Amazon–Vistra

Amazon buys the full output of Vistra's 200 Oak Hill solar plant, built on a reclaimed lignite mine in Rusk County, Texas, under a long-term power purchase agreement Vistra announced in August 2024; the plant began commercial operation in October 2025, and neither company gives the contract's length in years or its price.

A deal between Amazon / AWS, Vistra

Why it matters

Oak Hill shows what a hyperscaler contract does for a plan that had sat on the shelf. The plant stayed 'Under Development' in Vistra's decks until 2024, the year Vistra announced Amazon's contract for its full output, which in Vistra's words 'made construction and operation of Oak Hill's 200- facility possible'. Unlike Amazon's other Vistra deal, for half of the existing Comanche Peak nuclear plant, this one put a new plant on the grid.

Tap a figure for the line in its source.

Vistra gives Amazon / AWS

  • of solar power from the Oak Hill plant — its full output, by Vistra's account — under a long-term PPA whose length in years is not disclosed; the power goes onto the Texas grid

Amazon / AWS gives Vistra

  • payments at a price neither company discloses

Aug 8, 2024 announced in Vistra's Q2 2024 results, the site unnamed disclosed by the parties

What happened

Vistra, the Texas power company, sells Amazon the full output of its 200-megawatt Oak Hill solar plant in Rusk County, East Texas. The plant is built on a former lignite mine that fed the nearby Martin Lake coal plant until mining ended in 2016. Vistra announced the plant in 2020, expecting it online in 2022, but its own investor decks listed it as under development until 2024. Construction began that year, and in August Vistra announced a long-term contract with Amazon for the plant's power. The plant entered commercial operation in October 2025, and its power goes onto the Texas grid. Amazon's other Vistra deal, for half of the existing Comanche Peak nuclear plant, is to power a data center Amazon is building beside that plant. Neither company gives Oak Hill's contract length in years or its price. Vistra financed the plant with its own project loans: $88 million of construction loans, now a term loan, and a $106 million bridge loan it repaid in January 2026. Vistra booked $98 million of transferable federal tax credits when the plant entered service. A second 200 phase is being built at the site under a separate contract with a buyer Vistra has not named.

Sources 36 documents — 9 other documents · 8 company releases · 7 regulatory filings · 6 SEC filings · 3 transcripts · 3 government statements

Research trail Found 239 documents and read 204 of them while checking this deal and related ones.

