Fermi–TensorWave, Project Matador

Fermi signed to build TensorWave a 222 Texas data center and lease it for 15 years at about $6.5B by Fermi's estimate. The lease ended without taking effect, so no rent was owed.

A deal between Fermi America, TensorWave, AMD

Why it matters

Fermi's lease with TensorWave never took effect despite AMD's offer to back the rent once the building was finished and rent began. Fermi called the signed lease 'binding', but closing conditions went unmet and the lease was terminated. The stated $6.5B never became revenue.

Tap a figure for the line in its source.

Fermi America gives TensorWave

  • a data center at Project Matador, Texas, that Fermi would build and run, leased for 15 years from its last phase — signed Aug 9 2026, never delivered
  • disputedin all if TensorWave took up its option on two more buildings — 'a total of' in Fermi's 10-Q, 'more than' in its release, 'the ceiling' in a TensorWave-side post

TensorWave gives Fermi America

  • of rent and charges over the 15 years, by Fermi's estimate — never owed: the lease was terminated before it took effect

AMD gives Fermi America

  • credit support behind TensorWave's rent, announced Oct 13 2026, to start only once the building was finished and rent began; its amount never disclosed, and terminated with the lease

Aug 10, 2026 announced by Fermiterminated Nov 10 2026, never effective disclosed by the parties

What happened

Fermi signed its first tenant, TensorWave, in August 2026. Fermi is building Project Matador, a private power and data-center campus in the Texas Panhandle. TensorWave is a cloud provider that rents out AMD chips. It agreed to lease a 222-megawatt data center for 15 years. Fermi estimated the lease was worth about $6.5 billion to it. The lease would take effect only after board approvals, guarantees and project-level financing to pay for construction. Fermi sought a backer with an investment-grade credit rating to support the rent payments. On October 13, Fermi announced that AMD had signed on. AMD is one of TensorWave's investors, and TensorWave runs only AMD chips. AMD's support would start only once the building was finished and rent began. The closing date moved from September 30 to October 31. The closing conditions were still unmet at the new deadline. On November 10, the lease and AMD's support ended. Fermi has called it a complex deal that needed a third party's credit. It has yet to say which side ended it or which condition went unmet. No rent was ever owed, and the $6.5 billion never became revenue.

Sources 18 documents — 9 SEC filings · 4 company releases · 2 transcripts · 2 social posts · 1 other document

Research trail Found 188 documents and read 172 of them while checking this deal and related ones.

  1. SEC · SEC filingsec.gov
    States 6 figures: 222 MW facility power · lease term · $6.5B contracted revenue · structure · guaranties · closing conditions
  2. SEC · SEC filingsec.gov
    States 2 figures: 156 MW critical IT · 2.5% escalator
  3. SEC · SEC filingsec.gov
    States 2 figures: termination · 200 MW ttu condition
  4. Newswire · company releasenewswire.com
    States 2 figures: closing extended · tenant amd ties
  5. Newswire · company releasenewswire.com
    States 2 figures: 222 MW amd credit support · 650 MW amd expansion framework
  6. SEC · SEC filingsec.gov
    States amd support terminated
  7. company releaseinvestor.fermiamerica.com
    Cited by the record; no single figure is quoted from it.
  8. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  9. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  10. company release (archived copy)accessnewswire.com
    Cited by the record; no single figure is quoted from it.
  11. other documentirp.cdn-website.com
    Cited by the record; no single figure is quoted from it.
  12. transcriptNov 12, 2026fool.com
    Cited by the record; no single figure is quoted from it.
  13. transcriptAug 20, 2026fool.com
    Cited by the record; no single figure is quoted from it.
  14. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  15. social postlinkedin.com
    Cited by the record; no single figure is quoted from it.
  16. social postlinkedin.com
    Cited by the record; no single figure is quoted from it.
  17. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  18. SEC filingdata.sec.gov
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: Fermi Q2 2026 10-Q (filed Aug 14) + Q3 2026 10-Q (filed Nov 12) + DEF 14A (Oct 2); Fermi releases of Aug 10, Sep 22, Oct 13 and Nov 3 2026, the Oct 14 TensorWave fact sheet (8-K Item 7.01, furnished) and the Nov 12 earnings release (furnished); Q2 and Q3 call transcripts · as of Nov 2026

