Siemens Energy turbine slots

Buyers had ordered or paid to reserve 104 of Siemens Energy gas turbines by September 2026 — 65 GW in firm orders and 39 GW in reservations Siemens expects to turn into orders by September 2027; GE Vernova's firm orders were about the same, with more of its larger total still in reservations; at the last count about a quarter of Siemens' total was for data centers.

A record about Siemens Energy alone — no other party in it has a page here.

Why it matters

By each maker's own count, Siemens Energy and GE Vernova held about the same firm turbine backlog at Sep 30 2026 (65 and 64 ). GE Vernova's larger total holds more paid slot reservations (58 of 122 GW, against 39 of 104). In the quarter GE Vernova turned more reservations into orders than it signed, while Siemens added 14 GW and converted none. Each maker sets its own threshold for counting a reservation as an order.

Nov 11, 2026 reported in Siemens Energy's Q4 FY26 analyst presentationupdated Nov 21, 2026operational disclosed by the parties

What happened

Siemens Energy is a German maker of large gas turbines for new power plants. At the end of September 2026 it had 104 gigawatts spoken for. That included 65 gigawatts of firm orders and 39 gigawatts in slot reservation agreements. Under these agreements, customers pay to hold a factory slot before signing an order. GE Vernova sells the same kind of reservation. Both companies keep reservations out of their order backlogs and take some orders without any reservation. Siemens says it tries to limit how many reservations it holds and aims to turn them into orders within about six months. GE Vernova's chief executive gives six to eighteen months. From July to September, though, Siemens signed 14 gigawatts of new reservations and converted none. It expects to turn its 39 gigawatts into orders by September 2027. GE Vernova went the other way that quarter, turning more reservations into orders than it signed, as it had forecast. By September the two had about the same firm orders, 65 and 64 gigawatts. GE Vernova's larger total, 122 gigawatts, held more reservations, 58 gigawatts. Each company decides when a reservation counts as an order. At the last count, in March, about a quarter of Siemens's committed gigawatts were for data centers. It says it tries to keep their share of its orders around that level. In single quarters their share has ranged from about a fifth to about two-fifths, the higher figure worked out from numbers on its analyst call. It aims to be able to deliver about 30 gigawatts a year by 2030. It says its factories are booked out through September 2028. Its executives give different figures for what a reservation costs.

Sources 36 documents — 13 transcripts · 12 company releases · 5 other documents · 3 SEC filings · 3 press reports

Research trail Found 170 documents and read 161 of them while checking this deal and related ones.

  1. transcriptassets.siemens-energy.com
    States 4 figures: 95 GW commitments jun 2026 · SRA definition · 30 GW capacity ladder · 110–120 GW market view
  2. company releaseassets.siemens-energy.com
    States 2 figures: 69 GW backlog vs SRA split · 15 GW apr jun 2026 bookings
  3. company releaseassets.siemens-energy.com
    States 2 figures: €17.9B orders apr jun 2026 · €3,756M gas services revenue
  4. company releaseassets.siemens-energy.com
    States 104 GW commitments sep 2026
  5. company releaseassets.siemens-energy.com
    States 80 GW commitments dec 2025
  6. GE Vernova · SEC filingsec.gov
    States 58 GW ge vernova reservations
  7. company releaseassets.siemens-energy.com
    States 24 GW data center commitments
  8. company releaseassets.siemens-energy.com
    States 5 GW williams data centers
  9. transcriptassets.siemens-energy.com
    States sold out
  10. company releaseassets.siemens-energy.com
    States €563M reservation fee liability
  11. Stock Analysis · transcriptstockanalysis.com
    States 70% firm share
  12. Stock Analysis · transcriptstockanalysis.com
    States €162B backlog excludes SRAs
  13. Stock Analysis · transcriptstockanalysis.com
    States 15–16 GW expected fiscal 2026 deliveries
  14. company releaseassets.siemens-energy.com
    Cited by the record; no single figure is quoted from it.
  15. company releaseassets.siemens-energy.com
    Cited by the record; no single figure is quoted from it.
  16. company releaseassets.siemens-energy.com
    Cited by the record; no single figure is quoted from it.
  17. company releaseassets.siemens-energy.com
    Cited by the record; no single figure is quoted from it.
  18. company releaseassets.siemens-energy.com
    Cited by the record; no single figure is quoted from it.
  19. transcriptstockanalysis.com
    Cited by the record; no single figure is quoted from it.
  20. transcriptstockanalysis.com
    Cited by the record; no single figure is quoted from it.
  21. transcriptstockanalysis.com
    Cited by the record; no single figure is quoted from it.
  22. transcriptstockanalysis.com
    Cited by the record; no single figure is quoted from it.
  23. transcriptstockanalysis.com
    Cited by the record; no single figure is quoted from it.
  24. transcriptstockanalysis.com
    Cited by the record; no single figure is quoted from it.
  25. transcriptstockanalysis.com
    Cited by the record; no single figure is quoted from it.
  26. transcriptstockanalysis.com
    Cited by the record; no single figure is quoted from it.
  27. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  28. other documentsupplychainbrain.com
    Cited by the record; no single figure is quoted from it.
  29. press reportenergyconnects.com
    Cited by the record; no single figure is quoted from it.
  30. press reportutilitydive.com
    Cited by the record; no single figure is quoted from it.
  31. other documentFeb 27, 2026pv-magazine-usa.com
    Cited by the record; no single figure is quoted from it.
  32. other documentwoodmac.com
    Cited by the record; no single figure is quoted from it.
  33. press reportpowermag.com
    Cited by the record; no single figure is quoted from it.
  34. other documentopen-factory.com
    Cited by the record; no single figure is quoted from it.
  35. other documentoilprice.com
    Cited by the record; no single figure is quoted from it.
  36. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: Siemens Energy analyst presentations Q2 FY25–Q4 FY26 (and Q4 FY24's market view; Q4 FY26 deck Nov 11 2026) + CMD 2025 Gas Services deck + Q3 and Q4 FY26 earnings releases + FY25 Annual Report + Q4 FY25 shareholder letter + Q3/Q4 FY26 pre-close transcripts and the Q2 FY26 pre-close script (Siemens-hosted) + earnings, media, CMD and Dec 2025 pre-close call transcripts (StockAnalysis); GE Vernova 2Q'26 and 3Q'26 8-K ex-99.1 + its 1Q25, 3Q25 and 2Q26 call transcripts and BofA conference transcript (3/18/2026); DPC Holdings 424B4; Bloomberg via SupplyChainBrain and Energy Connects; Utility Dive; POWER; open-factory; OilPrice; pv magazine; Wood Mackenzie; SemiAnalysis · as of Sep 2026

