Hut 8 Beacon Point, Nueces County TX

Hut 8 has leased 704 of data-center capacity it is building in Texas, $19.6B of rent over two 15-year leases, to a tenant it never names — reportedly Nvidia.

A deal between Hut 8, Nvidia, Lambda, Anthropic

Why it matters

Hut 8's $4.25B project bond depends on rent from a tenant its filings never name. Press reports citing anonymous sources say Nvidia holds the lease, Lambda installs Nvidia chips and Anthropic buys the output. If the reports are right, bondholders' exposure runs through Nvidia's own products, though no party confirms the chain at Beacon Point.

Tap a figure for the line in its source.

Nvidia gives

  • of rent over two 15-year leases, up to $50.2B with all renewals; tenant named only by the press → Hut 8
  • space at the site plus the Nvidia chips Lambda installs there — reported, terms undisclosed → Lambda

Hut 8 gives Nvidia

  • of data-center capacity in two halves, first halls due Q3 2027 and Q2 2028

Anthropic gives Lambda

  • for computing at the site, per anonymous sources; Anthropic's IPO filing describes agreements with Lambda but names no site; separate from the rent

Lambda gives Anthropic

  • disputedof computing, per press reports that disagree on how much

May 6, 2026 disclosed in Hut 8's Q1 results releaseupdated Nov 19, 2026signed: Phase 1 lease dated Mar 12 2026 disclosed by the parties

What happened

Hut 8, a bitcoin miner turned data center landlord, is building a one-gigawatt campus called Beacon Point near Corpus Christi, Texas. It signed two 15-year leases with a single tenant. Each covers 352 megawatts of computing load and is worth about $9.8 billion in rent over the base term. In June 2026, a Hut 8 subsidiary borrowed $4.25 billion in the bond market to build the first phase. The bonds carry a 6.129% coupon, or interest rate, and an investment-grade Baa2 rating. The bonds are non-recourse to the parent company. The landlord has never named the tenant. It describes the tenant only as investment-grade, with a “multi-trillion-dollar market capitalization.” The bond documents describe it as “rated AA- or higher.” The tenant's identity comes only from press reports. In July, the Financial Times reported that the tenant is Nvidia. On August 31, the Wall Street Journal reported that Nvidia holds the lease and Lambda installs Nvidia chips in the buildings. Lambda is a cloud provider Nvidia has invested in. The Journal also reported that Anthropic buys the resulting computing power from Lambda for about $35 billion. The six-year term comes solely from the news agency AFP, which got it from a single source. None of the four companies has confirmed that any of these reported arrangements take place at Beacon Point. Anthropic's October 2026 IPO filing describes its agreements with Lambda without naming a site, a landlord or Nvidia's lease. Those agreements have a separate deal record. The reported $35 billion covers a compute purchase. The filed $19.6 billion covers rent. The record never adds the amounts for these separate contracts together.

Sources 33 documents — 16 SEC filings · 11 press reports · 3 company releases · 1 other document · 1 transcript · 1 research note

Research trail Found 228 documents and read 216 of them while checking this deal and related ones.

  1. SEC filingsec.gov
    States 6 figures: $4.25B notes principal · notes no guarantee · phase 2 financing · construction status · notes schedule · 6.27% notes cost and mark
  2. SEC filingsec.gov
    States 5 figures: 352 MW phase 2 lease · $9.8B phase 2 terms · 704 MW campus contracted capacity · $19.6B campus contract value · notes rating security recourse
  3. SEC filingsec.gov
    States 5 figures: $50.2B renewal ceiling · 704 MW tenant same for both phases · 1,000 MW utility interconnection · energization target · 57% dsx redesign
  4. SEC filingsec.gov
    States 2 figures: $9.8B phase 1 lease · $25.1B phase 1 options and delivery
  5. Hut 8 · SEC filingsec.gov
    States 2 figures: phase 1 lease date · qualifying tenant list
  6. SEC filingsec.gov
    States 2 figures: tenant as stated · 352 MW notes use of proceeds
  7. SRN News · press reportsrnnews.com
    States 2 figures: $35B reported deal value · 350 MW reported capacity
  8. Yahoo Finance · press reportfinance.yahoo.com
    States 2 figures: reported lessee · no party confirms
  9. PR Newswire · company releaseprnewswire.com
    States notes pricing
  10. SEC filingsec.gov
    States 6.13% notes independent holder
  11. a hosted document · other documentcdn.sanity.io
    States $9–11M capex guidance
  12. Hut 8 · company releasehut8.com
    States $17B two phase capital investment
  13. Nvidia · SEC filingsec.gov
    States $20B nvidia third party leases
  14. TNW · press reportthenextweb.com
    States ft names nvidia
  15. Yahoo Finance · press reportfinance.yahoo.com
    States reuters could not verify
  16. Yahoo Finance · press reportfinance.yahoo.com
    States reported term
  17. Investing.com · press report (archived copy)investing.com
    States reported chain
  18. press reportblockspace.media
    States 1 GW batch zero status
  19. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  20. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  21. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  22. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  23. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  24. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  25. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  26. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  27. company releaseprnewswire.com
    Cited by the record; no single figure is quoted from it.
  28. transcriptAug 11, 2026fool.com
    Cited by the record; no single figure is quoted from it.
  29. press report (archived copy)datacenterdynamics.com
    Cited by the record; no single figure is quoted from it.
  30. press reportglobaldatacenterhub.com
    Cited by the record; no single figure is quoted from it.
  31. press reportthenextweb.com
    Cited by the record; no single figure is quoted from it.
  32. press reportSep 1, 2026247wallst.com
    Cited by the record; no single figure is quoted from it.
  33. research noteeventhorizoniq.substack.com
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: Hut 8 8-K Items 1.01/2.03 + ex-4.1 indenture (2026-06-10), 8-K ex-99.1 (2026-06-05), 8-K Item 7.01 ex-99.1 (2026-06-04, furnished), 8-K Item 8.01 + ex-99.1 (2026-07-20), Q1-2026 and Q2-2026 10-Qs, Q1 (2026-05-06) and Q2 results releases + Q1 call (company transcript) and Q2 call (Motley Fool transcript), PRNewswire releases, hut8.com; NVIDIA 10-Q qtr ended 2026-07-26; Aristotle Core Bond N-PORT-P; FT via TNW / Reuters-Yahoo (Jul 28), WSJ via Bloomberg-Yahoo / Investing.com (Wayback) / GDCH / DCD (Wayback), Reuters via srnnews, AFP via Yahoo (Aug 31–Sep 1); Blockspace (Sep 8); eventhorizoniq (read 2026-09); Hut 8 Q3-2026 10-Q and Q3 release (8-K ex-99.1, furnished) (Nov 4 2026) (updated 2026-11); Anthropic S-1/As of Nov 10 and 17 and 424B4 of Nov 19 2026 read for the site, the landlord and the Lambda facility lease · as of Nov 2026

The evidence 36 sourced figures · 5 disputes

The record's headline Hut 8 Beacon Point, Nueces County TX: two 15-year leases for 704 of critical IT, $19.6B base term ($50.2B with options), to a tenant Hut 8 describes only as 'rated AA- or higher' — Nvidia, per the FT; $4.25B 6.129% Baa2 non-recourse notes fund Phase 1; the WSJ adds a ~$35B Anthropic–Lambda compute deal on ~350 MW with Nvidia holding the lease

