Nvidia–SB Energy–OpenAI, PORTS-Pike

Nvidia will cover up to $105B if OpenAI defaults on 4.25 of SB Energy leases in Ohio. In return, the site must use only Nvidia chips for at least 20 years.

A deal between Nvidia, SB Energy, OpenAI, SoftBank

Why it matters

Nvidia's guarantee of OpenAI's leases with SB Energy, a landlord it partly owns, requires at least twenty years of chip exclusivity. The guarantee is capped at $105B and pays only if OpenAI defaults and proceeds from reletting or selling the buildings fall short of a declining minimum. OpenAI must reimburse any payout, and so far only $1.5B has moved, into SB Energy.

Tap a figure for the line in its source.

SB Energy gives

  • in 17 buildings on 20-year leases; the rent is blacked out in every filed lease → OpenAI
  • of the campus running only Nvidia computing hardware, promised in the guarantee → Nvidia

Nvidia gives SB Energy

  • to cover the shortfall if OpenAI defaults — on the first nine buildings (4.25 ) only
  • invested in SB Energy in Aug 2026, with $1.5B more promised when it lists on the stock market

OpenAI gives Nvidia

  • an undisclosed fee for the guarantee, plus repayment of anything Nvidia pays out

Jul 2026 reported by the WSJ (talks stage)updated Nov 21, 2026signed Aug 17 2026 disclosed by the parties

What happened

SB Energy, SoftBank's data center arm, is building a campus for OpenAI on the former uranium-enrichment site in Pike County, Ohio. The plans call for 17 buildings and about 8 gigawatts of computing load. OpenAI signed a 20-year lease for each building in August 2026. Landlords and lenders do not normally take on 20 years of rent risk for a company with OpenAI's credit. Nvidia stepped in as guarantor. If OpenAI goes insolvent or stops paying, Nvidia's guarantee comes into play. Nvidia covers any gap between a scheduled minimum value and what the buildings fetch from a new tenant or sale. The guarantee covers the first nine buildings (4.25 ) and is capped at $105 billion in total. Nvidia pays only if OpenAI defaults. The guarantee takes effect building by building from about 2028–29 as each is ready. OpenAI has agreed to reimburse Nvidia for anything it pays. In return, the campus must use Nvidia chips exclusively for at least 20 years. By guaranteeing its own customer's rent, Nvidia aims to secure future orders for its own chips. Nvidia also put $1.5 billion in cash into SB Energy the same day and promised another $1.5 billion when SB Energy lists. Nothing is built yet. The power plants intended to supply the site have been announced and have yet to be contracted. The widely reported “$105 billion financing” is a cap on what Nvidia might have to pay. No money has changed hands under the guarantee.

Sources 16 documents — 10 SEC filings · 4 company releases · 2 government statements

Research trail Found 257 documents and read 247 of them while checking this deal and related ones.

  1. SEC filingsec.gov
    States 10 figures: guaranty consideration · leases · lease term · 472 MW building configuration · 10 GW gross grid load · $1.5B nvidia equity funded · 90% nvidia equity pricing · $3B nvidia equity total · 9.2 GW generation plan (for context) · generation binding status
  2. SEC filingsec.gov
    States 4 figures: $105B guaranty cap · 4.25 GW guaranteed capacity · guaranty mechanics · ready for service
  3. SEC filingsec.gov
    States 3 figures: guaranty scope · guaranty phasing · $3.5B pre existing ai cloud guaranties (for context)
  4. company release (archived copy)openai.com
    States 2 figures: 8 GW contracted capacity · 800 MW first phase
  5. Nvidia · SEC filingsec.gov
    States compute exclusivity
  6. SEC filingsec.gov
    States $150B nvidia revenue opportunity
  7. Nvidia · SEC filingsec.gov
    States $40M community fund
  8. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  9. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  10. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  11. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  12. company releasenvidianews.nvidia.com
    Cited by the record; no single figure is quoted from it.
  13. company releaseblogs.nvidia.com
    Cited by the record; no single figure is quoted from it.
  14. company releaseaep.com
    Cited by the record; no single figure is quoted from it.
  15. government statement (archived copy)Feb 2026commerce.gov
    Cited by the record; no single figure is quoted from it.
  16. government statement (archived copy)meti.go.jp
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: Nvidia 8-K (Item 1.01, 2026-08-17) + 10-Q qtr ended 2026-07-26 + ex-10.1 guaranty form; SB Energy S-1 (2026-09-01) + S-1/A lease form (ex-10.30) and guaranty form (ex-10.31); OpenAI + Nvidia releases; AEP Ohio / Commerce / METI for the grid and generation layer · as of Sep 2026