  1. SEC · SEC filingsec.gov
    States 2 figures: commercial operation · $88M construction loan
  2. SEC · SEC filingsec.gov
    States 2 figures: $98M itc · $106M bridge loan
  3. company releaseinvestor.vistracorp.com
    States 200 MW contract volume
  4. SEC · SEC filingsec.gov
    States 200 MW oak hill named
  5. SEC · SEC filingsec.gov
    States 200 MW aws named
  6. roic.ai · transcriptroic.ai
    States full offtake
  7. company releasevistracorp.com
    States offtake term
  8. company releasesustainability.aboutamazon.com
    States amazon list
  9. company releasevistracorp.com
    States construction start
  10. powertexasforward.com · other documentpowertexasforward.com
    States mining ended
  11. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  12. company releaseinvestor.vistracorp.com
    Cited by the record; no single figure is quoted from it.
  13. other documentfilecache.investorroom.com
    Cited by the record; no single figure is quoted from it.
  14. SEC filingsec.gov
    Cited by the record; no single figure is quoted from it.
  15. company releaseinvestor.vistracorp.com
    Cited by the record; no single figure is quoted from it.
  16. other documentfilecache.investorroom.com
    Cited by the record; no single figure is quoted from it.
  17. company releaseinvestor.vistracorp.com
    Cited by the record; no single figure is quoted from it.
  18. other documentfilecache.investorroom.com
    Cited by the record; no single figure is quoted from it.
  19. company releaseinvestor.vistracorp.com
    Cited by the record; no single figure is quoted from it.
  20. transcriptroic.ai
    Cited by the record; no single figure is quoted from it.
  21. transcriptroic.ai
    Cited by the record; no single figure is quoted from it.
  22. other documentfilecache.investorroom.com
    Cited by the record; no single figure is quoted from it.
  23. regulatory filinginterchange.puc.texas.gov
    Cited by the record; no single figure is quoted from it.
  24. regulatory filinginterchange.puc.texas.gov
    Cited by the record; no single figure is quoted from it.
  25. regulatory filinginterchange.puc.texas.gov
    Cited by the record; no single figure is quoted from it.
  26. regulatory filinginterchange.puc.texas.gov
    Cited by the record; no single figure is quoted from it.
  27. regulatory filinginterchange.puc.texas.gov
    Cited by the record; no single figure is quoted from it.
  28. regulatory filinginterchange.puc.texas.gov
    Cited by the record; no single figure is quoted from it.
  29. regulatory filinginterchange.puc.texas.gov
    Cited by the record; no single figure is quoted from it.
  30. government statementeia.gov
    Cited by the record; no single figure is quoted from it.
  31. government statement (archived copy)assets.comptroller.texas.gov
    Cited by the record; no single figure is quoted from it.
  32. government statement (archived copy)assets.comptroller.texas.gov
    Cited by the record; no single figure is quoted from it.
  33. other documentfiles-backend.assets.thrillshare.com
    Cited by the record; no single figure is quoted from it.
  34. other documentindustrialinfo.com
    Cited by the record; no single figure is quoted from it.
