Core Scientific–CoreWeave

CoreWeave rents about 590 of data-center capacity at five Core Scientific sites — 262 MW of it at Denton, Texas — on 12-year licenses Core Scientific counts at more than $10B, and pays for most of the construction itself, getting part of it back as credits against its fees.

A deal between CoreWeave, Core Scientific

Why it matters

CoreWeave funds the substantial majority of a more-than-$5B build at its landlord's sites. Prepaid fees for Core Scientific's equipment become the landlord's revenue and offset CoreWeave's bills. Both companies borrow against the same licenses, and CoreWeave accounts for 84% of Core Scientific's revenue.

Tap a figure for the line in its source.

Core Scientific gives CoreWeave

  • of data-center capacity at five sites, six facilities in all — 262 of it at Denton, Texas — on 12-year licenses (seven years at Austin)
  • of the build itself for Denton's 70 expansion, with no credit back — its only direct outlay on the contract, its CEO said
  • two five-year renewal options on each license, at CoreWeave's election — whether Austin's has them is disputed

CoreWeave gives Core Scientific

  • disputedof license fees over the 12-year terms by Core Scientific's count — $10.2B in its releases, which were furnished, not filed; about $9.28B was still owed at Sep 30 2026 by its filed accounts
  • pays for the substantial majority of a build of more than $5B — the part that buys Core Scientific's own equipment as prepaid fees, up to $1.5M per of which comes back as credits against half of each monthly fee; the rest is equipment CoreWeave owns until the term ends

Mar 6, 2024 Austin's 16 MW announced by Core Scientific and CoreWeaveupdated Nov 21, 2026 disclosed by the parties

What happened

Core Scientific is a bitcoin miner converting its sites into data centers. It rents about 590 megawatts of capacity at five of those sites to CoreWeave under licenses signed between February 2024 and February 2025. The licenses run 12 years each, with a term of seven at Austin. The largest share is 262 at Core Scientific's campus in Denton, Texas. CoreWeave owns the chips there. A lender and the Wall Street Journal say the chips are meant for OpenAI. Core Scientific's chief executive, citing public statements, has said OpenAI is working with CoreWeave there. CoreWeave pays for the substantial majority of construction. CoreWeave prepays fees to fund purchases of Core Scientific's own equipment. Core Scientific credits those fees against CoreWeave's monthly bills. The rest of CoreWeave's contribution is equipment it owns until the licenses end. At September 30, 2026, 485 MW were in service and billing. CoreWeave accounted for 84% of Core Scientific's revenue in the first nine months of 2026. Core Scientific's releases put the licenses at $10.2 billion over their terms. Core Scientific furnished those releases to the SEC without filing them. Its filed proxy says 'more than $10 billion'. Its accounts show about $9.3 billion of fees still owed at September 30, 2026. Both companies now borrow against these contracts. Core Scientific sold $3.3 billion of notes secured on the five sites, with a repayment schedule tied to CoreWeave's rent. CoreWeave moved 31 of the agreements into a financing vehicle of its own. Core Scientific rents the land at Denton from the city. Under its terms, the ground lease runs to 2035 and can be extended only together with the city's power contract. Core Scientific's books assume 25 years. The buildings pass to the city when the lease ends.

Sources 50 documents — 36 SEC filings · 5 other documents · 2 transcripts · 2 government statements · 2 company releases · 1 market-data page · 1 press report · 1 research note

Research trail Found 185 documents and read 172 of them while checking this deal and related ones.

  1. SEC filingsec.gov
    States 7 figures: 262 MW denton allocation · license term · $100 monthly fee per kw · up to $1.5M credit cap per MW · denton license · buildings revert · PPA term
  2. SEC filingsec.gov
    States 5 figures: 16 MW first contract · 200 MW initial contracts · 120 MW final option · $104M denton expansion capex · $17.6M ground lease amendment
  3. SEC filingsec.gov
    States 5 figures: 590 MW leased capacity · prepaid fees · cw spv · $3.3B landlord notes · notes amortization
  4. SEC filingsec.gov
    States 3 figures: $1.8B payments not yet commenced · 485 MW billing · 84% concentration
  5. SEC filingsec.gov
    States 2 figures: cw spv sites · cw spv rating
  6. SEC filinginvestors.corescientific.com
    States 16 MW first announcement
  7. SEC filingsec.gov
    States more than $3.5B initial value
  8. SEC filingsec.gov
    States extension options
  9. d1io3yog0oux5.cloudfront.net · transcriptd1io3yog0oux5.cloudfront.net
    States $1.45M revenue per MW
  10. SEC filingsec.gov
    States more than $5B build investment
  11. SEC filingsec.gov
    States 250 MW delivery guidance
  12. SEC filingsec.gov
    States denton end customer
  13. a local government agenda · government statementlegistar2.granicus.com
    States $53,949.81 monthly ground rent
  14. SEC filingsec.gov
    States more than 500 MW tenant side
  15. MarketBeat · market-data pagemarketbeat.com
    States $104M landlord capex
  16. wholesale.banking.societegenerale.com · other documentwholesale.banking.societegenerale.com
    States denton end customer lender
  17. Tiger Brokers · press reportitiger.com
    States denton end customer press
  18. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  19. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  20. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  21. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  22. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  23. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  24. company releaseinvestors.corescientific.com
    Cited by the record; no single figure is quoted from it.
  25. SEC filinginvestors.corescientific.com
    Cited by the record; no single figure is quoted from it.
  26. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  27. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  28. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  29. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  30. other documentd1io3yog0oux5.cloudfront.net
    Cited by the record; no single figure is quoted from it.
  31. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  32. company releaseinvestors.corescientific.com
    Cited by the record; no single figure is quoted from it.
  33. SEC filinginvestors.corescientific.com
    Cited by the record; no single figure is quoted from it.
  34. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  35. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  36. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  37. SEC filingSep 10, 2026investors.corescientific.com
    Cited by the record; no single figure is quoted from it.
  38. government statementlegistar2.granicus.com
    Cited by the record; no single figure is quoted from it.
  39. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  40. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  41. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  42. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  43. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  44. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  45. transcripts205.q4cdn.com
    Cited by the record; no single figure is quoted from it.
  46. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  47. other documentstorage.courtlistener.com
    Cited by the record; no single figure is quoted from it.
  48. other documentstorage.courtlistener.com
    Cited by the record; no single figure is quoted from it.
  49. other documentstorage.courtlistener.com
    Cited by the record; no single figure is quoted from it.
  50. research noteepoch.ai
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: Core Scientific FY2024 10-K and 10-K/A, Q1 and Q2 2025 10-Q/As, Q3 2025 10-Q, FY2025 10-K, Q1, Q2 and Q3 2026 10-Qs, DEF 14As (Mar 2025 and Mar 2026), indenture (May 2026); Two Seas Capital's DEFC14A (Sep 2025); Core Scientific's releases of Mar 6, Jun 3, Jun 25, Aug 6, Oct 22 and Nov 20 2024 and Feb 26 2025, its decks, the Jun 2024 investor day and the Q1-2025 call, the Apr 2026 offering memo and the Sep 2026 8-K (all furnished or unfiled); City of Denton Third Amendment (Oct 2024); CoreWeave 424B4 and SEC letter (Mar 2025), Rule 425 materials (Jul 2025), Q3-2025 10-Q and call, DDTL 3.0 and March 2026 SPV credit agreements; Malikie v. Core Scientific, E.D. Tex. (third-party complaint, answer, stipulation; 2026); Société Générale (Nov 2025), the WSJ via Tiger Brokers (Dec 2025), Epoch AI (read 2026-10) · as of Sep 2026

