Google–NextEra

Google signed a 25-year deal for most of the power of Iowa's shut Duane Arnold nuclear plant (615 ), which NextEra plans to restart by early 2029 if regulators approve; the price is undisclosed.

A deal between Google, NextEra Energy

Why it matters

Google's commitment to buy power for 25 years made a reactor retired for economic reasons worth restarting, with a federal loan of up to $1.9B behind it. Four-fifths of the contract depends on a licence extension past 2034, which the NRC's tracker still lists as unfiled.

Tap a figure for the line in its source.

NextEra Energy gives Google

  • disputedof the restarted plant's output for 25 years, from early 2029 if regulators approve — whether Google's contract covers all of it is contested

Google gives NextEra Energy

  • payments at an undisclosed price, which both companies say enable the investment to restart the plant and cover the cost of producing its power

Oct 27, 2025 announced by NextEra and Googleupdated Nov 21, 2026restart underway → online no later than Q1 2029 disclosed by the parties

What happened

Google's data-center demand is bringing back Iowa's only nuclear plant, which retired for economic reasons. Under a 25-year agreement signed in October 2025, Google will buy most of the 615 plant's output once it restarts. A local co-op will take about 50 MW on the same terms. The Energy Department has closed a loan of up to $1.9 billion for the restart. Neither company says what Google pays. The goal is to restart by early 2029, if regulators approve. The plant's licence runs only to 2034. Most of Google's 25 years depend on a licence extension that the Nuclear Regulatory Commission (NRC) still lists as not yet submitted. Alliant, the utility that bought most of the plant's output, agreed in 2018 to pay NextEra $110 million to end its contract five years early. The plant shut in 2020 after a windstorm damaged it. NextEra has since bought out its two co-op partners and owns the plant outright.

Sources 22 documents — 8 company releases · 7 SEC filings · 5 regulatory filings · 1 other document · 1 government statement

Research trail Found 348 documents and read 319 of them while checking this deal and related ones.

  1. regulatory filingnrc.gov
    States PPA term
  2. company releasenewsroom.nexteraenergy.com
    States 615 MW announced capacity
  3. DocumentCloud (hosted document) · other documents3.documentcloud.org
    States 50 MW cipco offtake
  4. NextEra · SEC filingsec.gov
    States restart target
  5. regulatory filingnrc.gov
    States nrc decisions
  6. regulatory filingnrc.gov
    States licence term
  7. US Department of Energy · government statementenergy.gov
    States up to $1.9B doe loan
  8. NextEra · SEC filingsec.gov
    States 100% ownership
  9. NextEra · company releaseinvestor.nexteraenergy.com
    States up to $0.16 eps guidance
  10. NextEra · company releaseinvestor.nexteraenergy.com
    States $50–100M early spend
  11. company releasenewsroom.nexteraenergy.com
    States $110M prior PPA buyout
  12. company releasenexteraenergy.com
    States more than $75M local tax
  13. company releaseinvestor.nexteraenergy.com
    Cited by the record; no single figure is quoted from it.
  14. company releaseblog.google
    Cited by the record; no single figure is quoted from it.
  15. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  16. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  17. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  18. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  19. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  20. regulatory filingnrc.gov
    Cited by the record; no single figure is quoted from it.
  21. regulatory filingnrc.gov
    Cited by the record; no single figure is quoted from it.
  22. company releasenewsroom.nexteraenergy.com
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: NextEra–Google release (Oct 27 2025) + NEE 8-Ks, FY25 10-K, Q2'26 10-Q and Q3'26 10-Q + IUC order GCU-2025-0013 + NRC record (draft EA, schedule letter, transfer order) + DOE loan release (Sep 8 2026) + Alphabet Q3'26 10-Q · as of Oct 2026

The evidence 12 sourced figures · 7 disputes

The record's headline Google–NextEra: 25-yr PPA to restart Iowa's Duane Arnold nuclear plant

Size
615 MW plant / 25 yr
When
Oct 2025 (PPA) → Jul 2026 (100% owned) → Sep 2026 (DOE loan) → online by Q1 2029 (target)
Status
restart underway → online no later than Q1 2029 (target)
Structure
25-year wholesale PPA with Google Energy LLC; CIPCO buys ~50 MW (8.13%) under its own PPA on consistent terms; plus a separate, unpriced agreement to explore new US nuclear
Programme
Time-to-power
Parties
Google offtaker (via Google Energy LLC) · NextEra Energy plant owner-operator (100% since Jul 2026) + DOE borrower
Record
disclosed / primary source · as of Oct 2026

