Why it matters
Lenders financing Galaxy's Helios campus underwrite CoreWeave's rent one phase at a time as the campus shifts from bitcoin mining to data centers. Deutsche Bank's $1.4B loan is ring-fenced to Galaxy's Phase I company and the $3.5B of 9.875% notes to its Phase II company, alongside Galaxy's uncapped promise to finish the build. Galaxy's filings give $4.68B in remaining CoreWeave rent for Phase I alone.
Tap a figure for the line in its source.
Galaxy gives
- of computing capacity (critical IT) in three phases — 133 handed over in Q2 2026, 260 MW from Q2 2027, 133 MW from 2028 — using about 800 MW of the campus's 1,630 MW of approved power; the other 830 MW has no tenant yet → CoreWeave
- two five-year extension options beyond each 15-year base term, at CoreWeave's election → CoreWeave
- an uncapped promise to fund the second phase's completion if the note money and other funds fall short → Lenders & bondholders
CoreWeave gives Galaxy
- of rent over the three leases by Galaxy's own count, stated only on its website; its filings give the first lease's $4.68B still to come, and a bond deck it furnished gives the second's $10.4B minimum
- of rent paid in advance, still held by Galaxy as deferred revenue at Sep 30 2026
Lenders & bondholders gives Galaxy
- Deutsche Bank term loan for the first phase, $1.3B drawn, secured only on that phase's company
- of 9.875% notes due 2031 to build the second phase, sold at a $17.5M discount to face value
What happened
Galaxy, a crypto financial firm, is turning Helios into data centers for CoreWeave. Galaxy owns the bitcoin-mining campus in Dickens County, West Texas. Three 15-year leases, signed from spring 2025 to January 2026, give CoreWeave 526 megawatts of computing capacity. Galaxy handed over the first 133 in the second quarter of 2026 and earned $79.1 million in rent from that capacity in the third quarter. The other 393 are due from the second quarter of 2027 into 2028. Galaxy puts the value of the leases at more than $15 billion, a figure it gives only on its website. Galaxy's filings list $4.68 billion in remaining rent for the first lease. A bond presentation Galaxy furnished to the SEC without filing it gives a $10.4 billion minimum for the second lease. Each phase has its own financing. The first has a $1.4 billion Deutsche Bank loan, and the second has $3.5 billion of 9.875% bonds. Galaxy says CoreWeave told Galaxy the first phase's computing is currently set aside for a multi-trillion-dollar investment-grade hyperscaler, a large cloud operator. Galaxy does not name the hyperscaler. Another 830 megawatts of approved power at Helios has no tenant yet.
Sources 33 documents — 19 SEC filings · 10 company releases · 4 government statements
Research trail Found 190 documents and read 171 of them while checking this deal and related ones.
- States 8 figures: 133 MW phase i · 393 MW phases ii iii · initial term end · 830 MW unleased power (for context) · $79.1M lease revenue · $4684.354M minimum lease income · $150M prepaid rent · $1.4B phase i loan
- States 4 figures: lease term · 133 MW phase iii · $1.8B phase i cost · $4B phase ii cost
- States 3 figures: 526 MW total capacity · 260 MW phase split · lease chronology
- States 3 figures: $10.4B phase ii minimum · 13.7% phase ii yield · 3–5% phase ii escalator
- States 2 figures: phase ii lease · notes amortization
- States 2 figures: $3.507B phase ii notes · completion guarantee
- States at least 132.7 MW phase i data center
- States 133 MW first announcement
- States 4.75% phase i loan rate
- States 10% phase i loan all in
- States end user
- States tenant names landlord
- States phase ii schedule
- States more than $15B contracted revenue
- States more than $7.5B capital investment