The evidence 15 sourced figures · 6 disputes

The record's headline Fermi–TensorWave, Project Matador: a 222 , 15-year, ~$6.5B turnkey lease with AMD credit support behind the rent — signed Aug 9 2026, never closed, terminated Nov 10 2026

Size
222 MW · ~$6.5B over 15 years (Fermi's estimate) — terminated before it took effect
When
Aug–Nov 2026 — signed Aug 9 → AMD credit support announced Oct 13 → closing date passed Oct 31 → terminated Nov 10
Status
terminated Nov 10 2026, never effective — signed Aug 9 2026; closing moved from Sep 30 to Oct 31 (First Amendment, Sep 22) and made extendable to Dec 31 (amended and restated Oct 9), then passed Oct 31 without extension; AMD's credit support, announced Oct 13, terminated with it
Structure
build-to-suit, modified net (turnkey) lease from Fermi Campus 1 LLC to TensorWave TEX1, LLC: 15-year initial term from the final delivery phase, two 5-year renewals, an option on two more buildings; the tenant's obligations guaranteed by TensorWave Inc.; Fermi guaranteeing its landlord's obligations and completion; AMD credit support for the rent (from rent start on the final phase, ending early after 12 consecutive months of investment-grade rating, per the furnished fact sheet — see credit-support-window); effective only at closing (Board approvals, work letters and guaranties, an operations schedule and service-level agreement, project-level financing)
Programme
Fermi–TensorWave
Parties
Fermi America landlord, through Fermi Campus 1 LLC: would design, build, own and operate the data center and the power behind it; guarantor of its subsidiary's obligations and of completion · TensorWave tenant, through TensorWave TEX1, LLC — an all-AMD GPU cloud; TensorWave Inc. guaranteed its subsidiary's obligations · AMD credit support for the tenant's rent (announced Oct 13 2026, terminated with the lease) — and maker of the only GPUs TensorWave runs, and one of its investors (AMD Ventures)
Capital
the seller's own money or backing comes back as its sales
Record
disclosed / primary source · as of Nov 2026

