Microsoft Fairwater, Mount Pleasant WI

Microsoft funds its Wisconsin Fairwater AI campus itself: $3.3B for a first data center, $4B for a second, 'more than $7 billion' in all; no Microsoft statement on file gives the utility's $20B+.

A record about Microsoft alone — no other party in it has a page here.

Why it matters

Microsoft is building Fairwater outright in Wisconsin, leaving few public figures for its cost. Microsoft's pledges total 'more than $7 billion' and do not say whether they cover GPUs. The utility's '$20+ billion' includes $13 billion that matches village tax-roll estimates, while Epoch's model puts the first facility's cost at $14.0B, including chips.

Mar 27, 2023 announced by Mount Pleasant, Racine County and development agenciesupdated Nov 20, 2026first facility declared fully operational disclosed by the parties

What happened

Microsoft is building its first 'Fairwater' AI data-center campus in Mount Pleasant, Wisconsin with its own money. It began buying the land from the village in 2023. The district was first assembled for Foxconn. Microsoft pledged $3.3 billion in May 2024. It says the first facility's equipment came online in April 2026 and declared the facility fully operational in June. Microsoft added $4 billion in September 2025 for a second facility of similar size, scheduled for 2028. That comes to 'more than $7 billion' by Microsoft's count. The local utility tells investors Microsoft announced over $20 billion. No Microsoft statement in the record says so. The extra $13 billion matches village staff's January estimates of what two more proposed campuses would add to the tax roll. Planners have since estimated a lower amount for one of them. For the site's power, Microsoft has given a 2-gigawatt goal. Through the press, it has put the first phase at 400–450 and said the site could reach 900 MW in a few years. Epoch AI's model puts the first facility's IT power, or power for computing equipment, at 369 MW. That is the highest of the point estimates, which start at 114 MW. Epoch AI's model puts the facility's cost at $14.0 billion, including chips. Epoch AI also says developer QTS built the second Fairwater site, near Atlanta, and rented it to Microsoft.

Sources 53 documents — 14 other documents · 12 company releases · 10 press reports · 7 research notes · 6 SEC filings · 3 government statements · 1 regulatory filing

Research trail Found 158 documents and read 154 of them while checking this deal and related ones.

  1. company releaseSep 18, 2025blogs.microsoft.com
    States 2 figures: $4B second pledge · 250 MW fossil matching
  2. Microsoft · company releaseSep 18, 2025blogs.microsoft.com
    States 2 figures: site · cluster
  3. company releaseJun 23, 2026news.microsoft.com
    States 2 figures: first facility complete · $4.7B local construction spend
  4. rcedc.org · other documentMar 2023rcedc.org
    States $1B first announcement
  5. mtpleasantwi.gov · government statementmtpleasantwi.gov
    States $50.085M land purchase
  6. company releaseMay 8, 2024news.microsoft.com
    States $3.3B first pledge
  7. WPR · press reportApr 2026wpr.org
    States $262.5M reported spend
  8. company releaseJun 2026local.microsoft.com
    States 1.45 GW carbon free contracted
  9. mtpleasantwi.gov · government statementmtpleasantwi.gov
    States $5M village incentive
  10. d2kbkoa27fdvtw.cloudfront.net · other documentd2kbkoa27fdvtw.cloudfront.net
    States $7,973,638,329 durand valuation
  11. d2kbkoa27fdvtw.cloudfront.net · other documentd2kbkoa27fdvtw.cloudfront.net
    States $5,329,561,500 international valuation
  12. d2kbkoa27fdvtw.cloudfront.net · other documentd2kbkoa27fdvtw.cloudfront.net
    States $6,095,690,000 durand revaluation
  13. company releasenews.microsoft.com
    States fairwater atlanta
  14. press reportwpr.org
    States phase two pause
  15. SEC · SEC filingsec.gov
    States $13B utility account
  16. research noteepoch.ai
    States $14B epoch model
  17. company releaseNov 12, 2025blogs.microsoft.com
    Cited by the record; no single figure is quoted from it.
  18. company releaselocal.microsoft.com
    Cited by the record; no single figure is quoted from it.
  19. company releasemicrosoft.com
    Cited by the record; no single figure is quoted from it.
  20. company releasemicrosoft.com
    Cited by the record; no single figure is quoted from it.
  21. other documentrcedc.org
    Cited by the record; no single figure is quoted from it.
  22. other documentrcedc.org
    Cited by the record; no single figure is quoted from it.
  23. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  24. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  25. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  26. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  27. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  28. press reportAug 14, 2026wpr.org
    Cited by the record; no single figure is quoted from it.
  29. press reportwpr.org
    Cited by the record; no single figure is quoted from it.
  30. other documenttmj4.com
    Cited by the record; no single figure is quoted from it.
  31. other documentJan 21, 2026spectrumnews1.com
    Cited by the record; no single figure is quoted from it.
  32. press reportwpr.org
    Cited by the record; no single figure is quoted from it.
  33. press reportApr 4, 2025insurancejournal.com
    Cited by the record; no single figure is quoted from it.
  34. press reportwpr.org
    Cited by the record; no single figure is quoted from it.
  35. press reportwpr.org
    Cited by the record; no single figure is quoted from it.
  36. press reportMar 2025wpr.org
    Cited by the record; no single figure is quoted from it.
  37. other documentfox6now.com
    Cited by the record; no single figure is quoted from it.
  38. other documentgeronimopower.com
    Cited by the record; no single figure is quoted from it.
  39. government statementapps.dnr.wi.gov
    Cited by the record; no single figure is quoted from it.
  40. other documentcrowncorr.com
    Cited by the record; no single figure is quoted from it.
  41. company releaseopenai.com
    Cited by the record; no single figure is quoted from it.
  42. company releaseopenai.com
    Cited by the record; no single figure is quoted from it.
  43. research noteepoch.ai
    Cited by the record; no single figure is quoted from it.
  44. research noteepoch.ai
    Cited by the record; no single figure is quoted from it.
  45. research noteepochai.substack.com
    Cited by the record; no single figure is quoted from it.
  46. research notenewsletter.semianalysis.com
    Cited by the record; no single figure is quoted from it.
  47. research notenewsletter.semianalysis.com
    Cited by the record; no single figure is quoted from it.
  48. other documentblog.synmax.com
    Cited by the record; no single figure is quoted from it.
  49. research notemeasuredai.substack.com
    Cited by the record; no single figure is quoted from it.
  50. regulatory filingcdn.misoenergy.org
    Cited by the record; no single figure is quoted from it.
  51. press reporttheguardian.com
    Cited by the record; no single figure is quoted from it.
  52. other documentanthropocenefii.org
    Cited by the record; no single figure is quoted from it.
  53. other documentmedia.marketnews.com
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: Microsoft: release (May 8 2024), On the Issues and Official Microsoft Blog (Sep 18 2025), Source feature and a second Official Microsoft Blog post (Nov 12 2025), release (Jun 23 2026), construction update (Mar 2026), Mount Pleasant boards (Jun 2026), FY26 Q1 and Q3 calls; Village of Mount Pleasant fact sheet (Mar 28 2023), Plan Commission staff reports (Jan 21 and Oct 14 2026) and news flash (Sep 28 2026); the Village's, County's and development agencies' releases on RCEDC's site (Mar 27 and May 31 2023); Legislative Fiscal Bureau (Mar 18 2026); WEC Energy Group FY2025 10-K, Q2-2026 and Q3-2026 10-Qs and investor decks (furnished); Wisconsin Electric's rebuttal testimony (Stasik) in PSC docket 6630-TE-113, attached to the PSC of Wisconsin's comments in FERC ER26-3265; Microsoft's air-permit application to the Wisconsin DNR (Sep 2024); OpenAI (Jan 20 and May 5 2026); Geronimo Power (Oct 1 2024); MISO's list of announced large loads (Dec 6 2024); Epoch AI; SemiAnalysis; SynMax; measuredai; WPR, FOX6, TMJ4, Spectrum News, Bloomberg via Insurance Journal, the Guardian; AFII and MNI on Atlanta's owner; Crown Corr (read 2026-10) · as of Oct 2026