Size
$19.6B base-term rent / $50.2B with all options · 704 MW critical IT (filed; tenant unnamed) · $4.25B 6.129% notes for Phase 1 · reported only, for this site: ~$35B / ~350 MW / six years, Anthropic → Lambda (Anthropic's S-1 describes its Lambda agreements, naming no site — anth-lambda)
When
Mar 12 2026 Phase 1 lease (disclosed May 6) → Jun 9 2026 notes → Jul 20 2026 Phase 2 lease → Jul 28 FT names Nvidia → Aug 31 WSJ: Anthropic–Lambda ~$35B; 15-year terms + 3 × 5-year options per lease; delivery Q3 2027 / Q2 2028
Status
signed: Phase 1 lease dated Mar 12 2026 (amended Apr 29), notes closed Jun 9 2026 at par, Phase 2 lease signed Jul 2026; under construction at Sep 30 2026 (Hut 8's Q3 10-Q: both phases; substation, foundation and utility work at Phase 1, civil design for Phase 2 — its release), nothing delivered — energization Q1 2027, first halls Q3 2027 / Q2 2028 (targets; ERCOT base-load status conditional); Phase 2 not yet financed ('actively pursuing financing'); neither lease filed as an exhibit; the Anthropic–Lambda layer at this site is reported only — no party places it here, and Anthropic's S-1 (Oct 26 2026) describes its Lambda agreements without naming a site (anth-lambda)
Structure
landlord side, FILED: two 15-year triple-net leases of 352 MW critical IT each — ~500 MW utility each, on a 1,000 MW AEP Texas interconnection for the campus — with a 3% annual escalator ('take-or-pay' is the results releases' word — furnished, May 6 and Aug 2026; the 10-Qs and 8-Ks say triple-net only), three 5-year renewal options per lease, to one tenant Hut 8 describes only by rating; Phase 1 built with $4.25B of 6.129% senior secured notes due Nov 30 2042 issued by Beacon Point DC LLC — non-recourse to Hut 8 Corp., first-priority liens on the issuer's assets plus a pledge of its equity by Beacon Point Holding LLC, Baa2 (Moody's), interest from Nov 30 2026, amortising from May 30 2030, par call May 30 2042 — financing the six Phase 1 halls ONLY (Phase 2 financing undisclosed in the documents on file). Reported layer, WSJ, unconfirmed at this site (Anthropic's S-1 since describes its Lambda agreements, naming no site — anth-lambda): Nvidia holds the lease and 'reached its own agreement with Hut 8 some weeks before'; Lambda installs Nvidia chips, pays Nvidia an undisclosed amount for the space, and sells the compute to Anthropic under a ~$35B agreement covering ~350 MW (the six-year term is AFP's single source, not the Journal's — its retellings state no term)
Programme
Nvidia circular capital
Parties
Hut 8 landlord, developer and project-bond issuer (Beacon Point DC LLC, pledged by Beacon Point Holding LLC); names no tenant in any filing or release · Nvidia REPORTED lessee (FT Jul 28, five people; WSJ Aug 31) — unnamed by Hut 8, which prints NVIDIA only as the DSX reference architecture the halls are built to and, in the indenture, as the first of six Qualifying (replacement) Tenants — the identical list, Nvidia-first, that Hut 8's River Bend indenture carries for its Fluidstack tenancy, i.e. boilerplate, not a naming; reported chip supplier to Lambda and investor in both Lambda and Anthropic; its own 10-Q carries $20B of 'data center leases not commenced for third party' that it matches to no site · Lambda REPORTED operator — installs Nvidia chips, pays Nvidia an undisclosed amount for the space, sells the compute to Anthropic (WSJ); has said nothing; its $926M term loan B (Aug 27) funds GPUs for 'a committed customer deployment with an investment-grade offtaker', unnamed · Anthropic REPORTED end buyer at this site — ~$35B for ~350 MW (WSJ; Reuters and Bloomberg one anonymous source each), over six years per AFP's single source (the WSJ retellings state no term); declined to comment; no Anthropic document was on file for this record — its S-1 (Oct 26 2026) has since described agreements with Lambda without naming a site (anth-lambda)
Capital
the seller's own money or backing comes back as its sales
Record
disclosed / primary source · as of Nov 2026

Flows 5 as the record states them

  • Nvidia → Hut 8lease-payments$19.6B of base-term rent across both leases ($9.8B each over 15 years incl. the 3% escalator; $50.2B if all six 5-year options are exercised) — FILED by the landlord against an UNNAMED tenant; Nvidia sits on this flow only on the FT/WSJ reporting. Rent starts on delivery (Q3 2027 / Q2 2028); Hut 8's expected average annual NOI is $1.31B for the campus
  • Hut 8 → Nvidiacapacity704 MW of critical IT in two 352 MW phases (six halls per phase, NVIDIA DSX reference architecture, ~500 MW utility each) on 1,000 MW of AEP Texas interconnection; Phase 1 halls from Q3 2027, Phase 2 from Q2 2028 — targets, not deliveries; ERCOT base-load status conditional
  • Lambda → Nvidiaspace-rentundisclosed — 'Lambda pays NVIDIA an undisclosed amount for access to the space' (WSJ via GDCH); 'not immediately clear' (WSJ via Investing.com). The Next Web's retelling has Lambda holding the lease itself — see contested lease-chain
  • Lambda → Anthropiccompute~350 MW (Reuters' source; the WSJ per DCD, Bloomberg per GDCH) — whether that is one 352 MW phase or a slice of both is not established (see contested capacity-covered); 'to meet growing demand for Anthropic's Claude AI' (Reuters)
  • Nvidia → Lambdachip-salesundisclosed — the compute Lambda installs is 'chips purchased from Nvidia, which is also an investor in Lambda' (WSJ via Investing.com); Lambda's Aug-2026 $926M term loan B funds 'the purchase and deployment of GPU infrastructure supporting a committed customer deployment with an investment-grade offtaker' — offtaker unnamed

