchanged in the Q3 deck): Pecos/Auburn 1H27, Dalton/Muskogee 2H27, Hunt 1H28, the full ~530 MW by end-2028. Of the 1,925 MW reservation only ~385 MW is grid-connected today (Hunt ~192 + Muskogee ~192); the remaining ~1,540 MW (Pecos ~815 + Muskogee ~725) sits in load study / behind-the-meter — the Q3 deck splits it ~600 MW load study (Pecos ~200, Muskogee ~400) and ~940 MW behind-the-meter (Pecos ~615, Muskogee ~325): reservation-power-path. NOT this deal: Riot Platforms' separate 25 MW AMD lease at Rockdale, TX (own landlord, 10-yr, ~$311M) and AMD–Anthropic's up-to-2-GW MI450 deployment — they must never be merged into it.

More between AMD and Core Scientific

The record holds no other deal between them.

Everything between AMD and Core Scientific →