The evidence 18 sourced figures · 7 disputes

The record's headline Siemens Energy turbine slots: backlog + reservations 87 → 95 → 104 at Sep 2026 (65 GW firm, 39 GW reserved); reservations rose 26 → 39 GW in a quarter with none converted while GE Vernova's fell, leaving the two makers' firm backlogs level at 65 and 64 GW

Size
104 GW committed at 30 Sep 2026 (65 GW firm backlog + 39 GW slot reservations); 95 GW at 30 Jun 2026 (69 + 26)
When
Aug 2026 (Q3 FY26: 87 → 95 GW) → Sep 2026 (pre-close: 'trending towards' ~100 GW by fiscal year-end) → Nov 2026 (Q4 FY26: 95 → 104 GW)
Status
operational — series through Q4 FY26 (Sep 30 2026), reported Nov 11 2026; the 39 GW of reservations expected to convert to orders in FY27 (to Sep 2027); booked out through fiscal 2028 (Sep 2028)
Structure
slot reservation agreements (a fee holds a factory slot; meant to turn into a firm order within a defined period, typically ~6 months) kept outside the firm backlog and the euro order backlog (€162bn at Jun 2026, €164bn at Sep 2026)
Programme
Time-to-power
Parties
Siemens Energy turbine-maker; sells the factory slot before the order, then aims to convert it within months
Record
disclosed / primary source · as of Sep 2026