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: Galaxy Q3-2026 10-Q (filed Nov 9 2026), Q2-2026 10-Q, FY2025 10-K, S-4/A (Mar 2025) and S-1 (May 2025); the Phase I loan 8-K (Aug 15 2025) and credit agreement (8-K/A ex-10.1); the Phase II notes' 8-K and indenture (Jul 28 2026); its Q2 and Q3 2026 releases and decks and the Jul 22 2026 bond deck (all furnished); its Mar 28 2025 and Aug 15 2025 releases, website posts (May 4 and Aug 12 2026), CEO letter (Apr 8 2026) and calls (Oct 21 2025, Oct 27 2026), none filed; CoreWeave's 424B4 (Mar 2025), Q1 and Q3 2026 10-Qs and a Rule 425 interview (Oct 7 2025); TDLR registrations (Mar 2026) · as of Nov 2026
The evidence 30 sourced figures · 7 disputes · 1 for context
The record's headline Galaxy–CoreWeave, Helios (Dickens County TX): three 15-year leases for 526 of critical IT on ~800 MW of gross power — 133 MW handed over Q2 2026, 393 MW from Q2 2027; 830 MW of approved power unleased; '>$15B' of rent only on Galaxy's website, $4.68B filed for Phase I; each phase financed on its own ($1.4B loan, $3.5B 9.875% notes)
- Size
- 526 MW critical IT on ~800 MW gross (133 MW handed over Q2 2026 + 393 MW from Q2 2027) · three 15-yr base terms + 2 × 5-yr options · '>$15B' contracted (Galaxy's website); filed: Phase I's $4.68B still to come · $1.4B Phase I loan + $3.507B 9.875% Phase II notes
- When
- Nov 7 2024 non-binding term sheet, tenant unnamed → Mar 2025 Phase I lease (dated Mar 12 by the loan; 'April 2025' in later filings — contested), announced Mar 28 → Apr 2025 Phase II option → Aug 2025 Phase II lease (Aug 8), final option, $1.4B loan (Aug 15) → Jan 2026 Phase III lease; 830 MW more approved at the campus (Jan 15) → Q2 2026 Phase I handed over, first rent → Jul 28 2026 $3.507B notes → Q2 2027 first Phase II hall → early 2028 last Phase II hall; 2028 Phase III rent · base terms 15 years + 2 × 5-year options
- Status
- Phase I's 133 MW handed over through Q2 2026 and billing ($79.1M of lease revenue in Q3 2026); Phase II under construction, the first of eight halls due Q2 2027 and the last early 2028; Phase III leased Jan 2026, initial rent targeted for 2028, its financing to be sought in 1H 2027; 830 MW of approved power at the campus unleased at Sep 30 2026
- Structure
- three leases of data halls at Helios I to CoreWeave, Inc. itself — Phase I (133 MW of critical IT, ~200 MW gross; the 'Lease Agreement', which also held CoreWeave's two expansion options), Phase II (260 MW, ~400 MW gross; dated Aug 8 2025, amended Jan 21 and Jun 3 2026) and Phase III (133 MW, ~200 MW gross; Jan 2026). Each runs a 15-year base term that starts when its last data hall is turned over, each earlier hall leased to the end of it, with two 5-year extension options for CoreWeave; Phase II's rent rises each year with CPI, at least 3% and at most 5%. Phases I and II each sit in their own Galaxy subsidiary and are financed on their own: Galaxy Helios I LLC's $1.4B Deutsche Bank term loan, secured on that company's assets and 'not secured by any assets of Galaxy Digital', with GDH LP's completion and limited-recourse carve-out guarantees; Galaxy Helios Data Centers II LLC's $3.507B of 9.875% notes, whose credit support is that issuer, its guarantor subsidiary and the Phase II project, with GDH LP's uncapped completion guarantee. None of the three leases is in the record's documents
- Programme
- CoreWeave contract web
- Parties
- CoreWeave tenant — CoreWeave, Inc. itself, named in the Phase I loan and the Phase II indenture; holds two 5-year extension options. Its own 10-Qs describe a single-site, construction-cost-linked lease without naming the landlord (contested tenant-side-lease) · Galaxy landlord, developer and operator, through subsidiaries — Galaxy Helios I LLC (Phase I, the loan's borrower), Galaxy Helios Data Centers II LLC (the notes' issuer), Galaxy Power LLC (signed the Phase II lease, since assigned); GDH LP gives the completion guarantees · Lenders & bondholders Deutsche Bank AG (the Phase I term loan) and the buyers of the Phase II notes (sold through initial purchasers represented by Morgan Stanley); Galaxy's other assets are not their security
- Site
- Helios
- Record
- disclosed / primary source · as of Nov 2026
Flows 5 as the record states them
