Why it matters
The same Ellendale AI data-center leases underpin borrowing by landlord Applied Digital and a subsidiary of cloud operator CoreWeave. CoreWeave's rent backs $3.94B of Applied Digital's project notes. A CoreWeave subsidiary took over 200 of the leases, and DBRS says the subsidiary's A (low) GPU loan rests on a contract with Meta.
Tap a figure for the line in its source.
Applied Digital gives CoreWeave
- of critical IT load, the whole campus, in three buildings: 100 and 150 MW leased in May 2025, a third 150 MW in August 2025 — 250 MW running by October 2026, the last due in 2027
- shares under two , at $7.19 and $10.75 a share, issued with the leases and booked by Applied Digital as $206.9M of lease incentives; CoreWeave assigned them to trading firms
CoreWeave gives Applied Digital
- of rent over the leases' initial terms of about 15 years, by Applied Digital's count (three five-year renewals not counted); about $0.6B a year once all three buildings run, by its filed table of minimum payments
- of the base rent still scheduled, if CoreWeave ends a lease early for convenience; but CoreWeave may walk away without a fee if Applied Digital misses its delivery dates
- letter of credit and parent guarantees, when CoreWeave moved 200 of the leases to a subsidiary that borrows on an investment-grade rating (March 2026)
Lenders & bondholders gives Applied Digital
- $3.94Bof project notes that help pay for the buildings, secured on them: $2.35B at 9.25% for the first two, $1.59B at 7% for the third
What happened
Applied Digital built its first AI data-center campus, Polaris Forge 1, near Ellendale and leased all of it to CoreWeave, a cloud company that rents out computing on graphics chips. Applied Digital is based in Dallas and began by hosting crypto-mining machines in North Dakota. CoreWeave signed leases for two buildings of 100 and 150 megawatts in May 2025. Those leases were worth about $7 billion over roughly 15 years. CoreWeave leased a third building of 150 megawatts in August 2025. That brought the campus to 400 megawatts and the leases to about $11 billion by Applied Digital's count. With the leases, Applied Digital gave CoreWeave to buy about 21.5 million of Applied Digital's shares. CoreWeave soon passed the warrants to trading firms. Applied Digital has borrowed $3.94 billion in bonds backed by the buildings to help pay for them. CoreWeave fills the buildings with its own chips. The first two buildings were running by October 2026, and the third is due in 2027. In March 2026 CoreWeave moved 200 megawatts of the leases to a subsidiary whose loan carries an investment-grade rating. CoreWeave added its own guarantees and a $50 million letter of credit, a bank commitment to pay under specified terms. A rating agency says the subsidiary's loan rests on a contract with Meta.
Sources 31 documents — 21 SEC filings · 5 company releases · 3 research notes · 1 regulatory filing · 1 other document
Research trail Found 203 documents and read 189 of them while checking this deal and related ones.
- States 4 figures: 250 MW first two leases · $3B first two value · lease term · delivery default
- States 4 figures: warrants · warrants outstanding · 150 MW second building · 150 MW third building
- States 3 figures: spv leases · $50M letter of credit · spv rating
- States 2 figures: $11B lease table · warrants assigned
- States 2 figures: 150 MW option exercise · $85.7M warrant value
- States $11B contract value
- States 100% termination fee
- States 150 MW third lease
- States $10.851517B min payments
- States tenant 13g
- States 100 MW first building
- States $500M NOI guidance
- States eln04 memorandum
- States $2.35B notes eln02 03
- States $178M interest reserve
- States $1.59B notes eln04
- States 350 MW utility service
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: Applied Digital 8-Ks (Jun 2 2025 with the ELN-02 and ELN-03 leases; Aug 29 2025 with its release; Nov 2025 and Jun 2026 notes; Jun 9 2026, furnished), 8-K/A (Apr 1 2026), FY2025 and FY2026 10-Ks, 10-Qs (Aug 31 2025, Aug 31 2026), DEF 14A (Sep 25 2026), the ELN-04 lease (Sep 2025 8-K/A) and the 2030 notes' indenture; its releases (Jun 2 2025 – Oct 7 2026; furnished or unfiled); CoreWeave's Schedule 13G and 13G/A (2025) and 8-K (Mar 30 2026); Morningstar DBRS (Apr 3 2026); MDU Resources Q3 2026 10-Q and the ND PSC's order in Case PU-24-332 (Feb 5 2025); the WSJ (Sep 25 2025), Epoch AI (Jul 2026), Measured AI (Nov 11 2026) · as of Nov 2026