Resolved figures 36 each with the verbatim line from its document

  • phase-1-lease$9.8B
    352 MW of critical IT (~500 MW utility), 15-year triple-net lease, ~$9.8B base contract value incl. 3% annual escalators, expected average annual NOI ~$655.0M — Hut 8's Q1-2026 10-Q, where the tenant is 'a multi-trillion-dollar market capitalization, high-investment-grade technology company'. Disclosed May 6 2026 (Q1 results release, furnished: 'a high-investment-grade tenant … on a triple-net, take-or-pay basis'; PRNewswire release, tenant profile: 'Confidential, high-investment-grade company'); never 8-K'd under Item 1.01 on its own. The first hall was scoped for 224 MW and re-designed to NVIDIA's DSX architecture for 352 MW 'within the same land and utility footprint', which management says lifted base-term value 'by $3.6 billion, from $6.2 to $9.8 billion' (Q1 call)
    “We entered into a long-term triple-net lease with a multi-trillion-dollar market capitalization, high-investment-grade technology company at our Beacon Point Campus, located in Nueces County, Texas, representing a significant infrastructure partnership with a base contract value of approximately $9.8 billion over a 15-year term, inclusive of 3% annual rent escalations and expected to generate average annual net operating income (“NOI”) of approximately $655.0 million.”
    Hut 8 Q1-2026 10-Q, Q1 2026 Highlights — Beacon Point Lease · sec.gov
  • phase-1-lease-date
    dated March 12, 2026, amended April 29, 2026 — the only dated statement of the Phase 1 signing anywhere on file, in the indenture's definition of 'Data Center Lease'. The 10-Q dates it only to 'Q1 2026 Highlights'. The same definitions clause defines 'Tenant' as 'the tenant that is party to the Data Center Lease, or any Qualifying Tenant appointed pursuant to the terms of this Indenture' — no name here either. The lease itself is not an exhibit to anything: rent per MW, delay and termination rights, security and any guaranty are unknown
    “means the lease agreement dated March 12, 2026, between the Issuer, as landlord, and the Tenant, as amended by the first amendment to data center lease agreement dated April 29, 2026”
    Indenture, Jun-10 8-K ex-4.1 — Definitions · sec.gov
  • phase-1-options-and-delivery$25.1B
    three 5-year renewal options take Phase 1's potential value to ~$25.1B (base $9.8B → ~2.56× over 30 years, consistent with the 3% escalator compounding); 'Initial delivery is expected in Q3 2027' — a target the Phase 1 release repeats ('Initial data hall delivery expected in Q3 2027'). On the Q1 call the CFO said that 'beginning in Q2 2027, the data halls at River Bend and Beacon Point Phase 1 are expected to come online' — the two campuses together. The Q2 call's page summary (the transcript site's, not the spoken text) separates them: River Bend's initial halls in 'the second quarter of 2027', Beacon Point Phase 1's data hall delivery in 'the third quarter of 2027'. So Q3 2027 stands for Beacon Point. Rent, and therefore the notes' debt service, starts with delivery; the debt-service reserve in the indenture ($481,892,625 of construction-period interest) is what carries the coupon until then
    “The agreement includes three 5-year renewal options, extending potential total contract value to approximately $25.1 billion. Initial delivery is expected in Q3 2027.”
    Hut 8 Q1-2026 10-Q, Q1 2026 Highlights — Beacon Point Lease · sec.gov
  • phase-2-lease352 MW
    a second 352 MW / ~500 MW-utility lease signed in July 2026 'with the same high-investment-grade technology company that is the tenant for Beacon Point Phase 1', fully contracting the campus; NOI ~$655.0M/yr — the Phase 1 economics repeated ('substantially the same terms as the Phase 1 lease', Jul-20 release). Announced Jul 20 under Item 8.01 (the 8-K incorporates the release), not Item 1.01: like Phase 1, no lease document is filed
    “In July 2026, we entered into a second long-term triple-net lease with the same high-investment-grade technology company that is the tenant for Beacon Point Phase 1, fully contracting our Beacon Point campus in Nueces County, Texas. Beacon Point Phase 2 comprises 352 MW of additional critical IT capacity (approximately 500 MW utility capacity) and is expected to generate average annual NOI of approximately $655.0 million.”
    Hut 8 Q2-2026 10-Q, Q2 2026 Highlights — Beacon Point Phase 2 Lease · sec.gov
  • phase-2-terms$9.8B
    ~$9.8B base contract value over a 15-year initial term incl. 3% annual escalators; three 5-year options → ~$25.1B; initial delivery from Q2 2028 — nine months after Phase 1's Q3 2027. How Phase 2 is financed is undisclosed: the $4.25B notes fund Phase 1 only (see notes-use-of-proceeds), and no second offering exists on file — the record does not extrapolate one (Hut 8's Q3 10-Q says it is 'actively pursuing financing': phase-2-financing)
    “The Beacon Point Phase 2 Lease has an estimated base contract value of approximately $9.8 billion over its 15-year initial term, including 3% annual rent escalators, and three five-year renewal options that could increase its potential value to approximately $25.1 billion. Initial delivery is expected to start in Q2 2028.”
    Hut 8 Q2-2026 10-Q, Q2 2026 Highlights — Beacon Point Phase 2 Lease · sec.gov
  • campus-contracted-capacity704 MW
    704 MW of critical IT contracted (2 × 352) against ~1 GW of utility capacity — the whole campus, one tenant. This is the figure 247wallst collapses into 'the Anthropic allocation' (see contested capacity-covered) and the '704 of 949 contracted megawatts' that Morgan Stanley's bear case (via eventhorizoniq) reads as single-counterparty concentration: 74% of Hut 8's contracted AI capacity sits with one unnamed tenant
    “The second lease fully contracts the Beacon Point campus, bringing Beacon Point’s total contracted critical IT capacity to 704 MW (approximately 1 GW utility capacity).”
    Hut 8 Q2-2026 10-Q, Q2 2026 Highlights · sec.gov
  • campus-contract-value$19.6B
    ~$19.6B aggregate base contract value and ~$1.31B expected average annual NOI across the two leases; ~$50.2B if all renewal options are exercised. Three landlord numbers for one campus, and the press has fused them with a fourth: FT's 'up to $50 billion' is this $50.2B ceiling read as a deal size; pulse2's '$50.2 billion lease' is the two welded; the WSJ's $35B is a different contract altogether (see contested headline-value). Base rent, not revenue: nothing is billable before Q3 2027. The Q3 results release (Nov 4, furnished) restates the $19.6B and about $1.3B of NOI 'on a triple-net, take-or-pay basis'; the Q3 10-Q, the filed document, restates neither, so the Q2 10-Q stays the filed source
    “Together, the two leases represent approximately $19.6 billion of aggregate base contract value and $1.31 billion of expected average annual NOI, with potential aggregate contract value of approximately $50.2 billion if all renewal options are exercised.”
    Hut 8 Q2-2026 10-Q, Q2 2026 Highlights · sec.gov
  • renewal-ceiling$50.2B
    $50.2B = 2 × $25.1B, the campus value if every one of the six 5-year options is exercised, i.e. rent through ~2058 on halls that do not exist yet; the Jul-20 release (filed under Item 8.01) states it as 'upside economics'. Carried so that it is never mistaken for a signed figure: the signed figure is $19.6B
    “Economics: Three 5-year renewal options per lease increase potential campus-level contract value to $50.2 billion if all options are exercised.”
    Hut 8 8-K ex-99.1 (Jul 20 2026, Item 8.01) — Transaction Highlights · sec.gov
  • tenant-same-for-both-phases704 MW
    one counterparty for the whole campus — 'the high-investment-grade company that executed the Phase 1 lease' doubled to 704 MW; the release's tenant profile line reads in full 'High-investment-grade company; the Phase 1 tenant'. Hut 8's descriptors across its documents, in order: 'a high-investment-grade tenant' (Q1 release) → 'a multi-trillion-dollar market capitalization, high-investment-grade technology company' (Q1 10-Q) → 'a high-investment-grade company (i.e., rated AA- or higher)' (Jun 8-Ks) → 'the Phase 1 tenant' (Jul 20). Never a name
    “The tenant, the high-investment-grade company that executed the Phase 1 lease, has doubled its contracted IT capacity at the campus to 704 MW.”
    Hut 8 8-K ex-99.1 (Jul 20 2026, Item 8.01) · sec.gov
  • utility-interconnection1,000 MW
    1,000 MW of utility capacity under an executed interconnection agreement with AEP Texas (AEP subsidiary), 'initial energization expected in Q1 2027' — the campus's whole power basis, with 'no incremental capacity required to serve the Phase 2 lease'. ~1,000 MW utility for 704 MW critical IT is a ~70% ratio, in line with the ~500 MW per 352 MW phase. What the grid side has NOT done: the ERCOT large-load review (PUCT Project 59142, Governor Abbott's Aug-3 audit directive) left the site's base-load designation conditional as of Sep 8 (see batch-zero-status)