Resolved figures 12 each with the verbatim line from its document

  • ppa-term25 years
    25 years, signed Oct 27 2025 by NextEra's Duane Arnold subsidiary and Google — the IUC order names the buyer as Google Energy LLC and calls it 'a wholesale PPA' executed that day; NextEra's Q3'25 8-K and FY25 10-K, the joint release and the NRC's draft EA all say 25 years. From a Q1-2029 restart it would run to ~2054, about 20 years past the plant's licence (see licence-term)
    “On October 27, 2025, NEDA signed a 25-year power purchase agreement with Google to supply carbon-free energy from DAEC to Google’s cloud and artificial intelligence infrastructure in Iowa”
    NRC draft EA (Jul 2026) · nrc.gov
  • announced-capacity615 MW
    615 MW is NextEra's figure for the plant, used in the joint release and in NextEra's filings and releases — its plant fact sheet from the operating years already gave '615 MWe' net, and the plant's engineering director said on a tour that there are no plans to produce more than 615 MW (Business Record's paraphrase, Sep 2026). Google's own post says 'more than 600 MW'. The regulatory record gives the same plant other figures, on other bases (see contested capacity-conventions)
    “Once operational, Google will purchase power from the 615-MW plant as a 24/7 carbon-free energy source to help power Google’s growing cloud and AI infrastructure in Iowa”
    NextEra–Google joint release (Oct 27 2025) · newsroom.nexteraenergy.com
  • cipco-offtake50 MW
    ~50 MW (8.13% of output) to Central Iowa Power Cooperative, then a 20% co-owner, under its own PPA executed Dec 23 2025 — NextEra's Q3'25 8-K: 'CIPCO will purchase 50 megawatts of the plant's output on terms and conditions consistent with the Google PPA'; CIPCO told the IUC it will use the power 'to serve its members'. Settled; whether the rest is all Google's is not (see google-share)
    “Similarly, on December 23, 2025, DAE and CIPCO executed a PPA under which CIPCO is to receive 8.13 percent of DAEC's output (approximately 50 MW).”
    IUC final order, GCU-2025-0013 (Jun 18 2026) · s3.documentcloud.org
  • restart-target2029
    no later than Q1 2029, 'perhaps as early as the fourth quarter of 2028' (NextEra's Q3'25 8-K). The 'no later than' bound is restated in the Jul-2026 and Oct-2026 earnings releases ('remains on track') and recalled in the Sep-2026 loan release; none repeats the Q4-2028 upside. The IUC order records NEDA's target as Q4 2028 through Q1 2029, and the FY25 10-K gives 'an estimated commercial operation date in 2029'. A company target 'pending regulatory approvals', not a date any regulator has set (see contested restart-window)
    “NextEra Energy Resources' Duane Arnold nuclear plant in Iowa remains on track to be recommissioned and re-enter service no later than the first quarter of 2029.”
    NEE Q3'26 8-K ex-99 (Oct 21 2026) · sec.gov
  • nrc-decisions2028
    the NRC staff expects to issue its final decisions on the restart licensing actions by Jan 29 2028, keyed to the licensee's own plan to transition 'to an operational status' in early 2028 — a licensing milestone, not the restart, and an estimate the NRC says 'could change'. One component review is dated two ways by the NRC itself: its Dec-2025 acceptance email expects the operating-licence amendment's safety review 'by December 2026', while this letter lists it as December 15, 2027 — in a sentence that also misdates that acceptance email as 'December 15, 2026' — so the NRC documents leave it unclear which date is meant
    “to an operational status would be in early 2028, therefore the staff expects to issue its final decisions on the licensing actions by January 29, 2028.”
    NRC schedule letter (Mar 25 2026) · nrc.gov
  • licence-term2034
    the restart would be licensed only through Feb 21 2034, the end of the current renewed licence (DPR-49): the NRC's review and draft EA cover operation to that date — the EA's emissions estimates count 6 years of operation — and nothing beyond. Running Google's 25 years needs a subsequent licence renewal (see contested licence-extension). The single 'February 21, 3034' in NEDA's environmental report is a typo; the same report says 2034 elsewhere
    “NextEra Energy Duane Arnold, LLC (NEDA) submitted a series of licensing and regulatory requests that are necessary to reauthorize power operations at the Duane Arnold Energy Center (DAEC) through February 21, 2034, the end of the current operating license term under DAEC's Renewed Facility Operating License No. DPR-49.”
    NRC environmental audit plan (ML26030A013) · nrc.gov