The evidence 27 sourced figures · 5 disputes
The record's headline Applied Digital–CoreWeave, Polaris Forge 1 (Ellendale ND): three ~15-year leases for all 400 of the campus, ~$11B over the initial terms by the landlord's filings — the third lease's share $4.0B in its 8-K, $5B in the 2026 proxy; on 21.5M Applied Digital shares to the tenant, which assigned them on; 200 MW moved to a CoreWeave in Mar 2026; $3.94B of the landlord's project notes on the buildings
- Size
- 400 MW of critical IT · ~$11B over ~15-year initial terms (three leases; landlord's filings) · warrants on 21,456,132 Applied Digital shares to the tenant · $3.94B of the landlord's project notes on the buildings
- When
- May 28 2025 two leases (250 MW) → Jun 2 2025 announced → Jun 2025 CoreWeave assigns the first warrant → Jul 24 2025 option on the third building exercised → Aug 28 2025 third lease (400 MW) → Oct 27 / Nov 24 2025 ELN-02 ready → Nov 20 2025 $2.35B notes → Mar 30 2026 200 MW to CoreWeave's SPV → Jun 5 2026 ELN-04 memorandum → Jun 16 2026 $1.59B notes → Jul 1 / Oct 1 2026 ELN-03 ready (250 MW) → ELN-04 due in calendar 2027
- Status
- ELN-02 (100 MW) ready Nov 24 2025 and ELN-03 (150 MW) Oct 1 2026 — 250 MW running; ELN-04 (150 MW) under construction, full ready-for-service expected in calendar 2027 · 200 MW leased to CoreWeave's SPV since Mar 30 2026 · ELN-04's move to an SPV agreed in a Jun 5 2026 memorandum, conditional on an investment-grade rating, not reported done
- Structure
- three datacenter leases, one per building, each held by its own Applied Digital subsidiary and guaranteed by Applied Digital: ELN-02 (100 MW, four data halls; APLD ELN-02 LLC) and ELN-03 (150 MW, six halls; APLD ELN-03 LLC), signed May 28 2025, and ELN-04 (150 MW; APLD ELN-02 C LLC), signed Aug 28 2025 after CoreWeave exercised its option. The filings call them Buildings 2, 3 and 4; Applied Digital's 2026 releases call them Buildings 1, 2 and 3 — the record uses the ELN names. Each lease runs about 15 years from commencement with three five-year extensions at CoreWeave's election; CoreWeave may end one for convenience by paying 100% of the remaining base rent. Since Mar 30 2026 two of ELN-02's halls and all of ELN-03 are leased to CoreWeave Compute Acquisition Co. VIII, LLC, under CoreWeave springing guaranties. The landlord builds through project companies — APLD ComputeCo LLC (ELN-02 and ELN-03) and APLD ComputeCo 3 LLC (ELN-04), both under APLD HPC Holdings 2 LLC — financed by senior secured notes; CoreWeave buys and installs the computing equipment
- Programme
- CoreWeave contract web
- Parties
- CoreWeave tenant of all three leases (CoreWeave, Inc.); since Mar 30 2026 its wholly owned CoreWeave Compute Acquisition Co. VIII holds two ELN-02 halls and the whole ELN-03 lease under CoreWeave's springing guaranties; owns the computing equipment inside; received, then assigned, the warrants · Applied Digital landlord and builder through APLD ELN-02 LLC, APLD ELN-03 LLC and APLD ELN-02 C LLC, whose lease obligations it guarantees; issuer of the warrants · Lenders & bondholders holders of the project notes — $2.35B of APLD ComputeCo's 9.250% notes due 2030 (offering led by Morgan Stanley) and $1.59B of APLD ComputeCo 3's 7.000% notes due 2031 (led by Goldman Sachs); unnamed
- Capital
- the seller's own money or backing comes back as its sales
- Record
- disclosed / primary source · as of Nov 2026
Flows 5 as the record states them
- Applied Digital → CoreWeavecapacity400 MW of critical IT load across three buildings at Polaris Forge 1 — ELN-02 100 MW (ready Nov 2025), ELN-03 150 MW (ready Oct 2026), ELN-04 150 MW (calendar 2027); 250 MW running in Oct 2026
- CoreWeave → Applied Digitallease-payments~$11B over the initial ~15-year terms (FY2026 10-K table; Sep 2026 proxy) — ~$3B (ELN-02) + ~$4B (ELN-03) + $4.0B or $5B (ELN-04, contested third-lease-value); $10.85B of filed minimum contracted payments at Aug 31 2025, about $0.6B a year in FY2028–FY2030; renewals not counted
