Amazon–Vistra

Vistra is to supply Amazon 1,200 ('up to', its results release says) of Comanche Peak nuclear power for 20 years from late 2027; the price is undisclosed, and Texas has yet to approve the hookup.

A deal between Amazon / AWS, Vistra

Why it matters

Amazon is pursuing a direct line to a running nuclear plant in Texas, the kind of connection federal regulators stopped Talen from expanding in Pennsylvania. Amazon would take half the plant's output for up to 40 years and provide enough backup generation for the entire output to return to the grid in an emergency.

Tap a figure for the line in its source.

Vistra gives Amazon / AWS

  • of Comanche Peak's nuclear power for 20 years, with options to extend for up to 20 more — first deliveries in late 2027, the full amount by 2031–2032
  • land beside the plant for Amazon's data center, which the power is to reach over Amazon's own lines, netted at the plant's meters rather than carried by the grid

Amazon / AWS gives Vistra

  • payments at an undisclosed price; Vistra expects the deal to add about 8–10% to its free cash flow if Amazon uses the full capacity

Sep 29, 2025 announced by Vistra in an 8-K, its customer unnamedupdated Nov 18, 2026signed before Sep 1 2025 disclosed by the parties

What happened

Vistra will sell Amazon power from its Comanche Peak nuclear plant in Somervell County, Texas. Vistra is also leasing Amazon land beside the plant for a data center. The power is to reach the site over Amazon's own lines, bypassing the public grid. The deal covers 1,200 megawatts, half the plant's output, for 20 years with options for 20 more. Deliveries are due to start in late 2027 and reach the full amount around 2031–2032. Amazon is to provide backup generation equal to the data center's demand. That would let the plant send its entire output back to the grid in a grid emergency. Neither company disclosed the price. Analysts' estimates run from about $75 to $120 per megawatt-hour. Half are calculated from Vistra's own cash-flow forecasts. The other estimates give no method. Texas's utility commission has yet to approve the hookup. Its staff recommends approval with the grid operator's conditions.

Sources 35 documents — 11 other documents · 10 regulatory filings · 5 SEC filings · 5 press reports · 1 company release · 1 transcript · 1 research note · 1 government statement

Research trail Found 145 documents and read 134 of them while checking this deal and related ones.

