NIPSCO–Microsoft

Microsoft will buy power for a planned Indiana data center from NiSource's NIPSCO for 20 years, rising to 788 from 2031, fully funding the new supply, NiSource says; it awaits Indiana's approval.

A deal between Microsoft, NiSource

Why it matters

Microsoft's data center contract with NIPSCO pays for shared power resources through charges set to repay NiSource's investment. NiSource expects those charges to earn a higher return than NIPSCO's regulated business. The rates, minimum charges, termination payments and range of returns stay private until the contract reaches Indiana's utility regulator, which is expected by year-end.

Tap a figure for the line in its source.

NiSource gives Microsoft

  • of capacity and electric service for its data center in NIPSCO's northern Indiana territory, from 2028 and rising each year to 788 from 2031, for 20 years after the data center is first energized; NIPSCO is to build the transmission to connect it
  • added to GenCo's pool, which supplies the contract under a NIPSCO–GenCo power purchase agreement and serves other large customers too: two 239 gas turbines GenCo plans to build, expected by the end of 2029, and a 600 MW battery it is to rent (below). NiSource: 'Microsoft fully funds all generation and transmission required to serve its load'
  • battery (2,400 MWh) that a company of AGP Group is to build, own and run, and GenCo to rent for about 20.5 years from the first phase's start, expected by Dec 1, 2027, for about $2.2B in all — a finance lease on NiSource's books, and void unless AGP signs a construction contract and an interconnection agreement by Jan 31, 2027

Microsoft gives NiSource

  • an initial capacity payment in 2026; from the second quarter of 2027 to the end of the term, monthly capacity charges on negotiated rates and actual use, subject to minimums, plus pass-through charges and an existing-system charge passed back to NIPSCO's other customers — set to repay NiSource's investment with a return in a range it does not disclose. No amount, rate or minimum is public
  • termination payments if the contract ends other than through NIPSCO's default, which NiSource believes will reimburse its investment; either side may end it on certain defaults, or if the IURC and FERC approvals it needs are not obtained

Oct 16, 2026 announced by NiSource; its 8-K on the battery toll is of the same dayupdated Nov 21, 2026signed in October 2026 disclosed by the parties

What happened

NIPSCO, NiSource's utility for northern Indiana, signed a contract to supply power and make capacity available to a Microsoft data center in its territory. The site is very likely the campus Microsoft is building in La Porte, though no deal document names La Porte as the site. The contract runs for 20 years from when the data center first gets power. Supply starts in 2028 and reaches 788 megawatts in 2031. NiSource Generation Company (GenCo), a NiSource affiliate set up for data centers, holds the shared pool of plants, batteries and power contracts that will supply the power. GenCo is to add about 1,100 megawatts for the deal. GenCo plans to build two gas turbines. A developer, AGP, will build and own a 600-megawatt battery, which GenCo will rent for about $2.2 billion over some 20 years. The rental takes effect only if AGP signs the contracts to build the battery and connect it to the grid by January 31, 2027. NiSource says Microsoft fully funds the generation and transmission it needs through charges set to repay NiSource's investment and give NiSource a return. NiSource also says the deal raises the savings it expects to pass on to its other customers from $1.4 billion to about $1.75 billion. The rates, minimum charges and termination payments are still private. The contract has yet to be filed with Indiana's utility regulator.

Sources 19 documents — 6 company releases · 4 SEC filings · 3 regulatory filings · 2 government statements · 2 other documents · 1 transcript · 1 press report

Research trail Found 85 documents and read 74 of them while checking this deal and related ones.