Resolved figures 18 each with the verbatim line from its document

  • commitments-jun-202695 GW
    95 GW of 'total customer commitments' at 30 Jun 2026 — 69 GW of firm backlog + 26 GW of slot reservation agreements (backlog-vs-sra-split); ~40 GW of firm orders booked in the fiscal year's first nine months (13 + 12 + 15 GW); 'trending towards' ~100 GW at the 30 Sep 2026 fiscal year-end — 'our communicated approximately 100 gigawatts', which the CEO had given on the Aug 5 call ('somewhere around, what is it, 100 GW, right, towards the end of the year. This is what we're trending towards') — the top of the 90–100 GW the CEO gave in May (Q2 FY26 call). The year-end figure came with FY26 results on Nov 11 2026: 104 GW (commitments-sep-2026). This Sep 30 pre-close call, which Siemens publishes as a transcript, repeats the Q3 totals (15 and 95 GW) unchanged and was Siemens' last statement of them before those results
    “During the first three quarters, we booked around 40 gigawatts of firm gas turbine orders, including 15 gigawatts in Q3. Total customer commitments, including reservation agreements, stood at 95 gigawatts and are trending towards our communicated approximately 100 gigawatts by fiscal year-end.”
    Siemens Energy Q4 FY26 pre-close call transcript (Siemens-hosted, Sep 30 2026) · assets.siemens-energy.com
  • commitments-sep-2026104 GW
    104 GW of 'total commitments' at 30 Sep 2026, the fiscal year-end — 65 GW of firm backlog + 39 GW of slot reservation agreements — above the 'approximately 100 gigawatts' Siemens had guided (commitments-jun-2026). The quarter, Jul–Sep 2026 (fiscal Q4), in the deck's footnote: 'In Q4 we booked ~2 GW of new orders (0 GW converted from SRAs), shipped 6 GW and added 14 GW of SRAs', 52 gas turbines booked, all small and medium. Backlog fell 69 → 65 GW (69 + 2 − 6 = 65) and reservations rose 26 → 39 GW, where 26 + 14 = 40 and 95 + 2 + 14 − 6 = 105: a 1 GW gap the deck's whole numbers leave (the monitor's arithmetic). For the year: 'FY26 new unit orders 42 GW', and the 39 GW of reservations are 'expected to be converted into firm orders in FY27', the year to Sep 2027. The release says the group's order intake 'moderated from the exceptionally strong levels of the first three quarters, reflecting normal project phasing' (group-wide wording, not turbines alone); the group's order backlog was €164bn, Gas Services' €74bn
    “Total commitments at the end of the FY26 stood at 104 GW (65 GW backlog / 39 GW SRAs).”
    Siemens Energy Q4 FY26 analyst presentation (Nov 11 2026), Gas Services footnote · assets.siemens-energy.com
  • backlog-vs-sra-split69 GW
    the split at 30 Jun 2026, which the deck files under 'firm customer commitments': 69 GW of firm backlog and 26 GW of reservations. Over five quarters firm backlog more than doubled — 29 GW (31 Mar 2025, Q2 FY25 deck) → 37 (30 Jun 2025, Q3 FY25 deck) → 'around 60 GW as of Q2 Fiscal Year 2026' (Jun 2026 pre-close) → 69 — while reservations, as each quarter's results gave them, stayed at 21–29 GW: 21 → 21 → 28 (30 Sep 2025, Q4 FY25 deck) → 29 ('outstanding' when the CEO spoke on the Q1 FY26 call, Feb 2026) → 27 (31 Mar 2026, CEO, Q2 FY26 call) → 26. The next quarter broke the pattern: reservations rose to 39 GW and firm backlog eased to 65 GW at 30 Sep 2026 (commitments-sep-2026). Between two of those reports they stood higher: '36 GW, which are currently customer reservations' (IR, Dec 2025 pre-close), counting the 8 GW added in the fiscal year's first six weeks. Reservations are not inside the firm backlog, so backlog + reservations is the total, not a double count (the GW 'new units backlog' Siemens gave at its Nov 2025 CMD did count them in: fy25-year-end). Collision hazard: Siemens' 31 Mar 2025 pair (29 GW backlog + 21 GW reservations) is the same pair GE Vernova reported for the same date (pw-gev-sra) — two companies, not one figure
    “High level of firm customer commitments (69 GW backlog / 26 GW SRAs)”
    Siemens Energy Q3 FY26 analyst presentation (Aug 5 2026), p.6 · assets.siemens-energy.com
  • apr-jun-2026-bookings15 GW
    how 87 became 95 in Apr–Jun 2026 (Siemens' fiscal Q3): 15 GW of firm orders booked, 12 GW of them converted from reservations; 6 GW shipped; reservations 27 → 26 GW, so about 11 GW of new reservations were signed (27 − 12 + 11 = 26, and 87 + 15 − 12 + 11 − 6 = 95 — the monitor's arithmetic; a UBS analyst on the Q3 FY26 call put the quarter's new slots at 11 GW). 73 gas turbines booked for power generation and oil and gas, 25 large and 48 industrial, and a 42% market share in gas turbines above 100 MW for the quarter (CFO, Q3 FY26 call). JPMorgan's ~12.5 GW for the same quarter is contested (bookings-tally)
    “15 GW booked (12 GW converted from SRAs2), 6 GW shipped”
    Siemens Energy Q3 FY26 analyst presentation (Aug 5 2026), p.6 · assets.siemens-energy.com
  • commitments-dec-202580 GW
    the series on Siemens' 'total commitments' basis (firm backlog + reservations), each step from that quarter's own report: 50 GW at 31 Mar 2025 (29 + 21 in the Q2 FY25 deck, which gives no total — the monitor's sum) → 58 GW at 30 Jun 2025 ('Considering the order backlog of 37 GW, we have now a total commitment of 58 GW', CEO, Q3 FY25 call) → FY25 year-end on two bases (contested fy25-year-end) → 80 GW at 31 Dec 2025: 13 GW booked from 102 turbines ('for power generation and oil gas', CFO), 12 GW of it converted from reservations, 12 GW of new reservations, 3 GW delivered (this deck; CEO, Q1 FY26 call) → 87 GW at 31 Mar 2026: 12 GW booked from 77 turbines (26 large, 45 medium, 6 small; 'for power generation, oil and gas', CFO), 9 GW converted, more than 3 GW delivered (CEO, Q2 FY26 call) → 95 GW at 30 Jun 2026. In units, orders nearly doubled in a year: 'A year earlier, we sold 100 gas turbines. In 2025, we sold 194 gas turbines.' (Karim Amin, head of Gas Services, CMD, Nov 2025)
    “13 GW booked, 80 GW total commitments, thereof 22 GW data center related”
    Siemens Energy Q1 FY26 analyst presentation (Feb 11 2026) · assets.siemens-energy.com
  • sra-definition6 months
    what a Siemens slot reservation agreement is, in its own words: 'structured commitments rather than speculative reservations', 'generally intended to convert into firm orders within a defined period, typically around six months' (Sep 2026; in June: 'within on average 6-12 months'; earlier it gave horizons for its whole reservation book — the 36 GW of Dec 2025 'should turn into orders within the next 12 months', IR, Dec 2025 pre-close, and in Feb 2025 the CEO expected the ~20 GW then secured to 'convert into orders in Fiscal Year 2025 and Fiscal Year 2026', Q1 FY25 call), with 'Reservation fees and advance payments' as 'economic protection'; it has 'not seen any delays or cancellations of previously signed slot reservation agreements or orders' (Sep 2026). At the year-end it gave its whole reservation book a horizon again: the 39 GW are 'expected to be converted into firm orders in FY27', the year to Sep 2027, after a quarter in which none converted (Q4 FY26 deck; commitments-sep-2026). In May, asked whether data-center customers had begun to cancel projects, the CEO had answered 'I wouldn't call it cancellations particular. No, not like this', describing bigger customers 'trying to shift between sites' where they can get permits quicker (Q2 FY26 call). A reservation stays out of the firm backlog in GW (69 + 26 in June, 65 + 39 in September) and the order backlog in euros (backlog-excludes-sras) — though the GW 'new units backlog' of the Nov 2025 CMD counted reservations in (fy25-year-end); when it turns into an order its fee 'is certainly then calculated into the down payment' (IR, Dec 2025 pre-close), and current reservations carry better margins too ('Orders booked today carry better margins than both, the backlog executed in the past and orders signed in the first half of this fiscal year. Margins embedded in current slot reservation agreements also continue to be higher', Sep 2026). Bloomberg reported a conversion rate 'above 90%' (SupplyChainBrain, Jun 2026); no Siemens deck, release or call transcript on file states one. GE Vernova's reservation is the same instrument — a deposit holds a factory slot, 'not yet in backlog' until site and EPC are set (pw-gev-sra) — so the instrument compares; what differs is how much of each maker's total is still unconverted and where each draws the line between a reservation and an order (ge-vernova-reservations) and, unsettled, what a reservation costs (sra-fee-level). Both makers give a conversion time: against Siemens' six months (6–12 in June, and twelve for the whole book in Dec 2025), GE Vernova's CEO said 'I would say 6 to 18 months today', 'maybe extending a little bit' because customers now reserving slots into 2031 are 'still working through their EPC fuel and other dynamics like that' (BofA conference, Mar 18 2026, the GE Vernova transcript pw-gev-sra quotes for its condition: site chosen, EPC under way)
    “Slot reservation agreements remain an important part of our commercial process. They are structured commitments rather than speculative reservations and are generally intended to convert into firm orders within a defined period, typically around six months.”
    Siemens Energy Q4 FY26 pre-close call transcript (Siemens-hosted, Sep 30 2026) · assets.siemens-energy.com
  • firm-share70%
    the 'current split' in May 2026: 'roughly 70% firm orders and 30% reservations' (CEO, Q2 FY26 call; at 30 Jun it was 69 of 95 GW, 73%, and at 30 Sep 65 of 104, 63% — the monitor's arithmetic). Asked by UBS on the same call whether the 70% would hold for the full year, the CEO gave no figure: 'I cannot tell you how much is now reservation agreements then and orders'. What Siemens states as policy is to convert fast and not to pile up reservations: 'Our focus remains on short-term conversion, allowing us to fully benefit from the favorable pricing environment' (same call); 'we try to keep the, let's say, reservation agreements in terms of gigawatt relatively, limited is the wrong word, but we obviously more look on orders than on the piling up the reservation agreements' (CEO, Q3 FY26 call); 'what we're trying to do is to not have too much in terms of reservations. That's our strategy.' (CEO, Q3 FY26 media call, interpreted). On the Q2 call BofA's analyst set it against Siemens' U.S. peers — 'over the past two quarters, you've signed 19 GW of new slots, whereas your U.S. peers signed 40 GW' (Siemens' own figures give about 19–20: 12 GW of new reservations in Oct–Dec, then 7 or 8 in Jan–Mar, depending on whether that quarter opened at the 29 GW 'outstanding' in February or the 28 that Oct–Dec's flows leave, and closed at 27 with 9 converted; GE Vernova's releases give 21 + 19 = 40 GW of new reservations for the same two quarters — the monitor's arithmetic) — and the CEO answered 'I wouldn't compare myself against somebody else', pointing to conversion speed and to orders that come with no reservation at all: 'Not each and every order comes with a reservation agreement.' GE Vernova takes such orders too: 3, 2 and 2 GW in the three quarters to Jun 2026, about what Siemens took (1, 3 and 3 GW, booked less converted), against 21, 19 and 18 GW of new reservations, about twice Siemens' 12, 7–8 and about 11, while converting 24 GW to Siemens' 33 (the releases and decks — the monitor's arithmetic). So what sets the two mixes apart is how many reservations each signs and how fast it converts them, not orders that skip a reservation (the monitor's reading)
    “Second, we continue to see strong conversion from reservation agreements into firm orders, with a current split of roughly 70% firm orders and 30% reservations.”
    Siemens Energy Q2 FY26 earnings call (StockAnalysis transcript, May 12 2026), CEO · stockanalysis.com
  • ge-vernova-reservations58 GW
    the same date at the other big Western maker, from GE Vernova's own releases (pw-gev-sra holds its series): 64 GW of backlog + 58 GW of slot reservations at 30 Sep 2026 (122 GW in its own total, 3Q26 release), against Siemens' 65 + 39 = 104 GW (commitments-sep-2026); in that quarter GE Vernova signed 8 GW of new reservations and 3 GW of orders and converted 13 GW, while Siemens signed 14 GW of reservations and converted none. At 30 Jun 2026 the pairs were 53 + 63 = 116 GW and 69 + 26 = 95 (GE Vernova's 2Q26 release; backlog-vs-sra-split). Same instrument, kept outside firm backlog by both, and the opposite mix in June, which narrowed in a quarter: reservations went from 54% to 48% of GE Vernova's total and from 27% to 38% of Siemens' (63 / 116, 58 / 122, 26 / 95 and 39 / 104 — the monitor's arithmetic). GE Vernova had forecast its side of the turn: 'In the second half of the year, we expect to convert many of these SRAs into orders', reaching 'an important inflection point with gigawatts and backlog greater than SRAs' (GE Vernova CEO, 2Q26 call, Jul 22 2026), and at 30 Sep its backlog was again the larger half (pw-gev-sra). So the two headline totals (104 vs 122 GW) still carry different shares of unconverted slots, and the firm backlogs, now about level (65 vs 64 GW), are the nearer like-for-like — nearer, not equal, because each maker draws its own line between a reservation and an order. GE Vernova keeps a reservation out of backlog until the customer has secured its EPC contract, its gas supply is clear and permitting is progressing, and its CEO says 'the orders classification to be candid is more our classification than the customers', since in many cases customers provide 'enough financial capital on day one that one could argue we could be booking these things as orders' (GE Vernova CEO, 3Q25 call, Oct 22 2025, on file for GE Vernova). Whether the two companies' gigawatts count the same equipment is only half documented: GE Vernova says its GW 'align with McCoy reporting', which may differ from customers' announcements that 'cite the total combined cycle output of the plant, including the power from steam turbines' (GE Vernova CEO, 1Q25 call, Apr 2025, a transcript pw-gev-sra cites); Siemens counts steam-turbine output in its capacity GW ('steam turbine output is included in this view', IR, Dec 2025 pre-close), and its Q4 FY26 deck splits the 65 GW firm backlog by application and by region 'in GW including steam turbine capacity of combined cycle configuration'; nothing on file says the same of the 39 GW of reservations
    “Signed 11 gigawatts (GW) of new gas equipment contracts, including 8 GW of slot reservation agreements and 3 GW of orders. Converted 13 GW of existing slot reservation agreements to orders and shipped 5 GW of equipment; resulting in backlog growth from 53 to 64 GW and a decrease in slot reservation agreements from 63 to 58 GW.”