- Applied Digital → CoreWeavewarrantswarrants on 13,062,521 shares at $7.19 (May 28 2025) and 8,393,611 at $10.75 (Aug 28 2025) — fair value $85.7M + $121.2M = $206.9M (our sum), booked as lease incentives; assigned by CoreWeave to PEAK6, Jane Street and, through Jane Street, Wells Fargo
- CoreWeave → Applied Digitalcredit-supportspringing guaranties of payment and performance from CoreWeave, Inc. for its SPV on the ELN-02 halls and the ELN-03 lease, and a $50M letter of credit on the ELN-02 halls it still leases itself (Mar 30 2026)
- Lenders & bondholders → Applied Digitaldebt$2.35B of 9.250% senior secured notes due 2030 (APLD ComputeCo, Nov 20 2025, sold at 97.000%) for ELN-02 and ELN-03 + $1.59B of 7.000% senior secured notes due 2031 (APLD ComputeCo 3, Jun 16 2026, at par) for ELN-04 = $3.94B face (our sum)
Resolved figures 27 each with the verbatim line from its document
- contract-value$11Babout $11B of rent over the leases' initial terms, for 400 MW of critical IT load in three buildings — Applied Digital's own figure, in its filed proxy and in its FY2026 10-K's lease table ('~$11.0B', 15 years; lease-table). Its Aug 29 2025 release, filed with the 8-K under Item 8.01, said the third lease took the total to 'approximately $11B, which includes $7B in revenue from the initial two approximately 15-year leases'. Every document that states the figure is the landlord's: CoreWeave's 10-Qs, its FY2025 10-K and its DDTL 4.0 papers on file name neither Applied Digital nor Ellendale (tenant-13g). The renewals are not counted
“With the signing of the third CoreWeave lease, the total contracted lease revenue on this campus for the initial term is approximately $11 billion, supported by 400MW of critical IT load.”
Applied Digital DEF 14A (filed Sep 25 2026), letter to stockholders · sec.gov - lease-table$11Bthe FY2026 10-K's table of its leases at May 31 2026: Polaris Forge 1, anchor tenant CoreWeave, 400 MW, 15 years, ~$11.0B, delivery 2H25–1H27 — beside four other campuses leased to hyperscalers it does not name (~$36.2B and 1,410 MW in all; not this record's). Its footnote: the figure 'reflects the initial 15-year base term of each lease and excludes renewal options'. The '1H27' end has since slipped to calendar 2027 (third-building)
“Polaris Forge 1 CoreWeave 400 MW 15 years ~$11.0B 2H25–1H27”
Applied Digital FY2026 10-K (fiscal year ended May 31 2026), Business — lease portfolio table · ir.applieddigital.com - first-two-leases250 MWtwo leases signed May 28 2025 by Applied Digital's subsidiaries APLD ELN-02 LLC and APLD ELN-03 LLC with CoreWeave, Inc., each for the full capacity of a building then under construction — ELN-02, 100 MW, and ELN-03, 150 MW ('Building 2' and 'Building 3' in the 8-K) — on what the 8-K calls a 400 MW campus; Applied Digital guarantees each subsidiary's obligations. Announced Jun 2 2025, with CoreWeave holding an option on the campus's third building (option-exercise). The campus is designed to grow to 1 GW over time, the release said; the leases cover 400 MW
“On May 28, 2025, APLD ELN-02 LLC and APLD ELN-03 LLC, subsidiaries of Applied Digital Corporation, a Nevada corporation (the “Company”), each entered into a datacenter lease (together, the “Datacenter Leases”) with CoreWeave, Inc. (“CoreWeave”) to deliver up to an aggregate of 250 MW of infrastructure to host CoreWeave’s HPC operations at the Company’s 400 MW Ellendale, North Dakota datacenter campus (the “Ellendale Campus”).”
Applied Digital 8-K (filed Jun 2 2025), Item 1.01 · sec.gov - first-two-value$3Babout $3B for ELN-02's 100 MW and about $4B for ELN-03's 150 MW over the initial terms — the 'approximately $7 billion' of the Jun 2 2025 release, and the $7B the Aug 2025 release counts inside the ~$11B (contract-value)
“The total contract value, for the initial approximately fifteen (15)-year term, (i) for the Building 2 Datacenter Lease is expected to be approximately $3 billion, and (ii) for the Building 3 Datacenter Lease is expected to be approximately $4 billion.”