  1. SEC · SEC filingsec.gov
    States 3 figures: term years · 2,400 MW plant share · licences
  2. SEC · SEC filingsec.gov
    States 2 figures: 1,200 MW contract volume · delivery start
  3. SEC · SEC filingsec.gov
    States 2 figures: 1,200 MW announcement · 8–10% fcf accretion
  4. Texas PUC · regulatory filinginterchange.puc.texas.gov
    States 2 figures: 100 MW load ramp · reserve margin
  5. Texas PUC · regulatory filinginterchange.puc.texas.gov
    States 1,200 MW co located load
  6. Texas PUC · regulatory filinginterchange.puc.texas.gov
    States delivery structure
  7. company releaseNov 2026press.aboutamazon.com
    States amazon offtake
  8. powertexasforward.com · other documentpowertexasforward.com
    States 1,200 MW vistra campus page
  9. SEC · SEC filingsec.gov
    States 3,800 MW combined program
  10. Texas PUC · regulatory filinginterchange.puc.texas.gov
    States puc review
  11. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  12. other documentfilecache.investorroom.com
    Cited by the record; no single figure is quoted from it.
  13. transcriptNov 6, 2026fool.com
    Cited by the record; no single figure is quoted from it.
  14. regulatory filinginterchange.puc.texas.gov
    Cited by the record; no single figure is quoted from it.
  15. regulatory filinginterchange.puc.texas.gov
    Cited by the record; no single figure is quoted from it.
  16. regulatory filinginterchange.puc.texas.gov
    Cited by the record; no single figure is quoted from it.
  17. regulatory filinginterchange.puc.texas.gov
    Cited by the record; no single figure is quoted from it.
  18. regulatory filinginterchange.puc.texas.gov
    Cited by the record; no single figure is quoted from it.
  19. regulatory filinginterchange.puc.texas.gov
    Cited by the record; no single figure is quoted from it.
  20. other documentsomervellcountytx.iqm2.com
    Cited by the record; no single figure is quoted from it.
  21. press reporttradingview.com
    Cited by the record; no single figure is quoted from it.
  22. other documentFeb 19, 2026zeta.creativecirclecdn.com
    Cited by the record; no single figure is quoted from it.
  23. press report (archived copy)datacenterdynamics.com
    Cited by the record; no single figure is quoted from it.
  24. other documentMay 7, 2026texastribune.org
    Cited by the record; no single figure is quoted from it.
  25. other document (archived copy)cleanview.co
    Cited by the record; no single figure is quoted from it.
  26. other documentworldnuclearreport.org
    Cited by the record; no single figure is quoted from it.
  27. other documentSep 2025rtoinsider.com
    Cited by the record; no single figure is quoted from it.
  28. other document (archived copy)enverus.com
    Cited by the record; no single figure is quoted from it.
  29. other documenteglplc.com
    Cited by the record; no single figure is quoted from it.
  30. press reportpowermag.com
    Cited by the record; no single figure is quoted from it.
  31. research notetheshuffledeep.substack.com
    Cited by the record; no single figure is quoted from it.
  32. press report (archived copy)tipranks.com
    Cited by the record; no single figure is quoted from it.
  33. press reportFeb 6, 2026cnbc.com
    Cited by the record; no single figure is quoted from it.
  34. other documentcbsnews.com
    Cited by the record; no single figure is quoted from it.
  35. government statementenergy.gov
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: Vistra 8-K (Sep 29 2025), FY2025 10-K and Q3 2026 10-Q; Vistra's FY2025 results release and deck, Q3 2026 call and Comanche Peak data-center page; Amazon's Somervell County page (Nov 2026); Texas PUC Docket 59399 (applications, joint testimony, ERCOT study errata and exhibits, Staff brief); BofA, Enverus, EGL, PEI via POWER, The Shuffle; Reuters, Hood County News, DCD, Texas Tribune, WNISR · as of Nov 2026

The evidence 15 sourced figures · 4 disputes

The record's headline Amazon–Vistra: 20-yr PPA for 1,200 of Comanche Peak nuclear power — half the plant — for a data center Amazon is building beside it

Size
1,200 MW / 20 yr, options for up to 20 more (half the ~2,400 MW plant) · from Q4 2027, full by 2031–32 · price undisclosed
When
before Sep 1 2025 (CP Company and Amazon sign the contract for the net metering arrangement, by the PUC filings) → Sep 29 2025 (Vistra's 8-K: a 20-year PPA with 'a large, investment grade company') → Jan 29 2026 (Vistra and Amazon representatives tell Hood County's commissioners court the 1,200 MW is for an Amazon data center on Comanche Peak property, per Hood County News) → Feb 19 2026 (PUC application, the customer unnamed) → Feb 26 2026 (Vistra's FY2025 results name AWS) → May 19 2026 (amended application, Amazon Data Services co-applicant) → Oct 13 and Oct 29 2026 (ERCOT's study and its errata) → Nov 10 2026 (initial briefs) → Q4 2027 (first deliveries; the first 100 MW of load) → 2031–2032 (the full 1,200 MW)
Status
signed before Sep 1 2025 (CP Company's contract with Amazon, by the PUC filings); announced Sep 29 2025; 'construction has started' on the data center (Vistra's CEO, Nov 6 2026); the net metering arrangement before the Texas PUC — initial briefs filed Nov 10 2026, Commission Staff recommending approval subject to ERCOT's proposed conditions, no order among the documents read; first deliveries expected Q4 2027
Structure
a 20-year power purchase agreement between Vistra and AWS (Amazon Data Services, Inc. in the Texas PUC docket) for 1,200 MW of the ~2,400 MW plant, with options to extend for up to 20 more years; the PPA itself is not filed. The power is to reach Amazon's data center on land that Vistra's subsidiary Comanche Peak Power Company LLC (CP Company, the plant's owner) leases to it beside the plant, over customer-owned lines, its consumption netted at the plant's ERCOT settlement meters — a net metering arrangement under PURA §39.169 that the PUC must approve (Docket 59399). Amazon brings backup generation at least as large as the load, not synchronized to the grid
Programme
Time-to-power
Parties
Amazon / AWS buyer — AWS in Vistra's filings; Amazon Data Services, Inc. leases the land, builds the data center, its lines and its backup generation, and is co-applicant at the PUC · Vistra seller — owns and runs the plant through its subsidiary Comanche Peak Power Company LLC, the docket's applicant and Amazon's landlord
Record
disclosed / primary source · as of Nov 2026