    GEV 3Q'26 8-K ex-99.1, Power segment (Oct 28 2026) · sec.gov
  • backlog-excludes-sras€162B
    the euro backlog counts orders only: 'No, the reservations are not included in the order backlog. The EUR 162 billion that we have in the order backlog are orders' — the CEO, answering Bloomberg on the Q3 FY26 media call; he went on: 'We see more orders than reservations. Not every company does it that way, but that's our approach.' The transcript is StockAnalysis's text of the interpreted English feed, and elsewhere calls the quarter's €17.9bn of orders 'the amount of revenue' (orders-apr-jun-2026), so its figures are read against the release; this answer matches Siemens' own documents, which list backlog and reservations separately (Q3 deck), carry the fees as a liability (reservation-fee-liability) and count as orders 'accepted purchase orders for which enforceable rights and obligations exist', 'excluding letters of intent' (Annual Report 2025, Note 26). The €162bn is the group's, all four segments, Gas Services' share €73bn; up from €154bn at 31 Mar 2026 and €136bn a year earlier
    “No, the reservations are not included in the order backlog. The EUR 162 billion that we have in the order backlog are orders, and what we're trying to do is to not have too much in terms of reservations.”
    Siemens Energy Q3 FY26 media call (StockAnalysis transcript of the interpreted feed, Aug 5 2026), CEO · stockanalysis.com
  • orders-apr-jun-2026€17.9B
    €17.9bn (€17,926m) of group orders in Apr–Jun 2026, 'another record level'; growth 'was driven by a new record order intake at Gas Services' (€9,967m — gas-services-revenue), 'as well as strong increases at Grid Technologies and Transformation of Industry'; book-to-bill 1.57; order backlog €162bn. Revenue was €11.4bn (€11,447m, +18.5% comparable), not €17.9bn, which the media-call transcript calls 'the amount of revenue' — this record follows the release. The U.S. booked €8,048m of the €17,926m. Group figures: Grid Technologies, Transformation of Industry and Siemens Gamesa are in both totals
    “Orders reached another record level of €17.9bn. Growth was driven by a new record order intake at Gas Services, as well as strong increases at Grid Technologies and Transformation of Industry. Book-to-bill ratio (ratio of orders to revenue) was 1.57, while order backlog increased to €162bn at quarter-end.”
    Siemens Energy Q3 FY26 earnings release (Aug 5 2026) · assets.siemens-energy.com
  • gas-services-revenue€3,756M
    Gas Services alone in Apr–Jun 2026: orders €9,967m (+61.9% comparable) against revenue €3,756m (+20.8%), a book-to-bill of 2.65 — 'record orders for the quarter', led by U.S. demand 'including large orders related to data centers' and by new power plants in the Middle East and Asia; the segment's order backlog €73bn (€53bn a year earlier, Q3 deck). Utility Dive's 'sales up 62% ... to €10 billion' is the ORDERS line: this record follows the table
    “Orders 9,967 6,180 61.9%¹ Revenue 3,756 3,118 20.8%”
    Siemens Energy Q3 FY26 earnings release (Aug 5 2026), Gas Services table · assets.siemens-energy.com
  • data-center-commitments24 GW
    about a quarter of the GW committed is for data centers: 12 of 54 GW at FY25 year-end (CEO, Q4 FY25 call; the 54 GW basis, fy25-year-end), 22 of 80 GW at 31 Dec 2025 (Q1 FY26 deck) — 15 GW of those 22 reservations (CEO, Q1 FY26 call) — and 24 of 87 GW at 31 Mar 2026, 'that is, orders and reservations' (this deck; CEO, Q2 FY26 call). A single quarter's orders can run well above that: on the same Q2 call, 'The 5 GW of order intake in quarter two brings our total data center-related commitments to 24 GW', of '12 GW of new turbine orders' that quarter — about two-fifths (the monitor's arithmetic) — and, answering Morgan Stanley, the CEO said of data centers 'with the 25%-30%, that is something which we enjoy, but at the same time we balance out' (base unstated); on the media call that day, asked for data centers' share of order intake: 'approximately a share of 25% with regards to the order intake in general. Within the 20%-25% level, we try to keep the situation as it is on a long-term basis' (interpreted). The Q3 FY26 deck gives no split; on the Aug 5 media call the CEO gave one for that quarter's orders: 'If I remember correctly, it was 20% of our orders when it comes to capacities. A little less than in the previous quarter because we're trying to strike a balance here consciously.' (interpreted; the quarter before ran about two-fifths on the analyst call's figures). Siemens, of its markets as a whole: 'Data centers are an important additional driver, but they are not the foundation of our outlook' (Sep 2026 pre-close). Data centers lean to reservations — half of the 29 GW of reservations outstanding at the Q1 FY26 call (CEO, Feb 2026) — as they do at GE Vernova (pw-gev-sra). Other bases, such as the U.S. alone, are contested (data-center-share-bases)
    “12 GW booked, 87 GW total commitments, thereof 24 GW data center related”
    Siemens Energy Q2 FY26 analyst presentation (May 12 2026) · assets.siemens-energy.com
  • williams-data-centers5 GW
    a data-center customer on Siemens' own slide: 'Williams Data Centers, US Powering AI – 5 GW across multiple frames', an example on the Gas Services deck's 'Doubled orders to ~200 GTs in one year' slide, beside its '~78 GW New unit backlog' (CMD, Nov 2025). Siemens' Gas Services head calls it 'the Williams agreement that we did' and names the frames — 'F-classes', 'SGT-800s' and 'aero derivatives that are all being delivered in a fast manner' (Karim Amin, CMD) — but no terms, price or delivery dates are disclosed, and no document on file ties the 5 GW to particular data centers; Williams is not a monitor entity, so no ribbon. SemiAnalysis lists three Siemens SGT-400s, rated 14.3 MW each, among other makers' machines at Williams' Socrates South plant for Meta in Ohio — about 43 MW of the plant's 306 MW nameplate (the monitor's arithmetic), not carried here (see the note)
    “Williams Data Centers, US Powering AI – 5 GW across multiple frames”
    Siemens Energy CMD 2025 Gas Services presentation (Nov 20 2025), p.4 · assets.siemens-energy.com
  • expected-fiscal-2026-deliveries15–16 GW
    what ships: 3 GW in Oct–Dec 2025 (CEO, Q1 FY26 call), more than 3 GW in Jan–Mar 2026 (CEO, Q2 FY26 call), 6 GW in Apr–Jun 2026 (Q3 deck), and 'around 15 GW, maybe 16 GW' expected for the year to 30 Sep 2026 (CEO, Q3 FY26 call; Utility Dive: 'could deliver 15-16 GW of gas turbines this year'). The year-end deck gives 6 GW shipped in Jul–Sep 2026 (commitments-sep-2026), so the four quarters' figures add to more than 18 GW (the monitor's sum), above that estimate. Against the 104 GW of commitments at 30 Sep 2026 that is under six years at this year's rate, or about three and a half at the 2030 capacity target (104 ÷ more than 18 and 104 ÷ 30 — the monitor's arithmetic; at 30 Jun it was 95 ÷ 15–16, about six. The second assumes the commitments count steam-turbine output as the capacity GW do, which the Q4 FY26 deck shows for the firm backlog's split and nothing on file shows for the reservations: ge-vernova-reservations): the arithmetic behind 'booked out' (sold-out)