  1. SEC · SEC filingsec.gov
    States 7 figures: 788 MW contract capacity · term · payments · return · termination · supply · 239 MW turbines
  2. company releasenisource.com
    States 3 figures: announced · 1,100 MW pool addition · $1.75B customer savings
  3. SEC · SEC filingsec.gov
    States 3 figures: 600 MW battery toll · $2.2B toll payments · toll conditions
  4. investor-relations PDF · company releases1.q4cdn.com
    States $2.3B turbine capex
  5. SEC · SEC filingsec.gov
    States 80.1% genco
  6. Motley Fool · transcriptOct 28, 2026fool.com
    States approval path
  7. iedc.in.gov · government statementJun 4, 2024iedc.in.gov
    States campus
  8. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  9. company releasenisource.com
    Cited by the record; no single figure is quoted from it.
  10. other documentnisourcegenco.com
    Cited by the record; no single figure is quoted from it.
  11. press report (archived copy)datacenterdynamics.com
    Cited by the record; no single figure is quoted from it.
  12. company releaseApr 2026local.microsoft.com
    Cited by the record; no single figure is quoted from it.
  13. regulatory filingcdn.misoenergy.org
    Cited by the record; no single figure is quoted from it.
  14. regulatory filingcdn.misoenergy.org
    Cited by the record; no single figure is quoted from it.
  15. regulatory filingcdn.misoenergy.org
    Cited by the record; no single figure is quoted from it.
  16. company releaselocal.microsoft.com
    Cited by the record; no single figure is quoted from it.
  17. other documentabc57.com
    Cited by the record; no single figure is quoted from it.
  18. government statementecm.idem.in.gov
    Cited by the record; no single figure is quoted from it.
  19. company releaseJan 13, 2026blogs.microsoft.com
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: NiSource 10-Q for Q3 2026 (Oct 28 2026) — 'Microsoft Contract', pool and AGP passages; NiSource 8-K, Item 2.03 (Oct 16 2026: the AGP battery toll); NiSource release (Oct 16 2026); Q3 2026 earnings slides, release (ex. 99.1) and call (Oct 28 2026; Motley Fool transcript); 424B5 prospectus supplement (Nov 2 2026); NIPSCO's $57.5M release (Oct 28 2026); nisourcegenco.com; IEDC release (Jun 4 2024) and Microsoft's La Porte boards (Apr 2026) for the campus; DCD (Oct 19 2026); MISO's EPR statistics (Nov 3 2026), large-load list (Dec 2024) and ERAS requests for the contested cells and the note (read 2026-11) · as of Nov 2026

The evidence 17 sourced figures · 4 disputes

The record's headline NIPSCO–Microsoft: capacity and power for a northern Indiana data center for 20 years after it is first energized, expected in 2028, rising to 788 from 2031 — served from NiSource's GenCo pool, which it is to enlarge for the deal by ~1,100 MW (two 239 MW gas turbines and a 600 MW battery it is to rent for ~$2.2B if AGP meets the toll's Jan 2027 conditions), saying Microsoft fully funds the generation and transmission its load requires; the contract is not yet filed with Indiana's regulator