  35. other documentindustrialinfo.com
    Cited by the record; no single figure is quoted from it.
  36. other documentindustrialinfo.com
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: Vistra Q2 2024, Q3 2025 and FY2025 results releases (8-K ex-99.1) and decks, Aug 2024 and May 2025 calls, 2024 and 2025 sustainability reports and Oak Hill page; Vistra FY2025 10-K and Q1 2025 and Q3 2026 10-Qs; Amazon's carbon-free energy projects list; Texas PUC filings (Oncor interconnection agreement, PGC registrations, REC certification), FERC self-certification, EIA Table 6.3; Texas Comptroller Chapter 313 certificate and Henderson ISD board book; Industrial Info Resources · as of Nov 2026

The evidence 12 sourced figures · 3 disputes

The record's headline Amazon–Vistra: long-term PPA for the full output of Oak Hill, a 200 solar plant on a reclaimed East Texas lignite mine, running since Oct 2025 — length and price undisclosed

Size
200 MW of solar, the plant's full output · long-term, length in years undisclosed · price undisclosed · in commercial operation since Oct 2025
When
Sep 29 2020 (Vistra announces Oak Hill among its Vistra Zero solar projects, 'Expected online in 2022') → Feb 2022–May 2024 (Vistra's decks list it 'Under Development') → Nov 2 2023 (Oncor's interconnection agreement) → 2024 (construction begins) → Aug 8 2024 (Vistra announces the 200 MW PPA with Amazon) → Dec 2024 (BCOP credit agreement) → May 2025 ($88M of construction loans) → Oct 2025 (commercial operation; placed in service for its tax credits; Amazon's list: Oct 14) → Nov 6 2025 (Q3 2025 results release names Oak Hill's PPA with Amazon) → Jan 2026 ($106M bridge loan repaid) → Feb 26 2026 (FY2025 results: 'a PPA also with AWS') → Mar 2026 (EIA lists the unit among new generators)
Status
operating: in commercial operation since October 2025 (Vistra's FY2025 10-K); the PPA's length and price are not public; the plant's construction loans became a term loan maturing in December 2029, and its bridge loan was repaid in January 2026
Structure
a long-term power purchase agreement between Vistra and Amazon (AWS in Vistra's FY2025 results) for the full output of the 200 MW Oak Hill Solar Facility in Rusk County, East Texas (ERCOT) — Dry Creek Solar I in its regulatory filings, owned through Oak Hill Solar LLC — on the reclaimed Oak Hill lignite mine. The PPA is not filed: no document read gives its length in years, its price, a volume in MWh, or whether it settles physically or financially; the power goes onto the ERCOT grid. Vistra financed the build through BCOP, its project-level credit facility for four solar projects: construction loans that became a term loan at commercial operation, and a bridge loan guaranteed by Vistra as the beneficiary of the plant's tax credits
Programme
Time-to-power
Parties
Amazon / AWS buyer — 'Amazon' in Vistra's 2024–25 releases and sustainability reports, 'AWS' in its FY2025 results; 'Amazon Solar Farm Texas - Oak Hill' on Amazon's own list of its carbon-free energy projects · Vistra seller — built and owns the plant, through Oak Hill Solar LLC in its regulatory filings; financed it through BCOP, its project-level borrower
Record
disclosed / primary source · as of Nov 2026