Applied Digital 8-K (filed Jun 2 2025), Item 1.01 · sec.gov - lease-term15about 15 years for each lease, each phase's term running from its own commencement (the dates are redacted), then three extensions of 60 months each at the tenant's election ('Three (3) Extension Options, each to extend the Term of all the Data Halls for an Extension Term of sixty (60) months', the leases' Basic Lease Information; the third lease's is the same). Applied Digital's tables and contract values leave the renewals out (lease-table)
“Each Datacenter Lease has an initial approximately fifteen (15)-year term followed by three (3) five (5)-year options to extend the term.”
Applied Digital 8-K (filed Jun 2 2025), Item 1.01 · sec.gov - termination-fee100%CoreWeave may end a lease for convenience, in whole, on notice, by paying an early termination fee of 100% of the base rent still scheduled for the rest of the term (plus taxes on it), before the termination date can occur (§2.4; the ELN-03 and ELN-04 leases carry the same definition, and a redacted passage follows it). The landlord's notes claim that fee for redeeming them: the 2030 notes' indenture has a 'Designated Account' for any termination fee CoreWeave pays, to be applied only to redeeming those notes at par (notes-eln02-03), and the 2031 notes must generally be redeemed at par from termination fees (notes-eln04) — in both, subject to deferral and to a replacement tenant taking the lease
“The term “Early Termination Fee” shall mean and refer to an amount equal to one hundred percent (100%) of the total scheduled amount of Base Rent (plus any applicable Taxes – Other on such Base Rent) that would have become due under this Lease for the remaining Term of this Lease.”
ELN-02 datacenter lease (Applied Digital 8-K ex. 10.1, filed Jun 2 2025), §2.4 Early Termination · sec.gov - delivery-defaultthe landlord's side of the risk: CoreWeave may terminate an affected lease if Applied Digital misses certain installation and delivery requirements by a specified date, subject to limited exclusions — and then 'with no termination fee or any other further payments due to the Company'. Applied Digital committed to start service at ELN-02 on specified dates in the second half of 2025 and at ELN-03 in the first half of 2026 (the dates are redacted); ELN-02 was ready by Nov 24 2025 and ELN-03's first phase on Jul 1 2026, 'on schedule' by that day's release (first-building, second-building)
“In addition, CoreWeave has the right to terminate any affected Datacenter Lease, if, subject to certain limited exclusions and procedural terms and conditions, the Company fails to satisfy certain installation and delivery requirements under the applicable Datacenter Lease by a specified date.”
Applied Digital 8-K (filed Jun 2 2025), Item 1.01 · sec.gov - option-exercise150 MWCoreWeave exercised its option on the campus's third building on Jul 24 2025; the option called for a third lease on 'the same rent and escalators' as the first two, within 60 days — which bears on the third lease's value (third-lease-value). The Jul 30 2025 results release (furnished) said that lease 'would add approximately $4 billion in contracted revenue'
“In addition, on July 24, 2025, CoreWeave exercised its option for an additional 150MW in our third building at Polaris Forge 1, which is currently in planning stages with an anticipated ready for service date in 2027. Under the option terms, the parties are expected to enter into a new, third lease agreement on substantially the same terms, including the same rent and escalators, as the existing two leases, within 60 days.”
Applied Digital FY2025 10-K (fiscal year ended May 31 2025), MD&A · ir.applieddigital.com - third-lease150 MWthe third lease, signed Aug 28 2025 by APLD ELN-02 C LLC for the full capacity of ELN-04 ('Building 4' in the 8-K), a 150 MW building Applied Digital would build, then in design and expected to be service-ready in mid-2027; it took CoreWeave's leased capacity at the campus to 400 MW, on 'substantially the same terms and conditions' as the first two, Applied Digital guaranteeing its subsidiary. Its value is disputed between two filings (third-lease-value)
“Accordingly, on August 28, 2025, APLD ELN-02 C LLC, a subsidiary of the Company, and CoreWeave entered into a third datacenter lease (the “Building 4 Lease”) for the full capacity of Building 4 at Polaris Forge 1 (“Building 4”), a 150MW data center to be constructed by the Company.”