Resolved figures 15 each with the verbatim line from its document

  • facility-power222 MW
    222 MW of total facility power for the first phase, measured 'following commencement of the final delivery phase' — the figure every Fermi document uses (the Oct 13 release says '222 megawatts (MW) of gross power capacity'). Not the data halls' computing load (critical-it). The lease itself was never filed, and TensorWave, a private company, files nothing
    “The TensorWave Lease represents the Company’s first customer lease at its Project Matador campus and provides for a build-to-suit data center facility that the Landlord will develop, construct, deliver, and operate, and that will be supported by 222 MW of total facility power following commencement of the final delivery phase.”
    Fermi Q2 2026 10-Q, Note 9 Subsequent Events (filed Aug 14 2026) · sec.gov
  • critical-it156 MW
    156 MW of critical IT capacity — the computing load itself, inside the 222 MW of total power. Stated only in the fact sheet Fermi furnished with its Oct 14 8-K under Item 7.01, which the 8-K says 'shall not be deemed “filed”'
    “222 MW Phase one total power capacity 156 MW Critical IT capacity”
    Fermi TensorWave fact sheet, Oct 14 2026 (Ex. 99.1 to 8-K Item 7.01, furnished) · sec.gov
  • lease-term15
    a 15-year initial term that starts only when the LAST delivery phase commences, plus two 5-year renewal options — so the term, and the $6.5B, would have run from early 2028 at the soonest on Fermi's schedules (delivery-schedule)
    “The TensorWave Lease has an initial term of 15 years following commencement of the final delivery phase, with two renewal options of five years each, and is expected to generate approximately $6.5 billion in total contracted revenue over the initial term, excluding any renewal terms or the exercise of the expansion option.”
    Fermi Q2 2026 10-Q, Note 9 Subsequent Events (filed Aug 14 2026) · sec.gov
  • contracted-revenue$6.5B
    ~$6.5B over the 15-year initial term — Fermi's own estimate of what the lease would bring it ('expects to receive'), renewals and the expansion option excluded; the Aug 10 release: 'for the first phase'. No rent schedule, rate per MW or split between rent and power charges was ever disclosed. Every repetition — TensorWave's counsel Foley (Aug 12), TensorWave's posts, the press — traces to Fermi's figure. None of it became owed: the lease never took effect and was terminated (termination), and the Q3 10-Q says the termination 'had no effect' on its financial statements
    “The Lease is a modified net lease under which the Company expects to receive approximately $6.5 billion in contracted revenue over its initial 15-year term, excluding the exercise of any renewals or the expansion option.”
    Fermi Q2 2026 10-Q, MD&A — TensorWave Lease Overview (filed Aug 14 2026) · sec.gov
  • escalator2.5%
    rent rising 2.5% a year — stated only in the furnished fact sheet; neither 10-Q gives an escalator for this lease
    “Term: 15 - year initial term with two 5 - year renewal options; 2.5% annual escalators”
    Fermi TensorWave fact sheet, Oct 14 2026 (Ex. 99.1 to 8-K Item 7.01, furnished) · sec.gov
  • structure
    a build-to-suit, turnkey lease: Fermi's subsidiary would design, build, own and operate the data center and the power behind it, and TensorWave would pay rent plus fixed and variable power charges and some taxes. The fact sheet (furnished) adds Fermi's own projections for the phase: a project-level NOI margin of 'approximately 75% - 80%', with natural gas and variable power passed through, and build costs of '$3 - 4M per MW of total power capacity' for power and '$10 - 12M per MW of critical IT capacity' for the data center — estimates, never tested by a build
    “The TensorWave Lease is a modified net lease under which TensorWave is also responsible, as additional rent, for fixed and variable power charges and certain taxes.”
    Fermi Q2 2026 10-Q, Note 9 Subsequent Events (filed Aug 14 2026) · sec.gov
  • guaranties