    “On the capacity delivery this year, I would scratch my head, but it's around 15 GW, maybe 16 GW, something like this, gigawatt type of range, I would believe you're going to see.”
    Siemens Energy Q3 FY26 earnings call (StockAnalysis transcript, Aug 5 2026), CEO · stockanalysis.com
  • capacity-ladder30 GW
    the supply response, in units then GW: medium gas turbines (20–100 MW) from ~50 a year in FY25 to ~80 in FY26, the added units online in the second half, and ~100 by FY28; large ones (100–600 MW) from ~35 to ~50 a year, 'fully on track' and contributing 'from fiscal year 2027 onwards' (Sep 2026 pre-close for the unit steps, 'fully on track' and FY27; the Q3 deck, p.5, for the MW bands, the second-half timing, ~100 and '50+' for FY28); ~30 GW of annual delivery capacity by 2030 (this quote; at the Nov 2025 CMD, 210 to 230 units, 'something in the range of 30 gigawatts, give or take', for FY28–30, '>30 GW' on the slide). Near-term capacity in GW comes in several measures (contested gt-capacity-gw). pw-gev-sra's capacity ladder also ends at 30 GW in 2030 — two makers' targets, not one figure, and not on one basis: Siemens footnotes its capacity GW 'Including steam turbine capacity of combined cycle configuration' (CMD Gas Services deck), while GE Vernova gives its capacity steps in simple-cycle terms ('up to 24 gigawatts of simple cycle output' by 2028) and its CEO says 'When we normally talk about gas, gigawatts and kind of Wall Street terms, we try to match it with McCoy, which is without the steam turbine' — though his project examples in the same answer were combined-cycle gigawatts ('So it includes the steam turbine') (BofA conference, Mar 18 2026, a transcript pw-gev-sra cites)
    “We continue to target approximately 30 gigawatts of annual delivery capacity by 2030.”
    Siemens Energy Q4 FY26 pre-close call transcript (Siemens-hosted, Sep 30 2026) · assets.siemens-energy.com
  • sold-out
    the factory is booked out through fiscal 2028, which ends in September 2028: 'sold out with respect to capacity, even taking into account the announced expansions until 2028, and we are now booking slots for 2029 and beyond' (IR, Dec 2025 pre-close); 'sold-out until fiscal year 2028, with fiscal year 2029 slots filling up very quickly', and fiscal 2029 expected 'to be largely sold-out with limited capacity available in fiscal year 2030' by the end of the year (IR, Mar 2026 pre-close script, Siemens-hosted); and in June 'booked out onto '28' with 2029 and 2030 'filling up very quickly', so that 2029 'might be already short-term slot', 'especially if you talk about large gas turbines' (IR, this call). Not quite to the last slot: in February the CEO still had 'some slots, also 2027, 2028' to balance in mid-size turbines (Q1 FY26 call). An early slot costs more: 'faster delivery continues to command a premium' (June); 'Attractive delivery windows continue to command a premium, especially in the United States' (Sep 2026 pre-close)
    “I mean on the one hand, as we are booked out onto '28 and let's say, '29 and 2030 is filling up very quickly.”
    Siemens Energy Q3 FY26 pre-close call transcript (Siemens-hosted, Jun 29 2026), Q&A · assets.siemens-energy.com
  • reservation-fee-liability€563M
    the only balance for the fees in Siemens' accounts on file: reservation fees received sit in other current liabilities — €563m at 30 Sep 2025 against €244m a year earlier (audited FY25 Annual Report), with no split by segment, and not turbine slots alone: Grid Technologies takes reservations too ('We do see this actually in GT as well as in GS', CEO, Q1 FY25 call, Feb 2025, of data-center customers' reservation agreements; 'There's also an element of reservation fees for GT', CFO, Q1 FY26 call). Asked on that call to put a number on the fees behind the quarter's record free cash flow, the CFO declined: 'we do not disclose the amount of reservation fees'. What one reservation costs is contested (sra-fee-level). The cash comes first: Q3 FY26 free cash flow pre-tax 'again benefited from customer advance payments, including reservation fees, in connection with higher orders' (Q3 release), the fees themselves in the cash-flow statement's 'other' line ('The Q3 other line included reservation fees', Sep 2026 pre-close; the CFO on the Q3 FY26 call: 'in the other line, you do have reservation fees included'); group contract liabilities were €28,071m at 30 Jun 2026 against €22,321m at 30 Sep 2025, and their rise put €5,359m into nine months of operating cash flow (Q3 release; group-wide, not Gas Services alone) — the release gives the balances, and the Annual Report puts FY25's rise 'mainly due to higher advance payments in connection with the increase in new orders'. The two makers book the cash differently: Siemens carries the fees on their own line among its liabilities and folds a fee into the down payment when the order comes ('the reservation fee, whenever it turns into an order, is certainly then calculated into the down payment fee', IR, Dec 2025 pre-close); GE Vernova reports its reservation deposits with its order down payments, in contract liabilities and deferred income (pw-gev-sra)
    “Other current liabilities consist of the following items: Sep 30, (in millions of €) 2025 2024 Liabilities to personnel 2,025 1,977 Accruals for pending invoices 1,026 853 Reservation fees 563 244”
    Siemens Energy Annual Report 2025, notes (other current liabilities) · assets.siemens-energy.com
  • market-view110–120 GW
    Siemens' own planning assumption, not a count: an annual gas-turbine market of ~110–120 GW 'over the coming years', plus 10–20 GW of 'potential upside from data centers' ('roughly 130 to 140' with the upside, IR, same call). Of it, 'up to 80 GW' comes from electricity demand growth, fleet replacement, coal-to-gas and the need for dispatchable capacity, and 'The remainder of the above-mentioned demand forecast is driven by the build-out of data center infrastructure' (Sep 2026). The total has risen: 'a 90 GW-100 GW gas market, including combined cycle' with a Siemens share target of 'around 25%-30%' (Dec 2025 pre-close), then ~110–120 GW since June 2026, when IR called new Middle East projects 'one factor', said 'one of the major drivers might be also, especially the data center related topic', and concluded that 'the main driver for the step-up will be rather related to AI data center topics' (Jun 2026 pre-close). Without data centers, Sep 2026 gives only a ceiling, 'up to 80 GW' from the non-data-center drivers, and no floor. Siemens' earlier figure, side by side: its Q4 FY24 deck (Nov 2024) gave a 'gas market of ~70 GW per year', with 'peaking and data centers applications (>10 GW p.a.)' as the upside, on S&P Global's figures, which IR recalled on that June call as 'a base market of somewhere around 70 to 80 gigawatts'. So the non-data-center market is at most about 10 GW above the deck's ~70 GW (the monitor's arithmetic); whether it rose at all, the documents do not say. Independent tallies of global orders are not carried here (note)
    “For gas turbines, our planning assumption remains an annual market of around 110 to 120 gigawatts over the coming years, with a further 10 to 20 gigawatts of potential upside from data centers.”
    Siemens Energy Q4 FY26 pre-close call transcript (Siemens-hosted, Sep 30 2026) · assets.siemens-energy.com