- CoreWeave → Galaxyrentrent on 526 MW over three 15-year base terms — 'more than $15 billion in contracted revenue over the life of the lease agreements' by Galaxy's website (contracted-revenue), 'over $1B' a year on average by its decks (contested all-phases-annual). Filed, only Phase I's: $79.1M recognized in Q3 2026 and $4.68B of future minimum lease income at Sep 30 2026. Phase II's $10.4B minimum is in a furnished bond deck; Phase III's rent is undisclosed. $150M paid in advance (prepaid-rent)
- Galaxy → CoreWeavecapacity526 MW of critical IT on ~800 MW of gross power at Helios I, Dickens County TX: Phase I 133 MW (~200 MW gross) handed over in Q2 2026; Phase II 260 MW (~400 MW gross), two buildings of eight halls, from Q2 2027 into early 2028; Phase III 133 MW (~200 MW gross), rent from 2028. The campus's other 830 MW of approved power is not leased
- Lenders & bondholders → Galaxyfinancing$1.4B senior secured term loan from Deutsche Bank AG to Galaxy Helios I LLC (Aug 15 2025): one-month Term SOFR, floored at 2.50%, plus 4.75%, maturing Aug 15 2028; $1.3B drawn at Sep 30 2026; 'approximately 10% to 11%' all-in if held to maturity, by the CFO
- Lenders & bondholders → Galaxydebt$3,507,000,000 of 9.875% senior secured notes due Aug 1 2031, issued at 99.500% by Galaxy Helios Data Centers II LLC (Jul 28 2026), to finance part of Phase II's build and fund debt-service reserves; principal amortizes only from the first payment date ten months after Phase II's rent is first paid (notes-amortization)
- Galaxy → Lenders & bondholderscompletion-guaranteeGDH LP's 'customary, uncapped completion guarantee' to the notes, to fund each Phase II phase to rent commencement under the CoreWeave lease if the notes' proceeds and other available funds fall short; on the Phase I loan, 'customary completion and limited recourse carve-out guarantees'
Resolved figures 30 each with the verbatim line from its document
- total-capacity526 MW526 MW of critical IT leased to CoreWeave across the three phases by 2028 — 133 + 260 + 133 MW — on ~800 MW of gross power (~200 + ~400 + ~200 MW, the Q3-2026 deck's footnote). The same 526 MW in Galaxy's filings and releases since Aug 2025, when CoreWeave took its final option and 'committed to the full 800 MW of approved power capacity at the Helios datacenter campus' (financing release)
“Together, the Phase II Lease and the Phase III Lease are expected to increase CoreWeave’s contracted capacity at the Helios data center campus to 526 MW of critical IT load by 2028.”
Galaxy FY2025 10-K (filed Feb 26 2026), Business — Data Centers · sec.gov - phase-i133 MWPhase I: 133 MW of critical IT on ~200 MW of gross power, developed for CoreWeave, Inc. under the 15-year 'Lease Agreement' — handed over through Q2 2026 (lease-revenue). The month this filing gives the agreement, April 2025, is contested (phase-i-lease-date)
“Galaxy’s Helios data center campus, located in the panhandle region of West Texas, has developed the first 133 megawatts (“MW”) of critical IT load, utilizing approximately 200 MW of gross power capacity, for CoreWeave, Inc. (“CoreWeave”) under a 15-year lease agreement (the “Lease Agreement”) entered into in April 2025.”
Galaxy Q3-2026 10-Q (filed Nov 9 2026), MD&A — Overview · sec.gov - phases-ii-iii393 MWthe other 393 MW of critical IT, under the Phase II and Phase III leases, on 600 MW of the campus's approved gross power, 'expected to be delivered starting in the second quarter of 2027' (this 10-Q's own sentence); 'starting in 2027' in the FY2025 10-K
“In addition to the initial 200 MW described above, 600 MW of this gross power capacity will support the incremental 393 MW of critical IT load leased to CoreWeave under the Phase II and Phase III leases pursuant to the Lease Agreement, which is expected to be delivered starting in the second quarter of 2027.”
Galaxy Q3-2026 10-Q, MD&A — Overview · sec.gov - phase-split260 MWthe 393 MW split by lease: 260 MW under Phase II and 133 MW under Phase III
“The Phase II Lease provides for the uptake of an additional 260 MW of incremental critical IT load and the Phase III lease provides for the uptake of an additional 133 MW of incremental critical IT load.”