The evidence 34 sourced figures · 10 disputes

The record's headline Core Scientific–CoreWeave: ~590 of colocation licenses at five sites (262 MW at Denton TX), 12-year terms — the tenant funds most of the build; Core Scientific's $10.2B headline only in releases it furnished ('more than $10 billion' filed); Denton's land is the City's

Size
~590 MW · >$10B over 12-yr terms (filed proxy; '$10.2B' furnished only by Core Scientific)
When
Feb 2024 Austin → Jun–Oct 2024 ~200 MW (Jun 3, or May by one 10-K/A passage: contract-date) and three options → Feb 2025 Denton +70 MW (~590 MW) · billing from 2024 (Austin) to full build 1H 2027 · 12-year terms from each commencement (Austin seven)
Status
signed Feb 2024 – Feb 2025 · 485 of 590 MW billing at Sep 30 2026 (395 at Jun 30) · full build expected 1H 2027 · 31 agreements assigned to CW SPV in H1 2026, CoreWeave still a primary obligor (the Q2 10-Q names none; by the Q1 10-Q, CW SPV is the licensee under Dalton 1's and Denton North's)
Structure
colocation licenses, booked by the landlord as operating leases: six facilities at five sites, each license running 12 years from its own commencement (Austin seven), with two five-year extension options for CoreWeave (disputed at Austin); base fee $100/kW/month escalating 3.5% a year (Austin $115, 3.0%); CoreWeave funds the build — the landlord's own equipment as prepaid fees, up to $1.5M/MW credited back against half of each monthly fee, and the rest as 'Contributed Assets' it owns until the term ends; CoreWeave pays power as a pass-through; late-delivery credits of $20,000–30,000 a day and CoreWeave's right to terminate an order 120 days late (offering memo, furnished). None of the agreements appears as an exhibit in the 10-K text on file
Programme
CoreWeave contract web
Parties
CoreWeave licensee — pays the fees and most of the build; since H1 2026 its indirect subsidiary CW SPV holds 31 of the agreements, CoreWeave still a primary obligor; a CoreWeave affiliate is the Denton licensee · Core Scientific licensor and builder — on land it owns (Marble, Muskogee) or leases (Austin; Denton from the City; both Dalton facilities from the Dalton-Whitfield County Joint Development Authority, in bond-financed sale-leasebacks); about 84% of its revenue in the first nine months of 2026 is CoreWeave's; its five site subsidiaries secure $3.3B of notes
Site
CoreWeave Denton
Record
disclosed / primary source · as of Sep 2026

Flows 3 as the record states them

  • CoreWeave → Core Scientificlicense-feesbase fees on ~590 MW over 12-year terms: 'more than $10 billion' of projected revenue (filed proxy) / $10.2B (furnished releases); ≈ $9.28B of noncancellable payments still owed at Sep 30 2026 (10-Q lessor tables, our sum); power passed through on top
  • CoreWeave → Core Scientificconstruction-fundingthe substantial majority of more than $5B of build-out (proxy). The part that buys Core Scientific's own equipment is booked as prepaid base license fees and recognized as revenue as capacity enters service (Q2-2026 10-Q), and up to $1.5M/MW of it comes back to CoreWeave as credits against half of each monthly fee; the rest, the 'Contributed Assets', CoreWeave owns until the term ends (memo)
  • Core Scientific → CoreWeavecapacity~590 MW of critical IT across six facilities at five sites — Denton 262, Dalton 4 145, Muskogee 70, Marble 65, Dalton 1 30, Austin 16.5 (offering memo); 485 MW billing at Sep 30 2026

