Entergy Arkansas–Google

Google buys power for its Arkansas data center from Entergy for 20 years, at rates Entergy says pay for a $1.6B solar plant; a pending amendment adds 250 and ~$600M of batteries and lines.

A deal between Google, Entergy Arkansas

Why it matters

Entergy says Google's minimum bills are set to pay off a $1.6 billion solar-and-battery plant Entergy owns and runs for all customers. Entergy says Google would cover the cost of added projects once it takes service. The rates and minimum-bill share are redacted, so outsiders cannot check the model behind that promise.

Tap a figure for the line in its source.

Entergy Arkansas gives Google

  • of electric service to the West Memphis campus, which must buy all its power from Entergy with limited exceptions — from Feb 1 2027 by Entergy's application, or from the earlier of Jun 1 2027 and the new Galet substation's completion by the contract summary — renewing in 5-year terms; the maximum demand and the ramp are redacted
  • of load under the amendment, on a faster ramp than the original's — the only load figure a filing gives for the contract; the campus's total is redacted (600 at full ramp under the original contract, by the press's account of a staff memo)
  • solar plant with a 350 , four-hour battery — Arkansas Cypress Solar in Jefferson County, built and owned by Entergy to serve all its customers, approved in Mar 2026 and expected in service by the end of 2028 — whose clean-energy credits go to Google
  • 250 + 100 MWof new four-hour batteries in the amendment, their certificates pending — Driver (1,000 MWh, Mississippi County) and Jones Mill (400 MWh, Hot Spring County), $550.6M together, expected Jun 1 2028 — whose construction financing Google prepays and whose cost, and any shortfall in their 40% tax credits, its rates are set to cover

Google gives Entergy Arkansas

  • a minimum monthly demand charge whatever it uses, on a share of its maximum demand the filings redact (80%, Google told legislators, per an unofficial transcript), set to recover the solar plant's and the new batteries' revenue requirements and a share of Entergy's existing costs, with overruns passed on up to 125% of the plant's $1.8B estimate and 130% of the batteries'
  • in accelerated payments scheduled from 2025 to 2029, and $83M in minimum demand payments, which Entergy sets aside and credits to rates later; the Commission rejected the short spread Entergy proposed and in Jan 2026 had it spread over the plant's life, and the amendment does the same with Google's new payments toward the batteries, from 2032. Whether the $83M recurs every year is disputed
  • of the transmission to serve the campus, paid ahead of construction — a new 500/230 kV substation (Galet) under the original contract, its expansion and two new 230 kV lines under the amendment — with overruns up to 130% of each estimate; the amounts are redacted ($190M for the original, by Google's account)
  • solar PPA for 20 years (Big Island, Mississippi County): Entergy buys the output and Google its clean-energy credits, at the PPA price plus an adder less what the power and capacity earn in the market — 100% of the PPA's cost during the contract, Entergy says. The Commission denied the PPA in Sep 2026 and reopened it on Oct 22
  • a termination payment if it leaves, recovering what the minimum bills have not of the plants' cost, and an immediate payment of two years of minimum bills on termination or default; backed by Alphabet's guaranties, a letter of credit if Alphabet's rating falls, a four-month billing deposit and insurance worth twelve months of minimum bills. About $2B in the original contract, declining after 13 years, by the press's account of a staff memo, which Google's letter repeats

Sep 5, 2025 Entergy Arkansas's application to the Arkansas PSC, which names Googleupdated Nov 21, 2026 disclosed by the parties

What happened

Entergy Arkansas, the utility for much of the state, agreed to power Google's new West Memphis data center for 20 years. The Arkansas Public Service Commission approved the original contract in December 2025. Google pays a minimum monthly bill even if it uses less power. Entergy says this bill is set to pay for a $1.6 billion solar plant with batteries it is building in Jefferson County for all customers. Google also pays up front for the lines to its campus. An amendment signed in October 2026 would add 250 megawatts of demand and bring it on faster. It also adds about $600 million of batteries and transmission and a 440-megawatt solar purchase the Commission had rejected weeks earlier. The amendment still needs approval. Entergy says Google would cover all those costs and puts savings for other customers at $2.1 billion. The public documents black out the campus's total possible power demand, Google's rates and most of what it pays. The public figures are disputed. The regulator's slides to legislators count $526 million in Google contributions toward the plant. Entergy and Google say Google's payments under the original contract total about $2.1 billion over 20 years. That figure is separate from the estimated savings.

Sources 46 documents — 28 regulatory filings · 9 company releases · 4 other documents · 2 SEC filings · 2 press reports · 1 government statement

Research trail Found 157 documents and read 151 of them while checking this deal and related ones.