The evidence 19 sourced figures · 9 disputes

The record's headline Microsoft Fairwater, Mount Pleasant WI: a self-funded AI campus — $3.3B pledged (May 2024) + $4B for a second facility, 'more than $7 billion' by Microsoft's count; first facility declared fully operational Jun 2026; the utility's '$20+ billion' adds a $13B that matches the Village's January taxable-value estimates for two proposed campuses; Atlanta, the second Fairwater site, has no dollar or figure from Microsoft in the record

Size
$3.3B + $4B pledged — 'more than $7 billion' by Microsoft's count · first facility declared fully operational Jun 2026, second scheduled by Microsoft for 2028 · the utility's '$20+ billion' is in no Microsoft statement in the record
When
Mar 27 2023 a $1B, 315-acre campus announced → May 31 2023 land purchase closed → May 8 2024 $3.3B pledge → Jan–Mar 2025 work on later phases paused → Sep 18 2025 +$4B for a second facility ('more than $7 billion') → Apr 2026 equipment online, by Microsoft's account → Jun 23 2026 declared fully operational → 2028 second facility (Microsoft's schedule)
Status
first facility declared fully operational (Jun 23 2026) · second under construction, scheduled by Microsoft for 2028 · site plans for two more campuses approved Jan 2026; an amendment to Durand Avenue's plan (seven larger buildings) approved by the Plan Commission Oct 14 2026, the Village Board's vote to follow
Structure
self-funded: Microsoft bought the first 315 acres from the Village for $50,085,000 in 2023, and more land since from the Village and private owners, and builds, owns and runs the facilities (the chips are Microsoft's by Epoch's account) — no venture, lease or project financing of Microsoft's for the Wisconsin campus appears in any document on file; the debt in the district is the Village's and the County's. Public support: the state's sales and use tax exemption for certified data centers (WEDC certified the project Oct 1 2023) and the Village's tax-increment incentive of up to $5M a year, which Microsoft redirected to the Village and RCEDC in Sep 2026. Power comes from We Energies, for which Microsoft says it is 'pre-paying for the energy and electrical infrastructure that we'll use'; the tariff, the plants built for its load and the transmission are a power deal of their own, not this record
Programme
Microsoft buildout
Parties
Microsoft owner, builder and operator — bought the land, pays for the buildings with its own money and runs the site; the chips are Microsoft's by Epoch's account; by its own account its AI datacenters power OpenAI, Microsoft AI, Copilot and other AI workloads, and the Fairwater sites its network links will work together to support them
Sites
MS Fairwater (Atlanta) · MS Fairwater (Wisconsin)
Record
disclosed / primary source · as of Oct 2026

