Why it matters
Microsoft is building Fairwater outright in Wisconsin, leaving few public figures for its cost. Microsoft's pledges total 'more than $7 billion' and do not say whether they cover GPUs. The utility's '$20+ billion' includes $13 billion that matches village tax-roll estimates, while Epoch's model puts the first facility's cost at $14.0B, including chips.
What happened
Microsoft is building its first 'Fairwater' AI data-center campus in Mount Pleasant, Wisconsin with its own money. It began buying the land from the village in 2023. The district was first assembled for Foxconn. Microsoft pledged $3.3 billion in May 2024. It says the first facility's equipment came online in April 2026 and declared the facility fully operational in June. Microsoft added $4 billion in September 2025 for a second facility of similar size, scheduled for 2028. That comes to 'more than $7 billion' by Microsoft's count. The local utility tells investors Microsoft announced over $20 billion. No Microsoft statement in the record says so. The extra $13 billion matches village staff's January estimates of what two more proposed campuses would add to the tax roll. Planners have since estimated a lower amount for one of them. For the site's power, Microsoft has given a 2-gigawatt goal. Through the press, it has put the first phase at 400–450 and said the site could reach 900 MW in a few years. Epoch AI's model puts the first facility's IT power, or power for computing equipment, at 369 MW. That is the highest of the point estimates, which start at 114 MW. Epoch AI's model puts the facility's cost at $14.0 billion, including chips. Epoch AI also says developer QTS built the second Fairwater site, near Atlanta, and rented it to Microsoft.
Sources 53 documents — 14 other documents · 12 company releases · 10 press reports · 7 research notes · 6 SEC filings · 3 government statements · 1 regulatory filing
Research trail Found 158 documents and read 154 of them while checking this deal and related ones.
- States 2 figures: $4B second pledge · 250 MW fossil matching
- States 2 figures: site · cluster
- States 2 figures: first facility complete · $4.7B local construction spend
- States $1B first announcement
- States $50.085M land purchase
- States $3.3B first pledge
- States $262.5M reported spend
- States 1.45 GW carbon free contracted
- States $5M village incentive
- States $7,973,638,329 durand valuation
- States $5,329,561,500 international valuation
- States $6,095,690,000 durand revaluation
- States fairwater atlanta
- States phase two pause
- States $13B utility account
- States $14B epoch model
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: Microsoft: release (May 8 2024), On the Issues and Official Microsoft Blog (Sep 18 2025), Source feature and a second Official Microsoft Blog post (Nov 12 2025), release (Jun 23 2026), construction update (Mar 2026), Mount Pleasant boards (Jun 2026), FY26 Q1 and Q3 calls; Village of Mount Pleasant fact sheet (Mar 28 2023), Plan Commission staff reports (Jan 21 and Oct 14 2026) and news flash (Sep 28 2026); the Village's, County's and development agencies' releases on RCEDC's site (Mar 27 and May 31 2023); Legislative Fiscal Bureau (Mar 18 2026); WEC Energy Group FY2025 10-K, Q2-2026 and Q3-2026 10-Qs and investor decks (furnished); Wisconsin Electric's rebuttal testimony (Stasik) in PSC docket 6630-TE-113, attached to the PSC of Wisconsin's comments in FERC ER26-3265; Microsoft's air-permit application to the Wisconsin DNR (Sep 2024); OpenAI (Jan 20 and May 5 2026); Geronimo Power (Oct 1 2024); MISO's list of announced large loads (Dec 6 2024); Epoch AI; SemiAnalysis; SynMax; measuredai; WPR, FOX6, TMJ4, Spectrum News, Bloomberg via Insurance Journal, the Guardian; AFII and MNI on Atlanta's owner; Crown Corr (read 2026-10) · as of Oct 2026
The evidence 19 sourced figures · 9 disputes
The record's headline Microsoft Fairwater, Mount Pleasant WI: a self-funded AI campus — $3.3B pledged (May 2024) + $4B for a second facility, 'more than $7 billion' by Microsoft's count; first facility declared fully operational Jun 2026; the utility's '$20+ billion' adds a $13B that matches the Village's January taxable-value estimates for two proposed campuses; Atlanta, the second Fairwater site, has no dollar or figure from Microsoft in the record