  1. Arkansas PSC · regulatory filingapps.apsc.arkansas.gov
    States 5 figures: parties · minimum bill · 100% transmission · termination · load flexibility
  2. Arkansas PSC · regulatory filingapps.apsc.arkansas.gov
    States announced
  3. regulatory filingapps.apsc.arkansas.gov
    States approval
  4. Arkansas PSC · regulatory filingapps.apsc.arkansas.gov
    States amendment
  5. Arkansas PSC · regulatory filingapps.apsc.arkansas.gov
    States term
  6. Arkansas PSC · regulatory filingapps.apsc.arkansas.gov
    States 250 MW expansion load
  7. SEC filingsec.gov
    States 600 MW cypress
  8. Arkansas PSC · regulatory filingapps.apsc.arkansas.gov
    States $443M accelerated payments
  9. company releaseentergy.com
    States $600M expansion investment
  10. Arkansas PSC · regulatory filingapps.apsc.arkansas.gov
    States $550.6M batteries
  11. regulatory filingapps.apsc.arkansas.gov
    States 440 MW big island
  12. entergyarkansas.com · other documententergyarkansas.com
    States $1.76 construction financing
  13. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  14. regulatory filingapps.apsc.arkansas.gov
    Cited by the record; no single figure is quoted from it.
  15. regulatory filingapps.apsc.arkansas.gov
    Cited by the record; no single figure is quoted from it.
  16. regulatory filingapps.apsc.arkansas.gov
    Cited by the record; no single figure is quoted from it.
  17. regulatory filingapps.apsc.arkansas.gov
    Cited by the record; no single figure is quoted from it.
  18. regulatory filingapps.apsc.arkansas.gov
    Cited by the record; no single figure is quoted from it.
  19. regulatory filingapps.apsc.arkansas.gov
    Cited by the record; no single figure is quoted from it.
  20. regulatory filingapps.apsc.arkansas.gov
    Cited by the record; no single figure is quoted from it.
  21. regulatory filingapps.apsc.arkansas.gov
    Cited by the record; no single figure is quoted from it.
  22. regulatory filingapps.apsc.arkansas.gov
    Cited by the record; no single figure is quoted from it.
  23. regulatory filingapps.apsc.arkansas.gov
    Cited by the record; no single figure is quoted from it.
  24. regulatory filingapps.apsc.arkansas.gov
    Cited by the record; no single figure is quoted from it.
  25. regulatory filingapps.apsc.arkansas.gov
    Cited by the record; no single figure is quoted from it.
  26. regulatory filingapps.apsc.arkansas.gov
    Cited by the record; no single figure is quoted from it.
  27. regulatory filingapps.apsc.arkansas.gov
    Cited by the record; no single figure is quoted from it.
  28. regulatory filingapps.apsc.arkansas.gov
    Cited by the record; no single figure is quoted from it.
  29. regulatory filingapps.apsc.arkansas.gov
    Cited by the record; no single figure is quoted from it.
  30. regulatory filingapps.apsc.arkansas.gov
    Cited by the record; no single figure is quoted from it.
  31. company releaseentergy.com
    Cited by the record; no single figure is quoted from it.
  32. company releaseblog.google
    Cited by the record; no single figure is quoted from it.
  33. company releaseentergy.com
    Cited by the record; no single figure is quoted from it.
  34. company releaseMar 2026entergy.com
    Cited by the record; no single figure is quoted from it.
  35. company releaseentergy.com
    Cited by the record; no single figure is quoted from it.
  36. company releaseentergy.com
    Cited by the record; no single figure is quoted from it.
  37. other documentlittlerockchamber.com
    Cited by the record; no single figure is quoted from it.
  38. government statementarkleg.state.ar.us
    Cited by the record; no single figure is quoted from it.
  39. company releaseOct 2026s201.q4cdn.com
    Cited by the record; no single figure is quoted from it.
  40. company releaseentergy.com
    Cited by the record; no single figure is quoted from it.
  41. regulatory filingcdn.misoenergy.org
    Cited by the record; no single figure is quoted from it.
  42. regulatory filingcdn.misoenergy.org
    Cited by the record; no single figure is quoted from it.
  43. other documentpatternenergy.com
    Cited by the record; no single figure is quoted from it.
  44. other documentredtaperecordings.com
    Cited by the record; no single figure is quoted from it.
  45. press report (archived copy)arkansasonline.com
    Cited by the record; no single figure is quoted from it.
  46. press reportlatitudemedia.com
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: Arkansas PSC Docket 25-055-P — Entergy Arkansas's application (Sep 2025; errata Sep 9; p. 6 refiled Oct 16 2026) with Stack's direct and Hunt's direct (unredacted Oct 15 2026), the contract's Table 3 (refiled Oct 15 2026), Orders No. 9 (Dec 4 2025) and 11 (Jan 29 2026) and the Feb 5 2026 compliance filing, the amended and restated application with Palmer's, Dalrymple's (Exhibit KRD-1), Elbe's and Hunt's testimony (Oct 19–20 2026), Orders No. 13 and 14 and the docket index; Docket 25-054-U (Cypress Solar testimony, Sep 5 2025); Docket 26-073-U (the batteries' certificates and Cullipher's testimony, Oct 29 2026); Docket 26-003-U (the Big Island PPA: Order No. 6, Order No. 7, the joint motion of Nov 2 2026); Entergy / Entergy Arkansas 10-Q for Q3 2026 and Q3 release (8-K, furnished); Entergy Arkansas releases (Oct 2 2025, Mar 5 2026, Oct 19 2026), statements (Sep 2–3 2026), Google fact sheet, GAJA facts page, battery fact sheet and renewable portfolio list; MISO's 2024 plan and EPR statistics; Google's blog, statement and letter (Little Rock Regional Chamber); the APSC's slides to the Joint Energy Committee (Oct 19 2026) and the Sep 15 2026 hearing transcript; the Arkansas Democrat-Gazette's report of the APSC records (Aug 31 2026) and Latitude Media for the contested cells (read 2026-11) · as of Nov 2026

The evidence 16 sourced figures · 7 disputes

The record's headline Entergy Arkansas–Google: 20 years of power for the West Memphis data center under a contract approved Dec 2025, at rates Entergy says are built to pay for a $1.6B, 600 solar plant with batteries — and, in an amendment filed Oct 19 2026 and awaiting a ruling Entergy asked for by Jan 15 2027, 250 MW more load, ~$600M of new batteries and transmission and a 440 MW solar PPA the regulator had denied, which Entergy says Google will pay for; the campus's total load and Google's rates are redacted