Applied Digital 8-K (filed Aug 29 2025), Item 1.01 · sec.gov - min-payments$10.851517B$10.85B of minimum contracted payments due from the three leases at Aug 31 2025 — the lessor table of the quarter the third lease was signed, which the 10-Q gives for these leases alone (Applied Digital's next lease, at Polaris Forge 2, came on Oct 20 2025). It leaves out reimbursed operating expenses and variable rent increases. By fiscal year (to May 31): $586.0M in FY2028, $606.6M in FY2029 and $624.8M in FY2030, when all three buildings are due to run — about $0.6B a year. The first two leases' total was $6.76B at May 31 2025 (FY2025 10-K); later tables add the other campuses ($35.7B at Aug 31 2026). A newsletter (Measured AI, Nov 2026) puts the campus's initial rent at about $576M a year, rising about 3% a year (~$120 per kW a month), and attributes it to Applied Digital; no Applied Digital document on file states those figures
“Minimum Contracted Payments FY26 $ 81,000 FY27 356,340 FY28 586,030 FY29 606,611 FY30 624,809 Thereafter 8,596,727 Total $ 10,851,517”
Applied Digital 10-Q, quarter ended Aug 31 2025, Leases note — lessor accounting · ir.applieddigital.com - warrants13,062,521warrants on Applied Digital common stock issued to CoreWeave with the leases: 13,062,521 shares at $7.19 with the first two (May 28 2025) and 8,393,611 at $10.75 with the third (Aug 28 2025) — 21,456,132 in all (our sum), each exercisable for 10 years, in cash or cashless. Under the May 2025 letter agreement, any further lease or expansion that raises CoreWeave's contracted capacity at Applied Digital's data centers brings more warrants on the same terms, their price and number set at issue; that obligation ends on a change of control of either company. Applied Digital books their fair value as a lease incentive (warrant-value)
“In connection with certain data center leases with CoreWeave, the Company issued warrants to CoreWeave to purchase up to 13,062,521 and 8,393,611 shares of the Company’s common stock on May 28, 2025 and August 28, 2025, respectively, at an exercise price of $7.19 and $10.75 per share, respectively (the “CoreWeave Warrants”).”
Applied Digital 10-Q, quarter ended Aug 31 2026 (filed Oct 7 2026), warrants note · ir.applieddigital.com - warrant-value$85.7M$85.7M ($6.56 a warrant share) for the first warrant and $121.2M ($14.44 a share) for the third lease's (Aug 2025 10-Q; FY2026 10-K) — $206.9M in all (our sum), recorded as lease incentive assets and amortized over each lease's life once it commences: the landlord's own equity given to its tenant, set against the rent
“The resulting fair value of the CoreWeave Warrant was $6.56 per warrant, totaling $85.7 million which was recorded to lease incentive asset and additional paid in capital on the Company's consolidated balance sheets, and will be amortized over the life of the respective CoreWeave Lease once such lease commences.”
Applied Digital FY2025 10-K, warrants note · ir.applieddigital.com - warrants-assigned6,531,261CoreWeave kept none of the warrants: it assigned the first to PEAK6 Capital Management (6,531,261 shares) and Jane Street (6,531,260) in June 2025 — Jun 9 here, Jun 10 in the FY2025 10-K and CoreWeave's own 13G/A (warrant-assignment-date) — and the third lease's to Jane Street Global Trading on Oct 31 2025; around May 15 2026 Jane Street assigned both of its warrants to Wells Fargo Bank, N.A. CoreWeave's own cash-flow statements show $100.6M from a 'Sale of warrants received as lease incentive' in the first half of 2025, naming no issuer
“On June 9, 2025, CoreWeave assigned a portion of the CoreWeave Warrant to acquire up to 6,531,261 shares of the Company's common stock to PEAK6 Capital Management, LLC (the “PEAK6 Warrant”).”
Applied Digital FY2026 10-K, warrants note · ir.applieddigital.com - warrants-outstanding21,455,83221,455,832 of the 21,456,132 warrant shares were outstanding at Aug 31 2026: 300 had been exercised, cashless, under PEAK6's portion — in the quarter to Aug 31 2025, by that quarter's 10-Q
“As of August 31, 2026, 21,455,832 warrant shares remain outstanding.”
Applied Digital 10-Q, quarter ended Aug 31 2026, warrants note · ir.applieddigital.com - tenant-13g13,062,521the tenant's own word on the deal: CoreWeave's Schedule 13G (event May 28 2025) reports the first warrant's shares, 5.5% of Applied Digital's stock by the rule's count, as issued 'in connection with commercial data center lease agreements' with Applied Digital's subsidiaries; its amendment (event Jun 10 2025) reports 0.0%, after the assignment. These are the only CoreWeave filings on file that name Applied Digital — its 10-Qs (Jun and Sep 2025, Sep 2026), its FY2025 10-K and its Mar 30 2026 8-K and credit agreement do not, nor Ellendale or North Dakota
“The securities reported in Rows 5, 7, and 9 consist of 13,062,521 shares of the Common Stock of Applied Digital Corporation (the "Issuer") issuable upon the exercise of vested warrants (the "Initial Warrant") to purchase shares of Common Stock of the Issuer, which Initial Warrant is directly beneficially owned by CoreWeave, Inc. (the "Reporting Person"). The Initial Warrant was issued to the Reporting Person on May 28, 2025, in connection with commercial data center lease agreements entered into by and between the Reporting Person and certain subsidiaries of the Issuer.”