Flows 2 as the record states them

  • Vistra → Amazon / AWSpowerthe full output of the 200 MW Oak Hill solar plant under a long-term PPA, length in years undisclosed — onto the ERCOT grid; in commercial operation since October 2025 (contested operation-date)
  • Amazon / AWS → Vistrappa-paymentsprice undisclosed; no total, length or schedule of payments is public

Resolved figures 12 each with the verbatim line from its document

  • contract-volume200 MW
    200 MW with Amazon, announced Aug 8 2024 beside a 405 MW PPA with Microsoft in Illinois ('together totaling over 600 MW'). The release names no site; the same day's deck lists Oak Hill (Rusk County, 200 MW, 'In Construction, 2025') as Vistra's one 200 MW Texas solar project under construction, and Vistra's later releases and decks name it (see oak-hill-named). Vistra's 10-K and 10-Qs name AWS only as the buyer at Comanche Peak (pw-amzn-comanche-peak), never as Oak Hill's
    “Today, Vistra announced two new power purchase agreements, together totaling over 600 MW, with two of the world's leading tech companies - one for 200 MW with Amazon in Texas and one for 405 MW with Microsoft in Illinois.”
    Vistra Q2 2024 results release (Aug 8 2024) · investor.vistracorp.com
  • full-offtake
    the whole plant: Vistra's CEO, Jim Burke, on the call of Aug 8 2024, right after 'We began construction on two new large scale solar projects, one in Texas and one in Illinois.' The contract's 200 MW is the plant's 200 MW. Vistra's Oak Hill page: 'Its output is contracted under a long-term power purchase agreement, while the power flows to the ERCOT grid for the benefit of all electricity users', and 'A long-term power purchase agreement made construction and operation of Oak Hill's 200-MW facility possible, while increasing the amount of power flowing to the grid for all customers' benefit.' The page names no buyer; the agreement it means is the one of its next line, 'Vistra first disclosed the agreement and the facility's commercial operation date in its third-quarter 2025 results', the release that names Amazon (see oak-hill-named). Whether Amazon takes the power physically or the contract settles financially against the grid price, no document read says
    “To ensure full off-take from these facilities, we executed new long-term power purchase agreements with two of the world's leading technology companies, one with Amazon and the other with Microsoft.”
    Vistra Q2 2024 earnings call (Aug 8 2024), transcript via roic.ai · roic.ai
  • offtake-term
    long-term, in Vistra's words, with no number of years: 'structured with a long-term off-take agreement' (its 2024 and 2025 sustainability reports), 'Long-term power purchase agreement' (its Oak Hill page). No document of either company gives the PPA's length, its price, a volume in MWh or a total, and the PPA is not filed. Every '20-year' in Vistra's AWS disclosures is Comanche Peak's (pw-amzn-comanche-peak)
    “This project meets the needs of our customer, Amazon, and is structured with a long-term off-take agreement.”
    Vistra 2025 sustainability report · vistracorp.com
  • oak-hill-named200 MW
    Vistra's Q3 2025 results release (Nov 6 2025) names the plant with its buyer. Its decks had paired them before: 'Began construction on projects in support of contracts with Amazon and Microsoft with expected COD in 2025 and 2026, respectively' (Feb 27 2025), then 'Construction continues on our Vistra Zero projects for Oak Hill (Amazon) and Pulaski (Microsoft)' (May 7 2025); so had its 2024 sustainability report ('partnering with Amazon to establish an offtake agreement for the facility'). Vistra's Oak Hill page says 'Vistra first disclosed the agreement and the facility's commercial operation date in its third-quarter 2025 results' — so of the commercial operation date, not of the agreement, which its Aug 2024 release announced (see contract-volume)
    “Achieved commercial operations date (COD) for our new Oak Hill 200 MW solar facility supported by a power purchase agreement with Amazon in Texas (ERCOT).”
    Vistra Q3 2025 results release (Nov 6 2025, 8-K ex-99.1) · sec.gov
  • aws-named200 MW
    Vistra's FY2025 results (Feb 26 2026): its CEO's list of 2025's milestones, after the 20-year AWS PPA at Comanche Peak — the 'also' points to that one, a separate contract (pw-amzn-comanche-peak). Here the buyer is AWS (Amazon Web Services); Vistra's other documents on Oak Hill say Amazon
    “commissioning of the 200-MW Oak Hill Solar Facility on our retired and reclaimed coal mine site, which includes a PPA also with AWS”
    Vistra FY2025 results release (Feb 26 2026, 8-K ex-99.1) · sec.gov
  • amazon-list
    the buyer's side: Amazon's own downloadable list of its carbon-free energy projects has 'Amazon Solar Farm Texas - Oak Hill', Rusk County, Texas, with a system size of 200.00 MW and an 'Operational Date' of Oct 14 2025 — independent of Vistra's documents. It names no seller, length or price, and the list does not define its date field
    “Amazon Solar Farm Texas - Oak Hill,"Oct 14, 2025",United States,Texas,Rusk, 200.00”