Size
20-year special rate contract (Feb 2027–Feb 2047 by Entergy's application) · maximum demand redacted (600 MW at full ramp under the original, by the press's account of a staff memo; the amendment adds 250 MW) · Cypress Solar: 600 MW of solar + a 350 MW four-hour battery, $1,602M ($1.8B with AFUDC) · amendment: Driver (250 MW / 1,000 MWh) + Jones Mill (100 MW / 400 MWh) batteries, $550.6M; the Galet substation's expansion + two 230 kV lines; the Big Island 440 MW (ac) solar PPA, 20 years · ~$600M of planned investment + the PPA, 'covered by Google' · $443M of accelerated payments (2025–2029) + $83M of minimum demand payments, deferred and amortized over the plant's life (Order No. 11)
When
Jul 25 2025 (original agreement dated) → Aug 15 2025 (docket opened, no customer named) → Sep 5 2025 (application filed, naming Google; errata Sep 9) → Oct 2 2025 (announced by both companies) → Nov 17 2025 (hearing) → Dec 4 2025 (approved, Order No. 9; Entergy's amortization of Google's early payments rejected) → Dec 18 2025 (Entergy signs the Big Island PPA) → Jan 29 2026 (Order No. 11: the payments amortized over the plant's life, Cypress's tax credits allowed in Google's pricing) → Feb 5 2026 (Entergy's compliance schedule) → Mar 2026 (Cypress Solar approved) → Aug 31 2026 (the $526M story) → Sep 16 2026 (Big Island PPA denied) → Oct 7 2026 (amended agreement and Big Island credits agreement dated) → Oct 15–16 2026 (the $443M schedule and the deferral amounts made public) → Oct 19 2026 (amendment filed and announced) → Oct 22 2026 (Big Island rehearing granted) → Oct 29 2026 (batteries filed; Order No. 14) → Jan 4 2027 (hearing) → Jan 15 2027 (ruling requested) → Feb 1 2027 (term begins, per Entergy's application) → Jun 1 2028 (batteries expected) → Dec 31 2028 (Cypress Solar projected) → Feb 1 2047 (term ends, per the application)
Status
original contract approved without modification Dec 4 2025 (Order No. 9), which rejected Entergy's short amortization of Google's early payments; on rehearing Jan 29 2026 (Order No. 11) the payments were set to be amortized over the plant's life. Amendment filed Oct 19 2026 and pending: staff and intervenor testimony Nov 16, hearing Jan 4 2027, ruling requested by Jan 15 2027; the Commission's ten questions (Order No. 14, Oct 29 2026) — among them whether the Big Island contract is enforceable before the PPA is approved — due Nov 9 2026. The batteries' certificates filed Oct 29 2026, decision targeted Apr 2027. The Big Island PPA denied Sep 16 2026, rehearing granted Oct 22 2026 for further consideration (Staff and Attorney General responses proposed for Nov 20). Cypress Solar under construction, expected in service by the end of 2028 (2029 in one Entergy list)
Structure
one special rate contract under Arkansas's promotional-practice rules — an Agreement for Electric Service between Entergy Arkansas, LLC and Altitude Capital, LLC, a subsidiary of Alphabet Inc. ('Google' in the filings), dated Jul 25 2025 and amended and restated Oct 7 2026 — with, attached to the amendment, the Big Island Solar Clean Energy Attributes Purchase and Sales Agreement (Exhibit K, a final draft in the public copy; executed Oct 7 2026, per Entergy), under which Google buys the clean-energy credits of Entergy's Big Island PPA, and a non-binding term sheet (Exhibit I) for matching the rest of its load with clean-energy attributes; Alphabet guarantees the payments under two parent guaranties. What Google pays for are Entergy-owned system resources that serve all its customers — Cypress Solar, the Driver and Jones Mill batteries, the transmission; the plant was certified in Mar 2026 (25-054-U), the batteries' certificates are sought in 26-073-U, and the Big Island PPA is Entergy's, with Big Island Solar 1, LLC, awaiting approval on rehearing (26-003-U)
Programme
Time-to-power
Parties
Google customer — Altitude Capital, LLC, a subsidiary of Alphabet Inc. ('Google' in the filings), which takes the power for its West Memphis data center and the clean-energy credits of the plants it pays for; Alphabet guarantees its payments · Entergy Arkansas utility — builds, owns and runs Cypress Solar (certified Mar 2026) and the transmission, and, if certified, the two batteries, as resources for all its customers; recovers Cypress's construction financing through the GAJA rider and asks to move the plant, the batteries and Google's revenues into its formula rate plan; buys Big Island's output under the PPA, if approved, and sells Google its credits
Record
disclosed / primary source · as of Nov 2026

Flows 2 as the record states them

  • Entergy Arkansas → Googlepowerelectric service to the West Memphis campus for 20 years — Google buying all its power there from Entergy, with limited exceptions — up to a maximum demand the filings redact (600 MW at full ramp in Oct 2029 under the original contract, by the press's account of a staff memo; the amendment adds 250 MW on a faster ramp), served from Entergy's system with the 600 MW Cypress solar plant and its 350 MW battery and, under the amendment, the 250 MW Driver and 100 MW Jones Mill batteries, and from market purchases until they are in; with the clean-energy credits of Cypress Solar and, if its PPA is approved, of the 440 MW Big Island plant
  • Google → Entergy Arkansaspower-paymentsminimum fixed and variable demand charges each month whatever it uses, on a redacted share of its maximum demand, set to recover the Cypress plant's and, under the amendment, the two batteries' revenue requirements and a share of Entergy's existing costs, trued up for overruns (caps at 125% and 130% of the estimates) and tax-credit shortfalls; $443M of accelerated payments scheduled over 2025–2029 and $83M of minimum demand payments, both deferred from the ramp period, and, under the amendment, further accelerated payments toward the batteries; contributions in aid of construction for 100% of the transmission and for the batteries' construction financing; the market capacity and energy bought to serve it until the new resources are in; if its PPA is approved, Big Island's cost plus an adder less the market value of its output, for the term; a termination payment, guaranteed by Alphabet