Size
capacity commitment from 2028, 788 MW from 2031 · 20-year initial term from first energization · supplied from GenCo's shared pool, to be enlarged by ~1,100 MW: two 239 MW gas turbines (~$2.3B on NiSource's slide, transmission and infrastructure included; by end-2029) + a 600 MW / 2,400 MWh battery to be rented from AGP for ~20.5 years under a toll not yet in force, ~$2.2B of storage payments (a finance lease) · Microsoft's charges, minimums and termination payments undisclosed · the savings NiSource expects for its other customers, all three GenCo customers together: $1.4B → ~$1.75B
When
Jun 3–4 2024 (Microsoft's $1B La Porte data center announced; NIPSCO 'working closely with Microsoft' on its energy needs) → Oct 15 2026 (GenCo signs the battery toll with AGP) → Oct 16 2026 (the agreement announced; the 8-K on the toll) → Oct 28 2026 (Q3 10-Q and call: 788 MW from 2031, the terms, the two turbines) → 2026 (Microsoft's initial capacity payment) → by end-2026 (the contract to be filed with the IURC) → by Jan 31 2027 (the toll's conditions due) → 1H 2027 (an IURC order sought) → Q2 2027 (monthly capacity charges begin) → by Dec 1 2027 (the battery's first phase expected) → 2028 (service expected to begin) → by end-2029 (the turbines expected) → 2031 (788 MW) → ~2048 (20 years after first energization, if that is in 2028 — our arithmetic)
Status
signed in October 2026 (the 10-Q; the battery toll on Oct 15) and announced Oct 16; not yet filed. NiSource expects to file the special contract with the IURC by year-end 2026 and seeks an order in the first half of 2027, under the expedited 90-to-120-day review set for its data-center contracts (Luhrs, Q3 call; slide 9: 'Expected by YE 2026'); the NIPSCO–GenCo PPA and the two turbines need the IURC's approval too, and either side may end the contract if the IURC and FERC approvals are not obtained. The battery toll takes effect only if AGP signs an EPC contract and an interconnection agreement by Jan 31 2027; nothing on file says it has. Service expected from 2028, full demand by 2031; the turbines by the end of 2029; the battery's first phase by Dec 1 2027
Structure
a special contract between Northern Indiana Public Service Company LLC (NIPSCO), NiSource's Indiana electric utility, and Microsoft Corporation, for capacity and electric service to Microsoft's data center in NIPSCO's territory, to be submitted to the Indiana Utility Regulatory Commission (IURC) for approval. The supply comes from GenCo's Pool Resource Assets — owned plants, batteries and contracted capacity serving several large customers, NIPSCO choosing which resources meet which load — under a power purchase agreement between NIPSCO and NiSource Generation Company LLC (GenCo), also to go to the IURC. GenCo is an affiliate of NIPSCO, not its subsidiary: its sole owner, Generation Holdings II, is 80.1% NiSource's and 19.9% two Blackstone Infrastructure affiliates'. For the deal GenCo plans to add two 239 MW F-frame combustion turbines it is to build under an EPC contract with Quanta (subject to IURC approval), and a Battery Storage System Tolling Agreement signed Oct 15 2026 with Atlas Storage 1 LLC, an indirect subsidiary of AGP Capital Holdings Pte. Ltd. (AGP Group): AGP is to develop, build, own and run a 600 MWAC / 2,400 MWh battery on the MISO grid; GenCo is to supply its charging power, direct its dispatch, keep its revenues and pay storage payments for ~20.5 years, and may buy it at set intervals and at the end. NIPSCO is to build the transmission to connect Microsoft's facilities
Programme
Time-to-power
Parties
Microsoft customer — Microsoft Corporation, which is to build, commission and run the data centers (NiSource's slide) and to take capacity and power from NIPSCO; its only words in the deal's documents are its energy-markets director's quote in NiSource's release · NiSource utility and generator — NIPSCO, its Indiana utility, holds the contract and is to build the transmission; GenCo, its 80.1%-owned generation affiliate, is to supply the load from its shared pool under a PPA with NIPSCO, build the two gas turbines and rent the AGP battery; NiSource Inc. files the disclosures
Record
disclosed / primary source · as of Nov 2026

Flows 2 as the record states them

  • NiSource → Microsoftpowercapacity and electric service to Microsoft's data center in NIPSCO's territory: a capacity commitment from 2028, rising each year to 788 MW from 2031, for 20 years after first energization; supplied from GenCo's shared pool, to be enlarged by ~1,100 MW for the deal — two 239 MW gas turbines GenCo is to build (by end-2029) and a 600 MW / 2,400 MWh battery it is to rent from AGP for ~20.5 years (a toll not yet in force) — under a NIPSCO–GenCo PPA, over transmission NIPSCO is to build
  • Microsoft → NiSourcepower-paymentsan initial capacity payment in 2026; from Q2 2027 to the end of the initial term, monthly capacity charges on negotiated rates and actual consumption, subject to specified minimums, plus pass-through charges and an existing system charge passed back to NIPSCO's other customers — structured to return NiSource's invested capital with an unlevered return in an undisclosed range; termination payments NiSource believes would reimburse its investment. No amount, rate or minimum is public