The evidence 20 sourced figures · 8 disputes · 2 for context

The record's headline Nvidia–SB Energy–OpenAI, PORTS-Pike: $105B residual-value guaranty cap on OpenAI's first 4.25 -IT of a 20-year, 8.0 GW-IT lease — exclusivity for Nvidia compute, $1.5B into the landlord

Size
$105B guaranty cap (contingent) on 4.25 of 8.0 GW-IT · $1.5B equity funded + $1.5B at IPO
When
Aug 2026 → first 800 MW 2028; first guaranty FY2029; 20-year terms
Status
signed Aug 17 2026 — 17 leases executed, guaranties attach lease by lease from FY2029 as buildings reach ready-for-service; nothing built; the 9.2 GW of neighboring gas generation is announced, not contracted
Structure
residual-value guaranties of the tenant's lease obligations to the landlord (pays the shortfall vs a declining guaranteed minimum value after re-lease/sale, on insolvency or payment default) + landlord equity (prepaid forward at 90% of IPO price + IPO-price private placement), in exchange for ≥20-year Nvidia-reference-architecture exclusivity at the site; OpenAI compensates Nvidia under a separate, undisclosed agreement and indemnifies every dollar paid
Programme
Nvidia circular capital
Parties
Nvidia lease guarantor + landlord investor + exclusive compute supplier · SB Energy landlord: builds, owns, operates 17 buildings under 20-yr NNN leases · OpenAI tenant (8.0 GW-IT) + guaranty counterparty (compensates + indemnifies Nvidia) · SoftBank controls SB Energy; a non-registrant affiliate develops the neighboring gas generation
Capital
the seller's own money or backing comes back as its sales
Record
disclosed / primary source · as of Sep 2026

Flows 5 as the record states them

  • Nvidia → SB Energyresidual-value-guarantyup to $105B cumulative cap on the first nine buildings (~4.25 GW-IT) — contingent: pays only the shortfall between a declining guaranteed minimum value and re-lease/sale proceeds after an OpenAI insolvency or payment default; attaches lease by lease from FY2029; option, in Nvidia's sole discretion, on the remaining ~3.75–3.8 GW-IT (contested size)
  • Nvidia → SB Energyequity$1.5B prepaid forward FUNDED Aug 17 2026 (settles in Class N shares at 90% of the IPO price) + $1.5B private placement at the IPO price, contingent on the offering — $3.0B in total per the S-1
  • OpenAI → SB Energylease-payments17 × 20-year triple-net leases, ~8.0 GW-IT (17 × ~472 MW-IT); rent redacted in every filed lease; phased commencement tied to ready-for-service
  • OpenAI → Nvidiachip-spendthe site 'will exclusively install and deploy NVIDIA reference architecture' for not less than 20 years (§20(e) of both parties' filed guaranty forms — a guarantor–landlord covenant, not a clause of the lease); Nvidia's own sizing: each hardware generation ~1.5M GPUs / $150–200B of Nvidia revenue, multiple upgrade cycles over 20 years — an opportunity figure, not a contract
  • OpenAI → Nvidiaguaranty-compensationundisclosed — 'such compensation is provided separately by OpenAI under a separate agreement' (S-1); plus reimbursement and indemnity 'for any and all amounts actually paid' (8-K)