Resolved figures 16 each with the verbatim line from its document

  • announced
    first public on Sep 5 2025. The docket opened on Aug 15 with a motion for a protective order whose cover sheet names no customer; on Sep 5 Entergy Arkansas filed its redacted application to the Arkansas Public Service Commission for 'a long-term special rate contract between Altitude, LLC (“Customer” or for purposes of this filing, “Google”), a subsidiary of Alphabet, Inc.' (Docket 25-055-P; an errata of Sep 9 restates it in full, for a slip on its first page), and the same day its Cypress Solar testimony named the customer as 'Altitude Capital, LLC, a subsidiary of Alphabet, Inc. (“Customer” or for purposes of this filing, “Google”)' (Docket 25-054-U). Google confirmed it was behind the campus days later — 'In partnership with Entergy, our electricity utility provider, Google will cover the full energy costs associated with powering this facility', its statement as DCD reported it on Sep 9 — and the two companies announced the contract on Oct 2 2025 beside Google's '$4 billion investment in Arkansas through 2027'. The second phase was announced and filed on Oct 19 2026
    “Attached please find an errata filing for Entergy Arkansas, LLC’s (EAL) Application for Approval to Enter into a Special Rate Contract and for all Other Related Approvals filed on September 5, 2025 (Application).”
    Entergy Arkansas errata to its application, Docket 25-055-P (Sep 9 2025) · apps.apsc.arkansas.gov
  • parties
    the paper: an Agreement for Electric Service between Entergy Arkansas, LLC and Altitude Capital, LLC — 'a subsidiary of Alphabet Inc. (Google)' in Entergy's 10-Q, 'Altitude, LLC' in the first application, 'Attitude Capital, LLC' in Order No. 9 — dated Jul 25 2025, amended and restated by an agreement dated Oct 7 2026 'focused primarily on providing an increase in overall maximum demand and an acceleration of the original pace at which Google can ramp up its load to its maximum demand' (Palmer). Both contracts are filed under seal — 'PAGES 1 - 212 HAVE BEEN REMOVED' from the public copy of the amendment, whose last pages carry the Big Island exhibit — except one page of the original that Entergy refiled unredacted on Oct 15 2026, its 'Contribution Milestone Payment Schedule' (accelerated-payments); Exhibit KRD-1 sums up the key terms in public, and Google asked that the amendment and 'the CIAC and milestone payment amounts' be kept highly sensitive
    “Entergy Arkansas, LLC (“EAL”) and Altitude Capital, LLC (“Customer;” together with EAL, each a “Party”) have entered into an Agreement for Electric Service dated July 25, 2025 (the “Original ESA”) that was amended and restated by an Amended and Restated Agreement for Electric Service dated October 7, 2026”
    Exhibit KRD-1 to Dalrymple's amended and restated direct testimony, Docket 25-055-P (Oct 19 2026) · apps.apsc.arkansas.gov
  • approval
    the original contract approved without modification on Dec 4 2025 (Order No. 9), after a public hearing on Nov 17 2025, the order noting that 'the entire Agreement and vast portions of the record in this Docket have been redacted by EAL'. The same order rejected the amortization Entergy proposed for Google's early payments (accelerated-payments) and deferred a ruling on the plant's tax credits; on rehearing in January 2026 (Order No. 11) the Commission set the payments' amortization to the plant's life, let the credits be used in Google's pricing, and recommended that a special contract resting on a shared resource disclose the total cost of the facilities, the total and nature of the customer's contributions, the whole ratemaking with its inputs, the term and any opt-out. The amendment says it follows them where it can, and asks a waiver for what Google wants kept sealed — the amended contract, 'the CIAC and milestone payment amounts' and the rate model's inputs
    “By this Order, the Arkansas Public Service Commission (Commission) approves, without modification, as being consistent with the public interest, the Agreement for Electric Service (Agreement or SRC) between Entergy Arkansas, LLC (EAL or the Company), and Attitude Capital, LLC (for purposes of this filing, Google)”
    Arkansas PSC Order No. 9, Docket 25-055-P (Dec 4 2025) · apps.apsc.arkansas.gov
  • amendment
    the amendment, filed Oct 19 2026 and not in effect until approved ('The effectiveness of the Amended Agreement is subject to Arkansas Public Service Commission approval', KRD-1). Entergy asked for a ruling by Jan 15 2027 — the statute gives the Commission 90 days — 'in order for Google to have the assurance it requires to proceed with selection of the Arkansas site'; the hearing is set for Jan 4 2027, staff and intervenor testimony due Nov 16 2026 (Order No. 13). On Oct 29 the Commission put ten numbered questions to Entergy, answers due Nov 9 (Order No. 14), among them how the filing meets Order No. 11's disclosure recommendations, whether this is the docket to move Cypress Solar into the formula rate plan, whether the Big Island contract (Exhibit K) is enforceable before the PPA is approved, and what the RIM test shows without the two batteries. Entergy's Q3 release lists it as 'an expansion of its service agreement with Google' (furnished)
    “Therefore, in order for Google to have the assurance it requires to proceed with selection of the Arkansas site, EAL respectfully requests that the Commission issue a ruling on this Application by Friday, January 15, 2027.”
    Entergy Arkansas amended and restated application, Docket 25-055-P (Oct 19 2026) · apps.apsc.arkansas.gov
  • term20 years
    20 years. Entergy's application puts the amended term at Feb 1 2027 to Feb 1 2047 unless Google extends it, Palmer adding that 'These dates could move back slightly depending upon the construction of the resources needed to begin serving Google'; Exhibit KRD-1 counts it from the earlier of Jun 1 2027 and the Galet substation's in-service date (contested term-start). It renews itself in 5-year terms unless either party gives 3 years' notice (contested renewal). Google 'is required to purchase all of its electric energy needs from EAL, with limited stated exceptions' (KRD-1)
    “The Amended Agreement has a term of 20 years, beginning February 1, 2027, and ending February 1, 2047”
    Palmer, amended and restated direct testimony, Docket 25-055-P (Oct 19 2026) · apps.apsc.arkansas.gov
  • expansion-load250 MW
    the amendment's added load: 'the Customer’s expanded 250 MW load' (Entergy's Cullipher, in the batteries' docket, where 'Customer' is Google) — the only figure for the contract's load in a filing. MISO's list of expedited requests for April 2026 carries 'Galet 230kV: Expand Substation', Entergy Arkansas's, at a load value of 250 MW, under study. The amended testimony's public copy blanks the old and the new maximum demand and the months to full load, saying only that Google 'will be ramping faster than the ramp reflected in the Original Agreement' (Dalrymple), and the release says the expansion 'will fulfill Google’s plan for data center buildings on the site'. With the original's 600 MW as the press reported it (original-demand), the campus would come to about 850 MW — our arithmetic, which reads the 250 MW as an addition
    “This ability to interconnect using existing infrastructure is a key factor that enables the Driver BESS to meet the schedule associated with serving the Customer’s expanded 250 MW load.”
    Cullipher, direct testimony, Docket 26-073-U (Oct 29 2026) · apps.apsc.arkansas.gov
  • cypress600 MW
    Arkansas Cypress Solar: a 600 MW (AC) solar plant with a 350 MW four-hour battery (408 MW installed in its first year) and its transmission, interconnecting at Entergy's White Bluff substation in Jefferson County — Entergy-owned and a resource for all its customers, approved with cost recovery through the Generating Arkansas Jobs Act (GAJA) rider in March 2026 and expected to be in service by the end of 2028 (contested cypress-in-service). Its estimated cost is $1,602M — in Palmer's words '$1.6 billion (but as I explained above, $1.8 billion was included in the calculation of the Google rates because it includes AFUDC)', the financing cost during construction; $1.8B is the contract's 'Estimated Cypress Cost', against which Google's rates absorb overruns 'up to 125% of the Estimated Cypress Costs (approximately $450 million above the Estimated Cypress Costs)' and tax-credit shortfalls (minimum-bill). Google 'will receive the benefit of the clean energy attributes associated with Cypress Solar' (Hunt), while the plant 'is being added to EAL’s resource portfolio to provide service to all customers, including Google'