Resolved figures 17 each with the verbatim line from its document

  • announced
    first public on Oct 16 2026, in NiSource's release: 'a new long-term energy agreement with Microsoft for its previously announced northwest Indiana campus', with no contract value, load, generation mix or site, and 'Further operational and financial details' left to its third-quarter call. NiSource's 8-K of the same date, filed for GenCo's Oct 15 battery toll, never names Microsoft; the 10-Q says NIPSCO entered into the agreement 'In October 2026'. Microsoft's only words in the deal's documents are those of Jeff Riles, its senior director of energy markets, in the release: 'Microsoft has always been committed to paying our own way and identifying long-term solutions like this one to ensure that our data centers don't increase electricity prices for other ratepayers'
    “NiSource Inc. (NYSE: NI) announced today a new long-term energy agreement with Microsoft for its previously announced northwest Indiana campus.”
    NiSource release (Oct 16 2026) · nisource.com
  • contract-capacity788 MW
    a capacity commitment beginning in 2028 and rising to 788 MW from 2031 — utility load, not a count of chips; the yearly steps are not disclosed. NiSource's slide, on customer demand: 'Increasing annually starting in 2028, ramp to full demand by 2031', and '(Supports 788 MW)'. The release gives no megawatts for the load; its ~1,100 MW is the supply added for it (pool-addition). With Microsoft, NIPSCO's data-center commitments are 'expected to increase to 3,888 MW by the end of 2032' (the Nov 2 2026 prospectus). MISO's list of expedited reviews carries a NIPSCO 'Substation D 788MW Load Addition', naming no customer — a match on the number alone (campus-load)
    “In October 2026, NIPSCO entered into an agreement with Microsoft, which will be submitted to the IURC for approval, under which NIPSCO will provide capacity and electricity services to Microsoft’s data center facility to be located in NIPSCO’s service territory pursuant to a capacity commitment beginning in 2028 and increases to 788 MW commencing in 2031 (the “Microsoft Contract”).”
    NiSource 10-Q for Q3 2026 (Oct 28 2026) — MD&A, 'Microsoft Contract' · sec.gov
  • term20 years
    20 years after the data center is first energized — the 10-Q; the release: 'Microsoft is expected to begin taking electric service under a 20-year term starting in 2028'; NiSource's slide: '20-year initial contract term'. The two agree only if first energization comes in 2028, NiSource's expectation (service-start); the contract fixes no calendar end, and no renewal terms are disclosed. Longer than Alphabet's pool contract, a '15-year agreement' (NiSource's slide 7)
    “The initial term of the Microsoft Contract ends 20 years after the initial energization of Microsoft’s data center.”
    NiSource 10-Q for Q3 2026 — MD&A, 'Microsoft Contract' · sec.gov
  • payments
    what Microsoft pays, in the 10-Q's words: an initial capacity payment in 2026, then, from the second quarter of 2027 to the end of the initial term, monthly capacity charges 'based on negotiated rates and actual consumption (subject to specified minimum amounts throughout the initial term)', with 'certain pass-through charges' and an existing system charge 'used to pass savings back to existing electric customers' (customer-savings). Payments begin before service, expected in 2028. No amount, rate or minimum is disclosed, and the contract is not filed. NiSource's slide, on pricing: 'Capacity charge + pass through charges', 'Designed to ensure return on and of pool resource assets on an accelerated basis'
    “Microsoft will make an initial capacity payment in 2026, and commencing in the second quarter of 2027 through the end of the initial term, Microsoft will pay monthly capacity charges that are based on negotiated rates and actual consumption (subject to specified minimum amounts throughout the initial term), together with certain pass-through charges and an existing system charge which will be used to pass savings back to existing electric customers.”
    NiSource 10-Q for Q3 2026 — MD&A, 'Microsoft Contract' · sec.gov
  • return
    what the charges are built to earn: a return 'of and on our invested capital over the twenty-year initial term', with provisions to adjust the capacity charge 'designed to provide us with an unlevered internal rate of return on our invested capital over the initial term within a defined range' — the range undisclosed — which NiSource expects to give 'an overall realized return greater than that of NIPSCO’s current electric operations, driven by execution and financing', one that construction costs, operating performance and financing costs may move. This is the sense of the release's 'Microsoft fully funds all generation and transmission required to serve its load': Microsoft's charges repay what NiSource invests, with a return; the plants are GenCo's, or AGP's
    “These charges are structured to provide us with a return of and on our invested capital over the twenty-year initial term.”
    NiSource 10-Q for Q3 2026 — MD&A, 'Microsoft Contract' · sec.gov
  • termination
    either side may end the contract on certain defaults or if the IURC and FERC approvals are not obtained; if it ends other than through NIPSCO's default, Microsoft is required to make 'certain termination payments that we believe will be sufficient to reimburse us for our investment costs, and NIPSCO has certain obligations to mitigate' (the 10-Q). The amounts, and whether they are capped, are not disclosed. NiSource's slide: 'Certain termination protections in place, including reimbursement of expenses'
    “Either party may terminate the Microsoft Contract upon certain defaults or failure to obtain necessary related approvals from the IURC and FERC.”