Resolved figures 20 each with the verbatim line from its document

  • guaranty-cap$105B
    $105B — the cumulative cap on Nvidia's aggregate payment obligation for its initial commitment (the first nine buildings, ~4.25 GW-IT). Stated identically in the 8-K, the 10-Q, the CFO commentary, the executed guaranty form ('shall not exceed $105,000,000,000') and, from the other side, SB Energy's S-1 ('aggregate remedy cap is $105 billion'). It is a ceiling on a CONTINGENT obligation, not financing: the cap phases in as leases commence, the guaranteed minimum value 'holds constant and then declines on a defined schedule over the 20-year leases' (S-1), and the schedule itself is not disclosed — a headline cap with no time profile
    “NVIDIA’s aggregate payment obligation is cumulatively capped at $105 billion for its initial commitment under the Agreements.”
    Nvidia 8-K Item 1.01 (filed 2026-08-17) · sec.gov
  • guaranteed-capacity4.25 GW
    ~4.25 GW of IT load — the leases the guaranties cover: PORTS-Pike Buildings 1–9, 4,248 MW-IT in the S-1's project table (9 × ~472 MW-IT). The guaranty form ties the guaranteed minimum value to 'four and one quarter (4.25) GW of critical IT load' and says it 'is comprised of data center, power, and transmission related costs'. The other eight buildings (3,776 MW-IT) are leased but NOT guaranteed unless Nvidia exercises its option (see contested option-capacity)
    “On August 17, 2026, NVIDIA entered into multiple residual value guaranties (collectively, the “Agreements”) with SB Energy (the “Lessor”) relating to leases for approximately 4.25 gigawatts of IT load in the aggregate at the Portsmouth Site.”
    Nvidia 8-K Item 1.01 · sec.gov
  • guaranty-mechanics
    a residual-value guaranty — not a full rent guaranty (the 10-Q: 'limited to defined portions of lease and power payments') and not a whole-project backstop: on a Trigger Event (OpenAI insolvency causing a lease default, or OpenAI failing to pay) Nvidia pays the SHORTFALL between the lease's guaranteed minimum value and what the landlord recovers by re-letting or selling — after Nvidia elects to assume the lease, force a re-let, run a sale, let the lease terminate, or defer for up to a year while paying project costs. Terminates at the earliest of the 20th anniversary of each lease's commencement, OpenAI terminating per the lease, OpenAI 'achieving a satisfactory credit rating', or other customary events. The S-1 adds that Nvidia may put an assignee into the lease, so a replacement tenant could be less creditworthy than OpenAI — with the guaranty staying in place
    “NVIDIA will pay an amount generally equal to any shortfall between the guaranteed minimum value of a lease (as set forth in the Agreements) and amounts recovered through a replacement lease or sale.”
    Nvidia 8-K Item 1.01 · sec.gov
  • guaranty-scope
    what the cap does NOT cover, in Nvidia's own words: defined portions of lease and power payments only — not the full cost of the site, not all of the tenant's obligations. Exposure 'declines as OpenAI fulfills its lease payments' (10-Q MD&A). Read with the S-1's 'over $6 billion in credit support' that PORTS-Pike interconnection alone may require of SB Energy — the landlord still carries the letters of credit
    “Our guarantees are limited to defined portions of lease and power payments and not the full cost of the site or all of the tenant’s obligations.”
    Nvidia 10-Q, quarter ended 2026-07-26 (Commitments and Contingencies — Guarantees) · sec.gov
  • guaranty-phasing2029
    nine phases, one per guaranteed building; each guaranty becomes effective when its lease commences and the amounts step up as each phase is completed, the first expected in Nvidia's fiscal 2029 (Feb 2028–Jan 2029) — consistent with the 8-K's 'ready-for-service … expected beginning in 2028'; the S-1's portfolio table puts the LAST ready-for-service date for Buildings 1–9 at 2031 (2032 for 10–17). Until then the $105B is a cap on nothing