Resolved figures 34 each with the verbatim line from its document

  • first-contract16 MW
    16 MW at Austin, Texas, signed Feb 29 2024 — the first of the licenses, in a building Core Scientific itself leases (a former Hewlett Packard data center), announced by both companies on Mar 6 2024 with 'more than $100 million' of potential revenue (first-announcement). Billing since the second quarter of 2024 ('lease operations at our Austin, Texas data center, which commenced in the second quarter of 2024', FY2025 10-K). Its allocation is 16.5 MW in the 2026 offering memo — 16 MW as signed, 16.5 MW as allocated, ~20 MW the site's grid capacity (the memo's list of all six, in denton-allocation)
    “On February 29, 2024, the Company entered into a long-term contract with CoreWeave, Inc. (“CoreWeave”) to deliver 16 MW of infrastructure at the Company’s Austin, Texas facility.”
    Core Scientific FY2024 10-K/A (filed Mar 2 2026), MD&A — Developments During 2024 · sec.gov
  • first-announcement16 MW
    the day the deal became public: a joint announcement of the Austin contract on Mar 6 2024 ('The total potential revenue associated with the contract is more than $100 million'). Core Scientific furnished it under Item 7.01; only its IR site's copy of the exhibit is on file. Every later step — the ~200 MW series of Jun 3 2024, three options, the Denton expansion — added to this relationship, and the ~590 MW counts Austin in
    “and CoreWeave, the leading specialized GPU cloud provider, today announced a multi-year contract for Core Scientific to supply up to 16 MW of data center infrastructure to CoreWeave.”
    Core Scientific 8-K ex-99.1 (Mar 6 2024; furnished, Item 7.01) — IR copy · investors.corescientific.com
  • initial-contracts200 MW
    a series of 12-year contracts for ~200 MW, entered into on Jun 3 2024 and released that evening (IR page: 'June 03, 2024 8:38 pm EDT'), which also gave CoreWeave options on further sites 'over the next 60 to 90 days'. The release (furnished) said all the capital to convert the sites 'will be funded by CoreWeave', an estimated $300M of it credited back 'at no more than 50% of monthly fees until fully repaid'. The overview that opens the 10-K/A's MD&A dates the same expansion 'In May 2024' (contested contract-date)
    “Following the commencement of operations in the Austin, Texas facility, on June 3, 2024, the Company entered into a series of long-term contracts with CoreWeave to deliver approximately 200 MW of infrastructure to host CoreWeave’s HPC operations, which will require the Company to modify multiple existing sites.”
    Core Scientific FY2024 10-K/A, MD&A — Developments During 2024 · sec.gov
  • initial-valuemore than $3.5B
    'over $3.5 billion' over the initial 12-year terms once the ~200 MW is running, ~$290M a year on average — Core Scientific's projection, footnoted 'before prepaid build out costs'. It reached EDGAR in a furnished release (Item 7.01), as each later running total first did; the 10-Qs and 10-Ks give megawatts, terms and GAAP lease payments, never these totals, though the filed proxy says 'more than $10 billion' and a shareholder's filed proxy repeats the $10.2B (contract-value)
    “Once the approximately 200 MW of HPC infrastructure is operational, the project is estimated to generate total cumulative revenue for Core Scientific of over $3.5 billion during the initial 12-year terms of the contracts.”
    Core Scientific 8-K ex-99.1 (filed with the SEC Jun 4 2024; furnished, Item 7.01) · sec.gov
  • final-option120 MW
    the final option, ~120 MW, announced Oct 22 2024 — the last of three CoreWeave took in 2024: ~70 MW announced Jun 25 (Core Scientific converts 100 MW of its own infrastructure to deliver it), 112 MW on Aug 6 (382 MW in all at five sites) and the final ~120 MW on Oct 22 (~500 MW 'of critical IT load at six Core Scientific sites', on ~700 MW of gross infrastructure). The furnished releases priced them at $1.225B, ~$2.0B and ~$2.0B of projected cumulative revenue ('projected additional cumulative revenue' in August's and October's), for running totals of more than $4.7B, $6.7B and $8.7B — 'before capex credits provided to CoreWeave', the August and October footnotes say, where June's says 'before prepaid build out costs'. The 112 MW's value is contested (option-112-value). The Jun 2024 70 MW option is a different contract from the Feb 2025 Denton expansion, though both are ~70 MW and were announced at ~$1.2B (the expansion's value is contested: feb-2025-value)
    “Further, on August 6, 2024, the Company announced that CoreWeave had executed an option to secure an additional 112 MW of infrastructure to host its HPC operations. On October 22, 2024, the Company announced that CoreWeave had exercised its final option for an additional 120 MW of infrastructure.”
    Core Scientific FY2024 10-K/A, MD&A — Developments During 2024 · sec.gov
  • denton-expansion-capex$104M
    the ~$104M of capital expenditures Core Scientific is 'contractually committed' to for its Feb 26 2025 expansion at Denton: +70 MW, taking the campus to 'just over 260 MW' of critical IT and CoreWeave's total at Core Scientific to ~590 MW 'across six sites' (release, furnished). Six facilities at five sites — Dalton has two — is how the 2026 offering memo counts the same portfolio, so the release's 'six sites' and the 10-Q's 'five sites' agree. For this expansion Core Scientific funds $104M of capex ('$1.5M per MW') for the 'powered core and shell' with 'no capex credit', CoreWeave the rest (Q1-2025 deck, furnished); 69.6 MW and $104.4M in the memo. Its value ($1.2B vs CoreWeave's ~$1.7B) and whether the 70 MW is critical IT or gross power are contested (feb-2025-value, expansion-basis)
    “On February 26, 2025, the Company announced a new agreement with CoreWeave to deliver an additional 70 MW of infrastructure at the Company’s Denton, Texas facility. Under the terms of this agreement, the Company is contractually committed to approximately $104 million in capital expenditures.”
    Core Scientific FY2024 10-K/A, subsequent events · sec.gov
  • leased-capacity590 MW
    ~590 MW of 'leased customer power capacity across five sites': the whole of the licenses, the same 590 MW as at Dec 31 2025 and Mar 31 2026 ('Leased Customer Power Capacity' in the FY2025 10-K and Q1-2026 10-Q). The sites are Austin TX, Dalton GA (two facilities), Denton TX, Marble NC and Muskogee OK. The tenant says the same: 'more than 500 MW' at Dec 31 2024 in its IPO prospectus and 'about 590 MW' in its Mar 2025 letter to the SEC staff (tenant-side)
    “In 2024, we announced our first HDC contract with CoreWeave, a provider of HPC services, which was subsequently expanded to approximately 590 MW of leased customer power capacity across five sites.”
    Core Scientific Q2-2026 10-Q (filed Jul 28 2026), MD&A — Overview · sec.gov
  • denton-allocation262 MW
    Denton's 262 MW, the largest of CoreWeave's six allocations by facility as the April 2026 notes offering memo summarizes the license agreements (the memo here is Core Scientific's 'Supplemental Information regarding Core Scientific, Inc.', furnished for its notes offering as 8-K ex-99.2; the document never calls itself a memorandum): Dalton 1 30 MW, Dalton 4 145 MW, Marble 65 MW, Muskogee 70 MW, Denton 262 MW, Austin 16.5 MW — 588.5 MW in all (our sum), the ~590 MW. For Austin, this record uses 16.5 MW, not the 16 MW signed or the ~20 MW of grid power. The memo calls them 'six data center facilities across five sites that have been 100% licensed to CoreWeave', with ~900 MW of grid capacity secured across the five; it is furnished (Item 7.01)
    “CoreWeave’s power allocation for each facility, as set forth in the CoreWeave Licensing Agreements, is as follows: (i) Dalton 1 – 30 MW, (ii) Dalton 4 – 145 MW, (iii) Marble Campus – 65 MW, (iv) Muskogee Campus – 70 MW, (v) Denton Campus – 262 MW, and (vi) Austin Campus – 16.5 MW.”
    Core Scientific 8-K ex-99.2, notes offering memo (Apr 21 2026; furnished, Item 7.01) · sec.gov
  • license-term12