Resolved figures 19 each with the verbatim line from its document

  • first-announcement$1B
    the day the campus became public: the Village of Mount Pleasant, Racine County, RCEDC, WEDC and Milwaukee 7 announced plans for Microsoft to buy a 315-acre parcel in the Village — 'The aim is to create a data center campus' — under a development agreement for 'a $1 billion, 315-acre data center campus' (Mar 27 2023). The Village's fact sheet of the next day gives both 'plans to invest $1 billion' and, among the development agreement's terms, a campus built 'at a cost of more than $1 billion' (land-purchase), and the Legislative Fiscal Bureau's table of the state's certified data centers lists $1,000,000,000 of planned expenditure for it (reported-spend). Every later pledge is for this campus and the land around it
    “The development agreement notes that Microsoft will develop a $1 billion, 315-acre data center campus.”
    Village of Mount Pleasant, Racine County, RCEDC, WEDC and Milwaukee 7 release (Mar 27 2023) · rcedc.org
  • land-purchase$50.085M
    the first site, bought outright: the Village agreed to sell Microsoft 'approximately 315 acres within TID 5 for $50,085,000' (fact sheet of Mar 28 2023, for the Mar 30 board vote), and the Village, Racine County, RCEDC, WEDC and Milwaukee 7 announced the closing of the 'approximately $50 million land purchase' on May 31 2023 (RCEDC's post). TID 5 is the tax-increment district assembled for Foxconn: Foxconn released its rights to the 315 acres and receives the proceeds, net of costs, 'as partial reimbursement of the funds Foxconn advanced in 2017 to acquire lands in TID 5'. The development agreement also let Microsoft recoup part of its property taxes (village-incentive). Microsoft has bought more land since; the figures on file for its holdings do not reconcile
    “An Agreement for Microsoft Corporation to purchase and the Village to sell approximately 315 acres within TID 5 for $50,085,000 by July 31, 2023.”
    Village of Mount Pleasant fact sheet (Mar 28 2023); the Village's, County's and agencies' release on RCEDC's site (May 31 2023) · mtpleasantwi.gov
  • first-pledge$3.3B
    $3.3B 'between now and the end of 2026' for a datacenter campus in Mount Pleasant (May 8 2024; the release says President Biden would join the announcement), beside an AI co-innovation lab and an AI-skilling program. It gives no MW or chip count for the datacenter, names no customer, and does not break the $3.3B into land, buildings and equipment. In Sep 2025 Microsoft said finishing its first datacenter would be 'fulfilling our initial $3.3 billion investment pledge'
    “First, Microsoft will invest $3.3B between now and the end of 2026 to expand its national cloud and AI infrastructure capacity through the development of a state-of-the-art datacenter campus in Mount Pleasant, Wisconsin.”
    Microsoft release (May 8 2024) · news.microsoft.com
  • phase-two-pause900
    the pause: in Jan 2025 Microsoft stopped early work on the next phase — 'We have paused early construction work for this second phase while we evaluate scope and recent changes in technology and consider how this might impact the design of our facilities', a spokesperson told WPR — restarted it, and by Mar 20 2025 had paused work on the 900-acre expansion site again, while the first phase stayed 'fully on track' and 'our $3.3 billion commitment remains intact'. The paused 900 acres lie 'just west of that site, as well as to the northwest along Durand Avenue' (WPR); by the Village's account as WPR reported it in Jan 2025, the paused work was construction 'inside the 115-acre site to the west' and earthwork 'in the 791 acres at Durand Avenue'. Microsoft's Sep 2024 air-permit application puts the second facility, MKE16/17, 'directly west of, and adjacent to' the first, and six data centers (MKE Area 2) on 'approximately 792 acres' south of Durand Avenue; matching the paused parcels to those plans is our reading — no document on file says which buildings the pause stopped. The $4B for a second facility came six months later (second-pledge)
    “Once again, Microsoft has paused work on a 900-acre portion of its Mount Pleasant data center campus.”
    WPR (Mar 20 2025, and Jan 2 2025, updated Jan 9, for the first pause and the Village's account of the parcels); Microsoft's air-permit application to the Wisconsin DNR (Sep 2024) for the plans · wpr.org
  • second-pledge$4B
    an additional $4B 'to be spent in the next three years to build our second datacenter of similar size and scale', taking Microsoft's own total in Wisconsin to 'more than $7 billion' (Sep 18 2025) — the $3.3B and the $4B, which WEC's decks write as '$7.3 billion – Phase 1 and 2' (program-total). The second facility, 'immediately adjacent to the first', was at foundations, steel erection and underground utilities in Jun 2026 (second-facility-timing)
    “And we’re not done. Today, we’re committing an additional $4 billion to be spent in the next three years to build our second datacenter of similar size and scale — bringing our total investment in Wisconsin to more than $7 billion.”
    Microsoft On the Issues, Brad Smith (Sep 18 2025) · blogs.microsoft.com
  • site315
    Microsoft's own description of the first campus: 315 acres — the parcel the Village sold it (land-purchase) — and 'three massive buildings' with 1.2 million square feet under roof (Sep 18 2025). Other sources count its buildings and floor area in other units; those counts are not carried here
    “The new Fairwater AI datacenter in Wisconsin stands as a remarkable feat of engineering, covering 315 acres and housing three massive buildings with a combined 1.2 million square feet under roofs.”
    Official Microsoft Blog, Scott Guthrie (Sep 18 2025) · blogs.microsoft.com
  • cluster
    what runs inside: 'a single, massive cluster of interconnected NVIDIA GB200 servers' — racks of 72 Nvidia Blackwell GPUs, each rack one NVLink domain, laid out over two stories so racks also connect to those above and below — fed by a separate storage and compute datacenter (Sep 18 2025). Microsoft's count is 'hundreds of thousands' of GPUs, with no number (first-facility-gpus)