Galaxy FY2025 10-K, Business — Data Centers · sec.gov - lease-chronologyhow the three leases came about: the Phase I Lease Agreement held CoreWeave's options, which it exercised in April 2025 (Phase II, ~260 MW — Galaxy's Apr 23 2025 release) and August 2025 (Phase III, its final option); the Phase II and Phase III leases followed in August 2025 and January 2026
“CoreWeave exercised its options under the Lease Agreement in April 2025 and August 2025, and we entered into the Phase II (the “Phase II Lease”) and Phase III (the “Phase III Lease”) lease agreements pursuant to such options in August 2025 and January 2026, respectively.”
Galaxy FY2025 10-K, Business — Data Centers · sec.gov - phase-ii-leasethe Phase II lease as the notes' indenture defines it: dated Aug 8 2025, signed by Galaxy Power LLC as landlord with CoreWeave, Inc. — the parent, not a subsidiary — as tenant, amended twice in 2026 and assigned to the issuer's subsidiary landlord. The indenture's 'Tenant' is 'CoreWeave, Inc., a Delaware corporation'
““Data Center Lease” means the lease agreement dated August 8, 2025, between Galaxy Power LLC, as landlord, and CoreWeave, Inc., as tenant, as amended by that certain First Amendment, dated January 21, 2026, and by that certain Second Amendment, dated June 3, 2026, as assigned to the Landlord pursuant to the Assignment & Assumption Agreement”
Galaxy 8-K ex-4.1, indenture for the 9.875% notes due 2031 (filed Jul 28 2026) — definitions · sec.gov - phase-i-data-centerat least 132.7 MWPhase I's building as its lender defines it: data halls with 'at least 132.7 megawatts of critical electric power' for CoreWeave under the 'Coreweave Lease' — the 133 MW, unrounded. The same agreement dates that lease 'as of March 12, 2025' (contested phase-i-lease-date)
““Data Center” means that certain Data Center Facility to be constructed on the Trust Property pursuant to, among other agreements, the Construction Agreement and other Material Project Documents, which will comprise, when fully completed (a) the Building, (b) the Data Halls to be fitted out in the Building with an aggregate of at least 132.7 megawatts of critical electric power available for use by Coreweave pursuant to the Coreweave Lease”
Galaxy 8-K/A ex-10.1, Phase I credit agreement with Deutsche Bank (filed Oct 20 2025) — definitions · sec.gov - first-announcement133 MWthe day the deal became public with CoreWeave's name: Galaxy's 2024 results release of Mar 28 2025, which also put Phase I at 'approximately $4.5 billion of total revenue' over the 15 years (contested phase-i-total). The Nov 7 2024 release it refers to announced 'a non-binding term sheet with a U.S.-based hyperscaler' for Helios, unnamed. Galaxy's Apr 23 2025 release calls it 'the 15-year, 133 megawatt (“MW”) lease agreement previously announced on March 28, 2025'. A release of Galaxy Digital Holdings Ltd. (then TSX: GLXY) on its IR site, not an SEC filing
“Subsequent to year-end, and further to the term sheet announced on November 7, 2024, Galaxy entered a 15-year lease agreement with CoreWeave. As part of the agreement, Galaxy will deliver 133 megawatts ("MW") of Critical IT Load to host CoreWeave's artificial intelligence ("AI") and high-performance computing ("HPC") infrastructure at our Helios data center campus in the panhandle region of West Texas.”
Galaxy Q4-2024 results release (Mar 28 2025), IR site · investor.galaxy.com - lease-term15a 15-year base term, starting when a phase's last data hall is turned over, each earlier hall leased to its end — so rent on a phase's first halls runs longer than 15 years; plus two 5-year extension options for CoreWeave ('15 Years Base Lease Term + Two 5-Year CoreWeave Extension Options', the July bond deck). With both, 25 years and a '$30B+' 'Total Potential Contract value' including escalators (this deck) — option-contingent, not drawn. CoreWeave's unnamed single-site lease runs 'sixteen' years (contested tenant-side-lease)
“Each data hall is leased through the end of the 15-year base term, which commences upon turnover of the final data hall; revenue is earned as individual data halls are delivered.”