    “The Transaction fully commercializes the Beacon Point campus against its 1,000 MW of utility capacity, secured under an interconnection agreement with AEP Texas for electric delivery service.”
    Hut 8 8-K ex-99.1 (Jul 20 2026, Item 8.01) · sec.gov
  • energization-target2027
    initial energization Q1 2027 — 'remains on schedule' as of Jul 20, with site preparation under way and long-lead equipment procured; first Phase 1 hall Q3 2027, first Phase 2 hall Q2 2028. All three are Hut 8 targets: a converted-miner greenfield with a 2027 date and a grid review still open, so this record's status line said 'nothing built' (it now says under construction, nothing delivered — construction-status)
    “Site preparation is underway, and long-lead critical equipment has been procured. Initial energization remains on schedule for Q1 2027.”
    Hut 8 8-K ex-99.1 (Jul 20 2026, Item 8.01) · sec.gov
  • dsx-redesign57%
    the one place Hut 8 prints 'NVIDIA' in connection with the tenant: the first Phase 1 hall was redesigned 'to NVIDIA's DSX reference architecture', giving 57% more IT capacity (224 → 352 MW) on the same land and utility footprint, and Phase 2 is 'a second 352 MW AI factory designed to NVIDIA's DSX reference architecture'. DSX is Nvidia's design standard for AI factories — Nvidia's own answer to the FT was that it 'is working with ecosystem partners … through the DSX AI factory architecture' — so the architecture is consistent with, and does not establish, Nvidia as the tenant
    “Hut 8 has designed the campus around its tenant's evolving requirements throughout development, including a redesign of the first data hall for Phase 1 to NVIDIA's DSX reference architecture, enabling 57% more IT capacity within the same land and utility footprint.”
    Hut 8 8-K ex-99.1 (Jul 20 2026, Item 8.01) · sec.gov
  • tenant-as-stated
    'a high-investment-grade company (i.e., rated AA- or higher) as of the date hereof' — the most specific thing the landlord has ever filed about its tenant, in the notes 8-K (Item 1.01) and the pricing release. AA- or higher narrows the field to a handful of the largest issuers, so the filing is consistent with the FT's Nvidia and equally with several other companies; no document on file rates any of them. It is a description, not an identification, and this record never promotes it
    “which data center facility will be leased to a tenant that is a high-investment-grade company (i.e., rated AA- or higher) as of the date hereof (the “Tenant”) pursuant to the Data Center Lease Agreement (as amended, the “Lease”)”
    Hut 8 8-K Item 1.01 (filed 2026-06-10) — Use of Proceeds · sec.gov
  • qualifying-tenant-list
    the indenture's replacement-tenant test — who may take over the lease without a rating-agency confirmation if the Tenant leaves: '(A) Nvidia Corporation, Apple Inc., Microsoft Corporation, Amazon.com, Inc., Alphabet Inc. (including Google LLC) and Meta Platforms, Inc.' or their guaranteed affiliates, else anyone with a Rating Agency Confirmation. Nvidia is FIRST on the list; the River Bend indenture (Apr 2026) carries the same six names, also Nvidia-first, plus a '$50.0 billion' enterprise-value alternative — and River Bend's tenant is Fluidstack USA IV Inc. under a Google guarantee, named in that indenture's own definitions, so the ordering demonstrably says nothing about who the tenant is. The tier-1 filing has been read as naming the tenant or pricing the deal. It does neither. The record carries it as what it is: the issuer's standard replacement-tenant boilerplate, which happens to start with Nvidia — not evidence
    “means either (i) any of (A) Nvidia Corporation, Apple Inc., Microsoft Corporation, Amazon.com, Inc., Alphabet Inc. (including Google LLC) and Meta Platforms, Inc. and any of their successors or assigns or (B) so long as the Person in clause (A) provides a guarantee, any of their respective controlled affiliates or (ii) any Person provided that the Issuer obtains a Rating Agency Confirmation”
    Indenture, Jun-10 8-K ex-4.1 — Definitions, 'Qualifying Tenant' · sec.gov
  • notes-principal$4.25B
    $4.25B of 6.129% senior secured notes due November 30, 2042, issued June 9 2026 by Beacon Point DC LLC (indirect wholly owned subsidiary) in a 144A/Reg S private offering, at 100% of principal, J.P. Morgan as representative of the initial purchasers, Wilmington Trust as trustee and collateral agent. Fully amortising; interest from Nov 30 2026. DCD's '$4.5bn' in the body of its pricing story contradicts its own headline and is not carried. Restated unchanged in the Q3 10-Q (Sep 30 2026: principal $4.25 billion), which adds that the notes 'were issued at par'
    “On June 9, 2026, Beacon Point DC LLC ("Beacon Point DC"), an indirect wholly owned subsidiary of the Company, issued $4.25 billion aggregate principal amount of 6.129% senior secured notes due November 30, 2042 (the "Beacon Point Notes") in a private offering.”
    Hut 8 Q3-2026 10-Q, Note 11 — Beacon Point Notes · sec.gov
  • notes-rating-security-recourse
    Baa2 (Moody's) — in the FILED 10-Q as well as the furnished Q2 release ('rated Baa2 and priced 20 basis points inside the issuance spread of the River Bend notes … without recourse to Hut 8 Corp.'); the Jun-4/5 documents say only 'investment-grade'. Secured by first-priority liens on substantially all of the issuer's assets and a pledge of the issuer's equity by its parent Beacon Point Holding LLC; non-recourse to Hut 8. 'first IG-rated non-recourse greenfield bond on an ex-miner site' is this record's framing, not a party claim — Hut 8's own superlative was for River Bend ('the first investment-grade construction financing for a single-sponsor data center project'); the Meridian Arc $5.7B 6.25% high-yield comparator (Fluidstack, Apr 2026) is on file only through secondary mentions and is not a cell here. S&P BBB-/Fitch/DSCR/PUE detail is on file only via ccir.io / GDCH summaries — tier 3, not carried. The Q3 10-Q repeats security and recourse in new words and does not restate the rating (notes-no-guarantee)
    “The Beacon Point Notes are rated Baa2 by Moody’s Ratings, secured by first-priority liens on substantially all assets of Beacon Point DC, other than certain excluded property, as well as a pledge of the equity interests in Beacon Point DC held by Beacon Point Holding LLC, the direct parent company of Beacon Point DC. The Beacon Point Notes are non-recourse to Hut 8.”
    Hut 8 Q2-2026 10-Q, Q2 2026 Highlights — $4.25 Billion Beacon Point Phase 1 Financing · sec.gov
  • notes-use-of-proceeds352 MW
    PHASE 1 ONLY: 'a turnkey data center, comprising six data halls with a combined total of 352 megawatts of critical IT capacity' on ~521 acres, plus the substation, debt-service reserves and fees. So the bond finances half the contracted campus; the second 352 MW has no disclosed financing. The 521 acres here vs 524 in the 10-K vs 525 on hut8.com is Hut 8 disagreeing with itself (see contested site-acreage)
    “The Issuer intends to use the proceeds from the Offering to (i) finance (1) the development and construction of a turnkey data center, comprising six data halls with a combined total of 352 megawatts (“MW”) of critical IT capacity, to be built on an approximately 521-acre property in Nueces County, Texas (the “Property”)”
    Hut 8 8-K Item 1.01 (filed 2026-06-10) — Use of Proceeds · sec.gov
  • notes-no-guarantee
    the Q3 10-Q says what stands behind the bonds, and what does not: 'The Beacon Point Notes are obligations solely of Beacon Point DC and are not guaranteed by the parent company, the tenant, or any of their respective subsidiaries or affiliates' — the Q2 10-Q said only that they are non-recourse to Hut 8. No tenant guarantee stands behind the notes: they are serviced from the lease ('Rent payable under the lease is expected to be the principal source of cash flow used to service the Beacon Point Notes'), and 'The data center is leased in its entirety to a high-investment-grade company under a triple-net lease' — still unnamed. Whether the lease itself carries a parent guaranty or other credit support, no filing says: the leases are not filed (phase-1-lease-date)
    “The Beacon Point Notes are obligations solely of Beacon Point DC and are not guaranteed by the parent company, the tenant, or any of their respective subsidiaries or affiliates.”
    Hut 8 Q3-2026 10-Q, Note 11 — Beacon Point Notes · sec.gov
  • phase-2-financing