    Amazon, carbon-free energy projects list (CSV) · sustainability.aboutamazon.com
  • construction-start2024
    2024, by Vistra's account — between its May 8 2024 deck, which still listed Oak Hill as 'Under Development', and its Aug 8 2024 deck ('In Construction, 2025'), the day its results release said 'We've started construction on two new solar facilities, a 200 MW site backed by Amazon in Texas and a 405 MW site backed by Microsoft in Illinois.' Other documents give earlier starts: Vistra's Sep 29 2020 release said it was 'breaking ground on six new solar projects', Oak Hill among them, 'Expected online in 2022', and Industrial Info reported in May 2022 that 'Vistra began construction in March' on Oak Hill and a sibling project. Vistra's decks from Feb 2022 to May 2024 kept it 'Under Development', its expected year moving from 2023–2024 to 2025+ and then 2025
    “In 2024, Vistra began construction on the 200-MW Oak Hill Solar Facility in Texas.”
    Vistra 2024 sustainability report · vistracorp.com
  • commercial-operation2025
    October 2025, in Vistra's annual report — the same month the plant 'met the requirements to be placed in service' for its tax credits (see itc); its Q3 2025 deck: '200-MW Oak Hill Solar Facility in ERCOT reached commercial operations in October'. Amazon's list gives Oct 14 2025. Other filings give other dates (contested operation-date). Forecasts had run later: a 'Scheduled Commercial Operation Date: January 01,2026' in Oncor's Nov 2023 interconnection agreement, and commercial operation 'expected to commence in January 2026' in Oak Hill Solar's FERC self-certification of Apr 28 2025; on May 7 2025 Vistra's CEO said the site was 'approximately 90% complete and on track for a fourth quarter 2025 commercial operations date'
    “In October 2025, the Oak Hill project achieved commercial operation, and the construction loans automatically converted into a term loan maturing in December 2029.”
    Vistra FY2025 10-K · sec.gov
  • mining-ended2016
    the site is the former Oak Hill lignite mine, which for 30 years fed the nearby Martin Lake coal plant: opened in 1986, it 'once supported more than 240 workers', and mining there ended in 2016 (Vistra's 2024 sustainability report). Vistra's FY2025 results call it 'our retired and reclaimed coal mine site'; the plant's amended Chapter 313 application (Mar 2022) puts it on 'approximately 2,923 acres of contiguous land entirely within Henderson ISD'
    “Today, solar panels sit atop the reclaimed former mine land, where mining ended in 2016.”
    Vistra, Oak Hill Solar Facility page (dated Nov 5 2026) · powertexasforward.com
  • itc$98M
    $98M of transferable investment tax credits recognized in Q4 2025, when the plant was placed in service, and $6M more in Q3 2026 — $104M so far (our sum), booked as an asset. The total Vistra expects is not given, and the 10-Q's account of its credit sales through Sep 30 2026 lists only nuclear production tax credits, none of Oak Hill's. The plant's bridge loan was guaranteed by Vistra 'as the beneficiary of the underlying investment tax credits' (see bridge-loan)
    “In October 2025, our Oak Hill 200 MW solar facility in Texas met the requirements to be placed in service. As a result, we recognized transferable ITCs associated with the project of $98 million in the three months ended December 31, 2025 and $6 million in each of the three and nine months ended September 30, 2026, in other noncurrent assets in the consolidated balance sheet.”
    Vistra Q3 2026 10-Q · sec.gov
  • construction-loan$88M
    $88M of construction loans funded in May 2025 under BCOP, Vistra's project-level credit facility for four solar projects (Baldwin, Coffeen, Oak Hill and Pulaski; entered Dec 2024), converted in October 2025, when the plant reached commercial operation, into a term loan maturing in December 2029. The term loans 'will amortize over a 20-year period beginning on the … term conversion date (for Oak Hill and Pulaski)', with 'debt amortization and interest payments … funded by cash flows from the underlying project' (Q1 2025 10-Q) — a schedule for the loan, not the PPA's length, which no document gives. Oak Hill's own balance since is not broken out: the Baldwin, Coffeen and Oak Hill term loans totaled $202M at Sep 30 2026 (Q3 2026 10-Q)
    “Oak Hill: In May 2025, BCOP funded $88 million of construction loans for the Oak Hill project with a scheduled maturity in November 2025.”
    Vistra FY2025 10-K · sec.gov
  • bridge-loan$106M
    a $106M bridge loan for the plant under BCOP, at Term SOFR plus 1.625%, outstanding at Dec 31 2025, its maturity extended in October 2025 from November 2025 to Jan 30 2026, and repaid by Vistra at maturity in January 2026. 'Repayment of the Bridge Loans is guaranteed by Vistra as the beneficiary of the underlying investment tax credits expected to be generated by the applicable projects' (FY2025 10-K)
    “In January 2026, Vistra repaid the $106 million Oak Hill Bridge Loan at maturity.”
    Vistra Q3 2026 10-Q · sec.gov