- Size
- $3.3B + $4B pledged — 'more than $7 billion' by Microsoft's count · first facility declared fully operational Jun 2026, second scheduled by Microsoft for 2028 · the utility's '$20+ billion' is in no Microsoft statement in the record
- When
- Mar 27 2023 a $1B, 315-acre campus announced → May 31 2023 land purchase closed → May 8 2024 $3.3B pledge → Jan–Mar 2025 work on later phases paused → Sep 18 2025 +$4B for a second facility ('more than $7 billion') → Apr 2026 equipment online, by Microsoft's account → Jun 23 2026 declared fully operational → 2028 second facility (Microsoft's schedule)
- Status
- first facility declared fully operational (Jun 23 2026) · second under construction, scheduled by Microsoft for 2028 · site plans for two more campuses approved Jan 2026; an amendment to Durand Avenue's plan (seven larger buildings) approved by the Plan Commission Oct 14 2026, the Village Board's vote to follow
- Structure
- self-funded: Microsoft bought the first 315 acres from the Village for $50,085,000 in 2023, and more land since from the Village and private owners, and builds, owns and runs the facilities (the chips are Microsoft's by Epoch's account) — no venture, lease or project financing of Microsoft's for the Wisconsin campus appears in any document on file; the debt in the district is the Village's and the County's. Public support: the state's sales and use tax exemption for certified data centers (WEDC certified the project Oct 1 2023) and the Village's tax-increment incentive of up to $5M a year, which Microsoft redirected to the Village and RCEDC in Sep 2026. Power comes from We Energies, for which Microsoft says it is 'pre-paying for the energy and electrical infrastructure that we'll use'; the tariff, the plants built for its load and the transmission are a power deal of their own, not this record
- Programme
- Microsoft buildout
- Parties
- Microsoft owner, builder and operator — bought the land, pays for the buildings with its own money and runs the site; the chips are Microsoft's by Epoch's account; by its own account its AI datacenters power OpenAI, Microsoft AI, Copilot and other AI workloads, and the Fairwater sites its network links will work together to support them
- Sites
- MS Fairwater (Atlanta) · MS Fairwater (Wisconsin)
- Record
- disclosed / primary source · as of Oct 2026
Resolved figures 19 each with the verbatim line from its document
- first-announcement$1Bthe day the campus became public: the Village of Mount Pleasant, Racine County, RCEDC, WEDC and Milwaukee 7 announced plans for Microsoft to buy a 315-acre parcel in the Village — 'The aim is to create a data center campus' — under a development agreement for 'a $1 billion, 315-acre data center campus' (Mar 27 2023). The Village's fact sheet of the next day gives both 'plans to invest $1 billion' and, among the development agreement's terms, a campus built 'at a cost of more than $1 billion' (land-purchase), and the Legislative Fiscal Bureau's table of the state's certified data centers lists $1,000,000,000 of planned expenditure for it (reported-spend). Every later pledge is for this campus and the land around it
“The development agreement notes that Microsoft will develop a $1 billion, 315-acre data center campus.”
Village of Mount Pleasant, Racine County, RCEDC, WEDC and Milwaukee 7 release (Mar 27 2023) · rcedc.org - land-purchase$50.085Mthe first site, bought outright: the Village agreed to sell Microsoft 'approximately 315 acres within TID 5 for $50,085,000' (fact sheet of Mar 28 2023, for the Mar 30 board vote), and the Village, Racine County, RCEDC, WEDC and Milwaukee 7 announced the closing of the 'approximately $50 million land purchase' on May 31 2023 (RCEDC's post). TID 5 is the tax-increment district assembled for Foxconn: Foxconn released its rights to the 315 acres and receives the proceeds, net of costs, 'as partial reimbursement of the funds Foxconn advanced in 2017 to acquire lands in TID 5'. The development agreement also let Microsoft recoup part of its property taxes (village-incentive). Microsoft has bought more land since; the figures on file for its holdings do not reconcile
“An Agreement for Microsoft Corporation to purchase and the Village to sell approximately 315 acres within TID 5 for $50,085,000 by July 31, 2023.”