    NiSource 10-Q for Q3 2026 — MD&A, 'Microsoft Contract' · sec.gov
  • approval-path
    how it gets approved: NiSource expects to file the special contract with the IURC by year-end 2026 and seeks an order in the first half of 2027, under the expedited 90-to-120-day review set for its data-center contracts (Michael Luhrs, its chief commercial officer, on the Oct 28 call; NiSource's slide 9: special contract filed with the IURC 'Expected by YE 2026'). The NIPSCO–GenCo PPA 'will be submitted to the IURC for approval' and 'The F-frame CTs will be subject to approval by the IURC' (the 10-Q); the release names 'receipt, timing and terms of required regulatory approvals in connection with the agreements' among its risks
    “Expect to file the special contract with the IURC by year end and are seeking an order in the first half of 2027, consistent with the expedited 90 to 120-day review framework established for our data center agreements.”
    NiSource Q3 2026 earnings call (Oct 28 2026; Motley Fool transcript) — Luhrs · fool.com
  • campus
    which data center: no deal document names it — the release says 'its previously announced northwest Indiana campus', the 10-Q 'Microsoft’s data center facility to be located in NIPSCO’s service territory'. The only such campus on file is La Porte, where a $1B Microsoft data center, 245,000 sq ft on 489 acres at the Radius Industrial Park, was announced in Jun 2024, and where NIPSCO said then that it had 'been working closely with Microsoft' on its energy needs (this quote). DCD: 'While not explicitly confirmed, it seems likely that the agreement will serve Microsoft’s under-construction data center in La Porte'; it also reports that Microsoft owns 939 acres in Mishawaka. The record does not assume the site
    “we have been working closely with Microsoft on plans to fulfill the energy needs for the new data center in the city of La Porte”
    IEDC release (Jun 4 2024), quoting NIPSCO's Vince Parisi · iedc.in.gov
  • supply
    from GenCo's Pool Resource Assets, not plants dedicated to Microsoft: NIPSCO 'will retain discretion to select and dispatch Pool Resource Assets to meet committed customer demand in a way that maintains reliability and efficiency without direct involvement or approval from specific customers', and 'will enter into a PPA with GenCo in connection with the Microsoft Contract, which will be submitted to the IURC for approval'; NIPSCO 'will construct transmission infrastructure to connect Microsoft facilities to the grid' (the 10-Q). The pool's other customers are Alphabet and, for part of its load, Amazon (NiSource's slide 26). After the deal it is ~1,900 MW (slide 27): Tipton 167 MW (a build-transfer agreement), Mitchell 100 MW, the two turbines, the AGP battery, Nebo 75 MW and ~500 MW of contracted generation
    “The customer’s electricity supply under the Microsoft Contract will be provided through Pool Resource Assets.”
    NiSource 10-Q for Q3 2026 — MD&A, 'Microsoft Contract' · sec.gov
  • pool-addition1,100 MW
    about 1,100 MW added to GenCo's pool for the agreement — 'roughly 500 megawatts of combustion turbines and 600 megawatts of battery storage' (Luhrs, on the Q3 call); NiSource's slide: '~1,100 megawatts of pool resource assets' and 'Transmission infrastructure'. The filed parts are the two 239 MW turbines (turbines) and the 600 MWAC AGP battery (battery-toll), 1,078 MW together (our sum). Supply, not Microsoft's load (788 MW, contract-capacity). The release calls the whole 'GenCo-owned'; the battery is AGP's (pool-ownership). Its next words: 'Microsoft fully funds all generation and transmission required to serve its load'
    “The GenCo-owned pool portfolio will be increased by approximately 1,100 MW with NIPSCO and GenCo to provide transmission and generation infrastructure to ensure adequate assets to serve Microsoft’s data center and NIPSCO’s customers while providing a safe, reliable, and coordinated power supply.”
    NiSource release (Oct 16 2026) · nisource.com
  • turbines239 MW
    two 239 MW F-frame combustion turbines for the pool (478 MW, our sum; 'roughly 500 megawatts' on the call). GenCo has signed the F-Frames EPC Contract with Quanta and equipment supply contracts, 'including a contract to acquire turbines'; 'we believe that the F-frame CTs should reach commercial operation by the end of 2029', though 'The target price, project scope and project schedule under the F-Frames EPC Contract are subject to change', and 'The F-frame CTs will be subject to approval by the IURC' (the 10-Q). Where they will stand is not disclosed
    “GenCo also plans to construct two 239 MW F-frame CTs to be added to the Pool Resource Assets.”
    NiSource 10-Q for Q3 2026 — MD&A, 'Data Center Strategy & Pool Resource Assets' · sec.gov
  • turbine-capex$2.3B
    ~$2.3B on NiSource's slide for the two turbines' line — 'Inclusive of transmission investment', its note says: 'anticipated capital expenditures in connection with capacity resources expected to be owned', leaving out 'PPAs and market purchases' (the AGP battery among them), which 'will also require significant cash payments'. Asked on the call about $2.3B for the turbines, the CFO, Shawn Anderson: 'All the transmission and infrastructure is also included … So it is not just the 2 f frame CTs', and of the generation alone, 'We have not disclosed that' — so no cost per kilowatt can be worked out
    “Combustion Turbine 1 239 MW Full Ownership $2.3B Pre-Construction Combustion Turbine 2 239 MW Full Ownership Pre-Construction”
    NiSource Q3 2026 earnings slides (Oct 28 2026), slide 27 · s1.q4cdn.com
  • battery-toll600 MW