    “This datacenter runs a single, massive cluster of interconnected NVIDIA GB200 servers and millions of compute cores and exabytes of storage, all engineered for the most demanding AI workloads.”
    Official Microsoft Blog, Scott Guthrie (Sep 18 2025) · blogs.microsoft.com
  • first-facility-complete2026
    done inside the pledge's window: construction complete and the facility 'now fully operational' on Jun 23 2026, after equipment came online with startup activities in April — within the end-2026 window of the $3.3B pledge; 2028 is the second facility's date, not the first's. Nadella had told investors on Apr 29 2026 that it 'came online earlier this month, six weeks ahead of schedule'; how much of it was serving workloads at each date is disputed (online)
    “Village of Mount Pleasant, Wis. — June 23, 2026 — Microsoft Corp. on Tuesday announced that it has completed construction of its first datacenter facility in the Village of Mount Pleasant, after bringing equipment online and conducting startup activities in April.”
    Microsoft release (Jun 23 2026) · news.microsoft.com
  • local-construction-spend$4.7B
    a third dollar figure, with its own scope: Microsoft's estimate of what it will have spent on construction locally in Wisconsin over 2024–2028, beside direct purchases from 29 businesses in 11 Wisconsin counties (Jun 23 2026). Microsoft does not say how it relates to the $3.3B and $4B pledges, so the record never sums it with them
    “Microsoft estimates that the company will have spent $4.7 billion between 2024 and 2028 locally on hyperscale construction in Wisconsin.”
    Microsoft release (Jun 23 2026) · news.microsoft.com
  • reported-spend$262.5M
    spending reported to the state: Microsoft reported $262.5M of expenditures to WEDC for 2024 under the state's data-center contract, which certified the Mount Pleasant project on Oct 1 2023 for Wisconsin's sales and use tax exemption on data-center purchases, with $1,000,000,000 of planned expenditure and a $150,000,000 minimum qualified investment (Legislative Fiscal Bureau memo, Mar 18 2026). The memo says these are expenditures incurred in 2024, that Microsoft, having met the minimum qualified investment, need not report after 2024, and that the sales tax forgone on them comes to an estimated $10.5M (Table 3); it does not say which costs they cover. Bloomberg put Microsoft's spending in the project's first six months at '$262 million on construction', from documents it did not name (via Insurance Journal, Apr 4 2025) — a near-match that the documents on file do not tie to the same report; Microsoft's Jun 2026 boards give '$700 million in spending on direct construction suppliers in Racine county'. The memo's 'committed $20.6 billion' is the contested program-total
    “In total, Microsoft has committed $20.6 billion to Wisconsin data center projects, well above the $1 billion planned investment under its contract with WEDC and above the $262.5 million in expenditures reported to WEDC for 2024.”
    Wisconsin Legislative Fiscal Bureau memo (Mar 18 2026) · wpr.org
  • fossil-matching250 MW
    matching, not supply: Microsoft says it 'will match every kilowatt hour we consume that comes from a fossil fuel source one for one with carbon-free energy we put back onto the grid', and that this includes 'a new 250 MW solar project in Portage County' then under construction (Sep 18 2025) — the project announced with National Grid Renewables on May 8 2024 to 'begin operating in 2027', whose power purchase agreement with Microsoft the developer, now Geronimo Power, announced on Oct 1 2024. Its output goes onto the regional grid; it is not a supply contract for the campus, which We Energies serves
    “This includes a new 250 MW solar project in Portage County that is under construction to support this commitment.”
    Microsoft On the Issues, Brad Smith (Sep 18 2025) · blogs.microsoft.com
  • carbon-free-contracted1.45 GW
    the matching book in Wisconsin, Jun 2026: 'We will match every kWh from fossil fuel with carbon-free energy on the regional grid. To deliver on that promise', 1.45 GW contracted — agreements with We Energies for 1.2 GW of new solar and battery projects online 'starting in December 2028', plus the 250 MW Portage PPA (Microsoft's Mount Pleasant boards). Capacity to be built on the grid, not power delivered to the campus
    “Microsoft has signed contracts that enable 1.45 GW of carbon free energy to be constructed in Wisconsin.”
    Microsoft Mount Pleasant community boards (Jun 2026) · local.microsoft.com
  • village-incentive$5M
    the local incentive, redirected: the 2023 development agreement let Microsoft 'recoup 42 percent of the annual incremental property taxes it pays on the improvements it builds, not to exceed $5 million per year', payments 'contingent on the Village having received sufficient Tax Increment Revenue to have first paid all other TID obligations' (fact sheet, Mar 28 2023); on Sep 28 2026 the Village announced that Microsoft was redirecting it — about $4.9M a year back to the Village, which plans to spend it on tax relief (a lower tax levy from 2027, and capital costs met without borrowing), and about $100,000 to RCEDC. The state's sales-tax exemption (reported-spend) is a separate benefit
    “Microsoft has made the decision to redirect its $5 million annual development incentive, paving the way for the Village of Mount Pleasant to advance immediate and long-term property tax relief.”
    Village of Mount Pleasant news flash (Sep 28 2026); fact sheet (Mar 28 2023) · mtpleasantwi.gov
  • utility-account$13B
    the utility's account, not Microsoft's: on the slide '2.6 GW of Demand Forecasted through 2030' of WEC Energy's Sep 4 2026 investor deck (8-K ex-99.1, furnished under Item 7.01; the utility's, not a party's, so tier 2), the Microsoft campus is 'Announced investment of $20+ billion', split '$7.3 billion – Phase 1 and 2' and '$13 billion - Additional', with 'Building 15 additional data centers beyond Phase 1 and 2' and 'Phase 1 operations commenced in April 2026'; its decks have carried the split since Feb 2026. No Microsoft page on file states $20B or $13B for Wisconsin: the $7.3B is the two pledges, and the $13B matches the Village staff's January taxable-value estimates for the two proposed campuses, $13.30B together (expansion-value)
