AEP–Google

AEP plans to spend about $4 billion on a 702 plant of Bloom Energy fuel cells near Cheyenne, Wyoming, and sell its power to Google for 20 years; the price is not disclosed.

A deal between Google, AEP, Bloom Energy

Why it matters

AEP plans to invest about $4 billion outside its service territory near Cheyenne for one buyer that agreed to take the output for 20 years. AEP's filings say an unnamed buyer covers AEP's costs if the conditions fail. The price and whether the conditions were met before the December milestone are still undisclosed.

Tap a figure for the line in its source.

AEP gives Google

  • of power for 20 years from a plant of Bloom Energy fuel cells near Cheyenne that AEP develops, builds and owns through Cheyenne Fuel Cell, LLC — fully operational by the end of 2028 by AEP's October release, though a May 2026 investor deck reportedly said no later than 2030
  • the plant AEP plans to invest in, ~92% AEP's and nearly 8% held by funds advised by Basalt Infrastructure Partners; whether the ~$2.65B of fuel cells AEP bought in January is inside it or on top of it, no AEP document says

Google gives AEP

  • payments for the plant's power under the 20-year PPA, at a price neither company discloses
  • a , as AEP's filings describe the plant's unnamed offtaker: AEP to be compensated 'for all capital and costs incurred' if the 's conditions are not met (Jan 2026), and since a June 2026 amendment 'additional consideration' if the revised conditions are not met in December 2026 — whether that offtaker is Google's PPA, AEP does not say

Oct 14, 2026 announced by AEP, naming Google; its Jan 2026 8-K named no customerupdated Nov 19, 2026announced Oct 14 2026 disclosed by the parties

What happened

American Electric Power is building a Bloom Energy fuel-cell plant near Cheyenne, Wyoming, to sell power to Google for 20 years. The utility serves 11 states, and Wyoming is outside its service area. The fuel cells turn natural gas into electricity without burning it. AEP says it plans to invest about $4 billion in the 702-megawatt plant. AEP owns about 92% and funds advised by Basalt Infrastructure Partners own nearly 8%. AEP expects the plant to be fully running by the end of 2028. Plans call for capturing most of its carbon emissions and storing them underground nearby. AEP's filings have described a plant like it since January 2026 but give no customer name. They describe a purchase of about $2.65 billion of fuel cells and a 20-year contract for all the output of a plant near Cheyenne. Under that contract, the unnamed customer covers AEP's costs if the conditions are unmet. The customer asked for more time in June, and the new deadline falls in December 2026. Neither company says what Google pays.

Sources 17 documents — 6 SEC filings · 4 press reports · 3 company releases · 2 other documents · 1 transcript · 1 research note

Research trail Found 59 documents and read 58 of them while checking this deal and related ones.

  1. company releaseaep.com
    States 4 figures: 702 MW capacity · $4B investment · 92% ownership · term
  2. SEC · SEC filingsec.gov
    States 2 figures: $2.65B fuel cell purchase · 100% offtake
  3. company releaseblog.google
    States 2 figures: 702 MW counterparty · technology
  4. SEC · SEC filingsec.gov
    States conditions
  5. Motley Fool · transcriptJul 30, 2026fool.com
    States capital plan
  6. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  7. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  8. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  9. company releaseaep.com
    Cited by the record; no single figure is quoted from it.
  10. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  11. press reportpowermag.com
    Cited by the record; no single figure is quoted from it.
  12. press reportdatacenterfrontier.com
    Cited by the record; no single figure is quoted from it.
  13. press reportglobaldatacenterhub.com
    Cited by the record; no single figure is quoted from it.
  14. other documentnewsletter.hntrbrk.com
    Cited by the record; no single figure is quoted from it.
  15. research notemeasuredai.substack.com
    Cited by the record; no single figure is quoted from it.
  16. other documentwebull.com
    Cited by the record; no single figure is quoted from it.
  17. press reportutilitydive.com
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: AEP release (Oct 14 2026) and Google's post (Nov 5 2026) for the deal; AEP 8-K, Item 8.01 (event Jan 4 2026), FY2025 10-K and 10-Qs for Q1–Q3 2026 for the fuel-cell purchase and the unnamed offtake; AEP Q2 2026 call (Jul 30 2026; Motley Fool transcript); AEP releases of Oct 28 2026 (8-K ex. 99.1) and Nov 3 2026; POWER, Data Center Frontier, Global Data Center Hub, Hunterbrook, Measured AI and Benzinga (via Webull) for the contested cells and the note (read 2026-11) · as of Nov 2026