    a Battery Storage System Tolling Agreement signed Oct 15 2026 between GenCo and Atlas Storage 1 LLC, an indirect subsidiary of AGP Capital Holdings Pte. Ltd.: AGP is to build, own and run a 600 MWAC / 2,400 MWh battery on MISO's grid — four hours at full power (our arithmetic); GenCo is to supply the electricity that charges it, at its own expense, instruct its dispatch and keep the economic benefit of its capacity, energy and other services, if the toll takes effect (toll-conditions). The delivery term 'is expected to be approximately twenty and a half years' (~20.5), from the first phase's commercial operation, 'expected by December 1, 2027'; GenCo has 'an exclusive and irrevocable option to purchase the Project at specified intervals during and at the end of the delivery term'. The release: 'In connection with the Microsoft agreement, GenCo has contracted 600 MW of battery storage', to be added to the pool 'designed to serve multiple large-load customers'; the 8-K never names Microsoft. Its site is not stated (note)
    “On October 15, 2026, NiSource Generation Company LLC (“GenCo”), a subsidiary of NiSource Inc. (the “Company”), entered into a Battery Storage System Tolling Agreement (the “Tolling Agreement”) with Atlas Storage 1 LLC, an indirect subsidiary of AGP Capital Holdings Pte. Ltd. (“AGP Group”), pursuant to which AGP Group will develop, construct, own, and operate a 600 MWAC / 2,400 MWh stand-alone battery energy storage system (the “Project”) interconnected to the electric transmission system operated by the Midcontinent Independent System Operator, Inc. (“MISO”).”
    NiSource 8-K (Oct 16 2026), Item 2.03 · sec.gov
  • toll-payments$2.2B
    about $2.2B of storage payments over the ~20.5-year delivery term — 'regular storage payments based on a fixed rate (subject to certain adjustments) and the Project’s actual power capacity'. A nominal sum over two decades, not a construction cost or a present value, and paid by GenCo, not by Microsoft. NiSource expects to account for the toll 'as a finance lease obligation under FASB ASC Topic 842' (the 8-K; the 10-Q's Note 14 says the same). Slide 27 lists it as 'AGP Battery 600 MW PPA', outside its owned-capital totals
    “GenCo’s aggregate storage payments over the delivery term are expected to be approximately $2.2 billion.”
    NiSource 8-K (Oct 16 2026), Item 2.03 · sec.gov
  • toll-conditions
    not yet in force: the toll takes effect only if AGP signs an EPC contract and an interconnection agreement 'reasonably satisfactory to AGP Group' by Jan 31 2027; nothing on file says either is signed. The 8-K also lists 'the receipt, timing and terms of required regulatory approval in connection with the Tolling Agreement' among its risks
    “Effectiveness of the Tolling Agreement is conditioned upon AGP Group’s execution of a contract for the engineering, procurement, and construction of the Project and an interconnection agreement reasonably satisfactory to AGP Group, in each case by January 31, 2027.”
    NiSource 8-K (Oct 16 2026), Item 2.03 · sec.gov
  • genco80.1%
    who owns the supply: GenCo — NiSource Generation Company LLC, formerly NIPSCO Generation LLC — is NIPSCO's affiliate, not its subsidiary. Its sole owner, Generation Holdings II, has been 80.1% NiSource's since Oct 2025, when a 19.9% interest was issued to two Blackstone Infrastructure affiliates for $35.2M in cash (the 10-Q); its purpose is to 'own and operate GenCo, which will acquire and build generation assets and provide capacity and electricity to support our data center customers'. It serves large loads 'under a structure designed to protect existing Northern Indiana Public Service Company LLC (NIPSCO) electric customers from incremental costs', and 'Large-load customers fully fund the generation and infrastructure required to serve their needs' (the release) — said of all three: NIPSCO's Oct 28 release names its 'previously announced agreements with Amazon, Alphabet and Microsoft' and says 'Under those agreements, large-load customers will fund the infrastructure needed to serve them'. Across its three customers, 3,578 MW of GenCo-built generation and capacity is planned against 3,888 MW of committed capacity by the end of 2032 (this prospectus)
    “We have announced plans to construct, through NiSource Generation Company LLC (formerly known as NIPSCO Generation LLC), an affiliate of NIPSCO in which we own an 80.1% indirect interest, 3,578 MW of generation and capacity assets to serve our data center customers, further supported by BTAs, capacity agreements and market capacity purchases as needed.”
    NiSource 424B5 prospectus supplement (Nov 2 2026) · sec.gov
  • customer-savings$1.75B
    NiSource's projection for NIPSCO's other electric customers, all three GenCo customers together: ~$1.75B, up from the $1.4B it gave before Microsoft, 'equating to as much as $140 per customer annually' — 'approximately $140 per year for an average residential customer' at full ramp (Lloyd Yates, its chief executive, on the call) — as bill credits expected to begin in the first quarter of 2027 (NIPSCO's Oct 28 release; 'as early as January pending IURC approval', Yates). Under the contracts 'a portion of the revenues generated through their contracts will be returned directly to existing NIPSCO electric customers' (the Oct 28 release); for Microsoft, through the existing system charge (payments). No figure is given for Microsoft alone: ~$0.35B is a subtraction ($1.75B − $1.4B) that assumes the two estimates share a basis. The span and basis differ by document (savings-horizon); no regulator has reviewed the Microsoft part. Not the $57.5M credit NIPSCO announced on Oct 28, which 'builds on' the $1.75B
    “The agreement builds on the previously disclosed $1.4 billion expected customer savings over the life of data center customer contracts, increasing total expected NIPSCO electric customer savings to approximately $1.75 billion, equating to as much as $140 per customer annually.”
    NiSource release (Oct 16 2026) · nisource.com