    “Microsoft Data Center ▪ Announced investment of $20+ billion ▪ $7.3 billion – Phase 1 and 2 ▪ $13 billion - Additional ▪ Building 15 additional data centers beyond Phase 1 and 2”
    WEC Energy Group investor deck, 8-K ex-99.1 (Sep 4 2026; furnished, Item 7.01) · sec.gov
  • durand-valuation$7,973,638,329
    Durand Avenue, the larger of the two proposed campuses: an updated site plan (a preliminary one was approved in Aug 2024) with nine data centers of 579,796 square feet each, which Village staff put at $7,973,638,329 of taxable value (Plan Commission, Jan 21 2026) — what the finished campus would add to the tax roll, not what Microsoft would spend on it. With International Drive's $5,329,561,500 it makes $13.30B (our sum), which every '$13 billion' figure on file for the two campuses matches (expansion-value); an Oct 2026 amendment, approved by the Plan Commission with the Village Board's vote to follow, would replace the nine with seven larger buildings (durand-revaluation)
    “The total taxable value for the proposed development is $7,973,638,329, which would generate approximately $136,249,581 in incremental tax revenues while TID 5 remains open, and $45,204,264 in village revenues once TID 5 closes.”
    Village of Mount Pleasant Plan Commission staff report, 12023 Durand Avenue (Jan 21 2026) · d2kbkoa27fdvtw.cloudfront.net
  • international-valuation$5,329,561,500
    International Drive, the second proposed campus: six data centers of 568,103 square feet each, $5,329,561,500 of taxable value by Village staff (Plan Commission, Jan 21 2026). A Microsoft spokesperson confirmed the proposed expansion to WPR (Jan 20 2026) — 'These preliminary plans are the next step in our yearslong development process' — with no dollar figure; WPR's 'worth more than $13 billion' sums the two campuses' taxable values
    “The total taxable value for the proposed development is $5,329,561,500, which would generate approximately $92,741,619 in incremental tax revenues while TID 5 remains open, and $30,769,391 in village revenues once TID 5 closes.”
    Village of Mount Pleasant Plan Commission staff report, 2700 International Drive (Jan 21 2026) · d2kbkoa27fdvtw.cloudfront.net
  • durand-revaluation$6,095,690,000
    Durand Avenue's amended plan: seven one-story data center buildings in place of nine — larger ones; with the offices and guardhouse, the plan has over 5.8 million square feet of building space against just over 5.2 million in the approved plan (WPR, Oct 15 2026, and the Village's spokesperson) — which staff put at $6,095,690,000 of taxable value (Plan Commission, Oct 14 2026), down from $7,973,638,329, because 'planners are using a more conservative estimate now for what the possible future value of the buildings would be' (the Village's spokesperson to WPR); the Plan Commission approved the amended plan with conditions, and the Village Board was expected to vote on it later in October (WPR). Microsoft: 'The changes in no way reflect a reduction in our ambition'. With International Drive unchanged the two campuses would come to about $11.43B (our sum); the amendment postdates WEC's Sep 4 2026 deck and its '$13 billion - Additional'
    “The staff estimate the total taxable value for the proposed development at $6,095,690,000, which would generate approximately $103,148,899 in incremental tax revenues while TID 5 remains open, and $33,546,541 in village revenues once TID 5 closes.”
    Village of Mount Pleasant Plan Commission staff report, 12023 Durand Avenue (Oct 14 2026) · d2kbkoa27fdvtw.cloudfront.net
  • epoch-model$14B
    a model, not a disclosure: Epoch AI's directory (updated Jul 25 2026) estimates the operating first facility (its 'Building 1') at 446k H100-equivalents, 369 MW of IT power and a $14.0B capital cost, from satellite imagery, company disclosures and regulatory filings. Its methodology page gives the cost model: a '$38B capital cost per gigawatt of IT power', most of it 'compute' (servers and network infrastructure) — 369 MW × $38B per GW ≈ $14.0B (our arithmetic) — so it counts the chips, where no Microsoft statement on file says whether its $3.3B does; the two are never one range. Epoch projects 4,528k H100e, 2,263 MW and $85.7B for Q2 2028 (build-out-power). The site's h100e, mw and capexB are this model
    “It hosts an estimated 446k H100-equivalents of AI compute, supported by 369 MW of IT power at a capital cost of $14.0 B.”
    Epoch AI Data Centers directory, Microsoft Fairwater Wisconsin (updated Jul 25 2026); Epoch's methodology page for the cost model · epoch.ai
  • fairwater-atlanta
    Atlanta, the second Fairwater site, with no site-wide figure from Microsoft: 'The new AI datacenter in Atlanta, which began operation in October, is the second in Microsoft's Fairwater family' (Nov 12 2025), with, by Microsoft's account, the same architecture and design as Wisconsin (SemiAnalysis notes that 'the cooling system is different'), Nvidia GB200 NVL72 rack-scale systems, and a dedicated network linking the sites — Scott Guthrie, the same day: 'connected to our first Fairwater site in Wisconsin'. So the second site was running some six months before the first started up (Apr 2026). No Microsoft statement on file gives a dollar figure, the site's MW or its GPU count — Guthrie's post gives only rack- and row-level power, and its racks 'can scale to hundreds of thousands of NVIDIA Blackwell GPUs' — and it is not Microsoft's own build: Epoch's directory has it 'Built by QTS with Microsoft as the tenant' (tier 2), and the financing analyses on file describe a QTS project company that owns the buildings and leases them to Microsoft (AFII, MNI). Its figures are Epoch's model, on the fairwateratl entity; its financing is a deal of its own
    “The new AI datacenter in Atlanta, which began operation in October, is the second in Microsoft’s Fairwater family.”
    Microsoft Source feature (Nov 12 2025) · news.microsoft.com