    three layers of support as signed in August: TensorWave Inc. guaranteed its subsidiary's obligations, unconditionally; Fermi guaranteed its own landlord subsidiary's obligations and gave a completion guaranty for the build; and a third guarantee, of the rent, was still being negotiated with 'a global leader in AI infrastructure' — named as AMD on Oct 13 (amd-credit-support)
    “The Lease provides that the Tenant’s obligations under the Lease are to be guaranteed by TensorWave Inc., the Tenant’s parent, pursuant to an unconditional guaranty that includes financial-reporting and change-of-control covenants. The Company is in the process of negotiating a guarantee of the Tenant’s rent obligations with a global leader in AI infrastructure.”
    Fermi Q2 2026 10-Q, MD&A — TensorWave Lease Overview (filed Aug 14 2026) · sec.gov
  • closing-conditions
    signed Aug 9 2026 but not in force until a closing: Board approvals and project-level financing among the conditions, and either party free to terminate if they were not met. Fermi's Sep 22 release lists them in full: 'executing and delivering related work letters and guaranties; finalizing operations schedules and a service-level agreement; obtaining Board approvals; and securing project-level financing sufficient to fund construction of the leased premises'. Fermi's proxy statement (DEF 14A, Oct 2 2026, filed) names among its risks 'our ability to consummate the transactions under our lease with TensorWave, and to obtain adequate credit support for our obligations thereunder'
    “The effectiveness of the TensorWave Lease is subject to the satisfaction or waiver of customary closing conditions, including Board approvals and the Landlord obtaining project-level financing, at a closing expected to occur on or before September 30, 2026 (subject to extension), and either party may terminate the TensorWave Lease if those conditions are not satisfied.”
    Fermi Q2 2026 10-Q, Note 9 Subsequent Events (filed Aug 14 2026) · sec.gov
  • closing-extended
    First Amendment, Sep 22 2026: closing moved from Sep 30 to Oct 31, 'to allow more time to finalize that guaranty and complete the remaining closing conditions' — the rent guaranty with 'an investment-grade counterparty' still under negotiation. Fermi's Q3 10-Q (filed) records the amendment, and that on Oct 9 the parties 'amended and restated the TensorWave Lease to, among other things, provide that the parties may extend the October 31, 2026 closing date to no later than December 31, 2026' — an extension they did not take
    “The amendment extends the closing date under the Lease from September 30, 2026 to October 31, 2026.”
    Fermi release, Sep 22 2026 (Newswire) · newswire.com
  • amd-credit-support222 MW
    AMD signed a credit support agreement behind the phase-one lease — announced Oct 13 2026, after Fermi's Sep 22 release still had the guaranty under negotiation; 'Signed' in the Oct 14 fact sheet, which adds AMD's ratings ('A/stable S&P, A1/stable Moody’s') and that it 'supports project financing'; Fermi's release calls it 'a key milestone toward securing project financing'. Its amount, form and any fee were never disclosed and the agreement was never filed. AMD's only words on it are its strategy chief's quote in Fermi's release; AMD's own Q3 10-Q (filed Nov 4) names neither Fermi nor TensorWave, and its $8.5B of guarantees for 'certain commercial partners' is dated Sep 26 2026, before this agreement was signed. When the support would start and end is contested (credit-support-window). Terminated with the lease (amd-support-terminated)
    “today announced that it has signed a credit support agreement with AMD, the high performance and adaptive computing leader, supporting a lease for phase one of Fermi's Project Matador energy and AI buildout in Carson County, Texas, with 222 megawatts (MW) of gross power capacity in line with Fermi's first customer lease as announced on August 10, 2026.”
    Fermi release, Oct 13 2026 (Newswire) · newswire.com
  • amd-expansion-framework650 MW