    “Each guarantee generally becomes effective upon commencement of the applicable lease, with corresponding guarantee amounts increasing, as each of the nine phases of data center construction is completed, the first of which is expected in fiscal year 2029.”
    Nvidia 10-Q, quarter ended 2026-07-26 · sec.gov
  • ready-for-service2028
    Nvidia pays nothing unless the landlord has satisfied the lease's ready-for-service conditions for the relevant premises — 'expected beginning in 2028'. OpenAI's post says the first 800 MW 'largely using existing AEP infrastructure' in 2028 (see first-phase); AEP expects new-transmission power to flow in 2029; the S-1's table gives a 'Last RFS' of 2031 for the guaranteed buildings and 2032 for the option buildings
    “NVIDIA’s payment obligations are subject to specified conditions, including among other things, that the Lessor has satisfied applicable ready-for-service conditions under the lease for the relevant premises, expected beginning in 2028.”
    Nvidia 8-K Item 1.01 · sec.gov
  • compute-exclusivity20
    the consideration, in the contract: the premises 'will exclusively install and deploy NVIDIA reference architecture' for not less than twenty years from each lease's commencement — in the executed guaranty form (Nvidia 10-Q ex-10.1) and, word for word, in SB Energy's own filed copy of the same guaranty (S-1/A ex-10.31), with the carve-outs redacted ([***]; the 10-Q says 'subject to limited exceptions'). It is a covenant between guarantor and landlord: the filed form of PORTS-Pike lease (S-1/A ex-10.30) does not carry it and never names Nvidia, so the tenant is bound to Nvidia compute through the guaranty's parties, not through its own lease. This is what makes the guaranty circular: Nvidia underwrites its customer's rent to lock its own chips into 8 GW for two decades
    “The parties agree that the Premises will exclusively install and deploy NVIDIA reference architecture for accelerated computing hardware and compute technologies, including [***] for a period of not less than twenty (20) years from the Commencement Date of the Lease.”
    Form of Residual Value Guaranty, Nvidia 10-Q ex-10.1 §20(e) · sec.gov
  • guaranty-consideration
    SB Energy pays Nvidia nothing for the guaranties; OpenAI does, under a separate agreement whose existence is disclosed and whose size and form are not — the tenant is buying its own credit enhancement from its chip supplier. The 8-K adds the other leg: OpenAI 'has agreed to reimburse and indemnify NVIDIA for any and all amounts actually paid by NVIDIA to the Lessor'. So the $105B is, on paper, an OpenAI liability that Nvidia fronts; whether OpenAI could pay it back in the insolvency that triggers it is the question the structure does not answer
    “We did not offer and do not owe any compensation to NVIDIA for the guaranties; such compensation is provided separately by OpenAI under a separate agreement.”
    SB Energy S-1 (filed 2026-09-01), Recent Developments · sec.gov
  • leases17
    17 individual triple-net leases signed Aug 17 2026 between 17 SB Energy subsidiaries (each a landlord) and one OpenAI affiliate (tenant), ~8.0 GW-IT in aggregate; the first nine on a fixed-yield yield-on-cost rent formula, the last eight on a floating yield within a set range, each with a capex cost target. Rent itself is [***] in every filed lease, so no per-lease or per-GW value exists anywhere on file. A confidential-draft 18-building design was superseded and is not carried here
    “On August 17, 2026, 17 of our subsidiaries, each as landlord, and an affiliate of OpenAI, as tenant, entered into individual lease agreements for the PORTS-Pike Technology Campus, resulting in 17 leases covering approximately 8.0 GW-IT of critical IT capacity in the aggregate.”
    SB Energy S-1, Recent Developments · sec.gov
  • lease-term20 years