Contested figures 30 not reconciled — every position side by side, with its source and tier

program-total2 positions, side by side
more than $7 billion — the most Microsoft has said it will invest in Wisconsin: 'bringing our total investment in Wisconsin to more than $7 billion' (Sep 18 2025), i.e. its $3.3B and $4B pledges; no Microsoft page on file gives a larger total Microsoft On the Issues (Sep 18 2025)
over $20 billion — the utility's account: 'Microsoft has announced plans to invest over $20 billion in data centers in southeastern Wisconsin over the next several years' (WEC Energy's filed 10-Qs for Q2 and Q3 2026, in the same words; 'southern Wisconsin' in its FY2025 10-K), on its decks 'Announced investment of $20+ billion' = $7.3B for Phase 1 and 2 + '$13 billion - Additional' (utility-account); the Legislative Fiscal Bureau: 'Microsoft has committed $20.6 billion' (Mar 18 2026). Filed by the utility, but no Microsoft announcement of $20B is on file, and its $13B leg matches the Village staff's January taxable-value estimates (expansion-value) — so tier 2 WEC Energy Group FY2025 10-K and Q2-2026 and Q3-2026 10-Qs (filed), decks (furnished); Legislative Fiscal Bureau memo (Mar 18 2026)
expansion-value2 positions, side by side
about $13 billion of investment — how the two proposed campuses are described: '$13 billion - Additional' (WEC's decks, Feb–Sep 2026), 'Total investment of $13.3 billion was announced for these projects' (Legislative Fiscal Bureau, Mar 18 2026), and Richard Stasik, WEC's vice president for regulatory affairs, in rebuttal testimony for Wisconsin Electric, received in February, in the PSC of Wisconsin's Very Large Customer tariff case, which the PSC attached to its FERC comments (Aug 14 2026): Microsoft 'recently confirmed it plans to construct two additional data center campuses in Mount Pleasant, which public reporting indicates will involve an additional $13 billion in investment', footnoted to a Racine County Eye story not on file. WPR's 'two new campuses worth more than $13 billion' (Jan 20 2026) says worth, not investment, and gives the two parts as taxable values. Microsoft's own confirmation of the expansion named no dollar figure, and the same day, in the Milwaukee Business Journal's account as excerpted on RCEDC's news page, a Microsoft spokesman 'declined to comment on the cost for the future phases, which he said are “still at an early stage in the development process.”' WEC decks (furnished); WPR; Legislative Fiscal Bureau memo; Milwaukee Business Journal as excerpted on RCEDC's news page (Jan 20 2026); Wisconsin Electric rebuttal testimony (Stasik), PSC docket 6630-TE-113 (received Feb 10 2026), attached to the PSC of Wisconsin's comments in FERC docket ER26-3265 (Aug 14 2026)
$13.30B of estimated taxable value, about $11.43B on the amended plan before the Village Board — Village staff's estimates for the two proposed campuses at the Jan 21 2026 Plan Commission, $7,973,638,329 for Durand Avenue and $5,329,561,500 for International Drive (durand-valuation, international-valuation; the sum is ours), which every '$13 billion' in the other position matches; TMJ4 and Spectrum News call the figure taxable value, and WPR gives its two parts as taxable values, while WEC (its decks, and its witness, who cites 'public reporting') and the Legislative Fiscal Bureau give no derivation. On Durand's Oct 2026 amendment, which would put seven larger buildings in place of nine, valued on 'a more conservative estimate' ($6,095,690,000, durand-revaluation), the pair would come to about $11.43B (our sum). An estimate of what the finished campuses would add to the tax roll — a different measure from what Microsoft will spend on them, which it has not said Village of Mount Pleasant Plan Commission staff reports (Jan 21 and Oct 14 2026); WPR, TMJ4, Spectrum News (Jan and Oct 2026)
phase1-grid-demand2 positions, side by side
450 MW — 'A spokesperson for Microsoft said the company anticipates the first phase of its Mount Pleasant project will require 450 megawatts' (WPR, Feb 3 2025); a witness for the Citizens Utility Board repeated it in testimony before the PSC (docket 6630-CE-317), citing the Milwaukee Journal Sentinel, and found it 'consistent with WEPCO's forecast for Microsoft load' up to a date the public copy leaves blank, after which, the witness testified, that forecast rises further for the site's future phases WPR (Feb 3 2025); CUB testimony, PSC docket 6630-CE-317
400 MW at most — 'Microsoft says the maximum electricity needs for Phase 1 opening next year is 400 megawatts', and its needs 'in a few years might be 900 megawatts' (FOX6, Sep 18 2025). Both figures reach the record from Microsoft through the press; no filing among the documents read states the first phase's load on its own authority — the utility's forecast for Microsoft, which CUB's witness checked the spokesperson's figure against, is blank in the public testimony — and neither figure says what boundary it measures FOX6 Milwaukee (Sep 18 2025)
first-facility-it5 positions, side by side
337.6 MW — a bid notice for the 'MKE03 Data Center, MKE04 Data Center, Administration Building (ADMIN), and Central Utility Plant (CUP) Building', which 'will comprise of a 337.6MW Data Center' on the first campus's land (posted on RCEDC's Microsoft page on Dec 19 2023; the notice itself is not on file) — it does not say whether that is IT or total power, and it covers the administration and utility buildings too RCEDC, 'Microsoft in Racine County' page (bid notice, posted Dec 19 2023)
about 343–348 MW — SemiAnalysis: each Fairwater pairs 'a standard CPU & storage facility of 48MW' with a GPU building that 'boasts ~300MW' (Nov 12 2025); its Feb 2026 piece puts the GPU cluster at 295MW (the sums are ours) — neither piece labels these figures IT or facility power, though the November piece gives the campus's full build-out as IT capacity (build-out-power) SemiAnalysis (Nov 12 2025; Feb 9 2026)
369 MW of IT power — Epoch AI's model of the operating first facility (epoch-model), its range on the fairwaterwi pageEpoch AI, data_center_timelines.csv, "Microsoft Fairwater Wisconsin" — 2026-04-16: Buildings operational 1.0; IT power (MW) 369.0; Power (MW) 442.0 Epoch AI directory (Jul 25 2026); data_center_timelines.csv, snapshot 2026-11-19 · epoch.ai
114 MW — SynMax heads its post on an Aug 20 2026 thermal drone pass 'MKE04 72 MW and MKE03 42 MW (114 MW first facility; campus building out)' without deriving the figures, which its table lists as each hall's 'Capacity' beside status and dates it credits to IIR Energy, while the pass itself reads MKE04's cooling array as 'running under partial or ramping load, not full output across every bank' SynMax (drone flight Aug 20 2026)
about 300 MW built — the Guardian (Aug 17 2026), in a paragraph that opens 'This is very common, said Ren' (Shaolei Ren, a professor at the University of California, Riverside) and uses no quotation marks: 'Three years later, only 300MW has been built', of the Wisconsin project as the article frames it, with no derivation. None of these five is a measured load The Guardian, Aisha Down and Ed Zitron (Aug 17 2026)
first-facility-gpus3 positions, side by side
no number from Microsoft — 'hundreds of thousands of the world’s most powerful NVIDIA GPUs' for its Mount Pleasant facility (Sep 18 2025), in racks of 72 (cluster) Microsoft On the Issues + Official Microsoft Blog (Sep 18 2025)
over 150,000 GB200 — SemiAnalysis: the ~300MW GPU building 'represents over 150k GB200 GPUs per building' (Nov 12 2025), from its datacenter model SemiAnalysis (Nov 12 2025)
176.4k B200 — Epoch's model of the operating first facility (446k H100-equivalents), 352.8k once the second facility runs (Q1 2027 in its table)Epoch AI, data_center_chip_quantities.csv, "Microsoft Fairwater Wisconsin" — 2026-04-16: B200, 176391 units (Estimate) — 2027-02-20: B200, 352782 units (Estimate). data_center_timelines.csv, 2026-04-16: H100 equivalents 445679.63617988885 Epoch AI directory (Jul 25 2026); data_center_chip_quantities.csv and data_center_timelines.csv, snapshot 2026-11-19 · epoch.ai
build-out-power6 positions, side by side
2 GW — Nadella: 'Fairwater in Wisconsin, which will go online next year and scale to two gigawatts alone' (FY26 Q1 call, Oct 29 2025); it does not say IT or facility power, or by when Microsoft FY26 Q1 earnings call (Oct 29 2025)