    a second Fermi–AMD agreement, signed the same day: a 'partnership and framework' for expansion to 650 MW — Fermi's CEO: it 'establishes a framework for phases two and three'. Not a lease, and no figure for AMD's part in it. The Nov 12 release ends only 'The AMD credit support agreement associated with TensorWave'; none of Fermi's November documents (the Q3 10-Q, release, deck and prepared remarks) mentions the framework, so what became of it is not stated
    “The companies have also signed an agreement outlining a partnership and framework for future expansion of up to 650 MW of gross power capacity.”
    Fermi release, Oct 13 2026 (Newswire) · newswire.com
  • termination
    terminated Nov 10 2026, never having taken effect: the Oct 31 closing date passed without the extension to Dec 31 that the restated lease allowed, and the lease ended 'in accordance with its terms'. Note 9 of the same 10-Q: the termination 'had no effect' on the financial statements — no rent was ever owed or booked. On Nov 3 Fermi had said the closing conditions 'were not fully satisfied by October 31, 2026, and therefore the Lease has not yet become effective', and that 'Neither party has exercised any right to terminate the Lease'. Which condition failed, and who ended the lease, is not stated (termination-who). Fermi filed no 8-K under Item 1.01 or 1.02 for the lease, its amendments, the AMD agreement or the termination (EDGAR's index of its filings, to Nov 12 2026): its terms reached the filed record only in the two 10-Qs, the proxy naming it only among its risks. The same filing reports a non-binding letter of intent signed the same day with an unnamed investment-grade hyperscaler for about 600 MW of powered land — another deal, not this record (note)
    “The closing date under the TensorWave Lease passed without extension on October 31, 2026, and on November 10, 2026, the TensorWave Lease was terminated in accordance with its terms.”
    Fermi Q3 2026 10-Q, MD&A — Recent Developments (filed Nov 12 2026) · sec.gov
  • amd-support-terminated
    AMD's credit support ended with the lease, in Fermi's Nov 12 earnings release (furnished). Fermi's CEO, in the call's prepared remarks: 'The TensorWave lease will not move forward. That deal was a complex turnkey lease with a neocloud, involving multiple parties and requiring the support of third-party credit.'
    “Fermi and TensorWave have terminated the Data Center Lease and Services Agreement signed in August 2026. The AMD credit support agreement associated with TensorWave is also terminated.”
    Fermi Q3 2026 earnings release (Ex. 99.1 to the Nov 12 2026 8-K, furnished) · sec.gov
  • ttu-condition200 MW
    what rode on the lease for Fermi: its ground lease with the Texas Tech University System needs a notice to proceed by Dec 31 2026 before vertical construction, and the notice waits on a Phase 1 tenant lease of at least 200 MW — the condition the Q2 10-Q pointed to the TensorWave lease for ('see Note 9, Subsequent Events, regarding the TensorWave Lease'). After the termination the Q3 10-Q says it 'has not been satisfied' and that Fermi is discussing an extension with TTU
    “Issuance of the notice to proceed is conditioned on, among other things, our execution of a lease with a Phase 1 tenant for not less than 200 MW of capacity, which condition has not been satisfied.”
    Fermi Q3 2026 10-Q, Risk Factors (filed Nov 12 2026) · sec.gov
  • tenant-amd-ties
    why the record is marked circular: the rent's backer also made the only GPUs the tenant runs and was one of its investors — AMD Ventures co-led TensorWave's Series B of June 2026 (tensorwave entity) — and the building was to hold 'tens of thousands of next-generation AMD Instinct GPUs' (Aug 10 release). No document sizes AMD's stake in TensorWave or what TensorWave buys from AMD
    “Powered exclusively by AMD Instinct™ Series GPUs, TensorWave delivers high-bandwidth, memory-optimized infrastructure that scales with the most demanding training and inference workloads. Backed by funding from investors including Magnetar, AMD Ventures, Maverick Silicon, Nexus Venture Partners, and Western Frontier, TensorWave operates one of the world's largest all-AMD GPU clouds and is expanding rapidly to meet global demand.”
    Fermi release, Sep 22 2026 (Newswire) — 'About TensorWave' · newswire.com

