Lambda

A California 'neocloud' that buys Nvidia GPUs, installs them in leased data-center space and rents the computing time out, borrowing against the chips and its customers' contracts to pay for them; Nvidia is one of its investors.

6 deals (6 T1) · 5 flows on the money map ·

Deals 6

sort: · · ·
  1. by Oct 1, 2026 updated Nov 18
  2. Aug 31, 2026 updated Nov 19
  3. Aug 10, 2026 updated Nov 21
  4. May 6, 2026 updated Nov 19
  5. Nov 3, 2025 updated Nov 19
  6. Jun 21, 2024 updated Nov 18

Money in and out 5 ribbons

Who pays Lambda (left), and whom it pays (right). Width is a rough size in $B, per year for multi-year deals.

← swipe to see the whole chart →

sourced deal · 5 of 5 full amount, no yearly rate · 1 of 5

As a table · 5 ribbons
Timeline 8 dated entries
  1. Nov 2026Anthropic's S-1/A of Nov 10 (and its 424B4 of Nov 19) says Lambda did not secure the facility lease by the date set, so the ~$34.9B August agreement is terminable by either party; neither has given notice and Anthropic does not currently intend to terminate (T1) — anth-lambda
  2. Oct 2026Anthropic's S-1 (Oct 26) describes the Lambda Agreements of May, June and August 2026: ~$41.3B for compute on Nvidia GPUs over terms into 2034, fees only as capacity is delivered and accepted; ~$34.9B of it the August agreement, which either party may end if Lambda does not timely secure the facility lease; no site, MW or GPU count named (T1) — anth-lambda
  3. Oct 2026$1.008B fixed-rate delayed-draw term loan closed Oct 1: 6.78%, final maturity May 30 2033, A (low) from DBRS and Baa1 from Moody's per Lambda, for three deployments with two investment-grade offtakers, unnamed (T1 release); DBRS: more than 30,000 Nvidia GB300 and VR200 GPUs in Seattle, Kansas City and Dallas, and a parent it calls 'non-investment-grade' (T1) — lam-ddtl-2026 · WSJ via TechCrunch (Oct 6): raising up to $4B at a $14.5B pre-money valuation before a planned 2027 IPO (T2)
  4. Aug 2026Anthropic ~$35B compute agreement at Hut 8's Beacon Point reported (WSJ Aug 31; Reuters and Bloomberg one source each on the $35B; the six-year term is AFP's single source; T2; no party confirmed it then — Anthropic's S-1 of Oct 26 later described an August agreement with Lambda, naming no site, anth-lambda) — see nv-hut8-beacon-point · $926M senior secured term loan B closed Aug 27 (SOFR + 3.00%, 99.5) for GPUs 'supporting a committed customer deployment with an investment-grade offtaker' — unnamed (T1 release) — lam-tlb-2026 · Bloomberg (Aug 28): about $1B of 'private short-dated debt' for chips Microsoft will lease — possibly the Oct 1 loan (T2; lam-ddtl-2026) · Bloomberg: talks to raise up to $3B at $12B+ (T2)
  5. May 2026$1B senior secured credit facility closed May 7, upsized from the $275M facility of Aug 2025 (T1 release) — distinct from the ~$1B of 'private short-dated debt' Bloomberg reported on Aug 28 2026 (T2)
  6. Nov 2025Microsoft multibillion GB300 agreement (Nov 3 — lam-msft) · Series E >$1.5B led by TWG Global, with USIT participating (Nov 18) (T1 releases)
  7. Aug 2025The last 6 MW of the Vernon space Super Micro sublicenses to it commences Aug 15 — all 21 MW in service, in tranches since Jan 24 (T1, Super Micro's FY2026 10-K) — smci-lambda-vernon
  8. Jun 2024Super Micro leases 21 MW in Vernon, California, for 10 years and sublicenses all of it to Lambda the same day, for the landlord's charges plus a margin, staying liable itself (T1, Super Micro 8-K, Jun 21) — smci-lambda-vernon

Timeline entries carry no source field yet; some name one inline.

Notes in the record on Lambda

Lambda, Inc. Microsoft multibillion GB300 agreement 11/2025 (lam-msft); Series E >$1.5B led by TWG Global (Nov 2025); $1B senior secured credit facility closed May 7 2026 (upsized from $275M — company release); $926M senior secured term loan B closed Aug 27 2026 (priced Aug 12 at SOFR + 3.00%, 99.5; Baa2 from Moody's, per Lambda) for one investment-grade offtaker, unnamed by Lambda — lam-tlb-2026 (the $917M was Bloomberg's launch size, not a second facility); $1.008B fixed-rate delayed-draw term loan closed Oct 1 2026 (6.78%, final maturity May 30 2033; A (low) from DBRS, Baa1 from Moody's per Lambda) for three deployments with two investment-grade offtakers, unnamed — lam-ddtl-2026, whose rating agency calls the parent 'non-investment-grade'; Bloomberg (Aug 25): in talks to raise up to $3B at a $12B+ valuation, IPO reportedly targeted; WSJ via TechCrunch (Oct 6): raising up to $4B at a $14.5B pre-money valuation, led by Coatue and Blackstone, before a planned 2027 IPO (the first in talks, the second under way; neither carried as a mark). Anthropic's S-1 (Oct 26 2026; the figures unchanged through its 424B4 of Nov 19) describes the 'Lambda Agreements' of May, June and August 2026: ~$41.3B over terms into 2034, fees only as capacity is delivered and accepted, ~$34.9B of it the August agreement, which either party could end if Lambda did not secure the facility lease by a set date — and which, since the S-1/A of Nov 10, the filing says Lambda did not, so it is terminable by either party, with no notice given and Anthropic not currently intending to terminate — anth-lambda. REPORTED operator of the Anthropic compute at Hut 8's Beacon Point — see nv-hut8-beacon-point; Lambda has not confirmed it publicly, though TechCrunch's account of the WSJ's October report says much of the backlog growth shown in a Lambda letter to investors 'appears to be driven by' Anthropic's commitment. The Sep-2025 Nvidia–Lambda leaseback, reported at $1.5B for 18,000 servers or GPUs, is one Information report (unit contested) and is not carried; '$1.5B' names three different Lambda quantities on file (Series E, that leaseback, a 2026 revenue projection).