over 2 GW of IT — SemiAnalysis: 'At full buildout, this will be one of the world’s largest campuses, with over 2GW of IT capacity' (Nov 12 2025) SemiAnalysis (Nov 12 2025)
2,263 MW of IT by Q2 2028 — Epoch's projection, with 'Buildings 3-11' operational on May 13 2028 on a nine-building plan whose grading it saw in May 2026, before Durand Avenue's Oct 2026 amendment to seven, still before the Village Board (durand-revaluation); its Buildings 1–11 are the two facilities and that plan, so the six-building plan it lists among its sources is not among them. Microsoft's own June boards plan only the first four of that campus's buildings for completion, late in the year of Epoch's projection, with further phases to follow, and say completion 'does not indicate datacenter operation/availability'Epoch AI, data_center_timelines.csv, "Microsoft Fairwater Wisconsin" — 2028-05-13: Construction status "Buildings 3-11 are estimated to be operational."; Buildings operational 11.0; IT power (MW) 2263.0 Epoch AI directory (Jul 25 2026); data_center_timelines.csv, snapshot 2026-11-19 · epoch.ai
around 3 GW in 2027 — Epoch's earlier vintage of the same model: 'That one is reaching around three gigawatts in 2027', for 'around 5 million H100 equivalent GPUs' (webinar recorded Nov 20 2025) Epoch AI webinar (recorded Nov 20 2025)
2.6 GW of grid power for one proposed campus — measuredai (Jul 22 2026), on Durand Avenue ('Campus 3' in its numbering of four): 'Campus 3’s two planned substations — named Jupiter and Cosmos — at no less than 1.2 GW per substation, against a stated Campus 3 target of 2.6 GW of grid power to the data center buildings', credited to 'Microsoft’s own filings', which it does not name. A grid-power target for one campus, not the site's whole build-out measuredai (Jul 22 2026)
1.5 GW, at least mid-2027 — SemiAnalysis, in its passage on the Wisconsin campus: 'We also believe Microsoft poorly planned the 1.5GW expansion. Full capacity is slated for at least mid-2027 delivery from a power transmission standpoint' (Nov 12 2025). It does not say which buildings the 1.5GW covers, or whether it is IT or facility power SemiAnalysis (Nov 12 2025)
second-facility-timing4 positions, side by side
2028 — Microsoft: the second facility, 'immediately adjacent to the first', 'is scheduled to be completed in 2028' (Jun 23 2026). Its finer dates: its March 2026 construction update says of Phase 2 ('KR & H'), 'This phase is scheduled to be completed in early 2028'; its June boards say 'Buildings one (1) through three (3) are planned for completion mid 2028' in the 'Estimated timeline for Area 3A' — that Area 3A is the second facility is our reading, as the boards put Area 3A in the 'construction phase' and Area 3B in the 'operation phase'. The boards add that a 'Construction completion date does not indicate datacenter operation/availability' Microsoft release (Jun 23 2026); Microsoft's construction update (Mar 2026) and Mount Pleasant boards (Jun 2026)
Feb 20 2027 — Epoch projects 'Building 2 is operational' then, from the gap between the two buildings' land clearing, a Microsoft spokesperson's 'fully on track' for the first phase (Mar 2025), on a Microsoft schedule where 'southern datacenter buildings complete, and preparation begins for operations' was expected by late 2026, and the 1,480 MW of load a MISO list gives Microsoft in Mount Pleasant, with a planned date of 2026 — which Epoch describes as what 'MISO was planning' and itself calls 'not 100% consistent' with its estimates. The list itself says its data are 'from public announcements and publicly available information', that it 'is not a forecasting document for MISO', and that 'Timing for full load is to be determined'Epoch AI, data_center_timelines.csv, "Microsoft Fairwater Wisconsin" — 2027-02-20: Construction status "Building 2 is operational."; Buildings operational 2.0; IT power (MW) 737.0 Epoch AI directory (Jul 25 2026; data_center_timelines.csv, snapshot 2026-11-19); MISO's list of announced large loads (updated Dec 6 2024) · epoch.ai
Q4 2026 — a cladding subcontractor's page for the 'MKE 16/17 Data Center Project' (owner 'Microsoft Corporation') says 'Completed 4th Quarter of 2026' beside its scope, '170,000 SF of Insulated Metal Wall Panels'; it does not say whether the date is its panels' or the project's. MKE16/17 is the second facility: Microsoft's Sep 2024 air-permit application puts it 'directly west of, and adjacent to' the first Crown Corr project page; Microsoft's construction permit application to the Wisconsin DNR (MKE Area 2, Sep 2024, prepared by Stantec)
Dec 31 2027 — IIR Energy, as SynMax relays it: 'IIR Energy lists it as Planned with a reported start of December 31, 2027', of MKE16, whose shell SynMax's own drone pass of Aug 20 2026 saw under construction. Neither says whether that start is construction's end or operation's SynMax (drone flight Aug 20 2026), crediting IIR Energy
online2 positions, side by side
online in April 2026 — 'Our Fairwater datacenter in Wisconsin came online earlier this month, six weeks ahead of schedule, allowing us to recognize revenue earlier' (Nadella, Apr 29 2026); WEC's filed Q2-2026 and Q3-2026 10-Qs, in the same words: 'The first phase of the project went into service in April 2026'; Microsoft's Jun 23 release: equipment online and startup in April, 'now fully operational' (first-facility-complete) Microsoft FY26 Q3 earnings call (Apr 29 2026); WEC Energy Group Q2-2026 and Q3-2026 10-Qs; Microsoft release (Jun 23 2026)
not yet online in May, or only in part — 'In May, Microsoft admitted to a Wisconsin newspaper that Fairwater was not yet online' (the Guardian, Aug 17 2026, which names the paper only in its link, to a Milwaukee Journal Sentinel story not on file), just after saying that Epoch's satellite footage 'appears to indicate only part of it is operational' — though Epoch's own directory marks the first facility operational from a Microsoft post on X in April. Ed Zitron's own newsletter, relaying the same paper's story, has Microsoft expecting start-up activity to continue 'for the next several weeks', and Microsoft's June boards say its 'first parcel is moving into operation'; a newsletter, measuredai, reports that 'Campus 1 received its conditional certificate of occupancy on May 26, 2026' (Jul 22 2026). The documents on file do not show how much of the first facility was serving workloads at each date The Guardian, Aisha Down and Ed Zitron (Aug 17 2026); Epoch AI directory; Ed Zitron's newsletter (May 12 2026); Microsoft's Mount Pleasant boards (Jun 2026); measuredai (Jul 22 2026)
who-uses-it4 positions, side by side
OpenAI alongside Microsoft's own workloads — Microsoft: the network linking its Fairwater sites 'will connect multiple sites' with GPUs, storage and CPU cores 'which all work together to support OpenAI, the Microsoft AI Superintelligence Team, Copilot capabilities and other leading AI workloads' (Nov 12 2025); and, in its post on the Wisconsin site, 'Microsoft's AI datacenters power OpenAI, Microsoft AI, our Copilot capabilities and many more leading AI workloads' Microsoft Source feature (Nov 12 2025); Official Microsoft Blog, Scott Guthrie (Sep 18 2025)
OpenAI, in its own words — Mount Pleasant is 'our latest AI campus with Microsoft', listed among 'all of our Stargate AI campuses' (Jan 20 2026), and OpenAI trains frontier models on GB200 supercomputers including 'in Microsoft’s Fairwater supercomputers' (May 5 2026). No Microsoft page on file calls the site Stargate OpenAI (Jan 20 and May 5 2026)
all OpenAI — SemiAnalysis: 'We show below the Wisconsin facility – fully dedicated to OpenAI' (Nov 12 2025), from its datacenter model; a newsletter, measuredai, states it as fact ('The GPU building is fully dedicated to OpenAI'), and Ed Zitron's newsletter writes that Microsoft's Fairwater data centers 'are entirely reserved for OpenAI', which it says it has confirmed SemiAnalysis (Nov 12 2025); measuredai; Ed Zitron's newsletter (May 6 2026)
OpenAI and Microsoft — Epoch: 'AI chips owned by Microsoft and likely used by OpenAI and Microsoft' (Jul 25 2026)Epoch AI, data_centers.csv, "Microsoft Fairwater Wisconsin" — Owner Microsoft #confident; Users OpenAI #likely, Microsoft #likely Epoch AI directory (Jul 25 2026); data_centers.csv, snapshot 2026-11-19 · epoch.ai