    Phase 2 is not yet financed: 'We are actively pursuing financing for the development and construction of Beacon Point Phase 2', Hut 8's Q3 10-Q says, in the paragraph that notes the campus 'became fully contracted' in July. Its Nov 4 release (furnished) says it has 'Advanced financing plans for Beacon Point Phase 2, evaluating a range of structures', and its CEO that both campuses are expected 'to be funded entirely at the project level, without requiring equity issuance or recourse debt at the parent'. No offering, amount, lender or date is stated; the $4.25B of notes fund Phase 1 only (notes-use-of-proceeds), and Phase 2's first hall is targeted for Q2 2028 (phase-2-terms)
    “We are actively pursuing financing for the development and construction of Beacon Point Phase 2.”
    Hut 8 Q3-2026 10-Q, MD&A — Liquidity and Capital Resources · sec.gov
  • construction-status
    Hut 8's own stage for the campus moved by Sep 30 2026: both phases (500 MW of utility capacity each) are in 'Energy Capacity Under Construction', which its 10-Q defines as 'sites where we have executed definitive commercial agreements and commenced construction activities' — 1,330 MW with River Bend's 330 MW, against zero a year earlier. The Nov 4 release (furnished) says what began: 'commencement of construction of the campus substation, foundation work and underground utility work at Phase 1, and civil design for Phase 2'; initial data hall delivery is still targeted for Q3 2027 (Phase 1) and Q2 2028 (Phase 2), the same targets as before (phase-1-options-and-delivery, phase-2-terms), and its CEO says construction 'remains on track to meet our delivery targets'. No data hall is delivered
    “Energy Capacity Under Construction as of September 30, 2026 was 1,330 MW, comprised of the 330 MW River Bend site, 500 MW Beacon Point Phase 1 site, and the 500 MW Beacon Point Phase 2 site, compared to zero MW as of September 30, 2025.”
    Hut 8 Q3-2026 10-Q, MD&A — Energy Capacity Under Construction; Q3 release (8-K ex-99.1, furnished Nov 4 2026) for the work begun · sec.gov
  • notes-schedule
    interest semi-annually from Nov 30 2026; principal amortises from May 30 2030 (four years out — 'we pushed amortization from 2 years on River Bend to 4 years on Beacon Point', CFO, Q2 call) through maturity; make-whole before the May 30 2042 par call, par thereafter; mandatory offers at 101% on a change of control and at 100% on a Data Center Lease Termination Default; partial redemption at par if the debt-service coverage ratio falls below 1.1:1.0 after commencement. The lease is the only source of debt service, which is why the indenture polices the tenant's replacement (qualifying-tenant-list). The Q3 10-Q repeats the schedule and the redemption terms unchanged
    “Scheduled principal payments commence on May 30, 2030 and continue semi-annually through maturity. The Beacon Point Notes may be redeemed before the applicable par call date of May 30, 2042 at a make-whole redemption price and thereafter at 100% of the principal amount, in each case plus accrued and unpaid interest.”
    Hut 8 Q3-2026 10-Q, Note 11 — Beacon Point Notes · sec.gov
  • notes-pricing165
    T+165 bp, 20 bp inside the River Bend notes' spread (6.192%, Apr 2026) — the closing release; the offering's illustrative model is 'sculpted to a 1.34x DSCR to repay the debt completely by the end of the initial lease term' (Jun-4 launch 8-K ex-99.1 'Illustrative Financial Information', furnished under Item 7.01). Hut 8's own read of the sequence: a second investment-grade project bond, one notch better rated and tighter, six weeks after the first
    “At T+165 basis points, the Notes priced 20 basis points inside the River Bend notes issuance spread.”
    Hut 8 closing release (PRNewswire, Jun 9 2026) · prnewswire.com
  • notes-cost-and-mark6.27%
    6.27% effective rate, unchanged, after $46.4M of issuance costs ('Gross proceeds from the issuance were $4.25 billion and debt issuance costs were $46.4 million'). What moved is the mark: at Sep 30 2026 the notes' 'Unamortized debt issuance costs were $45.5 million, resulting in a net carrying amount of $4.20 billion' and the estimated fair value was $3.90B (Level 2) — down from $4.30B at Jun 30 (Q2 10-Q: slightly above par three weeks after issue), about 8% under the $4.25B of principal. The 10-Q gives no reason; the sister River Bend notes are marked $3.05B on $3.25B of principal in the same note. Carried at amortized cost; the fair value is disclosed beside it. Proceeds sit in restricted project accounts until drawn ('Unused proceeds from the River Bend and Beacon Point senior secured notes are held in restricted project accounts', Q3 10-Q)
    “As of September 30, 2026, the effective interest rate on the Beacon Point Notes was 6.27% and the estimated fair value was $3.90 billion, determined using Level 2 inputs.”
    Hut 8 Q3-2026 10-Q, Note 11 — Beacon Point Notes · sec.gov
  • notes-independent-holder6.13%
    the one genuinely independent corroboration of the notes on file: a registered bond fund's N-PORT-P holdings schedule listing 'Beacon Point DC LLC, 6.13%, 11/30/2042' (a 750,000 par position; the coupon rounded to two decimals) — a third party, with no relationship to Hut 8, reporting the instrument to the SEC. A second fund's N-PORT marks the sister River Bend notes ('HUT 8 DC LLC, 6.19%, 11/15/42'). Everything else about the bond, like everything about the leases, is issuer-stated
    “Beacon Point DC LLC, 6.13%, 11/30/2042 (a)”
    Aristotle Core Bond Fund N-PORT-P (holdings at 2026-06-30) · sec.gov
  • capex-guidance$9–11M
    $9–11M per critical MW — management's build-cost guidance for Beacon Point, 'the same range that we guided River Bend to' (Q1 call; the 2025 10-K states the same $9–11M/MW for River Bend, filed). At the midpoint, 352 MW ≈ $3.5B per phase against $4.25B of Phase 1 notes (the balance funds reserves, the substation and fees) and ≈ $7B for the campus. Compare Riot's $11–12M/IT MW at Rockdale and TeraWulf's $10–12M/MW at Hawesville: the converted-miner build cost is converging on one band. This figure is Hut 8's OWN spend and must never be reconciled against the ~$17B on the campus page, which includes the tenant's compute (see two-phase-capital-investment)
    “On the CapEx, we guided to the same range that we guided River Bend to, so $9 to $11 million per megawatt is what we guided River Bend to, and we have the same guidance here.”
    Hut 8 Q1-2026 earnings call, CFO Q&A (company transcript PDF) · cdn.sanity.io
  • two-phase-capital-investment$17B
    'approximately $17 billion' of combined capital investment for Phases 1 and 2 — Hut 8's campus web page (a company statement, in no filing), itemised on the same page as 'Data center and compute infrastructure ~$8.5B' per phase. So it INCLUDES the tenant's compute and is not Hut 8's build cost: at $9–11M/MW Hut 8's own share would be roughly $7B, which leaves ~$10B that is presumably tenant hardware — an editor's reading, because no document allocates the $17B between landlord and tenant and the page says nothing about who buys the compute. The page establishes only the $17B figure; the reading that leaves it 'unreconciled against $7.5B of project debt' falls away once the compute is separated out. Blockspace repeats it; no filing does
    “The first two phases of the project are expected to represent a combined capital investment of approximately $17 billion, supporting approximately 1,900 construction jobs and approximately 230 permanent operations roles.”
    hut8.com — Beacon Point campus page, Investment & Impact · hut8.com
  • nvidia-third-party-leases$20B
    NVIDIA's side of a ledger it does not name: its Q2 FY2027 10-Q (quarter ended Jul 26 2026, filed Aug 26) carries a new 'Additional Commitments' line, 'Data center leases not commenced for third party', $20B ($1B in each of FY2029–31, $17B '2032 and thereafter'), with the prose 'We have entered into data center leases with terms of approximately fifteen years that are expected to commence between fiscal year 2028 and fiscal year 2029 … We expect to reassign these data center leases to third parties.' Two ~15-year leases commencing FY2028–29 (Q3 2027 and Q2 2028 fall in NVIDIA's FY2028 and FY2029), to be reassigned — the shape of Beacon Point and of the WSJ's Nvidia → Lambda chain. The line did not exist in the Q1 FY27 10-Q (Apr 26), i.e. it appears after the Jul-20 Phase 2 lease. NVIDIA names no landlord, site or assignee, so this is an EDITOR'S INFERENCE stated as such, never a resolved identification; that $20B sits beside Hut 8's $19.6B is suggestive and unreconciled — NVIDIA's ladder is its own commitment measure, not the landlord's contract value, and the record does not equate them. Distinct from the same table's $36B 'AI cloud agreements' and from the main table's $25B 'Data center leases not commenced' (NVIDIA's own R&D leases)