    20-year initial term per lease, NNN — the PORTS-Pike term. The 15-year terms elsewhere in the same S-1 and its exhibits (ex-10.28/10.29) are the Milam County and Cosmos leases, a different deal; merging them into one 'lease term' is the most likely misreading of the filing. The guaranty and the exclusivity covenant are both keyed to the same 20 years
    “Each of the 17 buildings is subject to a separate 20-year NNN lease.”
    SB Energy S-1, Business — PORTS-Pike Technology Campus · sec.gov
  • building-configuration472 MW
    17 buildings × ~472 MW-IT = ~8,024 MW-IT (S-1 project table: Buildings 1–9 4,248 · Buildings 10–17 3,776), on ~10 GW of gross grid load. Four discrete construction projects in phased sequence. The 4.25 / 3.78 split of the guaranty is this table's two rows
    “The PORTS-Pike Technology Campus is designed to comprise 17 data center buildings, each with approximately 472 MW of critical IT capacity at the building level, aggregating to approximately 8.0 GW-IT of data center capacity and supported by approximately 10 GW of gross power load.”
    SB Energy S-1, Business — PORTS-Pike Technology Campus · sec.gov
  • contracted-capacity8 GW
    ~8 GW-IT — OpenAI's own statement of what it contracted, matching the S-1's 8.0 GW-IT / 8,024 MW-IT and the release's '8-IT GW'. The '10 GW' cited in ~40 claims on file is the same campus's GROSS grid load, not a rival capacity (the release: 'at least 10 GW of new energy generation, which results in 8 IT-GW'); the DOE/AEP '10 GW data center' phrasing is that denominator. OpenAI's post also states the payment posture: it 'will begin paying only as completed capacity becomes available for lease'
    “OpenAI has entered into an agreement to secure approximately 8 gigawatts-IT at the PORTS-Pike Technology Campus in Pike County, Ohio, working with SB Energy, NVIDIA, and the U.S. Department of Energy.”
    OpenAI, 'OpenAI joins PORTS-Pike project' (Aug 17 2026; live page bot-blocks — Wayback snapshot) · web.archive.org
  • gross-grid-load10 GW
    ~10 GW of gross power from the grid for 8.0 GW-IT (an ~80% IT-to-grid ratio), to be supplied by PJM plus ~9.2 GW of new neighboring gas generation. Utility service exists today only for 0.8 GW (an AEP Ohio Electric Service Agreement + Letter of Agreement, conditioned on transmission upgrades); utility service agreements for the 9.2 GW 'are subject to final regulatory approvals' (S-1 table footnote)
    “The PORTS-Pike Technology Campus requires approximately 10 GW of gross power load from the grid to support its 8.0 GW-IT of planned data center capacity, expected to be supported by the PJM transmission system and new neighboring gas-fired generation facilities.”
    SB Energy S-1, Risk Factors · sec.gov
  • nvidia-equity-funded$1.5B
    $1.5B — the one cash flow that has actually happened: a Prepaid Forward Contract with Energy Global (SB Energy's parent LP), funded in full on Aug 17 2026 and contributed down to SB Energy, settling at the IPO into non-voting Class N shares. The release's 'NVIDIA will invest $1.5 billion in SB Energy' is this leg; the pre-filing 'up to $3B' scoop (The Information / WSJ, contradictory attribution) was the two legs together, which the S-1 confirms
    “NVIDIA funded the full $1.5 billion under the Prepaid Forward Contract on August 17, 2026, and Energy Global then contributed those proceeds to us.”
    SB Energy S-1, Recent Developments (+ ex-10.27 Prepaid Forward Contract) · sec.gov
  • nvidia-equity-pricing90%
    the prepaid forward settles at 90% of the IPO price — a 10% discount for money in early ('Discount Rate is 90%' in ex-10.27, which also carries a preference floor of the greater of 1.4× the purchase amount or 20%/yr compounding if no qualified offering occurs). Nvidia's resulting stake cannot be computed: no IPO price exists