Contested figures 7 not reconciled — every position side by side, with its source and tier

fy25-year-endone entry, in its own words
what Siemens had committed at FY25 year-end (30 Sep 2025), on two bases in one week — no pick: 54 GW, 'the total commitments increased to 54 gigawatts in fiscal year 2025, thereof 26 gigawatts orders and 28 gigawatts reservations' (CEO, Q4 FY25 call; IEEFA's Sam Reynolds relays it in pv magazine as orders Siemens holds: 'Siemens has … of firm turbine orders') — the year's order FLOW plus the reservation stock; vs 70 GW on the 'new unit backlog' basis that the FY26 series continues ('the 78 gigawatts six weeks ago was 70' — Karim Amin, CMD, Nov 20 2025), which reached ~78 GW with 8 GW 'secured within the first weeks of FY26' (Q4 FY25 shareholder letter) and is footnoted 'Based on orders booked in FY24, FY25 and secured orders expected to be booked in the next 12 months' (CMD Gas Services deck). The figures add up — 26 + 28 = 54; the deck's 16 + 26 GW of FY24–25 bookings + 28 = 70; 70 + 13 booked − 12 converted + 12 new reservations − 3 delivered = 80 at 31 Dec 2025 (our arithmetic) — but no document reconciles the two: the 70/78 basis is footnoted by the years its orders were booked; Siemens calls it a 'backlog' — 'the backlog that would turn into revenue in the next two to three years' (Amin, CMD) — and 'customer commitments for new capacities' (shareholder letter) — 'commitments' being the CEO's word for the other basis too; and no document says whether turbines already shipped are netted out of it Siemens Q4 FY25 call (Nov 2025) vs CMD 2025 (Nov 20 2025: Amin, StockAnalysis transcript; Gas Services deck) + Q4 FY25 shareholder letter; pv magazine (2/27/2026)
bookings-tallyone entry, in its own words
Apr–Jun 2026 gas-turbine bookings: 15 GW, Siemens' own count (Q3 deck; 'including 15 gigawatts in Q3', Sep 2026 pre-close) vs ~12.5 GW in JPMorgan's tally as Bloomberg reported it ('Siemens Energy AG booked the most orders in the second quarter, with about 12.5 gigawatts, followed by GE Vernova Inc. at 11.3 gigawatts and Mitsubishi Power Ltd. at 5.3 gigawatts', Energy Connects, Aug 11 2026). The bank's method is not on file; its 11.3 GW for GE Vernova also differs from GE Vernova's own 2 GW of orders + 10 GW converted. Nothing on file reconciles the two counts. The record's figures are Siemens' own (apr-jun-2026-bookings); the tally is kept as an outside count, and it ranks Siemens first in the quarter Siemens Q3 FY26 deck vs JPMorgan via Bloomberg (Energy Connects, 8/11/2026)
sra-fee-levelone entry, in its own words
what a Siemens reservation costs — its own people disagree, and its CFO says 'we do not disclose the amount of reservation fees ... It's quite variable, depending upon the contract and the size and the customer' (Q1 FY26 call): (a) below the order down payment — a reservation-fee inflow of 'approximately EUR 190 million' in Oct–Dec 2024 (CFO, Q1 FY25 call), by IR's account the one time Siemens put an amount on the fees it receives for reservations ('we only once really provided further details on the amount we receive for reservation agreements'; the balance of fees held sits in its accounts: reservation-fee-liability), recalled as 'for roughly 20 GW, we receive EUR 200 million' (~€10m per GW: the monitor's arithmetic on IR's pairing, which sets one quarter's inflow against all the reservations then secured; IR added 'That might, let's say, vary a bit'), with 'the down payments when the order comes in ... significantly higher than the reservation fee' and the down payment 'normally 10%-15% of the project volume' (Dec 2025 pre-close); (b) typically 'between 10% and 15% of a turbine's purchase price' to reserve a slot 'for about six months', per Gas Services head Karim Amin as Bloomberg reported it (SupplyChainBrain, Jun 2026); (c) asked by Reuters whether Siemens could get more from customers than the usual share the reporter named, the CEO answered 'We're not squeezing anything out of our customers' and 'Let's say 10%-20%', set up so 'this looks like a down payment, but that down payment will lapse if you don't buy the turbine' (Q3 FY26 media call, interpreted). Industry-wide, IEEFA's Sam Reynolds, relaying what 'Companies are reporting': 'can get up to 20% of the total cost of the order' (pv magazine). Terms may have stiffened between 2025 and 2026, or fee and down payment are being run together; no document settles it. At GE Vernova the deposit and the order's down payment are about the same: its CEO says customers 'have often put down 20% to 25% of the gas turbine contract in deposit', and its CFO puts the down payments on orders and reservations alike at about a fifth (pw-gev-sra's sources) — where Siemens' IR has the down payment well above the fee. Range only, no pick Siemens Q1 FY25 and Q1 FY26 calls + Dec 2025 pre-close (StockAnalysis transcripts); Bloomberg via SupplyChainBrain (6/12/2026); Q3 FY26 media call (interpreted); pv magazine (2/27/2026); GE Vernova BofA conference (3/18/2026) and 1Q25 call (CFO), both cited on pw-gev-sra
data-center-share-basesone entry, in its own words
how much of Siemens' turbine demand is data centers depends on the base: globally about a quarter (data-center-commitments; 'about 25% of Siemens Energy's turbine demand, while roughly 60% comes from conventional applications', Bloomberg via SupplyChainBrain, Jun 2026 — the same split the CEO gave of 'our total global commitments' on the February call; FY25 'only between 20%-25% of the overall order intake for the gas service business', IR, Dec 2025 pre-close) vs much higher in the U.S. — in a passage on U.S. demand, Gas Services 'has secured gas turbine orders totaling 14 GW in the fiscal year to date. 60% of those are for data centers.', and later '40% of our gas turbines are related to the data center business. Globally, that figure stands at about 25%.' (Q3 FY25 media call, Aug 2025, interpreted; a few sentences earlier in the same answer the CEO gives a share of the same size for all 'new applications', power ships included, and on the English analyst call the same day that share was the quarter's orders from all new applications worldwide, data centers a third of the gigawatts). Orders vs commitments, GW vs units, U.S. vs world: the documents give these shares on different bases; no pick Siemens Q3 FY25 media call (interpreted) + Q3 FY25 and Q1 FY26 calls + Dec 2025 pre-close (StockAnalysis transcripts); Bloomberg via SupplyChainBrain (6/12/2026)
lead-timeone entry, in its own words
how long a Siemens turbine takes depends on the frame and on what is measured, no single number: large frames stay '3 years, maybe 3-4 years' in the backlog and smaller frames, 'perhaps', 12–24 months (CFO, Q1 FY26 call); asked on the May media call (by Energate) how long customers wait once they order, recalling 'four years for gas turbines', the CEO said 'Yes, this is the delivery time that still applies', smaller turbines being ones that 'can be delivered much quicker' (interpreted); 'Across parts of our portfolio, lead times are now three to four years and beyond' (CFO, Q3 FY26 call, on the group's backlog — not turbines alone), which Utility Dive rendered as 'lead times across the company now run three years or more'; slots sold out until 2028 with 2029 being booked (sold-out). Industry-wide, Wood Mackenzie's supply-chain team found the average lead time 'almost five years after receipt of order' as of 2025, against about two years in 2021, adding 'Lead times may have edged up slightly since then' (Wood Mackenzie blog, Feb 2026). A delivery slot, a time in backlog, a wait from order to delivery and an industry average are different measures; no pick Siemens Q1/Q3 FY26 calls (StockAnalysis transcripts) + Q2 FY26 media call (5/12/2026, interpreted); Utility Dive (8/10/2026); Wood Mackenzie (2/20/2026)
gt-capacity-gwone entry, in its own words
Siemens' near-term turbine capacity in GW comes as different measures, not one series: from 17 GW 'a year ago' to '22 average capacity between fiscal year 2025 and fiscal year 2027' (Karim Amin, CMD, Nov 2025; the CMD slide footnotes both 'Including steam turbine capacity of combined cycle configuration'); 'a flight level capacity around 20 GW' for FY26 (CEO, Q3 FY25 call, Aug 2025, with no basis given); 'around 25 GW in fiscal year 2027, including combined cycle application, which means that steam turbine output is included' — what the plans announced before the CMD would have given (IR, Dec 2025 pre-close): the slide's basis, but one year's figure where the slide's is a three-year average; against ~15–16 GW expected in Aug 2026 to ship in FY26, and more than 18 GW that the four quarters' shipments add to (expected-fiscal-2026-deliveries). Units are the firmer measure (capacity-ladder); the GW move with the frame mix, the period and whether steam-turbine output is counted Siemens CMD 2025 (Nov 20 2025), Q3 FY25 call (Aug 2025), Dec 2025 pre-close (StockAnalysis transcripts); Q3 FY26 call
combined-oem-backlogone entry, in its own words
the big three's books added up — Bloomberg calls Siemens 'one of the world's three dominant manufacturers of gas turbines, alongside GE Vernova Inc. and Mitsubishi Power Ltd.' — and every total is a third party's sum or relay on mixed definitions; no turbine maker states one: 157 GW firm + 89 GW of disclosed reservations for the three (open-factory: GE Vernova 53 + 63, Siemens 69 + 26, Mitsubishi 35 GW large-frame only, with no reservations split out); 'at least 157.6 GW' firm and 'about 246.6 GW' with reservations for four makers, Ansaldo included (POWER, Sep 1 2026, which notes 'Reporting periods and definitions differ'); 'over 170GW' of combined backlog for 'major IGT OEMs, including' the three, per unnamed 'public sources' (DPC Holdings' 424B4, Jun 2026); and 220 GW, which OilPrice's author adds up — GE Vernova's total with its reservations, Siemens' firm backlog without, Mitsubishi's large frames only — and says 'overstates the case, because none of them is counting the same thing'. Mitsubishi's 35 GW has no MHI primary on file. Range only open-factory / POWER (9/1/2026) / DPC Holdings 424B4 (6/2026) / OilPrice (8/22/2026); Bloomberg via SupplyChainBrain