    12 years from each license's own commencement (Austin seven), with two successive five-year extensions at CoreWeave's option except at Austin. The filed 10-Qs carry the 12 years ('initial lease terms of 12 years from commencement'); who holds the options is the memo's account — the Feb 2025 release's 'The company also retains the option for two additional five-year renewal terms' names no company, but the same release calls Core Scientific 'the company' ('The company is actively seeking additional sites'), so on its face it gives the options to Core Scientific, against the memo's 'available to CoreWeave'. Whether Austin has extensions is contested (austin-extensions). The landlord does not count on renewal (extension-options)
    “The CoreWeave Licensing Agreements run for an initial term of 12 years across all sites (with the exception of the Austin Colocation License Agreement, which is for a term of seven years), with two successive five-year extension options available to CoreWeave (with the exception of the Austin Colocation License Agreement, which does not include extension options).”
    Core Scientific notes offering memo (Apr 21 2026; furnished) · sec.gov
  • extension-options
    Core Scientific's own accounts treat CoreWeave's renewal options as 'not reasonably certain to be exercised' and leave them out of the lease term — while, as a tenant itself, it counts renewals it is 'reasonably certain of exercising' (FY2024 10-K/A lease policy), which on our reading is how its Denton ground lease comes to be booked at 25 years; the 10-K/A gives no reason (ground-lease-term)
    “Certain arrangements include options to extend the term. These extension options are not reasonably certain to be exercised and are excluded from the lease term and calculation of lease payments at lease commencement.”
    Core Scientific FY2025 10-K (filed Mar 2 2026), Note 2 — Revenue Recognition, Colocation · sec.gov
  • monthly-fee-per-kw$100
    the fee rate the licenses set: $100 per kW per month base fee ($115 at Austin), rising 3.5% a year (3.0% at Austin), with power billed on top. 590 MW at $100/kW-month is ~$708M in a first year, and 12 years of 3.5% steps make ~$10.3B (our arithmetic, ignoring Austin's shorter term and the credits) — the order of the $10.2B headline. In the furnished memo only
    “CoreWeave pays a base license fee of $100 per kW per month (or $115 per kW per month for the Austin Campus), with annual rent increases of 3.5% (3.0% for the Austin Campus) built into the CoreWeave Licensing Agreements.”
    Core Scientific notes offering memo (Apr 21 2026; furnished) · sec.gov
  • revenue-per-mw$1.45M
    $1.45M of revenue per MW a year on the ~200 MW contracts of June 2024, inside the $1.4M–$1.6M Core Scientific had guided on its Q1-2024 call — its June 12 2024 investor day, in the transcript and in the deck it furnished ('CoreWeave HPC Contracts Revenue Per MW/ Year $1.4M – $1.6M $1.45M'). It fits the fee rate (monthly-fee-per-kw): $100 per kW a month rising 3.5% a year averages about $122 over 12 years, about $1.46M per MW a year (our arithmetic)
    “Our revenue is $1.45 million per year per megawatt”
    Core Scientific investor day (Jun 12 2024), transcript on its IR site · d1io3yog0oux5.cloudfront.net
  • payments-not-yet-commenced$1.8B
    $1.8B of future noncancellable payments at Sep 30 2026 on CoreWeave licenses that had not yet commenced — the footnote half of the filed measure of what CoreWeave owes. Each 10-Q and 10-K lessor note gives the minimum payments on licenses that have commenced plus, in a footnote, those that have not: $151.5M + $10.0B at Mar 31 2025 (≈ $10.15B, our sum, a month after the Denton expansion), $1.77B + $8.17B at Dec 31 2025 (≈ $9.94B), $3.39B + $5.8B at Mar 31 2026 (≈ $9.19B), $6.09B + $3.1B at Jun 30 2026 (≈ $9.19B) and $7.48B + $1.8B at Sep 30 2026 (≈ $9.28B). Core Scientific leases 'property to a customer under licensing agreements' and its colocation revenue is 'derived entirely from a single customer, CoreWeave', so these are CoreWeave's payments; the Q3-2026 10-Q's footnote names CoreWeave itself, and leaves AMD's July 2026 leases, none yet commenced, out of both tables (amd-corz). The filings never tie them to the $10.2B (contract-value)
    “(1)Operating lease payments expected to be received exclude $1.8 billion in total future noncancellable operating lease payments expected to be received for CoreWeave operating leases that have not yet commenced as of September 30, 2026, which have initial lease terms of 12 years from commencement.”
    Core Scientific Q3-2026 10-Q (filed Nov 5 2026), lessor accounting note · sec.gov
  • build-investmentmore than $5B
    'more than $5 billion of infrastructure investment' in the builds at Denton, Marble, Muskogee and Dalton, 'the substantial majority' of it 'expected to be funded by our customer', CoreWeave (the proxy's letter to stockholders). Core Scientific collects the money before it pays contractors — 'customer funding receivable' of $383.8M at Jun 30 2026, 'amounts due from the Company’s customer for construction-related payables and accrued expenses incurred on their behalf' (Q2-2026 10-Q). Of Core Scientific's $1.5B of capital expenditures in the first nine months of 2026, at all its sites, '$180.9 million was funded by CoreWeave pursuant to its existing colocation service agreement' (Q3-2026 10-Q). Estimated cost $5.5B, ~$4.4B (~80%) contributed by the two companies together by April 2026 (offering memo, furnished). Two carve-outs: the memo excepts Austin's license from CoreWeave's duty to fund the build ('Except with respect to the Austin Colocation License Agreement'), and Core Scientific funds the powered core and shell of Denton's 70 MW expansion itself, $104M with no credit back (denton-expansion-capex) — 'our only direct capital outlay on the contract', its CEO said (landlord-capex)
    “In total, these buildouts represent more than $5 billion of infrastructure investment, the substantial majority of which is expected to be funded by our customer.”
    Core Scientific definitive proxy statement (DEF 14A, Mar 2026), letter to stockholders · sec.gov
  • prepaid-fees
    how the part of the build money that buys Core Scientific's own equipment is booked: as prepaid base license fees, deferred revenue that 'is recognized as revenue as capacity is placed into service over the course of several billing cycles as the prepaid fees are used up' — while CoreWeave takes it back as 'build credits' during the first billing period, up to $1.5M per MW (credit-cap-per-mw). The rest of the build is the memo's 'Contributed Assets', which CoreWeave provides at its own cost (except at Austin) and owns until the term ends. The FY2025 10-K splits Core Scientific's construction commitments the same way, on our reading — it never uses the memo's terms, but its customer funding receivable is for costs 'incurred on their behalf' (Note 6): at Dec 31 2025, of about $989.8M, '$716.8 million will be passed through to the Company’s customer as invoiced and $30.1 million will be funded by the customer as prepaid base license fees'. So part of the tenant's construction money returns to the landlord as revenue and to the tenant as a discount on its bills
    “Colocation deferred revenue reflects advance payments received from our customer for contracted capacity, including prepaid base license fees received in connection with the customer-funded development of colocation facilities. During the initial billing period, CoreWeave receives build credits that offset a portion of amounts otherwise due, which affects the timing of cash collection relative to revenue recognition.”
    Core Scientific Q2-2026 10-Q, MD&A — Deferred Revenue · sec.gov
  • credit-cap-per-mwup to $1.5M
    up to $1.5M per MW, the cap on the build credit — its terms in the offering memo (furnished): the build costs CoreWeave pays or reimburses for the licensor's equipment are credited against base fees up to that cap, 'as a fifty percent (50%) credit against the amount of each monthly base license fee' until used up; the rest of the build is 'items purchased directly by CoreWeave and contributed for use in the facility' (Q1-2025 deck, furnished). An 'End of Term Credit' of $217,163 per MW (Denton, Dalton 1, Dalton 4) or $228,413 (Muskogee, Marble) applies in a license's last two months. The pool's total is contested (credit-pool)
    “Under the CoreWeave Licensing Agreements (as defined below), CoreWeave covers all construction costs, which are offset by partial revenue credits capped at $1.5 million per MW.”