Flows 3 as the record states them

  • Vistra → Amazon / AWSpower1,200 MW of Comanche Peak's output for 20 years, options for up to 20 more; from Q4 2027, full by 2031–2032 (contested full-ramp) — to Amazon's data center beside the plant over customer-owned lines, netted at the plant's meters, once the Texas PUC approves (puc-review)
  • Amazon / AWS → Vistrappa-paymentsprice undisclosed — analysts' estimates ~$75–120/MWh, tier 3 (contested ppa-price); Vistra expects ~8–10% incremental Adjusted FCFbG accretion if the full capacity is used
  • Vistra → Amazon / AWSland-leaseland beside the plant leased to Amazon Data Services for the data center, with the plant's surface water rights for its cooling, leased too by Amazon's account; rent not disclosed

Resolved figures 15 each with the verbatim line from its document

  • contract-volume1,200 MW
    1,200 MW of 'carbon-free power' from Comanche Peak for 20 years — the Q3 2026 10-Q's 'Comanche Peak Power Purchase Agreement' passage, word for word the Q2 10-Q's and the same in substance in the FY2025 10-K and the Q1 10-Q, and in the Sep 29 2025 8-K but for the customer's name (see announcement). Half the plant's ~2,400 MW (see plant-share). Whether 1,200 MW is a firm volume or a ceiling, only the unfiled PPA would show: Vistra's own results release and campus page say 'up to 1,200' (contested capacity-qualifier)
    “In September 2025, Vistra announced that we entered into a 20-year PPA (with options to extend for up to an additional 20 years) with Amazon Web Services (AWS), pursuant to which we agreed to supply AWS 1,200 MW of carbon-free power from the Comanche Peak Nuclear Power Plant.”
    Vistra Q3 2026 10-Q · sec.gov
  • term-years20
    20 years, with options to extend for up to 20 more — up to 40 in all if every option is taken (our addition). No document on file says who holds the options or on what terms. The FY2025 10-K sets the deal under the heading 'Long-term contracts entered in 2025 underwrite higher base profitability in the future'. Begun in late 2027, the first 20 years end about 2047, inside both reactors' licences; the options would run past them (see licences)
    “In September 2025, we announced that we had entered into a 20-year power purchase agreement (PPA) (with options to extend for up to an additional 20 years) with Amazon Web Services (AWS) to supply 1,200 MW of carbon-free power from our Comanche Peak Nuclear Power Plant.”
    Vistra FY2025 10-K · sec.gov
  • delivery-start2027
    Q4 2027, as Vistra 'anticipates', ramping 'to full capacity by 2032' — the same sentence in the 8-K, the FY2025 10-K and each 2026 10-Q. The data center's own schedule at the PUC starts with 100 MW in or around October 2027 (see load-ramp), and Vistra's campus page says 'Vistra expects the customer to begin incrementally taking power starting in late 2027.' When deliveries reach the full amount: contested full-ramp
    “Vistra anticipates power delivery to begin in the fourth quarter of 2027 and ramp to full capacity by 2032.”
    Vistra Q3 2026 10-Q · sec.gov
  • announcement1,200 MW
    first disclosed on Sep 29 2025 in an 8-K under Item 8.01 (filed, not furnished), the customer unnamed: 'a large, investment grade company'. Reuters the same day: 'an unnamed buyer'; Scotiabank's Andrew Weisel said some investors seemed unsatisfied 'as the contract covers only 50% of the Comanche Peak plant's capacity and as Vistra not naming the customer suggests it might not be a data center.' Vistra's Q3 2025 release (Nov 6 2025) still said 'an investment grade counterparty'; its FY2025 results (Feb 26 2026) and 10-K name AWS. A month earlier, by Hood County News's account of the Hood County commissioners court on Jan 29 2026, 'Vistra and Amazon representatives announced 1,200 megawatts is the amount of electricity that will be provided for an Amazon data center located on Comanche Peak property'
    “On September 29, 2025, Vistra Corp. (“Vistra” or the “Company”) announced that it has entered into a 20-year power purchase agreement (with options to extend for up to an additional 20 years) (the “PPA”) with a large, investment grade company (the “Customer”), pursuant to which the Company has agreed to supply to the Customer 1,200 MW of carbon-free power from the Comanche Peak Nuclear Power Plant.”
    Vistra 8-K (Sep 29 2025) · sec.gov
  • fcf-accretion8–10%
    ~8–10% incremental Adjusted Free Cash Flow before Growth — the deal's only financial figure from either party: a percentage, on forwards as of Aug 29 2025 and Vistra's own fiscal-2026 and conversion assumptions, and only 'if the Customer utilizes the full capacity'. Every dollar figure and $/MWh price on file is worked back from it, from Vistra's later fleet-wide figure, or shows no working (contested ppa-price). On Vistra's Q3 2026 call, 'the final ramp of the AWS Comanche Peak agreement assumed in 2032' was among the opportunities 'not fully reflected' in its outlook to 2030