The evidence 10 sourced figures · 6 disputes

The record's headline AEP–Google: a 702 Bloom fuel-cell plant near Cheyenne, Wyoming, on a 20-year PPA — AEP plans ~$4B and owns ~92% beside Basalt's funds; its Jan 2026 8-K had a ~$2.65B fuel-cell purchase and a 20-year near Cheyenne for an unnamed customer, whose conditions were pushed to a Dec 2026 milestone

Size
702 MW · 20-year PPA, price undisclosed · ~$4B planned by AEP (Cheyenne Fuel Cell, LLC: ~92% AEP, nearly 8% Basalt-advised funds) · ~$2.65B fuel-cell purchase, Jan 2026 (inside the $4B or not — contested) · fully operational by end-2028 (AEP) or no later than 2030 (a May 2026 deck, reported)
When
Nov 2024 (AEP buys 100 MW of Bloom fuel cells, with an option to 1 GW by the end of 2025) → Jan 4 2026 (~$2.65B fuel-cell purchase and a 20-year offtake near Cheyenne, customer unnamed; 8-K signed Jan 8) → Jun 2026 (the conditions' deadline extended by mutual agreement) → Jul 30 2026 (Q2 call: outside the $78B plan; the offtaker may take the fuel cells elsewhere if Cheyenne does not advance) → Oct 14 2026 (Google named: 702 MW, ~$4B) → Oct 28 2026 (Q3 10-Q, customer still unnamed) → Nov 3 2026 (AEP Infrastructure formed) → Nov 5 2026 (Google's post) → Dec 2026 (milestone) → end-2028 (fully operational, AEP's target)
Status
announced Oct 14 2026; construction to start in 2026 and the plant fully operational by the end of 2028 (AEP). The offtake's conditions, expected by Q2 2026, were extended in June 2026 to a December 2026 milestone (Q2 10-Q); AEP's Q3 10-Q (Oct 28 2026) drops the conditions sentence without saying they were met, and still calls the customer 'a high investment grade third-party customer'. AEP's Nov 3 2026 release counts 'a recently announced 20-year agreement to develop a fuel cell facility for Google in Wyoming' among AEP Infrastructure's opportunities
Structure
a 20-year power purchase agreement under which Google buys power from Cheyenne Fuel Cell, LLC — approximately 92% owned and controlled by AEP, nearly 8% owned by funds advised by Basalt Infrastructure Partners, LLP — whose 702 MW plant near Cheyenne AEP develops and builds with Bloom Energy's solid oxide fuel cells, carbon capture planned to store the emissions at Tallgrass's Eastern Wyoming Sequestration Hub. AEP's filings describe the agreements behind a plant there without naming the customer: an unregulated AEP subsidiary's unconditional purchase on Jan 4 2026 of 'a substantial portion' of its option for solid oxide fuel cells, for ~$2.65B — the option in AEP's Nov 2024 agreement with Bloom Energy — and a 20-year offtake of 100% of the plant's output by 'a high investment grade third party customer', subject to conditions, AEP to be compensated for its capital and costs if they fail. The project sits in AEP Infrastructure, a business unit formed Nov 3 2026
Programme
Time-to-power
Parties
Google buyer — acquires the plant's power under the 20-year PPA, for its first Wyoming data center (googlecheyenne); its post calls the project 'contracted with AEP' · AEP seller and builder — develops, builds and ~92% owns the plant through Cheyenne Fuel Cell, LLC, beside funds advised by Basalt Infrastructure Partners (nearly 8%); in Jan 2026 an unregulated AEP subsidiary bought fuel cells for a plant near Cheyenne under the option of AEP's Nov 2024 agreement with Bloom Energy · Bloom Energy fuel-cell supplier — the plant's solid oxide fuel cells are Bloom's (AEP's release; Google's post), bought by an unregulated AEP subsidiary in Jan 2026 for ~$2.65B under the option of AEP's Nov 2024 purchase agreement with Bloom (AEP's 8-K and FY2025 10-K)
Site
Google Cheyenne
Record
disclosed / primary source · as of Nov 2026

Flows 3 as the record states them

  • AEP → Googlepowerthe output of a 702 MW fuel-cell plant near Cheyenne for 20 years, the plant to be fully operational by the end of 2028 (AEP's target); 100% of the output, in AEP's filings on its unnamed offtaker
  • Google → AEPppa-paymentspayments under the 20-year PPA, price undisclosed; in AEP's filings on the unnamed offtaker, compensation for 'all capital and costs incurred' if the offtake's conditions fail, and 'additional consideration' if the revised conditions are not met in December 2026
  • AEP → Bloom Energyfuel-cell-purchase~$2.65B for solid oxide fuel cells: an unconditional purchase executed Jan 4 2026 by an unregulated AEP subsidiary (8-K), under the option of AEP's Nov 2024 purchase agreement with Bloom Energy (FY2025 10-K) — no MW given; whether it sits inside the ~$4B AEP plans for the plant, no AEP document says (purchase-in-project)