    Core Scientific notes offering memo (Apr 21 2026; furnished) · sec.gov
  • landlord-capex$104M
    the May 7 2025 call: in the CEO's prepared remarks (Adam Sullivan), CoreWeave funds 'virtually all' of the capex and Core Scientific's only direct outlay is the $104M for Denton's expansion, and the licenses are 'a take-or-pay fixed-price contract'; asked by an analyst about the '$300 million coming out of escrow' that CoreWeave's S-1 mentioned, the CFO (Jim Nygaard) said 'We were able to effectively eliminate the escrow arrangement' and that Core Scientific does not pay a contractor 'until we receive the funds from CoreWeave'
    “From a capital perspective, CoreWeave is funding virtually all of the CapEx associated with these deployments. Our only direct capital outlay on the contract is $104 million associated with a 70 megawatt expansion we announced during our last earnings call.”
    Core Scientific Q1-2025 earnings call (MarketBeat transcript) · marketbeat.com
  • billing485 MW
    485 of the 590 MW billing at Sep 30 2026, the other 105 MW 'in various stages of construction and commissioning'; 120 MW at Dec 31 2025 (FY2025 10-K), 225 MW at Mar 31 2026 (Q1 10-Q) and 395 MW at Jun 30 2026 (Q2 10-Q); 437 MW by mid-July, 'representing approximately $635 million in average annualized colocation GAAP revenue' (Q2 release, furnished). Full build expected in the first half of 2027 (offering memo). Commencement had occurred at Austin, Denton and Marble by April 2026 (memo); Denton was billing in 2025 (FY2025 10-K)
    “Billable customer power capacity of 485 MW as of September 30, 2026, against 590 MW of leased customer power capacity to CoreWeave, with the remaining 105 MW in various stages of construction and commissioning.”
    Core Scientific Q3-2026 10-Q (filed Nov 5 2026), MD&A — 2026 Highlights · sec.gov
  • delivery-guidance250 MW
    the company's own year-end target, missed: in October 2025 it expected 250 MW billable by the end of 2025, after 'a variety of weather and construction related delays have moved the delivery dates to later in fiscal 2025 than planned' (same 10-Q); it billed 120 MW at Dec 31 2025 (FY2025 10-K). The WSJ's sources (Dec 2025, via Tiger Brokers) put a ~60-day concrete delay at Denton behind a slip of 'several months' in the ~260 MW cluster; that December CoreWeave eased its DDTL 3.0 covenants to fit the later deliveries (cw-ddtl3-2025)
    “Under these arrangements, we expect to deliver 250MW of billable capacity by the end of 2025.”
    Core Scientific Q3-2025 10-Q (filed Oct 24 2025), MD&A — Overview · sec.gov
  • concentration84%
    CoreWeave was ~84% of Core Scientific's revenue in the nine months to Sep 30 2026 (~77% in H1 and 83% in Q2, by the Q2-2026 10-Q) and all of its colocation revenue: lease revenue $215.4M in Q3 ($157.3M operating + $58.2M variable) and $429.6M in the nine months (Q3-2026 10-Q); in Q2, $136.7M ($98.8M of license fees + $37.9M variable: $35.1M of power 'passed through to our customer without markup' and $2.8M of maintenance and other, by the segment table). 'High-density colocation is now our primary business', the 10-Qs say, with mining being wound down
    “Our colocation revenue is currently derived entirely from a single customer, CoreWeave, a provider of HPC services. For the nine months ended September 30, 2026, CoreWeave represented approximately 84% of our total revenue.”
    Core Scientific Q3-2026 10-Q (filed Nov 5 2026), MD&A — Key Factors Affecting Our Financial Performance · sec.gov
  • cw-spv31
    in H1 2026 CoreWeave moved 31 agreements to 'CW SPV', an indirect subsidiary, which is now the licensee; CoreWeave remains a primary obligor. Core Scientific's warning in the same passage: its 'practical ability to enforce recourse against CoreWeave would depend on its financial condition at the time of any default'
    “During the period, CoreWeave entered into assignment and assumption agreements transferring certain license agreements to CW SPV, a special purpose vehicle that is an indirect subsidiary of CoreWeave. CoreWeave remains a primary obligor under those 31 agreements.”
    Core Scientific Q2-2026 10-Q, MD&A — Key Factors Affecting Our Financial Performance · sec.gov
  • cw-spv-sites
    which licenses: Dalton 1's and Denton North's, with their orders — CoreWeave's notice that it intended to assign them, and in the same passage 'CW SPV is now the Licensee under the License Agreements' (Q1-2026 10-Q, under Recent Developments, undated). The Q2-2026 10-Q counts 31 agreements assigned during the six months and names none of them; that these two are among the 31 is our reading, since the Q1 10-Q, filed May 6 2026, already has them in the vehicle within that half. Which CoreWeave financing the vehicle belongs to, no document on file says: CoreWeave's March 2026 SPV credit agreement pledges a 'Colocation License Agreement' whose parties are redacted
    “The Company received notice from its counterparty, CoreWeave, Inc., of its intention to enter into assignment and assumption agreements for our Dalton 1 and Denton North Colocation License Agreements and Orders, as amended, ("License Agreements") with a special purpose vehicle that is an indirect subsidiary of CoreWeave, Inc. ("CW SPV"). We understand that CW SPV received certain commitments from a customer sufficient for the debt issued by CW SPV to obtain an investment grade rating. While CoreWeave remains a primary obligor under the terms of the License Agreements, as a result of the assignment and assumption agreements, CW SPV is now the Licensee under the License Agreements.”
    Core Scientific Q1-2026 10-Q (filed May 6 2026), MD&A — CoreWeave Special Purpose Vehicle · sec.gov
  • cw-spv-rating
    what stands behind the vehicle's debt, as Core Scientific understands it: commitments from a customer — unnamed, and the filing does not say whose — sufficient for the debt to obtain an investment-grade rating. The Q2-2026 10-Q calls the vehicle 'a special purpose vehicle financing structure'
    “We understand that CW SPV received certain commitments from a customer sufficient for the debt issued by CW SPV to obtain an investment grade rating.”
    Core Scientific Q1-2026 10-Q, MD&A — CoreWeave Special Purpose Vehicle · sec.gov
  • landlord-notes$3.3B
    the landlord's side: $3.30B of 7.75% senior secured notes due 2031, issued May 6 2026 by Core Scientific Finance and secured on 'Core Scientific Austin LLC, Core Scientific Denton LLC, Core Scientific Dalton LLC, Core Scientific Marble LLC and Core Scientific Muskogee LLC' — the five site companies to which Core Scientific assigns the CoreWeave licenses (offering memo). The proceeds funded a debt-service reserve and repaid a $1.0B term loan; their net amount is disputed
    “On May 6, 2026, Core Scientific Finance, an indirect wholly-owned subsidiary of the Company, completed a private offering of $3.30 billion aggregate principal amount of 7.75% Senior Secured Notes due 2031 at an issue price of 99.25% of the principal amount.”
    Core Scientific Q2-2026 10-Q, Note 7 — Debt · sec.gov
  • notes-amortization
    the notes repay on CoreWeave's clock: principal (at an initial 11.50% a year of the original amount) starts only after rent commences and CoreWeave's build credits are used up — 'the timing of principal amortization is directly linked to our operational delivery milestones under our colocation arrangements', the 10-Q says. CoreWeave's credits come before the bondholders' principal
    “The First Installment Payment Date is defined as the first semi-annual payment date occurring at least 15 days after both rent commencement under the related data center leases and the abatement of all revenue credits provided to the tenant. Revenue credits refer to fixed amounts credited against the tenant’s payment obligation during the initial ramp-up period under the license agreements.”
    Core Scientific Q2-2026 10-Q, MD&A — Debt Service and Capital Requirements · sec.gov
  • denton-license