  • doe-loanup to $1.9B
    up to $1.9B from the Energy Department's Office of Energy Dominance Financing, a combined conditional commitment and financial close on Sep 8 2026 (NextEra's release the same day). NextEra's Q3'26 10-Q (Oct 21 2026) words it as 'a federal loan arrangement providing for up to $1.9 billion of financing, guaranteed by the U.S. Department of Energy', entered into in September 2026 by 'a NEER subsidiary'; its Q3 release says the company 'closed a loan with the U.S. Department of Energy of up to $1.9 billion to support the restart'. 'Up to' is the facility's ceiling: no draw, rate, tenor or share of the restart's cost is disclosed. The lender's money, not Google's — and not a cost estimate (see restart-cost)
    “WASHINGTON—The U.S. Department of Energy’s (DOE) Office of Energy Dominance Financing (EDF) today announced the financial close of a loan of up to $1.9 billion to NextEra Energy to help finance the restart of the Duane Arnold Energy Center in Linn County, Iowa.”
    DOE release (Sep 8 2026) · energy.gov
  • ownership100%
    100% NextEra since Jul 15 2026. Before: NextEra ~70%, Central Iowa Power Cooperative 20%, Corn Belt Power Cooperative 10%. The agreements to buy the co-ops' 30% were announced with the PPA (Oct 2025); the NRC approved the licence transfer on Mar 30 2026, and NEDA told the NRC the deal closed on Jul 15. No cash price is disclosed: NextEra's CEO said on the Q3'25 call that the buyout 'was done in exchange for us assuming their decommissioning liability', and the co-ops kept their own decommissioning funds (NRC, citing the transfer application: 'the CIPCO and Corn Belt fund balances would not be transferred to NEDA')
    “In July 2026, NextEra Energy Resources obtained 100% ownership of Duane Arnold through the acquisition of the remaining ownership interest.”
    NEE Q3'26 10-Q · sec.gov
  • eps-guidanceup to $0.16
    up to $0.16 a year of adjusted earnings per share, averaged over the first 10 years of operation — NextEra's guidance, assuming 100% ownership (since achieved) and eligibility for the nuclear production tax credit (its 2025 value $30/MWh, adjusted for inflation thereafter) with a 10% energy-community bonus; no IRS or Treasury determination for the plant is among the documents read. The only number either company gives for what the deal earns
    “Expected to contribute up to $0.16 of annual adjusted EPS on average over first 10 years of operation”
    NEE investor conference deck (Dec 8 2025) · investor.nexteraenergy.com
  • early-spend$50–100M
    $50–100M committed in 2025, before the Google contract, when NextEra put a restart at 'technically achievable as early as Q4 2028' — the only restart spending NextEra has put a number on (also reported from its FERC filing by Utility Dive); the total is undisclosed (see restart-cost)
    “COD technically achievable as early as Q4 2028 • $50 - $100 MM committed in 2025”
    NEE investor deck (Sep 2 2025) · investor.nexteraenergy.com
  • prior-ppa-buyout$110M
    $110M — what the plant's main buyer, Alliant Energy's Iowa utility (IPL: 'approximately 430 MW of capacity and the resulting energy' under a 2014–2025 PPA), agreed in 2018 to pay NextEra in Sep 2020 to end its Duane Arnold PPA five years early (2025 → 2020); the plant was then due to retire in late 2020 and stopped that August. Both parties' documents say $110M (Alliant's Q2-2018 filing; this release); a 2018 local-press $114M, used in its account of Alliant's savings arithmetic, is not explained
    “Alliant Energy has agreed to make a $110 million buyout payment to NextEra Energy Resources in September 2020 to cover the cost to shorten the term of the DAEC PPA from 2025 to 2020.”
    NextEra–Alliant release (Jul 27 2018) · newsroom.nexteraenergy.com
  • local-taxmore than $75M
    more than $75M for all taxing districts over the project's life, of which more than $41M goes to the local school district and $26M to Linn County — parts of the $75M, not additions (Business Record's list puts the $41M beside 'about $75 million to all other taxing districts'). A projection from the economic study NextEra cites (Strategic Economic Research's, per that firm's own page) — one company-cited model, so tier 2; the same study is behind NextEra's jobs and '$9 billion' figures
    “The same study found that Duane Arnold would provide more than $75 million for all taxing districts over the life of the project, including more than $41 million for the local school district and $26 million for Linn County.”
    NextEra Duane Arnold project page (citing the study) · nexteraenergy.com