    “Data center leases not commenced for third party — — 1 1 1 17 20”
    NVIDIA 10-Q, quarter ended 2026-07-26 — Commitments (Additional Commitments table, in billions) · sec.gov
  • ft-names-nvidia
    the Financial Times, Jul 28 2026, 'citing five people familiar with the arrangement': Nvidia is the counterparty to both 15-year leases, 'worth as much as $50bn to the developer over its full life' — the $50bn being Hut 8's $50.2B renewal ceiling. ONE origin behind every naming on file (TNW, DCF, Yahoo/Insider Monkey, brecorder, 36kr, cryptopolitan, pulse2 all repeat the same five-people attribution); confidence is the FT's, not the outlet count's. Nvidia's response, to Reuters: it 'is working with ecosystem partners to accelerate the deployment of efficient AI infrastructure through the DSX AI factory architecture' — neither confirming nor denying. Hut 8 did not respond.
    “The FT reported citing five people familiar with the arrangement, that Nvidia is the counterparty behind two 15-year leases at Hut 8’s Beacon Point campus in Nueces County, near Corpus Christi, and that the deal could be worth as much as $50bn to the developer over its full life.”
    The Next Web, Jul 28 2026, relaying the FT · thenextweb.com
  • reuters-could-not-verify
    Reuters' same-day wire on the FT story: it 'could not immediately verify the report'; Hut 8 did not respond; Nvidia answered with the DSX line above 'without confirming or denying'. Six weeks later Reuters was still sourcing the Anthropic–Lambda deal to a single anonymous source. There is no document from any party that names Nvidia as Beacon Point's tenant, and — given a live antitrust angle around Nvidia's cloud programme (see the nvidia entity) — there may never be one
    “Reuters could not immediately verify the report. Hut 8 did not respond to a request for comment outside business hours.”
    Reuters via Yahoo Finance, Jul 28 2026 · finance.yahoo.com
  • reported-deal-value$35B
    $35B — Anthropic → Lambda, for 'a Texas data center' developed by Hut 8 in Nueces County: the WSJ broke it Aug 31 2026; Reuters confirmed with 'a source familiar with the matter' (srnnews and Investing.com are byte-identical copies of the one wire); Bloomberg 'according to a person familiar'. Three partially independent anonymous sources for the SIZE; the structural claims (Nvidia holds the lease, Lambda pays Nvidia) are WSJ-only. No party statement and no filing among the sources then on file: they included no Anthropic document of any kind, and every Anthropic compute figure then in circulation ($35B here, $45B Nscale, $50B Fluidstack, $9.1B Riot, $19B TeraWulf …) was press unless a landlord filed it. Anthropic's S-1 (Oct 26 2026) has since described its agreements with Lambda, an August one among them, without naming a site: they are anth-lambda's, which draws the anthropic→lambda ribbon, and the site stays the press's. Tier 2 with the attribution kept; never added to the $19.6B
    “Aug 31 (Reuters) – Anthropic has signed a cloud-computing deal worth $35 billion with Lambda, a cloud provider backed by Nvidia, for a Texas data center, a source familiar with the matter said on Monday.”
    Reuters via srnnews, Aug 31 2026 · srnnews.com
  • reported-capacity350 MW
    'about 350 megawatts' (Reuters' source; the WSJ the same by DCD's account, Bloomberg by GDCH's) — numerically one 352 MW phase, but no report says which phase, or whether it is a slice of both; the Energy Mag piece says the reports 'don't establish' it. GDCH's '$16.7M per MW a year' is $35B ÷ 350 MW ÷ 6 on unconfirmed inputs and is not a figure. 247wallst's '700 megawatt campus' as the Anthropic allocation is a scope collapse (see contested capacity-covered)
    “The project is being developed in Nueces County by crypto-mining-turned-AI data center company Hut 8 and covers a capacity of about 350 megawatts, the source said, speaking on condition of anonymity as the information is not public.”
    Reuters via srnnews, Aug 31 2026 · srnnews.com
  • reported-term6
    six years — AFP's single source; the WSJ retellings do not state a term and TNW says 'no term was disclosed'. Six years is also the 'typical' duration NVIDIA gives its AI-cloud service agreements in its 10-Q, and the term AFP and Bloomberg report for Anthropic's $45B Nscale deal — a pattern, not corroboration. The six-year figure rests on this one attribution. Anthropic's S-1 later gave its Lambda agreements only an end, 'into 2034', and no term (anth-lambda, contested august-term)
    “The San Francisco-based AI lab has agreed to a six-year deal with Lambda, a source familiar with the deal told AFP.”
    AFP via Yahoo Finance, Sep 1 2026 · finance.yahoo.com
  • reported-lessee
    'Nvidia would hold the lease on the data center' — Bloomberg relaying the WSJ; GDCH's summary of the Journal adds that Nvidia 'reached its own agreement with Hut 8 some weeks before the Anthropic agreement'. If true, this is the lease Hut 8 filed in June and July without a name, and NVIDIA's $20B third-party-leases line is its mirror. Bloomberg's own contribution is the Hut 8 identification and the ~350 MW; the lessee claim is WSJ-only in every outlet
    “Infrastructure company Hut 8 is developing the Texas data center involved in the project, said the person, who asked not to be identified because the discussions are private. The Wall Street Journal previously reported on the agreement, saying that Nvidia would hold the lease on the data center, which is in Nueces County, Texas.”
    Bloomberg via Yahoo Finance, Aug 31 2026 · finance.yahoo.com
  • reported-chain
    the WSJ's structure in Investing.com's retelling: Lambda installs 'chips purchased from Nvidia, which is also an investor in Lambda' in Hut 8's building; what Lambda pays Nvidia for the space 'was not immediately clear'. GDCH's summary of the same Journal piece: 'Lambda installs NVIDIA chips at the facility and sells the resulting compute capacity to Anthropic … Lambda pays NVIDIA an undisclosed amount for access to the space, and … NVIDIA is an investor in both Anthropic and Lambda.' Four parties, three contracts (Hut 8–Nvidia lease, Nvidia–Lambda space, Lambda–Anthropic compute), one of them filed without a name and two of them undisclosed in every particular. The circular flag on this record rests on this reported layer — every leg of the loop (lessee, chip seller, investor in operator and buyer) is tier 2/3; at the filed layer there is no circularity at all
    “Lambda will use the data center that Hut 8 is developing to install chips purchased from Nvidia, which is also an investor in Lambda. The amount Lambda will pay Nvidia to access the data-center space was not immediately clear.”
    WSJ via Investing.com (Wayback 2026-09-03), Aug 31 2026 · web.archive.org
  • no-party-confirms
    'Anthropic-confirmed Sep 1 per several outlets' is in no document on file. Bloomberg: Anthropic 'declined to comment', Nvidia, Lambda and Hut 8 'didn't immediately respond'; GDCH: 'No party has confirmed the terms'; TNW: 'Neither company has announced it'; DCD 'has contacted Lambda for comment'. Hut 8's most recent release on file (Aug 10, its response to the ERCOT audit directive) says nothing about any of it. The sources then on file describe the four-party stack entirely through press reporting. Anthropic's S-1 (Oct 26 2026) has since described its agreements with Lambda, naming no site, landlord or Nvidia lease, so it places none of the stack here (anth-lambda); its S-1/As of Nov 10 and 17 and its 424B4 of Nov 19 2026 still name none, and add that Lambda did not secure the 'facility lease' its August agreement depends on by the date set, so that agreement is terminable by either party — whether that facility is this one, no document says
    “A representative for Anthropic declined to comment. Nvidia, Lambda and Hut 8 didn't immediately respond to requests for comment.”
    Bloomberg via Yahoo Finance, Aug 31 2026 · finance.yahoo.com
  • batch-zero-status1 GW
    ERCOT's Batch Zero large-load review gave the 1 GW site a CONDITIONAL base-load designation (notices sent to utilities Sep 3–4; Hut 8 'announced' it, per Blockspace — the announcement itself is not on file). Earlier, the only status on file was Hut 8's hedge that it 'believes' Beacon Point 'may be among 23 projects' ERCOT had classified, and ERCOT's own list did not name it. Conditional means the Q1 2027 energization and the Q3 2027 first hall are still targets on the grid side too — the delivery risk that sits under the $4.25B
    “Hut 8: The company announced that it received conditional base load designation for its 1 GW Beacon Point site last Friday.”
    Blockspace, Sep 8 2026 · blockspace.media