    Denton's license is the only one of the six whose CoreWeave party the memo gives as 'its affiliate' — on our reading, the DDTL 3.0 loan's Co-Borrower, which holds it 'as assignee of Parent' (denton-end-customer) — and the only 'Amended and Restated' one; the filed May 2026 indenture lists it as 'the colocation license agreement (Denton, Texas combined)'. CoreWeave itself signed it: in a patent suit in federal court in Texas (Malikie Innovations v. Core Scientific), Core Scientific's claim against CoreWeave (Mar 2026) says the two 'entered into an Amended and Restated Colocation License Agreement' on Feb 26 2025, 'which amends, restates, supersedes, and combines agreements dated August 2, 2024, and June 3, 2024', under which CoreWeave has installed its equipment in Core Scientific's data centers, 'including the Denton, Texas data center'; CoreWeave's answer (Jun 2026) admits 'that it and Core Scientific entered into' that agreement, 'dated February 26, 2025'. 262 MW in eight buildings, A through H, on City of Denton land (offering memo, furnished)
    “Core Scientific and CoreWeave (or its affiliate, with respect to the Denton Colocation License Agreement) have entered into: (1) that certain Colocation License Agreement with respect to certain services and space located on the Dalton Campus (as amended, the “Dalton 1 Colocation License Agreement”); (2) that certain Amended and Restated Colocation License Agreement with respect to certain services and space located on the Denton Campus (as amended, the “Denton Colocation License Agreement”)”
    Core Scientific notes offering memo (Apr 21 2026; furnished) — CoreWeave Licensing Agreements · sec.gov
  • denton-end-customer
    OpenAI, on our reading of two documents' names — no Core Scientific filing ties OpenAI to Denton. CoreWeave's DDTL 3.0 credit agreement (filed Jul 2025; cw-ddtl3-2025), the loan for OpenAI's 'Phoenix 1' order under their Mar 7 2025 master services agreement, lets the borrowers pay rent under 'the Amended and Restated Colocation License Agreement' with Core Scientific — the name the offering memo gives only Denton's license, and the agreement under which, Core Scientific told a court, CoreWeave's equipment sits at Denton (denton-license). The site itself is tied to OpenAI by a lender and the press (denton-end-customer-lender, denton-end-customer-press) and by Core Scientific's CEO, relaying public statements in the prepared remarks of the May 7 2025 call: 'Notably, we understand from public statements that OpenAI is working with CoreWeave in Denton' (the transcript landlord-capex cites); Epoch AI lists OpenAI as the user, '(likely)'. The record draws no OpenAI link: the licensee is CoreWeave
    ““Permitted O&M Payments” shall mean payments relating to (a) lease or rent payments under the Amended and Restated Colocation License Agreement by and between Core Scientific, Inc. and the Co- Borrower (as assignee of Parent) or any other applicable data center or lease agreements”
    CoreWeave 8-K ex-10.1, DDTL 3.0 credit agreement (filed Jul 2025) — definitions · sec.gov
  • denton-end-customer-lender
    Société Générale, a lender in CoreWeave's DDTL 3.0, on its own site (Nov 2025): the loan finances GPUs 'to serve OpenAI’s workloads', to be housed at Denton — the one document that puts the OpenAI loan's chips at this site outright. The $2.6B in its line is the size of the loan (cw-ddtl3-2025), not a term of these licenses, so this row carries no figure
    “The $2.6 billion Delayed Draw Term Facility will be used to acquire the latest Nvidia GPU chips (Blackwell GB200s), assembled in Dell servers, and housed in a dedicated Core Scientific-operated data center in Denton, Texas.”
    Société Générale, 'Financing the rise of neoclouds' (Nov 2025) · wholesale.banking.societegenerale.com
  • denton-end-customer-press
    the WSJ (Dow Jones, via Tiger Brokers, Dec 16 2025): CoreWeave plans to rent Denton's chips to OpenAI, and Core Scientific is 'one of CoreWeave’s biggest landlords'. Tiger's copy credits Dow Jones, the WSJ's publisher; that the story is the WSJ's rests on Epoch AI's source list for the site ('WSJ - plans to rent to OpenAI')
    “CoreWeave plans to rent the chips at its Denton data-center cluster to OpenAI once it is built. The builder is Core Scientific, a former crypto-mining company based in Austin that has emerged as one of CoreWeave’s biggest landlords.”
    WSJ (Dow Jones) via Tiger Brokers (Dec 16 2025) · itiger.com
  • ground-lease-amendment$17.6M
    $17.6M of minimum lease payments at inception on the November 2024 amendment of the Denton ground lease, which the 10-K/A books as a new operating lease of 25 years; the FY2024 10-K as first filed says the same. The land under Denton is the City of Denton's: Core Scientific leases it (originally ~31 acres and access to 297 MW of power; the Nov 2024 amendments added land and power 'to Enable High-Performance Computing Expansion' — Nov 20 2024 release, which does not name CoreWeave). Whether 25 years or the contract's 2035 governs is contested (ground-lease-term)
    “In November 2024, the Company entered into a lease amendment with The City of Denton (the "Denton Lease Amendment") for additional land and access to power. The Denton Lease Amendment created an additional right-of-use asset and was recorded as a new operating lease. The term of the Denton Lease Amendment is 25 years. At lease inception, total future minimum lease payments related to the Denton Lease Amendment were $17.6 million.”
    Core Scientific FY2024 10-K/A, Leases note · sec.gov
  • monthly-ground-rent$53,949.81
    $53,949.81 a month (~$0.65M a year, our arithmetic), adjusted every two years by the Dallas–Fort Worth CPI — this record follows the Third Amendment (made as of Oct 22 2024), which states it in figures and words, and the offering memo repeats it; the council presentation's '$53,939.81/mo.' is a slip. Small beside the license fees on the same land; the term is the exposure (ground-lease-term)
    “The monthly Rent shall be in the sum of $53,949.81 (Fifty-three thousand, nine hundred forty nine dollars and 81cents) per month.”
    City of Denton, Third Amendment to Lease Agreement with Core Scientific (ordinance exhibit, made as of Oct 22 2024) · legistar2.granicus.com
  • buildings-revert
    at the end of the ground lease the buildings are the City's — whatever term governs (ground-lease-term). Core Scientific owns the improvements it licenses to CoreWeave only while it holds the land
    “All improvements constructed by Core Scientific Denton or Core Scientific become property of the City of Denton upon expiration or termination.”
    Core Scientific notes offering memo (Apr 21 2026; furnished) — The Denton Campus · sec.gov
  • ppa-term14
    14 years, the term of Denton's power purchase agreement with the City's utility, Denton Municipal Electric (dated Sep 3 2021), with two seven-year extensions on a year's notice, each needing the ground lease extended too (memo; the PPA's date is from the Third Amendment, which recites the same term). Core Scientific, not CoreWeave, is the utility's customer (CoreWeave pays the power costs through). The campus total is contested (denton-power)
    “The DME Contract term is 14 years, with two additional seven-year extension options available upon one year’s written notice to DME, provided that the Denton Ground Lease must also be extended or renewed for the same amount of time.”
    Core Scientific notes offering memo (Apr 21 2026; furnished) — The Denton Campus · sec.gov
  • tenant-sidemore than 500 MW
    CoreWeave's own words, in its IPO prospectus: 'more than 500 MW' at Core Scientific at Dec 31 2024; after the Denton expansion its letter to the SEC staff (from its counsel, Mar 5 2025) put the total at 'about 590 MW'. After the takeover was voted down (cw-corz-failed), its CEO said on the Q3-2025 call (Nov 10 2025): 'Instead, we will continue to work closely with Core Scientific on the approximately 590 megawatts of capacity we have already leased.' Its Q3-2025 10-Q names Core Scientific only for the merger agreement and its termination; its FY2025 10-K and its Q1, Q2 and Q3 2026 10-Qs do not name Core Scientific in the text on file
    “We relentlessly and creatively explore additional opportunities to add power capacity, as demonstrated by our agreement with Core Scientific for more than 500 MW of capacity as of December 31, 2024.”
    CoreWeave IPO prospectus (424B4, Mar 2025) · sec.gov