Resolved figures 10 each with the verbatim line from its document

  • capacity702 MW
    702 MW — AEP's release and Google's post ('a first-of-its-kind, commercial-scale, 702 MW fuel cell development with carbon capture and storage (CCS)'): the contracted size, as both parties publish it. AEP's 8-K gives no MW for the January purchase ('a substantial portion' of a 900 MW option). Measured AI's 'approximately 650 MW' 'actually being interconnected' (Aug 2026, two months before the 702 MW was announced, its document not named) is not adopted, and its 900 MW is an air-permit ceiling, not a build
    “American Electric Power (Nasdaq: AEP) plans to invest approximately $4 billion to advance a new 702-megawatt fuel cell generation project near Cheyenne, Wyoming, under a long-term 20-year power purchase agreement (PPA) with Google, marking a significant step in AEP’s strategy to serve growing demand from large-scale customers.”
    AEP release (Oct 14 2026) · aep.com
  • counterparty702 MW
    Google's side, in its post announcing its first Wyoming data center: the project 'is contracted with AEP' for 702 MW of fuel cells with carbon capture and storage — the counterparty restating AEP's figure, not an independent measure of the plant
    “The project is contracted with AEP to feature a first-of-its-kind, commercial-scale, 702 MW fuel cell development with carbon capture and storage (CCS) — the largest planned development of its kind to date.”
    Google post (Nov 5 2026) · blog.google
  • investment$4B
    approximately $4B, which AEP 'plans to invest' — its release's figure for the plant; AEP publishes no breakdown, and whether the ~$2.65B fuel-cell purchase of January is inside it is contested (purchase-in-project). Not the Mainspring linear-generator agreement announced the day before, which 'could be worth up to $4 billion' (Utility Dive, from Mainspring's chief executive) — a different deal (note)
    “American Electric Power (Nasdaq: AEP) plans to invest approximately $4 billion to advance a new 702-megawatt fuel cell generation project near Cheyenne, Wyoming”
    AEP release (Oct 14 2026) · aep.com
  • ownership92%
    the seller is Cheyenne Fuel Cell, LLC, ~92% AEP's and nearly 8% held by funds advised by Basalt Infrastructure Partners; the price and terms of Basalt's stake are not disclosed. AEP's Nov 3 2026 release places the project in a new unit, AEP Infrastructure, formed to 'develop new generation resources backed by long-term customer contracts'
    “Under the PPA, Google will acquire power from Cheyenne Fuel Cell, LLC, which is approximately 92% owned and controlled by AEP, and nearly 8% owned by funds advised by Basalt Infrastructure Partners, LLP.”
    AEP release (Oct 14 2026) · aep.com
  • term20
    20 years — 'a long-term 20-year power purchase agreement (PPA) with Google'; AEP's filings give the unnamed offtake the same term ('a 20 year offtake arrangement', the 8-K). No start or end date is published; construction is to start in 2026 and the plant to be fully operational by the end of 2028 (contested full-operation)
    “under a long-term 20-year power purchase agreement (PPA) with Google”
    AEP release (Oct 14 2026) · aep.com
  • technology
    Bloom Energy's solid oxide fuel cells, which run on natural gas and, AEP says, generate electricity 'without combustion of natural gas'; 'made in America by Bloom Energy' (Google). Both plan carbon capture — AEP: 'the project includes plans to integrate carbon capture technology'; Google: the capture and permanent geologic storage of 'a large majority of its carbon emissions at Tallgrass’s nearby Eastern Wyoming Sequestration Hub', bringing its contracted CCS capacity to 'nearly 1 gigawatt'. No capture rate, cost or start date is published
    “The fuel cells for this project will be made in America by Bloom Energy and will help minimize emissions and water use in the production of energy for our data infrastructure.”