Contested figures 9 not reconciled — every position side by side, with its source and tier

campus-load2 positions, side by side
788 MW from 2031 — the contract's capacity commitment (the 10-Q; slide 8: '(Supports 788 MW)'), the only load a deal document gives. MISO's Nov 2026 expedited-review statistics list a 'Substation D 788MW Load Addition' under NIPSCO, expected in service Dec 31 2027 and 'Under Study', naming no customer: the same number, not a confirmation NiSource 10-Q for Q3 2026; Q3 2026 earnings slides; MISO EPR statistics (Nov 3 2026)
538 MW, for 2032 — 'Microsoft* LaPorte, Indiana' in MISO's list of large loads announced in its regions ('Updated December 6, 2024'), which says its data 'is from public announcements and publicly available information' and is 'Not intended for reliance or planning purposes', and names no announcement for the figure. Two years older than the contract, perhaps another phase or scope — or, if the campus is not La Porte, another site MISO, large-load announcements list (updated Dec 6 2024)
pool-ownership2 positions, side by side
GenCo's — 'The GenCo-owned pool portfolio will be increased by approximately 1,100 MW' (the release); 'The Genco owned pool portfolio will be increased by approximately 1.1 thousand megawatts including roughly 500 megawatts of combustion turbines and 600 megawatts of battery storage' (Luhrs, on the call) NiSource release (Oct 16 2026); Q3 2026 call (Motley Fool transcript)
600 MW of it AGP's — the battery is one AGP Group 'will develop, construct, own, and operate', GenCo renting it with an option to buy (the 8-K), and slide 27 lists it as 'AGP Battery 600 MW PPA' beside the turbines' 'Full Ownership'; only the two 239 MW turbines are to be GenCo's own unless it buys the battery. 'GenCo-owned' may describe the portfolio rather than each asset; no document says NiSource 8-K (Oct 16 2026); Q3 2026 earnings slides
savings-horizon2 positions, side by side
over the life of the data-center contracts — the release: 'the previously disclosed $1.4 billion expected customer savings over the life of data center customer contracts, increasing total expected NIPSCO electric customer savings to approximately $1.75 billion'. Microsoft's contract runs 20 years from first energization, Alphabet's 15 (term) NiSource release (Oct 16 2026)
over the next 15 years — GenCo's website: 'We currently expect to generate approximately $1.75 billion in savings for existing NIPSCO electric customers over the next 15 years'. A total over contract lives that include a 20-year contract can run past 15 years, so the two spans agree only if the savings all fall within the first 15; neither document says whether the sum is nominal or discounted nisourcegenco.com (read Nov 2026)
service-start3 positions, side by side
2028 — NiSource: 'Microsoft is expected to begin taking electric service under a 20-year term starting in 2028' (the release); slide 9: first load energization 'Expected 2028', full ramp 'Expected by 2031'; the 10-Q: a capacity commitment 'beginning in 2028' NiSource release (Oct 16 2026); Q3 2026 earnings slides; 10-Q for Q3 2026
the end of 2027, for the wires — MISO expects NIPSCO's 'Substation D 788MW Load Addition' in service on Dec 31 2027 (under study), if that is this load: the customer is not named (campus-load) MISO EPR statistics (Nov 3 2026)
early spring 2029 for the first building — Microsoft's La Porte boards (Apr 2026): 'First datacenter building construction complete – Early Spring of 2029', the second in mid-spring and the third in 'Winter of 2029', with the caveat 'Construction completion date does not indicate datacenter operation/ availability' — if La Porte is the campus (campus) Microsoft La Porte community-meeting boards (Apr 2026)