Scope note what this record leaves to other records

NOT this record (not carried here, or routed): the power supply — We Energies' Very Large Customer tariff, Microsoft's payment-and-cancellation agreement for its 'first ~1,000MW of firm load', the Red Oak Ridge gas plant (its capacity differs between two utility filings), Microsoft's share of the Superior Solar project, ATC's Racine County Western Feed transmission line and the first facility's on-site substation, to be owned by We Energies and ATC, which a storm-water report in Microsoft's permit application, with Stantec's wetland maps, says 'is sized to support at least 752 MW' — a Microsoft–We Energies power deal, not yet a record of its own; Atlanta's financing — QTS Fayetteville I DC1-2's $4.6B of 5.700% senior secured notes due 2036 and the reported 20-year lease to Microsoft — not yet a record of its own; the Microsoft–OpenAI money loop, with OpenAI's share of Microsoft's commercial backlog → mo-partnership; Microsoft's company-wide capex → hyperscaler-capex; Microsoft's Kenosha site and Vantage's Port Washington campus — other sites. Disputed and not carried here: acreage beyond the 315-acre parcel carried here (one newsletter's 319 acres, the 200–215-acre building site of a bid notice and WPR; the second facility's parcel, 231 acres by a newsletter against the '115-acre site to the west' in the Village's account as WPR reported it (that those 115 acres are the second facility's parcel is our reading); Microsoft's holdings from 1,345 to more than 2,200 acres), building counts and floor area (counted in different units), construction start (from Aug 2023, by RCEDC's Nov 2023 fact sheet and Microsoft's counsel, Husch Blackwell, to 'in 2024', by the Village's TID report; Epoch dates land clearing to Jul 2023), jobs (nearly 550 on site vs 379 plus over 100; 2,300 union construction jobs expected 'by 2025' in 2024, more than 3,000 at peak since), the deadline for the next phase (2030 vs 2033) and what the Nov 2023 expansion agreement's $1.4B is (a minimum assessed value by 2028 in RCEDC's fact sheet and the Village's TID report; in the Village's 2026 budget, a 2023 developer's agreement 'calling for $1.4 billion of data centers to be constructed') — the amended agreement is on file only as a textless scan — Portage's community fund and economic-impact models, the Village's TID debt, Microsoft's company-wide capacity adds and contracted backlog, SemiAnalysis's belief that the $100B 'Stargate' cluster was meant for this campus, the scope of the $175M minimum that OpenAI says its partners will invest in Wisconsin (its post links that sentence to Vantage's Port Washington announcement), Epoch's cost per gigawatt ('$44B per gigawatt of server power' in the post introducing its hub, against the $38B per gigawatt of IT power behind the epoch-model figure), Atlanta's capacity (MNI's 'two 300+MW facilities'; in a newsletter, Cleanview's 350 MW and the newsletter's own 225 MW from generator counts, if three buildings were done ('not IT load!'); beside the Epoch model on fairwateratl), the QTS campus's acreage and building count, and Epoch's earlier 'upwards of $100B' and 'September 2027' vintages. Not disputed in the sources, and not carried: the campus's water use (Microsoft's own estimates, as the press relays them). Not adopted: a newsletter's 117MW and ~719MW are emergency-generator design ratings from the air permits, not IT load, and its 235MW divides the $3.3B by a generic $14 million per megawatt (a TD Cowen analyst's rate). Not corroboration: the $13.3B that a Microsoft-commissioned model says hyperscalers will spend with Wisconsin suppliers — Microsoft's, Meta's and Oracle and Vantage's sites together — only happens to match the expansion's taxable value.