Village of Mount Pleasant fact sheet (Mar 28 2023); the Village's, County's and agencies' release on RCEDC's site (May 31 2023) · mtpleasantwi.gov - first-pledge$3.3B$3.3B 'between now and the end of 2026' for a datacenter campus in Mount Pleasant (May 8 2024; the release says President Biden would join the announcement), beside an AI co-innovation lab and an AI-skilling program. It gives no MW or chip count for the datacenter, names no customer, and does not break the $3.3B into land, buildings and equipment. In Sep 2025 Microsoft said finishing its first datacenter would be 'fulfilling our initial $3.3 billion investment pledge'
“First, Microsoft will invest $3.3B between now and the end of 2026 to expand its national cloud and AI infrastructure capacity through the development of a state-of-the-art datacenter campus in Mount Pleasant, Wisconsin.”
Microsoft release (May 8 2024) · news.microsoft.com - phase-two-pause900the pause: in Jan 2025 Microsoft stopped early work on the next phase — 'We have paused early construction work for this second phase while we evaluate scope and recent changes in technology and consider how this might impact the design of our facilities', a spokesperson told WPR — restarted it, and by Mar 20 2025 had paused work on the 900-acre expansion site again, while the first phase stayed 'fully on track' and 'our $3.3 billion commitment remains intact'. The paused 900 acres lie 'just west of that site, as well as to the northwest along Durand Avenue' (WPR); by the Village's account as WPR reported it in Jan 2025, the paused work was construction 'inside the 115-acre site to the west' and earthwork 'in the 791 acres at Durand Avenue'. Microsoft's Sep 2024 air-permit application puts the second facility, MKE16/17, 'directly west of, and adjacent to' the first, and six data centers (MKE Area 2) on 'approximately 792 acres' south of Durand Avenue; matching the paused parcels to those plans is our reading — no document on file says which buildings the pause stopped. The $4B for a second facility came six months later (second-pledge)
“Once again, Microsoft has paused work on a 900-acre portion of its Mount Pleasant data center campus.”
WPR (Mar 20 2025, and Jan 2 2025, updated Jan 9, for the first pause and the Village's account of the parcels); Microsoft's air-permit application to the Wisconsin DNR (Sep 2024) for the plans · wpr.org - second-pledge$4Ban additional $4B 'to be spent in the next three years to build our second datacenter of similar size and scale', taking Microsoft's own total in Wisconsin to 'more than $7 billion' (Sep 18 2025) — the $3.3B and the $4B, which WEC's decks write as '$7.3 billion – Phase 1 and 2' (program-total). The second facility, 'immediately adjacent to the first', was at foundations, steel erection and underground utilities in Jun 2026 (second-facility-timing)
“And we’re not done. Today, we’re committing an additional $4 billion to be spent in the next three years to build our second datacenter of similar size and scale — bringing our total investment in Wisconsin to more than $7 billion.”
Microsoft On the Issues, Brad Smith (Sep 18 2025) · blogs.microsoft.com - site315Microsoft's own description of the first campus: 315 acres — the parcel the Village sold it (land-purchase) — and 'three massive buildings' with 1.2 million square feet under roof (Sep 18 2025). Other sources count its buildings and floor area in other units; those counts are not carried here
“The new Fairwater AI datacenter in Wisconsin stands as a remarkable feat of engineering, covering 315 acres and housing three massive buildings with a combined 1.2 million square feet under roofs.”