    “Assuming forwards as of Aug. 29, 2025, an Adjusted EBITDA Midpoint Opportunity consistent with Vistra’s previously communicated fiscal year 2026 expectation, and Vistra’s medium-term expected conversion ratio of Adjusted Free Cash Flow before Growth to Adjusted EBITDA, Vistra expects incremental Adjusted Free Cash Flow before Growth accretion to be in the range of approximately 8-10% if the Customer utilizes the full capacity.”
    Vistra 8-K (Sep 29 2025) · sec.gov
  • co-located-load1,200 MW
    the data center the power is for: Amazon Data Services (ADS) 'will build a data center on property it leases from CP Company', its demand approximately 1,200 MW at completion, starting in Q4 2027 and ramping from 100 MW to the full 1,200 MW over the following four years — the direct testimony of Barry T. Smitherman for both applicants, Comanche Peak Power Company LLC (CP Company, Vistra's subsidiary and the plant's owner) and ADS. On land adjacent to the plant that CP Company owns and leases to ADS: a complex of multiple buildings, linked by ADS-owned lines. Vistra's SEC filings say only that the power goes to AWS; the docket, Amazon's page and Vistra's campus page put it on this site (see amazon-offtake, vistra-campus-page). Press reports of 600 MW: contested load-at-site
    “center demand will be approximately 1,200 MW at completion.”
    PUC Docket 59399 — Smitherman direct testimony for CP Company and ADS (Oct 19 2026) · interchange.puc.texas.gov
  • load-ramp100 MW
    the data center's energization schedule, as CP Company gave it to ERCOT (response to an ERCOT request, Apr 8 2026; ERCOT Ex. PW-2): 100 MW in Q4 2027, 400 MW in Q4 2028, 800 MW in Q4 2029, 1,000 MW in Q4 2030 and 1,200 MW in Q4 2031 — cumulative load, not additions; ERCOT's study uses it. The Shuffle's '20%, 40%, 60%, 80%, and 100% over 2028–2032' is that newsletter's own assumption ('the ramp schedule has not been disclosed'). Whether the PPA's deliveries follow the load or a schedule of their own, no document says (contested full-ramp)
    “Under that schedule, Amazon plans to energize the first 100 MW in or around October 2027, with all 1,200 MW expected to be energized around October 2031.”
    ERCOT errata to its study report, PUC Docket 59399 (Oct 29 2026) · interchange.puc.texas.gov
  • delivery-structure
    behind the meter: the load is 'directly connected to Comanche Peak via customer-owned transmission facilities', its consumption netted at the plant's existing ERCOT settlement meters, and it 'is not expected to be served by grid power'. The applicants commit that the project includes customer-owned backup generation, not synchronized to the grid, with capacity 'equal to or exceeding the expected demand' of the load, used if ERCOT so instructs in an energy emergency — so that 'the full capacity of Comanche Peak will remain available to the ERCOT grid during emergency conditions'. The first application (Feb 19 2026, CP Company alone) named only 'a large load customer'; the amended one (May 19 2026) made ADS a joint applicant. The filings call the contract one 'for the net metering arrangement' and do not say in so many words that it is the PPA; Vistra's campus page: 'The data center will be powered by a direct agreement between Vistra and AWS using electricity from the existing nuclear plant'
    “CP Company and Amazon signed a contract for the net metering arrangement before September 1, 2025.”
    PUC Docket 59399 — amended joint application of CP Company and ADS (May 19 2026) · interchange.puc.texas.gov
  • amazon-offtake
    Amazon's own account: the campus 'sits on land owned by Vistra Corp., adjacent to the existing Comanche Peak Nuclear Power Plant'; 'electricity is delivered from the adjacent Comanche Peak Nuclear Power Plant through dedicated transmission lines to an on-site substation'; its cooling water comes from the plant's Comanche Creek reservoir 'under existing surface water rights owned by Vistra and leased to Amazon'. It gives no MW, term or price and does not mention a PPA
    “Amazon will be a direct off-taker from the plant, paying the full cost of the energy that supports our operations and providing a stable financial backstop for the plant's continued operation”
    Amazon, 'Our responsible approach to investing in Somervell County, Texas' (Nov 2026) · press.aboutamazon.com
  • vistra-campus-page1,200 MW