CoreWeave Schedule 13G on Applied Digital (event date May 28 2025) · sec.gov - first-building100 MWELN-02 ready: its first 50 MW on Oct 27 2025 and its second on Nov 24 2025, taking the building to its full 100 MW — 'Building 1' in these releases, the 8-K's 'Building 2'. The FY2026 10-K dates its completion both ways (first-building-operational)
“After achieving this milestone, Building 1 now operates at its full 100 MW critical IT load, marking the completion of the first of three contracted buildings at the campus.”
Applied Digital release (Nov 24 2025) · ir.applieddigital.com - second-building150 MWELN-03 ready: its first 75 MW on Jul 1 2026 — 'on schedule', taking live capacity at the campus to 175 MW (release of that day) — and its second 75 MW on Oct 1 2026, bringing 'fully operational critical IT load at the campus to 250 MW across two buildings and 10 data halls' (Oct 7 2026 results release, furnished). 'Building 2' in those releases, the 8-K's 'Building 3'
“During the quarter, we began commencing operations at our second HPC data center at our Polaris Forge 1 campus, which reached its full 150MW of capacity as of the date of filing of this Form 10-Q.”
Applied Digital 10-Q, quarter ended Aug 31 2026 (filed Oct 7 2026), MD&A · ir.applieddigital.com - third-building150 MWELN-04 under construction in Oct 2026, its full ready-for-service expected in calendar 2027 — 'mid 2027' when the lease was signed (Aug 2025 8-K) and in the FY2026 10-K's lease note. Its utility expects the building's load to begin ramping in January 2027 (utility-service)
“Our third HPC building at our Polaris Forge 1 campus, which is expected to provide an additional 150MW of capacity, is currently under construction. We anticipate reaching full ready for service in calendar year 2027.”
Applied Digital 10-Q, quarter ended Aug 31 2026, MD&A · ir.applieddigital.com - noi-guidance$500MApplied Digital's own projection, in its Oct 9 2025 results release (furnished): an annualized net operating income 'run rate of approximately $500 million once Polaris Forge 1 is fully operational' — an estimate, not a figure any lease states
“We believe we are on a projected annualized NOI run rate of approximately $500 million once Polaris Forge 1 is fully operational.”
Applied Digital Q1 FY2026 results release (Oct 9 2025; furnished) · ir.applieddigital.com - spv-leaseson Mar 30 2026 two of ELN-02's four data halls (50 MW, at 25 MW a hall — our arithmetic) were taken out of CoreWeave's own lease and leased, on substantially the same terms, to CoreWeave Compute Acquisition Co. VIII, LLC, a wholly owned subsidiary, for the rest of the initial term (the suspended term revives if the SPV lease ends); the whole ELN-03 lease was assigned to the same SPV, releasing CoreWeave, Inc. from it — 200 MW of the campus in all (our sum). CoreWeave gave springing guaranties of payment and performance for the SPV under both, and is to post a letter of credit for the halls it still leases itself (letter-of-credit). Applied Digital filed it as amending its Jun 2025 8-K, agreements 'intended to enhance the credit of the tenants'
“On March 30, 2026, the Company and CoreWeave Parent amended the ELN-02 Parent Lease to suspend the term for two of the four data halls covered by the lease (the “ELN-02 Parent Lease Amendment”) and the Company entered into a new datacenter lease with CoreWeave Compute Acquisition Co. VIII, LLC (“CoreWeave SPV”), a wholly owned subsidiary of CoreWeave Parent, for those two data halls on substantially the same terms as the ELN-02 Parent Lease (the “ELN-02 SPV Lease”).”
Applied Digital 8-K/A (filed Apr 1 2026), Item 1.01 · ir.applieddigital.com - letter-of-credit$50M$50M, the letter of credit CoreWeave, Inc. is to provide within 30 days of Mar 30 2026 to secure its obligations on the two ELN-02 halls it still leases itself; the FY2026 10-K, filed after those 30 days, still describes it as an obligation
“In addition, CoreWeave Parent is obligated to provide a letter of credit in the amount of $50,000,000 to secure obligations under the ELN-02 Parent Lease within 30 days (the “Letter of Credit”).”