Official Microsoft Blog, Scott Guthrie (Sep 18 2025) · blogs.microsoft.com - clusterwhat runs inside: 'a single, massive cluster of interconnected NVIDIA GB200 servers' — racks of 72 Nvidia Blackwell GPUs, each rack one NVLink domain, laid out over two stories so racks also connect to those above and below — fed by a separate storage and compute datacenter (Sep 18 2025). Microsoft's count is 'hundreds of thousands' of GPUs, with no number (first-facility-gpus)
“This datacenter runs a single, massive cluster of interconnected NVIDIA GB200 servers and millions of compute cores and exabytes of storage, all engineered for the most demanding AI workloads.”
Official Microsoft Blog, Scott Guthrie (Sep 18 2025) · blogs.microsoft.com - first-facility-complete2026done inside the pledge's window: construction complete and the facility 'now fully operational' on Jun 23 2026, after equipment came online with startup activities in April — within the end-2026 window of the $3.3B pledge; 2028 is the second facility's date, not the first's. Nadella had told investors on Apr 29 2026 that it 'came online earlier this month, six weeks ahead of schedule'; how much of it was serving workloads at each date is disputed (online)
“Village of Mount Pleasant, Wis. — June 23, 2026 — Microsoft Corp. on Tuesday announced that it has completed construction of its first datacenter facility in the Village of Mount Pleasant, after bringing equipment online and conducting startup activities in April.”
Microsoft release (Jun 23 2026) · news.microsoft.com - local-construction-spend$4.7Ba third dollar figure, with its own scope: Microsoft's estimate of what it will have spent on construction locally in Wisconsin over 2024–2028, beside direct purchases from 29 businesses in 11 Wisconsin counties (Jun 23 2026). Microsoft does not say how it relates to the $3.3B and $4B pledges, so the record never sums it with them
“Microsoft estimates that the company will have spent $4.7 billion between 2024 and 2028 locally on hyperscale construction in Wisconsin.”
Microsoft release (Jun 23 2026) · news.microsoft.com - reported-spend$262.5Mspending reported to the state: Microsoft reported $262.5M of expenditures to WEDC for 2024 under the state's data-center contract, which certified the Mount Pleasant project on Oct 1 2023 for Wisconsin's sales and use tax exemption on data-center purchases, with $1,000,000,000 of planned expenditure and a $150,000,000 minimum qualified investment (Legislative Fiscal Bureau memo, Mar 18 2026). The memo says these are expenditures incurred in 2024, that Microsoft, having met the minimum qualified investment, need not report after 2024, and that the sales tax forgone on them comes to an estimated $10.5M (Table 3); it does not say which costs they cover. Bloomberg put Microsoft's spending in the project's first six months at '$262 million on construction', from documents it did not name (via Insurance Journal, Apr 4 2025) — a near-match that the documents on file do not tie to the same report; Microsoft's Jun 2026 boards give '$700 million in spending on direct construction suppliers in Racine county'. The memo's 'committed $20.6 billion' is the contested program-total
“In total, Microsoft has committed $20.6 billion to Wisconsin data center projects, well above the $1 billion planned investment under its contract with WEDC and above the $262.5 million in expenditures reported to WEDC for 2024.”
Wisconsin Legislative Fiscal Bureau memo (Mar 18 2026) · wpr.org - fossil-matching250 MWmatching, not supply: Microsoft says it 'will match every kilowatt hour we consume that comes from a fossil fuel source one for one with carbon-free energy we put back onto the grid', and that this includes 'a new 250 MW solar project in Portage County' then under construction (Sep 18 2025) — the project announced with National Grid Renewables on May 8 2024 to 'begin operating in 2027', whose power purchase agreement with Microsoft the developer, now Geronimo Power, announced on Oct 1 2024. Its output goes onto the regional grid; it is not a supply contract for the campus, which We Energies serves
“This includes a new 250 MW solar project in Portage County that is under construction to support this commitment.”