Scope note what this record leaves to other records

Not this deal — not carried here or belonging elsewhere: Fermi America's Siemens turbines for its Project Matador AI campus (three SGT6-5000Fs and SGT-800 units, the warehouse loans that pay for them and a Rated Capacity Agreement that pays Siemens quarterly for ten years 'based on the operating reliability of each turbine' — all in Fermi's own filings; Fermi is not a monitor entity, and its filings state only an intention to seek vendor financing from equipment makers, naming none); Hallador's purchase of Energy World's secondhand Siemens turbines (a secondary-market sale); DPC Holdings' (Doncasters) IPO, a castings supplier that names Siemens Energy among its turbine customers — its figures are its own; Siemens Gamesa, Grid Technologies (its ~€2bn of H1 FY26 data-center orders are grid orders, not turbines, and their geography is disputed) and the transformer lead times; the named projects (Taweelah C, Oman's Misfah and Duqm, Xcel/SPS, AECI's Bristow, Dynamis's mobile units, YTL/Ganda, Saudi Arabia's Rumah 2/Nairyah 2, Syria, Pembina's Greenlight, Delfin's FLNG, B&W's steam turbines for Applied Digital, Almaty, Idaho Power's 2008 contract); three findings about other quantities (FY26 shareholder returns, Fermi's IPO proceeds, Q1 FY26 Gas Services revenue); the Meta references — SemiAnalysis lists three Siemens SGT-400s among other makers' machines at Williams' Socrates South plant for Meta in Ohio, Meta's Alan Duong sat on the CMD panel the CEO introduced as 'some of our most important customers', and no document ties Siemens to Meta by contract; group capex, service-contract length, the U.S. footprint and investment, the HL-class fleet count; figures where a call transcript disagrees with the company's own release (Q2 FY26 profit, the Q2-to-Q3 backlog step), which the releases settle; and the industry tallies (global orders in 2024 and 2025, combined-cycle $/kW, Mitsubishi's capacity plan, the U.S. gas-build pipeline). The headline figures hold as stated: Q3 FY26 orders €17.9bn, backlog €162bn, 'a new record order intake at Gas Services' (the release's phrase), 69 GW backlog + 26 GW SRAs (the deck), and the CEO's ~15–16 GW for the year. On whether reservation definitions are comparable across makers: the instrument is the same at Siemens and GE Vernova (a paid hold on a factory slot, kept outside the order backlog); the habits are not (Siemens aims to convert in about six months and held 27% of its total as reservations at 30 June and 38% at 30 September, after a quarter with no conversions; GE Vernova's CEO gives 6 to 18 months, and it held 54% at 30 June and 48% at 30 September, its backlog back above its reservations as it had forecast), nor is the line each draws between a reservation and an order (GE Vernova's CEO calls its own 'more our classification than the customers': ge-vernova-reservations), nor the bookkeeping of the fees (reservation-fee-liability); the fee level and the equipment a GW covers are not settled; and the documents on file do not allow a comparison with the third big maker: SemiAnalysis has all three selling 'nonrefundable reservation slots', but 'MHI does not split out reservations' (open-factory; combined-oem-backlog), and the one MHI document on file says nothing of them.