    “Entergy Arkansas filed an application with the APSC seeking a certificate of environmental compatibility and public need for the construction and operation of the Arkansas Cypress Solar facility, a planned 600 MW solar photovoltaic array with a 350 MW battery energy storage system and associated transmission facilities interconnecting at Entergy Arkansas’s White Bluff substation.”
    Entergy / Entergy Arkansas 10-Q for Q3 2026 (Nov 2 2026) · sec.gov
  • minimum-bill
    a minimum monthly demand charge Google owes whatever it uses: 'monthly minimum fixed and variable demand charges calculated based upon a percentage of maximum demand capacity at a rate to cover the amount of capital expended by EAL for the Generation/Capacity Facilities and an allocated portion of existing and future embedded resources and EAL’s return on capital' (KRD-1); when its actual demand charges are higher, Google pays those. The percentage, the fixed demand charge per kilowatt-month (raised by the amendment) and the variable charge are redacted; Google told legislators on Sep 15 2026 that it pays 80% of its contracted demand in minimum bills whatever it uses (an unofficial machine transcript), and the staff memo's ramp as the press reported it (40 MW of 50, then 480 of 600) is 80% too (original-demand). True-ups: Google's rates rise for Cypress overruns up to 125% of its $1.8B estimate and for the batteries' up to 130% of theirs ($116.9M and $48.4M above), any excess on the batteries negotiated; for 100% of any shortfall in the batteries' tax credits; and for Cypress's — 100% up to its unused overrun room, 60% beyond — with 60% of any Cypress surplus credited back. Until the new resources are in service, Google also pays for the market capacity and energy Entergy buys to serve it, 'to, at a minimum, keep EAL and its broader customer base whole' (Dalrymple). Whether all this covers Google's cost is Entergy's RIM test (customer-benefit)
    “monthly minimum fixed and variable demand charges calculated based upon a percentage of maximum demand capacity at a rate to cover the amount of capital expended by EAL for the Generation/Capacity Facilities and an allocated portion of existing and future embedded resources and EAL’s return on capital (the “Minimum Demand Charge”)”
    Exhibit KRD-1 (Dalrymple, amended and restated direct, Docket 25-055-P, Oct 19 2026) · apps.apsc.arkansas.gov
  • accelerated-payments$443M
    $443M of accelerated payments and $83M of minimum demand payments, which Entergy asked to defer to a regulatory liability and recognize later, 'over the term of the Agreement' (the application; the amounts unredacted on Oct 16 2026). The $443M is the contract's own 'Contribution Milestone Payment Schedule', whose page Entergy refiled unredacted on Oct 15 2026 (an image that is not included in the text on file; BUILD-EXCERPTS): Google's cash contributions toward accelerating the solar plant, $10M in 2025, $103M in 2026, $145M in 2027, $120M in 2028 and $65M in 2029. Entergy books both as payments for electric service during Google's ramp — 'included in the minimum bill beginning in 2025 and continuing during Google’s ramp period' (Hunt's original testimony, unredacted Oct 15 2026), above what Google's rate class would pay — not a contribution in aid of construction (CIAC), which would lower the plant's cost in rates. The Commission found them 'difficult to distinguish from CIAC' but let them stand as another form of payment if they met Act 373, which counts such payments only 'in a manner that provides comparable benefits for other customers over the life of the strategic investments': Order No. 9 rejected Entergy's version, a liability 'amortized over a period of time significantly shorter than the life of Cypress Solar', and Order No. 11 (Jan 29 2026) denied its schedule 'in favor of a schedule that is consistent with the life of the Cypress Solar assets', which Entergy filed on Feb 5. The amendment keeps that treatment — 'consistent with treatment the Commission approved for the Original Agreement' (Hunt) — asks to begin the amortization in 2032, and extends it to Google's new contributions toward the two batteries. The APSC's own comparison of the two treatments for legislators (Oct 19 2026) puts the difference at −$518,588,126 over 34 years (−$308,462,531 in present value), its text not saying which is subtracted from which. What the $526M total means is contested (google-payments)
    “Approval to defer $443 million in accelerated payments and $83 million in minimum demand payments to a regulatory liability and amortize these revenues over the term of the Agreement as specified in paragraph 4 below;”
    Entergy Arkansas application, Docket 25-055-P (Sep 2025), p. 6 as refiled Oct 16 2026 · apps.apsc.arkansas.gov
  • transmission100%
    100% of the transmission that connects the campus, paid by Google as contributions in aid of construction 'projected to equal the Estimated Transmission Cost and are timed to precede EAL’s expenditure of funds' (KRD-1), with overruns paid up to 130% of each estimate, any excess negotiated and any saving credited back. Under the original contract the upgrades include a new substation, Galet, near West Memphis — 'Construct a new 500/230kV substation to serve a new customer on the West Memphis - Heth 500kV line' (MISO's 2024 plan, which ranks it among its ten costliest local projects at $142M) — projected in service Jul 31 2027 (KRD-1); under the amendment, the expansion of its 230 kV yard 'with additional breakers' and 'two new 230 kV lines to interconnect the Customer’s additional data center buildings' (Dalrymple), projected for Jun 1 2028 and priced by a Class 5 facility study filed under seal. The amounts are redacted. $190M for the original upgrades comes from the APSC records the Arkansas Democrat-Gazette obtained ('an additional $190 million to Entergy for transmission system upgrades'), and Google's own letter repeats it ('$190 Million: Direct funding for necessary regional transmission and grid upgrades')
    “CIAC for 100 percent of the costs of the incremental transmission facilities needed to serve the Project;”
    Dalrymple, amended and restated direct testimony, Docket 25-055-P (Oct 19 2026) · apps.apsc.arkansas.gov
  • expansion-investment$600M
    about $600M of planned investment, plus the Big Island PPA, 'both of which will be covered by Google' (the release): the two batteries ($550.6M) and the Galet substation's expansion with two 230 kV lines, whose own cost is redacted. The $550.6M (Docket 26-073-U) and Latitude Media's 'about $550 million' are the batteries alone, a part of the ~$600M, not rival totals. The release: 'The project will fulfill Google’s plan for data center buildings on the site and accelerate the ramp-up of the original announced project'; 'Google is paying for this project under a new contract'; the new resources 'will not be charged through the Generating Arkansas Jobs Act Rider'; and 'Pending approval, the expansion project’s expected in-service date is in 2028'
    “The system resource upgrades will benefit all Entergy Arkansas customers and require approximately $600 million in planned investment and a power purchase agreement, both of which will be covered by Google, including:”
    Entergy Arkansas release (Oct 19 2026) · entergy.com
  • batteries$550.6M