    “On August 17, 2026, Energy Global entered into the Prepaid Forward Contract with NVIDIA under which NVIDIA prepaid $1.5 billion to Energy Global for our delivery of Class N common stock at the per-share initial public offering price before underwriting discounts and expenses, multiplied by 90%.”
    SB Energy S-1, Recent Developments · sec.gov
  • nvidia-equity-total$3B
    $3.0B in total = the funded $1.5B forward + a $1.5B Concurrent Private Placement (Share Purchase Agreement, ex-10.28) at the IPO price, closing 'simultaneously with' the offering and contingent on it — the offering is NOT conditioned on the placement. Record the headline as '$3B committed / $1.5B funded'; the second leg is announced-not-funded and draws no ribbon
    “The number of shares will equal $1.5 billion divided by the per-share initial public offering price before underwriting discounts and expenses, rounded down to the nearest whole share (reflecting an investment from NVIDIA of $3.0 billion in total between the Prepaid Forward Contract and the Share Purchase Agreement).”
    SB Energy S-1, Prospectus Summary — Concurrent Private Placement · sec.gov
  • generation-binding-status
    the qualifier every '$33B awarded / financed by Japan' claim needs: as of the prospectus date nothing is signed with any government on funding, construction, ownership or operation of the plants. SB Energy 'is not a party to any agreement relating to the U.S.–Japan Partnership' and expects no direct funding from it. The only executed Japanese instruments on file — NEXI insurance (~USD 1.255B) and a JBIC loan ($630M) — name neither Piketon nor SB Energy
    “As of the date of this prospectus, no binding agreement has been executed between us or any of our affiliates and any governmental entity with respect to the funding, construction, ownership or operation of the generation facilities.”
    SB Energy S-1, Risk Factors — Government Incentives · sec.gov
  • first-phase800 MW
    ~800 MW in 2028, mostly on existing AEP infrastructure; everything beyond needs new plants and new transmission. The project FAQ's '$30–40B' for this phase and the March-2026 '$10B' are promoter figures with no filing behind them (see contested phase-1-investment). The S-1's tier-1 corroboration is the 0.8 GW covered by the AEP Ohio ESA
    “The first 800 megawatts are expected to become available in 2028 largely using existing AEP infrastructure.”
    OpenAI, 'OpenAI joins PORTS-Pike project' (Wayback snapshot) · web.archive.org
  • nvidia-revenue-opportunity$150B
    Nvidia's own sizing of what the exclusivity is worth to it: ~1.5 million GPUs, or ~$150–200B of Nvidia revenue, PER hardware generation, with 'multiple infrastructure upgrade cycles' over the 20 years. An opportunity statement in CFO commentary, not a purchase contract — but it is the denominator against which a $105B contingent cap should be read
    “Each generation of NVIDIA infrastructure deployed at PORTS-Pike could represent approximately 1.5 million NVIDIA GPUs, or approximately $150 billion to $200 billion in NVIDIA revenue.”
    Nvidia Q2 FY2027 CFO commentary (8-K ex-99, Aug 2026) · sec.gov
  • community-fund$40M
    $80M = SB Energy's $40M community benefits fund + OpenAI's incremental $40M; OpenAI separately offers up to $84M of Codex credits to ~844,000 Ohio students (in-kind, not cash) — the '$160M in benefits' headline is 40 + 40 + 84 rounded down. Distinct from AEP Ohio's $18M multi-company bill-assistance programme. The joint release is the only source: it is furnished under the 8-K's Section 18 legend, not filed, and no filing repeats the figure (the S-1 has no community-fund number)
    “OpenAI has agreed to build on SB Energy’s originally announced $40 million community benefits fund with an incremental $40 million designed to support local priorities, including affordable energy, job creation and workforce development, and community and economic development.”
    joint release, Nvidia 8-K ex-99.1 (furnished, not filed) · sec.gov