Applied Digital 8-K/A (filed Apr 1 2026), Item 1.01 · ir.applieddigital.com - spv-ratingwhy, by CoreWeave's account to Applied Digital: it was refinancing debt tied to ELN-02 and ELN-03, and the refinanced debt was rated A3, against BB for CoreWeave itself (the 8-K/A names no agency). The SPV is the borrower under the $8.5B DDTL 4.0 it signed the same day (CoreWeave 8-K, Mar 30 2026; cw-ddtl4-2026), which Morningstar DBRS rates A (low) and describes as financing GPUs for four data centers at three sites — in Virginia, Georgia and North Dakota — under the SPV's contract with Meta (end-user). Neither CoreWeave's 8-K nor its credit agreement names Applied Digital or Ellendale; that DBRS's two North Dakota facilities are these buildings is our reading of the dates and names
“CoreWeave Parent informed us that it was refinancing certain of its debt obligations with respect to ELN-02 and ELN-03, and that the refinanced indebtedness received an investment grade credit rating of A3. These ratings compare favorably to CoreWeave Parent’s credit rating of BB.”
Applied Digital 8-K/A (filed Apr 1 2026), explanatory note · ir.applieddigital.com - eln04-memorandumthe third lease is to follow if a CoreWeave subsidiary earns an investment-grade rating: a memorandum of understanding of Jun 5 2026 to assign the ELN-04 lease to it on that condition (Item 7.01, furnished). The proxy (filed Sep 25 2026) says Applied Digital expected to implement it 'during the last quarter of Fiscal Year 2026' — a quarter that had ended on May 31 2026, before the memorandum was signed; the Oct 2026 10-Q mentions CoreWeave only in its warrants note
“The Company also announced that it entered into a Memorandum of Understanding on June 5, 2026, to assign the lease with CoreWeave, Inc. for ELN-04 (as defined below) to a CoreWeave, Inc. subsidiary, if that subsidiary achieves an investment grade credit rating.”
Applied Digital 8-K (filed Jun 9 2026), Item 7.01 (furnished) · ir.applieddigital.com - notes-eln02-03$2.35B$2.35B of 9.250% senior secured notes due Dec 15 2030, sold at 97.000% and closed Nov 20 2025 by APLD ComputeCo LLC (direct parent APLD HPC Holdings 2 LLC), to fund part of building ELN-02 and ELN-03, repay the Feb 2025 SMBC construction loan and fund debt-service reserves; principal amortizes semi-annually. The indenture routes any lease termination fee from CoreWeave or a qualifying tenant into a 'Designated Account', whose funds go only to redeeming the notes at par — a redemption the issuer may defer, and owes no longer if a qualifying tenant assumes or enters into a new lease in time (ex. 4.1, §3.11 and §4.23) — and sets aside $178.0M of the proceeds for interest during construction (interest-reserve). With the 2031 notes, $3.94B of project notes on the campus (our sum)
“The aggregate principal amount of notes sold in the offering was $2.35 billion. The notes were issued at a price equal to 97.000% of their principal amount.”
Applied Digital 8-K (filed Nov 2025), Item 1.01 · ir.applieddigital.com - interest-reserve$178M$178.0M of the 2030 notes' net proceeds deposited in an 'IDC Account' to pay the notes' interest while ELN-02 and ELN-03 were built; what remains 60 days after all the leases in effect at issue have commenced may go to the revenue account
“the account into which $178.0 million of the net proceeds from the offering of the Initial Notes will be deposited, to be used to fund interest on the Notes during construction of the Projects (the “IDC Account”)”
APLD ComputeCo indenture, 9.250% notes due 2030 (Applied Digital 8-K ex. 4.1, Nov 2025) · ir.applieddigital.com - notes-eln04$1.59B$1.59B of 7.000% senior secured notes due Jun 15 2031, sold at par and closed Jun 16 2026 by APLD ComputeCo 3 LLC, to build ELN-04, repay the $300M Goldman Sachs bridge loan and fund reserves — a coupon 2.25 percentage points under the 2030 notes' 9.25%, seven months later (our arithmetic). If a lease termination fee is received, APLD ComputeCo 3 must generally apply it to redeem these notes at par, subject to deferral and replacement-tenant provisions (Oct 2026 10-Q); Applied Digital gives only a completion guarantee
“The aggregate principal amount of notes sold in the offering was $1.59 billion. The notes were issued at a price equal to 100.000% of their principal amount.”