Galaxy Q3-2026 investor deck (8-K ex-99.2, Oct 27 2026; furnished), CoreWeave lease footnote · sec.gov - initial-term-endthe filed end date of the first term: 2040, in Galaxy's risk factors on its dependence on CoreWeave — which the filing calls 'our customer'. The filing does not say from which date it counts
“There can be no assurances that our customer will renew or sign a further contract when its initial contract expires in 2040.”
Galaxy Q3-2026 10-Q, Risk Factors · sec.gov - phase-iii133 MWPhase III: 133 MW of critical IT (~200 MW gross), leased in January 2026 (lease-chronology), initial rent targeted for 2028. Galaxy gives no rent, cost or financing for it; on the Oct 27 2026 call it said 'we anticipate pursuing Phase III financing in the first half of 2027'
“Phase III Contracted Critical IT Load3 133 MW 2028 Initial Rent Commencement”
Galaxy Q3-2026 investor deck (Oct 27 2026; furnished), 'CoreWeave Lease by Phase' · sec.gov - phase-ii-schedule8Phase II's halls, one at a time: the first of eight in Q2 2027, seven by the end of 2027, the last in early 2028 — Galaxy's own post, with HITT Contracting the general contractor since April 2026 (Q2-2026 release, furnished). The filed form is 'starting in the second quarter of 2027' (phases-ii-iii)
“the first of eight data halls are expected online in Q2 2027, with seven of eight halls online by year-end and the final hall following in early 2028.”
Galaxy, 'Q2 2026 Unwrapped' (galaxy.com, Aug 12 2026) · galaxy.com - lease-revenue$79.1Mthe first rent: $79.1M of lease revenue in Q3 2026 and $97.9M in the nine months — so $18.9M in Q2, as Phase I's halls were handed over (our subtraction; the Q2 10-Q's figure) — 'attributable to the commencement of the CoreWeave Phase I lease agreement'. Booked straight-line over the term. Galaxy had guided to 'approximately $80 million' a quarter from Q3 (Q2 release, furnished). The segment's 'Data centers operator revenue', $9.9M in Q3, is a separate line
“Data center lease revenue was $79.1 million and $97.9 million for the three and nine months ended September 30, 2026, attributable to the commencement of the CoreWeave Phase I lease agreement.”
Galaxy Q3-2026 10-Q, MD&A — Data Center Revenue · sec.gov - minimum-lease-income$4684.354M$4.68B of future minimum lease income at Sep 30 2026 — $63.4M for the rest of 2026, $259.1M in 2027 rising about 3% a year, $3.54B after 2030; $4.75B at Jun 30 2026 (Q2 10-Q). On our reading this is Phase I's alone: only Phase I had commenced, and the table's 2027 line leaves no room for Phase II's first-year rent ($155M in 2027 in the July bond deck). The only filed dollar measure of the leases
“The following table represents future minimum lease income of the Company’s operating leases as of September 30, 2026: (in thousands) Lease Income Year ending December 31, 2026 63,438 2027 259,079 2028 266,851 2029 274,857 2030 283,102 Thereafter 3,537,027 Total future minimum lease income $ 4,684,354”
Galaxy Q3-2026 10-Q, Note 13 — Leases (lessor) · sec.gov - prepaid-rent$150M$150M of rent CoreWeave paid in advance, received in 2025 and still in deferred lease revenue at Sep 30 2026, none of it yet recognized. Galaxy's July bond deck separately says 'a $100M options payment already received from CoreWeave' for Phase II; no document says whether the $100M is part of the $150M
“Beginning balance $ 150,000 $ — Prepaid rent — 150,000 Revenue recognized during the period — — Ending Balance $ 150,000 $ 150,000”
Galaxy Q3-2026 10-Q, Note 13 — Leases, deferred lease revenue · sec.gov - contracted-revenuemore than $15B'more than $15 billion in contracted revenue over the life of the lease agreements' — Galaxy's only figure for all three leases' rent, in a post on its website when the first hall went live (May 4 2026), never in a filing. It squares with Phase I's $4.68B filed (minimum-lease-income) plus Phase II's $10.4B furnished (phase-ii-minimum), ≈ $15.1B (our sum), with Phase III's rent undisclosed — a floor, not a total. Galaxy uses '$15 billion' for a different thing in its CEO letter: investment at Helios including the unleased 830 MW (capital-investment)
“The delivery markets a pivotal moment for Galaxy – Helios transitioning from a construction site to a cash-flowing business, unlocking more than $15 billion in contracted revenue over the life of the lease agreements.”