Contested figures 12 not reconciled — every position side by side, with its source and tier

option-capacity3 positions, side by side
~3.8 GW — Nvidia's 8-K ('approximately an additional 3.8 gigawatts') and 10-Q ('approximately 3.8 additional gigawatts'), both 'exercisable in its sole discretion' Nvidia 8-K + 10-Q
~3.78 GW-IT — SB Energy's S-1, six times, incl. the subsequent-events note; the S-1 table's Buildings 10–17 row is 3,776 MW-IT (8,024 − 4,248), so 3.78 is the building-level residual and 3.8 its rounding. That reconciliation is the monitor's arithmetic on the table — no document states which basis is authoritative, and the two party filings differ SB Energy S-1
3.75 IT-GW — in the Aug-17 joint release (8-K ex-99.1, furnished not filed, and its nvidianews copy) and in Jensen Huang's post on Nvidia's blog the same day ('to secure the remaining capacity of 3.75 gigawatts'): 8.0 − 4.25 on rounded headline numbers, contradicted by the 8-K's own Item 1.01 three pages earlier. Neither is a filing — the release is furnished under a Section 18 legend and filed nowhere, the blog is posted on Nvidia's site — and no filing repeats 3.75. Range 3.75–3.8; no pick joint release (furnished, not filed) + Nvidia blog, Aug 17 2026
option-deadlineone entry, in its own words
the mechanism is filed, the date is not: if Nvidia does not guarantee the remaining ~3.78 GW-IT 'by a date certain', OpenAI must secure a replacement guarantor rated at least A- (S&P) or Moody's equivalent — a rating OpenAI itself does not hold, which is the whole reason Nvidia is here. The 'date certain' appears nowhere in the S-1, the 8-K or the guaranty form, so the option's expiry — and with it, when Buildings 10–17 would have to find A- credit elsewhere — is unrecorded. IFR's read of the same prospectus is not a second source SB Energy S-1 (Recent Developments + Business) vs the gap
regional-grid-investment2 positions, side by side
$4.2B — 'new transmission investment' that SB Energy 'is committed to paying for' (AEP Ohio release, Mar 2026), repeated by the joint release ('invest at least $4.2 billion in new regional grid infrastructure'), DOE, and the project site's prose; new 765 kV lines, power flowing 2029. AEP's own 2Q26 deck carries the same $4.2B as its 'Piketon Transmission Opportunity' AEP Ohio release + joint release
$5.1B — the S-1 (most recent, tier 1): 'AEP Ohio and its affiliates intend to incur approximately $5.1 billion in capital costs', recovered from SB Energy 'plus a regulated return' through transmission and distribution charges over the operating term, with SB Energy posting collateral for the whole amount; also in two stat tiles on the project's own homepage while its prose still says $4.2B. Different mechanics (customer-paid capex vs utility capex passed through with a return) and the S-1 never mentions $4.2B — no document bridges them. Low/high $4.2–5.1B, never averaged SB Energy S-1
gas-generation-cost2 positions, side by side
$33B — U.S. Commerce fact sheet (Feb 18 2026, 'Portsmouth Powered Land Project … Cost: $33 Billion · Capacity: 9.2 GW · Operator: SB Energy'), the DOE announcement's rounding, and the S-1's own usage. ONE government fact sheet, present on file as three Wayback snapshots of one URL U.S. Dept. of Commerce fact sheet (Wayback)
~$33.3B (≈ ¥5.2 trillion) — Japan's METI, same-day announcement of the same project, with the yen figure behind it. Almost certainly one number under two roundings/FX conventions; neither document says so, and outlets split. Range $33.0–33.3B. Both are announced project cost, not funded construction: the S-1 says no binding governmental agreement exists, and the executed Japanese instruments (NEXI ~USD 1.255B insured, JBIC $630M — neither naming Piketon or SB Energy) are an order of magnitude smaller METI English release (Wayback)
pre-filing-guaranty-sizeone entry, in its own words
a dated negotiation timeline, not co-equal values: 'up to $250B' for a 10 GW concept (ONE WSJ report, late Jul 2026, people familiar; five outlets, one scoop) → 'less than $120B' for an opening phase (ONE WSJ report, Aug 14, via the Reuters wire) → $105B on 4.25 GW-IT, filed Aug 17. Neither press figure appears in any filing before or after; this record uses the filed cap. Kept here so the '$250B backstop' never re-enters the record as a live number WSJ via Reuters/CNBC (unnamed sources), superseded by the 8-K
phase-1-investmentone entry, in its own words
$10B (March-2026 announcement) vs '$30–40 billion investment for an approximately 800 MW data center' (the project's own FAQ, portscampus.com, as later revised; Echelon notes the FAQ 'now says' $30–40B) vs $33–40B (downstream, apparently folding the $33B gas plant into the data-center phase). A 3–4× spread on the same 800 MW; no filing states a phase-1 capex; nothing says what changed. $10–40B, unresolved DOE/Commerce (Mar 2026) vs portscampus.com FAQ (live + Wayback = one source)
campus-total-costone entry, in its own words
'more than $400B' vs '$500B or more' for the fully built campus — anonymous-source estimates (Bloomberg/WSJ/The Information lineage, reflected back by the project's boosters), built by multiplying an unstated $/GW onto 8–10 GW; six $/GW figures on file span 9× ($9–11B/GW powered shell to ~$40B/GW Vera Rubin), so the product is whatever definition was grabbed. Collides with two other '$500B's (Nvidia's third-party financing platforms; Stargate). No primary budget exists; the S-1's $178B backlog-associated capex is portfolio-wide, cash-basis, and not this number trade press, unnamed sources
jobsone entry, in its own words
three scopes, two vintages, ~9× apart: ~4,000 construction / 300–400 operating (phase 1 — project FAQ + March announcement) · >10,000 construction over 4 yrs / >2,000 operating (DOE March-2026 fact sheet) · 35,000 construction over a six-year buildout through 2032 / 2,500 operating (full campus — OpenAI post + project site, Aug 2026). All promoter or promoter-derived; no independent labour estimate on file portscampus.com FAQ · DOE fact sheet · OpenAI post