    Google post (Nov 5 2026) · blog.google
  • fuel-cell-purchase$2.65B
    ~$2.65B: on Jan 4 2026 'an unregulated subsidiary of AEP' executed an unconditional purchase of 'a substantial portion of its option for solid oxide fuel cells' for a fuel-cell plant (the 8-K), 'near Cheyenne, Wyoming' (the FY2025 10-K). The option is that of AEP's Nov 2024 purchase agreement with Bloom Energy, made through AEP Development Services — 100 MW of fuel cells 'with an option to acquire up to one gigawatt in total by the end of 2025' (the 10-K; the 8-K: 'an option to purchase an additional 900 MWs'). The 10-K says the January purchase was made 'under the existing option', after the window it gives; whether the option was extended or the order re-papered, no document on file says. AEP names no MW for it. Unconditional, unlike the offtake (conditions). The 10-Qs for Q2 and Q3 2026 call it 'its 1 GW option'
    “On January 4, 2026, an unregulated subsidiary of AEP executed (i) an unconditional purchase agreement to acquire a substantial portion of its option for solid oxide fuel cells for the development and construction of a fuel cell generation facility for approximately $2.65 billion”
    AEP 8-K, Item 8.01 (event Jan 4 2026) · sec.gov
  • offtake100%
    AEP's filings on the plant's customer, whom they never name: 'a 20 year offtake arrangement with a high investment grade third party customer for 100% of the output' of the plant near Cheyenne (the 8-K); the Q3 10-Q (Oct 28 2026), filed two weeks after the release named Google, repeats it. That this is Google's PPA is a match on place, term and buyer, not a filed statement (same-offtake)
    “a 20 year offtake arrangement with a high investment grade third party customer for 100% of the output of the fuel cell generation facility expected to be located near Cheyenne, Wyoming”
    AEP 8-K, Item 8.01 (event Jan 4 2026) · sec.gov
  • conditions
    the offtake was conditional: the 8-K expected its conditions 'to be satisfied by second quarter 2026' and, 'Should the conditions not be satisfied, AEP will be financially compensated for all capital and costs incurred.' In June 2026 'the deadline for those conditions was extended by mutual agreement of the parties' (Q2 10-Q). On the Q2 call (Jul 30 2026) AEP said the amendment 'modified some key protection terms so that AEP is adequately compensated for their requested timing accommodations', and that under the December 2026 milestone 'the hyperscaler has the ability to choose to deploy the fuel cells at an alternate location if the Cheyenne Wyoming site does not advance'. The Q3 10-Q drops the conditions sentence without saying they were met (conditions-status); what AEP gets if they fail is contested (exit-compensation)
    “Should the revised conditions not be satisfied in December 2026, AEP will be entitled to additional consideration to account for the extended timeline.”
    AEP 10-Q for Q2 2026 (Jul 30 2026) · sec.gov
  • capital-plan
    outside AEP's plan when it last said: on Jul 30 2026 it counted 'the fuel cells for the Wyoming project' among 'over $10 billion of incremental investments that are not included in the $78 billion' 2026–2030 plan, and its CFO said the fuel cells 'need to be installed and ready to go by the end of 2028 to qualify for the investment tax credit'. AEP's $100B plan for 2027–2031 (Oct 28 2026) does not say whether the project is in it
    “We also shared on the first quarter call that we have line of sight to over $10 billion of incremental investments that are not included in the $78 billion, consisting of the fuel cells for the Wyoming project, the Piketon transmission opportunity, and incremental power generation.”
    AEP Q2 2026 earnings call (Jul 30 2026; Motley Fool transcript) · fool.com