Galaxy, 'Q1 Recap: Helios Online' (galaxy.com, May 4 2026) · galaxy.com - phase-ii-minimum$10.4B$10.4B of minimum lease payments under Phase II over its 15-year initial term — 'remaining lease payments under the lease', excluding 'a $100M options payment already received from CoreWeave', assuming '3% annual inflation' (footnote 3). The deck's cash-flow table runs Phase II's rent from $155M in 2027 and $472M in 2028 to $830M in 2042, ≈ $10.35B in all (our sum). Galaxy's marketing deck for the notes, furnished (Item 7.01)
“$10.4Bn (3) (5) Minimum Contracted Lease Payments Q2’27 (5) Initial Targeted Rent Commencement Date”
Galaxy 8-K ex-99.1, notes offering presentation (Jul 22 2026; furnished) · sec.gov - phase-ii-yield13.7%13.7%, Phase II's starting rent as a share of its build cost ('Starting MRC Gross Yield on Cost') — on the ~$4.0B estimate (phase-ii-cost), about $548M a year to start (our arithmetic; no Galaxy document states a dollar starting rent). Not adopted: a newsletter's (Measured AI) rent of 14.5% of the build cost up to a $3.7B cost cap, which no primary document states
“13.7% Starting MRC Gross Yield on Cost”
Galaxy 8-K ex-99.1, notes offering presentation (Jul 22 2026; furnished) · sec.gov - phase-ii-escalator3–5%Phase II's rent rises each year with CPI, but at least 3% and at most 5% (footnote 4); the $10.4B assumes 3%
“3% if CPI is below 3%; 5% if CPI is greater than 5%; If CPI is between 3%-5%, annual escalation rate shall be equal to the CPI”
Galaxy 8-K ex-99.1, notes offering presentation (Jul 22 2026; furnished), footnote 4 · sec.gov - phase-i-cost$1.8B$1.8B, Galaxy's construction cost for Phase I after delivery — up from 'the $1.7 billion Phase I build' its Q3-2025 release (Oct 21 2025) said the $1.4B loan fully funds; about $13.5M per MW of critical IT (our arithmetic). Not adopted: the $800M 'Estimated Cost' on the state's building registration for 'Helios Light Speed' (scope not stated), and a newsletter's ~$2.25B, which adds work in progress to a budget that already holds it
“Galaxy successfully delivered 133 MW of critical IT to CoreWeave on schedule under the Phase I lease agreement, transitioning the site from construction to operational facility throughout Q2 2026. Phase I Delivered Critical IT Load3 133 MW Q2 2026 Delivery Date $315M Annual Base Revenue5 Construction Cost $1.8B”
Galaxy Q3-2026 investor deck (Oct 27 2026; furnished), 'CoreWeave Lease by Phase' · sec.gov - phase-ii-cost$4B~$4.0B, Galaxy's estimated construction cost for Phase II ('internal estimates', footnote 4) — the same in the Q2 deck. The $3.507B of notes finance part of it (phase-ii-notes). The state's three 'Galaxy Helios Phase 2' registrations sum to $3.5B (contested phase-ii-buildings)
“Phase II Contracted Critical IT Load3 260 MW Q2 2027 Initial Rent Commencement $675M Annual Base Revenue5 Est. Construction Cost4 $4.0B”
Galaxy Q3-2026 investor deck (Oct 27 2026; furnished), 'CoreWeave Lease by Phase' · sec.gov - capital-investmentmore than $7.5B'over $7.5 billion' of capital investment for the 800 gross MW leased to CoreWeave, i.e. all three phases. Less Phase I's $1.8B and Phase II's estimated ~$4.0B, that leaves roughly $1.7B or more for Phase III, if the letter's 'capital investment' and the decks' construction costs measure the same thing (our arithmetic; Galaxy gives no Phase III cost). The same letter's 'well north of $15 billion' adds the unleased 830 MW and is not this lease's
“The first 800 megawatts leased to CoreWeave, one of the leading AI cloud providers, represents over $7.5 billion of capital investment alone.”