For context, not this deal's figures 2 kept beside the deal so they are not mistaken for its numbers

  • pre-existing-ai-cloud-guaranties$3.5B
    $3.5B — Nvidia's OTHER land/power/shell guarantees (for 'select AI cloud partners', unnamed; $712M of it escrow-mitigated; five-to-seven-year terms), a different program that the 10-Q's exposure table adds to the $105B: 'Land, power, and shell guarantees for AI clouds $ 3.5 · SB Energy Corp. guarantees 105.0 · Total $ 108.5' (in billions). $108.5B is therefore Nvidia's FILED maximum gross guarantee exposure; the '~$200B by 2028', '~$300B' and '$400–500B' figures in circulation are analyst extrapolations (IFR's $125B is 25% × the $500B third-party financing platforms, a multiplication Nvidia's 'may provide … up to 25% … project-by-project' language does not license). The $108.5B total is a cell of that table, not a sentence, so it is given here, cited to the same page
    “The maximum gross exposure under all agreements is $3.5 billion.”
    Nvidia 10-Q, quarter ended 2026-07-26 (Guarantees) · sec.gov
  • generation-plan9.2 GW
    ~9.2 GW of new gas-fired generation neighboring the campus, out of 'at least 10 GW' of new generation (release) — the residual is non-gas. Pursued under the U.S.–Japan trade partnership (see contested gas-generation-cost). SB Energy is NOT the developer: the facilities 'are being developed by an affiliate of SoftBank that is not our subsidiary, and we do not expect to own or operate them' (S-1) — the power layer sits outside the IPO registrant and outside every guaranty here
    “The U.S.–Japan Partnership has been publicly announced with funding associated with the development and construction of approximately 9.2 GW of gas-fired generation facilities neighboring the PORTS-Pike Technology Campus.”
    SB Energy S-1, Risk Factors — Government Incentives · sec.gov

Scope note what this record leaves to other records

NOT this record (a separate deal that must never be merged here): everything Milam County / Texas — the 1.2 GW headline vs 753 MW-IT executed (308 + 445; the S-1's own table says ~400 for Building 2 while its narrative says ~445), the 15-year lease terms, ERCOT Muscovy/Voss transmission options — that is sg-oai-sb's site, a different deal; OpenAI's $500M equity, penny warrants (8,554,600 → 3,991,809; $5.486B liability at Jun 30 2026) and SB Energy's $50M software-purchase commitment to OpenAI under the Jan-2026 Foundation Agreement — an SB Energy–OpenAI relationship that predates PORTS, recorded in sg-oai-sb; SoftBank NAV ($445.3B at Jun 30 2026), SB Energy's $439B/$430B backlog and $178B backlog capex, the IPO's size/valuation, DigitalBridge ($3.0–3.9B) — company-level, on the sbenergy entity; the Transource/FirstEnergy 'Grid Growth' JV ($1.076B, FERC ER26-1655 — no source says it serves PORTS-Pike, and its '$1.1B' collides with the unrelated ~$1.1B AEP Baku–Gavin 765 kV line); Meta/Alphabet/Broadcom guarantee comparables (ONE tracker article, no underlying filing among the documents read); site acreage (3,700/3,775/3,777 are one DOE reservation; 640/189/1,016/770 are overlapping sub-parcels — nothing sums them); the Oklo–Meta '1.2 GW' nuclear proposal at PORTS (a different 1.2 GW). Nvidia's $500B third-party compute-financing platforms (Apollo/BlackRock/Blackstone/Brookfield/Goldman/KKR MOUs, Aug 2026) and the Sep-2025 up-to-$100B OpenAI LOI / ~12–16 GW opportunity are Nvidia-wide context — nv-openai. Not adopted: boilermakers.org's '$4.2 million' grid upgrade (a unit slip), marketwise's '$20.9B operating loss' (28× the audited figure), the S-1 fee table's $100,000,000 read as IPO size, a '$40B annualized revenue' headline scraped from page furniture.

More between these companies

  1. Jan 27, 2026 updated Nov 21
  2. Sep 23, 2025 updated Nov 20
  3. Sep 22, 2025 updated Nov 18
  4. May 22, 2025 updated Nov 21
  5. Mar 7, 2025 updated Nov 20
  6. Feb 3, 2025
  7. Jan 21, 2025 updated Nov 21

Everything between OpenAI and SoftBank → · Everything between Nvidia and OpenAI → · Everything between Nvidia and SoftBank → · Everything between SB Energy and OpenAI → · Everything between SB Energy and SoftBank →