Contested figures 16 not reconciled — every position side by side, with its source and tier

contract-value4 positions, side by side
$10.2B of 'Total Contracted Revenue' over 12-year terms — the headline of the Feb 26 2025 release as exhibited to the SEC, whose body says 'over $10 billion in potential cumulative revenue'. The 2024 releases built the same running total ($3.5B → more than $4.7B → $6.7B → $8.7B) and footnoted it as 'total cumulative revenue over all 12-year contract periods', before 'prepaid build out costs' in June and before 'capex credits provided to CoreWeave' from August: gross of the build credits. Two Seas Capital, a shareholder campaigning against CoreWeave's takeover, repeated the figure in its own proxy statement, filed in Core Scientific's EDGAR file ('bringing the total revenue over the twelve-year duration of the CoreWeave hosting contract to $10.2 billion before renewals', Sep 29 2025), citing the Feb 26 2025 release Core Scientific 8-K ex-99.1 (Feb 27 2025) and the Jun 3, Jun 25, Aug 6 and Oct 22 2024 releases — all furnished; Two Seas Capital DEFC14A (Sep 29 2025)
the same $10.2B as 'Total Projected Revenue' — the release on Core Scientific's own IR site (Business Wire copy, Feb 26 2025, 4:10 pm EST). Its filed proxy (Mar 2026) says 'increasing projected revenue over the 12-year term to more than $10 billion': a filed statement of their size, where the releases were furnished. Its filed proxy of a year earlier (Mar 2025) gave the 2024 licenses alone, before Denton's Feb 2025 expansion: 'HPC hosting contracts totaling over 500 MW, representing $8.7 billion in potential revenue over 12 years' (the letter to stockholders), the 2024 releases' last total Core Scientific IR release page (Feb 26 2025); DEF 14As (Mar 2025 and Mar 2026)
~$10B 'net of anticipated rent repayments under the terms of the licensing agreements' — the April 2026 offering memo, i.e. after the credits the 2024 totals were before. Two conventions that both land on about $10B, and no document bridges them Core Scientific notes offering memo (Apr 21 2026; furnished)
'$10B+ of future lease overhead to be paid for existing contractual sites' — the tenant's count, in the slides CoreWeave filed under Rule 425 for its bid to buy Core Scientific (Jul 7 2025): what the takeover would have spared it in fees on the sites already under contract ('Immediate elimination'). A filed statement of the licenses' size from the other side. The slide gives no term or basis; the same day's joint release and CoreWeave's investor call (its transcript also filed under Rule 425) both say 'over the next 12 years'. Core Scientific attached the same release to its own 8-K, so the landlord's file carries the figure too: 'Immediate elimination of over $10 billion of cumulative future lease overhead to be paid for existing contractual sites over the next 12 years'. The takeover was voted down (cw-corz-failed) CoreWeave Rule 425 slides and call transcript; the joint release as CoreWeave's 8-K ex-99.1 and as Core Scientific's (all Jul 7 2025)
feb-2025-value2 positions, side by side
$1.2B of contracted revenue for the +70 MW at Denton — Core Scientific's release; CoreWeave's letter to the SEC staff, from its counsel, says 'a $1.2 billion expansion with Core Scientific' (Mar 5 2025) Core Scientific 8-K ex-99.1 (Feb 27 2025; furnished); CoreWeave letter to SEC staff (CORRESP, Mar 5 2025)
~$1.7B of additional rent over 13 years, plus a $304M refund of escrowed funds — CoreWeave's prospectus on February 2025 changes to 'multiple lease agreements with a single landlord' that add 70 MW and change 'the contracted power capacity, term, and contractual payments'. The landlord is unnamed; Core Scientific fits by the month, the 70 MW and its CFO's answer to an analyst's question about 'the CoreWeave S1' escrow ('We were able to effectively eliminate the escrow arrangement', May 2025 call). A different measure across several leases, never reconciled with the $1.2B CoreWeave 424B4 (Mar 2025), subsequent events; Core Scientific Q1-2025 call
credit-pool2 positions, side by side
~$750M — 'Up to $1.5 Million per MW (or approximately $750 Million) of data center build out costs are funded by CoreWeave and credited against hosting payments at no more than 50% of monthly fees until fully repaid' (Q1-2025 deck; unchanged through the July 2026 deck): sized when the licenses were ~500 MW, and the Feb 2025 expansion carries no credit. The Jun 2024 release's $300M was the same credit on the first ~200 MW Core Scientific earnings decks (furnished)
$859M by our sum of the offering memo's per-site maximum credits — Dalton 1 $45M, Dalton 4 $218M, Marble $98M, Muskogee $105M, Denton $393M, none at Austin — each about $1.5M times the facility's allocation (the memo rounds two of them), Denton's counted on all 262 MW although for 69.6 MW of it Core Scientific itself bears $104.4M of the development costs. The memo gives no total of its own Core Scientific notes offering memo (Apr 21 2026; furnished)
ground-lease-term2 positions, side by side
25 years — the accounting term of the November 2024 amendment (FY2024 10-K and 10-K/A), to about 2049 (our arithmetic). The 10-K/A states the term and gives no reason for it. On our reading, its lessee policy, which counts 'periods covered by renewal options which the Company is reasonably certain of exercising', has the books assume the lease is extended — to the PPA's last option (2021 + 14 + 7 + 7 = 2049), further than the lease's own single extension allows. The City's Third Amendment adds to the lease a recital that the PPA's term 'was intended to be mirrored in the Lease Agreement' Core Scientific FY2024 10-K/A, Leases note and lease policy; City of Denton Third Amendment, recitals
through Dec 31 2035, the contract's Initial Term — 'to be extended contemporaneously with any extension(s) of the PPA ... for up to seven additional years', and ending automatically if the PPA ends (offering memo); the City's Third Amendment recites that Amendment No. 1 'extended the Initial Term to 14 years with one seven (7) year extension'. On this reading the land is held to 2042 at the latest: the 12-year Denton license that began billing in 2025 outlasts the Initial Term unless Core Scientific extends its power contract, and CoreWeave's two five-year renewals would outlast even the extension (our arithmetic) Core Scientific notes offering memo (Apr 21 2026; furnished); City of Denton Third Amendment (Oct 22 2024)
expansion-basisone entry, in its own words
critical IT — the Feb 2025 release (the 70 MW 'brings the full critical IT load to just over 260 MW'), the Q4-2024 deck ('~100 MW gross capacity / ~70 MW critical IT load expansion at Denton site') and the memo's 69.6 MW behind the $104.4M — vs gross power: the Q2-2025 10-Q and its 10-Q/A ('an additional approximately 70 MW of gross power at the Company’s Denton, Texas facility'). Only the first reading adds up to the ~590 MW of critical IT; no filing corrects the second Core Scientific release and Q4-2024 deck (furnished) vs Q2-2025 10-Q/A (filed)
gross-powerone entry, in its own words
~800 MW gross behind the ~590 MW in Core Scientific's decks ('~590 MW infrastructure (~800 MW gross)') vs 840 MW in CoreWeave's merger slides ('840 gross MW are under contract with CoreWeave', citing public filings at Mar 31 2025) vs ~850 MW from CoreWeave's CEO on CNBC ('about 850MW worth of infrastructure already contracted with them'). The memo's ~900 MW of grid capacity across the five sites is a wider boundary. Never reconciled Core Scientific Q1-2025 deck vs CoreWeave Rule 425 slides and CEO interview (Jul 2025)
option-112-valueone entry, in its own words
~$2.0B of 'projected additional cumulative revenue' (Aug 6 2024 release) vs '$1.9 billion over 12 years beginning in 2026' of 'total potential revenue' (Dec 2024 company presentation) for the same 112 MW, four months apart; the gap is never explained Core Scientific 8-K ex-99.1 (Aug 6 2024; furnished) vs Dec 2024 company presentation
contract-dateone entry, in its own words
Jun 3 2024 — the 10-K/A's MD&A, the option releases ('entered into with CoreWeave on June 3, 2024') and the indenture's dates for the Marble and Dalton 1 licenses ('dated as of June 3, 2024', 'dated June 3, 2024'), and Core Scientific's claim against CoreWeave in a patent suit (Mar 2026: Denton's license 'combines agreements dated August 2, 2024, and June 3, 2024') — vs 'In May 2024, we expanded our relationship with CoreWeave' in the overview that opens the same 10-K/A's MD&A. No document reconciles them Core Scientific FY2024 10-K/A; option releases (furnished); indenture (May 2026); third-party complaint, Malikie v. Core Scientific, E.D. Tex. (Mar 27 2026)
austin-extensionsone entry, in its own words
'Austin, Texas contract term is 7 years with elective extensions' (deck footnotes, e.g. Q1-2025) vs 'which does not include extension options' (offering memo, Apr 2026). The Austin license itself is not on file Core Scientific decks vs notes offering memo (all furnished)
denton-powerone entry, in its own words
394 MW — 'access to power to 394 MW' after the Nov 2024 amendments (release), the FY2025 10-K's power table and the memo's 'total potential campus load of approximately 394 MW' — vs 391 MW in Core Scientific's own FY2024 10-K table — vs 297 MW existing plus 74 MW 'to be energized' in its Sep 10 2026 8-K on ERCOT status (371 MW, our sum: an interconnection account, not the contract). The grid power behind CoreWeave's 262 MW at Denton Core Scientific release (Nov 20 2024), FY2024 and FY2025 10-Ks, offering memo, 8-K (Sep 10 2026; furnished)