    Vistra's own page for the project puts the PPA and the campus together: 'an agreement with Amazon Web Services (AWS) to lease part of its extensive Comanche Peak Nuclear Power Plant site for the building and operation of a cloud computing and digital innovation campus, powered by the nuclear plant'; 'The data center will be powered by a direct agreement between Vistra and AWS using electricity from the existing nuclear plant'; AWS, 'at its own cost', will develop and maintain on-site backup power; 'Vistra and AWS are developing all infrastructure and build-out, including the 345 kV private transmission line.' Its summary: contracted capacity 1,200 MW, first deliveries in 2027, 'reaching full contracted capacity by 2032'
    “Vistra and AWS entered into a 20-year power purchase agreement under which Comanche Peak will supply up to 1,200 megawatts of electricity. AWS will also build a data center campus on Vistra’s land at the power plant site.”
    Vistra, Comanche Peak data center campus page (dated Nov 5 2026) · powertexasforward.com
  • plant-share2,400 MW
    Comanche Peak is ~2,400 MW, two units of 1,200 MW net each (the 10-K's nuclear table), so the PPA's 1,200 MW is half of it — the '50%' Reuters quoted from Scotiabank on the day. The docket nets the load against the whole two-unit plant; no filing ties the contract to one unit (Goldman's '1,200 MW from the remaining Comanche Peak unit', via CNBC, is its own framing). The other half is unsold — 'We still have not contracted the second part of Comanche Peak' (Vistra's Stacey Dore, Q3 2026 call) — and 'The plant is also exploring ways to increase output' (Vistra's campus page)
    “Comanche Peak Glen Rose, TX ERCOT Nuclear Uranium 2,400”
    Vistra FY2025 10-K (properties table) · sec.gov
  • licences2050
    Unit 1 licensed to 2050, Unit 2 to 2053. The PPA's first 20 years, from late 2027, end about 2047, inside both; the options for up to 20 more would run to about 2067, past both (our arithmetic). Vistra's campus page: 'Preparations are underway for a second license renewal that would allow the units to operate until 2070 and 2073, respectively' — no application is on file
    “Comanche Peak Unit 1 ERCOT 1,200 18 Months 2050”
    Vistra FY2025 10-K (nuclear units table) · sec.gov
  • combined-program3,800 MW
    Vistra counts this deal with Meta's (pw-meta-6gw) as ~3,800 MW of nuclear PPAs: 1,200 + 2,609 = 3,809 MW, rounded. The Shuffle's 3,376 MW is 1,200 + Meta's 2,176 MW of operating capacity, leaving out Meta's 433 MW of uprates. Stated only in the results release, an 8-K exhibit, not in a filed report
    “Industry-leading power purchase agreements (PPAs) for ~3,800 megawatts of nuclear power with Amazon Web Services (AWS) at our Comanche Peak nuclear facility and nuclear energy, capacity, and uprates with Meta at our various PJM nuclear facilities”
    Vistra FY2025 results release (Feb 26 2026, 8-K ex-99.1) · sec.gov
  • puc-review
    pending: the Texas PUC must approve, deny or condition the net metering arrangement. The applicants ask for approval resting on their own commitments; ERCOT's study recommends six conditions — among them that the load fully curtail within 30 minutes of an ERCOT instruction in a grid emergency (a default ERCOT's witness says it means to propose for every such arrangement, with 10 minutes for a load that confirms it can curtail that fast) and, by the Oct 29 errata, at least 60 minutes' notice before a curtailment instruction when practicable — and ERCOT's brief argues the applicants' commitments are not an adequate substitute. Commission Staff sides with ERCOT. No order is among the documents read; the docket's latest filings are the Nov 10 2026 briefs
    “Staff recommends that the proposed net metering arrangement be approved subject to ERCOT's Proposed Conditions without the addition of Applicants' proposed finding.”
    PUC Docket 59399 — Commission Staff's initial brief (Nov 10 2026) · interchange.puc.texas.gov
  • reserve-margin0.74
    ERCOT's corrected estimate of what the hookup does to the grid's planning reserve margin once the load is full: winter 2031/2032, −0.69 percentage points at the peak-load hour and −0.74 at the peak net-load hour; fall 2031, −0.86 and −0.91. The Oct 29 errata replaced the Oct 13 study's −2.29/−2.34 (fall) and −2.49/−2.54 (winter); a public comment of Nov 5 still cites the withdrawn figure as 'up to -2.54%'. Over the ramp, fall 2027 to winter 2030/2031, the study found changes of −0.09 to −0.83 points
    “A similar calculation for winter 2031/2032 yields changes in the Peak Load and Peak Net Load reserve margins of negative 0.69 percentage points and negative 0.74 percentage points, respectively.”
    ERCOT errata to its study report, PUC Docket 59399 (Oct 29 2026) · interchange.puc.texas.gov