Applied Digital 8-K (filed Jun 2026), Item 1.01 · ir.applieddigital.com - utility-service350 MWthe campus's power, by its utility: Montana-Dakota Utilities has served Applied Digital's first Ellendale data center (180 MW at full capacity — the site where Applied Digital still hosts a crypto-mining customer) since March 2023, and North Dakota's regulators approved an agreement to serve 350 MW more of Applied Digital's data-center load; 280 MW of Applied Digital's load was online at MDU's Sep 2026 quarter report, which does not split it between the old site and the new buildings. The 350 MW agreement is with APLD-ELN-02 LLC, the first lease's landlord: the Public Service Commission's order of Feb 5 2025 (Case PU-24-332) approved raising it from 225 MW to 350 MW and extending its expiration to Aug 31 2030 — years before the leases' initial terms end (our reading of the two dates). Utility load, not critical IT: the leases' 400 MW is IT load
“The NDPSC approved an electric service agreement to serve an additional 350 MW of data center load with Applied Digital in the Company's service territory. The third HPC building at Ellendale is scheduled to begin ramping in January 2027. A total of 280 MW of Applied Digital's data center load is currently online.”
MDU Resources 10-Q, quarter ended Sep 30 2026 (filed Nov 2026); ND PSC order, Case PU-24-332 (Feb 5 2025) · sec.gov
Contested figures 10 not reconciled — every position side by side, with its source and tier
Scope note what this record leaves to other records
NOT this record (carried elsewhere or not carried): Applied Digital's other campuses and tenants — Polaris Forge 2 (Harwood ND, 200 MW, ~$5.0B in the 10-K, 'approximately $4 billion' in the proxy, an investment-grade hyperscaler it does not name; one industry primer names Oracle, unsourced), Polaris Forge 3 and Delta Forge 1 and 2 (810 MW, ~$20B, one high-investment-grade hyperscaler, unnamed) — and the portfolio totals (1,410 MW; ~$36.2B in the 10-K, $35.7B of minimum payments at Aug 31 2026, ~$86B with renewals; 'nearly 80%' or ~70% with investment-grade support on different bases) → the applieddigital entity's note, not carried here; Macquarie's preferred equity at APLD HPC TopCo 2, above the campus (up to $5.0B; ~$1.8B funded by May 31 2026; 13.5% of TopCo 2's common; $450M scheduled for this campus with up to $250M more if triggered, and whether that was funded) → not carried: it finances the whole HPC business, not this campus or CoreWeave's equity; Applied Digital's own equity in the project (≥$619M / ~$1.2B / '$1 billion' on three bases) → not carried; CoreWeave's DDTL 4.0 itself ($8.5B, its tranches, rate and covenant) → cw-ddtl4-2026, cited here only for who borrows on the SPV's halls; CoreWeave's Meta order forms ($14.2B, $21.0B) → cw-meta; CoreWeave's company totals (debt, backlog, lease obligations, bond yields) → not carried; Fitch's ratings and rating cases on the 2030 and 2031 notes (BB-; a 1.50x project life coverage ratio at 2030; average DSCRs 1.04x and 1.52x), and analysts' models (a 1.01x 2028 DSCR, $627.5M of NOI, $146K or $1.83M of rent per MW) → not carried: estimates on other bases; Applied Digital's revenue by quarter, and its revenue concentration, which the filings give only for lettered customers → not carried; the Jan 2024 conditional 100 MW anchor tenant (~$2.2B over 10 years) and the 400 MW letter of intent with an unnamed hyperscaler → earlier arrangements no document ties to CoreWeave, not carried; MDU's ratepayer figures, the Jamestown–Ellendale 345 kV line, generator counts and ratings, and the campus's design PUE (1.15 vs 1.18) → site facts, not carried; Epoch's chip and IT-power estimates (93k rising to 505k or 507k H100-equivalents; 68 MW) → not carried; CoreWeave's $222.3M of 'warrants received as lease incentive' by Sep 30 2025 → not carried: no issuer named, and it does not match Applied Digital's $206.9M; Nvidia's part in Applied Digital's Sep 2024 share placement and its $2B in CoreWeave → not this deal. Not adopted: Epoch's summary line, 'two roughly 15-year leases with CoreWeave cover 400 MW across three buildings, an initial contract worth about $7 billion', which joins the first two leases' value to the three-lease campus; and a reading of the March 2026 hall suspension as lost capacity — the halls moved to the SPV on substantially the same terms (spv-leases).