Contested figures 11 not reconciled — every position side by side, with its source and tier

same-offtake2 positions, side by side
the same contract — AEP's filings show one fuel-cell plant near Cheyenne, and the January offtake and Google's PPA share the place, the 20-year term and an investment-grade buyer AEP called 'the hyperscaler' on its Q2 call; Data Center Frontier calls the January buyer 'an unidentified investment-grade customer, now confirmed as Google', citing nothing for it AEP 8-K, 10-Qs and Q2 call; Data Center Frontier (Oct 2026)
not stated — AEP's release names Google without referring to the January agreements, and its Q3 10-Q, filed two weeks later, still describes 'a high investment grade third-party customer'; Global Data Center Hub: 'The October release names Google but does not say whether this is the same arrangement, or whether those conditions are now satisfied' AEP Q3 2026 10-Q (Oct 28 2026); Global Data Center Hub (Oct 2026)
purchase-in-project2 positions, side by side
inside — Data Center Frontier: 'The equipment purchase formed part of the project's development history, rather than representing a separate $2.65 billion investment in addition to the $4 billion project announced in October' (its own reading; it cites no AEP statement for it) Data Center Frontier (Oct 2026)
not stated — no AEP document bridges the two figures; Global Data Center Hub: 'If the January purchase and the Cheyenne project are the same, roughly $1.35 billion separates the equipment agreement from the $4 billion investment … AEP has not published the bridge'. Neither a sum of the two nor the gap is AEP's figure Global Data Center Hub (Oct 2026); AEP filings
full-operation2 positions, side by side
by the end of 2028 — AEP's release: 'the facility is expected to be fully operational by the end of 2028', construction starting in 2026; the date the investment tax credit sets, by AEP's CFO on Jul 30 2026: the fuel cells 'need to be installed and ready to go by the end of 2028' AEP release (Oct 14 2026); AEP Q2 2026 call
no later than 2030 — AEP's May 2026 investor deck, against 'no later than 12/31/2028' in its February deck, as Hunterbrook reports them ('a potential delay of up to two years in under 90 days'); the decks are not on file, and its affiliate Hunterbrook Capital disclosed it was short Bloom's stock at publication. AEP's October date is its newest; whether 2030 was dropped or is a contractual outside date beside a 2028 target, no document says Hunterbrook (Jul 2026), on AEP's Feb and May 2026 investor decks
conditions-status2 positions, side by side
open when last filed — 'The offtake arrangement remains subject to specified conditions', the deadline extended to a December 2026 milestone (Q2 10-Q, as of Jun 30 2026); the Q3 10-Q drops that sentence but does not say the conditions were met AEP 10-Qs for Q2 and Q3 2026
settled — Benzinga's report of AEP's Q3 call (via Webull): 'AEP finalized commercial agreements for its Wyoming Fuel Cell Project', 'with construction underway'; the call's transcript is not on file, and AEP's own releases call the agreement announced without saying its conditions were satisfied Benzinga via Webull (Oct 28 2026)
exit-compensation2 positions, side by side
all capital and costs incurred — the 8-K, if the conditions are not satisfied; since June 2026, 'additional consideration to account for the extended timeline' if the revised conditions are not met in December 2026 (Q2 10-Q), its amount undisclosed AEP 8-K (Jan 2026); AEP 10-Q for Q2 2026
cost plus about 10% — AEP's CFO on the May 2026 call, as two outlets retell it: the hyperscaler 'can walk away by covering AEP’s costs incurred, plus roughly 10%' (Hunterbrook, also 'roughly 110% of “all capital and costs incurred”'); AEP can 'put the fuel cells back to the hyperscaler at a cost plus' roughly 10% (Measured AI). The transcript is not on file, and the June amendment 'modified some key protection terms' (Q2 call) Hunterbrook (Jul 2026); Measured AI (Aug 2026)
ppa-priceone entry, in its own words
undisclosed — neither AEP's release nor Google's post gives a price, a payment or a total, and AEP's filings give none for the unnamed offtake. The est ribbon stands in with AEP's ~$4B for the plant (link comment) AEP release (Oct 14 2026); Google post (Nov 5 2026); AEP filings

Scope note what this record leaves to other records

Not this record: Black Hills' contracts to serve the same data center (pw-bkh-google) — up to 590 MW of grid service and ~2.1 GW of third-party plants it manages on a private microgrid, which may or may not include this one (contested there, in-microgrid); the campus itself and Tallgrass's Cheyenne Power Hub (the googlecheyenne site). Bloom Energy's side of the purchase: the ~$2.65B is AEP's figure, drawn as the aep→bloomenergy ribbon (AEP's 8-K names no seller; its FY2025 10-K places the purchase under the option of its Nov 2024 agreement with Bloom), and Bloom's own filings on file give no figure for the order; Bloom's company figures → the bloomenergy entity; Bloom's backlog, its dispute with Hunterbrook and the Jefferies note Hunterbrook cites, tracing 'nearly 40%' of Bloom's product backlog to the AEP deal, are not carried here. AEP's earlier fuel cells — the 100 MW of Nov 2024 and Ohio Power's two customer-sited contracts of ~98 MW — are on the aep entity. AEP's Mainspring linear-generator agreement, announced by Mainspring on Oct 13 2026 (up to 1.6 GW, an agreement 'which could be worth up to $4 billion' by Utility Dive's account — that deal's figure, not this plant's; POWER's '892 MW' adds its 190 MW initial order to this plant's 702). Not adopted: Measured AI's 'As of June 30, 2026, AEP carries the whole facility at $4 billion of incremental capex' (no AEP document before Oct 14 gives a $4B figure — the Q2 call speaks only of 'over $10 billion' of incremental investments); Hunterbrook's ~$2.65 per watt, which needs the $2.65B to buy ~1 GW; the ~$5.7M per MW of Data Center Frontier and Global Data Center Hub ($4B ÷ 702 MW — 'a simple division, not guidance', the latter says).