Contested figures 4 not reconciled — every position side by side, with its source and tier

capacity-qualifierone entry, in its own words
1,200 MW — Vistra's filed words: the 8-K ('has agreed to supply to the Customer 1,200 MW'), the FY2025 10-K and each 2026 10-Q ('agreed to supply AWS 1,200 MW') vs up to 1,200 MW — Vistra's FY2025 results release (its CEO: 'a 20-year power purchase agreement with AWS for up to 1,200 MW'), its campus page ('will supply up to 1,200 megawatts') and POWER ('up to 1,200 MW') vs approximately 1,200 MW — the PUC filings, which size the data center's load ('approximately 1,200 MW at completion'). The PPA is not filed, so whether 1,200 MW is a firm delivery obligation or a ceiling that follows the data center's ramp is not shown; the 8-K conditions its 8–10% on the customer using 'the full capacity' Vistra 8-K, 10-K and 10-Qs / FY2025 results release, campus page, POWER / PUC Docket 59399
full-rampone entry, in its own words
Q4 2031 — the data center's energization schedule, CP Company's to ERCOT (1,200 MW in Q4 2031), and ERCOT's study ('all 1,200 MW expected to be energized around October 2031') vs 2032 — the 8-K, the FY2025 10-K and the 2026 10-Qs ('ramp to full capacity by 2032'), Vistra's Q4 2025 deck ('full ramp by 4Q 2032'), its campus page ('reaching full contracted capacity by 2032') and its Q3 2026 call ('the final ramp of the AWS Comanche Peak agreement assumed in 2032'). The first is the load's energization, the second the PPA's deliveries; 'by 2032' could take in late 2031, '4Q 2032' could not. No document reconciles them PUC Docket 59399 (ERCOT Ex. PW-2; ERCOT errata) / Vistra filings, deck, page and call
load-at-siteone entry, in its own words
~1,200 MW — the PUC filings for both applicants ('approximately 1,200 MW at completion', on a schedule reaching 1,200 MW in Q4 2031) and ERCOT's study; Hood County News on the Jan 29 2026 meeting (1,200 MW 'for an Amazon data center located on Comanche Peak property') vs 600 MW — the Texas Tribune (May 7 2026: Somervell County 'has a tax abatement deal with Amazon for a 600-megawatt data center', linking the county's file), Cleanview's database ('It will have a capacity of 600 MW', no source given) and WNISR 2026 ('half of that capacity would power a 600-MW data center that Amazon plans to build adjacent to the reactor site … the other half would be for other Amazon data centers in Texas', citing DCD, which gives no MW, and Cleanview). The county's executed agreement with ADS on file states no MW; the abatement application the 600 MW may come from was not read. Whether 600 MW is a first phase, no document on file says; Amazon's own page gives no size PUC Docket 59399 + Hood County News / Texas Tribune, Cleanview (via Wayback), WNISR 2026
ppa-priceone entry, in its own words
undisclosed — no document of either party gives a price, a payment or a total (EGL: 'contract terms were not disclosed'; The Shuffle: 'Neither contract discloses a price'). The estimates on file run ~$75–120/MWh, all tier 3: about $75–110 (The Shuffle, worked back from the CEO's expected ~25% accretion once all of Vistra's nuclear contracts deliver in full, less Meta's share — 'good only as an order of magnitude') · $90 (Enverus: 'Comanche Peak at $90', no working shown) · ~$90–100 (PEI, via POWER) · 'an all-in price in the high $90/MWh' (EGL, from the 8–10%) · $100 (Jefferies, Sep 22 2025, a week before the 8-K, as The Shuffle relays it) · $105–120, midpoint ~$112 (BofA, Sep 29 2025: 8–10% of an assumed $4,080M of 2026 free cash flow, 1,200 MW at 100% for 10,512 GWh a year, and a $55/MWh ERCOT West power price). Shared inputs, not corroboration; the '$326-408 million' a year of added free cash flow TipRanks attributes to Morgan Stanley's David Arcaro is the same 8–10% of the same $4.08B BofA, Enverus (via Wayback), EGL, POWER/PEI, The Shuffle, TipRanks (via Wayback)