Galaxy, 2025 Annual Report — letter from the CEO (galaxy.com, Apr 8 2026) · galaxy.com - phase-i-loan$1.4BPhase I's $1.4B senior secured term loan from Deutsche Bank AG to Galaxy Helios I LLC, signed Aug 15 2025, to build the Dickens County project; $1.3B drawn at Sep 30 2026 ($433.5M at Sep 30 2025). Secured on all of Galaxy Helios I's assets and its equity, 'not secured by any assets of Galaxy Digital'; GDH LP gave 'customary completion and limited recourse carve-out guarantees' (loan 8-K). It matures Aug 15 2028 — Galaxy's CFO said it plans to refinance once Phase I is stabilized (Oct 2025 call)
“On August 15, 2025, Galaxy Helios I LLC (“Galaxy Helios I”), an indirect wholly owned subsidiary of GDH LP, entered into a credit agreement (the “Credit Agreement”) with Deutsche Bank AG providing for a senior secured term loan facility in an aggregate principal amount of up to $1.4 billion.”
Galaxy Q3-2026 10-Q, Note 16 — Data Centers Financing · sec.gov - phase-i-loan-rate4.75%its price: one-month Term SOFR with a 2.50% floor, plus a 4.75% margin, with upfront, undrawn and termination fees besides
“As described in the Credit Agreement, the benchmark rate consists of one month Term SOFR, with a floor of 250 basis points, and the applicable margin is 4.75%.”
Galaxy 8-K, Items 1.01/2.03 (filed Aug 15 2025) · sec.gov - phase-i-loan-all-in10%'approximately 10% to 11%' all-in if held to maturity, fees included, at 80% loan-to-cost — the CFO on the Q3-2025 call. The 8.48–9.1% in third parties' tables is the coupon at a SOFR fixing, a different measure
“It's a three-year loan secured by all Helios Phase 1 assets, priced at SOFR plus 475 basis points plus ancillary fees, bringing the all-in cost to approximately 10% to 11%, if held to maturity.”
Galaxy Q3-2025 earnings call (Oct 21 2025), company transcript · investor.galaxy.com - phase-ii-notes$3.507B$3,507,000,000 of 9.875% senior secured notes due Aug 1 2031, sold Jul 28 2026 at 99.500% by Galaxy Helios Data Centers II LLC ('$3.5 billion' in the 10-Q; a $17.5M discount), to finance part of 'two buildings containing eight data halls' with 400 MW of utility and 260 MW of critical IT capacity — Phase II — and fund debt-service reserves; interest from Feb 1 2027. Proceeds not yet spent sat in U.S. Treasuries at Sep 30 2026 (10-Q). Subject to exceptions, the proceeds of any 'Data Center Lease Termination Fee' must be offered to the noteholders
“The aggregate principal amount of Notes sold in the Offering was $3,507,000,000.”
Galaxy 8-K, Items 1.01/2.03 (filed Jul 28 2026) · sec.gov - completion-guaranteewhat Galaxy itself stands behind on Phase II: GDH LP's uncapped promise to fund each phase of the project to rent commencement under the CoreWeave lease if the notes' money and other funds fall short — a completion guarantee, not a guarantee of the notes
“In connection with the Offering, Galaxy Digital Holdings LP (“Galaxy LP”), the indirect parent of the Issuer, has provided a customary, uncapped completion guarantee with respect to the Project”
Galaxy 8-K, Items 1.01/2.03 (filed Jul 28 2026) — Completion Guarantee · sec.gov - notes-amortizationwhen the notes start to repay: on the first payment date (Feb 1 or Aug 1) ten months after CoreWeave first pays rent following the Commencement Date — the indenture's rule; the 8-K's 'at least ten months after the completion of the Project' is its summary. Until then, interest only
““Amortization Commencement Date” means the first Payment Date to occur after the date that is ten (10) months after the date on which rent is first paid pursuant to the Data Center Lease following the Commencement Date”
Galaxy 8-K ex-4.1, indenture (filed Jul 28 2026) — definitions · sec.gov - end-userwhat Galaxy knows of the end user: CoreWeave has told it Phase I's load comes from a contract 'currently allocated to' an unnamed hyperscaler, and who will use Phases II and III is not yet known — 'They decide at that point in time, in 2027'. Galaxy's May post said the same ('a multi-trillion-dollar investment-grade public company will be the end user for Phase I GPUs'). The party is not named, so the record names none and draws no link to it
“We have been communicated from CoreWeave that the loads running today that we see every day on the screen in Helios I are coming from a customer contract that's currently allocated to a large multi-trillion dollar investment grade hyperscaler.”