Microsoft On the Issues, Brad Smith (Sep 18 2025) · blogs.microsoft.com - carbon-free-contracted1.45 GWthe matching book in Wisconsin, Jun 2026: 'We will match every kWh from fossil fuel with carbon-free energy on the regional grid. To deliver on that promise', 1.45 GW contracted — agreements with We Energies for 1.2 GW of new solar and battery projects online 'starting in December 2028', plus the 250 MW Portage PPA (Microsoft's Mount Pleasant boards). Capacity to be built on the grid, not power delivered to the campus
“Microsoft has signed contracts that enable 1.45 GW of carbon free energy to be constructed in Wisconsin.”
Microsoft Mount Pleasant community boards (Jun 2026) · local.microsoft.com - village-incentive$5Mthe local incentive, redirected: the 2023 development agreement let Microsoft 'recoup 42 percent of the annual incremental property taxes it pays on the improvements it builds, not to exceed $5 million per year', payments 'contingent on the Village having received sufficient Tax Increment Revenue to have first paid all other TID obligations' (fact sheet, Mar 28 2023); on Sep 28 2026 the Village announced that Microsoft was redirecting it — about $4.9M a year back to the Village, which plans to spend it on tax relief (a lower tax levy from 2027, and capital costs met without borrowing), and about $100,000 to RCEDC. The state's sales-tax exemption (reported-spend) is a separate benefit
“Microsoft has made the decision to redirect its $5 million annual development incentive, paving the way for the Village of Mount Pleasant to advance immediate and long-term property tax relief.”
Village of Mount Pleasant news flash (Sep 28 2026); fact sheet (Mar 28 2023) · mtpleasantwi.gov - utility-account$13Bthe utility's account, not Microsoft's: on the slide '2.6 GW of Demand Forecasted through 2030' of WEC Energy's Sep 4 2026 investor deck (8-K ex-99.1, furnished under Item 7.01; the utility's, not a party's, so tier 2), the Microsoft campus is 'Announced investment of $20+ billion', split '$7.3 billion – Phase 1 and 2' and '$13 billion - Additional', with 'Building 15 additional data centers beyond Phase 1 and 2' and 'Phase 1 operations commenced in April 2026'; its decks have carried the split since Feb 2026. No Microsoft page on file states $20B or $13B for Wisconsin: the $7.3B is the two pledges, and the $13B matches the Village staff's January taxable-value estimates for the two proposed campuses, $13.30B together (expansion-value)
“Microsoft Data Center ▪ Announced investment of $20+ billion ▪ $7.3 billion – Phase 1 and 2 ▪ $13 billion - Additional ▪ Building 15 additional data centers beyond Phase 1 and 2”
WEC Energy Group investor deck, 8-K ex-99.1 (Sep 4 2026; furnished, Item 7.01) · sec.gov - durand-valuation$7,973,638,329Durand Avenue, the larger of the two proposed campuses: an updated site plan (a preliminary one was approved in Aug 2024) with nine data centers of 579,796 square feet each, which Village staff put at $7,973,638,329 of taxable value (Plan Commission, Jan 21 2026) — what the finished campus would add to the tax roll, not what Microsoft would spend on it. With International Drive's $5,329,561,500 it makes $13.30B (our sum), which every '$13 billion' figure on file for the two campuses matches (expansion-value); an Oct 2026 amendment, approved by the Plan Commission with the Village Board's vote to follow, would replace the nine with seven larger buildings (durand-revaluation)
“The total taxable value for the proposed development is $7,973,638,329, which would generate approximately $136,249,581 in incremental tax revenues while TID 5 remains open, and $45,204,264 in village revenues once TID 5 closes.”