Scope note what this record leaves to other records

Not this record: NiSource's Amazon and Alphabet contracts (on the nisource entity) — with the savings dispute in Amazon's IURC case, the Schahfer gas plant's in-service date and the IURC's GenCo orders; NiSource's company-wide figures — the $14.0–14.5B of planned data-center expenditures for all three customers (Q3 10-Q), a relabeled measure whose rise from the Q2 10-Q's $9.25–9.75B is not Microsoft's cost, the ~$8B GenCo capital plan for 2027–2033 and GenCo's EPS guidance (on the entity) — and NIPSCO's 2024 and 2026 resource plans; the $57.5M credit NIPSCO announced on Oct 28 2026, which 'builds on' the $1.75B; the La Porte campus itself — its jobs (up to 200 by the end of 2032 in the 2024 announcement, more than 600 for the first phase in Microsoft's groundbreaking post), land (489 acres in 2024, ~500 in Microsoft's 2026 boards, about 1,200 more annexed to the east, ABC57), buildings (six in the first phase and 17 on an expanded plot, DCD — 'How many of these will be data centers is unclear') and its 42 emergency diesel generators of 3,000 ekW each (IDEM's air-permit application: backup, not load); Microsoft's 7.9 GW of new generation 'contracted to add' across MISO (its Jan 2026 post), which predates this deal. Where the battery stands is not stated: MISO's fast-track (ERAS) list carries a 600 MW 'Atlas Storage LLC' battery request on NIPSCO's Babcock–Stillwell 345 kV line in La Porte County, in service requested Oct 1 2027 — the same name and size as the toll's, though no document links them — and NIPSCO's own 600 MW battery request at Malden, in Porter County, is a different project. Not adopted: '408 megawatts' for the two turbines (an analyst's question in the transcript; the 10-Q says two of 239 MW, management 'roughly 500'); the transcript's summary bullet, 'adding 1,100 megawatts of capacity', easy to take for Microsoft's load (788 MW); '$1.7 billion' (the chief executive's spoken rounding of $1.75B); '$0.40 to $0.60' of GenCo EPS (the superseded range, corrected on the call to $0.52–$0.68 for 2033).

More between Microsoft and NiSource

The record holds no other deal between them.

Everything between Microsoft and NiSource →