Galaxy Q3-2026 earnings call (Oct 27 2026), company transcript · investor.galaxy.com - tenant-names-landlordthe tenant naming its landlord: CoreWeave's CEO, in a Bloomberg interview CoreWeave filed under Rule 425 during its bid for Core Scientific, gives Galaxy as an example of the other providers of power it has turned to. CoreWeave's 10-Qs and 10-K name neither Galaxy nor Helios
“A great example of that is Galaxy Digital. You know, where we're able to go ahead and get large blocks of continuous power to continue to buy infrastructure that will be made available to our clients as they continue to build.”
CoreWeave Rule 425 filing, the CEO's Bloomberg interview (Oct 7 2025) · sec.gov
Contested figures 15 not reconciled — every position side by side, with its source and tier
For context, not this deal's figures 1 kept beside the deal so they are not mistaken for its numbers
- unleased-power830 MW830 MW of the campus's approved gross power not yet leased: ERCOT has approved 'over 1.6 gigawatts' at Helios — 1,630 MW, of which 800 MW (Helios I) carries CoreWeave's 526 MW and 830 MW (Helios II, approved Jan 15 2026 — 8-K, Item 8.01) is 'available to be contracted'. The 830 MW and the 1 GW load request beyond it are Galaxy's site, not this lease (galaxy entity)
“The remaining 830 MW of approved power capacity remains available to be contracted.”
Galaxy Q3-2026 10-Q, MD&A — Overview · sec.gov
Scope note what this record leaves to other records
NOT this record (carried elsewhere or not carried): the campus's and Galaxy's power beyond the 800 MW leased — Helios II's 830 MW (here only as the remainder, unleased-power), 'a path to 3.6 GW of total potential power' at Helios (Q3 deck) and the >5.7 GW Texas pipeline with Caspian, Selene and Merlin (Q3 10-Q) → the galaxy entity; Helios's purchase from Argo Blockchain in Dec 2022 ($65M by both parties, ~$77M with costs in Galaxy's 2023 S-4/A) and its 160 acres with an option on ~157 more (Argo's 20-F) → the galaxy entity; Galaxy's corporate capital — the 2029 and 2031 exchangeable notes, the Jun 2025 offering, the Oct 2025 Capital Group placement (whose new-share count Galaxy prints both as 9,027,778 and 9,072,778) — not carried; CoreWeave's own company figures — $47.5B of total indebtedness at Sep 30 2026, its backlog, Meta's order forms (cw-meta), CDS levels and a Goldman Sachs debt projection relayed by a podcast — not carried here; the notes' trading (89.25 on Nov 5 2026 by Reuters), their issue spread (554 vs 544.4 bp in two index tables) and a B+ rating known only from Reuters — not carried; backup generation at Helios (120 or 121 diesel generators, ~251–252 MW, in two TCEQ filings vs 327.2 MW in a PUCT registration) and Phase I's construction time (12–14 months by one newsletter, ~18 by Clayco, the contractor) — site facts, not carried. Not adopted: a newsletter's Phase II rent formula (14.5% of cost up to a $3.7B cap), its Phase III cost and rent estimates and its ~$19.7B three-lease total, and its naming of Microsoft as Phase I's end user — no primary document states any of them, and an end user the parties do not name is not decoded here (end-user); Knight Frank's '460MW'; MintVentures' 2024 dates for the 2025 leases; Epoch AI's modelled $5.0B and 528 MW, which price in IT hardware and project to 2029. Not marked circular: CoreWeave's $150M of prepaid rent and the $100M option payment are rent paid early to the landlord, not money that returns to the tenant; the Nvidia and OpenAI loops around CoreWeave that Galaxy's bond deck cites in its credit story belong to CoreWeave's own records.