Contested figures 10 not reconciled — every position side by side, with its source and tier

tenant-identity2 positions, side by side
UNNAMED — Hut 8 in every document: 'a high-investment-grade tenant' (Q1 release) → 'a multi-trillion-dollar market capitalization, high-investment-grade technology company' (Q1 10-Q) → 'a high-investment-grade company (i.e., rated AA- or higher) as of the date hereof' (Jun-10 8-K) → 'the Phase 1 tenant' (Jul-20 release). The indenture defines 'Tenant' by reference to the lease, not by name, and lists Nvidia first among six acceptable REPLACEMENTS — the same six names in the same Nvidia-first order as Hut 8's River Bend indenture, whose tenant is Fluidstack with a Google guarantee, so the ordering is the issuer's boilerplate and identifies no one; the halls are built to NVIDIA's DSX architecture. Consistent with Nvidia, and with five other companies. The landlord's silence is tier 1 — and unbroken in the Q3 10-Q (Nov 4): 'leased in its entirety to a high-investment-grade company under a triple-net lease', and the notes 'not guaranteed by … the tenant' Hut 8 10-Qs (through Q3), 8-Ks, indenture (Beacon Point vs River Bend)
NVIDIA — the Financial Times, Jul 28 2026, five people familiar; the WSJ, Aug 31, 'Nvidia would hold the lease'. Seven-plus outlets, one FT origin; Reuters 'could not immediately verify'; Nvidia 'without confirming or denying'; Hut 8 no comment. NVIDIA's own 10-Q carries $20B of unnamed ~15-year third-party leases commencing FY2028–29 that fit the shape (editor's inference). This record names Nvidia as REPORTED lessee in roles and on a ghosted ribbon, never as the tenant of record FT via TNW/Yahoo-Reuters; WSJ via Bloomberg/GDCH
lease-chain2 positions, side by side
WSJ's chain (Aug 31): Hut 8 → Nvidia holds the lease (its own agreement with Hut 8 'some weeks before') → Lambda installs Nvidia chips and pays Nvidia an undisclosed amount for the space → Lambda sells the compute to Anthropic. Every relay (DCD, TechRepublic, Energy Mag, GDCH, 247wallst, Reuters, Bloomberg) attributes the structure to the Journal, so it is one source however many print it WSJ via Bloomberg/Yahoo, GDCH, DCD (Wayback)
The Next Web's retelling of the same report: 'Lambda holds the lease on a data centre in Nueces County, Texas, developed by Hut 8, while Nvidia has a separate arrangement with Hut 8 to secure the capacity, and Lambda deploys Nvidia chips into it' — the outlier, almost certainly the same WSJ origin misread, carried because it is on file. The FILED layer under both versions is identical and silent: Hut 8 ↔ one unnamed tenant, two leases, no sublease or assignment disclosed by anyone (the indenture does contemplate a 'novation' or 'Qualifying Data Center Lease' replacing the lease — mechanism, not event) The Next Web, Aug 31 2026 vs Hut 8 filings
capacity-covered2 positions, side by side
~350 MW — Reuters' source, the WSJ (by DCD's account) and Bloomberg (by GDCH's) for the Anthropic–Lambda agreement; AFP's copies on file give no capacity: numerically one of the two 352 MW phases, but no source says which (Phase 1 delivering Q3 2027, Phase 2 Q2 2028), or whether it is a slice of both; the Energy Mag piece says so explicitly. Whether the other 352 MW serves someone else, Nvidia itself, or a later Anthropic tranche is unknown. So is the reverse: whether the Anthropic–Lambda capacity is itself part of the up to 1,050 MW that Hut 8 and Anthropic 'may jointly diligence and develop' across Hut 8's pipeline (fs-hut8-river-bend tranche-3), reached through Nvidia's lease. The FY-2025 10-K that states that tranche also lists 524 acres Hut 8 owned in Nueces County; none of Hut 8's 2026 10-Qs or results releases names Anthropic Reuters via srnnews; WSJ via DCD (Wayback); Bloomberg via GDCH; Hut 8 FY-2025 10-K
700 MW — 247wallst: Nvidia 'holds the lease on the underlying data center, a 700 megawatt campus in Nueces County' — the campus's 704 MW collapsed into the Anthropic deal's scope ('that capacity'). One outlet, no source, and the campus figure is filed at 704 not 700; kept as the range's high end because reading it as the Anthropic allocation doubles the deal. 350–700 MW, never averaged 247wallst, Sep 1 2026
headline-value3 positions, side by side
$35B — Anthropic → Lambda compute purchase (WSJ; Reuters/Bloomberg one anonymous source each), over six years per AFP's single source. What Anthropic reportedly PAYS for compute, which prices the GPUs and Lambda's margin on top of the rent. Not a lease and not Hut 8's number WSJ via Reuters/Bloomberg/AFP
$19.6B — Hut 8's aggregate base-term contract value for both leases (filed: Q2 10-Q, Jul-20 8-K ex-99.1), rent only, 15 years, before options. The only signed dollar figure on this record Hut 8 Q2-2026 10-Q
$50.2B — the same rent if all six 5-year options are exercised (filed), which the FT rendered as 'leases worth up to $50 billion' and pulse2 fused into a '$50.2 billion lease' headline. Three quantities that price three different things; the record never sums, averages or reconciles them, and the campus's 704 MW goes with the $19.6B Hut 8 Q2-2026 10-Q vs FT (via TNW) vs pulse2
site-acreageone entry, in its own words
521 → 524 → 525 acres, all Hut 8's own: 'an approximately 521-acre property' (Jun-5 and Jun-10 8-Ks, the notes' use of proceeds — the site the BOND is secured on); 'a total of 524 acres of land in Nueces County, Texas for $17.5 million' purchased Nov–Dec 2025 (2025 10-K — the land the company BOUGHT); '525 acres' (hut8.com campus page, investor deck, and every press retelling). Rounding, a carve-out, or three scopes — no deed or plat on file decides it. Low stakes; carried because it shows the website and the filings are not the same record Hut 8 8-Ks vs 10-K vs hut8.com