Scope note what this record leaves to other records

NOT this record (carried elsewhere or not carried): CoreWeave's 2025 bid for Core Scientific (0.1235 CRWV a share, voted down Oct 30 2025) → cw-corz-failed — the disputed deal value ($9B / $5.0B / $7.6B / $6.6B), premium (27–71%) and the bankers' and Two Seas' valuations are not carried here; AMD's July 2026 leases (377 MW + a Neocloud's 152 MW, the 1,925 MW reservation, the warrant, the credit-support scope) → amd-corz, and the company totals that add them to CoreWeave's ('$24B+', 'over 3 GW' in the Q2-2026 deck) are not this record's; CoreWeave's DDTL 3.0 → cw-ddtl3-2025 (cited here only for the license it pays rent under); Core Scientific's March 2026 restatement of FY2024–Q3 2025 (demolition and conversion costs at the HPC sites wrongly capitalized — the 14 restated figures for capex, PP&E, net income, operating loss, SG&A and cash flows) → not carried here: company accounts, not license terms (several do not belong on cw-corz-failed either); the $3.3B notes' own terms (net proceeds $3.24B vs $2.9B, the reserve account, the 8.25% that is the memo's 'assumed coupon' where the notes priced at 7.75%), the repaid $1.0B term loan and the Hunt County and Polaris purchases → not carried here; CoreWeave's company-wide figures (backlog, active power, capex, and the 393 MW single-site lease with an unnamed lessor, which is not Core Scientific's) → not carried here. Disputed and not carried here: Denton's leased acreage (~64 / 70.13 / ~78 / 78.85 acres) and its 'real property investment' ($4B in the City's papers vs $6.1B in Core Scientific's release) — site facts, not license terms; build cost per MW ($5–13M across dates and scopes); management's spoken figures on the calls (243 vs ~245 MW billing on May 6 2026; 'more than 185 megawatts' delivered, and 'close to 200' and 'nearly 100' megawatts billing, on the same Mar 2 2026 call) — the filed quarter-end series in billing is carried instead; and when the relationship began (2018 by CoreWeave's CEO, 2019 by both companies' merger prospectus). Not circular: CoreWeave funds Core Scientific's own equipment as prepaid fees that become Core Scientific's revenue and come back to CoreWeave as credits — the customer-finances-supplier shape of micron-globalwafers, where the money becomes the landlord's revenue, not the tenant's. Not adopted: the Jun 2024 option (70 MW, $1.225B; the Dec 2024 deck's '$1.2 billion … beginning in 2025') and the Feb 2025 Denton expansion (70 MW, announced at $1.2B: feb-2025-value) are two contracts, both inside the 590 MW; the release's 'six sites' and the 10-Q's 'five sites' are one portfolio (six facilities, two at Dalton); the May 2026 indenture's date for Denton's license, 'dated February 26, 2024' — three days before Austin's, the first — against Feb 26 2025 in both companies' court filings (denton-license), a slip of the year. Not carried here: the patent suit itself (Malikie Innovations v. Core Scientific, E.D. Tex.) — Core Scientific's claim that CoreWeave must indemnify it under their agreements, and the plaintiffs' claims against Core Scientific, dismissed by stipulation on Oct 7 2026.