    two four-hour batteries added by the amendment, to be Entergy-owned system resources, picked in its 2025 requests for proposals and expected in service Jun 1 2028: Driver BESS, 250 MW and 1,000 MWh, at the existing Driver Solar plant near Osceola in Mississippi County, and Jones Mill BESS, 100 MW and 400 MWh, beside the Arklahoma substation near the Ironwood plant under construction in Hot Spring County. $550.6M together ($389.4M + $161.2M, in the 10-Q and Dalrymple too; development costs and asset-retirement obligations included, per the certificate application); the contract summary's estimates differ slightly (battery-split). Google prepays their construction financing (AFUDC) through contributions in aid of construction, makes further accelerated payments toward them, and its minimum demand charge is set to cover their revenue requirement, assumes a 40% federal tax credit on each and rises by 100% of any shortfall; overruns pass to Google up to 130% of each estimate ($116.9M and $48.4M above). If the batteries slip past Nov 30 2028, Google's minimum demand charges fall to the demand Entergy can deliver; from Jun 1 2029 Entergy commits to deliver the full contract demand, counting on its White Bluff Unit 1's conversion to gas (828 MW, pending approval). Entergy asks to put them in its formula rate plan, Google's revenues offsetting them, and values them at $561M of net capacity and energy benefits to other customers before Google's support; certificates applied for Oct 29 2026 (Docket 26-073-U), decision targeted April 2027
    “The total combined cost of the Projects is estimated to be $550.6 million ($389.4. million for Driver BESS and $161.2 million for the Jones Mill BESS).”
    Entergy Arkansas application for the batteries' certificates, Docket 26-073-U (Oct 29 2026) · apps.apsc.arkansas.gov
  • big-island440 MW
    the Big Island PPA: Entergy's 20-year purchase, executed Dec 18 2025, of the output of a 440 MW (AC) solar plant Pattern Energy is developing outside Wilson in Mississippi County (seller Big Island Solar 1, LLC), with delivery to begin no later than Dec 31 2028 (Exhibit K). The Commission denied it on Sep 16 2026 (Order No. 6): Entergy 'has not substantiated that the instant PPA provides net benefits to customers', which Entergy had put at $29–$214M; Entergy says the amendment added it 'based on Arkansas Public Service Commission guidance from the initial filing of the resource' (the release). Under the credits agreement the two executed on Oct 7 2026 (Exhibit K to the amendment, a final draft in the public copy), Google buys the plant's clean-energy credits for the term at 'the PPA price in the Big Island PPA in $ per MWh plus an adder', less each month's market value of the plant's energy and accredited capacity — so Google, in Entergy's words, 'will pay 100 percent of the cost of the Big Island Solar PPA during the term of the Amended Agreement' (Dalrymple), and bears 'the risk that market revenues will not exceed the cost of the PPA' (Order No. 7, summarizing Entergy's petition). On Oct 22 the Commission granted rehearing 'solely for the purpose of further consideration', struck the contract Entergy had attached to its petition and told it to refile; the parties proposed Staff and Attorney General responses by Nov 20 and Entergy's reply by Dec 2 2026. The PPA price is redacted, and Order No. 14 asks whether Exhibit K is enforceable before the PPA is approved
    “EAL witness Dalrymple testifies that on December 18, 2025, EAL executed a PPA for a 440 MW solar energy resource to be constructed at an approximately 3,200-acre greenfield site in Mississippi County, Arkansas, with Big Island Solar 1, LLC.”
    Arkansas PSC Order No. 6, Docket 26-003-U (Sep 16 2026) · apps.apsc.arkansas.gov
  • termination2
    a termination payment 'designed to recover the remaining amounts attributable to the Generation/Capacity Facility costs that are not recovered from Minimum Demand Charges' (KRD-1), based on 'the net present value of the years of minimum bill demand charges remaining at the time of termination' (Dalrymple; the number of years redacted) — higher under the amendment, its maximum redacted — and, new in the amendment, 'an immediate payment equal to two years of minimum bill charges even if the payment is made under protest', which the testimony does not say is on top of the fee or toward it. If the contract ends before approval or before the Galet substation is in service, Google owes at least what Entergy has spent on the plants and the transmission; it is excused only by an extended delay of Galet or the plants through Entergy's fault, or 24 consecutive months without service. Security: two Alphabet guaranties, one for the transmission contributions and one for the rest, part of which must become cash or a letter of credit if Alphabet's rating falls (on a stricter schedule than before); a billing deposit of four months' estimated bills, up from two; and insurance against Alphabet's non-payment worth the next twelve months of minimum demand charges, at Google's expense. No filing states an amount: 'a termination fee of about $2 billion' for the first 13 years, declining after, is the staff memo's as the press reported it, and Google's letter repeats 'a declining $2 billion termination penalty'
    “In addition, the Amended Agreement requires the Customer, upon early termination or default, to make an immediate payment equal to two years of minimum bill charges even if the payment is made under protest.”
    Dalrymple, amended and restated direct testimony, Docket 25-055-P (Oct 19 2026) · apps.apsc.arkansas.gov
  • construction-financing$1.76
    who pays while the plant is built, before Google takes service in 2027: the GAJA rider all customers pay carries Cypress Solar's construction financing — 'approximately $1.76 of the $5.77 GAJA Rider is currently associated with Arkansas Cypress Solar' for a residential customer using 1,000 kWh, the rest mostly Jefferson Power Station and Ironwood Power Station (Entergy Arkansas) — and in 2026 'customers see about $33 million in financing costs for EAL’s construction activity, which is about $400 million in that same period' (Palmer). Entergy's answer is that Google 'will ultimately pay the cost of Arkansas Cypress Solar over the life of its contract'; the amendment asks to move the plant out of the rider and into the formula rate plan, where Google's revenues are counted, once it is in service, and keeps the new batteries out of the rider altogether, Google prepaying their financing (Palmer). Residential customers began paying the $5.77 in June 2026, for three new plants, Cypress among them (the Arkansas Democrat-Gazette)
    “For a residential customer using 1,000 kWh, approximately $1.76 of the $5.77 GAJA Rider is currently associated with Arkansas Cypress Solar.”
    Entergy Arkansas, Generating Arkansas Jobs Act facts (entergyarkansas.com/GeneratingARjobs) · entergyarkansas.com
  • load-flexibility
    part of Google's load can be cut first: under the original contract, 'for a specified period before EAL completes construction of planned resources, the Agreement affords flexibility to treat a portion of the load of the Project as curtailable before other firm load is curtailed' (Order No. 9, summarizing Dalrymple) — the 'EEA-2 curtailment provision' in the amendment's words — which Google described to legislators on Sep 15 2026 as demand response of up to 10 hours an event and over 100 hours a year (an unofficial machine transcript; the filings give no hours). New in the amendment: registration of part of its load as a MISO load-modifying resource from planning year 2028/2029 and other mechanisms whose details are redacted, Google bearing 'full financial responsibility for any penalties, non-performance charges, or other cost consequences' of failing to perform. Entergy calls them a bridge 'over the initial few years of the contract term (until the incremental resources needed to serve the load come online)', which it needs with the new batteries 'to commit to firm service for Google' at the expanded level (Dalrymple)
    “In addition to the EEA-2 curtailment provision that existed under the Original Agreement, the Amended Agreement enhances protections for all other EAL customers by adding new load flexibility mechanisms.”
    Dalrymple, amended and restated direct testimony, Docket 25-055-P (Oct 19 2026) · apps.apsc.arkansas.gov