Scope note what this record leaves to other records

NOT this record (carried elsewhere): Hut 8's River Bend campus — 245 MW to Fluidstack USA IV (lease dated Dec 15 2025), $7.0B / $17.7B, NOI $6.9B / $454M, Google guarantee, $3.25B 6.192% notes due Nov 15 2042 (Hut 8 DC LLC, closed Apr 30 2026, 16.5-yr, ~95% LTC), 330 MW Entergy, initial hall Q1 2027 (Jacobs) vs Q2 2027 (Hut 8), 592+35 vs 611 acres, the West Feliciana PILOT ($90M/yr ceiling vs ~$60M first payment), the '2,295 MW with Anthropic' aggregate (245 signed + 1,000 ROFO + 1,050 diligence) → goog-anth-backstops' landlord ledger and the campus's own record; Hut 8 portfolio totals (949 MW / 1,330 MW utility / $26.6B / >$1.75B NOI after Jul 20; 597 MW / $16.8B before), the $7.5B of project debt, Q2 revenue $74.9M, the American Bitcoin stake (~80% → ~54%), the Coinbase loan, the securities litigation ($2.4M settlement) → the hut8 entity; NVIDIA-wide lines — $36B AI-cloud service commitments (the disclosed figure; Hudson Labs' '$29B' is a different Note-10 line), the WSJ-reported Aug-28 pause of that revenue-share programme (techstrong's '50%' is unsourced; the 10-Q quantifies nothing), $279B supply commitments, $108.5B guarantee exposure, the $105B SB Energy guaranty → the nvidia entity and nv-sbe-ports-pike; Lambda's financings ($926M TLB, $1B facility, Series E >$1.5B, the $3B/$12B+ talks), the Sep-2025 $1.5B Nvidia–Lambda leaseback (18,000 servers-or-GPUs, one Information report), fund marks on Lambda and Anthropic private shares → the lambda entity; Anthropic's sibling deals ($45B Nscale — not '$45B EnCore', a 247wallst-only string; $45B SpaceX, $10B Volta, $50B Fluidstack, AFP's unreconciled 'at least $135 billion' 2026 total) → their own records or nothing; the ERCOT queue (438 GW ERCOT vs 474 GW Abbott letter), PUCT Project 59142, Hut 8's Aug-10 closed-loop-cooling response → colour only. Not adopted: the indenture's 'Nvidia Corporation' / '$50.0 billion' read as a tenant naming and a deal size (they are the replacement-tenant test); pulse2's '$50.2 billion lease'; DCD's '$4.5bn'; 247wallst's '700 MW' as the Anthropic allocation; context-free deck cells '$42.8B' / '$67.9B' (portfolio upside arithmetic: $17.7B + $25.1B [+ $25.1B]); GDCH's '$16.7M per MW' and ccir.io's '$5.27/GPU-hr' (arithmetic on unconfirmed inputs); the '$9.8B cumulative NOI = $9.8B contract value' identity (a triple-net lease's NOI ≈ its rent — one number, not two facts); three figures scraped from a 247wallst 'related articles' block.

More between these companies

  1. Nov 9, 2026 updated Nov 19
  2. Aug 31, 2026 updated Nov 19
  3. Dec 17, 2025 updated Nov 20
  4. Nov 18, 2025 updated Nov 20
  5. Aug 2025 updated Nov 21

Everything between Hut 8 and Anthropic → · Everything between Nvidia and Anthropic → · Everything between Lambda and Anthropic →