Contested figures 7 not reconciled — every position side by side, with its source and tier

google-shareone entry, in its own words
~565 MW, ~92% — CIPCO takes ~50 MW (8.13%) under its own PPA with Google Energy LLC 'taking the rest' (IUC order, from the consumer advocate's testimony); NextEra as the press relays it: Google 'set to receive around 565' (KCRG, Nov 2025, citing the company) and 'The remaining 565 megawatts will go to Google Energy' (Business Record, Sep 2026, citing a spokesperson); the joint release has CIPCO buying 'the remaining portion of the plant's output on the same terms as Google' vs 100%, which is 615 MW on NextEra's own figure for the plant, the one in the joint release — NextEra's FY25 10-K: 'NEER entered into a 25-year PPA for the full capacity of Duane Arnold', a sentence that names no buyer and was filed after CIPCO's PPA was signed. It may describe the two same-term PPAs as one; no document says so, and the Google PPA itself is not public IUC order + NextEra releases and press accounts vs NEE FY25 10-K
capacity-conventionsone entry, in its own words
615 MWe net (NextEra's fact sheet, the joint release and NextEra's own releases; MISO's queue holds four nuclear replacement requests at the plant's own bus that add up to the same figure) / ~610 MWe gross (NEDA's environmental report, whose pre-shutdown ratings 'are expected to remain unchanged under restart conditions'; the NRC draft EA's purpose: '610 MWe of baseload power generation capability through February 21, 2034') / 601 MWe net (the same EA's emissions appendix; EIA's 2010 summer capacity) / 600–619 MW ('historical peak winter net capacity range' in NextEra's FERC waiver request, via Power Engineering; 'up to 619 MW' of combined interconnection rights, Utility Dive) / 646 MW summer and winter net (MISO queue J3932, a nuclear interconnection request at the Duane Arnold 161 kV point, requested in service Jun 29 2029; the queue names no applicant, but MISO's fast-track (ERAS) register has NextEra Energy Resources filing for 'a 646 MW generating facility' at that substation, 646 MW requested against a facility maximum of 675.5 MW summer and winter, a request since withdrawn) / 621.9 MWe (ANS, no source given) / 'more than 600 MW' (Google). Different conventions and vintages, never reconciled in one document; no uprate filing is among the documents read, so why NextEra asked for 646 MW, with a 675.5 MW maximum, is unexplained, and TechCrunch's '601 megawatts' plus 'an additional 14 megawatts' at restart subtracts across bases NextEra fact sheet / NEDA ER + NRC draft EA / EIA / FERC waiver via trade press / MISO queue + ERAS register
restart-windowone entry, in its own words
Q4 2028 – Q1 2029, NextEra's own window (its earnings 8-Ks, Oct 2025 to Oct 2026; IUC order: NEDA's 'target commercial operational date is in the fourth quarter of 2028 through the first quarter of 2029') vs the later dates on file: the in-service date requested in MISO queue J3932, Jun 29 2029 (an applicant's request, not a ruling; see capacity-conventions), and the FERC waiver's commercial-operation deadline of Dec 31 2029 (Troutman) — NextEra 'could bring Duane Arnold back online in the fourth quarter of 2028, but asked for an additional year' in case of equipment or repair delays (Utility Dive, citing FERC; the order itself is not among the documents read). MISO's queue gives the plant's own replacement requests a negotiated in-service date just before NextEra's window opens. Outliers: Power Engineering's 'by 2030' restates that FERC deadline; DCD's 'Q1 2028 at the earliest', credited to 'FERC filings', matches no account of those filings on file — the other early-2028 dates on file for the plant are NRC licensing milestones and the in-service date requested in NextEra's withdrawn fast-track (ERAS) MISO request NextEra 8-Ks + IUC order vs MISO queue + ERAS register + FERC waiver (via Troutman, Utility Dive) vs trade press
restart-costone entry, in its own words
undisclosed — CEO Ketchum 'declined to provide financial details of the 25-year power purchase agreement with Google or put a figure on the capital investment required to resurrect the plant' (Reuters, Oct 28 2025); NextEra's leaders have since said only, in KCRG's paraphrase at the loan's closing, that the project 'will require an investment of multiple billions of dollars'. Figures in circulation, none a party's total: ≥$1B, 'at least $1 billion in direct construction investment' in an Oct-2025 economic analysis 'based on detailed cost estimates supplied by NextEra' (ENR) / 'more than $1.6bn', NucNet (Oct 28 2025), unattributed — the same figure as Constellation's Crane restart estimate / $1.600B, the Iowa Legislative Services Agency's fiscal-note modelling assumption, whose sources list NucNet. The DOE's up-to-$1.9B loan is a financing ceiling, not a cost Reuters / KCRG / ENR / NucNet / Iowa LSA FN 1605307 / DOE
ppa-priceone entry, in its own words
undisclosed — 'Neither company disclosed financial terms of the deal' (TechCrunch); Ketchum declined to give 'financial details' (Reuters). Neither files it: an EDGAR full-text search of Alphabet's filings for 'Duane Arnold' returns nothing, and NextEra gives only its EPS guidance (its Dec 8 2025 investor-conference deck). The record holds no estimate for this plant; the est ribbon borrows the ~$110/MWh it draws for Microsoft's Three Mile Island restart (pw-msft-tmi ppa-price), a different deal TechCrunch / Reuters / EDGAR full-text search
google-roleone entry, in its own words
buyer, per both companies: the PPA 'enables the investment to restart the plant and covers costs for the production of energy' (joint release; Google's post says 'we’re enabling the investment to restart the plant and covering costs for the production of energy') — no Google equity, loan or prepayment for the restart appears in any document vs 'Google provided the upfront investment to restart the Duane Arnold nuclear plant' (Iowa Public Radio caption, Apr 2026) and 'Google is providing funding for restart work at the plant through its entrance into a 25-year PPA' (ANS) — press readings of the same contract. NextEra's own spokesperson, when the deal was announced: 'Google will be paying for getting Duane Arnold back online' (KCRG), which fits either side. The record cannot close it: Alphabet's Q3'26 10-Q discloses 'financial guarantees to certain counterparties' 'to support counterparty procurement of long-lead time equipment for our future power purchase and energy agreements', 'with varying terms through January 2049' ($16.2B maximum at Sep 30 2026), company-wide and without naming a counterparty, so no document ties any of it to this plant NextEra–Google release + Google post vs IPR / ANS; KCRG; Alphabet Q3'26 10-Q
licence-extensionone entry, in its own words
planned — NEDA told the NRC in Jan 2025 that 'NextEra plans to submit an application for Subsequent License Renewal', and the NRC's tracker lists it for Oct–Dec 2025 vs not yet filed — the same NRC page (read Oct 2026) still carries Duane Arnold under 'Future Submittals', with nothing from it received or under review; KCRG (Apr 2026): 'NextEra is planning to work toward a twenty-year extension'. Until one is granted, operation ends Feb 21 2034, the end of the current licence (the NRC's audit plan and draft EA) NEDA letter ML25023A265 + NRC SLR status page vs KCRG