Contested figures 18 not reconciled — every position side by side, with its source and tier

term-start2 positions, side by side
Feb 1 2027 to Feb 1 2047 — Palmer: the amended agreement 'has a term of 20 years, beginning February 1, 2027, and ending February 1, 2047', dates that 'could move back slightly'; the application's promotional-practice table gives 'Beginning Date: February 1, 2027' and 'End Date: February 1, 2047' Palmer amended direct; amended application, Exhibit B (Oct 19 2026)
the earlier of Jun 1 2027 and the Galet substation's in-service date — Exhibit KRD-1: 'The initial term of the Amended Agreement is 20 years from the earlier of June 1, 2027, and the in-service date for the Galet Substation'. The two agree only if Galet is in service on Feb 1 2027; KRD-1 projects the original transmission upgrades, Galet among them, for Jul 31 2027, which would start the term on Jun 1 2027 (our reading) Exhibit KRD-1 (Oct 19 2026)
renewal2 positions, side by side
successive 5-year terms — the amendment 'will automatically renew for successive 5-year terms until one Party provides 3 years advance notice of its intent not to renew' (KRD-1) Exhibit KRD-1 (Oct 19 2026)
successive three-year terms — the original contract, per the staff memo as the Arkansas Democrat-Gazette reported it: 'an initial term of 20 years that will automatically renew for successive three-year terms until either party provides notice of termination or non-renewal'. Either the amendment lengthened the renewals or the memo's three years is the notice period; the original contract is sealed, so the documents on file do not settle which Arkansas Democrat-Gazette (Aug 31 2026)
original-demand2 positions, side by side
600 MW at full ramp — the staff memo as the press reported it: from February 2027 'the initial minimum bill demand will be 40 megawatts with a maximum contract demand of 50 megawatts', ramping over two and a half years 'to a minimum bill demand of 480 megawatts with a maximum contract demand of 600 megawatts', at full capacity by October 2029; minimum bills at 80% of the maximum match Google's own account (minimum-bill) Arkansas Democrat-Gazette (Aug 31 2026), from the APSC staff's prehearing memo
not stated in any filing — the original contract and the testimony on it are sealed on load, and the amendment's public testimony blanks both the old maximum demand and the new; the only filed figure for the contract's load is the amendment's added 250 MW (expansion-load) Dalrymple amended direct (Oct 19 2026); Order No. 9
google-payments4 positions, side by side
$526M toward a $1.6B plant — the APSC's own slides to the legislature's Joint Energy Committee (Oct 19 2026): 'Total Plant Cost: $1.6B' and 'Customer Contributions: $526M', from 'numbers provided to us in official regulatory filings' APSC slides to the Joint Energy Committee (Oct 19 2026)
$526M up front, about a third of the plant — the Arkansas Democrat-Gazette, from APSC records released under the state's records law: 'Google will pay Entergy Arkansas $526 million up front to build Cypress Solar, about one-third of the $1.6 billion price tag of the solar and battery facility', and a staff question for the hearing: 'Help me understand why Entergy said that Google will pay rates that cover the cost of this resource when in actuality, Google is paying well below the full cost of this resource?' The contract's own schedule spreads the $443M over 2025–2029 (accelerated-payments) Arkansas Democrat-Gazette (Aug 31 2026, updated Sep 3)
about $2.103B over 20 years — Entergy Arkansas (Sep 2 2026): 'Using the figures published in the article — $443 million plus $83 million minimum annually over 20 years — the total would be approximately $2.103 billion, not the amount reported'; its chief executive's letter to customers the next day repeats it, and Google's Arkansas public-affairs manager, in a letter the Little Rock Regional Chamber published: '$443 million + ($83 million × 20 years) = $2.103 billion', the $526M being 'our upfront contribution with just a single year of our annual payments'. No filing on file says the $83M is annual Entergy Arkansas statement (Sep 2 2026) and CEO letter (Sep 3 2026); Google letter (Little Rock Regional Chamber)
two amounts, both from the ramp period — what the filings show: Entergy asked to defer '$443 million in accelerated payments and $83 million in minimum demand payments' (the application, as refiled Oct 16 2026), revenues to be held back 'during Google’s ramp period' (Stack) — the $443M on the contract's schedule of $10M (2025) to $65M (2029) — and Order No. 9 says such prepayments 'appear to be associated with, and based on, monthly minimum demand charges and other rate charges for electric service'. No filing says the $83M recurs, and what Google's minimum bills come to after the ramp is redacted Entergy Arkansas application, p. 6 (refiled Oct 16 2026); Stack direct (Sep 2025); contract Table 3 (refiled Oct 15 2026); Order No. 9 (Dec 4 2025)
customer-benefit4 positions, side by side
$2.1B — the release: Google's payment of 'the full cost for the power resources it needs' under the original and updated agreement 'results in $2.1 billion in net benefits to help cover the fixed costs that all customers share', made of 'the previously announced $1.6 billion identified in Entergy’s Fair Share Plus pledge from the first phase' and 'at least $500 million in new customer savings starting in 2028 and extending over 20 years'; Palmer: 'at its expected service level, generating approximately $2.1 billion in cost savings to the benefit of all other customers' Entergy Arkansas release (Oct 19 2026); Palmer amended direct
about $2.5B in present value — Entergy's RIM test, base case (expected demand, tax credits realized): 'a RIM Test net present value benefit to all other EAL customers of $2.5 billion and a RIM benefit cost ratio of 1.54' (Elbe; $2,456,819 thousand in the corrected public exhibit, discounted at 5.76%); the application: 'net benefits ranging from an net-present value of $360 thousand to $2.5 billion' (sic), the ratio 1.07 to 1.54 over five scenarios — 1.39 without the tax credits, 1.30 and 1.16 with Google at its minimum demand with and without them, 1.07 at minimum demand without them and with Entergy's embedded costs in place of a new combustion turbine's. The $360 thousand cannot be squared with a 1.07 ratio on costs of billions, which implies hundreds of millions (our arithmetic; that case's exhibit is sealed), and the filings do not say which case gives the $2.1B Elbe amended direct + corrected Exhibit CKE-3 (Oct 19–20 2026); amended application
$1.1B — the first phase as filed: 'a net benefit of $1.1 billion and a positive Ratepayer Impact Measure benefit cost ratio of 1.31' (the original application), which Order No. 9 recites ('The Application states that the Project has $1.1 billion in net benefits subject to the achievement of certain milestones') and Entergy and Google repeated through September 2026 (Entergy's Oct 2 2025 release: 'over $1.1 billion in net benefits over the life of the contract'). The same application's promotional-practice table gives the ratio as 1.06; no document on file explains the difference, or announces the $1.6B the October release calls 'previously announced' original application (Sep 2025, errata Sep 9); Order No. 9; Entergy Arkansas release (Oct 2 2025)
$2.1B for the first phase alone, or up to $1.7B with another project — Entergy's Google fact sheet, uploaded in March 2026 and describing only the Jefferson County plant: Google's payments 'will produce at least $2.1 billion in net customer savings over the life of the contract'; Entergy's Mar 5 2026 release: 'up to $1.7 billion in savings for its customers thanks to the newly announced Google and Avaio data center projects', two campuses together Entergy Google fact sheet (2026/03 upload); Entergy release (Mar 5 2026)
cypress-in-service2 positions, side by side
by the end of 2028 — the 10-Q ('The facility is expected to be in service by the end of 2028') and the amendment's projected date, 'Cypress Solar and Storage Facility: December 31, 2028' (KRD-1) Entergy 10-Q for Q3 2026; Exhibit KRD-1
2029 (targeted) — Entergy's list of 'renewable generation projects in service or in development as of October 2026' gives Arkansas Cypress Solar (+ Battery) a 'Commercial Operation Date/ Start of Delivery Term' of 2029 (targeted); nothing on file explains the year Entergy renewable portfolio list (Oct 2026)
battery-split2 positions, side by side
$389.4M (Driver) and $161.2M (Jones Mill), $550.6M together — the certificate application, the 10-Q, Dalrymple and Palmer; Entergy's fact sheet rounds them to $389M and $161M 'including associated interconnection facilities' Docket 26-073-U application; Entergy 10-Q for Q3 2026; amended testimony; Entergy battery fact sheet
$389.6M (Driver) and $161M (Jones Mill) — the contract's 'Estimated Driver Cost' and 'Estimated Jones Mill Cost' (KRD-1), the baselines Google's overrun caps run from. The caps it states, $116.9M and $48.4M above, are 30% of $389.6M and of $161.2M (our arithmetic), so the $161M looks rounded, while Driver's $0.2M gap is in the contract's own estimate; no filing explains it Exhibit KRD-1 (Oct 19 2026)