Contested figures 6 not reconciled — every position side by side, with its source and tier

expansion-optionone entry, in its own words
the option on two more buildings, stated four ways by the parties: 'would increase the aggregate capacity leased to TensorWave to a total of 650 MW' (Fermi's Q2 10-Q, the only filed statement) vs 'would bring the partnership to a total of more than 650 MW' (Fermi's Aug 10 release; TensorWave's own post: 'more than 650 MW'; its co-founder Piotr Tomasik: 'past 650MW') vs 'Up to ~650 MW Total Facility Power Including Two Data Center Expansion Options' (Fermi's Q2 deck, furnished) and '650MW. That's the ceiling on the lease we just signed with Fermi America' (Ilya Tabakh's LinkedIn post). The 10-Q's MD&A adds that the two buildings 'must be energized on or before December 31, 2028'. Exact, floor or ceiling: the lease that would settle it was never filed. 'Towards 1GW', rendered on the same LinkedIn page, is another poster's (Matthew Higgins), not TensorWave's. AMD's separate Oct 13 framework says 'up to 650 MW of gross power capacity' (amd-expansion-framework). Moot since the termination Q2 10-Q vs Aug 10 release vs Q2 deck vs TensorWave-side posts
binding-statusone entry, in its own words
'it has executed its first binding customer lease' (Fermi, Aug 10) and 'A binding 15 - year phase one lease for 222 MW of total power capacity, backed by credit support from AMD' (fact sheet, Oct 14, furnished) vs 'The effectiveness of the TensorWave Lease is subject to the satisfaction or waiver of customary closing conditions' and 'There can be no assurance that these conditions will be satisfied or that the TensorWave Lease will commence' (Q2 10-Q, filed). Not a contradiction in law — a signed contract with conditions to closing — but the releases' 'binding' never carried the conditions, and its echoes repeated it without them. What followed settles the effect: 'the Lease has not yet become effective' (Fermi, Nov 3), then terminated (termination) Aug 10 release + Oct 14 fact sheet vs Q2 10-Q + Nov 3 release
delivery-scheduleone entry, in its own words
'Phased, beginning the second half of 2027' (Fermi's Aug 10 release) vs 'around the end of Q3, early Q4 of '27' for the build and revenue to start (Fermi's chief commercial officer, Aug 13 call) vs 'in phases beginning in late 2027 and continuing into the first quarter of 2028' (Q2 10-Q, Aug 14; its MD&A gives the targets: 'ranging from the end of 2027 through the first quarter of 2028 for the network hall, January 1, 2028 for data halls 1 and 2, and February 1, 2028 for data halls 3 and 4', with rent credits if late) vs 'Q4 2027 Phased delivery begins; completes early 2028' (fact sheet, Oct 14) — four statements in about nine weeks, the start drifting from 'the second half of 2027' to the fourth quarter. The 15-year term ran from the last phase, so this date set when the $6.5B would begin. Nothing was delivered Aug 10 release vs Aug 13 call vs Q2 10-Q vs Oct 14 fact sheet
termination-whoone entry, in its own words
'terminated in accordance with its terms' after the Oct 31 closing date passed without extension (Q3 10-Q) vs 'Fermi and TensorWave have terminated' it (Q3 release) vs 'Fermi terminated its data center lease and services agreement with TensorWave' (The Motley Fool's own summary above the call transcript, not Fermi's words). On the Nov 12 call an analyst asked 'Did you terminate that? Did they terminate it?' and Fermi's chairman answered 'we will not be providing any specific details as to specific negotiations between parties'. Who ended the lease, and which condition was not met, is unsettled Q3 10-Q vs Q3 release vs call transcript
credit-support-windowone entry, in its own words
'that backstop will be for the full 15 years' and 'that backstop fully guarantees that full 15 years' (Fermi's chief commercial officer on the Aug 13 call, before AMD was named or the agreement signed) vs the fact sheet after signing (Oct 14, furnished): 'ends early if TensorWave or its guarantor holds an investment - grade rating for 12 consecutive months'. The fact sheet also starts the support only when the lease's term starts — 'credit support beginning once construction is complete and rent starts', its disclaimer adding that 'AMD’s obligations begin only after construction is complete and rent commences on the final delivery phase' — so nothing covered the construction years, and on the later reading the cover could stop well short of 15 years. The agreement itself was never filed. Moot since the termination Aug 13 call vs Oct 14 fact sheet
premises-acreageone entry, in its own words
'approximately 250 acres' for the leased Premises — 'approximately 311,496 square feet, with total facility power of 222 MW, configured across four data halls and one network data hall' (Q2 10-Q, filed) vs 'a 330-acre campus that TensorWave is signed up for. It will be 3 phases' (Fermi's chief operating officer, Aug 13 call). Possibly phase one against all three phases — no document says Q2 10-Q vs Aug 13 call

Scope note what this record leaves to other records

Not this deal — carried elsewhere or not carried: the non-binding letter of intent Fermi signed on Nov 10 2026 with an unnamed investment-grade hyperscaler for about 600 MW of powered land, with its $200M prepayment and $15M early-construction agreements (another tenant and another product; one point for this deal: no 600 MW figure belongs here — fermi entity note); the MUFG covenant waiver of Oct 9 (fermi note); Fermi's cash, debt, power plans, permits, Hillcore framework, nuclear schedule and the 2025 'First Tenant' advance agreement; TensorWave's funding and capacity claims (tensorwave entity) and its separate TECfusions commitment; AMD's own guarantees for unnamed 'commercial partners' at Sep 26 2026 (AMD-wide, dated before this agreement); and the share-price moves of Aug 10–11 and Oct 13, which are on file only as aggregator headlines.