Village of Mount Pleasant Plan Commission staff report, 12023 Durand Avenue (Jan 21 2026) · d2kbkoa27fdvtw.cloudfront.net - international-valuation$5,329,561,500International Drive, the second proposed campus: six data centers of 568,103 square feet each, $5,329,561,500 of taxable value by Village staff (Plan Commission, Jan 21 2026). A Microsoft spokesperson confirmed the proposed expansion to WPR (Jan 20 2026) — 'These preliminary plans are the next step in our yearslong development process' — with no dollar figure; WPR's 'worth more than $13 billion' sums the two campuses' taxable values
“The total taxable value for the proposed development is $5,329,561,500, which would generate approximately $92,741,619 in incremental tax revenues while TID 5 remains open, and $30,769,391 in village revenues once TID 5 closes.”
Village of Mount Pleasant Plan Commission staff report, 2700 International Drive (Jan 21 2026) · d2kbkoa27fdvtw.cloudfront.net - durand-revaluation$6,095,690,000Durand Avenue's amended plan: seven one-story data center buildings in place of nine — larger ones; with the offices and guardhouse, the plan has over 5.8 million square feet of building space against just over 5.2 million in the approved plan (WPR, Oct 15 2026, and the Village's spokesperson) — which staff put at $6,095,690,000 of taxable value (Plan Commission, Oct 14 2026), down from $7,973,638,329, because 'planners are using a more conservative estimate now for what the possible future value of the buildings would be' (the Village's spokesperson to WPR); the Plan Commission approved the amended plan with conditions, and the Village Board was expected to vote on it later in October (WPR). Microsoft: 'The changes in no way reflect a reduction in our ambition'. With International Drive unchanged the two campuses would come to about $11.43B (our sum); the amendment postdates WEC's Sep 4 2026 deck and its '$13 billion - Additional'
“The staff estimate the total taxable value for the proposed development at $6,095,690,000, which would generate approximately $103,148,899 in incremental tax revenues while TID 5 remains open, and $33,546,541 in village revenues once TID 5 closes.”
Village of Mount Pleasant Plan Commission staff report, 12023 Durand Avenue (Oct 14 2026) · d2kbkoa27fdvtw.cloudfront.net - epoch-model$14Ba model, not a disclosure: Epoch AI's directory (updated Jul 25 2026) estimates the operating first facility (its 'Building 1') at 446k H100-equivalents, 369 MW of IT power and a $14.0B capital cost, from satellite imagery, company disclosures and regulatory filings. Its methodology page gives the cost model: a '$38B capital cost per gigawatt of IT power', most of it 'compute' (servers and network infrastructure) — 369 MW × $38B per GW ≈ $14.0B (our arithmetic) — so it counts the chips, where no Microsoft statement on file says whether its $3.3B does; the two are never one range. Epoch projects 4,528k H100e, 2,263 MW and $85.7B for Q2 2028 (build-out-power). The site's h100e, mw and capexB are this model
“It hosts an estimated 446k H100-equivalents of AI compute, supported by 369 MW of IT power at a capital cost of $14.0 B.”
Epoch AI Data Centers directory, Microsoft Fairwater Wisconsin (updated Jul 25 2026); Epoch's methodology page for the cost model · epoch.ai - fairwater-atlantaAtlanta, the second Fairwater site, with no site-wide figure from Microsoft: 'The new AI datacenter in Atlanta, which began operation in October, is the second in Microsoft's Fairwater family' (Nov 12 2025), with, by Microsoft's account, the same architecture and design as Wisconsin (SemiAnalysis notes that 'the cooling system is different'), Nvidia GB200 NVL72 rack-scale systems, and a dedicated network linking the sites — Scott Guthrie, the same day: 'connected to our first Fairwater site in Wisconsin'. So the second site was running some six months before the first started up (Apr 2026). No Microsoft statement on file gives a dollar figure, the site's MW or its GPU count — Guthrie's post gives only rack- and row-level power, and its racks 'can scale to hundreds of thousands of NVIDIA Blackwell GPUs' — and it is not Microsoft's own build: Epoch's directory has it 'Built by QTS with Microsoft as the tenant' (tier 2), and the financing analyses on file describe a QTS project company that owns the buildings and leases them to Microsoft (AFII, MNI). Its figures are Epoch's model, on the fairwateratl entity; its financing is a deal of its own
“The new AI datacenter in Atlanta, which began operation in October, is the second in Microsoft’s Fairwater family.”