Scope note what this record leaves to other records

Not this record: Steel River, Cypress Creek Energy's solar-and-storage project in northeast Arkansas — 2.5 GWdc of solar and 2.9 GWh of storage 'once fully complete', Google buying the energy of its first two phases, 1.6 GWdc and 1.9 GWh, under a PPA with Cypress Creek — which Entergy's release counts 'in addition to' its own resources, 'an arrangement between Google and Cypress Creek Energy'; the campus itself (Groot LLC's air permit, the city's 30-year tax agreement, jobs, the 1,178-acre site) and Google's '$4 billion investment in Arkansas through 2027', which covers more than the campus; Google's $25M Energy Impact Fund for Crittenden County and the first $1.25M it distributed, and its $5M of Steel River affordability initiatives; Entergy's company-wide Fair Share Plus totals; Entergy Arkansas's bonds, backlog and customer counts; Entergy's federal suit to stop the newspapers using the records the PSC released under the state's records law, in which the judge denied a restraining order (WREG). Not adopted: the release's 'over 1,000 megawatts of solar' is Cypress's 600 plus Big Island's 440, and its 2,800 megawatt-hours of batteries are Cypress's 1,400 plus Driver's 1,000 and Jones Mill's 400 — the two new batteries' 1,400 MWh coincide with Cypress's own; a Google executive's post gave Cypress's battery as 250 MW (every filing says 350 MW); KTLO's report, reprinted by now.solar, calls Big Island 'the nation's largest' solar farm (Cypress Creek's label for Steel River); a '$60 billion' bond headline linked from Entergy's Arkansas page, with no instrument on file; the Little Rock Regional Chamber dates Google's letter Jun 1 2026, months before the Aug 31 story it answers. The batteries' application gives Jones Mill two sizes. Its paragraph 2 asks for 'a 100 MW BESS', as do its Exhibit D and the testimony of Bradley Phillips of Alliance Technical Group, the firm that prepared its environmental impact statements. Jones Mill's statement (Exhibit F) calls it 'a 250 MW, four-hour, storage resource', Driver's size, in the sentence Driver's statement uses. The record follows paragraph 2: none of the documents read explains the 250 MW, and the docket had no staff testimony or order by Nov 22 2026.

More between Google and Entergy Arkansas

The record holds no other deal between them.