Scope note what this record leaves to other records

Not this deal — carried elsewhere or not carried: Somervell County's Chapter 381 agreement with Amazon Data Services, the incentives for the campus rather than the power — yearly grants of 90% of the county property taxes the project pays, for 15 consecutive years (the '90% in property tax rebates for 30 years' in CBS's 60 Minutes report was AWS's pitch to neighbouring Hood County, which it did not pursue); a minimum capital investment of $1 billion in the county by Dec 31 2028; at least 300 full-time positions by Dec 31 2030; $2.5M within 120 days of construction starting and $300,000 a year per substantially complete data-center building; construction 'expected to commence by January 1, 2027'. DCD's 'up to 18 two-story buildings across some 435 acres and see some $5 billion invested' reads a tax-abatement application that was not read; Amazon's own page expects 'at least 550 full-time positions'. Meta's PPAs (pw-meta-6gw; the vistra entity); DOE's conditional loan commitment for Vistra's PJM uprates, whose 'option to finance potential future uprates at Vistra's Comanche Peak' carries no amount; the KKR Helix Fund commitment in the same 10-Q (up to $1 billion; nothing in the 10-Q links it to AWS or Comanche Peak); and the 200-MW Oak Hill Solar Facility, 'which includes a PPA also with AWS' (Vistra's FY2025 results) — a separate Vistra–AWS contract, its own record (pw-amzn-oak-hill).

More between Amazon / AWS and Vistra

  1. Aug 8, 2024

Everything between Amazon / AWS and Vistra →