Microsoft Source feature (Nov 12 2025) · news.microsoft.com
Contested figures 30 not reconciled — every position side by side, with its source and tier
Scope note what this record leaves to other records
NOT this record (not carried here, or routed): the power supply — We Energies' Very Large Customer tariff, Microsoft's payment-and-cancellation agreement for its 'first ~1,000MW of firm load', the Red Oak Ridge gas plant (its capacity differs between two utility filings), Microsoft's share of the Superior Solar project, ATC's Racine County Western Feed transmission line and the first facility's on-site substation, to be owned by We Energies and ATC, which a storm-water report in Microsoft's permit application, with Stantec's wetland maps, says 'is sized to support at least 752 MW' — a Microsoft–We Energies power deal, not yet a record of its own; Atlanta's financing — QTS Fayetteville I DC1-2's $4.6B of 5.700% senior secured notes due 2036 and the reported 20-year lease to Microsoft — not yet a record of its own; the Microsoft–OpenAI money loop, with OpenAI's share of Microsoft's commercial backlog → mo-partnership; Microsoft's company-wide capex → hyperscaler-capex; Microsoft's Kenosha site and Vantage's Port Washington campus — other sites. Disputed and not carried here: acreage beyond the 315-acre parcel carried here (one newsletter's 319 acres, the 200–215-acre building site of a bid notice and WPR; the second facility's parcel, 231 acres by a newsletter against the '115-acre site to the west' in the Village's account as WPR reported it (that those 115 acres are the second facility's parcel is our reading); Microsoft's holdings from 1,345 to more than 2,200 acres), building counts and floor area (counted in different units), construction start (from Aug 2023, by RCEDC's Nov 2023 fact sheet and Microsoft's counsel, Husch Blackwell, to 'in 2024', by the Village's TID report; Epoch dates land clearing to Jul 2023), jobs (nearly 550 on site vs 379 plus over 100; 2,300 union construction jobs expected 'by 2025' in 2024, more than 3,000 at peak since), the deadline for the next phase (2030 vs 2033) and what the Nov 2023 expansion agreement's $1.4B is (a minimum assessed value by 2028 in RCEDC's fact sheet and the Village's TID report; in the Village's 2026 budget, a 2023 developer's agreement 'calling for $1.4 billion of data centers to be constructed') — the amended agreement is on file only as a textless scan — Portage's community fund and economic-impact models, the Village's TID debt, Microsoft's company-wide capacity adds and contracted backlog, SemiAnalysis's belief that the $100B 'Stargate' cluster was meant for this campus, the scope of the $175M minimum that OpenAI says its partners will invest in Wisconsin (its post links that sentence to Vantage's Port Washington announcement), Epoch's cost per gigawatt ('$44B per gigawatt of server power' in the post introducing its hub, against the $38B per gigawatt of IT power behind the epoch-model figure), Atlanta's capacity (MNI's 'two 300+MW facilities'; in a newsletter, Cleanview's 350 MW and the newsletter's own 225 MW from generator counts, if three buildings were done ('not IT load!'); beside the Epoch model on fairwateratl), the QTS campus's acreage and building count, and Epoch's earlier 'upwards of $100B' and 'September 2027' vintages. Not disputed in the sources, and not carried: the campus's water use (Microsoft's own estimates, as the press relays them). Not adopted: a newsletter's 117MW and ~719MW are emergency-generator design ratings from the air permits, not IT load, and its 235MW divides the $3.3B by a generic $14 million per megawatt (a TD Cowen analyst's rate). Not corroboration: the $13.3B that a Microsoft-commissioned model says hyperscalers will spend with Wisconsin suppliers — Microsoft's, Meta's and Oracle and Vantage's sites together — only happens to match the expansion's taxable value.