Contested figures 3 not reconciled — every position side by side, with its source and tier

operation-dateone entry, in its own words
October 2025 — Vistra's FY2025 10-K (commercial operation, and placed in service for its tax credits, both 'In October 2025') and its Q3 2025 deck ('reached commercial operations in October'); Oct 14 2025 — Amazon's list ('Operational Date') vs Aug 1 2025 — the date commercial operation 'Began / Will Begin', a single field on Oak Hill Solar's certification form for renewable energy credits (filed Sep 4 2025), whose own list of generating units gives 10/1/2025 vs March 2026 — the month EIA's table of new utility-scale generating units lists 'Oak Hill - Dry Creek' (200.0 MW, operator Vistra Zero LLC). Each may date a different event — commercial operation, placement in service for tax credits, eligibility for renewable credits, a reporting month; no document reconciles them Vistra FY2025 10-K and Q3 2025 deck; Amazon's project list / Texas PUC Project 58633 / EIA Electric Power Monthly, Table 6.3
plant-ratingone entry, in its own words
200 MW — Vistra's figure throughout (its FY2025 10-K's properties table: 'Oak Hill Rusk County, TX ERCOT Solar Renewable 200'), the contract's size, Amazon's 200.00 MW and EIA's 200.0 MW of net summer capacity vs 201.06–202.6 MW — Oncor's interconnection agreement as amended (Amendment No. 2, Jul 22 2024): 'dispatched as 202.6 MW, measured at the generator terminals and 201.06 MW at 34.5 kV' (205.54 MW at the generator terminals in the Nov 2 2023 original); Oak Hill Solar's FERC self-certification: 'approximately 202.6 MW / 216 MVA' vs 216 MW — the 60 inverters' 'total gross capacity of 216 MVA' (the amendment), and the PUC's renewable-credit notice: 'total rated nameplate capacity is 216 megawatts (MW)' (Sep 22 2025) vs 223.2 MW — Oak Hill Solar's power-generation-company registration (Oct 15 2024), matching the original design's 62 inverters and 223.2 MVA; its Feb 2025 renewal says 216 MW. Different measuring points and one design change; only the 200 MW is the contract's Vistra FY2025 10-K; Amazon's project list; EIA Table 6.3 / Texas PUC Project 35077 (Oncor interconnection agreement and Amendment No. 2); FERC self-certification (PUC Project 54974) / PUC Project 58633 / PUC Projects 57204 and 57430
plant-costone entry, in its own words
more than $191M — the company's estimate as Education Service Center Region 12 relays it ('The company estimates that the total investment in this project will be in excess of $191 million', Sep 16 2022, in Henderson ISD's board book of Dec 12 2022) vs $207.8M — the 'Proposed Total Investment in District' and 'Proposed Qualified Investment' in the Comptroller's certificate on Oak Hill Solar's Chapter 313 application (Jun 28 2022) vs $220M — Industrial Info Resources (Jan and May 2022) vs $260M — Industrial Info Resources (Aug 21 2025: 'The $260 million Oak Hill Plant in Henderson, Texas'). All are estimates: the first two were made in 2021–22 for a school-tax limitation, before construction began; Industrial Info shows no working, and its two figures are one publisher's revision. Vistra's filings give no cost for the plant. Not Oak Hill's: the 'more than $650 million' in Vistra's 2024 sustainability report is for the 405 MW Pulaski plant, and the ~$850 million of Sep 2020 is the whole Vistra Zero portfolio announced then ESC Region 12 analysis in Henderson ISD's board book (Dec 2022); Texas Comptroller Chapter 313 certificate (via Wayback) / Industrial Info Resources (2022, 2025)

Scope note what this record leaves to other records

Not this deal — carried elsewhere or not carried: the plant's Chapter 313 school-tax agreement with Henderson ISD, between the plant's owner and the district — an $80 million limitation on the plant's value for school maintenance-and-operations taxes from 2025 (raised from $30 million in the application's amendment 'to reflect 2022 values'), two qualifying jobs, the 2022 estimates of the owner's savings (about $2.2–3.9 million) and the construction-jobs forecasts; Oak Hill 2, a second 200 MW phase at the site, under construction and expected in service in 2027 (Vistra's Q3 2026 deck), 'supported by a power purchase agreement with a large investment-grade counterparty' (Vistra's Q2 2026 call) that Vistra has not named — a separate contract, not assumed to be Amazon's; Amazon's Comanche Peak nuclear PPA with Vistra (pw-amzn-comanche-peak), whose 20-year term and 1,200 MW are not Oak Hill's; the 405 MW Microsoft PPA at Pulaski, Illinois, announced the same day; and the rest of BCOP (the Baldwin, Coffeen and Pulaski loans, and the interest-rate swaps on the facility).