Scope note what this record leaves to other records

Not this deal — carried elsewhere or not carried: the separate Oct-2025 agreement 'to explore the development of new nuclear generation to be deployed in the U.S.' (no size, site or money stated); the Dec-2025 Google Cloud partnership — GW-scale data-center campuses, Google Cloud for NextEra's own systems, joint AI products, all unpriced (nextera entity note); Google's other nuclear bets — Kairos (pw-goog-kairos), Elementl's three sites 'each aiming for at least 600 MW' (May 2025), Constellation uprates adding 890 MW (Oct 2026: pw-goog-constellation); Alphabet's unnamed Jan-2026 PPA ($9.9B of lease payments in 2027–2047, or ~$3.5B plus the generating assets if conditions fail), which no filing ties to this plant and whose 2027–2047 schedule does not fit it; the new 620 MW load that MISO's expedited review had approved connecting by Apr 2026 at the plant's 161 kV bus (CIPCO for Linn County REC, expected in service Jul 1 2028, customer unnamed) and Google's proposed campus at Palo next door (Iowa Public Radio) — no document gives Google's load in MW; Crane's 835 MW (pw-msft-tmi); CIPCO's own decommissioning reserves ($174.1M at end-2024), which the transfer left with CIPCO (NRC, citing the transfer application: 'the CIPCO and Corn Belt fund balances would not be transferred to NEDA'); the plant's 1970s licensing and commercial-operation dates (two NextEra slide decks disagree, 1974 vs Feb 1975). Local figures, all projections: ~400 direct full-time operations jobs (joint release) / 433 'direct, full-time and ongoing jobs' (the economic study, per the IUC order) / 'more than 450' (DOE release) / 'more than 462' (DOE project page) — no document reconciles DOE's two counts; jobs during construction: 1,640 statewide, direct, indirect and induced (the study) vs 'nearly 1,500' (DOE). Iowa's 2026 sales-tax exemption for nuclear plants — the restart is the only project its fiscal notes model — costs the General Fund $20.1M / $13.8M / $7.0M in FY2027–29 by the Legislative Services Agency's final fiscal note ($33.1M in FY2027 in its first note on the bill), both on the LSA's own $1.600B cost assumption. The plant stopped on Aug 10 2020 after derecho damage to its cooling towers, ahead of its planned late-2020 retirement.